SC-S Prequalification Questionnaire (Bahasa&English)
SC-S Prequalification Questionnaire (Bahasa&English)
CSTS JO CSTS JO
SUBCONTRACTOR-S (SERVICES) PERTANYAAN PRA-KUALIFIKASI
PRE-QUALIFICATION QUESTIONNAIRE SUBKONTRACTOR-S (JASA)
LNG TANGGUH EXPANSION PROJECT PROYEK EKSPANSI LNG TANGGUH
INTRODUCTION PENGANTAR
1.1 Potential Subcontractors-S are requested, 1.1 Kandidat Subkontraktor-S diminta, pada tahap
at this stage, to submit a complete questionnaire ini, untuk mengirimkan kuesioner lengkap yang
giving full details of its structure, organization, memberikan perincian lengkap tentang struktur,
financial resources, and experience. All items organisasi, sumber daya keuangan, dan
should be completed, and supplementary pages pengalamannya. Semua item harus dilengkapi dan
may be inserted. The questionnaire is to be halaman tambahan dapat dimasukkan. Kuesioner
submitted in accordance with the instructions given harus diserahkan sesuai dengan instruksi yang
herein. diberikan di sini.
1.2 Applicant must ensure that their 1.2 Pemohon harus memastikan bahwa pengajuan
submission fully includes the necessary mereka sepenuhnya mencakup dokumentasi yang
documentation to demonstrate their experience and diperlukan untuk menunjukkan pengalaman dan
capabilities in design and construction for the kemampuan mereka dalam desain dan konstruksi
Works which they are interested in and wish to be untuk Pekerjaan yang mereka minati dan ingin
considered as a potential Subcontractor. dianggap sebagai Subkontraktor potensial.
1.3 Applicants must submit all the 1.3 Pelamar harus menyerahkan semua informasi
information hereinafter requested. Any yang selanjutnya diminta. Kuesioner apa pun tidak
questionnaire not filled out completely, or which diisi sepenuhnya, atau yang menghilangkan
omit requested information may be rejected. informasi yang diminta dapat ditolak.
1.4 All clarification questions shall be 1.4 Semua pertanyaan klarifikasi harus diarahkan,
directed, in writing, to the attention of the secara tertulis, kepada Departemen Konstruksi di
Construction Department at the following address: alamat berikut:
TO: CSTS JO
INDY Bintaro Office, 2nd Floor Jl.Boulevard Bintaro Jaya Block B7/A6
Sector VII CBD Bintaro Jaya, Tangerang Selatan 15224 Indonesia
E-mail: katsuki.ninomiya@csts-tep.com
This Questionnaire and any participation therein, Kuisioner ini dan setiap partisipasi di dalamnya,
including any statements whether oral or written termasuk pernyataan apakah secara lisan atau
between CSTS JO and any applicant shall not tertulis antara CSTS JO dan pemohon tidak boleh
create or be deemed to create any binding legal membuat atau dianggap membuat hubungan hukum
relationship or Contract or be construed to do so atau Kontrak yang mengikat atau ditafsirkan untuk
between Chiyoda Corporation and any applicant. melakukannya antara CSTS JO dan pemohon apa
All Subcontractors submitting responses do so with pun. Semua Subkontraktor yang mengirimkan
the understanding that CSTS JO accepts no tanggapan melakukannya dengan pemahaman
obligation of confidentiality with respect to any bahwa CSTS JO tidak menerima kewajiban
information disclosed to CSTS JO in the kerahasiaan sehubungan dengan informasi apa pun
questionnaire unless specifically covered by a yang diungkapkan kepada CSTS JO dalam
separate confidentiality agreement.
Name:
Date Prepared / Tanggal dokumen ini di tulis:
Position / Jabatan :
Company Name /
Nama Perusahaan
Line of Business /
Jenis Usaha
Date of Company
Established /
Tanggal Pendirian
perusahaan
VAT Code /
Nomor NPWP
Ownership /
Kepemilikan saham
%
Phone
Country / Negara
Details of Office / Factory / Warehouse location responsible for delivery of goods / services
Rincian lokasi Kantor / Pabrik / Gudang yang bertanggung jawab atas pengiriman barang / jasa
Address Phone
Details of Administrative Dept. responsible for invoicing the goods / services ordered
Rincian Departemen Administrasi bertanggung jawab untuk menagih barang / jasa yang dipesan
Note: Parent Company must be able to issue a Parent Company Guarantee for its subsidiary /
Catatan: Perusahaan Induk harus dapat menerbitkan Jaminan Perusahaan Induk untuk anak
perusahaannya
Capital Share Held by Parent Company (%) / Saham Modal Dimiliki oleh Perusahaan Induk (%):
Name & Position of Contact Person / Nama & Posisi Contact Person:
Capital Share Held by Parent Company (%)/ Saham Modal Dimiliki oleh Perusahaan Induk (%):
Name & Position of Contact Person / Nama & Posisi Contact Person:
A.02.2 - Describe the corporate structure of your A.02.2 - Jelaskan struktur perusahaan perusahaan Anda,
company, including the relationships between termasuk hubungan antara perusahaan Anda
your company and parent/associate dan orang tua / organisasi asosiasi dan setiap
organizations and any joint ventures, usaha patungan, kemitraan atau aliansi di
partnerships or alliances in which your mana perusahaan Anda merupakan peserta
company is a participant including any termasuk setiap proyek saat ini atau sedang
projects currently or being considered in dipertimbangkan di wilayah atau lokasi CSTS
region or location of the described CSTS JO. JO yang dijelaskan. Jelaskan hubungan
Describe the authoritative and fiscal otoritatif dan fiskal antara perusahaan Anda,
relationship between your company, the perusahaan induk dan perusahaan afiliasi.
