BIL NO. 2 : KERJA-KERJA SIVIL 24/7/2017 15/9/2017 53
1 Memecah & menanggal struktur sediada 24/7/2017 6/8/2017 13
2 Kerja Pembinaan dinding sekatan baharu 10/8/2017 15/9/2017 36
i Kerja dinding sekatan baharu 10/8/2017 9/9/2017 30 ii Kerja pintu baharu 25/8/2017 9/9/2017 15 iii Kerja siling baharu 30/8/2017 9/9/2017 10 iv Kerja mengecat baharu 8/9/2017 15/9/2017 7
BIL NO. 3 : KERJA-KERJA ELEKTRIKAL 23/7/2017 7/10/2017 76
1 Membuka pendawaian & SSB sediada 24/7/2017 13/8/2017 20 2 Pendawaian elektrik & PA system baru 15/8/2017 4/10/2017 50 i Trenches, truking & perpaipan 9/8/2017 30/8/2017 21 ii Pendawaian lampu, punca kuasa, isolator & PA 13/8/2017 17/9/2017 35 iii Submain kabel 16/9/2017 30/9/2017 14 iv Pemasangan lampu & aksesori 22/9/2017 4/10/2017 12
BIL NO. 4 : KERJA-KERJA MEKANIKAL 24/7/2017 30/9/2017 68
1 Sistem Hawa Dingin 24/7/2017 30/9/2017 68 i Membuka, mengalih dan memasang FCU 24/7/2017 25/8/2017 32 sediada ii Pendawaian dan perpaipan 22/8/2017 14/9/2017 23 iii Membekal & memasang FCU baharu 15/9/2017 30/9/2017 15
2 Sistem Pencegahan Kebakaran
i Membuka pendawaian & mengalih Fire Alarm Panel sediada 24/7/2017 16/8/2017 23 ii Pendawaian baharu serta pemasangan alat 19/8/2017 16/9/2017 28 pengesan asap dan haba baru