Anda di halaman 1dari 93

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA
NO. PERALATAN SATUAN KET.
(Rp)

1 Dump Truck 3 ton Jam 120,000


2 Dump Truck 9 ton Jam 170,000

3 Truk Bak Terbuka Engkel Jam 140,000

4 Truk Tanki Air Jam 300,000

5 Bulldozer 100 - 150 hp Jam 700,000

6 Motor Grader Jam 640,000

7 Wheel Loader Jam 280,000

8 Excavator Jam 660,000

9 Crane 35 ton Jam 450,000

10 Flat Bed Truck jam 440,000

11 Baby Roller / Pedestrian Jam 120,000

12 P.Tire Roller 8 - 10 ton Jam 550,000


13 Baby Roller jam 60,000

14 Vibrator Roller self 7 ton Jam 510,000

15 Pile Driver / Hammer jam 160,000

16 Water Pump Jam 40,000

17 Asphalt Sprayer Jam 140,000


18 Pick Up single cabin Jam 64,000

19 A M P Jam 5,600,000

20 Asphalt Finisher Jam 350,000

21 Concrete Vibrator Jam 60,000

22 Compressor Jam 320,000


23 Concrete Mixer 0,125m3 Jam 80,000

24 Concrete Cutter jam 40,000

25 Stamper Jam 40,000

26 Genset 5-25kva+bbm Jam 185,000

27 Alat Pengecat Marka Jam 320,000

28 Mesin Las jam 200,000

29 Stone Crusher jam 900,000

30 Truck Trailler trip 7,400,000


DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA
NO. URAIAN PEKERJA SATUAN KET.
(Rp)
1 Pekerja Hr 75,000

2 Mandor Hr 95,000

3 Tukang listrik Hr 95,000

4 Tukang kayu Hr 95,000

5 Kep. tk. kayu Hr 110,000

6 Tukang batu Hr 90,000

7 Kep. tk. batu Hr 110,000

8 Tukang besi Hr 90,000

9 Kep. tk. besi Hr 110,000

10 T u k a n g c a t Hr 90,000

11 K e p . t k . c a t Hr 110,000

12 T u k a n g p l i t u r Hr 90,000

13 T u k a n g j a l a n Hr 75,000

14 T u k a n g g a l i Hr 75,000

15 Tukang masak aspal Hr 75,000

16 T k . l e i d e n g Hr 90,000

17 M a s i n i s Hr 175,000

18 P e m b . M a s i n i s Hr 110,000

19 P e n j a g a a p i Hr 75,000

20 P e n j a g a m a l a m Hr 75,000

21 Sopir Hr 170,000

22 Pembantu Sopir Hr 110,000

509762178.xls 93 utk
DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA
NO. J E N I S B A H A N SAT KET
(Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 250,000
Bulat Belah m3 300,000
Pecah 10/15 m3 300,000
Pecah 5/7 m3 350,000
Pecah 3/5 m3 360,000
2 KERIKIL Timbun m3 200,000
Sawur / Koral m3 180,000
Beton 0,5/1 m3 370,000
Beton 1/2 m3 400,000
Beton 2/3 m3 390,000
Biasa m3 260,000
Tras Giling m3 330,000
3 BATU BATA ex lokal bh 600

4 PASIR Urug m3 230,000


Pasang m3 370,000
Beton m3 500,000
5 TANAH Padas m3 120,000
Liat m3 140,000
6 KAPUR Pasang m3 310,000
Semen Merah m3 200,000
7 PORTLAND CEMENT
Merk I 40 kg zak 44,000
Merk I 50 kg zak 54,000
Merk II 40 kg zak 43,000
Merk II 50 kg zak 54,000
Semen Putih 40 kg zak 80,000
Semen Putih 50 kg zak 95,000
Semen warna kg 12,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 190,000

2 GENTENG BETON Genteng Beton Warna standard bh 7,000


Genteng Beton Warna Special bh 10,500
Genteng Beton Warna Khusus bh 15,200
Kerpus Beton Warna Standard bh 10,050
Kerpus Beton Warna Special bh 12,000
Kerpus Beton Warna Khusus bh 13,500
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,400
Kodok bh 3,200
Kodok Glasur bh 4,350
Nok kerpus Kodok bh 6,800
Nok kerpus Kodok Glasur bh 12,000
Plentong super besar 18 bh/m2 bh 5,350
Nok kerpus plentong super bh 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 13,000
Vlaam tebal 3 mm bh 15,000
Kodok tebal 2 mm bh 14,000
Kodok tebal 3 mm bh 15,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 115,000
. 225 cm X 102 cm X 5 mm bh 125,000
. 250 cm X 102 cm X 5 mm bh 135,000
. 200 cm X 102 cm X 6 mm bh 120,000
. 225 cm X 102 cm X 6 mm bh 130,000
. 250 cm X 102 cm X 6 mm bh 140,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 47,000
. 180 cm X 105 cm X 4 mm bh 54,000
. 210 cm X 105 cm X 4 mm bh 63,000
. 240 cm X 105 cm X 4 mm bh 72,000
. 270 cm X 105 cm X 4 mm bh 81,000
. 300 cm X 105 cm X 4 mm bh 85,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 155,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 90,000
NOK Jabes nok
. Kerpus Genteng bh 40,000
. Stel Besar bh 50,000
. Paten Besar bh 47,000
Nokstel gelombang harflex
. Stel Besar bh 48,000
. Patent Besar bh 30,500
. Plat besar bh 55,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 110,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 17,000
. 100cm X 100 cm X 4 mm bh 20,000
. 50 cm X 200 cm X 3 mm bh 15,000
. 40 cm X 200 cm X 3 mm bh 14,000
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 30,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 72,500
uk. 122cm x 244cm x 4mm lbr 75,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 108,000
uk.122cm x 244cm x 6mm lbr 132,000
uk.122cm x 244cm x 8mm lbr 192,000
uk.122cm x 244cm x 10mm lbr 260,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 60,000
200 X 92 cm bh 65,000
250 X 92 cm bh 74,000
180 X 105 cm bh 90,000
210 X 105 cm bh 105,000
250 X 105 cm bh 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 24,500
BJLS 0,20 lebar 55 cm m' 30,000
BJLS 0,28 lebar 55 cm m' 30,000
BJLS 0,30 lebar 55 cm m' 36,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 45,000
BJLS 0,20 panjang 180 cm lbr 55,000
BJLS 0,30 panjang 180 cm lbr 60,000
BJLS 0,40 panjang 180 cm lbr 75,000
III . B A H A N K A Y U
1 JATI Papan m3 23,000,000
Balok/pesagen m3 20,500,000
2 KAMPER Papan m3 7,800,000
Balok/pesagen m3 7,500,000
3 KRUING Papan m3 7,000,000
Balok/pesagen m3 6,100,000
4 MERANTI Papan m3 5,700,000
Balok/pesagen m3 5,400,000
5 LANAN Papan m3 3,800,000
Balok/pesagen m3 2,200,000
6 BENGKIRAI Papan m3 10,000,000
Balok/pesagen m3 9,850,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 24,000
Kecil 6 x 7 x 400 cm bt 21,000
Besar 10 x 12 x 400 cm bt 34,000
Kayu cetakan m3 2,700,000
Kayu bakar m3 170,000
Bambu bt 12,000
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 36,000
20 X 20 cm m2 34,000
PC warna 30 X 30 cm m2 46,000
20 X 20 cm m2 42,000
Teraso 30 X 30 cm m2 56,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,500
PC abu-abu 15 x 20 bh 6,000

3 POLIS UBIN Lantai/badan m'


Plint m'
Trap m'

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 43,000
11 X 11 warna dos 46,000
Lokal 15 X 15 putih dos 47,500
15 X 15 warna dos 49,000
5 MOZAIK PORSELIN
10 X 20 cm m2 55,000
15 X 15 cm m2 55,000
20 X 20 cm m2 60,000
20 X 25 cm m2 56,000

6 Keramik 30 X 30 cm m2 57,000
20 X 20 cm m2 56,000
33 x 33 cm m2 60,000
25 x 25 cm m2 55,000
15 x 20 cm m2 57,000
2,500
7 Parquet Jati m2 310,000
8 Batu Paros m2 115,000
9 Batu Tempel Hitam m2 120,000
10 GRANITO 40 x 40 cm m2 250,000
30 x 30 cm m2 320,000
11 Marmer m2 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 40,000
Ø 20 cm - 100 cm bh 50,000
Ø 30 cm - 100 cm bh 70,000
Ø 50 cm - 100 cm bh 135,000
Ø 60 cm - 100 cm bh 190,000
Ø 70 cm - 100 cm bh 265,000
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
U 10 cm - 100 cm bh 22,500
U 15 cm - 100 cm bh 40,000
U 20 cm - 100 cm bh 45,000
U 30 cm - 100 cm bh 55,000
U 50 cm - 100 cm bh 70,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 12,000
20 X 20 cm bh 16,000
25 X 25 cm bh 17,000
30 X 30 cm bh 19,000
15 X 25 cm bh 13,000
15 X 30 cm bh 16,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 11,300
besi beton prestress kg 16,000
besi beton ulir kg 13,000

2 BESI PLAT Besi Strip kg 14,000

3 BESI PROFIL Besi Profil kg 14,500


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 22,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 30,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 14,000
Diameter 6 - 15 kg 14,500
Kawat Bronjong kg 10,000
5 BESI SIKU L 40 X 40 X 4 btg 120,000
L 50 X 50 X 5 btg 170,000
L 60 X 60 X 6 btg 250,000

6 KAWAT - Ikat beton/bendrat kg 16,000


- Harmonika 12 X 45 mm m2 20,500
- Harmonika 12 X 24 mm m2 21,000
- Harmonika 14 X 30 mm m2 20,000
- Harmonika 14 X 35 mm m2 27,500
- Kawat Nyamuk Nylon m2 18,000
- Kawat Kasa m2 20,000
- Saringan pasir m2 15,000
- Kawat loket m2 22,500
- Kawat duri rol 135,000
- Kawat bronjong kg 27,500
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 30,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 36,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 68,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - panjang 4 m

2 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN ½" btg 105,000 panjang 6 m
Pipa Medium B Galvanis DN 25 ( ¾" ) btg 150,000 panjang 6 m
Pipa Medium B Galvanis DN 32 ( 1" ) btg 180,000 panjang 6 m
Pipa Medium B Galvanis DN 50 ( 1½" ) btg 220,000 panjang 6 m
Pipa Medium B Galvanis DN 63 ( 2" ) btg 290,000 panjang 6 m
Pipa Medium B Galvanis DN 2½" btg 350,000 panjang 6 m
Pipa Medium B Galvanis DN 90 ( 3" ) btg 490,000 panjang 6 m
Pipa Medium B Galvanis DN 110 ( 4" ) btg 580,000 panjang 6 m
Pipa Medium B Galvanis DN 160 ( 6" ) btg 1,050,000 panjang 6 m
Pipa Medium B Galvanis DN 200 ( 8" ) btg 2,100,000 panjang 6 m
Pipa Medium B Galvanis DN 250 ( 10") btg - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 6,200
30 X 60 lbr 14,200
60 X 120 lbr 46,000
List Kayu Profil m' 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 68,000
3 HARD BOARD-uk: 4'X 8' lbr 52,000
GYPROC uk.120cmx240cmx9mm lbr
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 75,000
. 120 X 240 X 3 mm lbr 95,000
. 90 X 210 X 4 mm lbr 80,000
. 90 X 210 X 9 mm lbr 125,000
. 90 X 210 X 12 mm lbr 170,000
. 90 X 210 X 15 mm lbr 240,000
. 90 X 210 X 18 mm lbr 310,000
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
Tripleks
. 120 X 240 X 3 mm lbr 60,000
. 120 X 240 X 4 mm lbr 70,000
. 120 X 240 X 6 mm lbr 80,000
Multipleks
. 120 X 240 X 9 mm lbr 160,000
. 120 X 240 X 12 mm lbr 180,000
. 120 X 240 X 15 mm lbr 190,000
. 120 X 240 X 18 mm lbr 230,000
Formika ukuran pintu lbr 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 30,000
Dempul plamur kg 30,000
Ambril/amplas lbr 4,100
Batu Apung kg 35,000
Cat dasar kg 36,500
. Emco kg 55,000
. Yunior 66 (nippon paint) kg 58,000
- Koas bh 8,000
. Deculux kg 58,000
. Siralax ons 20,000
. Spiritus ltr 18,000
. Plitur jadi ltr 70,000

2 TEMBOK
Kalkarium kg 5,000
Kapur sirih kg 4,750
Plamur kg 32,000
Cat Tembok kg 23,000
Sintex 5 kg 115,000
Danabride 5 kg 115,000
Catylac 5 kg 125,000
Mowilex 2,50 kg 350,000

3 BESI
Menie kg 35,000
Cat mengkilat kg 58,000
Cat kg 85,000
Thinner A ltr 20,000
Minyak cat ltr 20,000
Thinner Super ltr 35,000
Residu (teer/aspal) drum 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 1,050,000
kapasitas 1100 liter. bh 2,000,000
Lem Aica Aibon kg 65,000
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 85,000
5 mm m2 95,000
2 ES KABUR 3 mm m2 85,000
5 mm m2 95,000
3 RAY BAND 3 mm m2 85,000
5 mm m2 92,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 3,300

SPLN LMK 1 X 2 1/2 mm2 m' 3,900

. 1X4 mm2 m' 6,000

1X6 mm2 m' 8,900

NYY :. 2 X 1 1/2 mm2 m' 9,450

PRIMA 2 X 2 1/2 mm2 m' 15,500

. 2X4 mm2 m' 28,000

2X6 mm2 m' 37,000

3 X 1 1/2 mm2 m' 14,000

3 X 2 1/2 mm2 m' 21,000

3X4 mm2 m' 36,500

3X6 mm2 m' 53,000

NYM :. 2 X 1 1/2 mm2 m' 8,000

PRIMA 2 X 2 1/2 mm2 m' 11,500

. 2X4 mm2 m' 23,000

3 X 1 1/2 mm2 m' 14,000

3 X 2 1/2 mm2 m' 22,000

3X4 mm2 m' 35,000

3X6 mm2 m' 48,000

2 SKAKELAR
Out bauw . Seri bh 21,000

. Engkel bh 15,000

In bauw . Seri bh 16,500

. Engkel bh 12,000

3 FUSE BOX (SEKERING KASA)


1 group bh 135,000

2 group bh 245,000

3 group bh 360,000

4 STEKER - Biasa bh 12,000

Arde bh 16,000

T Biasa bh 13,000

T dengan Arde bh 17,500


HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
5 FITING Flaon bh 11,000

Gantung bh 20,000

Kap bh 17,500

Kombinasi bh 350,000

6 STOP KONTAK - Arde Outbow putih bh 15,000

Arde Outbow hitam bh 6,000

Arde IB bh 15,000

Arde Putar bh 42,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 60,000
2 X slag bh 70,000
Yale : 1 X slag bh 95,000
2 X slag bh 155,000
Kuda : 1 X slag bh 60,000
2 X slag bh 75,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 16,000
Kupu-kupu biasa bh 4,500
Nylon kupu-kupu bh 9,000
Espagnoled - dalam negeri bh 50,000
Grendel Tanam luar negeri bh 11,000
Grendel biasa bh 20,000
Kait Angin bh 17,500
Door Stop bh 350,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,850,000
2 KLOSET JONGKOK bh 150,000
3 WASTAFEL PEDESTAL bh 1,050,000
4 WASTAFEL MEJA OVAL bh 950,000
5 WASTAFEL GANTUNG BULAT bh 450,000
6 WASTAFEL GANTUNG SUDUT bh 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 275,000
8 WASTAFEL BAK CUCI bh 165,000
9 TEMPAT SABUN GANTUNG bh 35,000
10 TEMPAT SABUN TANAM bh 25,000

11 SEPTIC TANK (ETERNIT GRESIK)


5 Pemakai 500 liter unit
10 Pemakai 1.000 liter unit -
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
12 LAIN - LAIN
Kran Air bh 45,000
Seal tape bh 4,100
Floor drain bh 35,000

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 18,000
2 PAKU - payung kg 30,000
3 PAKU - sekrup kg 8,000
4 PAKU - beton kg 30,000
5 MUR BAUT (kuda-kuda) kg 14,000
6 ANGKUR BAUT bh 13,500
7 LEM KAYU bh 20,000
8 Tali Ijuk kg 7,200

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 310,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 1,050,000
Fuji 250 watt bh 1,500,000
Shimizu . 100 watt bh 510,000
. 90 watt bh 380,000
Dab . 125 watt bh 400,000
. 175 watt bh 450,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 80,000
Merah/hitam m2 90,000
2 HOLLAND Abu-abu m2 80,000
Merah/hitam m2 90,000
3 UNIDECOR Abu-abu m2 75,000
Merah/hitam m2 90,000
4 UNI Abu-abu m2 80,000
Merah/hitam m2 90,000
5 TRIHEX Abu-abu m2 80,000
Merah/hitam m2 90,000
6 OLYMPIA HEXA Abu-abu m2 80,000
7 HEXAGONAL Abu-abu m2 90,000
Merah/hitam m2 80,000
8 CASTLE Abu-abu m2 90,000
9 TRAPEZ Abu-abu m2 80,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 80,000
11 STANDARD GRASS BLOCK ABU-ABU BH 8,500
12 BATACO BH 3,500
13 KANSTEEN m' 27,000
HARGA
NO. J E N I S B A H A N SAT KET
(Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 50,000
2 Sliding Pintu J4 bh 235,000
3 Naco per Daun bh 35,000
4 Rolling door Besi m2 325,000
Rolling door Almunium m2 275,000
5 Awning Almunium m2 225,000
6 Kusen Almunium 4" Putih m' 85,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,250,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 1,050,000

Hotmix Tebal = 4 Cm m2 67,500


Hotmix Tebal = 5 Cm m2 82,000
Hotmix Tebal = 6 Cm m2 97,000
Hotmix Tebal = 7 Cm m2 115,000
Binder Course ton 1,325,000
Wearing Course ton 1,400,000
Hot Roller Sheet ton 1,250,000
Sand Sheet ton 1,250,000
Sand Sheet Emulsi ton 1,500,000
Cold Mix ton 1,850,000
Prime / Tack Coard RC liter 8,000
Prime Coat MC liter 8,000
Prime / Tack Coat Emulsi liter 8,000
10 K A C A
Cermin tebal 5 mm m2 275,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 200,000


Pagar BRC 120 A2 /lb 250,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 10,000
Pintu Lipat Besi m2 425,000
Sunscreen Allumunim m2 350,000
Allumunium Foil m2 8,000
Soda api kg 15,000
Sabun kg 13,000
Air m3 20,000
Koas Alang-alang ikat 2,000
Solar (Industri) ltr 7,200
Premium (Industri) ltr 6,800
Pelumas ltr 45,000
Vynil 30x30 cm bh 6,500
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS SEPTEMBER 2017


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 679,679.00
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 155,248.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 2,074,242.50

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,656,215.00


5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,608,062.50

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 1,899,480.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 13,475.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 338,898.12

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 555,324.00

10 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,169,652.00

11 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 553,476.00

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 64,487.50

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 78,952.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 93,626.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 85,844.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 130,020.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 103,702.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 4,647.50


8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 28,270.00
Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 15,491.67
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 46,475.00

11 A.2.3.1.11 Urugan Pasir m3 329,395.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 456,137.00


Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang
13 A.2.3.1.13 m2 61,462.50
Resapan
14 A.2.3.1.14 Mengurug Sirtu Padat m3 287,237.50

509762178.xls 93/14 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,052,727.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,019,782.50

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 996,880.50

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 980,809.50


5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 958,710.50

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 844,662.50


Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 935,093.50
PP

8 A.3.2.1.8 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP m3 918,054.50

9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 617,050.50


Pasang Pondasi Siklop, 60% Beton Campuran 1PC :
10 A.3.2.1.10 m3 2,687,058.00
2PB : 3KR & 40% Batu B0elah
11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 988,003.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Membuat Beton mutu f'c=7,4 Mpa (K100), slum
1 A.4.1.1.1 m3 1,137,864.36
(12±2)cm, w/c = 0,87
Membuat Beton mutu f'c=9,8 Mpa (K125), slum
2 A.4.1.1.2 m3 1,160,978.33
(12±2)cm, w/c = 0,78
Membuat Beton mutu f'c=12,2 Mpa (K150), slum
3 A.4.1.1.3 m3 1,179,004.36
(12±2)cm, w/c = 0,72
Membuat Lantai Kerja Beton mutu f'c=7,4 MPa
4 A.4.1.1.4 m3 1,081,726.21
(K100), slum (3-6)cm, w/c = 0,87
Membuat Beton mutu f'c=14,5 MPa (K175), slum
5 A.4.1.1.5 m3 1,200,166.26
(12±2)cm, w/c = 0,66
Membuat Beton mutu f'c=16,9 MPa (K200), slum
6 A.4.1.1.6 m3 1,220,868.96
(12±2)cm, w/c = 0,61
Membuat Beton mutu f'c=19,3 MPa (K225), slum
7 A.4.1.1.7 m3 1,235,979.12
(12±2)cm, w/c = 0,58
Membuat Beton mutu f'c=21,7 MPa (K250), slum
8 A.4.1.1.8 m3 1,246,809.75
(12±2)cm, w/c = 0,56
Membuat Lantai Kerja Beton mutu f'c=24,0 MPa
9 A.4.1.1.9 m3 1,266,155.79
(K275), slum (12±2)cm, w/c = 0,53
Membuat Beton mutu f'c=26,4 MPa (K300), slum
10 A.4.1.1.10 m3 1,271,858.33
(12±2)cm, w/c = 0,52
Membuat Beton mutu f'c=28,8 MPa (K325), slum
11 A.4.1.1.11 m3 1,341,926.23
(12±2)cm, w/c = 0,49
Membuat Beton mutu f'c=31,2 MPa (K350), slum
12 A.4.1.1.12 m3 1,349,730.99
(12±2)cm, w/c = 0,48
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 14,712.50

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 19,655.35

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 31,431.40


16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 178,343.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 190,443.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 416,531.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 436,661.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 522,131.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 476,481.50

509762178.xls 93/15 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 391,781.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 107,734.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 88,038.50

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 113,371.50

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 30,602.00

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 21,747.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 111,413.50


Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,
4 A.4.2.1.4 m2 846,659.00
rangka baja Siku
5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,574.66

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 238,227.22

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 597,047.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 557,403.00


9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 485,298.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 506,825.00

11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 117,350.75

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 509,062.40

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 476,426.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 181,566.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 512,990.27

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 100,103.82


17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 131,224.50
Pemasangan Talang Datar / Jurai , Seng BJLS 28
18 A.4.2.1.18 m' 210,094.50
Lebar 90 cm
Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;
19 A.4.2.1.20 m2 116,583.50
Modul 60x120 cm dinding partisi
Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;
20 A.4.2.1.21 m2 146,366.00
Modul 60x60 cm dinding plafond
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 213,510.28
C dingin Profil C75
Pemasangan Atap Jurai Rangka Atap Baja Canal
22 A.4.2.1.23 m2 239,338.55
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING
Pemasangan Dinding Bata Merah ukuran (5x11x22)
1 A.4.4.1.1 m2 252,450.00
cm Tebal 1 bata Camp. 1SP: 2PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
2 A.4.4.1.2 m2 244,161.50
cm Tebal 1 Bata Camp. 1SP : 3PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
3 A.4.4.1.3 m2 237,231.50
cm Tebal 1 Bata Camp. 1SP : 4PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
4 A.4.4.1.4 m2 235,631.00
cm Tebal 1 Bata Camp. 1SP : 5PP

509762178.xls 93/16 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
5 A.4.4.1.5 m2 239,294.00
cm Tebal 1 Bata Camp. 1SP : 6PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
6 A.4.4.1.6 m2 226,476.80
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP
Pemasangan Dinding Bata Merah Ukuran
7 A.4.4.1.7 m2 122,023.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP
Pemasangan Dinding Bata Merah Ukuran
8 A.4.4.1.8 m2 117,295.20
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
Pemasangan Dinding Bata Merah Ukuran
9 A.4.4.1.9 m2 115,043.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
Pemasangan Dinding Bata Merah Ukuran
10 A.4.4.1.10 m2 113,655.30
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
Pemasangan Dinding Bata Merah Ukuran
11 A.4.4.1.11 m2 113,637.70
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
Pemasangan Dinding Bata Merah Ukuran
12 A.4.4.1.12 m2 111,842.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 114,537.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 101,051.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
Pemasangan Dinding Bata Merah Ukuran
15 A.4.4.1.15 m2 102,877.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
Pemasangan Dinding HB/CB 20, speci camp. 1SP :
16 A.4.4.1.16 m2 442,322.10
3PP
Pemasangan Dinding HB/CB 20, speci camp. 1SP :
17 A.4.4.1.17 m2 452,897.50
4PP
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
18 A.4.4.1.18 m2 347,124.80
3PP
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 354,655.40
4PP
Pemasangan Dinding HB/CB 10, speci camp. 1SP :
20 A.4.4.1.20 m2 255,524.50
3PP
Pemasangan Dinding HB/CB 10, speci camp. 1SP :
21 A.4.4.1.21 m2 261,626.20
4PP
Pemasangan Dinding Terawang (Rooster) Uk,
22 A.4.4.1.22 m2 460,982.50
(12x11x24)cm Camp. 1SP : 3PP
Pemasangan Dinding Terawang (Rooster) Uk,
23 A.4.4.1.23 m2 460,982.50
(12x11x24)cm Camp. 1SP : 4PP
Pemasangan Dinding Bata Berongga Ekspose Uk,
24 A.4.4.1.24 m2 148,241.50
(12x11x24)cm Camp. 1SP : 3PP
Pemasangan Dinding Bata Ringan Tebal 7,5 cm
25 A.4.4.1.25 m2 131,285.06
dengan Mortar Siap Pakai
Pemasangan Dinding Bata Ringan Tebal 10 cm
26 A.4.4.1.26 m2 147,858.21
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 68,254.34

