PEKERJAAN PASANGAN DINDING DAN PLASTERAN

1. Pekerjaan pasangan batu bata 1/2 bata campuran 1 Semen : 2 Pasir (Trasram).

Pekerjaan pasangan batu bata 1/2 bata campuran 1 : 2 (Trasram).meliputi pekerjaan


pasangan batu bata pada area KM/WC.
Satuan dalam pekerjaan pasangan batu bata adalah M2.

A. Menghitung Volume Pekerjaan


a. KM/WC – 1 (Bidang F5G5 – F6G6 – F5F6 – G5G6)

Rumus

Σ PPPB = Σ PPas.Bata – Σ lKusen

Σ lKusen = 0,700 M
h = 1,500 M
Bidang F5 – G5 (a) = 1,750 M
Bidang F6 – G6 (b) = 1,750 M
Bidang F5 – F6 (c) = 1,500 M
Bidang F5 – F6 (d) = 1,500 M

Total panjang pasangan batu bata Luas pas. trasram KM/WC 1


Σ PPas.Bata = 1,75 + 1,75 + 1,50 + 1,50 LPas.Trasram = 5,80 x 1,50
= 6,50 M = 8,70 M2

Σ PPPB = 6,50 – 0,70


= 5,80 M

b. KM/WC – 2
Bidang A9B9 – A10B10 – A9A10 – B9B10

Σ lKusen = 0,700 M
h = 1,500 M
Bidang A9 – B9 (a) = 1,500 M
Bidang A10 – B10 (b) = 1,500 M
Bidang A9 – A10 (c) = 1,200 M
Bidang B9 – B10 (d) = 1,200 M

46
Total panjang pasangan batu bata Luas pas. trasram KM/WC 2
Σ PPas.Bata = 1,50 + 1,50 + 1,20 + 1,20 LPas.Trasram = 4,70 x 1,50
= 5,40 M = 7,50 M2

Σ PPPB = 5,40 – 0,70 Total luas pas. trasram KM/WC


= 4,70 M Σ LPas.Trasram = 8,70 + 7,05
= 15,750 M2

B. Menghitung Analisa Biaya Pekerjaan

1 M2 Pek. Pas. Batu bata 1/2 Bata 1 : 2 (Trasram)


Bahan
70,0 Batu Bata Buah Rp 700 Rp 49.000
0,050 Pasir Pasangan M3 Rp 200.000 Rp 10.000
0,474 Semen PC Zak Rp 50.000 Rp 23.688
Rp 82.688
Upah Kerja
0,100 Tukang Batu OH Rp 120.000 Rp 12.000
0,010 Kepala Tukang OH Rp 125.000 Rp 1.250
0,015 Mandor OH Rp 130.000 Rp 1.950
0,300 Pekerja OH Rp 75.000 Rp 22.500
Rp 37.700

Total Bahan + Upah Kerja Rp 120.388

C. Menghitung Besar Biaya Pekerjaan

HARGA JUMLAH
NO URAIAN SAT VO L SATUAN HARGA
(Rp). (Rp).
2
1 Pek. Pas. Batu bata 1/2 Bata 1 : 2 (Trasram) M 15,750 120.388 1.896.111

47
2. Pekerjaan pasangan batu bata 1/2 bata campuran 1 Semen : 4 Pasir.

Pekerjaan pasangan batu bata 1/2 bata campuran 1 : 4 meliputi semua pekerjaan
pasangan batu bata kecuali pada area KM/WC.
Satuan dalam pekerjaan pasangan batu bata adalah M2.