parent company and affiliated companies.
A.02.3 - Describe any type of reorganization by your A.02.3 - Jelaskan semua jenis reorganisasi oleh
company in the past 3 years? (Merger, perusahaan Anda dalam 3 tahun
acquisitions, changes of ownership). If yes,
terakhir? (Merger, akuisisi, perubahan
provide background, rationale and current
state of the reorganization.
kepemilikan). Jika ya, berikan latar
belakang, alasan dan keadaan
reorganisasi saat ini.
A.02.4 – Describe if your company is currently A.02.4 - Jelaskan jika perusahaan Anda saat ini
operating under any form of bankruptcy beroperasi di bawah segala bentuk
protection and describe the background perlindungan kebangkrutan dan
and explain the current situation. gambarkan latar belakang dan jelaskan
situasi saat ini.
Paid up capital /
Modal disetor
Shareholders /
Pemegang saham
Insurance Company /
Perusahaan asuransi
Average Annual < 1 Million / di bawah 6 – 10 Million USD > 50 Million USD
Engineering/Construc satu juta dollar
tion Volume (Last 11 – 25 Million USD
Five Years) US$: 1 – 5 Million USD
Rata-Rata Volume
Tahunan Engineering
/ Konstruksi (dalam
Lima Tahun
Terakhir) dalam mata
uang US Dollar
A.03.3 – If your company is assessed to be A.03.3 - Jika perusahaan Anda dinilai secara
financially inadequate in relation to the finansial tidak memadai dalam kaitannya
size of the project, would the parent dengan ukuran proyek, apakah
and/or the ultimate parent company, perusahaan induk dan / atau perusahaan
whichever is acceptable to CSTS JO be induk utama, mana yang dapat diterima
prepared to provide a bank guarantee at oleh CSTS JO dipersiapkan untuk
its own costs? memberikan jaminan bank dengan biaya
sendiri?
A.03.4 – Describe any litigation pending against A.03.4 - Jelaskan litigasi apa pun yang tertunda
your company that impact this project. terhadap perusahaan Anda yang
memengaruhi proyek ini.
SECTION A.04 COMPANY EXPERIENCES / BAGIAN A.04 PENGALAMAN PERUSAHAAN
Indicate your sales under each Work Tunjukkan penjualan Anda di bawah
Category for the past five years by masing-masing Kategori Pekerjaan selama
percentage, and check the Sub-Categories lima tahun terakhir berdasarkan
in which your company has been engaged: persentase, dan periksa Sub-Kategori
tempat perusahaan Anda bergerak:
Camp Operation / Camp Facilities / Fasilitas Mess atau Tenda atau Camp
Peng-operasi-an Mess Camp Operation Service / Jasa Peng-operasi-an Mess atau
atau Tenda atau Camp: Tenda atau Camp
Fired Heaters / Jasa Fired Heater / Jasa yang berhubungan pemanas bersumber
yang berhubungan dari api
dengan pemanas Boiler / ketel tungku
bersumber dari api : Refractory / bahan tahan panas
Manpower Supply / Jasa Supervisory Staff / Jasa penyediaan tenaga kerja tingkat
penyediaan tenaga kerja: pengawas dan staf
Skilled Worker / Jasa penyediaan tenaga kerja tingkat
tenaga kerja buruh terlatih
Other: ( ) ( )
Other: ( ) ( )
Other: ( ) ( )
Other: ( ) ( )
Total: 100%
A.04.2 - Project Types / A.04.2 – Jenis jasa pekerjaan proyek
Indicate your company’s experience in the Tunjukkan pengalaman perusahaan Anda
following project types: dalam jenis jasa pekerjaan proyek berikut
ini:
3:
4:
5:
4:
5:
4:
5:
A.04.4 - Work History & Current Projects / A.04.4 - Sejarah Kerja & Proyek Saat Ini
Indicate in Annex I the projects completed Tunjukkan dalam Lampiran I proyek yang
by your company during the last five years diselesaikan oleh perusahaan Anda selama
and those that are currently under lima tahun terakhir dan proyek yang saat
construction. ini sedang dibangun.