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 63,493.54

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 61,752.46

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 60,300.90


5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 59,837.14

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 59,314.86

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 59,141.06

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 58,967.26

509762178.xls 93/17 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15
9 A.4.4.2.9 m2 58,196.60
mm
Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15
10 A.4.4.2.10 m2 58,388.00
mm
Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15
11 A.4.4.2.11 m2 53,625.00
mm
Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15
12 A.4.4.2.12 m2 54,945.00
mm
13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 85,002.72
14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 63,809.80

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 80,610.20

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 80,127.52

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 79,295.48


Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 75,416.00
mm
19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 38,458.64
Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10
20 A.4.4.2.20 m' 57,354.00
mm
Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal
21 A.4.4.2.21 m' 94,836.50
10 mm
Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10
22 A.4.4.2.22 m' 94,836.50
mm
23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 45,096.70
Pemasangan Finishing Siar Pasangan Dinding Bata
24 A.4.4.2.24 m2 25,364.68
Merah
Pemasangan Finishing Siar Pasangan Dinding
25 A.4.4.2.25 m2 12,078.00
Conblock ekspose
Pemasangan Finishing Siar Pas.Batu Kali Adukan
26 A.4.4.2.26 m2 55,537.90
1Pc : 2Pp
27 A.4.4.2.27 Pemasangan Acian m2 32,587.50

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 41,556.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 35,268.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 95,385.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 95,293.00

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 121,812.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 124,223.00

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 337,942.00

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 59,219.60

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 34,191.85


8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 36,689.09
Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20
9 A.4.4.3.33 m2 188,726.73
cm
10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 192,354.28

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 182,802.50

509762178.xls 93/18 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 191,922.50
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 m2 387,596.00
variasi / border
14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 32,701.35

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 79,060.85

16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 76,728.85


17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 670,911.73

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 195,189.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 366,437.50

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 222,289.41

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 202,133.25

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 211,010.25

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 202,133.25

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 212,154.25


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 745,394.22
Pemasangan Dinding Batu Paros / Batu Tempel
26 A.4.4.3.58 m2 243,560.63
Hitam
27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 138,373.40

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 108,240.00

29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 42,339.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 137,005.55

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 206,124.05

32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 143,116.05


33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 218,345.05

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT
Pemasangan Langit-langit Asbes (1,00x1,00) m,
1 A.4.5.1.1 m2 31,823.00
tebal 4 mm, 5 mm & 6 mm
Pemasangan Langit-langit Akustik Ukuran (30x30)
2 A.4.5.1.2 m2 107,349.00
cm
Pemasangan Langit-langit Akustik Ukuran (30x60)
3 A.4.5.1.3 m2 112,018.50
cm
Pemasangan Langit-langit Akustik Ukuran (60x120)
4 A.4.5.1.4 m2 97,322.50
cm
Memasang Langit-langit Tripleks Uk (120x240) cm,
5 A.4.5.1.5 m2 49,901.50
Tebal 3 mm, 4 mm & 6 mm
Memasang Langit-langit Lambriziring Kayu Jati, tebal
6 A.4.5.1.6 m2 543,158.00
6 mm
Memasang Langit-langit Gypsu Board, Ukuran
7 A.4.5.1.7 m2 43,705.20
(120x240) tebal 9 mm
Memasang Langit-langit Akuatik Uk (60x120) cm &
8 A.4.5.1.8 m2 220,467.50
Berikut Rangka Allumunium
9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 16,241.50

509762178.xls 93/19 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 87,956.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 141,641.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 127,946.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 103,158.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 116,633.00


6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 119,713.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 113,520.00


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 68,029.50
x 5 mm
Pemasangan Atap Asbes Gelombang (2,25x0,92 m)
9 A.4.5.2.9 m2 70,273.50
x 5 mm
Pemasangan Atap Asbes Gelombang (2,00x0,92 m)
10 A.4.5.2.10 m2 70,933.50
x 5 mm
Pemasangan Atap Asbes Gelombang (1,80x0,92 m)
11 A.4.5.2.11 m2 73,771.50
x 5 mm
Pemasangan Atap Asbes Gelombang (3,00x1,05 m)
12 A.4.5.2.12 m2 55,346.50
x 4 mm
Pemasangan Atap Asbes Gelombang (2,70x1,05 m)
13 A.4.5.2.13 m2 60,043.50
x 4 mm
Pemasangan Atap Asbes Gelombang (2,40x1,05 m)
14 A.4.5.2.14 m2 57,469.50
x 4 mm
Pemasangan Atap Asbes Gelombang (2,10x1,05 m)
15 A.4.5.2.15 m2 57,964.50
x 4 mm
Pemasangan Atap Asbes Gelombang (1,50x1,05 m)
16 A.4.5.2.16 m2 63,981.50
x 4 mm
Pemasangan Atap Asbes Gelombang (3,00x1,08 m)
17 A.4.5.2.17 m2 65,356.50
x 6 mm
Pemasangan Atap Asbes Gelombang (2,70x1,08 m)
18 A.4.5.2.18 m2 68,821.50
x 6 mm
Pemasangan Atap Asbes Gelombang (2,40x1,08 m)
19 A.4.5.2.19 m2 66,181.50
x 6 mm
Pemasangan Atap Asbes Gelombang (2,10x1,08 m)
20 A.4.5.2.20 m2 67,358.50
x 6 mm
Pemasangan Atap Asbes Gelombang (1,80x1,08 m)
21 A.4.5.2.21 m2 70,900.50
x 6 mm
22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 114,499.00

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 236,302.00

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 100,485.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 110,341.00

26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 124,184.50

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 130,564.50

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 67,688.50

29 A.4.5.2.38 Pemasangan Nok Sirap m' 55,467.50


30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 41,019.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 31,856.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 28,281.00

509762178.xls 93/20 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 m3 27,914,425.00
Kayu klas I
Pembuatan & Pemasangan Kosen Pintu & Jendela
2 A.4.6.1.2 m3 12,571,900.00
Kayu klas II atau III
Pembuatan & Pemasangan Pintu KlampStandard
3 A.4.6.1.3 m2 497,376.00
Kayu Klas II (Kayu Kamfer)
Pembuatan & Pemasangan Daun Pintu Klamp
4 A.4.6.1.4 m2 497,376.00
Sederhana Kayu Klas III
Pembuatan & Pemasangan Daun Pintu Panel, Kayu
5 A.4.6.1.5 m2 781,825.00
Klas I atau II
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 m2 562,540.00
Kayu Klas I atau II
Pembuatan & Pemasangan Pintu & Jendela Jalusi
7 A.4.6.1.7 m2 2,067,725.00
Kayu Klas I atau II (jati)
Pembuatan&Pemasangan Pintu kayu lapis
8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 620,361.50
cm)
Pembuatan&Pemasangan Pintu Plywood rangkap,
9 A.4.6.1.9 m2 669,262.00
rangka expose kayu klas I atau II
Pembuatan & Pemasangan Jalusi mati Kosen Kayu
10 A.4.6.1.10 m2 1,844,452.50
Klas I atau II
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 m2 1,077,714.00
Rangkap, Rangka Expose Kayu Klas I
Pembuatan & Pemasangan Pintu Teakwood
12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 718,052.50
II
Pembuatan&Memasang Konstruksi Kuda-kuda
13 A.4.6.1.13 m3 11,166,980.00
Konvensional Kayu I; II & III Bentang 6 meter
Pembuatan&Pemasangan Konstruksi Kuda-kuda
14 A.4.6.1.14 m3 30,333,297.50
Expose, Kayu Klas I
15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 10,415,460.00
Pemasangan Rangka Atap Genteng Keramik, Kayu
16 A.4.6.1.16 m2 170,582.50
Klas II
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 200,282.50
Klas II
18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 143,979.00
Pemasangan Rangka Langit-langit (50x1,00) m,
19 A.4.6.1.19 m2 186,202.50
kayu Klas II atau III
Pemasangan Rangka Langit-langit (60x60) cm, kayu
20 A.4.6.1.20 m2 191,950.00
Klas II atau III
Pemasangan Listplank Uk. (3x20)cm Kayu klas I
21 A.4.6.1.21 m' 307,312.50
atau II
Pemasangan Listplank Uk. (3x30)cm Kayu klas I
22 A.4.6.1.22 m' 127,462.50
atau klas II
Pemasangan Rangka Dinding Pemisah (60x120) cm
23 A.4.6.1.23 m2 299,651.00
Kayu klas II atau III
Pemasangan Dinding Pemisah Teakwood Rangkap
24 A.4.6.1.24 m2 387,651.00
Rangka Kayu Klas II
Pemasangan Dinding Pemisah Plywood Rangkap
25 A.4.6.1.25 m2 394,625.00
Rangka Kayu Klas II
Pemasangan Dinding Lambriziring dari Papan Kelas
26 A.4.6.1.26 m2 442,915.00
I
Pemasangan Dinding Lambriziring dari Plywood
27 A.4.6.1.27 m2 42,762.50
ukuran (120x240) cm
Pemasangan Dinding Bilik, Rangka Kayu Klas III
28 A.4.6.1.28 m2 139,761.60
atau IV

509762178.xls 93/21 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
HARGA SATUAN PEKERJAAN KUNCI dan
XII A.4.6.2
KACA
1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 225,307.50

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 158,028.75

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 224,028.75

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 29,411.25

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 17,957.50


6 A.4.6.2.7 Pemasangan Engsel Angin Buah 49,222.25

7 A.4.6.2.9 Pemasangan Kait Angin Buah 38,813.50

8 A.4.6.2.10 Pasang Door Closer Buah 447,686.25

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 47,074.50

10 A.4.6.2.13 Pemasangan Door Stop Buah 397,537.25

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 333,723.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 39,598.35

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 121,655.88


14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 133,755.88

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 351,555.88

HARGA SATUAN PEKERJAAN


XIII A.4.7.1
PENGECATAN
Pengikisan / pengerokan Permukaan Cat Tembok
1 A.4.7.1.1 m2 13,513.50
Lama
Pencucian Bidang Permukaan Tembok yang Pernah
2 A.4.7.1.2 m2 13,403.50
dicat
Pengerokan Karat Cat Lama permukaan Baja dg
3 A.4.7.1.3 m2 13,926.00
cara manual
Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp
4 A.4.7.1.4 m2 44,368.50
Cat dasar, 2 Lp Cat Penutup)
Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp
5 A.4.7.1.5 m2 59,900.50
Cat dasar, 3 Lp Cat Penutup)
6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 34,452.00

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 61,033.50

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 10,032.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 38,395.50


Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar
10 A.4.7.1.10 m2 21,057.30
2 Lap.Cat Penutup)
Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat
11 A.4.7.1.11 m2 14,054.70
Penutup)
12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 8,070.70

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 15,073.85


Pelaburan Tembok lama dengan Kapur Sirih
14 A.4.7.1.14 m2 7,163.75
(pemeliharaan)
15 A.4.7.1.15 Pemasangan Wallpaper m2 92,331.25

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 27,618.25


Pengecatan Permukaan Baja dg Meni Besi &
17 A.4.7.1.17 m2 54,326.25
Perancah

509762178.xls 93/22 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
HARGA SATUAN PEKERJAAN SANITASI
XIV A.5.1.1
DALAM GEDUNG
1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,561,141.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 613,800.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 757,130.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 797,582.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,149,951.00


6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,187,450.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,501,093.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,952,874.90

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 380,022.50

10 A.5.1.1.14 Pemasangan Floor Drain buah 51,507.50


Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 450,345.50
tinggi 35 cm
Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45
12 A.5.1.1.16 bh 660,572.00
tinggi 50 cm
Pemasangan Bak Kontrol Pas.Batu Bata 60x60
13 A.5.1.1.17 bh 793,997.19
tinggi 60 cm
14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 47,608.00

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 97,498.78

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 60,395.50

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 68,920.50

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 92,937.17

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 177,406.17

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 285,389.50

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 22,962.50


22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 25,520.00

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 29,356.25

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 34,585.83

25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 45,100.00

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 75,412.33

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 89,741.67


Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø
28 A.5.1.1.33 m' 84,392.00
20 cm
Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø
29 A.5.1.1.34 m' 41,783.50
15 cm
30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 127,915.70

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 594,929.50

509762178.xls 93/23 hspk


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN BEBAS
D A E R A H : KOTA SEMARANG & SEKITAR
SEPTEMBER 2017

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
A.2.2.1.2 1 m' 679,679.00
1 2,00 m
A TENAGA 57,100.00
L.01 0.2 OH Pekerja 75,000.00 15,000.00
L.02 0.4 OH Tukang Kayu 95,000.00 38,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.02 OH Mandor 95,000.00 1,900.00
B BAHAN 560,790.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 24,000.00 30,000.00
2.5 Kg Portalnd Semen 1,100.00 2,750.00
1.2 Lbr Seng Gelombang 3" - 5" 55,000.00 66,000.00
0.005 m3 Pasir Beton 500,000.00 2,500.00
0.009 m3 Koral Beton 390,000.00 3,510.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 6,100,000.00 439,200.00
0.06 Kg Paku Biasa 2" - 5" 18,000.00 1,080.00
0.45 Kg Meni Besi 35,000.00 15,750.00
C PERALATAN
D Jumlah A + B + C 617,890.00
E Overhead & Profit (contah 10%) 10% 61,789.00
F Harga Satuan Pekerjaan (D+E) 679,679.00
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 155,248.50
A Tenaga 18,575.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 122,560.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 6,100,000.00 73,200.00
0.02 Kg Paku Biasa 2" - 5" 18,000.00 360.00
0.007 m3 Kayu Papan 3/20 Kruing 7,000,000.00 49,000.00
C PERALATAN
D Jumlah A + B + C 141,135.00
E Overhead & Profit (contah 10%) 10% 14,113.50
F Harga Satuan Pekerjaan (D+E) 155,248.50

3 A.2.2.1.5 K.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 2,074,242.50

A Tenaga 472,750.00
L.01 2 OH Pekerja 75,000.00 150,000.00
L.02 2 OH Tukang Kayu 95,000.00 190,000.00
L.02 1 OH Tukang Batu 95,000.00 95,000.00
L.03 0.3 OH Kepala Tukang 110,000.00 33,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 1,412,925.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 24,000.00 30,000.00
0.18 m3 Kayu 6,100,000.00 1,098,000.00
0.80 Kg Paku Biasa 2" - 5" 18,000.00 14,400.00
1.1 Kg Besi Strip 14,000.00 15,400.00
35 Kg Portland Sement 1,100.00 38,500.00
0.15 m3 Pasir pasang 370,000.00 55,500.00
0.1 m3 Pasir Beton 500,000.00 50,000.00
0.15 m3 Koral Beton 390,000.00 58,500.00
30 buah Batu bata Merah 600.00 18,000.00
0.25 Lbr Seng Plat 24,500.00 6,125.00
0.20 buah Jendela Naco 35,000.00 7,000.00
0.08 m2 Kaca Polos 85,000.00 6,800.00
0.15 buah Kunci Tanam 70,000.00 10,500.00
0.06 Lbr Plywood 4 mm 70,000.00 4,200.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 1,885,675.00
E Overhead & Profit (contah 10%) 10% 188,567.50
F Harga Satuan Pekerjaan (D+E) 2,074,242.50

4 A.2.2.1.6 K.3 1 m2 Pembuatan Rumah Jaga (Konstruksi Kayu) 1,656,215.00


A Tenaga 238,750.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 1.50 OH Tukang Kayu 95,000.00 142,500.00
L.03 0.15 OH Kepala Tukang 110,000.00 16,500.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 1,266,900.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 24,000.00 72,000.00
0.18 m3 Kayu 6,100,000.00 1,098,000.00
0.80 Kg Paku Biasa 2" - 5" 18,000.00 14,400.00
1.50 Lbr Seng Gelombang 55,000.00 82,500.00
C PERALATAN
D Jumlah A + B + C 1,505,650.00
E Overhead & Profit (contah 10%) 10% 150,565.00
F Harga Satuan Pekerjaan (D+E) 1,656,215.00

5. A.2.2.1.7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 1,608,062.50


A Tenaga 291,750.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 2 OH Tukang Kayu 95,000.00 190,000.00
L.03 0.2 OH Kepala Tukang 110,000.00 22,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 1,455,750.00
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 24,000.00 40,800.00
0.21 m3 Kayu 6,100,000.00 1,281,000.00
0.3 Kg Paku Biasa 2" - 5" 18,000.00 5,400.00
10.5 Kg Portland Semen 1,100.00 11,550.00
0.03 m3 Pasir Beton 500,000.00 15,000.00
0.05 m3 Koral Beton 390,000.00 19,500.00
1.5 Lbr Seng Gelombang 55,000.00 82,500.00
0.25 Lbr Seng Plat 24,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 1,461,875.00
E Overhead & Profit (contah 10%) 10% 146,187.50
F Harga Satuan Pekerjaan (D+E) 1,608,062.50

6. A.2.2.1.8 K.3 1 m2 Pembuatan Bedeng Pekerja 1,899,480.00


A Tenaga 291,750.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 2 OH Tukang Kayu 95,000.00 190,000.00
L.03 0.2 OH Kepala Tukang 110,000.00 22,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 1,435,050.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 24,000.00 30,000.00
0.186 m3 Kayu 6,100,000.00 1,134,600.00
0.30 Kg Paku Biasa 2" - 5" 18,000.00 5,400.00
18.00 Kg Portland Semen 1,100.00 19,800.00
0.03 m3 Pasir Beton 500,000.00 15,000.00
0.05 m3 Koral Beton 390,000.00 19,500.00
1.50 Lbr Seng Gelombang 55,000.00 82,500.00
1.35 Lbr Playwood 95,000.00 128,250.00
C PERALATAN
D Jumlah A + B + C 1,726,800.00
E Overhead & Profit (contah 10%) 10% 172,680.00
F Harga Satuan Pekerjaan (D+E) 1,899,480.00

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 13,475.00


A Tenaga 12,250.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 12,250.00
E Overhead & Profit (contah 10%) 10% 1,225.00
F Harga Satuan Pekerjaan (D+E) 13,475.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 338,898.12


A Tenaga 291,750.00
L.01 1.00 OH Pekerja 75,000.00 75,000.00
L.02 2.00 OH Tukang Kayu 95,000.00 190,000.00
L.03 0.20 OH Kepala Tukang 110,000.00 22,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 16,339.20
1.250 Btg Bambu diameter 6 - 8 / 600 cm 12,000.00 15,000.00
0.186 Kg Tali Ijuk 7,200.00 1,339.20
C PERALATAN
D Jumlah A + B + C 308,089.20
E Overhead & Profit (contah 10%) 10% 30,808.92
F Harga Satuan Pekerjaan (D+E) 338,898.12

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 555,324.00
40cmx50cmx25cm
A Tenaga 31,800.00
L.02 0.30 OH Tukang Kayu 95,000.00 28,500.00
L.03 0.03 OH Kepala Tukang 110,000.00 3,300.00
B Bahan 473,040.00
0.036 m3 Kayu Papan Kelas III 7,000,000.00 252,000.00
0.036 m3 Kayu Balok Kelas III 6,100,000.00 219,600.00
0.080 kg Paku Biasa 18,000.00 1,440.00
C PERALATAN
D Jumlah A + B + C 504,840.00
E Overhead & Profit (contah 10%) 10% 50,484.00
F Harga Satuan Pekerjaan (D+E) 555,324.00

10 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,169,652.00


A Tenaga 1,063,320.00
L.02 13.334 OH Pekerja 75,000.00 1,000,050.00
L.04 0.666 OH Mandor 95,000.00 63,270.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,063,320.00
E Overhead & Profit (contah 10%) 10% 106,332.00
F Harga Satuan Pekerjaan (D+E) 1,169,652.00

11 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 553,476.00


B Tenaga 503,160.00
L.02 6.667 OH Pekerja 75,000.00 500,025.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan
C PERALATAN
D Jumlah A + B + C 503,160.00
E Overhead & Profit (contah 10%) 10% 50,316.00
F Harga Satuan Pekerjaan (D+E) 553,476.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 64,487.50


A TENAGA 58,625.00
L.01 0.75 OH Pekerja 75,000.00 56,250.00
L.04 0.025 OH Mandor 95,000.00 2,375.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 58,625.00
E Overhead & Profit (contah 10%) 10% 5,862.50
F Harga Satuan Pekerjaan (D+E) 64,487.50
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 78,952.50
A TENAGA 71,775.00
L.01 0.90 OH Pekerja 75,000.00 67,500.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 71,775.00
E Overhead & Profit (contah 10%) 10% 7,177.50
F Harga Satuan Pekerjaan (D+E) 78,952.50

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 93,626.50


A TENAGA 85,115.00
L.01 1.05 OH Pekerja 75,000.00 78,750.00
L.04 0.067 OH Mandor 95,000.00 6,365.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 85,115.00
E Overhead & Profit (contah 10%) 10% 8,511.50
F Harga Satuan Pekerjaan (D+E) 93,626.50

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 85,844.00


TENAGA 78,040.00
L.01 1.000 OH Pekerja 75,000.00 75,000.00
L.04 0.032 OH Mandor 95,000.00 3,040.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 78,040.00
E Overhead & Profit (contah 10%) 10% 7,804.00
F Harga Satuan Pekerjaan (D+E) 85,844.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 130,020.00


A TENAGA 118,200.00
L.01 1.50 OH Pekerja 75,000.00 112,500.00
L.04 0.060 OH Mandor 95,000.00 5,700.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 118,200.00
E Overhead & Profit (contah 10%) 10% 11,820.00
F Harga Satuan Pekerjaan (D+E) 130,020.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 103,702.50


A TENAGA 94,275.00
L.01 1.200 OH Pekerja 75,000.00 90,000.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 94,275.00
E Overhead & Profit (contah 10%) 10% 9,427.50
F Harga Satuan Pekerjaan (D+E) 103,702.50

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 4,647.50


A TENAGA 4,225.00
L.01 0.05 OH Pekerja 75,000.00 3,750.00
L.04 0.005 OH Mandor 95,000.00 475.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 4,225.00
E Overhead & Profit (contah 10%) 10% 422.50
F Harga Satuan Pekerjaan (D+E) 4,647.50

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 28,270.00


A TENAGA 25,700.00
L.01 0.330 OH Pekerja 75,000.00 24,750.00
L.04 0.010 OH Mandor 95,000.00 950.00

file:///conversion/tmp/scratch/509762178.xls 93/27 abk 2-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 25,700.00
E Overhead & Profit (contah 10%) 10% 2,570.00
F Harga Satuan Pekerjaan (D+E) 28,270.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 15,491.67
Pekerjaan galian
A TENAGA 42,250.00
L.01 0.50 OH Pekerja 75,000.00 37,500.00
L.04 0.050 OH Mandor 95,000.00 4,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 42,250.00
E Overhead & Profit (contah 10%) 10% 4,225.00
F Harga Satuan Pekerjaan (D+E) 46,475.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 46,475.00


A TENAGA 42,250.00
L.01 0.5 OH Pekerja 75,000.00 37,500.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 42,250.00
E Overhead & Profit (contah 10%) 10% 4,225.00
F Harga Satuan Pekerjaan (D+E) 46,475.00

11 A.2.3.1.11 1 m3 Urugan Pasir 329,395.00


A TENAGA 23,450.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.04 0.01 OH Mandor 95,000.00 950.00
B BAHAN 276,000.00
1.2 m3 Pasir Urug 230,000.00 276,000.00
C PERALATAN
D Jumlah A + B + C 299,450.00
E Overhead & Profit (contah 10%) 10% 29,945.00
F Harga Satuan Pekerjaan (D+E) 329,395.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 456,137.00


A TENAGA 108,000.00
L.01 0.800 OH Pekerja 75,000.00 60,000.00
L.02 0.400 OH Tukang Batu 90,000.00 36,000.00
L.03 0.04 OH Kepala Tukang 110,000.00 4,400.00
L.04 0.080 OH Mandor 95,000.00 7,600.00
B BAHAN 306,670.00
0.135 m3 Pasir Pasang 370,000.00 49,950.00
0.400 m3 Kapur Padam 310,000.00 124,000.00
0.948 m3 Tanah Liat 140,000.00 132,720.00
C PERALATAN
D Jumlah A + B + C 414,670.00
E Overhead & Profit (contah 10%) 10% 41,467.00
F Harga Satuan Pekerjaan (D+E) 456,137.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 61,462.50
Resapan
A TENAGA 12,675.00
0.15 OH Pekerja 75,000.00 11,250.00
0.015 OH Mandor 95,000.00 1,425.00
B BAHAN 43,200.00
6.00 kg Ijuk 7,200.00 43,200.00
C PERALATAN
D Jumlah A + B + C 55,875.00
E Overhead & Profit (contah 10%) 10% 5,587.50
F Harga Satuan Pekerjaan (D+E) 61,462.50

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 287,237.50


A TENAGA 21,125.00
0.25 OH Pekerja 75,000.00 18,750.00
0.025 OH Mandor 95,000.00 2,375.00
B BAHAN 240,000.00
1.2 m3 Sirtu 200,000.00 240,000.00
C PERALATAN
D Jumlah A + B + C 261,125.00
E Overhead & Profit (contah 10%) 10% 26,112.50
F Harga Satuan Pekerjaan (D+E) 287,237.50

file:///conversion/tmp/scratch/509762178.xls 93/28 abk 2-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 1,052,727.50
A TENAGA 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 761,650.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
202 Kg Portland Sement 1,100.00 222,200.00
0.485 m3 Pasir Pasang 370,000.00 179,450.00
C PERALATAN
D Jumlah A + B + C 957,025.00
E Overhead & Profit (contoh 10%) 10% 95,702.50
F Harga Satuan Pekerjaan (D+E) 1,052,727.50
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 1,019,782.50
A TENAGA 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 731,700.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
163 Kg Portland Sement 1,100.00 179,300.00
0.52 m3 Pasir Pasang 370,000.00 192,400.00
C PERALATAN
D Jumlah A + B + C 927,075.00
E Overhead & Profit (contoh 10%) 10% 92,707.50
F Harga Satuan Pekerjaan (D+E) 1,019,782.50