A. Menghitung Volume Pekerjaan

RUMUS LPBB = LPas.Bata – Σ LKusen

a. Bidang C2E2 – E2E3

Dinding Luas dinding


h = 3,800 M LPas.Bata = 4,50 x 3,80
Bidang C2 – E2 (a) = 3,500 M = 17,10 M2
Bidang E2 – E3 (b) = 1,000 M
Luas kusen
Kusen P1 LKusen = 1,30 x 2,20 x 1,00
P1 JKusen = 1,00 Buah = 2,86 M2
b = 1,30 M J1 LKusen = 0,70 x 1,70 x 2,00
h = 2,20 M = 2,38 M2
J1 JKusen = 2,00 Buah R1 LKusen = 0,30 x 0,50 x 5,00
b = 0,70 M = 0,75 M2
h = 1,70 M Total luas kusen
R1 JKusen = 5,00 Buah Σ LKusen = 2,86 + 2,38 + 0,75
b = 0,30 M = 5,99 M2
h = 0,50 M
Luas pasangan bata bersih
Total panjang pasangan batu bata LPBB = 17,10 – 5,99
Σ PPas.Bata = 3,50 + 1,00 = 11,11 M2
= 4,50 M

48
b. Bidang C4E4 – C2C4 – E3E4

Dinding Luas dinding


h = 3,800 M LPas.Bata = 8,50 x 3,80
Bidang C4 – E4 (a) = 3,500 M = 32,30 M2
Bidang C2 – C4 (b) = 3,000 M
Bidang E3 – E4 (c) = 2,000 M Luas kusen
Lubang LKusen = 2,00 x 3,00 x 1,00
Kusen = 6,00 M2
Lubang JKusen = 1,00 Buah Total luas kusen
b = 2,00 M Σ LKusen = 6,00 M2
h = 3,00 M
Luas pasangan bata bersih
Total panjang pasangan batu bata LPBB = 32,30 – 6,00
Σ PPas.Bata = 3,50 + 3,00 + 2,00 = 26,30 M2
= 8,50 M

c. Bidang E3G3 – G3G5

49
Dinding Luas dinding
h = 3,800 M LPas.Bata = 6,50 x 3,80
Bidang E3 – G3 (a) = 3,000 M = 22,80 M2
Bidang G3 – G5 (b) = 3,500 M
Luas kusen
Kusen J2 LKusen = 1,35 x 1,70 x 1,00
J2 JKusen = 1,00 Buah = 2,30 M2
b = 1,35 M R1 LKusen = 0,30 x 0,50 x 3,00
h = 1,70 M = 0,45 M2
R1 JKusen = 3,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 2,30 + 0,45
= 2,75 M2
Total panjang pasangan batu bata
Σ PPas.Bata = 3,50 + 3,00 Luas pasangan bata bersih
= 6,50 M LPBB = 22,80 – 2,75
= 20,05 M2

d. Bidang E5G5 – E4E5

Dinding Luas dinding


h = 3,800 M LPas.Bata = 4,00 x 3,80
Bidang E5 – G5 (a) = 3,000 M = 15,20 M2
Bidang E4 – E5 (b) = 1,000 M
Luas kusen
Kusen P2 LKusen = 0,90 x 2,20 x 1,00
P2 JKusen = 1,00 Buah = 1,98 M2
b = 0,90 M R1 LKusen = 0,30 x 0,50 x 2,00
h = 2,20 M = 0,30 M2
R1 JKusen = 2,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 1,98 + 0,30
= 2,28 M2
Total panjang pasangan batu bata
Σ PPas.Bata = 3,00 + 1,00 Luas pasangan bata bersih
= 4,00 M LPBB = 15,20 – 2,28
= 12,92 M2

50
e. Bidang E6G6 – F5F6

Dinding Luas dinding


h = 3,800 M LPas.Bata = 4,50 x 3,80
Bidang E6 – G6 (a) = 3,000 M = 17,10 M2
Bidang F5 – F6 (b) = 1,500 M
Luas kusen
Kusen P2 LKusen = 0,8 x 2,15 x 1,00
P3 JKusen = 1,00 Buah = 1,72 M2
b = 0,80 M
h = 2,15 M Luas pasangan bata bersih
LPBB = 17,10 – 1,72
Total panjang pasangan batu bata = 15,38 M2
Σ PPas.Bata = 3,00 + 1,50
= 4,50 M

