Update : 18 December 2020

Status Legend :
Done On Track
Detail Time Frame & Work Plan Belum
Delay
Dimulai

Repair Rotor 203-K-001T dan Pengadaan Parts 203-K-001T, 209-K-001T, 213-K-001T


Progress Legend :
Planning Actual

2020 2021
DESCRIPTION OF
NO RENCANA KERJA PIC Oct Nov Dec Jan Feb Target Status Remark
RECOMMENDATION
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1. Presentasi dan Prakualifikasi teknis 02/10/2020 PT. Taka, PT Sulzer, PT NTP, PT Dresser Rand
PRC

2 .Create PR & RKS MTN 12/10/2020 PR done 05 Nov 2020. PR No 7200006268


RKS done 06 Nov 2020
3. Create HPS MTN 18/12/2020 Target HPS done 18 Dec 2020

4. RFQ (Undangan Aanwijzing) PRC 01/12/2020 Aanwijzing Done 01 Dec 2020


Aanwijzing dilakukan setelah rapat dgn MCO & Indocor
5. Aanwijzing & Cek fisik Rotor PRC 08/12/2020 Survey fisik Rotor di site 08 Dec 2020

6. Pemasukan penawaran PRC 11/12/2020 Pemasukan penawaran closing 11 Dec 2020 (cap Pos)
1 Repair Rotor
7. BAPP, Presentasi dan review teknis PRC 14/12/2020 Pembukaan Sampul I 14 Dec 2020
Evaluasi Teknis on progress
8. TBE (approved) PRC 28/12/2020

9. IOM BOD PRC-JKT 30/12/2020

10. PO (approved) PRC 04/01/2021

11. Kontrak agreement PRC 11/01/2021

12. KOM dan Delivery PRC 23/06/2021 ETC : 6-8 months


6-8 Months
1. Create PR & RKS MTN 08/10/2020 PR 7000033537 released 06 Oct 2020

2. Create HPS MTN 16/11/2020 HPS sent to JKT 03 Dec 2020 - Parts Compressor
HPS parts Turbine menunggu konfirmasi MHI list parts yang tidak perlu
uprade
3. RFQ PRC 08/10/2020

4. Pemasukan penawaran PRC 23/11/2020 Menunggu revisi proposal MHI. Target minggu ke 3 Dec 2020
Pengadaan Parts
2 5. BAPP dan review & klarifikasi teknis PRC 24/11/2020 Pembukaan penawaran 24 Dec 2020
203-K-001T

6. TBE (approved) PRC 27/11/2020

7. IOM BOD PRC-JKT 11/12/2020

8. PO (approved) PRC 15/12/2020

9. Delivery MHI 15/09/2021 ETC : 9 months


9 Months
1. Create PR & RKS MTN 07/12/2020 List parts sudah diterima dari REL 10 Nov 2020
Ada perubahan part no dari MHI 04 Dec 2020
2. Create HPS MTN 28/12/2020

3. RFQ PRC 08/12/2020 List parts dikirim ke MHI 18 Dec 2020

4. Pemasukan penawaran PRC 11/01/2021

Pengadaan Parts 5. BAPP dan review & klarifikasi teknis PRC 13/01/2021
3
209-K-001T
6. TBE (approved) PRC 18/01/2021

Page 1 of 2
Status Legend :
Done On Track
Detail Time Frame & Work Plan Belum
Delay
Dimulai

Repair Rotor 203-K-001T dan Pengadaan Parts 203-K-001T, 209-K-001T, 213-K-001T


Progress Legend :
Planning Actual

2020 2021
DESCRIPTION OF
NO RENCANA KERJA PIC Oct Nov Dec Jan Feb Target Status Remark
RECOMMENDATION
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
7. IOM BOD PRC-JKT 25/01/2021

8. PO (approved) PRC 27/01/2021

9. Delivery MHI 27/10/2021 ETC : 9 months


9 Months
1. Create PR & RKS MTN 07/12/2020 List parts sudah diterima dari REL 10 Nov 2020
Ada perubahan part no dari MHI 04 Dec 2020
2. Create HPS MTN 28/12/2020

3. RFQ PRC 08/12/2020 List parts dikirim ke MHI 18 Dec 2020

4. Pemasukan penawaran PRC 11/01/2021

Pengadaan Parts 5. BAPP dan review & klarifikasi teknis PRC 13/01/2021
4
213-K-001T
6. TBE (approved) PRC 18/01/2021

7. IOM BOD PRC-JKT 25/01/2021

8. PO (approved) PRC 27/01/2021

9. Delivery MHI 27/10/2021 ETC : 9 months


9 Months

Page 2 of 2