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 996,880.50


A TENAGA 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 710,880.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
136 Kg Portland Sement 1,100.00 149,600.00
0.544 m3 Pasir Pasang 370,000.00 201,280.00
C PERALATAN
D Jumlah A + B + C 906,255.00
E Overhead & Profit (contoh 10%) 10% 90,625.50
F Harga Satuan Pekerjaan (D+E) 996,880.50

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 980,809.50


A TENAGA 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 696,270.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
117 Kg Portland Sement 1,100.00 128,700.00
0.561 m3 Pasir Pasang 370,000.00 207,570.00
C PERALATAN
D Jumlah A + B + C 891,645.00
E Overhead & Profit (contoh 10%) 10% 89,164.50
F Harga Satuan Pekerjaan (D+E) 980,809.50

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 958,710.50


A Tenaga 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 676,180.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
91 Kg Portland Sement 1,100.00 100,100.00
0.584 m3 Pasir Pasang 370,000.00 216,080.00

file:///conversion/tmp/scratch/509762178.xls 93/29 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 871,555.00
E Overhead & Profit (contoh 10%) 10% 87,155.50
F Harga Satuan Pekerjaan (D+E) 958,710.50

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 844,662.50


A Tenaga 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 572,500.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
0.17 m3 Kapur Pasang (KP) 310,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 34,000.00
0.340 m3 Pasir Pasang 370,000.00 125,800.00
C PERALATAN
D Jumlah A + B + C 767,875.00
E Overhead & Profit (contoh 10%) 10% 76,787.50
F Harga Satuan Pekerjaan (D+E) 844,662.50

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 935,093.50


A Tenaga 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 654,710.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
61 kg Portland Sement 1,100.00 67,100.00
0.147 m3 Kapur Pasang 310,000.00 45,570.00
0.492 m3 Pasir Pasang 370,000.00 182,040.00
C PERALATAN
D Jumlah A + B + C 850,085.00
E Overhead & Profit (contoh 10%) 10% 85,008.50
F Harga Satuan Pekerjaan (D+E) 935,093.50

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 918,054.50


A Tenaga 195,375.00
L.01 1.5 OH Pekerja 75,000.00 112,500.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 639,220.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
41 kg Portland Sement 1,100.00 45,100.00
0.131 m3 Kapur Pasang 310,000.00 40,610.00
0.523 m3 Pasir 370,000.00 193,510.00
C PERALATAN
D Jumlah A + B + C 834,595.00
E Overhead & Profit (contoh 10%) 10% 83,459.50
F Harga Satuan Pekerjaan (D+E) 918,054.50

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 617,050.50


A Tenaga 101,595.00
L.01 0.78 OH Pekerja 75,000.00 58,500.00
L.02 0.39 OH Tukang Batu 90,000.00 35,100.00
L.03 0.039 OH Kepala Tukang 110,000.00 4,290.00
L.04 0.039 OH Mandor 95,000.00 3,705.00
B Bahan 459,360.00
1.2 m3 Batu Belah 15/20 300,000.00 360,000.00
0.432 m3 Pasir Urug 230,000.00 99,360.00
C PERALATAN
D Jumlah A + B + C 560,955.00
E Overhead & Profit (contoh 10%) 10% 56,095.50
F Harga Satuan Pekerjaan (D+E) 617,050.50

file:///conversion/tmp/scratch/509762178.xls 93/30 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :
10 A.3.2.1.10 1 m3 2,687,058.00
3KR & 40% Batu B0elah
A Tenaga 355,100.00
L.01 3.4 OH Pekerja 75,000.00 255,000.00
L.02 0.85 OH Tukang Batu 90,000.00 76,500.00
L.03 0.085 OH Kepala Tukang 110,000.00 9,350.00
L.04 0.15 OH Mandor 95,000.00 14,250.00
B Bahan 2,087,680.00
0.480 m3 Batu Belah 15/20 cm 300,000.00 144,000.00
126 Kg Besi Beton 11,300.00 1,423,800.00
194 Kg Portland Semen 1,100.00 213,400.00
0.312 m3 Pasir Beton 500,000.00 156,000.00
0.468 m3 Koral Beton 260,000.00 121,680.00
1.8 Kg Kawat Beton 16,000.00 28,800.00
C PERALATAN
D Jumlah A + B + C 2,442,780.00
E Overhead & Profit (contoh 10%) 10% 244,278.00
F Harga Satuan Pekerjaan (D+E) 2,687,058.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 988,003.50


A Tenaga 272,105.00
L.01 2.40 OH Pekerja 75,000.00 180,000.00
L.02 0.8 OH Tukang Batu 90,000.00 72,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 8,800.00
L.04 0.119 OH Mandor 95,000.00 11,305.00
B Bahan 626,080.00
0.45 m3 Batu Belah 15/20 cm 300,000.00 135,000.00
194 Kg Portland Semen 1,100.00 213,400.00
0.312 m3 Pasir Beton 500,000.00 156,000.00
0.468 m3 Koral Beton 260,000.00 121,680.00
C PERALATAN
D Jumlah A + B + C 898,185.00
E Overhead & Profit (contoh 10%) 10% 89,818.50
F Harga Satuan Pekerjaan (D+E) 988,003.50

file:///conversion/tmp/scratch/509762178.xls 93/31 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 1,137,864.36
= 0,87
A Tenaga 159,465.00
L.01 1.65 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 874,957.14
247 Kg Portland Semen 1,100.00 271,700.00
869 Kg Pasir Beton 357.14 310,357.14
999 Kg Kerikil (maksimum 30 mm) 288.89 288,600.00
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,034,422.14
E Overhead & Profit (contoh 10%) 10% 103,442.21
F Harga Satuan Pekerjaan (D+E) 1,137,864.36
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 1,160,978.33
= 0,78
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 895,969.84
276 Kg Portland Semen 1,100.00 303,600.00
828 kg Pasir Beton 357.14 295,714.29
1,012 kg Kerikil (maksimum 30 mm) 288.89 292,355.56
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,055,434.84
E Overhead & Profit (contoh 10%) 10% 105,543.48
F Harga Satuan Pekerjaan (D+E) 1,160,978.33

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 1,179,004.36
w/c = 0,72
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 912,357.14
299 Kg Portland Semen 1,100.00 328,900.00
799 kg Pasir Beton 357.14 285,357.14
1,017 kg Kerikil (maksimum 30 mm) 288.89 293,800.00
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,071,822.14
E Overhead & Profit (contoh 10%) 10% 107,182.21
F Harga Satuan Pekerjaan (D+E) 1,179,004.36

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 1,081,726.21
(3-6)cm, w/c = 0,87
A Tenaga 110,770.00
L.01 1.200 OH Pekerja 75,000.00 90,000.00
L.02 0.200 OH Tukang Batu 90,000.00 18,000.00
L.03 0.020 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 872,617.46
230 Kg Portland Semen 1,100.00 253,000.00
893 kg Pasir Beton 357.14 318,928.57
1,027 kg Kerikil (maksimum 30 mm) 288.89 296,688.89
200 ltr Air 20.00 4,000.00
C PERALATAN
D Jumlah A + B + C 983,387.46
E Overhead & Profit (contoh 10%) 10% 98,338.75
F Harga Satuan Pekerjaan (D+E) 1,081,726.21

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 1,200,166.26
w/c = 0,66
A Tenaga 159,465.00
L.01 1.65 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00

file:///conversion/tmp/scratch/509762178.xls 93/32 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 931,595.24
326 Kg Portland Semen 1,100.00 358,600.00
760 Kg Pasir Beton 357.14 271,428.57
1,029 Kg Kerikil (maksimum 30 mm) 288.89 297,266.67
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,091,060.24
E Overhead & Profit (contoh 10%) 10% 109,106.02
F Harga Satuan Pekerjaan (D+E) 1,200,166.26

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,220,868.96
w/c = 0,61
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 950,415.87
352 Kg Portland Semen 1,100.00 387,200.00
731 Kg Pasir Beton 357.14 261,071.43
1,031 Kg Kerikil (maksimum 30 mm) 288.89 297,844.44
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,109,880.87
E Overhead & Profit (contoh 10%) 10% 110,988.09
F Harga Satuan Pekerjaan (D+E) 1,220,868.96

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,235,979.12
w/c = 0,58
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 964,152.38
371 Kg Portland Semen 1,100.00 408,100.00
698 Kg Pasir Beton 357.14 249,285.71
1,047 Kg Kerikil (maksimum 30 mm) 288.89 302,466.67
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,123,617.38
E Overhead & Profit (contoh 10%) 10% 112,361.74
F Harga Satuan Pekerjaan (D+E) 1,235,979.12

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,246,809.75
w/c = 0,56
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 973,998.41
384 Kg Portland Semen 1,100.00 422,400.00
692 Kg Pasir Beton 357.14 247,142.86
1,039 Kg Kerikil (maksimum 30 mm) 288.89 300,155.56
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,133,463.41
E Overhead & Profit (contoh 10%) 10% 113,346.34
F Harga Satuan Pekerjaan (D+E) 1,246,809.75

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,266,155.79
(12±2)cm, w/c = 0,53
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 991,585.71
406 Kg Portland Semen 1,100.00 446,600.00
684 kg Pasir Beton 357.14 244,285.71
1,026 kg Kerikil (maksimum 30 mm) 288.89 296,400.00
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,151,050.71
E Overhead & Profit (contoh 10%) 10% 115,105.07
F Harga Satuan Pekerjaan (D+E) 1,266,155.79

file:///conversion/tmp/scratch/509762178.xls 93/33 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,271,858.33
w/c = 0,52
A Tenaga 159,465.00
L.01 1.650 OH Pekerja 75,000.00 123,750.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 110,000.00 3,080.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 996,769.84
413 Kg Portland Semen 1,100.00 454,300.00
681 Kg Pasir Beton 357.14 243,214.29
1,021 Kg Kerikil (maksimum 30 mm) 288.89 294,955.56
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,156,234.84
E Overhead & Profit (contoh 10%) 10% 115,623.48
F Harga Satuan Pekerjaan (D+E) 1,271,858.33

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,341,926.23
w/c = 0,49
A Tenaga 202,825.00
L.01 2.1 OH Pekerja 75,000.00 157,500.00
L.02 0.35 OH Tukang Batu 90,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.105 OH Mandor 95,000.00 9,975.00
B Bahan 1,017,107.94
439 Kg Portland Semen 1,100.00 482,900.00
670 Kg Pasir Beton 357.14 239,285.71
1,006 Kg Kerikil (maksimum 30 mm) 288.89 290,622.22
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,219,932.94
E Overhead & Profit (contoh 10%) 10% 121,993.29
F Harga Satuan Pekerjaan (D+E) 1,341,926.23

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,349,730.99
w/c = 0,48
A Tenaga 202,825.00
L.01 2.10 OH Pekerja 75,000.00 157,500.00
L.02 0.350 OH Tukang Batu 90,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.105 OH Mandor 95,000.00 9,975.00
B Bahan 1,024,203.17
448 Kg Portland Semen 1,100.00 492,800.00
667 Kg Pasir Beton 357.14 238,214.29
1,000 Kg Kerikil (maksimum 30 mm) 288.89 288,888.89
215 ltr Air 20.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,227,028.17
E Overhead & Profit (contoh 10%) 10% 122,702.82
F Harga Satuan Pekerjaan (D+E) 1,349,730.99

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 147,125.00


A Tenaga 12,700.00
L.01 0.07 OH Pekerja 75,000.00 5,250.00
L.02 0.07 OH Tukang Besi 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 121,050.00
10.50 Kg Besi Beton (polos/ulir) 11,300.00 118,650.00
0.150 Kg Kawat Beton 16,000.00 2,400.00
C PERALATAN
D Jumlah A + B + C 133,750.00
E Overhead & Profit (contoh 10%) 10% 13,375.00
F Harga Satuan Pekerjaan (D+E) 147,125.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 196,553.50


A Tenaga 9,085.00
L.01 0.05 OH Pekerja 75,000.00 3,750.00
L.02 0.05 OH Tukang Besi 90,000.00 4,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 169,600.00
10.5 Kg Besi presstred polos 16,000.00 168,000.00
0.1 Kg Kawat Beton 16,000.00 1,600.00

file:///conversion/tmp/scratch/509762178.xls 93/34 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 178,685.00
E Overhead & Profit (contoh 10%) 10% 17,868.50
F Harga Satuan Pekerjaan (D+E) 196,553.50

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 314,314.00


A Tenaga 4,440.00
L.01 0.025 OH Pekerja 75,000.00 1,875.00
L.02 0.025 OH Tukang Besi 90,000.00 2,250.00
L.03 0.002 OH Kepala Tukang 110,000.00 220.00
L.04 0.001 OH Mandor 95,000.00 95.00
B Bahan 281,300.00
10.20 Kg Jaring Kawat Baja dilas 27,500.00 280,500.00
0.05 Kg Kawat Beton 16,000.00 800.00
C PERALATAN
D Jumlah A + B + C 285,740.00
E Overhead & Profit (contoh 10%) 10% 28,574.00
F Harga Satuan Pekerjaan (D+E) 314,314.00

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 178,343.00


A Tenaga 67,730.00
L.01 0.52 OH Pekerja 75,000.00 39,000.00
L.02 0.26 OH Tukang Kayu 90,000.00 23,400.00
L.03 0.026 OH Kepala Tukang 110,000.00 2,860.00
L.04 0.026 OH Mandor 95,000.00 2,470.00
B Bahan 94,400.00
0.04 m3 Kayu Klas III (Terentang) 2,200,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 18,000.00 5,400.00
0.1 Ltr Minyak Bekisting 10,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 162,130.00
E Overhead & Profit (contoh 10%) 10% 16,213.00
F Harga Satuan Pekerjaan (D+E) 178,343.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 190,443.00


A Tenaga 67,730.00
L.01 0.52 OH Pekerja 75,000.00 39,000.00
L.02 0.26 OH Tukang Kayu 90,000.00 23,400.00
L.03 0.026 OH Kepala Tukang 110,000.00 2,860.00
L.04 0.026 OH Mandor 95,000.00 2,470.00
B Bahan 105,400.00
0.045 m3 Kayu Klas III (Terentang) 2,200,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 18,000.00 5,400.00
0.1 Ltr Minyak Bekisting 10,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 173,130.00
E Overhead & Profit (contoh 10%) 10% 17,313.00
F Harga Satuan Pekerjaan (D+E) 190,443.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 416,531.50


A Tenaga 85,965.00
L.01 0.66 OH Pekerja 75,000.00 49,500.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 110,000.00 3,630.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 292,700.00
0.04 m3 Kayu Klas III (Terentang) 2,200,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 18,000.00 7,200.00
0.2 Ltr Minyak Bekisting 10,000.00 2,000.00
0.015 m3 Balok Kayu Klas II 6,100,000.00 91,500.00
0.35 Lbr Plywood tebal 9mm 160,000.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 24,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 378,665.00
E Overhead & Profit (contoh 10%) 10% 37,866.50
F Harga Satuan Pekerjaan (D+E) 416,531.50

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 436,661.50


A Tenaga 85,965.00
L.01 0.66 OH Pekerja 75,000.00 49,500.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 110,000.00 3,630.00
L.04 0.033 OH Mandor 95,000.00 3,135.00

file:///conversion/tmp/scratch/509762178.xls 93/35 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 311,000.00
0.04 m3 Kayu Klas III (Terentang) 2,200,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 18,000.00 7,200.00
0.2 Ltr Minyak Bekisting 10,000.00 2,000.00
0.018 m3 Balok Kayu Klas II 6,100,000.00 109,800.00
0.35 Lbr Plywood tebal 9mm 160,000.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 24,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 396,965.00
E Overhead & Profit (contoh 10%) 10% 39,696.50
F Harga Satuan Pekerjaan (D+E) 436,661.50

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 522,131.50


A Tenaga 85,965.00
L.01 0.66 OH Pekerja 75,000.00 49,500.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 110,000.00 3,630.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 388,700.00
0.04 m3 Kayu Klas III (Terentang) 2,200,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 18,000.00 7,200.00
0.2 Ltr Minyak Bekisting 10,000.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 6,100,000.00 91,500.00
0.35 Lbr Plywood tebal 9mm 160,000.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 24,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 474,665.00
E Overhead & Profit (contoh 10%) 10% 47,466.50
F Harga Satuan Pekerjaan (D+E) 522,131.50

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 476,481.50


A Tenaga 85,965.00
L.01 0.66 OH Pekerja 75,000.00 49,500.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 110,000.00 3,630.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 347,200.00
0.03 m3 Kayu Klas III (Terentang) 2,200,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 18,000.00 7,200.00
0.2 Ltr Minyak Bekisting 10,000.00 2,000.00
0.02 m3 Balok Kayu Klas II 6,100,000.00 122,000.00
0.35 Lbr Plywood tebal 9mm 160,000.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 24,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,500.00 22,000.00
C PERALATAN
D Jumlah A + B + C 433,165.00
E Overhead & Profit (contoh 10%) 10% 43,316.50
F Harga Satuan Pekerjaan (D+E) 476,481.50

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 391,781.50


A Tenaga 85,965.00
L.01 0.66 OH Pekerja 75,000.00 49,500.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 110,000.00 3,630.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 270,200.00
0.03 m3 Kayu Klas III (Terentang) 2,200,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 18,000.00 7,200.00
0.15 Ltr Minyak Bekisting 10,000.00 1,500.00
0.015 m3 Balok Kayu Klas II 6,100,000.00 91,500.00
0.35 Lbr Plywood tebal 9mm 160,000.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 24,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 356,165.00
E Overhead & Profit (contoh 10%) 10% 35,616.50
F Harga Satuan Pekerjaan (D+E) 391,781.50

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 107,734.00


A Tenaga 17,060.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.05 OH Tukang Kayu 90,000.00 4,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 80,880.00
0.0264 m3 Kayu Terentang 2,200,000.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 18,000.00 10,800.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 24,000.00 12,000.00

file:///conversion/tmp/scratch/509762178.xls 93/36 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 97,940.00
E Overhead & Profit (contoh 10%) 10% 9,794.00
F Harga Satuan Pekerjaan (D+E) 107,734.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 88,038.50
A Tenaga 20,515.00
L.01 0.180 OH Pekerja 75,000.00 13,500.00
L.02 0.020 OH Tukang batu 90,000.00 1,800.00
L.02 0.020 OH Tukang Kayu 95,000.00 1,900.00
L.02 0.020 OH Tukang Besi 90,000.00 1,800.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.009 OH Mandor 95,000.00 855.00
B Bahan 59,520.00
0.002 m3 Kayu Klas III 3,800,000.00 7,600.00
0.01 Kg Paku Biasa 2" - 5" 18,000.00 180.00
3.0 Kg Besi Beton Polos 11,300.00 33,900.00
0.45 Kg Kawat Beton 16,000.00 7,200.00
4.0 Kg Portland Semen 1,100.00 4,400.00
0.006 m3 Pasir Beton 500,000.00 3,000.00
0.009 m3 Kerikil 360,000.00 3,240.00
C PERALATAN
D Jumlah A + B + C 80,035.00
E Overhead & Profit (contoh 10%) 10% 8,003.50
F Harga Satuan Pekerjaan (D+E) 88,038.50

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 113,371.50
A Tenaga 33,875.00
L.01 0.297 OH Pekerja 75,000.00 22,275.00
L.02 0.033 OH Tukang batu 90,000.00 2,970.00
L.02 0.033 OH Tukang Kayu 95,000.00 3,135.00
L.02 0.033 OH Tukang Besi 90,000.00 2,970.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 69,190.00
0.003 m3 Kayu Klas III 3,800,000.00 11,400.00
0.02 Kg Paku Biasa 2" - 5" 18,000.00 360.00
3.6 Kg Besi Beton Polos 11,300.00 40,680.00
0.05 Kg Kawat Beton 16,000.00 800.00
5.5 Kg Portland Semen 1,100.00 6,050.00
0.009 m3 Pasir Beton 500,000.00 4,500.00
0.015 m3 Kerikil 360,000.00 5,400.00
C PERALATAN
D Jumlah A + B + C 103,065.00
E Overhead & Profit (contoh 10%) 10% 10,306.50
F Harga Satuan Pekerjaan (D+E) 113,371.50

file:///conversion/tmp/scratch/509762178.xls 93/37 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 30,602.00
A Tenaga 11,145.00
L.01 0.06 OH Pekerja 75,000.00 4,500.00
L.02 0.06 OH Tukang Besi 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 16,675.00
1.15 Kg Besi Profil 14,500.00 16,675.00
C PERALATAN
D Jumlah A + B + C 27,820.00
E Overhead & Profit (contoh 10%) 10% 2,782.00
F Harga Satuan Pekerjaan (D+E) 30,602.00

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 21,747.00


A Tenaga 11,145.00
L.01 0.06 OH Pekerja 75,000.00 4,500.00
L.02 0.06 OH Tukang Besi 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 8,625.00
1.15 kg Besi Baja IWF 7,500.00 8,625.00
C PERALATAN
D Jumlah A + B + C 19,770.00
E Overhead & Profit (contoh 10%) 10% 1,977.00
F Harga Satuan Pekerjaan (D+E) 21,747.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 111,413.50


A Tenaga 17,585.00
L.01 0.100 OH Pekerja 75,000.00 7,500.00
L.02 0.100 OH Tukang Besi 95,000.00 9,500.00
L.03 0.001 OH Kepala Tukang 110,000.00 110.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 11,700.00
1 ltr Solar 7,200.00 7,200.00
0.1 ltr Minyak Pelumas 45,000.00 4,500.00
C PERALATAN 72,000
0.800 jam Sewa Alat 90,000 72,000
D Jumlah A + B + C 101,285.00
E Overhead & Profit (contoh 10%) 10% 10,128.50
F Harga Satuan Pekerjaan (D+E) 111,413.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 846,659.00
rangka baja Siku
A Tenaga 194,990.00
L.01 1.05 OH Pekerja 75,000.00 78,750.00
L.02 1.05 OH Tukang Besi 95,000.00 99,750.00
L.03 0.105 OH Kepala Tukang 110,000.00 11,550.00
L.04 0.052 OH Mandor 95,000.00 4,940.00
B Bahan 574,700.00
15 Kg Besi Siku L.30.30.3 7,500.00 112,500.00
32.8 Kg Besi Plat Baja 14,000.00 459,200.00
0.05 Kg Kawat Las 60,000.00 3,000.00
C PERALATAN
D Jumlah A + B + C 769,690.00
E Overhead & Profit (contoh 10%) 10% 76,969.00
F Harga Satuan Pekerjaan (D+E) 846,659.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 25,746.60


A Tenaga 5,310.00
L.01 0.04 OH Pekerja 75,000.00 3,000.00
L.02 0.02 OH Tukang Besi 95,000.00 1,900.00
L.03 0.002 OH Kepala Tukang 110,000.00 220.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 2,796.00
0.04 kg Kawat Las 60,000.00 2,400.00
0.03 ltr Solar 7,200.00 216.00
0.004 ltr Minyak Pelumas 45,000.00 180.00

file:///conversion/tmp/scratch/509762178.xls 93/38 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

C PERALATAN 15,300
0.170 jam Sewa Alat 90,000 15,300
D Jumlah A + B + C 23,406.00
E Overhead & Profit (contoh 10%) 10% 2,340.60
F Harga Satuan Pekerjaan (D+E) 25,746.60

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 238,227.22


A Tenaga 120,690.00
L.01 0.65 OH Pekerja 75,000.00 48,750.00
L.02 0.65 OH Tukang Las Biasa 95,000.00 61,750.00
L.03 0.065 OH Kepala Tukang 110,000.00 7,150.00
L.04 0.032 OH Mandor 95,000.00 3,040.00
B Bahan 95,880.20
4.760 m' Besi Scuare tube 6,000.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,500.00 15,827.00
20.000 cm Pengelasan 2,574.66 51,493.20
C PERALATAN
D Jumlah A + B + C 216,570.20
E Overhead & Profit (contoh 10%) 10% 21,657.02
F Harga Satuan Pekerjaan (D+E) 238,227.22

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 597,047.00


A Tenaga 217,770.00
L.01 1.2 OH Pekerja 75,000.00 90,000.00
L.02 1.2 OH Tukang Besi 95,000.00 114,000.00
L.03 0.12 OH Kepala Tukang 110,000.00 13,200.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 325,000.00
1 m2 Pintu Gulung Besi 325,000.00 325,000.00
C PERALATAN
D Jumlah A + B + C 542,770.00
E Overhead & Profit (contoh 10%) 10% 54,277.00
F Harga Satuan Pekerjaan (D+E) 597,047.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 557,403.00


A Tenaga 81,730.00
L.01 0.44 OH Pekerja 75,000.00 33,000.00
L.02 0.44 OH Tukang Besi 95,000.00 41,800.00
L.03 0.044 OH Kepala Tukang 110,000.00 4,840.00
L.04 0.022 OH Mandor 95,000.00 2,090.00
B Bahan 425,000.00
1 m2 Pintu Lipat 425,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 506,730.00
E Overhead & Profit (contoh 10%) 10% 50,673.00
F Harga Satuan Pekerjaan (D+E) 557,403.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 485,298.00


A Tenaga 91,180.00
L.01 0.08 OH Pekerja 75,000.00 6,000.00
L.02 0.8 OH Tukang Besi 95,000.00 76,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 8,800.00
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 350,000.00
1 m2 Sunscreen Allumunium 350,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 441,180.00
E Overhead & Profit (contoh 10%) 10% 44,118.00
F Harga Satuan Pekerjaan (D+E) 485,298.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 506,825.00


A Tenaga 185,750.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 1 OH Tukang Besi 95,000.00 95,000.00
L.03 0.1 OH Kepala Tukang 110,000.00 11,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00

file:///conversion/tmp/scratch/509762178.xls 93/39 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

B Bahan 275,000.00
1 m2 Rolling Allumunium 275,000.00 275,000.00
C PERALATAN
D Jumlah A + B + C 460,750.00
E Overhead & Profit (contoh 10%) 10% 46,075.00
F Harga Satuan Pekerjaan (D+E) 506,825.00