SECTION B.01 ORGANIZATION & EMPLOYEES / BAGIAN B.01 ORGANISASI dan KARYAWAN
B.01.2 - Total Number of Permanent Employees B.01.2 - Jumlah Total Karyawan Permanen
Please indicate the breakdown of Harap tunjukkan rincian karyawan tetap di
permanent employees in your organisasi Anda:
organization:
Managerial Staff:
Administrators:
Engineers (See Section B.01.3):
CADD Technicians/Draftsmen:
HSE Staff:
Field Supervisors (See Section B.01.3):
Craftsmen (See Section B.01.4):
Other ( ):
Other ( ):
Other ( ):
Other ( ):
Other ( ):
Total:
Notes
i. The totals for Engineers, Field i. Total untuk Insinyur, Pengawas Lapangan dan
Supervisors and Craftsmen should Pengrajin harus sesuai dengan rincian yang
correspond with the breakdowns disediakan dalam Bagian B.01.3 dan B.01.4.
provided under Sections B.01.3 and
B.01.4. ii. Pengrajin dengan masa kerja kurang dari tiga
ii. Craftsmen with less than three years
tahun seharusnya tidak dimasukkan sebagai
of service should not be included as
Permanent Employees. Karyawan Tetap.
B.01.3 - Number of Engineers & Field Supervisors / B.01.3 - Jumlah Insinyur & Supervisor Lapangan
a) Engineers / Insinyur
Category / Jenis Insinyur Number / Jumlah orang
Architectural:
Civil:
Electrical:
Instrumentation:
Mechanical & Piping:
Other ( ):
Other ( ):
Other ( ):
Other ( ):
Other ( ):
Total:
Building:
Civil:
Electrical:
Instrumentation:
Insulation:
Mechanical: Erection & Installation:
Painting:
Piping:
Steel Structure:
Tank:
Other ( ):
Other ( ):
Other ( ):
Other ( ):
Other ( ):
Total:
Notes
i. The totals for Engineers and Field i. Total untuk Insinyur dan Pengawas Lapangan
Supervisors should correspond with harus sesuai dengan total yang disediakan
the totals provided under Section dalam Bagian B.01.2.
B.01.2.
B.01.4 - Number of Craftsmen / Jumlah orang pengrajin
Direct-Hire Basis / Perusahaan me-rekrut secara langsung, status pekerja sebagai pegawai
perusahaan
Through Labor Suppliers / Perusahaan me-rekrut melalui pihak ketiga, status pekerja
sebagai pegawai perusahaan pihak ketiga
b) Please indicate the area in Indonesia b) Tolong tunjukkan daerah di Indonesia dari mana
from which most of your skilled sebagian besar pekerja terampil Anda berasal:
workers originate:
c) Describe the typical sources c) Jelaskan sumber khas (lokasi) untuk tenaga
(locations) for contracted craft labor kerja kerajinan yang dikontrak dan jika
personnel and if direct hire, agent hire mempekerjakan langsung, menyewa agen
(TCN) or subcontract.
(TCN) atau subkontrak
.
d) What percentage of local Indonesian d) Berapa persentase pekerja lokal Indonesia dan
workers and local region workers do pekerja daerah setempat yang biasanya Anda
you typically employ on construction pekerjakan pada proyek konstruksi?
projects?
Note: Local Indonesia Worker is Catatan: Pekerja Lokal Indonesia adalah pekerja
worker from outside of project dari luar lokasi proyek
location Pekerja Daerah setempat adalah
Local Region Workers is pekerja dari area proyek di sekitarnya
worker from surrounding project area
Please indicate in Annex III the Harap cantumkan dalam Lampiran III perkiraan
estimated future workload of your beban kerja perusahaan Anda di masa mendatang
company for the next two years. untuk dua tahun ke depan.
Please note that responses to all questions under Harap perhatikan bahwa semua pertanyaan di
Section B.03 are mandatory. bawah Bagian B.03 wajib dijawab.
a) Indicate in Annex IV the work b) Tunjukkan dalam Lampiran V volume kerja dan
volumes and productive man-hours jam kerja produktif untuk berbagai kategori
for the various categories of work pekerjaan yang ditentukan untuk lima proyek
specified for the last full year for
terakhir yang diselesaikan yang tersedia
which you have records available.
catatannya untuk Anda.
