SCHEDULE PROJECT FEEDMILL MAGELANG TAHUN 2018

WAKTU BULAN PEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER DESEMBER KETERANGAN
NO URAIAN PEKERJAAN PIC
PENGERJAAN MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44

1 PENCARIAN KONSULTAN
TARGET PROJECT 9 BULAN
1 PENETAPAN KONSULTAN BS,AB,MS,KS 1 MINGGU
SELESAI
SUDAH DITETAPKAN PAKAI PAK TULUS OKTA 05-Feb

2 PERHITUNGAN BANGUNAN DAN KONSTRUKSI OLEH KONSULTAN MS,KS 4 MINGGU


PELAKSANAAN PROJECT
ADMINISTRASI SPK RIRIN 09-Feb DILAKUKAN SECARA
SUDAH MULAI RANCANGAN DESAIN OKTA 08-Feb SIMULTAN
PEMBUATAN TOPOGRAFI + PEMETAAN TANAH FINISH 08-Feb 13-Feb
PROSES DP 5% (Rp 12.500.000,-) RIRIN 13-Feb
2 PENCARIAN KONTRAKTOR BR,AB,MS,KS 2 MINGGU

MAIN BUILDING

3 PEKERJAAN MILL TOWER


1 PENENTUAN LOAD MS,KS 3 MINGGU
SEMENTARA SUDAH ADA LOAD SUDAH DI KONSULTAN 08-Feb 16-Feb 28-Feb
2 PENENTUAN CONTRACTOR BR,AB,MS,KS 2 MINGGU
PEMBAYARAN CONTRACTOR FEEDMILL TOWER
3 MULAI PEKERJAAN PANCANG MS,KS 3 MINGGU
PEMBAYARAN PEMANCANGAN
4 PENGGALIAN TUNNEL MS,KS 3 MINGGU
5 PEMASANGAN PILE CAP MS,KS 2 MINGGU
6 PEMBESIAN DAN PEMBUATAN TUNNEL MS,KS 4 MINGGU
7 FABRIKASI KONSTRUKSI MS,KS 8 MINGGU
8 ERECTION KONSTRUKSI MS,KS 16 MINGGU
9 PEMBUATAN RUANG CONTROL,DAN RUANGAN COMPRESSOR MS,KS 6 MINGGU
10 PEMASANGAN LANTAI TOWERMILL MS,KS 8 MINGGU
11 PEMASANGAN MESIN-MESIN FEEDMILL MS,KS 8 MINGGU
PEMBAYARAN CONTRACTOR MESIN
12 PEMASANGAN ATAP MS,KS 4 MINGGU
13 PEMASANGAN CLADING MS,KS 4 MINGGU
14 PEASANGAN WIRING MS,KS 8 MINGGU
15 FINISHING PENGECATAN MS,KS 4 MINNGU
16 KOMISIONING/TEST RUN ( BY AWILLA) MS,KS 4 MINGGU

4 PEKERJAAN SILO
1 PENENTUAN LOAD BR,AB,MS,KS 2 MINGGU
SUDAH ADA DI KONTAKTOR 08-Feb
2 PENENTUAN KONTRAKTOR MS,KS 2 MINGGU
BARU ADA PENAWARAN ERECTION DARI SPM 27-Jan
PERSIAPAN PEMBAYARAN CONTRACTOR PONDASI SILO
3 MULAI PEKERJAAN PANCANG MS,KS 3 MINGGU
PEMBAYARAN PEMANCANGAN
4 PENGGALIAN TUNNEL MS,KS 3 MINGGU
5 PEMOTONGAN PANCANG MS,KS 2 MINGGU
6 PEMASANGAN PILE CAP MS,KS 2 MINGGU
7 PEMBESIAN DAN PEMBUATAN TUNNEL MS,KS 5 MINGGU
8 PENGECORAN PONDASI MS,KS 4 MINGGU
9 PEMATANGAN PONDASI MS,KS 4 MINGGU
10 PEMASANGAN SILO MS,KS 18 MINGGU
PEMBAYARAN CONTRACTOR ERECTION SILO
11 PEMASANGAN CHAIN SILO MS,KS 4 MINGGU
12 PEMASANGAN WIRING SILO DAN WH MS,KS 6 MINGGU
13 FINISHING DAN PENGECATAN MS,KS 2 MINGGU