11 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 117,350.75


A Tenaga 7,982.50
L.01 0.043 OH Pekerja 75,000.00 3,225.00
L.02 0.043 OH Tukang Besi 95,000.00 4,085.00
L.03 0.0043 OH Kepala Tukang 110,000.00 473.00
L.04 0.0021 OH Mandor 95,000.00 199.50
B Bahan 98,700.00
1.1 m' Profil Allumunium 85,000.00 93,500.00
2 buah Skrup Fixer 800.00 1,600.00
0.06 Tube Sealant 60,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 106,682.50
E Overhead & Profit (contoh 10%) 10% 10,668.25
F Harga Satuan Pekerjaan (D+E) 117,350.75

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 509,062.40


A Tenaga 15,784.00
L.01 0.085 OH Pekerja 75,000.00 6,375.00
L.02 0.085 OH Tukang Besi 95,000.00 8,075.00
L.03 0.0085 OH Kepala Tukang 110,000.00 935.00
L.04 0.0042 OH Mandor 95,000.00 399.00
B Bahan 447,000.00
4.4 m' Profil Allumunium 85,000.00 374,000.00
14.6 m' Allumunium Strip 5,000.00 73,000.00
C PERALATAN
D Jumlah A + B + C 462,784.00
E Overhead & Profit (contoh 10%) 10% 46,278.40
F Harga Satuan Pekerjaan (D+E) 509,062.40

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 476,426.50


A Tenaga 15,915.00
L.01 0.085 OH Pekerja 75,000.00 6,375.00
L.02 0.085 OH Tukang Besi 95,000.00 8,075.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 417,200.00
4.4 m' Pintu Allumunium 85,000.00 374,000.00
4.5 m' Profil Kaca 6,000.00 27,000.00
0.27 tube Sealant 60,000.00 16,200.00
C PERALATAN
D Jumlah A + B + C 433,115.00
E Overhead & Profit (contoh 10%) 10% 43,311.50
F Harga Satuan Pekerjaan (D+E) 476,426.50

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 181,566.00


A Tenaga 65,060.00
L.01 0.35 OH Pekerja 75,000.00 26,250.00
L.02 0.35 OH Tukang Besi 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.018 OH Mandor 95,000.00 1,710.00
B Bahan 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 100,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 165,060.00
E Overhead & Profit (contoh 10%) 10% 16,506.00
F Harga Satuan Pekerjaan (D+E) 181,566.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 512,990.27


A Tenaga 310,155.00
L.01 1.67 OH Pekerja 75,000.00 125,250.00
L.02 1.67 OH Tukang Las 95,000.00 158,650.00
L.03 0.167 OH Kepala Tukang 110,000.00 18,370.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
file:///conversion/tmp/scratch/509762178.xls 93/40 abk 5-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

B Bahan 156,199.79
6.177 kg Besi Strip 14,000.00 86,478.00
27.08 cm Pengelasan 2,574.66 69,721.79
C PERALATAN
D Jumlah A + B + C 466,354.79
E Overhead & Profit (contoh 10%) 10% 46,635.48
F Harga Satuan Pekerjaan (D+E) 512,990.27

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 100,103.82


A Tenaga 18,575.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.1 OH Tukang 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 72,428.47
1.1 m2 Kawat Nyamuk nylon 18,000.00 19,800.00
11.11 cm Pengelasan 2,574.66 28,604.47
1.716 kg Baja Strip (0,2x2) cm 14,000.00 24,024.00
C PERALATAN
D Jumlah A + B + C 91,003.47
E Overhead & Profit (contoh 10%) 10% 9,100.35
F Harga Satuan Pekerjaan (D+E) 100,103.82

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 131,224.50


A Tenaga 36,295.00
L.01 0.2 OH Pekerja 75,000.00 15,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.001 OH Mandor 95,000.00 95.00
B Bahan 83,000.00
1.1 m2 Jendela Nako 35,000.00 38,500.00
10 buah Paku Skrup 1 - 2,5 cm 600.00 6,000.00
7 m' Besi Strip 5,500.00 38,500.00
C PERALATAN
D Jumlah A + B + C 119,295.00
E Overhead & Profit (contoh 10%) 10% 11,929.50
F Harga Satuan Pekerjaan (D+E) 131,224.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 210,094.50
cm
A Tenaga 56,700.00
L.01 0.20 OH Pekerja 75,000.00 15,000.00
L.02 0.4 OH Tukang Kayu 95,000.00 38,000.00
L.03 0.025 OH Kepala Tukang 110,000.00 2,750.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 134,295.00
1.05 Lbr Seng Plaat 24,500.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 18,000.00 270.00
0.019 m3 Kayu Papan Klas II atau III 5,700,000.00 108,300.00
C PERALATAN
D Jumlah A + B + C 190,995.00
E Overhead & Profit (contoh 10%) 10% 19,099.50
F Harga Satuan Pekerjaan (D+E) 210,094.50

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 76,120.00
BJLS 30 Lebar 45 cm
A Tenaga 36,295.00
L.01 0.20 OH Pekerja 75,000.00 15,000.00
L.02 0.20 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.001 OH Mandor 95,000.00 95.00
B Bahan 32,905.00
1.05 Lbr Seng Plaat 24,500.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 18,000.00 180.00
0.5 Kg Besi strip 14,000.00 7,000.00
C PERALATAN
D Jumlah A + B + C 69,200.00
E Overhead & Profit (contoh 10%) 10% 6,920.00
F Harga Satuan Pekerjaan (D+E) 76,120.00

file:///conversion/tmp/scratch/509762178.xls 93/41 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 116,583.50
60x120 cm dinding partisi
A Tenaga 46,485.00
L.01 0.250 OH Pekerja 75,000.00 18,750.00
L.02 0.250 OH Tukang Besi 95,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 110,000.00 2,750.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,500.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 29,750.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 105,985.00
E Overhead & Profit (contoh 10%) 10% 10,598.50
F Harga Satuan Pekerjaan (D+E) 116,583.50

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 146,366.00
60x60 cm dinding plafond
A Tenaga 65,060.00
L.01 0.350 OH Pekerja 75,000.00 26,250.00
L.02 0.350 OH Tukang Besi 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.018 OH Mandor 95,000.00 1,710.00
B Bahan 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,500.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 34,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 133,060.00
E Overhead & Profit (contoh 10%) 10% 13,306.00
F Harga Satuan Pekerjaan (D+E) 146,366.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 213,510.28
dingin Profil C75
A Tenaga 136,325.00
L.01 0.734 OH Pekerja 75,000.00 55,050.00
L.02 0.734 OH Tukang Besi 95,000.00 69,730.00
L.03 0.073 OH Kepala Tukang 110,000.00 8,030.00
L.04 0.037 OH Mandor 95,000.00 3,515.00
B Bahan 53,331.00
3.065 kg Baja Ringan Canal Dingin C75 14,500.00 44,442.50
C PERALATAN 4,444.25
10 % Peralatan *) harga bahan 44,442.50 4,444.25
D Jumlah A + B + C 194,100.25
E Overhead & Profit (contoh 10%) 10% 19,410.03
F Harga Satuan Pekerjaan (D+E) 213,510.28

Pemasangan Atap Jurai Rangka Atap Baja Canal Dingin


23 A.4.2.1.23 1 m2 239,338.55
Profil C75
A Tenaga 141,238.00
L.01 0.7604 OH Pekerja 75,000.00 57,030.00
L.02 0.7604 OH Tukang Besi 95,000.00 72,238.00
L.03 0.0760 OH Kepala Tukang 110,000.00 8,360.00
L.04 0.0380 OH Mandor 95,000.00 3,610.00
B Bahan 70,470.00
4.05 kg Baja Ringan Canal Dingin C75 14,500.00 58,725.00
C PERALATAN 5,872.50
10 % Peralatan *) harga bahan 58,725.00 5,872.50
D Jumlah A + B + C 217,580.50
E Overhead & Profit (contoh 10%) 10% 21,758.05
F Harga Satuan Pekerjaan (D+E) 239,338.55

file:///conversion/tmp/scratch/509762178.xls 93/42 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 252,450.00
Tebal 1 bata Camp. 1SP: 2PP

A Tenaga 68,050.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 0.2 OH Tukang Batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 161,450.00
140 Buah Bata Merah 600.00 84,000.00
43.5 Kg Portland Semen (PC) 1,100.00 47,850.00
0.08 m3 Pasir Pasang (PP) 370,000.00 29,600.00
C PERALATAN
D Jumlah A + B + C 229,500.00
E Overhead & Profit (contoh 10%) 10% 22,950.00
F Harga Satuan Pekerjaan (D+E) 252,450.00
Overhead & Profit (contoh 10%)

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


2 A.4.4.1.2 1 m2 244,161.50
Tebal 1 Bata Camp. 1SP : 3PP

A Tenaga 68,050.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 0.2 OH Tukang Batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 153,915.00
140 Buah Bata Merah 600.00 84,000.00
32.95 Kg Portland Semen (PC) 1,100.00 36,245.00
0.091 m3 Pasir Pasang (PP) 370,000.00 33,670.00
C PERALATAN
D Jumlah A + B + C 221,965.00
E Overhead & Profit (contoh 10%) 10% 22,196.50
F Harga Satuan Pekerjaan (D+E) 244,161.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 237,231.50
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 68,050.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 0.2 OH Tukang Batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 147,615.00
140 Buah Bata Merah 600.00 84,000.00
26.55 Kg Portland Semen (PC) 1,100.00 29,205.00
0.093 m3 Pasir Pasang (PP) 370,000.00 34,410.00
C PERALATAN
D Jumlah A + B + C 215,665.00
E Overhead & Profit (contoh 10%) 10% 21,566.50
F Harga Satuan Pekerjaan (D+E) 237,231.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 235,631.00
Tebal 1 Bata Camp. 1SP : 5PP

A Tenaga 68,050.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 0.2 OH Tukang Batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 146,160.00
140 Buah Bata Merah 600.00 84,000.00
22.2 Kg Portland Semen (PC) 1,100.00 24,420.00
0.102 m3 Pasir Pasang (PP) 370,000.00 37,740.00
C PERALATAN
D Jumlah A + B + C 214,210.00
E Overhead & Profit (contoh 10%) 10% 21,421.00
F Harga Satuan Pekerjaan (D+E) 235,631.00

file:///conversion/tmp/scratch/509762178.xls 93/43 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 239,294.00
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 68,050.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 0.2 OH Tukang Batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 149,490.00
140 Buah Bata Merah 600.00 84,000.00
18.5 Kg Portland Semen (PC) 1,100.00 20,350.00
0.122 m3 Pasir Pasang (PP) 370,000.00 45,140.00
C PERALATAN
D Jumlah A + B + C 217,540.00
E Overhead & Profit (contoh 10%) 10% 21,754.00
F Harga Satuan Pekerjaan (D+E) 239,294.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 226,476.80
Tebal 1 Bata Camp. 1SP : 3 KP :10PP

A Tenaga 68,050.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 0.2 OH Tukang Batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 137,838.00
140 Buah Bata Merah 600.00 84,000.00
10.08 Kg Portland Semen (PC) 1,100.00 11,088.00
0.0925 m3 Pasir Pasang (PP) 370,000.00 34,225.00
0.0275 m3 Kapur Pasang (KP) 310,000.00 8,525.00
C PERALATAN
D Jumlah A + B + C 205,888.00
E Overhead & Profit (contoh 10%) 10% 20,588.80
F Harga Satuan Pekerjaan (D+E) 226,476.80

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 122,023.00
Tebal 1/2 Bata Camp. 1SP : 2PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 76,905.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
18.95 Kg Portland Semen 1,100.00 20,845.00
0.038 m3 Pasir Pasang 370,000.00 14,060.00
C PERALATAN
D Jumlah A + B + C 110,930.00
E Overhead & Profit (contoh 10%) 10% 11,093.00
F Harga Satuan Pekerjaan (D+E) 122,023.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 117,295.20
Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 72,607.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
14.37 Kg Portland Semen 1,100.00 15,807.00
0.04 m3 Pasir Pasang 370,000.00 14,800.00

file:///conversion/tmp/scratch/509762178.xls 93/44 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 106,632.00
E Overhead & Profit (contoh 10%) 10% 10,663.20
F Harga Satuan Pekerjaan (D+E) 117,295.20

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 115,043.50
Tebal 1/2 Bata Camp. 1SP : 4PP

A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 70,560.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
11.50 Kg Portland Semen 1,100.00 12,650.00
0.043 m3 Pasir Pasang 370,000.00 15,910.00
C PERALATAN
D Jumlah A + B + C 104,585.00
E Overhead & Profit (contoh 10%) 10% 10,458.50
F Harga Satuan Pekerjaan (D+E) 115,043.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 113,655.30
Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 69,298.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
9.68 Kg Portland Semen 1,100.00 10,648.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 103,323.00
E Overhead & Profit (contoh 10%) 10% 10,332.30
F Harga Satuan Pekerjaan (D+E) 113,655.30

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 113,637.70
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 69,282.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
8.32 Kg Portland Semen 1,100.00 9,152.00
0.049 m3 Pasir Pasang 370,000.00 18,130.00
C PERALATAN
D Jumlah A + B + C 103,307.00
E Overhead & Profit (contoh 10%) 10% 10,330.70
F Harga Satuan Pekerjaan (D+E) 113,637.70

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 111,842.50
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 67,650.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
6.50 Kg Portland Semen 1,100.00 7,150.00
0.05 m3 Pasir Pasang 370,000.00 18,500.00

file:///conversion/tmp/scratch/509762178.xls 93/45 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 101,675.00
E Overhead & Profit (contoh 10%) 10% 10,167.50
F Harga Satuan Pekerjaan (D+E) 111,842.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 114,537.50
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP

A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 70,100.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
4.5 Kg Portland Semen 1,100.00 4,950.00
0.05 m3 Pasir Pasang 370,000.00 18,500.00
0.015 m3 Kapur Padam 310,000.00 4,650.00
C PERALATAN
D Jumlah A + B + C 104,125.00
E Overhead & Profit (contoh 10%) 10% 10,412.50
F Harga Satuan Pekerjaan (D+E) 114,537.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 101,051.50
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 57,840.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
0.018 m3 Semen Merah 200,000.00 3,600.00
0.018 m3 Pasir Pasang 370,000.00 6,660.00
0.018 m3 Kapur Padam 310,000.00 5,580.00
C PERALATAN
D Jumlah A + B + C 91,865.00
E Overhead & Profit (contoh 10%) 10% 9,186.50
F Harga Satuan Pekerjaan (D+E) 101,051.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 102,877.50
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 59,500.00
70 Buah Bata Merah 5 x 11 x 22 600.00 42,000.00
0.014 m3 Semen Merah 200,000.00 2,800.00
0.028 m3 Pasir Pasang 370,000.00 10,360.00
0.014 m3 Kapur Padam 310,000.00 4,340.00
C PERALATAN
D Jumlah A + B + C 93,525.00
E Overhead & Profit (contoh 10%) 10% 9,352.50
F Harga Satuan Pekerjaan (D+E) 102,877.50

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 442,322.10
A Tenaga 43,110.00
L.01 0.350 OH Pekerja 75,000.00 26,250.00
L.02 0.150 OH Tukang Batu 90,000.00 13,500.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.018 OH Mandor 95,000.00 1,710.00

file:///conversion/tmp/scratch/509762178.xls 93/46 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 359,001.00
12.500 buah Batako 4,250.00 53,125.00
30.320 kg PC 1,100.00 33,352.00
0.728 m3 Pasir Pasang 370,000.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 11,300.00 3,164.00
C PERALATAN
D Jumlah A + B + C 402,111.00
E Overhead & Profit (contoh 10%) 10% 40,211.10
F Harga Satuan Pekerjaan (D+E) 442,322.10

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 452,897.50
A Tenaga 43,110.00
L.01 0.350 OH Pekerja 75,000.00 26,250.00
L.02 0.150 OH Tukang Batu 90,000.00 13,500.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.018 OH Mandor 95,000.00 1,710.00

B Bahan 368,615.00
12.500 buah Batako 4,250.00 53,125.00
24.260 kg PC 1,100.00 26,686.00
0.772 m3 Pasir Pasang 370,000.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 11,300.00 3,164.00
C PERALATAN
D Jumlah A + B + C 411,725.00
E Overhead & Profit (contoh 10%) 10% 41,172.50
F Harga Satuan Pekerjaan (D+E) 452,897.50

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 347,124.80
A Tenaga 37,640.00
L.01 0.320 OH Pekerja 75,000.00 24,000.00
L.02 0.120 OH Tukang Batu 90,000.00 10,800.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.016 OH Mandor 95,000.00 1,520.00
B Bahan 277,928.00
12.500 buah Batako 3,700.00 46,250.00
22.740 kg PC 1,100.00 25,014.00
0.550 m3 Pasir Pasang 370,000.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 11,300.00 3,164.00
C PERALATAN
D Jumlah A + B + C 315,568.00
E Overhead & Profit (contoh 10%) 10% 31,556.80
F Harga Satuan Pekerjaan (D+E) 347,124.80

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 354,655.40
A Tenaga 37,640.00
L.01 0.320 OH Pekerja 75,000.00 24,000.00
L.02 0.120 OH Tukang Batu 90,000.00 10,800.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.016 OH Mandor 95,000.00 1,520.00
B Bahan 284,774.00
12.500 buah Batako 3,700.00 46,250.00
18.200 kg PC 1,100.00 20,020.00
0.582 m3 Pasir Pasang 370,000.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 11,300.00 3,164.00
C PERALATAN
D Jumlah A + B + C 322,414.00
E Overhead & Profit (contoh 10%) 10% 32,241.40
F Harga Satuan Pekerjaan (D+E) 354,655.40

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 255,524.50
A Tenaga 34,025.00
L.01 0.300 OH Pekerja 75,000.00 22,500.00
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00

file:///conversion/tmp/scratch/509762178.xls 93/47 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 198,270.00
12.500 buah Batako 3,500.00 43,750.00
15.160 kg PC 1,100.00 16,676.00
0.364 m3 Pasir Pasang 370,000.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 11,300.00 3,164.00
C PERALATAN
D Jumlah A + B + C 232,295.00
E Overhead & Profit (contoh 10%) 10% 23,229.50
F Harga Satuan Pekerjaan (D+E) 255,524.50

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 261,626.20
A Tenaga 34,025.00
L.01 0.300 OH Pekerja 75,000.00 22,500.00
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00

B Bahan 203,817.00
12.500 buah Batako 3,500.00 43,750.00
12.130 kg PC 1,100.00 13,343.00
0.388 m3 Pasir Pasang 370,000.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 11,300.00 3,164.00
C PERALATAN
D Jumlah A + B + C 237,842.00
E Overhead & Profit (contoh 10%) 10% 23,784.20
F Harga Satuan Pekerjaan (D+E) 261,626.20

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 460,982.50
(12x11x24)cm Camp. 1SP : 3PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 385,050.00
30 Buah Terawang / Roster 12,000.00 360,000.00
11 kg Portland Semen 1,100.00 12,100.00
0.035 m3 Pasir Pasang 370,000.00 12,950.00
C PERALATAN
D Jumlah A + B + C 419,075.00
E Overhead & Profit (contoh 10%) 10% 41,907.50
F Harga Satuan Pekerjaan (D+E) 460,982.50

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 460,982.50
(12x11x24)cm Camp. 1SP : 4PP
A Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 385,050.00
30 Buah Terawang / Roster 12,000.00 360,000.00
11 kg Portland Semen 1,100.00 12,100.00
0.035 m3 Pasir Pasang 370,000.00 12,950.00
C PERALATAN
D Jumlah A + B + C 419,075.00
E Overhead & Profit (contoh 10%) 10% 41,907.50
F Harga Satuan Pekerjaan (D+E) 460,982.50

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 148,241.50
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 34,025.00
L.01 0.30 OH Pekerja 75,000.00 22,500.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 95,000.00 1,425.00

file:///conversion/tmp/scratch/509762178.xls 93/48 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
OH Bahan 100,740.00
70 Buah Bata Roster 1,050.00 73,500.00
14 kg Portland Semen 1,100.00 15,400.00
0.032 m3 Pasir Pasang 370,000.00 11,840.00
C PERALATAN
D Jumlah A + B + C 134,765.00
E Overhead & Profit (contoh 10%) 10% 13,476.50
F Harga Satuan Pekerjaan (D+E) 148,241.50

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 131,285.06
Mortar Siap Pakai

m2 Tenaga 0.075 63,665.00


L.01 0.67 OH Pekerja 0.12 725000 75,000.00 50,250.00
L.02 0.13 OH Tukang Batu 1 6525 90,000.00 11,700.00
L.03 0.01 OH Kepala Tukang 13.3333333333333 110,000.00 1,430.00
L.04 0.003 OH Mandor 111.111111111111 95,000.00 285.00
OH Bahan 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,525.00 54,810.00
0.473 kg Mortar Siap Pakai 1,850.00 875.05

C PERALATAN
D Jumlah A + B + C 119,350.05
E Overhead & Profit (contoh 10%) 10% 11,935.01
F Harga Satuan Pekerjaan (D+E) 131,285.06

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 147,858.21
Mortar Siap Pakai
m2 Tenaga 0.075 63,740.00
L.01 0.671 OH Pekerja 0.12 700000 75,000.00 50,325.00
L.02 0.130 OH Tukang Batu 0.1 8400 90,000.00 11,700.00
L.03 0.013 OH Kepala Tukang 10 110,000.00 1,430.00
L.04 0.003 OH Mandor 83.3333333333333 95,000.00 285.00
OH Bahan 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,400.00 70,560.00
0.063 kg Mortar Siap Pakai 1,850.00 116.55

C PERALATAN
D Jumlah A + B + C 134,416.55
E Overhead & Profit (contoh 10%) 10% 13,441.66
F Harga Satuan Pekerjaan (D+E) 147,858.21

file:///conversion/tmp/scratch/509762178.xls 93/49 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 68,254.34
A Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 22,974.40
15.504 Kg Portland Semen 1,100.00 17,054.40
0.016 m3 Pasir Pasang 370,000.00 5,920.00
C PERALATAN
D Jumlah A + B + C 62,049.40
E Overhead & Profit (contoh 10%) 10% 6,204.94
F Harga Satuan Pekerjaan (D+E) 68,254.34
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 63,493.54
A Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 18,646.40
10.224 Kg Portland Semen 1,100.00 11,246.40
0.020 m3 Pasir Pasang 370,000.00 7,400.00
C PERALATAN
D Jumlah A + B + C 57,721.40
E Overhead & Profit (contoh 10%) 10% 5,772.14
F Harga Satuan Pekerjaan (D+E) 63,493.54

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 61,752.46


A Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 17,063.60
7.776 Kg Portland Semen 1,100.00 8,553.60
0.023 m3 Pasir Pasang 370,000.00 8,510.00
C PERALATAN
D Jumlah A + B + C 56,138.60
E Overhead & Profit (contoh 10%) 10% 5,613.86
F Harga Satuan Pekerjaan (D+E) 61,752.46

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 60,300.90


A Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 15,744.00
6.240 Kg Portland Semen 1,100.00 6,864.00
0.024 m3 Pasir Pasang 370,000.00 8,880.00
C PERALATAN
D Jumlah A + B + C 54,819.00
E Overhead & Profit (contoh 10%) 10% 5,481.90
F Harga Satuan Pekerjaan (D+E) 60,300.90

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 59,837.14


A Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 15,322.40
5.184 Kg Portland Semen 1,100.00 5,702.40
0.026 m3 Pasir Pasang 370,000.00 9,620.00
C PERALATAN
D Jumlah A + B + C 54,397.40
E Overhead & Profit (contoh 10%) 10% 5,439.74
F Harga Satuan Pekerjaan (D+E) 59,837.14

file:///conversion/tmp/scratch/509762178.xls 93/50 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 59,314.86
Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


Bahan 14,847.60
4.416 Kg Portland Semen 1,100.00 4,857.60
0.027 m3 Pasir Pasang 370,000.00 9,990.00
C PERALATAN
D Jumlah A + B + C 53,922.60
E Overhead & Profit (contoh 10%) 10% 5,392.26
F Harga Satuan Pekerjaan (D+E) 59,314.86

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 59,141.06


A Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 14,689.60
3.936 Kg Portland Semen 1,100.00 4,329.60
0.028 m3 Pasir Pasang 370,000.00 10,360.00
C PERALATAN
D Jumlah A + B + C 53,764.60
E Overhead & Profit (contoh 10%) 10% 5,376.46
F Harga Satuan Pekerjaan (D+E) 59,141.06

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 58,967.26


A Tenaga 39,075.00

L.01 0.30 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 14,531.60
3.456 Kg Portland Semen 1,100.00 3,801.60
0.029 m3 Pasir Pasang 370,000.00 10,730.00
C PERALATAN
D Jumlah A + B + C 53,606.60
E Overhead & Profit (contoh 10%) 10% 5,360.66
F Harga Satuan Pekerjaan (D+E) 58,967.26

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 58,196.60


A Tenaga 40,830.00

L.01 0.36 OH Pekerja 75,000.00 27,000.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 12,076.00
5.760 Kg Portland Semen 1,100.00 6,336.00
0.003 m3 Kapur Pasang 310,000.00 930.00
0.013 m3 Pasir Pasang 370,000.00 4,810.00
C PERALATAN
D Jumlah A + B + C 52,906.00
E Overhead & Profit (contoh 10%) 10% 5,290.60
F Harga Satuan Pekerjaan (D+E) 58,196.60

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 58,388.00


A Tenaga 40,830.00

L.01 0.36 OH Pekerja 75,000.00 27,000.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 12,250.00
3 kg Portland Semen 1,100.00 3,300.00
0.005 m3 Kapur Padam 310,000.00 1,550.00
0.020 m3 Pasir Pasang 370,000.00 7,400.00
C PERALATAN
D Jumlah A + B + C 53,080.00
E Overhead & Profit (contoh 10%) 10% 5,308.00
F Harga Satuan Pekerjaan (D+E) 58,388.00

file:///conversion/tmp/scratch/509762178.xls 93/51 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 53,625.00
A Tenaga 40,830.00

L.01 0.36 OH Pekerja 75,000.00 27,000.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 7,920.00
0.009 m3 Semen Merah 200,000.00 1,800.00
0.009 m3 Kapur Padam 310,000.00 2,790.00
0.009 m3 Pasir Pasang 370,000.00 3,330.00
C PERALATAN
D Jumlah A + B + C 48,750.00
E Overhead & Profit (contoh 10%) 10% 4,875.00
F Harga Satuan Pekerjaan (D+E) 53,625.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 54,945.00


