Anda di halaman 1dari 2

A.

2 Inspeksi Rail di Gedung Casting


A2.1) 1 mL Pekerjaan Pengencangan Baut Klem Rail, Girder OHC 20/3T, OHC 1T & Hoist 10T
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.012 250,000 2,976
Common Labour OH 0.048 140,000 6,667
Skill Labour OH 0.024 145,000 3,452
Foreman OH 0.024 175,000 4,167
Safety Officer OH 0.012 175,000 2,083
Jumlah Harga Upah 19,345
B Bahan
-
Jumlah Harga Bahan
C Alat
Torque Tools Wrench and good Paper Days 0.024 175,000 4,167
Vinyl Rope mL 0.020 156,000 3,120
Jumlah Harga Alat 7,287
D Harga Satuan Pekerjaan (A+B+C) 26,632

A2.2) 1 mL Pekerjaan Survey Rail untuk OHC 20/3T & Host Crane 10T
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.006 250,000 1,488
Surveyor OH 0.012 350,000 4,167
Common labour OH 0.012 140,000 1,667
Foreman OH 0.012 175,000 2,083
Safety Officer OH 0.006 175,000 1,042
Jumlah Harga Upah 10,446
B Bahan
-
Jumlah Harga Bahan
C Alat
Titting Level/water instrument Days 0.012 65,000 774
Transit/thedolite instrumen Days 0.012 850,000 10,119
Span Checkk meter equipment Days 0.012 185,000 2,202
Vinyl rope mL 0.020 156,000 3,120
Jumlah Harga Alat 16,215
D Harga Satuan Pekerjaan (A+B+C) 26,662

A2.3) 1 mL Pekerjaan Pengedjustan Baut Klem Rail OHC 20/3T & Hoist Crane 10T
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.010 250,000 2,381
Surveyor OH 0.038 350,000 13,333
Common Labour OH 0.019 140,000 2,667
Skill Labour OH 0.019 145,000 2,762
Foreman OH 0.019 175,000 3,333
Safety Officer OH 0.010 175,000 1,667
Jumlah Harga Upah 26,143
B Bahan
-
Jumlah Harga Bahan
C Alat
Titting Level/water instrument Days 0.019 65,000 1,238
Transit/thedolite instrumen Days 0.019 850,000 16,190
Span Checkk meter equipment Days 0.019 185,000 3,524
Vinyl rope mL 0.007 156,000 1,040
Jumlah Harga Alat 21,992
D Harga Satuan Pekerjaan (A+B+C) 48,135
B. Inspeksi Tahap II
B.1 Inspeksi Rail di Gedung Reduksi, LCS & LMS
B.1.1) 1 Pcs Pekerjaan Pemotongan Ujung Rail
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.042 250,000 10,417
Common Labour OH 0.167 140,000 23,333
Skill Labour OH 0.167 145,000 24,167
Foreman OH 0.083 175,000 14,583
Safety Officer OH 0.042 175,000 7,292
Jumlah Harga Upah 79,792
B Bahan
-
Jumlah Harga Bahan
C Alat
Welding Machine Days 0.083 65,000 5,417
Grinding Machine Days 0.083 75,000 6,250
Welding Rod Kg 0.083 38,000 3,167
Grinding Stone Pcs 0.083 35,000 2,917
Vinyl rope mL 0.007 156,000 1,040
Jumlah Harga Alat 18,790
D Harga Satuan Pekerjaan (A+B+C) 98,582

B.1.2) 1 mL Pekerjaan Pembersihan Debu Alumina pada di Sekitar Rail ACC & Traverser
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.004 250,000 893
Common Labour OH 0.014 140,000 2,000
Skill Labour OH 0.007 145,000 1,036
Foreman OH 0.007 175,000 1,250
Safety Officer OH 0.004 175,000 625
Jumlah Harga Upah 5,804
B Bahan
-
Jumlah Harga Bahan
C Alat
Waste Cloth kg 0.006 13,000 74
Paint Brush pcs 0.003 15,000 38
Wire Brush pcs 0.034 28,000 952
Vacum Machine days 0.001 156,000 119
Vinyl rope mL 0.004 156,000 594
Jumlah Harga Alat 1,777
D Harga Satuan Pekerjaan (A+B+C) 7,580

B.1.3) 1 mL Pekerjaan Pengencangan Baut Klem Rail, Girder Crane ACC & Traverser
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.012 250,000 2,976
Common Labour OH 0.048 140,000 6,667
Skill Labour OH 0.048 145,000 6,905
Foreman OH 0.024 175,000 4,167
Safety Officer OH 0.012 175,000 2,083
Jumlah Harga Upah 22,798
B Bahan
-
Jumlah Harga Bahan
C Alat
Torque tools wrench and good paper Days 0.024 175,000 4,167
Vinyl rope mL 0.020 156,000 3,120
Jumlah Harga Alat 7,287
D Harga Satuan Pekerjaan (A+B+C) 30,084

B.1.4) 1 m Pekerjaan Pengencangan Baut Klem Rail, Baut Girder OHC LCS & LMS
No. Uraian Satuan Koefisien Harga Satuan Harga Total Referensi
A Upah Kerja
Supervisor OH 0.012 250,000 2,976
Common Labour OH 0.095 140,000 13,333
Skill Labour OH 0.048 145,000 6,905
Foreman OH 0.024 175,000 4,167
Safety Officer OH 0.012 175,000 2,083
Jumlah Harga Upah 29,464
B Bahan
-
Jumlah Harga Bahan
C Alat
Torque tools wrench and good paper Days 0.024 175,000 4,167
Vinyl rope mL 0.007 156,000 1,040
Jumlah Harga Alat 5,207
D Harga Satuan Pekerjaan (A+B+C) 34,671