51
f. Bidang G5G8

Dinding V JKusen = 1,00 Buah


h = 3,800 M b = 0,70 M
Bidang G5 – G8 (a) = 5,000 M h = 0,30 M

Kusen Total panjang pasangan batu bata


J4 JKusen = 1,00 Buah Σ PPas.Bata = 5,00 M
b = 1,15 M
h = 1,70 M Luas dinding
R1 JKusen = 3,00 Buah LPas.Bata = 5,00 x 3,80
b = 0,30 M = 19,00 M2
h = 0,50 M

Luas kusen Total luas kusen


J4 LKusen = 1,15 x 1,70 x 1,00 Σ LKusen = 1,955 + 0,45 + 0,28
= 1,955 M2 = 2,685 M2
R1 LKusen = 0,30 x 0,50 x 3,00
= 0,45 M2 Luas pasangan bata bersih
V LKusen = 0,40 x 0,70 x 1,00 LPBB = 19,00 – 2,685
= 0,28 M2 = 16,315 M2

52
g. Bidang E8G8 – E6E8

Dinding Luas dinding


h = 3,800 M LPas.Bata = 6,50 x 3,80
Bidang E8 – G8 (a) = 3,000 M = 24,70 M2
Bidang E5 – E8 (b) = 3,500 M
Luas kusen
Kusen P2 LKusen = 0,90 x 2,20 x 1,00
P2 JKusen = 1,00 Buah = 1,98 M2
b = 0,90 M R1 LKusen = 0,30 x 0,50 x 2,00
h = 2,20 M = 0,30 M2
R1 JKusen = 2,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 1,98 + 0,30
= 2,28 M2
Total panjang pasangan batu bata
Σ PPas.Bata = 3,00 + 3,50 Luas pasangan bata bersih
= 6,50 M LPBB = 24,70 – 2,28
= 22,42 M2

53
h. Bidang D8E8 – D8D10

Dinding Luas dinding


h = 3,800 M LPas.Bata = 4,00 x 3,80
Bidang D8 – E8 (a) = 1,000 M = 15,20 M2
Bidang D8 – D10 (b) = 3,000 M
Luas kusen
Kusen P2 LKusen = 0,90 x 2,20 x 1,00
P2 JKusen = 1,00 Buah = 1,98 M2
b = 0,90 M R1 LKusen = 0,30 x 0,50 x 2,00
h = 2,20 M = 0,30 M2
R1 JKusen = 2,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 1,98 + 0,30
= 2,28 M2
Total panjang pasangan batu bata Luas pasangan bata bersih
Σ PPas.Bata = 1,00 + 3,00 LPBB = 15,20 – 2,28
= 4,00 M = 12,92 M2

54
i. Bidang D10G10 – G8G10

Dinding Luas dinding


h = 3,800 M LPas.Bata = 7,00 x 3,80
Bidang D10 – G10 (a) = 4,000 M = 26,60 M2
Bidang G8 – G10 (b) = 3,000 M
Luas kusen
Kusen J4 LKusen = 1,15 x 1,70 x 1,00
J4 JKusen = 1,00 Buah = 1,955 M2
b = 1,15 M R1 LKusen = 0,30 x 0,50 x 3,00
h = 1,70 M = 0,45 M2
R1 JKusen = 3,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 1,955 + 0,45
= 2,405 M2
Total panjang pasangan batu bata
Σ PPas.Bata = 4,00 + 3,00 Luas pasangan bata bersih
= 7,00 M LPBB = 26,60 – 2,405
= 24,195 M2