A Tenaga 40,830.00

L.01 0.36 OH Pekerja 75,000.00 27,000.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 9,120.00
0.007 m3 Semen Merah 200,000.00 1,400.00
0.007 m3 Kapur Padam 310,000.00 2,170.00
0.015 m3 Pasir Pasang 370,000.00 5,550.00
C PERALATAN
D Jumlah A + B + C 49,950.00
E Overhead & Profit (contoh 10%) 10% 4,995.00
F Harga Satuan Pekerjaan (D+E) 54,945.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 85,002.72


A Tenaga 52,290.00

L.01 0.40 OH Pekerja 75,000.00 30,000.00

L.02 0.20 OH Tukang batu 90,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 2,200.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 24,985.20
13.632 kg Portland Semen 1,100.00 14,995.20
0.027 m3 Pasir Pasang 370,000.00 9,990.00
C PERALATAN
D Jumlah A + B + C 77,275.20
E Overhead & Profit (contoh 10%) 10% 7,727.52
F Harga Satuan Pekerjaan (D+E) 85,002.72

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 63,809.80


A Tenaga 40,935.00
L.01 0.26 OH Pekerja 75,000.00 19,500.00
L.02 0.2 OH Tukang batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 22,874.80
10.368 Kg Portland Semen 1,100.00 11,404.80
0.031 m3 Pasir Pasang 370,000.00 11,470.00
C PERALATAN
D Jumlah A + B + C 65,044.80
E Overhead & Profit (contoh 10%) 10% 6,504.48
F Harga Satuan Pekerjaan (D+E) 71,549.28

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 80,610.20


A Tenaga 52,290.00

L.01 0.40 OH Pekerja 75,000.00 30,000.00

L.02 0.20 OH Tukang batu 90,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 2,200.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 20,992.00
8.320 kg Portland Semen 1,100.00 9,152.00
0.032 m3 Pasir Pasang 370,000.00 11,840.00

file:///conversion/tmp/scratch/509762178.xls 93/52 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 73,282.00
E Overhead & Profit (contoh 10%) 10% 7,328.20
F Harga Satuan Pekerjaan (D+E) 80,610.20

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 80,127.52


A Tenaga 52,290.00

L.01 0.400 OH Pekerja 75,000.00 30,000.00

L.02 0.200 OH Tukang batu 90,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 2,200.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 20,553.20
6.912 Kg Portland Semen 1,100.00 7,603.20
0.035 m3 Pasir Pasang 370,000.00 12,950.00
C PERALATAN
D Jumlah A + B + C 72,843.20
E Overhead & Profit (contoh 10%) 10% 7,284.32
F Harga Satuan Pekerjaan (D+E) 80,127.52

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 79,295.48


A Tenaga 52,290.00

L.01 0.40 OH Pekerja 75,000.00 30,000.00

L.02 0.2 OH Tukang batu 90,000.00 18,000.00

L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 19,796.80
5.888 Kg Portland Semen 1,100.00 6,476.80
0.036 m3 Pasir Pasang 370,000.00 13,320.00
C PERALATAN
D Jumlah A + B + C 72,086.80
E Overhead & Profit (contoh 10%) 10% 7,208.68
F Harga Satuan Pekerjaan (D+E) 79,295.48

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 75,416.00


A Tenaga 57,310.00

L.01 0.440 OH Pekerja 75,000.00 33,000.00

L.02 0.22 OH Tukang batu 90,000.00 19,800.00

L.03 0.022 OH Kepala Tukang 110,000.00 2,420.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 11,250.00
0.009 m3 Semen Merah 200,000.00 1,800.00
0.009 m3 Kapur Padam 310,000.00 2,790.00
0.018 m3 Pasir Pasang 370,000.00 6,660.00
C PERALATAN
D Jumlah A + B + C 68,560.00
E Overhead & Profit (contoh 10%) 10% 6,856.00
F Harga Satuan Pekerjaan (D+E) 75,416.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 38,458.64


A Tenaga 19,640.00

L.01 0.15 OH Pekerja 75,000.00 11,250.00

L.02 0.075 OH Tukang batu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 110,000.00 880.00

L.04 0.008 OH Mandor 95,000.00 760.00


B Bahan 15,322.40
5.184 Kg Portland Semen 1,100.00 5,702.40
0.026 m3 Pasir Pasang 370,000.00 9,620.00
C PERALATAN
D Jumlah A + B + C 34,962.40
E Overhead & Profit (contoh 10%) 10% 3,496.24
F Harga Satuan Pekerjaan (D+E) 38,458.64

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 57,354.00

A Tenaga 46,780.00

L.01 0.080 OH Pekerja 75,000.00 6,000.00

L.02 0.40 OH Tukang batu 90,000.00 36,000.00

L.03 0.040 OH Kepala Tukang 110,000.00 4,400.00

L.04 0.004 OH Mandor 95,000.00 380.00

file:///conversion/tmp/scratch/509762178.xls 93/53 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 5,360.00
0.5 Kg Portland Semen 1,100.00 550.00
0.013 m3 Pasir Pasang 370,000.00 4,810.00
C PERALATAN
D Jumlah A + B + C 52,140.00
E Overhead & Profit (contoh 10%) 10% 5,214.00
F Harga Satuan Pekerjaan (D+E) 57,354.00

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 94,836.50
mm
A Tenaga 58,715.00
L.01 0.450 OH Pekerja 75,000.00 33,750.00
L.02 0.225 OH Tukang batu 90,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 110,000.00 2,530.00
L.04 0.023 OH Mandor 95,000.00 2,185.00
B Bahan 27,500.00
10 Kg Portland Semen 1,100.00 11,000.00
15 Kg Batu Granit 1,100.00 16,500.00
C PERALATAN
D Jumlah A + B + C 86,215.00
E Overhead & Profit (contoh 10%) 10% 8,621.50
F Harga Satuan Pekerjaan (D+E) 94,836.50

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 94,836.50

A Tenaga 58,715.00
L.01 0.450 OH Pekerja 75,000.00 33,750.00
L.02 0.225 OH Tukang batu 90,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 110,000.00 2,530.00
L.04 0.023 OH Mandor 95,000.00 2,185.00
B Bahan 27,500.00
10 Kg Portland Semen 1,100.00 11,000.00
15 m3 Batu Traso 1,100.00 16,500.00
C PERALATAN
D Jumlah A + B + C 86,215.00
E Overhead & Profit (contoh 10%) 10% 8,621.50
F Harga Satuan Pekerjaan (D+E) 94,836.50

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 45,096.70


Tenaga 34,025.00

L.01 0.30 OH Pekerja 75,000.00 22,500.00

L.02 0.1 OH Tukang batu 90,000.00 9,000.00

L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


Bahan 6,972.00
4.32 Kg Portland Semen 1,100.00 4,752.00
0.006 m3 Pasir Pasang 370,000.00 2,220.00
C PERALATAN
D Jumlah A + B + C 40,997.00
E Overhead & Profit (contoh 10%) 10% 4,099.70
F Harga Satuan Pekerjaan (D+E) 45,096.70

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 25,364.68
Merah
A Tenaga 19,640.00

L.01 0.15 OH Pekerja 75,000.00 11,250.00

L.02 0.075 OH Tukang batu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 110,000.00 880.00

L.04 0.008 OH Mandor 95,000.00 760.00


B Bahan 3,418.80
3.108 Kg Portland Semen 1,100.00 3,418.80
C PERALATAN
D Jumlah A + B + C 23,058.80
E Overhead & Profit (contoh 10%) 10% 2,305.88
F Harga Satuan Pekerjaan (D+E) 25,364.68

file:///conversion/tmp/scratch/509762178.xls 93/54 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 12,078.00
ekspose
A Tenaga 9,220.00

L.01 0.070 OH Pekerja 75,000.00 5,250.00

L.02 0.035 OH Tukang batu 90,000.00 3,150.00

L.03 0.004 OH Kepala Tukang 110,000.00 440.00

L.04 0.004 OH Mandor 95,000.00 380.00


B Bahan 1,760.00
1.600 Kg Portland Semen 1,100.00 1,760.00
C PERALATAN
D Jumlah A + B + C 10,980.00
E Overhead & Profit (contoh 10%) 10% 1,098.00
F Harga Satuan Pekerjaan (D+E) 12,078.00

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 55,537.90
2Pp

Tenaga 39,075.00

L.01 0.3 OH Pekerja 75,000.00 22,500.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


Bahan 11,414.00
6.34 Kg Portland Semen 1,100.00 6,974.00
0.012 m3 Pasir Pasang 370,000.00 4,440.00
C PERALATAN
D Jumlah A + B + C 50,489.00
E Overhead & Profit (contoh 10%) 10% 5,048.90
F Harga Satuan Pekerjaan (D+E) 55,537.90

27 A.4.4.2.27 1 m2 Pemasangan Acian 32,587.50

Tenaga 26,050.00
L.01 0.20 OH Pekerja 75,000.00 15,000.00
L.02 0.10 OH Tukang batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.010 OH Mandor 95,000.00 950.00
Bahan 3,575.00
3.25 Kg Portland Semen 1,100.00 3,575.00
C PERALATAN
D Jumlah A + B + C 29,625.00
E Overhead & Profit (contoh 10%) 10% 2,962.50
F Harga Satuan Pekerjaan (D+E) 32,587.50

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 41,556.90

Tenaga 26,050.00
L.01 0.20 OH Pekerja 75,000.00 15,000.00
L.02 0.10 OH Tukang batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.010 OH Mandor 95,000.00 950.00
Bahan 11,729.00
6.34 Kg Portland Semen 1,850.00 11,729.00
C PERALATAN
D Jumlah A + B + C 37,779.00
E Overhead & Profit (contoh 10%) 10% 3,777.90
F Harga Satuan Pekerjaan (D+E) 41,556.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 35,268.75

Tenaga 26,050.00
L.01 0.20 OH Pekerja 75,000.00 15,000.00
L.02 0.10 OH Tukang batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.010 OH Mandor 95,000.00 950.00
Bahan 6,012.50
3.25 Kg Mortar Siap Pakai 1,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 32,062.50
E Overhead & Profit (contoh 10%) 10% 3,206.25
F Harga Satuan Pekerjaan (D+E) 35,268.75

file:///conversion/tmp/scratch/509762178.xls 93/55 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3
dan DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 109,766.00


A Tenaga 33,290.00
L.01 0.25 OH Pekerja 75,000.00 18,750.00
L.02 0.125 OH Tukang Batu 95,000.00 11,875.00
L.03 0.013 OH Kepala Tukang 110,000.00 1,430.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 66,497.27
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,272.73 38,847.27
10.0 Kg Portland Semen 0.3 1,100.00 11,000.00
0.0450 m3 Pasir Pasang 0.09 370,000.00 16,650.00
C PERALATAN

D Jumlah A + B + C 99,787.27
E Overhead & Profit (contoh 10%) 10% 9,978.73
F Harga Satuan Pekerjaan (D+E) 109,766.00

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 110,082.50


A Tenaga 35,945.00
L.01 0.27 OH Pekerja 75,000.00 20,250.00
L.02 0.135 OH Tukang Batu 95,000.00 12,825.00
L.03 0.014 OH Kepala Tukang 110,000.00 1,540.00
L.04 0.014 OH Mandor 95,000.00 1,330.00
B Bahan 64,130.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,360.00 36,040.00
10.4 Kg Portland Semen 1,100.00 11,440.00
0.0450 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 100,075.00
E Overhead & Profit (contoh 10%) 10% 10,007.50
F Harga Satuan Pekerjaan (D+E) 110,082.50

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 142,783.50


A Tenaga 34,515.00
L.01 0.26 OH Pekerja 75,000.00 19,500.00
L.02 0.130 OH Tukang Batu 95,000.00 12,350.00
L.03 0.013 OH Kepala Tukang 110,000.00 1,430.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 95,288.18
11.87 Buah Ubin Warna 30x30 cm 4,181.82 49,638.18
10.0 Kg Portland Semen 1,100.00 11,000.00
1.50 Kg Semen warna 12,000.00 18,000.00
0.0450 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 129,803.18
E Overhead & Profit (contoh 10%) 10% 12,980.32
F Harga Satuan Pekerjaan (D+E) 142,783.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 140,794.50


A Tenaga 35,945.00
L.01 0.27 OH Pekerja 75,000.00 20,250.00
L.02 0.135 OH Tukang Batu 95,000.00 12,825.00
L.03 0.014 OH Kepala Tukang 110,000.00 1,540.00
L.04 0.014 OH Mandor 95,000.00 1,330.00
B Bahan 92,050.00
26.5 Buah Ubin Warna 20x20 cm 1,680.00 44,520.00
10.4 Kg Portland Semen 1,100.00 11,440.00
1.62 Kg Semen warna 12,000.00 19,440.00
0.0450 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 127,995.00
E Overhead & Profit (contoh 10%) 10% 12,799.50

F Harga Satuan Pekerjaan (D+E) 140,794.50


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 387,827.00
A Tenaga 33,290.00
L.01 0.250 OH Pekerja 75,000.00 18,750.00
L.02 0.125 OH Tukang Batu 95,000.00 11,875.00
L.03 0.013 OH Kepala Tukang 110,000.00 1,430.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 319,280.00
6.63 Buah Ubin Granito 40x40 cm 0.4 41,666.67 276,250.00

9.8 Kg Portland Semen 0.16 1,100.00 10,780.00


1.300 Kg Semen warna 6.25 12,000.00 15,600.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 352,570.00
E Overhead & Profit (contoh 10%) 10% 35,257.00
F Harga Satuan Pekerjaan (D+E) 387,827.00

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 73,236.90

A Tenaga 16,765.00
L.01 0.090 OH Pekerja 75,000.00 6,750.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 49,814.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 6,000.00 31,800.00
1.2 Kg Portland Semen 1,100.00 1,364.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 66,579.00
E Overhead & Profit (contoh 10%) 10% 6,657.90
F Harga Satuan Pekerjaan (D+E) 73,236.90

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 38,394.40


A Tenaga 16,765.00
L.01 0.090 OH Pekerja 75,000.00 6,750.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 18,139.00
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,500.00 14,575.00
1.14 Kg Portland Semen 1,100.00 1,254.00
0.100 Kg Semen Warna 12,000.00 1,200.00

0.003 m3 Pasir Pasang 370,000.00 1,110.00


C PERALATAN
D Jumlah A + B + C 34,904.00
E Overhead & Profit (contoh 10%) 10% 3,490.40
F Harga Satuan Pekerjaan (D+E) 38,394.40

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 230,872.40


A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.350 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 116,959.00
53.00 Buah Keramik 10 x 20 cm 1,100.00 58,300.00
8.19 Kg Portland Semen 1,100.00 9,009.00
2.75 Kg Semen Warna 12,000.00 33,000.00
0.0450 m3 Pasir Pasang 370,000.00 16,650.00

C PERALATAN
D Jumlah A + B + C 209,884.00
E Overhead & Profit (contoh 10%) 10% 20,988.40
F Harga Satuan Pekerjaan (D+E) 230,872.40
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 236,812.40
A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.350 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 122,359.00
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 550.00 58,300.00
8.19 Kg Portland Semen 1,100.00 9,009.00
3.20 Kg Semen Warna 12,000.00 38,400.00
0.0450 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 215,284.00
E Overhead & Profit (contoh 10%) 10% 21,528.40
F Harga Satuan Pekerjaan (D+E) 236,812.40

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 225,159.73


A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.35 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 111,765.67
10 Buah Ubin Keramik 33 x 33 cm 6,666.67 66,666.67
8.19 Kg Portland Semen 1,100.00 9,009.00

0.045 m3 Pasir Pasang 370,000.00 16,650.00


1.62 Kg Semen Warna 12,000.00 19,440.00
C PERALATAN
D Jumlah A + B + C 204,690.67
E Overhead & Profit (contoh 10%) 10% 20,469.07
F Harga Satuan Pekerjaan (D+E) 225,159.73

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 220,091.50


A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.35 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 107,158.18
11.87 Buah Ubin Keramik 30 x 30 cm 5,181.82 61,508.18
10.00 Kg Portland Semen 1,100.00 11,000.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
1.50 Kg Semen Warna 12,000.00 18,000.00
C PERALATAN
D Jumlah A + B + C 200,083.18
E Overhead & Profit (contoh 10%) 10% 20,008.32
F Harga Satuan Pekerjaan (D+E) 220,091.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 219,796.50


A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.35 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 106,890.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,240.00 59,360.00
10.40 Kg Portland Semen 1,100.00 11,440.00
1.62 Kg Semen Warna 12,000.00 19,440.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 199,815.00
E Overhead & Profit (contoh 10%) 10% 19,981.50
F Harga Satuan Pekerjaan (D+E) 219,796.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 428,175.00
variasi / border
A Tenaga 137,780.00
L.01 1.05 OH Pekerja 75,000.00 78,750.00
L.02 0.525 OH Tukang Batu 95,000.00 49,875.00
L.03 0.053 OH Kepala Tukang 110,000.00 5,830.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 251,470.00
33.0 Buah Ubin Keramik 5,200.00 171,600.00
9.80 Kg Portland Semen 1,100.00 10,780.00
4.37 Kg Semen Warna 12,000.00 52,440.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
C PERALATAN
D Jumlah A + B + C 389,250.00
E Overhead & Profit (contoh 10%) 10% 38,925.00
F Harga Satuan Pekerjaan (D+E) 428,175.00

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 38,861.90


A Tenaga 16,765.00
L.01 0.09 OH Pekerja 75,000.00 6,750.00
L.02 0.09 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 18,564.00
5.3 Buah Ubin Keramik 3,000.00 15,900.00
1.14 Kg Portland Semen 1,100.00 1,254.00
0.003 m3 Pasir Pasang 370,000.00 1,110.00
0.025 Kg Semen Warna 12,000.00 300.00
C PERALATAN
D Jumlah A + B + C 35,329.00
E Overhead & Profit (contoh 10%) 10% 3,532.90
F Harga Satuan Pekerjaan (D+E) 38,861.90

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 85,831.90


A Tenaga 16,765.00
L.01 0.09 OH Pekerja 75,000.00 6,750.00
L.02 0.09 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 61,264.00
10.6 Buah Ubin Keramik 5,500.00 58,300.00
1.14 Kg Portland Semen 1,100.00 1,254.00
0.003 m3 Pasir Pasang 370,000.00 1,110.00
0.05 Kg Semen Warna 12,000.00 600.00
C PERALATAN
D Jumlah A + B + C 78,029.00
E Overhead & Profit (contoh 10%) 10% 7,802.90
F Harga Satuan Pekerjaan (D+E) 85,831.90

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 84,665.90


A Tenaga 16,765.00
L.01 0.09 OH Pekerja 75,000.00 6,750.00
L.02 0.09 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 60,204.00
10.6 Buah Ubin Keramik 5,400.00 57,240.00
1.14 Kg Portland Semen 1,100.00 1,254.00
0.003 m3 Pasir Pasang 370,000.00 1,110.00
0.05 Kg Semen Warna 12,000.00 600.00
C PERALATAN
D Jumlah A + B + C 76,969.00
E Overhead & Profit (contoh 10%) 10% 7,696.90
F Harga Satuan Pekerjaan (D+E) 84,665.90
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 698,702.40
A Tenaga 92,925.00
L.01 0.7 OH Pekerja 75,000.00 52,500.00
L.02 0.35 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 542,259.00
1.06 buah Marmer 480,000.00 508,800.00
8.19 kg Portland Semen 1,100.00 9,009.00
0.045 m3 Pasir Pasang 370,000.00 16,650.00
0.65 kg Semen Warna 12,000.00 7,800.00
C PERALATAN
D Jumlah A + B + C 635,184.00
E Overhead & Profit (contoh 10%) 10% 63,518.40
F Harga Satuan Pekerjaan (D+E) 698,702.40

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 209,962.50


A Tenaga 31,625.00
L.01 0.17 OH Pekerja 75,000.00 12,750.00
L.02 0.17 OH Tukang Batu 95,000.00 16,150.00
L.03 0.017 OH Kepala Tukang 110,000.00 1,870.00
L.04 0.009 OH Mandor 95,000.00 855.00
B Bahan 159,250.00
1.05 m2 Karpet 130,000.00 136,500.00
0.35 kg Lem 65,000.00 22,750.00
C PERALATAN
D Jumlah A + B + C 190,875.00
E Overhead & Profit (contoh 10%) 10% 19,087.50
F Harga Satuan Pekerjaan (D+E) 209,962.50

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 503,167.50


A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.35 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 364,500.00
1.05 m2 Parquet Jati 310,000.00 325,500.00
0.6 Kg Lem Vynil 65,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 457,425.00
E Overhead & Profit (contoh 10%) 10% 45,742.50
F Harga Satuan Pekerjaan (D+E) 503,167.50

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 250,511.32


A Tenaga 132,750.00
L.01 1.00 OH Pekerja 75,000.00 75,000.00
L.02 0.50 OH Tukang Batu 95,000.00 47,500.00
L.03 0.050 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.050 OH Mandor 95,000.00 4,750.00
B Bahan 94,987.56
86 bh Porselen 524.39 45,097.56
9.30 Kg Portland Semen 82.6446 1,100.00 10,230.00

2.750 Kg Semen Warna 0.0121 12,000.00 33,000.00

0.018 m3 Pasir Pasang 0.11 370,000.00 6,660.00


C PERALATAN
D Jumlah A + B + C 227,737.56
E Overhead & Profit (contoh 10%) 10% 22,773.76
F Harga Satuan Pekerjaan (D+E) 250,511.32

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm, 250,431.50


A Tenaga 119,475.00
L.01 0.9 OH Pekerja 75,000.00 67,500.00
L.02 0.45 OH Tukang Batu 95,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 110,000.00 4,950.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 108,190.00
53 Buah Keramik 1,100.00 58,300.00
9.3 Kg Portland Semen 1,100.00 10,230.00
0.018 m3 Pasir Pasang 370,000.00 6,660.00
2.75 Kg Semen Warna 12,000.00 33,000.00
C PERALATAN
D Jumlah A + B + C 227,665.00
E Overhead & Profit (contoh 10%) 10% 22,766.50
F Harga Satuan Pekerjaan (D+E) 250,431.50

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm, 244,249.50


A Tenaga 119,475.00
L.01 0.9 OH Pekerja 75,000.00 67,500.00
L.02 0.45 OH Tukang Batu 95,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 110,000.00 4,950.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B Bahan 102,570.00
26.0 Buah Keramik 2,400.00 62,400.00
9.3 Kg Portland Semen 1,100.00 10,230.00
0.018 m3 Pasir Pasang 370,000.00 6,660.00
1.94 Kg Semen Warna 12,000.00 23,280.00
C PERALATAN
D Jumlah A + B + C 222,045.00
E Overhead & Profit (contoh 10%) 10% 22,204.50
F Harga Satuan Pekerjaan (D+E) 244,249.50

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 250,431.50


A Tenaga 119,475.00
L.01 0.9 OH Pekerja 75,000.00 67,500.00
L.02 0.45 OH Tukang Batu 95,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 110,000.00 4,950.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B Bahan 108,190.00
53.0 Buah Keramik 1,100.00 58,300.00
9.3 Kg Portland Semen 1,100.00 10,230.00
0.018 m3 Pasir Pasang 370,000.00 6,660.00
2.75 Kg Semen Warna 12,000.00 33,000.00
C PERALATAN
D Jumlah A + B + C 227,665.00
E Overhead & Profit (contoh 10%) 10% 22,766.50
F Harga Satuan Pekerjaan (D+E) 250,431.50

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 245,569.50


A Tenaga 119,475.00
L.01 0.9 OH Pekerja 75,000.00 67,500.00
L.02 0.45 OH Tukang Batu 95,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 110,000.00 4,950.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B Bahan 103,770.00
26.5 Buah Keramik 2,400.00 63,600.00
9.3 Kg Portland Semen 1,100.00 10,230.00
0.018 m3 Pasir Pasang 370,000.00 6,660.00
1.94 Kg Semen Warna 12,000.00 23,280.00
C PERALATAN
D Jumlah A + B + C 223,245.00
E Overhead & Profit (contoh 10%) 10% 22,324.50
F Harga Satuan Pekerjaan (D+E) 245,569.50

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 783,435.52


A Tenaga 172,575.00
L.01 1.3 OH Pekerja 75,000.00 97,500.00
L.02 0.65 OH Tukang Batu 95,000.00 61,750.00
L.03 0.065 OH Kepala Tukang 110,000.00 7,150.00
L.04 0.065 OH Mandor 95,000.00 6,175.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 539,639.11
1.06 buah Marmer 480,000.00 508,800.00
3.003 buah Paku 12 cm 35.00 105.11
12.44 kg Portlan Semen 1,100.00 13,684.00
0.025 m3 Pasir Pasang 370,000.00 9,250.00
0.65 kg Semen Warna 12,000.00 7,800.00
C PERALATAN
D Jumlah A + B + C 712,214.11
E Overhead & Profit (contoh 10%) 10% 71,221.41
F Harga Satuan Pekerjaan (D+E) 783,435.52

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 269,830.00


A Tenaga 92,925.00
L.01 0.70 OH Pekerja 75,000.00 52,500.00
L.02 0.35 OH Tukang Batu 95,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 152,375.00
1.10 m2 Batu Paros 115,000.00 126,500.00
11.75 Kg Portland Semen 1,100.00 12,925.00
0.035 m3 Pasir Pasang 370,000.00 12,950.00
C PERALATAN
D Jumlah A + B + C 245,300.00
E Overhead & Profit (contoh 10%) 10% 24,530.00
F Harga Satuan Pekerjaan (D+E) 269,830.00

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 152,174.00


A Tenaga 44,935.00
L.01 0.35 OH Pekerja 75,000.00 26,250.00
L.02 0.175 OH Tukang Batu 95,000.00 16,625.00
L.03 0.017 OH Kepala Tukang 110,000.00 1,870.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 93,405.00
11.87 bh Vynil 30x30cm 6,500.00 77,155.00
0.25 kg Lem 65,000.00 16,250.00

