TWJO-ITP-GEN-0003-CHK-001revF Concrete Pour
TWJO-ITP-GEN-0003-CHK-001revF Concrete Pour
TWJO-ITP-GEN-0003A-CHK-001revF Page 1 / 4
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
TWJO-ITP-GEN-0003B-CHK-001revF Page 2 / 4
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
C.4
Concrete pump, pipes, hopper condition checked /Kondisi
pipa, ember cor (hopper) , concrete pump di check
C.5 Internal Vibrators - no., condition, gap checked /Internal
vibrator-(jumlah, kondisi, celah dikontrol)
C.6 External Vibrators - no., condition, gap checked /External
vibrator-(jumlah, kondisi, celah dikontrol)
C.7
Concrete drop height checked. (shoud be ≤ 1.5 m) /Tinggi
jatuh beton sudah sesuai(sebaiknya kurang dari 1,5 meter)
(Tick both boxes if initial inspection is unsatisfactory) /beri tanda NCR : Perlu tindakan Complies : Not comply :
pada box bila inspeksi awal tidak memuaskan perbaikan Sesuai Tidak sesuai
Prepared and conformed by TWJO Civil Engineer: Verified by :
TWJO-ITP-GEN-0003C-CHK-001revF Page 3 / 4
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
A Drawing Check/Gambar
A1
Drawing status approved for construction /Status Gambar
telah disetujui
TWJO-ITP-GEN-0003D-CHK-001revF Page 4 of 4