j. Bidang B10D10 – B9B10

55
Dinding Luas dinding
h = 3,800 M LPas.Bata = 5,80 x 3,80
Bidang B10 – D10 (a) = 4,300 M = 22,04 M2
Bidang B9 – B10 (b) = 1,500 M
Luas kusen
Kusen R1 LKusen = 0,30 x 0,50 x 5,00
R1 JKusen = 5,00 Buah = 0,75 M2
b = 0,30 M
h = 0,50 M Total luas kusen
Σ LKusen = 0,75 M2
Total panjang pasangan batu bata
Σ PPas.Bata = 4,30 + 1,50 Luas pasangan bata bersih
= 5,80 M LPBB = 22,04 – 0,75
= 21,29 M2

k. Bidang C4C8

56
Dinding Luas dinding
h = 3,800 M LPas.Bata = 6,00 x 3,80
Bidang C4 – C8 (a) = 6,000 M = 22,80 M2
Luas kusen
Kusen
J3 LKusen = 2,00 x 1,70 x 1,00
J3 JKusen = 1,00 Buah
= 3,40 M2
b = 2,00 M
R1 LKusen = 0,30 x 0,50 x 5,00
h = 1,70 M
= 0,75 M2
R1 JKusen = 5,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 3,40 + 0,75
= 4,15 M2
Total panjang pasangan batu bata Luas pasangan bata bersih
Σ PPas.Bata = 6,00 M LPBB = 22,80 – 4,15
= 18,65 M2

l. Bidang A8C8 – A8A9

Dinding R1 JKusen = 5,00 Buah


h = 3,800 M b = 0,30 M
Bidang A8 – C8 (a) = 3,000 M h = 0,50 M
Bidang A8 – A9 (b) = 1,500 M

Kusen Total panjang pasangan batu bata


PJ JKusen = 1,00 Buah Σ PPas.Bata = 3,00 + 1,50
b1 = 0,90 M = 4,50 M
h1 = 2,20 M
b2 = 1,30 M Luas dinding
h2 = 1,70 M LPas.Bata = 4,50 x 3,80
= 17,10 M2

57
Luas kusen Total luas kusen
PJ LKusen1 = 0,90 x 2,20 x 1,00 Σ LKusen = 1,98 + 2,21 + 0,75
= 1,98 M2 = 4,94 M2
LKusen2 = 1,30 x 1,70 x 1,00
= 2,21 M2 Luas pasangan bata bersih
R1 LKusen = 0,30 x 0,50 x 5,00 LPBB = 17,10 – 4,94
= 0,75 M2 = 12,16 M2

m. Bidang A9B9 – A10B10 – A9A10

Dinding Total panjang pasangan batu bata


h = 3,800 M Σ PPas.Bata = 1,20 + 1,20 + 1,50
Bidang A9 – B9 (a) = 1,200 M = 3,90 M
Bidang A10 – B10 (b) = 1,200 M
Bidang A10 – B10 (c) = 1,500 M Luas dinding
LPas.Bata = 3,90 x 3,80
Kusen = 14,82 M2
P3 JKusen = 1,00 Buah
b = 0,80 M Luas kusen
h = 2.15 M J1 LKusen = 1,30 x 1,70 x 1,00
V JKusen = 1,00 Buah = 2,21 M2
b = 0,70 M R1 LKusen = 0,30 x 0,50 x 2,00
h = 0,40 M = 0,45 M2

Luas kusen Total luas kusen


P3 LKusen = 0,8 x 2,15 x 1,00 Σ LKusen = 1,72 + 0,28
= 1,72 M2 = 2,00 M2
V LKusen = 0,70 x 0,40 x 1,00
= 0,28 M2 Luas pasangan bata bersih
LPBB = 14,82 – 2,00
= 12,82 M2

58
n. Bidang C1E1 – C1C2 – E1E2

Dinding Luas dinding


h = 0,800 M LPas.Bata = 5,90 x 0,80
Bidang E1 – C1 (a) = 3,500 M = 4,72 M2
Bidang C1 – G2 (b) = 1,200 M
Bidang C1 – G2 (b) = 1,200 M Luas kusen
R1 LKusen = 0,30 x 0,50 x 3,00
Kusen = 0,45 M2
R1 JKusen = 3,00 Buah
b = 0,30 M Total luas kusen
h = 0,50 M Σ LKusen = 0,45 M2