C PERALATAN
D Jumlah A + B + C 138,340.00
E Overhead & Profit (contoh 10%) 10% 13,834.00
F Harga Satuan Pekerjaan (D+E) 152,174.00

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 118,068.50


A Tenaga 44,935.00
L.01 0.35 OH Pekerja 75,000.00 26,250.00
L.02 0.175 OH Tukang Batu 95,000.00 16,625.00
L.03 0.017 OH Kepala Tukang 110,000.00 1,870.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 62,400.00
2.2 m' Wallpaper 27,000.00 59,400.00
0.25 kg Lem 12,000.00 3,000.00
C PERALATAN
D Jumlah A + B + C 107,335.00
E Overhead & Profit (contoh 10%) 10% 10,733.50
F Harga Satuan Pekerjaan (D+E) 118,068.50

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 48,499.00


Tenaga 22,290.00
L.01 0.12 OH Pekerja 75,000.00 9,000.00
L.02 0.12 OH Tukang Batu 95,000.00 11,400.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.006 OH Mandor 95,000.00 570.00
Bahan 21,800.00
0.003 m3 Papan Kayu Klas II 7,000,000.00 21,000.00
0.05 kg Paku Sekrup 5 cm 16,000.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 44,090.00
E Overhead & Profit (contoh 10%) 10% 4,409.00
F Harga Satuan Pekerjaan (D+E) 48,499.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 164,305.35


Tenaga 71,873.50
L.01 0.25 OH Pekerja 75,000.00 18,750.00
L.02 0.5 OH Tukang Batu 95,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.0013 OH Mandor 95,000.00 123.50
Bahan 70,450.00
1.01 m2 Paving Block Tebal 6 Cm 45,000.00 45,450.00
0.05 m3 Pasir Beton 500,000.00 25,000.00
C PERALATAN 7,045.00
10 % Peralatan 70,450.00 7,045.00
D Jumlah A + B + C 149,368.50
E Overhead & Profit (contoh 10%) 10% 14,936.85
F Harga Satuan Pekerjaan (D+E) 164,305.35

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 239,803.85


Tenaga 90,623.50
L.01 0.5 OH Pekerja 75,000.00 37,500.00
L.02 0.5 OH Tukang Batu 95,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.0013 OH Mandor 95,000.00 123.50
Bahan 115,800.00
1.01 m2 Paving Block Tebal 8 Cm 80,000.00 80,800.00
0.07 m3 Pasir Beton 500,000.00 35,000.00
C PERALATAN 11,580.00
10 % Peralatan 115,800.00 11,580.00
D Jumlah A + B + C 218,003.50
E Overhead & Profit (contoh 10%) 10% 21,800.35
F Harga Satuan Pekerjaan (D+E) 239,803.85

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 170,415.85


Tenaga 71,873.50
L.01 0.25 OH Pekerja 75,000.00 18,750.00
L.02 0.5 OH Tukang Batu 95,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.0013 OH Mandor 95,000.00 123.50
Bahan 75,500.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 50,000.00 50,500.00
0.05 m3 Pasir Beton 500,000.00 25,000.00
C PERALATAN 7,550.00
10 % Peralatan 75,500.00 7,550.00
D Jumlah A + B + C 154,923.50
E Overhead & Profit (contoh 10%) 10% 15,492.35
F Harga Satuan Pekerjaan (D+E) 170,415.85

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 252,024.85


Tenaga 90,623.50
L.01 0.5 OH Pekerja 75,000.00 37,500.00
L.02 0.5 OH Tukang Batu 95,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.0013 OH Mandor 95,000.00 123.50
Bahan 125,900.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 90,000.00 90,900.00
0.07 m3 Pasir Beton 500,000.00 35,000.00
C PERALATAN 12,590.00
10 % Peralatan 125,900.00 12,590.00
D Jumlah A + B + C 229,113.50
E Overhead & Profit (contoh 10%) 10% 22,911.35
F Harga Satuan Pekerjaan (D+E) 252,024.85
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 31,823.00
mm, 5 mm & 6 mm

A Tenaga 10,050.00
L.01 0.03 OH Pekerja 75,000.00 2,250.00

L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00


L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.004 OH Mandor 95,000.00 380.00

B Bahan 18,880.00

1.1 Lbr Plat Asbes 17,000.00 18,700.00

0.01 Kg Paku 18,000.00 180.00

C PERALATAN

D Jumlah A + B + C 28,930.00

E Overhead & Profit (contoh 10%) 10% 2,893.00

F Harga Satuan Pekerjaan (D+E) 31,823.00


Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 107,349.00

A Tenaga 22,290.00
L.01 0.12 OH Pekerja 75,000.00 9,000.00

L.02 0.12 OH Tukang Kayu 95,000.00 11,400.00


L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.006 OH Mandor 95,000.00 570.00

B Bahan 75,300.00

12.0 Lbr Akustik Uk.30 x 30 cm 6,200.00 74,400.00

0.05 Kg Paku 18,000.00 900.00

C PERALATAN

D Jumlah A + B + C 97,590.00

E Overhead & Profit (contoh 10%) 10% 9,759.00

F Harga Satuan Pekerjaan (D+E) 107,349.00

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 112,018.50

A Tenaga 18,575.00
L.01 0.10 OH Pekerja 75,000.00 7,500.00

L.02 0.10 OH Tukang Kayu 95,000.00 9,500.00


L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 83,260.00

5.80 Lbr Akustik 14,200.00 82,360.00


0.05 Kg Paku 18,000.00 900.00

C PERALATAN

D Jumlah A + B + C 101,835.00

E Overhead & Profit (contoh 10%) 10% 10,183.50

F Harga Satuan Pekerjaan (D+E) 112,018.50

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 97,322.50

A Tenaga 18,575.00
L.01 0.10 OH Pekerja 75,000.00 7,500.00

L.02 0.10 OH Tukang Kayu 95,000.00 9,500.00


L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 69,900.00

1.50 Lbr Akustik 46,000.00 69,000.00

0.05 Kg Paku 18,000.00 900.00

C PERALATAN

D Jumlah A + B + C 88,475.00

E Overhead & Profit (contoh 10%) 10% 8,847.50

F Harga Satuan Pekerjaan (D+E) 97,322.50

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 49,901.50
mm, 4 mm & 6 mm

A Tenaga 18,575.00
L.01 0.10 OH Pekerja 75,000.00 7,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00

file:///conversion/tmp/scratch/509762178.xls 93/64 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 26,790.00

0.375 Lbr Tripleks (4 mm) 70,000.00 26,250.00

0.03 Kg Paku Tripleks 18,000.00 540.00


C PERALATAN

D Jumlah A + B + C 45,365.00

E Overhead & Profit (contoh 10%) 10% 4,536.50

F Harga Satuan Pekerjaan (D+E) 49,901.50

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 543,158.00

A Tenaga 148,600.00
L.01 0.8 OH Pekerja 75,000.00 60,000.00
L.02 0.8 OH Tukang Kayu 95,000.00 76,000.00

L.03 0.08 OH Kepala Tukang 110,000.00 8,800.00


L.04 0.04 OH Mandor 95,000.00 3,800.00

B Bahan 345,180.00

0.015 m3 Kayu Jati,Papan 23,000,000.00 345,000.00

0.01 Kg Paku 18,000.00 180.00

C PERALATAN

D Jumlah A + B + C 493,780.00

E Overhead & Profit (contoh 10%) 10% 49,378.00

F Harga Satuan Pekerjaan (D+E) 543,158.00

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 43,705.20
tebal 9 mm

A Tenaga 13,275.00

L.01 0.1 OH Pekerja 75,000.00 7,500.00


L.02 0.05 OH Tukang Kayu 95,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 26,457.00

0.364 Lbr Gypsum Board 68,000.00 24,752.00

0.11 Kg Paku Sekrup 15,500.00 1,705.00

C PERALATAN

D Jumlah A + B + C 39,732.00

E Overhead & Profit (contoh 10%) 10% 3,973.20

F Harga Satuan Pekerjaan (D+E) 43,705.20

Memasang Langit-langit Akuatik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 220,467.50
Rangka Allumunium

A Tenaga 92,875.00
L.01 0.5 OH Pekerja 75,000.00 37,500.00
L.02 0.5 OH Tukang Kayu 95,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.025 OH Mandor 95,000.00 2,375.00

B Bahan 107,550.00
3.6 m' Profil Allumunium "T" 4,000.00 14,400.00
0.15 kg Kawat Ø 4 mm 7,000.00 1,050.00
1.05 bh Ramset 22,000.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 46,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 200,425.00
E Overhead & Profit (contoh 10%) 10% 20,042.50
F Harga Satuan Pekerjaan (D+E) 220,467.50

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 16,241.50


A Tenaga 9,335.00
L.01 0.05 OH Pekerja 75,000.00 3,750.00
L.02 0.05 OH Tukang Kayu 95,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 5,430.00
1.05 m1 List Kayu Profil 5,000.00 5,250.00
0.01 Kg Paku 18,000.00 180.00
C PERALATAN
D Jumlah A + B + C 14,765.00
E Overhead & Profit (contoh 10%) 10% 1,476.50
F Harga Satuan Pekerjaan (D+E) 16,241.50

file:///conversion/tmp/scratch/509762178.xls 93/65 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 87,956.00

A Tenaga 19,960.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.075 OH Tukang Kayu 95,000.00 7,125.00

L.03 0.0075 OH Kepala Tukang 110,000.00 825.00


L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 60,000.00

25 Buah Genteng Plentong 2,400.00 60,000.00

C PERALATAN

D Jumlah A + B + C 79,960.00

E Overhead & Profit (contoh 10%) 10% 7,996.00

F Harga Satuan Pekerjaan (D+E) 87,956.00

Overhead & Profit (contoh 10%)


2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 141,641.50

A Tenaga 20,015.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.075 OH Tukang Kayu 95,000.00 7,125.00
L.03 0.008 OH Kepala Tukang 110,000.00 880.00
L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 108,750.00

25 Buah Genteng Kodok / Glasur 4,350.00 108,750.00

C PERALATAN

D Jumlah A + B + C 128,765.00

E Overhead & Profit (contoh 10%) 10% 12,876.50

F Harga Satuan Pekerjaan (D+E) 141,641.50

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 127,946.50

A Tenaga 20,015.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.075 OH Tukang Kayu 95,000.00 7,125.00
L.03 0.008 OH Kepala Tukang 110,000.00 880.00
L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 96,300.00

12 Buah Genteng Plentong Super / Besar 8,025.00 96,300.00


C PERALATAN

D Jumlah A + B + C 116,315.00

E Overhead & Profit (contoh 10%) 10% 11,631.50


F Harga Satuan Pekerjaan (D+E) 127,946.50

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 103,158.00

A Tenaga 51,390.00
L.01 0.4 OH Pekerja 75,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00

L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 42,390.00

5 Buah Genteng Bubung Plentong 4,350.00 21,750.00

8 Kg Portland Semen 1,100.00 8,800.00

0.032 m3 Pasir Pasang 370,000.00 11,840.00


C PERALATAN

D Jumlah A + B + C 93,780.00

E Overhead & Profit (contoh 10%) 10% 9,378.00

F Harga Satuan Pekerjaan (D+E) 103,158.00

file:///conversion/tmp/scratch/509762178.xls 93/66 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 116,633.00

A Tenaga 51,390.00
L.01 0.4 OH Pekerja 75,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00

L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00


L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 54,640.00

5 Buah Genteng Bubung Kodok / Glasur 6,800.00 34,000.00

8 Kg Portland Semen 1,100.00 8,800.00

0.032 m3 Pasir Pasang 370,000.00 11,840.00

C PERALATAN

D Jumlah A + B + C 106,030.00

E Overhead & Profit (contoh 10%) 10% 10,603.00

F Harga Satuan Pekerjaan (D+E) 116,633.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 119,713.00

A Tenaga 51,390.00
L.01 0.4 OH Pekerja 75,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00

L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00


L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 57,440.00

4 Buah Genteng Bubung Plentong Besar 9,200.00 36,800.00

8 Kg Portland Semen 1,100.00 8,800.00

0.032 m3 Pasir Pasang 370,000.00 11,840.00

C PERALATAN

D Jumlah A + B + C 108,830.00

E Overhead & Profit (contoh 10%) 10% 10,883.00

F Harga Satuan Pekerjaan (D+E) 119,713.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 113,520.00


A Tenaga 18,300.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.067 OH Tukang Kayu 95,000.00 6,365.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 84,900.00
0.6 Lbr Rooflight 90 x 180 140,000.00 84,000.00

0.05 Kg Paku Biasa 18,000.00 900.00

C PERALATAN
D Jumlah A + B + C 103,200.00

E Overhead & Profit (contoh 10%) 10% 10,320.00

F Harga Satuan Pekerjaan (D+E) 113,520.00

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 68,029.50
mm

A Tenaga 19,265.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.075 OH Tukang Kayu 95,000.00 7,125.00

L.03 0.008 OH Kepala Tukang 110,000.00 880.00


L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 42,580.00

0.5 Lbr Asbes Gelombang 81,200.00 40,600.00

0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00

C PERALATAN

D Jumlah A + B + C 61,845.00

E Overhead & Profit (contoh 10%) 10% 6,184.50

F Harga Satuan Pekerjaan (D+E) 68,029.50

file:///conversion/tmp/scratch/509762178.xls 93/67 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 70,273.50
mm

A Tenaga 18,585.00

L.01 0.14 OH Pekerja 75,000.00 10,500.00


L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00

L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 45,300.00

0.6 Lbr Asbes Gelombang 72,200.00 43,320.00

0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00

C PERALATAN

D Jumlah A + B + C 63,885.00

E Overhead & Profit (contoh 10%) 10% 6,388.50

F Harga Satuan Pekerjaan (D+E) 70,273.50

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 70,933.50
mm

A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00

L.03 0.007 OH Kepala Tukang 110,000.00 770.00


L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 45,900.00

0.6 Lbr Asbes Gelombang 73,200.00 43,920.00

0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00

C PERALATAN

D Jumlah A + B + C 64,485.00

E Overhead & Profit (contoh 10%) 10% 6,448.50

F Harga Satuan Pekerjaan (D+E) 70,933.50

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 73,771.50
mm

A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00

L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00


L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 48,480.00

0.75 Lbr Asbes Gelombang 62,000.00 46,500.00


0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00

C PERALATAN

D Jumlah A + B + C 67,065.00
E Overhead & Profit (contoh 10%) 10% 6,706.50

F Harga Satuan Pekerjaan (D+E) 73,771.50

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 55,346.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 31,730.00
0.35 Lbr Asbes Gelombang 85,000.00 29,750.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 50,315.00
E Overhead & Profit (contoh 10%) 10% 5,031.50
F Harga Satuan Pekerjaan (D+E) 55,346.50

file:///conversion/tmp/scratch/509762178.xls 93/68 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 60,043.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 36,000.00
0.42 Lbr Asbes Gelombang 81,000.00 34,020.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,585.00
E Overhead & Profit (contoh 10%) 10% 5,458.50
F Harga Satuan Pekerjaan (D+E) 60,043.50

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 57,469.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 33,660.00
0.44 Lbr Asbes Gelombang 72,000.00 31,680.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 52,245.00
E Overhead & Profit (contoh 10%) 10% 5,224.50
F Harga Satuan Pekerjaan (D+E) 57,469.50

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 57,964.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 34,110.00
0.51 Lbr Asbes Gelombang 63,000.00 32,130.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 52,695.00
E Overhead & Profit (contoh 10%) 10% 5,269.50
F Harga Satuan Pekerjaan (D+E) 57,964.50

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 63,981.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 39,580.00
0.80 Lbr Asbes Gelombang 47,000.00 37,600.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,165.00
E Overhead & Profit (contoh 10%) 10% 5,816.50
F Harga Satuan Pekerjaan (D+E) 63,981.50

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 65,356.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 40,830.00
0.37 Lbr Asbes Gelombang 105,000.00 38,850.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00

file:///conversion/tmp/scratch/509762178.xls 93/69 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 59,415.00
E Overhead & Profit (contoh 10%) 10% 5,941.50
F Harga Satuan Pekerjaan (D+E) 65,356.50

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 68,821.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 43,980.00
0.42 Lbr Asbes Gelombang 100,000.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 62,565.00
E Overhead & Profit (contoh 10%) 10% 6,256.50
F Harga Satuan Pekerjaan (D+E) 68,821.50

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 66,181.50
mm
A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 41,580.00
0.44 Lbr Asbes Gelombang 90,000.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 60,165.00
E Overhead & Profit (contoh 10%) 10% 6,016.50
F Harga Satuan Pekerjaan (D+E) 66,181.50

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 67,358.50
mm

A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 42,650.00
0.49 Lbr Asbes Gelombang 83,000.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,235.00
E Overhead & Profit (contoh 10%) 10% 6,123.50
F Harga Satuan Pekerjaan (D+E) 67,358.50

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 70,900.50
mm

A Tenaga 18,585.00
L.01 0.14 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 45,870.00
0.57 Lbr Asbes Gelombang 77,000.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 16,500.00 1,980.00
C PERALATAN
D Jumlah A + B + C 64,455.00
E Overhead & Profit (contoh 10%) 10% 6,445.50
F Harga Satuan Pekerjaan (D+E) 70,900.50

file:///conversion/tmp/scratch/509762178.xls 93/70 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 114,499.00
A Tenaga 26,550.00
L.01 0.2 OH Pekerja 75,000.00 15,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 77,540.00
11 Lbr Genteng Beton Standrad 7,000.00 77,000.00
0.03 Kg Paku Biasa 2" - 5" 18,000.00 540.00
C PERALATAN
D Jumlah A + B + C 104,090.00
E Overhead & Profit (contoh 10%) 10% 10,409.00
F Harga Satuan Pekerjaan (D+E) 114,499.00

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 236,302.00


A Tenaga 44,780.00
L.01 0.2 OH Pekerja 75,000.00 15,000.00
L.02 0.3 OH Tukang Kayu 95,000.00 28,500.00
L.03 0.003 OH Kepala Tukang 110,000.00 330.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 170,040.00
6.9 Buah Genteng Aspal 20,000.00 138,000.00
0.35 lbr Plywood 6 mm 80,000.00 28,000.00
0.03 kg Paku Biasa 2" - 5" 18,000.00 540.00
0.50 buah Plastic Aerotor 7,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 214,820.00
E Overhead & Profit (contoh 10%) 10% 21,482.00
F Harga Satuan Pekerjaan (D+E) 236,302.00

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 100,485.00


A Tenaga 26,550.00
L.01 0.2 OH Pekerja 75,000.00 15,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 64,800.00
1.02 m2 Genteng Metal 60,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 18,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 91,350.00
E Overhead & Profit (contoh 10%) 10% 9,135.00
F Harga Satuan Pekerjaan (D+E) 100,485.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 110,341.00


A Tenaga 39,710.00
L.01 0.166 OH Pekerja 75,000.00 12,450.00
L.02 0.25 OH Tukang Kayu 95,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 110,000.00 2,750.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 60,600.00
30 Lbr Genteng Sirap 1,900.00 57,000.00
0.2 Kg Paku Biasa 1/2" - 1" 18,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 100,310.00
E Overhead & Profit (contoh 10%) 10% 10,031.00
F Harga Satuan Pekerjaan (D+E) 110,341.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 124,184.50


A Tenaga 53,100.00
L.01 0.4 OH Pekerja 75,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.02 OH Mandor 95,000.00 1,900.00
B Bahan 59,795.00
3.5 Buah Nok Genteng Beton 10,050.00 35,175.00
0.05 Kg Paku Biasa 2" - 5" 18,000.00 900.00
10.8 Kg Portland Semen 1,100.00 11,880.00
0.032 m3 Pasir Pasang 370,000.00 11,840.00
1 Kg Semen Warna 12,000.00 12,000.00

file:///conversion/tmp/scratch/509762178.xls 93/71 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 112,895.00
E Overhead & Profit (contoh 10%) 10% 11,289.50
F Harga Satuan Pekerjaan (D+E) 124,184.50

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 130,564.50


A Tenaga 36,445.00
L.01 0.125 OH Pekerja 75,000.00 9,375.00
L.02 0.250 OH Tukang Kayu 95,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 110,000.00 2,750.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 82,250.00
2.0 Buah Nok Genteng Beton 30,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 18,000.00 900.00
0.0035 m3 Balok Kayu 6,100,000.00 21,350.00
C PERALATAN
D Jumlah A + B + C 118,695.00
E Overhead & Profit (contoh 10%) 10% 11,869.50
F Harga Satuan Pekerjaan (D+E) 130,564.50

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 67,688.50


A Tenaga 35,885.00
L.01 0.250 OH Pekerja 75,000.00 18,750.00
L.02 0.150 OH Tukang Kayu 95,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 25,650.00
1.1 Buah Nok Genteng 22,500.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 18,000.00 900.00

C PERALATAN
D Jumlah A + B + C 61,535.00
E Overhead & Profit (contoh 10%) 10% 6,153.50
F Harga Satuan Pekerjaan (D+E) 67,688.50

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 55,467.50


A Tenaga 36,445.00
L.01 0.125 OH Pekerja 75,000.00 9,375.00
L.02 0.25 OH Tukang Kayu 95,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 110,000.00 2,750.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 13,980.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 30,000.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 18,000.00 1,080.00
0.05 Kg Paku Biasa 2" - 5" 18,000.00 900.00

C PERALATAN
D Jumlah A + B + C 50,425.00
E Overhead & Profit (contoh 10%) 10% 5,042.50
F Harga Satuan Pekerjaan (D+E) 55,467.50

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 41,019.00


A Tenaga 15,930.00
L.01 0.12 OH Pekerja 75,000.00 9,000.00
L.02 0.06 OH Tukang Kayu 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 21,360.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 30,000.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 18,000.00 360.00
C PERALATAN
D Jumlah A + B + C 37,290.00
E Overhead & Profit (contoh 10%) 10% 3,729.00
F Harga Satuan Pekerjaan (D+E) 41,019.00

file:///conversion/tmp/scratch/509762178.xls 93/72 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 31,856.00
A Tenaga 19,240.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.07 OH Tukang Kayu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 9,720.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 30,000.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 18,000.00 720.00
C PERALATAN
D Jumlah A + B + C 28,960.00
E Overhead & Profit (contoh 10%) 10% 2,896.00
F Harga Satuan Pekerjaan (D+E) 31,856.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 28,281.00


A Tenaga 17,310.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.05 OH Tukang Kayu 95,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 8,400.00
1.05 m2 Sisalation / Allumunium Foil 8,000.00 8,400.00
C PERALATAN
D Jumlah A + B + C 25,710.00
E Overhead & Profit (contoh 10%) 10% 2,571.00
F Harga Satuan Pekerjaan (D+E) 28,281.00

file:///conversion/tmp/scratch/509762178.xls 93/73 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 27,914,425.00
Kayu klas I
A Tenaga 2,784,250.00
L.01 7 OH Pekerja 75,000.00 525,000.00
L.02 21 OH Tukang Kayu 95,000.00 1,995,000.00
L.03 2.10 OH Kepala Tukang 110,000.00 231,000.00
L.04 0.35 OH Mandor 95,000.00 33,250.00
B Bahan 22,592,500.00
1.1 m3 Kayu Klas I (Jati) , Balok 20,500,000.00 22,550,000.00
1.25 kg Paku Biasa 2" - 5 " 18,000.00 22,500.00
1 kg Lem Kayu 20,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 25,376,750.00
E Overhead & Profit (contoh 10%) 10% 2,537,675.00
F Harga Satuan Pekerjaan (D+E) 27,914,425.00

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 12,571,900.00
Kayu klas II atau III
Tenaga 2,386,500.00
L.01 6.00 OH Pekerja 75,000.00 450,000.00
L.02 18.00 OH Tukang Kayu 95,000.00 1,710,000.00
L.03 1.80 OH Kepala Tukang 110,000.00 198,000.00
L.04 0.30 OH Mandor 95,000.00 28,500.00
Bahan 9,042,500.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 7,500,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 18,000.00 22,500.00
1 kg Lem Kayu 20,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 11,429,000.00
E Overhead & Profit (contoh 10%) 10% 1,142,900.00
F Harga Satuan Pekerjaan (D+E) 12,571,900.00

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 497,376.00
Kayu Klas II (Kayu Kamfer)
A Tenaga 139,260.00
L.01 0.35 OH Pekerja 75,000.00 26,250.00
L.02 1.05 OH Tukang Kayu 95,000.00 99,750.00
L.03 0.105 OH Kepala Tukang 110,000.00 11,550.00
L.04 0.018 OH Mandor 95,000.00 1,710.00
B Bahan 312,900.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 18,000.00 900.00
C PERALATAN
D Jumlah A + B + C 452,160.00
E Overhead & Profit (contoh 10%) 10% 45,216.00
F Harga Satuan Pekerjaan (D+E) 497,376.00

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 497,376.00
Sederhana Kayu Klas III
Tenaga 139,260.00
L.01 0.35 OH Pekerja 75,000.00 26,250.00
L.02 1.05 OH Tukang Kayu 95,000.00 99,750.00
L.03 0.105 OH Kepala Tukang 110,000.00 11,550.00
L.04 0.018 OH Mandor 95,000.00 1,710.00
Bahan 312,900.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 18,000.00 900.00
C PERALATAN
D Jumlah A + B + C 452,160.00
E Overhead & Profit (contoh 10%) 10% 45,216.00
F Harga Satuan Pekerjaan (D+E) 497,376.00