PEKERJAAN GUDANG
5 GUDANG I
PENENTUAN KONTRAKTOR
SUDAH ADA PENAWARAN TIANG KENCANA 06-Feb
PEMBAYARAN CONTRACTOR PENGERJAAN GUDANG 1
1 PEMBESIAN LANTAI MS,KS 4 MINGGU
2 PENGECORAN LANTAI MS,KS 6 MINGGU
3 FINISHING MS,KS 4 MINGGU
WAKTU BULAN PEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER DESEMBER KETERANGAN
NO URAIAN PEKERJAAN PIC
PENGERJAAN MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44
6 GUDANG II
PENENTUAN KONTRAKTOR
SUDAH ADA PENAWARAN DARI TIANG KENCANA 06-Feb
PEMBAYARAN CONTRACTOR GUDANG 2
1 PEKERJAAN FABRIKASI MS,KS 6 MINGGU
2 PEMANCANGAN MS,KS 2 MINGGU
3 PENGGALIAN TUNNEL MS,KS 6 MINGGU
4 PEMBESIAN TUNNEL MS,KS 6 MINGGU
5 PENGECORAN TUNNEL MS,KS 3 MINGGU
6 PERATAAN TANAH MS,KS 2 MINGGU
7 ERECTION KONSTRUKSI MS,KS 6 MINGGU
8 PEMASANGAN ATAP MS,KS 6 MINGGU
9 PEMASANGAN DINDING MS,KS 8 MINGGU
10 PEMBESIAN LANTAI GUDANG MS,KS 4 MINGGU
11 PENGECCORAN LANTAI GUDANG MS,KS 4 MINGGU
12 FINISHING MS,KS 4 MINGGU

7 GUDANG FINISH GOOD


PENENTUAN KONTRAKTOR
PEMBAYARAN CONTRACTOR GUDANG 3
1 PEKERJAAN FABRIKASI MS,KS 6 MINGGU
2 PEMANCANGAN MS,KS 2 MINGGU
PEMBAYARAN PEMANCANGAN
3 PEMOTONGAN PANCANG MS,KS 2 MINGGU
4 PEMBESIAN MS,KS 6 MINGGU
5 PEMBUATAN PONDASI DAN PEDESTAL MS,KS 4 MINGGU
6 PERATAAN TANAH MS,KS 2 MINGGU
7 PENGECORAN LANTAI GUDANG MS,KS 6 MINGGU
8 ERECTION KONSTRUKSI MS,KS 6 MINGGU
9 MASANGAN DNDNG MS,KS 6 MINGGU
10 PEMASANGAN ATAP MS,KS 6 MINGGU
11 FINISHING MS,KS 4 MINGGU

8 PEMBUATAN JALAN
PEMBAYARAN CONTRACTOR JALAN
1 PERATAAN TANAH MS,KS 3 MINGGU
2 PEMBESIAN MS,KS 12 MINGGU
3 PENGECORAN MS,KS 12 MINGGU
4 FINISHING MS,KS 6 MINGGU

SUPPORT BUILDING

9 JEMBATAN TIMBANG
PENENTUAN KONTRAKTOR MS,KS,AF,BS 1 BULAN
PEMBAYARAN KONTRAKTOR JEMBATAN TIMBANG
PONDASI JEMBATAN TIMBANG MS,KS 1 BULAN
PONDASI KANOPI JEMBATAN TIMBANG MS,KS 2 MINGGU
KANOPI JEMBATAN TIMBANG MS,KS 1 BULAN
INSTALASI JEMBATAN TIMBANG MS,KS 13 HARI

10 KANTOR BS,AB
PENENTUAN PENAWARAN DARI KONTRAKTOR BS,AB 1 BULAN
PELAKSANAAN BS,AB 6 BULAN

11 MUSHOLA MS,KS 1 BULAN


12 KANTIN MS,KS 1 BULAN
13 RUANG LOKER MS,KS 1 BULAN
14 POS SECURITY MS,KS 1 BULAN

15 INTAKE JAGUNG MS,KS


KOTAKAN INTAKE MS,KS 1BULAN
PONDASI KANOPI INTAKE MS,KS 1 BULAN
KANOPI INTAKE JAGUNG MS,KS 3 BULAN

16 RUANG BOILER MS,KS 1 BULAN


PEKERJAAN SIPIL RUANGAN BOILER MS,KS 1 BULAN
INSTALASI BOILER MS,KS 2 BULAN

17 WET SILO
PONDASI WET SILO MS,KS 1 BULAN
ERECTION WET SILO MS,KS 1 BULAN

18 DRYER
PONDASI DRYER MS,KS 1 BULAN
ERECTION DRYER MS,KS 1 BULAN

NOTE:
BS = BAPAK BRAM SEBASTIAN AB = BAPAK ARIF BUDIMAN MS = BAPAK MOH.SHOLIHUDDIN KS = BAPAK KRISWIN