Total panjang pasangan batu bata Luas pasangan bata bersih


Σ PPas.Bata = 3,50 + 1,20 + 1,20 LPBB = 4,72 – 0,45
= 5,90 M = 4,27 M2

Total luas pasangan batu bata


Σ LPBB = 11,11 + 26,30 + 20,05 + 12,92 + 15,38 + 16,32 + 22,42 + 12,92 + 24,20 +
21,29 + 18,65 + 12,16 + 12,82 + 4,27
= 230,80 M2
Total luas pasangan batu bata 1 : 4 Σ LPB1 : 4

Rumus Σ LPB1 : 4 = Σ LPBB – Σ LPas.Trasram

Σ LPB1 : 4 = 230,80 – 15,750


= 215,05 M2

59
B. Menghitung Analisa Biaya Pekerjaan

1 M2 Pek. Pas. Batu bata 1/2 Bata 1 : 4


Bahan
70,0 Batu Bata Buah Rp 700 Rp 49.000
0,043 Pasir Pasangan M3 Rp 200.000 Rp 8.600
0,288 Semen PC Zak Rp 50.000 Rp 14.375
Rp 71.975
Upah Kerja
0,100 Tukang Batu OH Rp 120.000 Rp 12.000
0,010 Kepala Tukang OH Rp 125.000 Rp 1.250
0,015 Mandor OH Rp 130.000 Rp 1.950
0,300 Pekerja OH Rp 75.000 Rp 22.500
Rp 37.700

Total Bahan + Upah Kerja Rp 109.675

C. Menghitung Besar Biaya Pekerjaan

HARGA SATUAN JUMLAH HARGA


NO URAIAN SAT VOL
(Rp). (Rp).

2 Pek. Pas. Batu bata 1/2 Bata 1 : 4 M2 215,050 109.675 23.585.609

3. Pekerjaan plasteran campuran 1 Semen : 2 Pasir (Trasram) tebal 20 mm.

Pekerjaan plasteran campuran 1 : 2 (trasram) meliputi pekerjaan plasteran pada area


KM/WC.
Satuan dalam pekerjaan plasteran batu bata adalah M2.

A. Menghitung Volume Pekerjaan

Total plasteran luas plasteran 1 : 2 (Trasram) Σ LPlast1 : 2

Rumus Σ LPlast1 : 2 = Σ LPas.Trasram x 2

Σ LPlast1 : 2 = 15,75 x 2
= 31,50 M2

60
B. Menghitung Analisa Biaya Pekerjaan

1 M2 Pek. Plasteran tebal 20 mm 1 : 2 (Trasram)


Bahan
0,027 Pasir Pasangan M3 Rp 200.000 Rp 5.400
0,341 Semen PC Zak Rp 50.000 Rp 17.040
Rp 22.440
Upah Kerja
0,200 Tukang Batu OH Rp 120.000 Rp 24.000
0,020 Kepala Tukang OH Rp 125.000 Rp 2.500
0,013 Mandor OH Rp 130.000 Rp 1.690
0,260 Pekerja OH Rp 75.000 Rp 19.500
Rp 47.690

Total Bahan + Upah Kerja Rp 70.130

C. Menghitung Besar Biaya Pekerjaan

HARGA SATUAN JUMLAH HARGA


NO URAIAN SAT VOL
(Rp). (Rp).

3 Pek. Plasteran tebal 20 mm 1 : 2 (Trasram) M2 31,500 70.130 2.209.095

4. Pekerjaan plasteran campuran 1 Semen : 4 Pasir tebal 20 mm.

Pekerjaan plasteran campuran 1 : 2 (trasram) meliputi pekerjaan plasteran pada


semua area pasangan batu bata kecuali pada area KM/WC.
Satuan dalam pekerjaan plasteran batu bata adalah M2.