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 781,825.00
Klas I atau II
A Tenaga 397,750.00
L.01 1.00 OH Pekerja 75,000.00 75,000.00
L.02 3.00 OH Tukang Kayu 95,000.00 285,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 33,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 312,000.00
0.050 kg Lem Kayu 20,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 710,750.00
E Overhead & Profit (contoh 10%) 10% 71,075.00
F Harga Satuan Pekerjaan (D+E) 781,825.00

file:///conversion/tmp/scratch/509762178.xls 93/74 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 562,540.00
Kayu Klas I atau II
A Tenaga 318,200.00
L.01 0.800 OH Pekerja 75,000.00 60,000.00
L.02 2.400 OH Tukang Kayu 95,000.00 228,000.00
L.03 0.240 OH Kepala Tukang 110,000.00 26,400.00
L.04 0.040 OH Mandor 95,000.00 3,800.00
B Bahan 193,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 187,200.00
0.300 kg Lem Kayu 20,000.00 6,000.00
C PERALATAN
D Jumlah A + B + C 511,400.00
E Overhead & Profit (contoh 10%) 10% 51,140.00
F Harga Satuan Pekerjaan (D+E) 562,540.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 2,067,725.00
Kayu Klas I atau II (jati)
A Tenaga 397,750.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 3 OH Tukang Kayu 95,000.00 285,000.00
L.03 0.3 OH Kepala Tukang 110,000.00 33,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 23,000,000.00 1,472,000.00
0.5 kg Lem Kayu 20,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,879,750.00
E Overhead & Profit (contoh 10%) 10% 187,975.00
F Harga Satuan Pekerjaan (D+E) 2,067,725.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 620,361.50
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 278,425.00
L.01 0.700 OH Pekerja 75,000.00 52,500.00
L.02 2.100 OH Tukang Kayu 95,000.00 199,500.00
L.03 0.210 OH Kepala Tukang 110,000.00 23,100.00
L.04 0.035 OH Mandor 95,000.00 3,325.00
B Bahan 285,540.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 18,000.00 540.00
0.500 Ltr Lem Kayu 20,000.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 80,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 563,965.00
E Overhead & Profit (contoh 10%) 10% 56,396.50
F Harga Satuan Pekerjaan (D+E) 620,361.50

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 669,262.00
rangka expose kayu klas I atau II
A Tenaga 318,200.00
L.01 0.800 OH Pekerja 75,000.00 60,000.00
L.02 2.400 OH Tukang Kayu 95,000.00 228,000.00
L.03 0.240 OH Kepala Tukang 110,000.00 26,400.00
L.04 0.040 OH Mandor 95,000.00 3,800.00
B Bahan 290,220.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 18,000.00 540.00
0.5 Ltr Lem Kayu 20,000.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 80,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 608,420.00
E Overhead & Profit (contoh 10%) 10% 60,842.00
F Harga Satuan Pekerjaan (D+E) 669,262.00

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 1,844,452.50
Klas I atau II
A Tenaga 294,075.00
L.01 0.670 OH Pekerja 75,000.00 50,250.00
L.02 2.000 OH Tukang Kayu 95,000.00 190,000.00
L.03 0.200 OH Kepala Tukang 110,000.00 22,000.00
L.04 0.335 OH Mandor 95,000.00 31,825.00
B Bahan 1,382,700.00
0.06 m3 Kayu Klas I (Jati), papan 23,000,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 18,000.00 2,700.00
C PERALATAN
D Jumlah A + B + C 1,676,775.00
E Overhead & Profit (contoh 10%) 10% 167,677.50
F Harga Satuan Pekerjaan (D+E) 1,844,452.50

file:///conversion/tmp/scratch/509762178.xls 93/75 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 1,077,714.00
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 318,200.00
L.01 0.80 OH Pekerja 75,000.00 60,000.00
L.02 2.40 OH Tukang Kayu 95,000.00 228,000.00
L.03 0.24 OH Kepala Tukang 110,000.00 26,400.00
L.04 0.04 OH Mandor 95,000.00 3,800.00
B Bahan 661,540.00
0.025 m3 Kayu Klas I (Jati), papan 23,000,000.00 575,000.00
0.03 Kg Paku Biasa 1/2" - 1" 18,000.00 540.00
0.3 kg Lem Kayu 20,000.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 80,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 979,740.00
E Overhead & Profit (contoh 10%) 10% 97,974.00
F Harga Satuan Pekerjaan (D+E) 1,077,714.00

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 718,052.50
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 338,135.00
L.01 0.850 OH Pekerja 75,000.00 63,750.00
L.02 2.550 OH Tukang Kayu 95,000.00 242,250.00
L.03 0.255 OH Kepala Tukang 110,000.00 28,050.00
L.04 0.043 OH Mandor 95,000.00 4,085.00
B Bahan 314,640.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,800,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 18,000.00 540.00
0.08 kg Lem Kayu 20,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 80,000.00 80,000.00
0.5 Lbr Formika 75,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 652,775.00
E Overhead & Profit (contoh 10%) 10% 65,277.50
F Harga Satuan Pekerjaan (D+E) 718,052.50

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 11,166,980.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 1,591,000.00
L.01 4 OH Pekerja 75,000.00 300,000.00
L.02 12 OH Tukang Kayu 95,000.00 1,140,000.00
L.03 1.2 OH Kepala Tukang 110,000.00 132,000.00
L.04 0.2 OH Mandor 95,000.00 19,000.00
B Bahan 8,560,800.00
1.1 m3 Kayu Kamfer, balok 7,500,000.00 8,250,000.00
15 Kg Besi Strip 14,000.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 18,000.00 100,800.00
C PERALATAN
D Jumlah A + B + C 10,151,800.00
E Overhead & Profit (contoh 10%) 10% 1,015,180.00
F Harga Satuan Pekerjaan (D+E) 11,166,980.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 30,333,297.50
Expose, Kayu Klas I
A Tenaga 2,664,925.00
L.01 6.7 OH Pekerja 75,000.00 502,500.00
L.02 20.1 OH Tukang Kayu 95,000.00 1,909,500.00
L.03 2.01 OH Kepala Tukang 110,000.00 221,100.00
L.04 0.335 OH Mandor 95,000.00 31,825.00
B Bahan 24,910,800.00
1.2 m3 Kayu Klas I (jati), balok 20,500,000.00 24,600,000.00
15 Kg Besi Strip 14,000.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 18,000.00 100,800.00
C PERALATAN
D Jumlah A + B + C 27,575,725.00
E Overhead & Profit (contoh 10%) 10% 2,757,572.50
F Harga Satuan Pekerjaan (D+E) 30,333,297.50

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 10,415,460.00


A Tenaga 954,600.00
L.01 2.4 OH Pekerja 75,000.00 180,000.00
L.02 7.2 OH Tukang Kayu 95,000.00 684,000.00
L.03 0.72 OH Kepala Tukang 110,000.00 79,200.00
L.04 0.12 OH Mandor 95,000.00 11,400.00

file:///conversion/tmp/scratch/509762178.xls 93/76 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 8,514,000.00
1.1 m3 Kayu Klas I (Kamfer), balok 7,500,000.00 8,250,000.00
15 Kg Besi Strip 14,000.00 210,000.00
3 Kg Paku Biasa 2" - 5" 18,000.00 54,000.00
C PERALATAN
D Jumlah A + B + C 9,468,600.00
E Overhead & Profit (contoh 10%) 10% 946,860.00
F Harga Satuan Pekerjaan (D+E) 10,415,460.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 170,582.50
Klas II
A Tenaga 18,575.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 136,500.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 7,500,000.00 105,000.00
0.0036 m3 Reng (2x3) cm 7,500,000.00 27,000.00
0.25 Kg Paku Biasa 2" - 5" 18,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 155,075.00
E Overhead & Profit (contoh 10%) 10% 15,507.50
F Harga Satuan Pekerjaan (D+E) 170,582.50

Pemasangan Rangka Atap Genteng Beton, Kayu


17 A.4.6.1.17 1 m2 200,282.50
Klas II
A Tenaga 18,575.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 163,500.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 7,500,000.00 105,000.00
0.0072 m3 Reng (2x3) cm 7,500,000.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 18,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 182,075.00
E Overhead & Profit (contoh 10%) 10% 18,207.50
F Harga Satuan Pekerjaan (D+E) 200,282.50

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 143,979.00


A Tenaga 22,290.00
L.01 0.12 OH Pekerja 75,000.00 9,000.00
L.02 0.12 OH Tukang Kayu 95,000.00 11,400.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 108,600.00
0.014 m3 Kayu Klas II (Kamfer), balok 7,500,000.00 105,000.00
0.2 Kg Paku Biasa 2" - 5" 18,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 130,890.00
E Overhead & Profit (contoh 10%) 10% 13,089.00
F Harga Satuan Pekerjaan (D+E) 143,979.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 186,202.50
Klas II atau III
A Tenaga 50,175.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.30 OH Tukang Kayu 95,000.00 28,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 3,300.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 119,100.00
0.0154 m3 Kayu Klas II (Kamfer), balok 7,500,000.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 18,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 169,275.00
E Overhead & Profit (contoh 10%) 10% 16,927.50
F Harga Satuan Pekerjaan (D+E) 186,202.50

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 191,950.00
Klas II atau III
A Tenaga 47,750.00
L.01 0.2 OH Pekerja 75,000.00 15,000.00
L.02 0.3 OH Tukang Kayu 95,000.00 28,500.00
L.03 0.03 OH Kepala Tukang 110,000.00 3,300.00
L.04 0.01 OH Mandor 95,000.00 950.00

file:///conversion/tmp/scratch/509762178.xls 93/77 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 126,750.00
0.0163 m3 Kayu Klas II (Kamfer), balok 7,500,000.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 18,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 174,500.00
E Overhead & Profit (contoh 10%) 10% 17,450.00
F Harga Satuan Pekerjaan (D+E) 191,950.00

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 307,312.50
II
A Tenaga 29,175.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.020 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 250,200.00
0.0108 m3 Kayu klas I (Jati), papan 23,000,000.00 248,400.00
0.10 Kg Paku Biasa 2" - 5" 18,000.00 1,800.00
C PERALATAN
D Jumlah A + B + C 279,375.00
E Overhead & Profit (contoh 10%) 10% 27,937.50
F Harga Satuan Pekerjaan (D+E) 307,312.50

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 127,462.50
klas II
A Tenaga 29,175.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 86,700.00
0.011 m3 Kayu klas II (Kamfer), papan 7,800,000.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 18,000.00 900.00
C PERALATAN
D Jumlah A + B + C 115,875.00
E Overhead & Profit (contoh 10%) 10% 11,587.50
F Harga Satuan Pekerjaan (D+E) 127,462.50

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 299,651.00
Kayu klas II atau III
A Tenaga 59,710.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.45 OH Tukang Kayu 95,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 110,000.00 4,950.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 212,700.00
0.028 m3 Kayu klas II (Kamfer), balok 7,500,000.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 18,000.00 2,700.00
C PERALATAN
D Jumlah A + B + C 272,410.00
E Overhead & Profit (contoh 10%) 10% 27,241.00
F Harga Satuan Pekerjaan (D+E) 299,651.00

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 387,651.00
Rangka Kayu Klas II
A Tenaga 59,710.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.02 0.45 OH Tukang Kayu 95,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 110,000.00 4,950.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 292,700.00
0.028 m3 Kayu klas II (Kamfer), balok 7,500,000.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 18,000.00 2,700.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 80,000.00 68,800.00
0.56 Ltr Lem 20,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 352,410.00
E Overhead & Profit (contoh 10%) 10% 35,241.00
F Harga Satuan Pekerjaan (D+E) 387,651.00

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 394,625.00
Rangka Kayu Klas II
A Tenaga 66,050.00
L.01 0.020 OH Pekerja 75,000.00 1,500.00
L.02 0.600 OH Tukang Kayu 95,000.00 57,000.00
L.03 0.060 OH Kepala Tukang 110,000.00 6,600.00
L.04 0.010 OH Mandor 95,000.00 950.00

file:///conversion/tmp/scratch/509762178.xls 93/78 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 292,700.00
0.028 m3 Kayu klas II (Kamfer), balok 7,500,000.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 18,000.00 2,700.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 80,000.00 68,800.00
0.56 Ltr Lem 20,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 358,750.00
E Overhead & Profit (contoh 10%) 10% 35,875.00
F Harga Satuan Pekerjaan (D+E) 394,625.00

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 442,915.00

A Tenaga 238,650.00
L.01 0.6 OH Pekerja 75,000.00 45,000.00
L.02 1.8 OH Tukang Kayu 95,000.00 171,000.00
L.03 0.18 OH Kepala Tukang 110,000.00 19,800.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 164,000.00
0.007 m3 Kayu klas I (Jati), papan 23,000,000.00 161,000.00
0.1 Kg Paku Biasa 2" - 5" 18,000.00 1,800.00
0.15 Kg Paku Sekrup 3,5" 8,000.00 1,200.00
C PERALATAN
D Jumlah A + B + C 402,650.00
E Overhead & Profit (contoh 10%) 10% 40,265.00
F Harga Satuan Pekerjaan (D+E) 442,915.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 42,762.50
ukuran (120x240) cm
A Tenaga 9,975.00
L.01 0.025 OH Pekerja 75,000.00 1,875.00
L.02 0.075 OH Tukang Kayu 95,000.00 7,125.00
L.03 0.0080 OH Kepala Tukang 110,000.00 880.00
L.04 0.0010 OH Mandor 95,000.00 95.00
B Bahan 28,900.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 70,000.00 28,000.00
0.05 Kg Paku Biasa 1/2" - 1" 18,000.00 900.00
C PERALATAN
D Jumlah A + B + C 38,875.00
E Overhead & Profit (contoh 10%) 10% 3,887.50
F Harga Satuan Pekerjaan (D+E) 42,762.50

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 139,761.60
IV
A Tenaga 13,275.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.02 0.05 OH Tukang Kayu 95,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 113,781.00
1.500 m2 Bilik Bambu 22,500.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 5,700,000.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 18,000.00 216.00
0.003 m' List Kayu 2/4 5,000.00 15.00
C PERALATAN
D Jumlah A + B + C 127,056.00
E Overhead & Profit (contoh 10%) 10% 12,705.60
F Harga Satuan Pekerjaan (D+E) 139,761.60

file:///conversion/tmp/scratch/509762178.xls 93/79 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 225,307.50
A Tenaga 49,825.00
L.01 0.01 OH Pekerja 75,000.00 750.00
L.02 0.5 OH Tukang Kayu 95,000.00 47,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 155,000.00
1 Buah Kunci Tanam Biasa 155,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 204,825.00
E Overhead & Profit (contoh 10%) 10% 20,482.50
F Harga Satuan Pekerjaan (D+E) 225,307.50
Overhead & Profit (contoh 10%)

2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 158,028.75


A Tenaga 48,662.50
L.01 0.005 OH Pekerja 75,000.00 375.00
L.02 0.5 OH Tukang Kayu 95,000.00 47,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.0025 OH Mandor 95,000.00 237.50
B Bahan 95,000.00
1 Buah Kunci Tanam Kamar Mandi 95,000.00 95,000.00
C PERALATAN
D Jumlah A + B + C 143,662.50
E Overhead & Profit (contoh 10%) 10% 14,366.25
F Harga Satuan Pekerjaan (D+E) 158,028.75

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 224,028.75


A Tenaga 48,662.50
L.01 0.005 OH Pekerja 75,000.00 375.00
L.02 0.5 OH Tukang Kayu 95,000.00 47,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.0025 OH Mandor 95,000.00 237.50
B Bahan 155,000.00
1 Buah Kunci Selinder 155,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 203,662.50
E Overhead & Profit (contoh 10%) 10% 20,366.25
F Harga Satuan Pekerjaan (D+E) 224,028.75

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 29,411.25


A Tenaga 17,737.50
L.01 0.015 OH Pekerja 75,000.00 1,125.00
L.02 0.15 OH Tukang Kayu 95,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.0075 OH Mandor 95,000.00 712.50
B Bahan 9,000.00
1 Buah Engsel pintu 9,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 26,737.50
E Overhead & Profit (contoh 10%) 10% 2,673.75
F Harga Satuan Pekerjaan (D+E) 29,411.25

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 17,957.50


A Tenaga 11,825.00
L.01 0.01 OH Pekerja 75,000.00 750.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 4,500.00
1 Buah Engsel Jendela 4,500.00 4,500.00
C PERALATAN
D Jumlah A + B + C 16,325.00
E Overhead & Profit (contoh 10%) 10% 1,632.50
F Harga Satuan Pekerjaan (D+E) 17,957.50

file:///conversion/tmp/scratch/509762178.xls 93/80 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 49,222.25
A Tenaga 28,747.50
L.01 0.10 OH Pekerja 75,000.00 7,500.00
L.02 0.20 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.0005 OH Mandor 95,000.00 47.50
B Bahan 16,000.00
1 Buah Engsel Angin 16,000.00 16,000.00
C PERALATAN
D Jumlah A + B + C 44,747.50
E Overhead & Profit (contoh 10%) 10% 4,474.75
F Harga Satuan Pekerjaan (D+E) 49,222.25

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 38,813.50


A Tenaga 17,785.00
L.01 0.015 OH Pekerja 75,000.00 1,125.00
L.02 0.15 OH Tukang Kayu 95,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 17,500.00
1 Buah Kait Angin 17,500.00 17,500.00
C PERALATAN
D Jumlah A + B + C 35,285.00
E Overhead & Profit (contoh 10%) 10% 3,528.50
F Harga Satuan Pekerjaan (D+E) 38,813.50

8 A.4.6.2.10 1 Buah Pasang Door Closer 447,686.25


A Tenaga 56,987.50
L.01 0.05 OH Pekerja 75,000.00 3,750.00
L.02 0.5 OH Tukang Kayu 95,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.0025 OH Mandor 95,000.00 237.50
B Bahan 350,000.00
1 Buah Door Closer 350,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 406,987.50
E Overhead & Profit (contoh 10%) 10% 40,698.75
F Harga Satuan Pekerjaan (D+E) 447,686.25

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 47,074.50


A Tenaga 22,795.00
L.01 0.02 OH Pekerja 75,000.00 1,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.001 OH Mandor 95,000.00 95.00
B Bahan 20,000.00
1 Buah Kunci Selot 20,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 42,795.00
E Overhead & Profit (contoh 10%) 10% 4,279.50
F Harga Satuan Pekerjaan (D+E) 47,074.50

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 397,537.25


A Tenaga 11,397.50
L.01 0.01 OH Pekerja 75,000.00 750.00
L.02 0.1 OH Tukang Kayu 95,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.0005 OH Mandor 95,000.00 47.50
B Bahan 350,000.00
1 Buah Door Stop 350,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 361,397.50
E Overhead & Profit (contoh 10%) 10% 36,139.75
F Harga Satuan Pekerjaan (D+E) 397,537.25

file:///conversion/tmp/scratch/509762178.xls 93/81 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 333,723.50
A Tenaga 68,385.00
L.01 0.06 OH Pekerja 75,000.00 4,500.00
L.02 0.6 OH Tukang Kayu 95,000.00 57,000.00
L.03 0.06 OH Kepala Tukang 110,000.00 6,600.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 235,000.00
1 Buah Rel Pintu Dorong 235,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 303,385.00
E Overhead & Profit (contoh 10%) 10% 30,338.50
F Harga Satuan Pekerjaan (D+E) 333,723.50

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 39,598.35


A Tenaga 28,498.50
L.01 0.025 OH Pekerja 75,000.00 1,875.00
L.02 0.25 OH Tukang Kayu 95,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 110,000.00 2,750.00
L.04 0.00130 OH Mandor 95,000.00 123.50
B Bahan 7,500.00
1 Buah Kunci Lemari 7,500.00 7,500.00
C PERALATAN
D Jumlah A + B + C 35,998.50
E Overhead & Profit (contoh 10%) 10% 3,599.85
F Harga Satuan Pekerjaan (D+E) 39,598.35

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 121,655.88


A Tenaga 17,096.25
L.01 0.015 OH Pekerja 75,000.00 1,125.00
L.02 0.15 OH Tukang Kayu 95,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.00075 OH Mandor 95,000.00 71.25
B Bahan 93,500.00
1.1 m2 Kaca tebal 3mm 85,000.00 93,500.00
C PERALATAN
D Jumlah A + B + C 110,596.25
E Overhead & Profit (contoh 10%) 10% 11,059.63
F Harga Satuan Pekerjaan (D+E) 121,655.88

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 133,755.88


A Tenaga 17,096.25
L.01 0.015 OH Pekerja 75,000.00 1,125.00
L.02 0.15 OH Tukang Kayu 95,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.00075 OH Mandor 95,000.00 71.25
B Bahan 104,500.00
1.1 m2 Kaca tebal 5mm 95,000.00 104,500.00
C PERALATAN
D Jumlah A + B + C 121,596.25
E Overhead & Profit (contoh 10%) 10% 12,159.63
F Harga Satuan Pekerjaan (D+E) 133,755.88

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 351,555.88


A Tenaga 17,096.25
L.01 0.015 OH Pekerja 75,000.00 1,125.00
L.02 0.15 OH Tukang Kayu 95,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.00075 OH Mandor 95,000.00 71.25
B Bahan 302,500.00
1.1 m2 Kaca Cermin 275,000.00 302,500.00
C PERALATAN
D Jumlah A + B + C 319,596.25
E Overhead & Profit (contoh 10%) 10% 31,959.63
F Harga Satuan Pekerjaan (D+E) 351,555.88

file:///conversion/tmp/scratch/509762178.xls 93/82 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 13,513.50
Lama
A Tenaga 11,535.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 750.00
0.05 Kg Soda Api 15,000.00 750.00

C PERALATAN

D Jumlah A + B + C 12,285.00
E Overhead & Profit (contoh 10%) 10% 1,228.50

F Harga Satuan Pekerjaan (D+E) 13,513.50

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 13,403.50
dicat
A Tenaga 11,535.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 650.00

0.05 Kg Sabun 13,000.00 650.00

C PERALATAN

D Jumlah A + B + C 12,185.00

E Overhead & Profit (contoh 10%) 10% 1,218.50

F Harga Satuan Pekerjaan (D+E) 13,403.50

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 13,926.00
manual
A Tenaga 12,010.00
L.01 0.15 OH Pekerja 75,000.00 11,250.00
L.04 0.0080 OH Mandor 95,000.00 760.00
B Bahan 650.00
0.05 Kg Sabun 13,000.00 650.00
C PERALATAN
D Jumlah A + B + C 12,660.00
E Overhead & Profit (contoh 10%) 10% 1,266.00
F Harga Satuan Pekerjaan (D+E) 13,926.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 44,368.50
dasar, 2 Lp Cat Penutup)
A Tenaga 7,050.00
L.01 0.070 OH Pekerja 75,000.00 5,250.00
L.02 0.009 OH Tukang Cat 95,000.00 855.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 33,285.00
0.2000 kg Cat Menie 30,000.00 6,000.00
0.1500 kg Plamuur 30,000.00 4,500.00
0.1700 kg Cat Dasar 36,500.00 6,205.00
0.2600 kg Cat Penutup 58,000.00 15,080.00
0.0100 bh Kuas 8,000.00 80.00
0.0300 kg Pengencer 20,000.00 600.00
0.2000 lbr Amplas 4,100.00 820.00
C PERALATAN
D Jumlah A + B + C 40,335.00
E Overhead & Profit (contoh 10%) 10% 4,033.50
F Harga Satuan Pekerjaan (D+E) 44,368.50

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 59,900.50
dasar, 3 Lp Cat Penutup)
A Tenaga 15,950.00
L.01 0.070 OH Pekerja 75,000.00 5,250.00
L.02 0.105 OH Tukang Cat 95,000.00 9,975.00
L.03 0.004 OH Kepala Tukang 110,000.00 440.00
L.04 0.003 OH Mandor 95,000.00 285.00

file:///conversion/tmp/scratch/509762178.xls 93/83 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 38,505.00
0.2000 kg Cat Menie 30,000.00 6,000.00
0.1500 kg Plamuur 30,000.00 4,500.00
0.1700 kg Cat Dasar 36,500.00 6,205.00
0.3500 kg Cat Penutup 58,000.00 20,300.00
0.0100 bh Kuas 8,000.00 80.00
0.0300 kg Pengencer 20,000.00 600.00
0.2000 lbr Amplas 4,100.00 820.00
C PERALATAN
D Jumlah A + B + C 54,455.00
E Overhead & Profit (contoh 10%) 10% 5,445.50
F Harga Satuan Pekerjaan (D+E) 59,900.50

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 34,452.00


A Tenaga 16,200.00
L.01 0.04 OH Pekerja 75,000.00 3,000.00
L.02 0.063 OH Tukang Cat 95,000.00 5,985.00
L.03 0.063 OH Kepala Tukang 110,000.00 6,930.00
L.04 0.0030 OH Mandor 95,000.00 285.00
B Bahan 15,120.00
0.36 Ltr Teak Oil 42,000.00 15,120.00
C PERALATAN
D Jumlah A + B + C 31,320.00
E Overhead & Profit (contoh 10%) 10% 3,132.00
F Harga Satuan Pekerjaan (D+E) 34,452.00

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 61,033.50


A Tenaga 10,745.00
L.01 0.04 OH Pekerja 75,000.00 3,000.00
L.02 0.06 OH Tukang Cat 95,000.00 5,700.00
L.03 0.016 OH Kepala Tukang 110,000.00 1,760.00
L.04 0.0030 OH Mandor 95,000.00 285.00
B Bahan 44,740.00
0.15 Ltr Politur 70,000.00 10,500.00
0.372 Ltr Politur Jadi 70,000.00 26,040.00
2 Lbr Ampelas 4,100.00 8,200.00
C PERALATAN
D Jumlah A + B + C 55,485.00
E Overhead & Profit (contoh 10%) 10% 5,548.50
F Harga Satuan Pekerjaan (D+E) 61,033.50

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 10,032.00


A Tenaga 8,070.00
L.01 0.1 OH Pekerja 75,000.00 7,500.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 1,050.00
0.35 Ltr Residu atau Ter 3,000.00 1,050.00
C PERALATAN
D Jumlah A + B + C 9,120.00
E Overhead & Profit (contoh 10%) 10% 912.00
F Harga Satuan Pekerjaan (D+E) 10,032.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 38,395.50