A. Menghitung Volume Pekerjaan

Total plasteran luas plasteran 1 : 4 Σ LPlast1 : 4

Rumus Σ LPlast1 : 4 = Σ LPB1 : 4 x 2

Σ LPlast1 : 4 = 215,05 x 2
= 430,10 M2

61
B. Menghitung Analisa Biaya Pekerjaan

1 M2 Pek. Plasteran tebal 20 mm 1 : 4


Bahan
0,027 Pasir Pasangan M3 Rp 200.000 Rp 5.400
0,208 Semen PC Zak Rp 50.000 Rp 10.400
Rp 15.800
Upah Kerja
0,200 Tukang Batu OH Rp 120.000 Rp 24.000
0,020 Kepala Tukang OH Rp 125.000 Rp 2.500
0,013 Mandor OH Rp 130.000 Rp 1.690
0,260 Pekerja OH Rp 75.000 Rp 19.500
Rp 47.690

Total Bahan + Upah Kerja Rp 63.490

C. Menghitung Besar Biaya Pekerjaan

HARGA SATUAN JUMLAH HARGA


NO URAIAN SAT VOL
(Rp). (Rp).

4 Pek. Plasteran tebal 20 mm 1 : 4 M2 430,100 63.490 27.307.049

5. Pekerjaan Acian.

Pekerjaan acian meliputi pekerjaan acian pada semua area pasangan batu bata kecuali
pada area KM/WC dan pasangan batu alam.
Satuan dalam pekerjaan acian adalah M2.

A. Menghitung Volume Pekerjaan

Total plasteran luas acian Σ LAcian

Rumus Σ LAcian = Σ LPlast1 : 4 - Σ LKrmkDinding - Σ LPas.BatuAlam

62
Σ LKrmkDinding = Σ LPas.Trasram
= 15,75 M2
Σ LPas.BatuAlam = 0,80 x 3,46
= 2,768 M2
Total plasteran luas acian Σ LAcian
Σ LAcian = 430,10 – 15,75 – 2,768
= 411,582 M2

B. Menghitung Analisa Biaya Pekerjaan

1 M2 Pek. Acian
Bahan
0,081 Semen PC Zak Rp 50.000 Rp 4.063
Rp 4.063
Upah Kerja
0,100 Tukang Batu OH Rp 120.000 Rp 12.000
0,010 Kepala Tukang OH Rp 125.000 Rp 1.250
0,008 Mandor OH Rp 130.000 Rp 1.040
0,150 Pekerja OH Rp 75.000 Rp 11.250
Rp 25.540

Total Bahan + Upah Kerja Rp 29.603

C. Menghitung Besar Biaya Pekerjaan

HARGA SATUAN JUMLAH HARGA


NO URAIAN SAT VOL
(Rp). (Rp).

5 Pek. Acian M2 411,582 29.603 12.184.062

63
6. Total Biaya Pekerjaan Pasangan Dinding dan Plasteran.

HARGA SATUAN JUMLAH HARGA


NO URAIAN SAT VOL
(Rp). (Rp).

1 Pek. Pas. Batu bata 1/2 Bata 1 : 2 (Trasram) M2 15,750 120.388 1.896.111

2 Pek. Pas. Batu bata 1/2 Bata 1 : 4 M2 215,050 109.675 23.585.609

3 Pek. Plasteran tebal 20 mm 1 : 2 (Trasram) M2 31,500 70.130 2.209.095


2
4 Pek. Plasteran tebal 20 mm 1 : 4 M 430,100 63.490 27.307.049

5 Pek. Acian M2 411,582 29.603 12.184.062

Sub Total Pekerjaan Pasangan Dinding dan Plasteran 67.181.926