A Tenaga 29,245.00
L.01 0.16 OH Pekerja 75,000.00 12,000.00
L.02 0.16 OH Tukang Cat 95,000.00 15,200.00
L.03 0.016 OH Kepala Tukang 110,000.00 1,760.00
L.04 0.0030 OH Mandor 95,000.00 285.00
B Bahan 5,660.00
0.15 Ltr Vernis 25,000.00 3,750.00
0.05 Ltr Dempul 30,000.00 1,500.00
0.1 Lbr Ampelas 4,100.00 410.00
-
C PERALATAN
D Jumlah A + B + C 34,905.00
E Overhead & Profit (contoh 10%) 10% 3,490.50
F Harga Satuan Pekerjaan (D+E) 38,395.50

file:///conversion/tmp/scratch/509762178.xls 93/84 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 21,057.30
Lap.Cat Penutup)
A Tenaga 8,463.00
L.01 0.02 OH Pekerja 75,000.00 1,500.00
L.02 0.063 OH Tukang Cat 95,000.00 5,985.00
L.03 0.0063 OH Kepala Tukang 110,000.00 693.00
L.04 0.0030 OH Mandor 95,000.00 285.00
B Bahan 10,680.00
0.1 Kg Plamir 32,000.00 3,200.00
0.1 Kg Cat Dasar 15,000.00 1,500.00
0.26 Kg Cat Penutup 2 kali 23,000.00 5,980.00
C PERALATAN
D Jumlah A + B + C 19,143.00
E Overhead & Profit (contoh 10%) 10% 1,914.30
F Harga Satuan Pekerjaan (D+E) 21,057.30

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 14,054.70
Penutup)
A Tenaga 6,837.00
L.01 0.028 OH Pekerja 75,000.00 2,100.00
L.02 0.042 OH Tukang Cat 95,000.00 3,990.00
L.03 0.0042 OH Kepala Tukang 110,000.00 462.00
L.04 0.0030 OH Mandor 95,000.00 285.00
B Bahan 5,940.00
0.12 Kg Cat Dasar 15,000.00 1,800.00
0.18 Kg Cat Penutup 2 kali 23,000.00 4,140.00
C PERALATAN
D Jumlah A + B + C 12,777.00
E Overhead & Profit (contoh 10%) 10% 1,277.70
F Harga Satuan Pekerjaan (D+E) 14,054.70

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 8,070.70


A Tenaga 6,837.00
L.01 0.028 OH Pekerja 75,000.00 2,100.00
L.02 0.042 OH Tukang Cat 95,000.00 3,990.00
L.03 0.0042 OH Kepala Tukang 110,000.00 462.00
L.04 0.0030 OH Mandor 95,000.00 285.00
B Bahan 500.00
0.1 Kg Kalkarium 5,000.00 500.00
-
C PERALATAN
D Jumlah A + B + C 7,337.00
E Overhead & Profit (contoh 10%) 10% 733.70
F Harga Satuan Pekerjaan (D+E) 8,070.70

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 15,073.85


A Tenaga 11,593.50
L.01 0.150 OH Pekerja 75,000.00 11,250.00
L.02 0.001 OH Tukang Cat 95,000.00 95.00
L.03 0.0001 OH Kepala Tukang 110,000.00 11.00
L.04 0.0025 OH Mandor 95,000.00 237.50
B Bahan 2,110.00
0.15 Kg Kapur Sirih 8,000.00 1,200.00
0.1 lbr Amplas 4,100.00 410.00
0.25 ikat Alang-alang 2,000.00 500.00
C PERALATAN
D Jumlah A + B + C 13,703.50
E Overhead & Profit (contoh 10%) 10% 1,370.35
F Harga Satuan Pekerjaan (D+E) 15,073.85

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 7,163.75
(pemeliharaan)
A Tenaga 3,767.50
L.01 0.040 OH Pekerja 75,000.00 3,000.00
L.02 0.005 OH Tukang Cat 95,000.00 475.00
L.03 0.0005 OH Kepala Tukang 110,000.00 55.00
L.04 0.0025 OH Mandor 95,000.00 237.50

file:///conversion/tmp/scratch/509762178.xls 93/85 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 2,745.00
0.30 Kg Kapur Sirih 4,750.00 1,425.00
0.2 lbr Amplas 4,100.00 820.00
0.25 ikat Alang-alang 2,000.00 500.00
C PERALATAN
D Jumlah A + B + C 6,512.50
E Overhead & Profit (contoh 10%) 10% 651.25
F Harga Satuan Pekerjaan (D+E) 7,163.75

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 92,331.25


A Tenaga 22,937.50
L.01 0.020 OH Pekerja 75,000.00 1,500.00
L.02 0.200 OH Tukang Cat 95,000.00 19,000.00
L.03 0.0200 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.0025 OH Mandor 95,000.00 237.50
B Bahan 61,000.00
1.20 lbr Wall Paper 40,000.00 48,000.00
0.2 kg Lem 65,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 83,937.50
E Overhead & Profit (contoh 10%) 10% 8,393.75
F Harga Satuan Pekerjaan (D+E) 92,331.25

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 27,618.25


A Tenaga 20,957.50
L.01 0.02 OH Pekerja 75,000.00 1,500.00
L.02 0.2 OH Tukang Cat 95,000.00 19,000.00
L.03 0.002 OH Kepala Tukang 110,000.00 220.00
L.04 0.0025 OH Mandor 95,000.00 237.50
B Bahan 4,150.00
0.1 Kg Meni Besi 35,000.00 3,500.00
0.01 Kg Perekat / Lem 65,000.00 650.00
C PERALATAN
D Jumlah A + B + C 25,107.50
E Overhead & Profit (contoh 10%) 10% 2,510.75
F Harga Satuan Pekerjaan (D+E) 27,618.25

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 54,326.25
Perancah
A Tenaga 40,837.50
L.01 0.25 OH Pekerja 75,000.00 18,750.00
L.02 0.225 OH Tukang Cat 95,000.00 21,375.00
L.04 0.0075 OH Mandor 95,000.00 712.50
B Bahan 8,550.00
0.1 Kg Meni Besi 35,000.00 3,500.00
0.01 Kg Perekat / Lem 65,000.00 650.00
0.002 m3 Perancah Kayu 2,200,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 49,387.50
E Overhead & Profit (contoh 10%) 10% 4,938.75
F Harga Satuan Pekerjaan (D+E) 54,326.25

file:///conversion/tmp/scratch/509762178.xls 93/86 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 2,561,141.00
A Tenaga 367,310.00
L.01 3.3 OH Pekerja 75,000.00 247,500.00
L.02 1.1 OH Tukang Batu 95,000.00 104,500.00
L.03 0.001 OH Kepala Tukang 110,000.00 110.00
L.04 0.16 OH Mandor 95,000.00 15,200.00
Buah Bahan 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,850,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,850,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 2,328,310.00
E Overhead & Profit (contoh 10%) 10% 232,831.00
F Harga Satuan Pekerjaan (D+E) 2,561,141.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 613,800.00
A Tenaga 397,700.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 1.5 OH Tukang Batu 95,000.00 142,500.00
L.03 1.5 OH Kepala Tukang 110,000.00 165,000.00
L.04 0.16 OH Mandor 95,000.00 15,200.00
B Bahan 160,300.00
1 Buah Kloset Jongkok 150,000.00 150,000.00
6 Kg Portland Semen 1,100.00 6,600.00
0.01 m3 Pasir Pasang 370,000.00 3,700.00
C PERALATAN
D Jumlah A + B + C 558,000.00
E Overhead & Profit (contoh 10%) 10% 55,800.00
F Harga Satuan Pekerjaan (D+E) 613,800.00

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 757,130.00


A Tenaga 190,500.00
L.01 1 OH Pekerja 75,000.00 75,000.00
L.02 1 OH Tukang Batu 95,000.00 95,000.00
L.03 0.1 OH Kepala Tukang 110,000.00 11,000.00
L.04 0.1 OH Mandor 95,000.00 9,500.00
B Bahan 497,800.00
1 Buah Urinoir 375,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 375,000.00 112,500.00
6 Kg Portland Semen 1,100.00 6,600.00
0.01 m3 Pasir Pasang 370,000.00 3,700.00
C PERALATAN
D Jumlah A + B + C 688,300.00
E Overhead & Profit (contoh 10%) 10% 68,830.00
F Harga Satuan Pekerjaan (D+E) 757,130.00

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 797,582.50


A Tenaga 129,775.00
L.01 1.2 OH Pekerja 75,000.00 90,000.00
L.02 0.145 OH Tukang Batu 95,000.00 13,775.00
L.03 0.15 OH Kepala Tukang 110,000.00 16,500.00
L.04 0.1 OH Mandor 95,000.00 9,500.00
B Bahan 595,300.00
1 Buah Wastafel 450,000.00 450,000.00
0.3 - Perlengkapan 30% Harga Wastafel 450,000.00 135,000.00
6 Kg Portland Semen 1,100.00 6,600.00
0.01 m3 Pasir Pasang 370,000.00 3,700.00
C PERALATAN
D Jumlah A + B + C 725,075.00
E Overhead & Profit (contoh 10%) 10% 72,507.50
F Harga Satuan Pekerjaan (D+E) 797,582.50

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,149,951.00

A Tenaga 85,410.00
L.01 0.075 OH Pekerja 75,000.00 5,625.00
L.02 0.75 OH Tukang Batu 95,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.003 OH Mandor 95,000.00 285.00

file:///conversion/tmp/scratch/509762178.xls 93/87 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
B Bahan 960,000.00
1 Buah Batchuip 800,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 800,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 1,045,410.00
E Overhead & Profit (contoh 10%) 10% 104,541.00
F Harga Satuan Pekerjaan (D+E) 1,149,951.00

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,187,450.00


A Tenaga 743,500.00
L.01 3 OH Pekerja 75,000.00 225,000.00
L.02 4.5 OH Tukang Batu 95,000.00 427,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.9 OH Mandor 95,000.00 85,500.00
B Tukang Batu 336,000.00
1 Buah Bak Fibreglass 300,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 300,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 1,079,500.00
E Overhead & Profit (contoh 10%) 10% 107,950.00
F Harga Satuan Pekerjaan (D+E) 1,187,450.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,501,093.54
A Tenaga 770,850.00
L.01 6.00 OH Pekerja 75,000.00 450,000.00
L.02 3.00 OH Tukang Batu 95,000.00 285,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 33,000.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 593,780.49
150.0 bh Batu Bata 600.00 90,000.00
120 Kg Portland Semen 0.11 1,100.00 132,000.00
0.3 m3 Pasir Pasang 0.0121 370,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 524.39 188,780.49
6 Kg Semen Nat 12,000.00 72,000.00
C PERALATAN
D Jumlah A + B + C 1,364,630.49
E Overhead & Profit (contoh 10%) 10% 136,463.05
F Harga Satuan Pekerjaan (D+E) 1,501,093.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,952,874.90


A Tenaga 697,210.00
L.01 3.50 OH Pekerja 75,000.00 262,500.00
L.02 4.50 OH Tukang Batu 95,000.00 427,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.018 OH Mandor 95,000.00 1,710.00
B Bahan 1,330,119.30 5,623,585.36
0.9 m3 Beton K.150 1,179,004.36 1,061,103.92
180 Kg Baja Tulangan 0.11 14,712.50 2,648,250.00
8.0 m2 Kayu Bekisting 0.05 0.0121 135,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,402.44 701,219.51
10 % Perlengkapan 1,330,119.30 133,011.93
C PERALATAN
D Jumlah A + B + C 6,320,795.36
E Overhead & Profit (contoh 10%) 10% 632,079.54
F Harga Satuan Pekerjaan (D+E) 6,952,874.90

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 380,022.50


A Tenaga 35,475.00
L.01 0.030 OH Pekerja 75,000.00 2,250.00
L.02 0.300 OH Tukang Batu 95,000.00 28,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 3,300.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 310,000.00
1 unit Bak Cuci Piring 250,000.00 250,000.00
1 bh Water drain 60,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 345,475.00
E Overhead & Profit (contoh 10%) 10% 34,547.50
F Harga Satuan Pekerjaan (D+E) 380,022.50

file:///conversion/tmp/scratch/509762178.xls 93/88 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 51,507.50
A Tenaga 11,825.00
L.01 0.010 OH Pekerja 75,000.00 750.00
L.02 0.100 OH Tukang Batu 95,000.00 9,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 35,000.00
1 bh Floor Drain 35,000.00 35,000.00

C PERALATAN
D Jumlah A + B + C 46,825.00
E Overhead & Profit (contoh 10%) 10% 4,682.50
F Harga Satuan Pekerjaan (D+E) 51,507.50

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 450,345.50
35 cm
A Tenaga 239,365.00
L.01 2.160 OH Pekerja 75,000.00 162,000.00
L.02 0.720 OH Tukang Batu 95,000.00 68,400.00
L.03 0.072 OH Kepala Tukang 110,000.00 7,920.00
L.04 0.011 OH Mandor 95,000.00 1,045.00
B Bahan 170,040.00
40.00 bh Batu Bata 600.00 24,000.00
44.00 kg Semen Portland 1,100.00 48,400.00
0.07 m3 Pasir Pasang 370,000.00 25,900.00
0.06 m3 Pasir Beton 500,000.00 30,000.00
0.07 m3 Kerikil 260,000.00 18,200.00
1.60 kg Baja Tulangan 14,712.50 23,540.00
C PERALATAN
D Jumlah A + B + C 409,405.00
E Overhead & Profit (contoh 10%) 10% 40,940.50
F Harga Satuan Pekerjaan (D+E) 450,345.50

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 660,572.00
tinggi 50 cm
A Tenaga 351,980.00
L.01 3.200 OH Pekerja 75,000.00 240,000.00
L.02 1.150 OH Tukang Batu 95,000.00 109,250.00
L.03 0.011 OH Kepala Tukang 110,000.00 1,210.00
L.04 0.016 OH Mandor 95,000.00 1,520.00
B Bahan 248,540.00
70.00 bh Batu Bata 600.00 42,000.00
77.00 kg Semen Portland 1,100.00 84,700.00
0.13 m3 Pasir Pasang 370,000.00 48,100.00
0.09 m3 Pasir Beton 500,000.00 45,000.00
0.02 m3 Kerikil 260,000.00 5,200.00
1.60 kg Baja Tulangan 14,712.50 23,540.00
C PERALATAN
D Jumlah A + B + C 600,520.00
E Overhead & Profit (contoh 10%) 10% 60,052.00
F Harga Satuan Pekerjaan (D+E) 660,572.00

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 793,997.19
60 cm
A Tenaga 351,980.00
L.01 3.200 OH Pekerja 75,000.00 240,000.00
L.02 1.150 OH Tukang Batu 95,000.00 109,250.00
L.03 0.011 OH Kepala Tukang 110,000.00 1,210.00
L.04 0.016 OH Mandor 95,000.00 1,520.00
B Bahan 369,835.63
123.00 bh Batu Bata 600.00 73,800.00
114.00 kg Semen Portland 1,100.00 125,400.00
0.18 m3 Pasir Pasang 370,000.00 68,080.00
0.12 m3 Pasir Beton 260,000.00 31,200.00
4.85 kg Baja Tulangan 14,712.50 71,355.63
C PERALATAN
D Jumlah A + B + C 721,815.63
E Overhead & Profit (contoh 10%) 10% 72,181.56
F Harga Satuan Pekerjaan (D+E) 793,997.19

file:///conversion/tmp/scratch/509762178.xls 93/89 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 47,608.00
A Tenaga 16,155.00
L.01 0.054 OH Pekerja 75,000.00 4,050.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.027 OH Mandor 95,000.00 2,565.00
B Bahan 27,125.00
1.20 m' Pipa Galvanis Ø ½" 17,500.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 17,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 43,280.00
E Overhead & Profit (contoh 10%) 10% 4,328.00
F Harga Satuan Pekerjaan (D+E) 47,608.00

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 97,498.78


A Tenaga 43,625.00
L.01 0.010 OH Pekerja 75,000.00 750.00
L.02 0.400 OH Tukang Batu 95,000.00 38,000.00
L.03 0.040 OH Kepala Tukang 110,000.00 4,400.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 45,010.25
1.00 bh Kran Air 45,000.00 45,000.00
0.0025 bh Sealtape 4,100.00 10.25
C PERALATAN
D Jumlah A + B + C 88,635.25
E Overhead & Profit (contoh 10%) 10% 8,863.53
F Harga Satuan Pekerjaan (D+E) 97,498.78

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 60,395.50


A Tenaga 16,155.00
L.01 0.054 OH Pekerja 75,000.00 4,050.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.027 OH Mandor 95,000.00 2,565.00
B Bahan 38,750.00
1.20 m' Pipa Galvanis Ø ¾" 25,000.00 30,000.00
0.35 Ls Perlengkapan 35% x pipa 25,000.00 8,750.00
C PERALATAN
D Jumlah A + B + C 54,905.00
E Overhead & Profit (contoh 10%) 10% 5,490.50
F Harga Satuan Pekerjaan (D+E) 60,395.50

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 68,920.50


A Tenaga 16,155.00
L.01 0.054 OH Pekerja 75,000.00 4,050.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.027 OH Mandor 95,000.00 2,565.00
B Bahan 46,500.00
1.20 m' Pipa Galvanis Ø 1" 30,000.00 36,000.00
0.35 Ls Perlengkapan 35% x pipa 30,000.00 10,500.00
C PERALATAN
D Jumlah A + B + C 62,655.00
E Overhead & Profit (contoh 10%) 10% 6,265.50
F Harga Satuan Pekerjaan (D+E) 68,920.50

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 92,937.17


A Tenaga 27,655.00
L.01 0.108 OH Pekerja 75,000.00 8,100.00
L.02 0.180 OH Tukang Batu 95,000.00 17,100.00
L.03 0.018 OH Kepala Tukang 110,000.00 1,980.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 56,833.33
1.20 m' Pipa Galvanis Ø 1½" 36,666.67 44,000.00
0.35 Ls Perlengkapan 35% x pipa 36,666.67 12,833.33
C PERALATAN
D Jumlah A + B + C 84,488.33
E Overhead & Profit (contoh 10%) 10% 8,448.83
F Harga Satuan Pekerjaan (D+E) 92,937.17

file:///conversion/tmp/scratch/509762178.xls 93/90 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 177,406.17
A Tenaga 34,695.00
L.01 0.135 OH Pekerja 75,000.00 10,125.00
L.02 0.225 OH Tukang Batu 95,000.00 21,375.00
L.03 0.023 OH Kepala Tukang 110,000.00 2,530.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 126,583.33
1.20 m' Pipa Galvanis Ø 3" 81,666.67 98,000.00
0.35 Ls Perlengkapan 35% x pipa 81,666.67 28,583.33
C PERALATAN
D Jumlah A + B + C 161,278.33
E Overhead & Profit (contoh 10%) 10% 16,127.83
F Harga Satuan Pekerjaan (D+E) 177,406.17

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 285,389.50


A Tenaga 34,695.00
L.01 0.135 OH Pekerja 75,000.00 10,125.00
L.02 0.225 OH Tukang Batu 95,000.00 21,375.00
L.03 0.023 OH Kepala Tukang 110,000.00 2,530.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 224,750.00
1.20 m' Pipa Galvanis Ø 4" 145,000.00 174,000.00
0.35 Ls Perlengkapan 35% x pipa 145,000.00 50,750.00
C PERALATAN
D Jumlah A + B + C 259,445.00
E Overhead & Profit (contoh 10%) 10% 25,944.50
F Harga Satuan Pekerjaan (D+E) 285,389.50

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 22,962.50


A Tenaga 9,250.00
L.01 0.036 OH Pekerja 75,000.00 2,700.00
L.02 0.060 OH Tukang Batu 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 11,625.00
1.20 m' Pipa PVC Ø ½" 7,500.00 9,000.00
0.35 Ls Perlengkapan 35% x pipa 7,500.00 2,625.00
C PERALATAN
D Jumlah A + B + C 20,875.00
E Overhead & Profit (contoh 10%) 10% 2,087.50
F Harga Satuan Pekerjaan (D+E) 22,962.50

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 25,520.00


A Tenaga 9,250.00
L.01 0.036 OH Pekerja 75,000.00 2,700.00
L.02 0.060 OH Tukang Batu 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 13,950.00
1.20 m' Pipa PVC Ø ¾" 9,000.00 10,800.00
0.35 Ls Perlengkapan 35% x pipa 9,000.00 3,150.00
C PERALATAN
D Jumlah A + B + C 23,200.00
E Overhead & Profit (contoh 10%) 10% 2,320.00
F Harga Satuan Pekerjaan (D+E) 25,520.00

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 29,356.25


A Tenaga 9,250.00
L.01 0.036 OH Pekerja 75,000.00 2,700.00
L.02 0.060 OH Tukang Batu 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 17,437.50
1.20 m' Pipa PVC Ø 1" 11,250.00 13,500.00
0.35 Ls Perlengkapan 35% x pipa 11,250.00 3,937.50
C PERALATAN
D Jumlah A + B + C 26,687.50
E Overhead & Profit (contoh 10%) 10% 2,668.75
F Harga Satuan Pekerjaan (D+E) 29,356.25

file:///conversion/tmp/scratch/509762178.xls 93/91 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 34,585.83
A Tenaga 13,875.00
L.01 0.054 OH Pekerja 75,000.00 4,050.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 17,566.67
1.20 m' Pipa PVC Ø 1½" 11,333.33 13,600.00
0.35 Ls Perlengkapan 35% x pipa 11,333.33 3,966.67
C PERALATAN
D Jumlah A + B + C 31,441.67
E Overhead & Profit (contoh 10%) 10% 3,144.17
F Harga Satuan Pekerjaan (D+E) 34,585.83

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 45,100.00


A Tenaga 13,875.00
L.01 0.054 OH Pekerja 75,000.00 4,050.00
L.02 0.090 OH Tukang Batu 95,000.00 8,550.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 27,125.00
1.20 m' Pipa PVC Ø 2" 17,500.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 17,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 41,000.00
E Overhead & Profit (contoh 10%) 10% 4,100.00
F Harga Satuan Pekerjaan (D+E) 45,100.00

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 75,412.33


A Tenaga 20,765.00
L.01 0.081 OH Pekerja 75,000.00 6,075.00
L.02 0.135 OH Tukang Batu 95,000.00 12,825.00
L.03 0.0135 OH Kepala Tukang 110,000.00 1,485.00
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 47,791.67
1.20 m' Pipa PVC Ø 3" 30,833.33 37,000.00
0.35 Ls Perlengkapan 35% x pipa 30,833.33 10,791.67
C PERALATAN
D Jumlah A + B + C 68,556.67
E Overhead & Profit (contoh 10%) 10% 6,855.67
F Harga Satuan Pekerjaan (D+E) 75,412.33

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 89,741.67


A Tenaga 9,250.00
L.01 0.036 OH Pekerja 75,000.00 2,700.00
L.02 0.060 OH Tukang Batu 95,000.00 5,700.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 72,333.33
1.20 m' Pipa PVC Ø 4" 46,666.67 56,000.00
0.35 Ls Perlengkapan 35% x pipa 46,666.67 16,333.33
C PERALATAN
D Jumlah A + B + C 81,583.33
E Overhead & Profit (contoh 10%) 10% 8,158.33
F Harga Satuan Pekerjaan (D+E) 89,741.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 84,392.00
cm
A Tenaga 10,620.00
L.01 0.080 OH Pekerja 75,000.00 6,000.00
L.02 0.040 OH Tukang Batu 95,000.00 3,800.00
L.03 0.004 OH Kepala Tukang 110,000.00 440.00
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 66,100.00
1.60 bh pipa tanah 12,000.00 19,200.00
35.00 kg Semen Portlan 1,100.00 38,500.00
0.014 m3 Pasir Pasang 370,000.00 5,180.00
0.014 m3 Pasir Urug 230,000.00 3,220.00
-

file:///conversion/tmp/scratch/509762178.xls 93/92 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 76,720.00
E Overhead & Profit (contoh 10%) 10% 7,672.00
F Harga Satuan Pekerjaan (D+E) 84,392.00

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 41,783.50
cm
A Tenaga 7,965.00
L.01 0.060 OH Pekerja 75,000.00 4,500.00
L.02 0.030 OH Tukang Batu 95,000.00 2,850.00
L.03 0.003 OH Kepala Tukang 110,000.00 330.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 30,020.00
1.60 bh pipa tanah 9,500.00 15,200.00
6.80 kg Semen Portlan 1,100.00 7,480.00
0.013 m3 Pasir Pasang 370,000.00 4,810.00
0.011 m3 Pasir Urug 230,000.00 2,530.00

C PERALATAN
D Jumlah A + B + C 37,985.00
E Overhead & Profit (contoh 10%) 10% 3,798.50
F Harga Satuan Pekerjaan (D+E) 41,783.50

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 127,915.70


A Tenaga 18,585.00
L.01 0.140 OH Pekerja 75,000.00 10,500.00
L.02 0.070 OH Tukang Batu 95,000.00 6,650.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 97,702.00
1.10 bh pipa beton 50,000.00 55,000.00
0.027 m3 Batu Bata 450,000.00 12,150.00
3.920 kg Semen Portlan 1,100.00 4,312.00
0.056 m3 Pasir Pasang 370,000.00 20,720.00
0.024 m3 Pasir Urug 230,000.00 5,520.00
C PERALATAN
D Jumlah A + B + C 116,287.00
E Overhead & Profit (contoh 10%) 10% 11,628.70
F Harga Satuan Pekerjaan (D+E) 127,915.70

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 594,929.50


A Tenaga 50,445.00
L.01 0.380 OH Pekerja 75,000.00 28,500.00
L.02 0.190 OH Tukang Batu 95,000.00 18,050.00
L.03 0.019 OH Kepala Tukang 110,000.00 2,090.00
L.04 0.019 OH Mandor 95,000.00 1,805.00
B Bahan 490,400.00
1.10 bh pipa beton 190,000.00 209,000.00
0.55 m3 Batu Bata 450,000.00 247,500.00
10.300 kg Semen Portlan 1,100.00 11,330.00
0.061 m3 Pasir Pasang 370,000.00 22,570.00
0.069 m3 Pasir Urug 230,000.00 15,870.00
C PERALATAN
D Jumlah A + B + C 540,845.00
E Overhead & Profit (contoh 10%) 10% 54,084.50
F Harga Satuan Pekerjaan (D+E) 594,929.50

file:///conversion/tmp/scratch/509762178.xls 93/93 abk 14-14

Anda mungkin juga menyukai