B.04.1 - If your company has manuals or standards B.04.1 - Jika perusahaan Anda memiliki manual atau
for project control (Manpower, standar untuk kontrol proyek (Tenaga Kerja,
Schedule, Progress and Cost Control) Jadwal, Kemajuan dan Kontrol Biaya), silakan
please check the appropriate box and centang kotak yang sesuai dan berikan perincian
provide details of such control systems sistem kontrol seperti di bawah ini:
below:
B.04.3 - Describe your overall material B.04.3 - Jelaskan proses pengadaan material Anda
procurement process. Describe how secara keseluruhan. Jelaskan bagaimana logistik
logistics are managed to ensure timely dikelola untuk memastikan pengiriman material
deliverable of materials. yang tepat waktu.
B.04.4 - PLANNING CONTROL / KONTROL DARI SEGI PERENCANAAN
a) Describe your standard plan of a) Jelaskan rencana standar pelaksanaan Anda
execution for Projects and how to untuk Proyek dan cara mengatasi persyaratan
address the schedule requirements. jadwal. Sorot setiap tindakan inovatif yang telah
Highlight any innovative actions you Anda terapkan untuk memenuhi persyaratan
have implemented in order to meet jadwal kontrak apa pun.
the schedule requirements of any
contract.
c) Describe the system you would use c) Jelaskan sistem yang akan Anda gunakan untuk
to measure progress and physical mengukur kemajuan dan penyelesaian fisik pada
completion on a project. suatu proyek.
SECTION B.05 HEALTH, SAFETY & BAGIAN B.05 MANAJEMEN KESEHATAN,
ENVIRONMENTAL (HSE) MANAGEMENT KESELAMATAN & LINGKUNGAN (HSE)
I. HSE Governance
I. Tata Kelola HSE
Submit Copy of HSE Certification (OHSAS
18001, ISO 14001, etc.); Menyerahkan Foto copy Sertifikasi HSE (OHSAS
Submit a copy of HSE Policy; 18001, ISO 14001, dll.);
Submit a copy of HSE Management System Kirim salinan Kebijakan HSE;
Manual; Menyerahkan salinan Manual Sistem Manajemen
Company Organization Chart and PROJECT HSE;
Organization Chart, specifying the number and Bagan Organisasi Perusahaan dan Bagan
the appointments of HSE personnel; Organisasi PROYEK, yang menentukan jumlah
Provide details of employee’s orientation program dan penunjukan personil HSE;
and HSE training program. How often are Berikan detail program orientasi karyawan dan
formalized programs conducted? Is HSE training program pelatihan HSE. Seberapa sering program
given also, for specialized operations? formal dilakukan? Apakah pelatihan HSE juga
What arrangements does your Company have for diberikan, untuk operasi khusus?
provision and upkeep of Personal Protective Pengaturan apa yang dimiliki Perusahaan Anda
Equipment (PPE), both standard issue and that untuk penyediaan dan pemeliharaan Alat
required for specialized activities; Pelindung Diri (APD), baik masalah standar dan
Provide details of how do you ensure that plant yang diperlukan untuk kegiatan khusus;
and equipment used within your premises, sites or Berikan perincian tentang bagaimana Anda
other locations by your employees are correctly memastikan bahwa pabrik dan peralatan yang
registered, controlled and maintained in a safe digunakan di dalam gedung, lokasi, atau lokasi
working condition. Anda yang lain oleh karyawan Anda terdaftar,
Project HSSE Acknowledge Requirements dikontrol, dan dipelihara dengan benar dalam
(PHSSER) kondisi kerja yang aman.
Persyaratan Pengakuan HSSE Proyek (PHSSER)
Provide a list of the last 5 (five) years safety Berikan daftar statistik keselamatan 5 (lima) tahun
statistics within your organization. terakhir dalam organisasi Anda.
The list should indicate the number of Fatalities, Daftar tersebut harus menunjukkan jumlah Fatalitas,
Worked Man-hours, Lost Time Injuries (LTI), Jam Kerja Pria, Cedera Waktu Hilang (LTI),
Lost Time Injuries Frequency Rate (LTIFR), Tingkat Frekuensi Cedera Waktu Hilang (LTIFR),
TRIR (Total Recordable Injury Rate) in 1,000,000 TRIR (Total Tingkat Cedera yang Dapat Dicatat)
Man-hours Work, Work Restricted Cases, dalam 1.000.000 Jam Kerja Man, Kasus Terbatas
Medical Treatment Cases, First Aid Cases, Kerja, Perawatan Medis Kasus, Kasus
Occupational Health Diseases and Near-Misses. Pertolongan Pertama, Penyakit Kesehatan Kerja
dan nyaris meninggal.
Where appropriate, separate statistics should be
Apabila diperlukan, statistik terpisah harus
given for different locations.
diberikan untuk lokasi yang berbeda.
SAFETY RECORD (LAST 5 YEARS Incl. current Year) / REKAMAN KEAMANAN (TERAKHIR 5 TAHUN Termasuk Tahun sekarang)
20 ( )
20 ( )
20 ( )
20 ( )
TOTAL
REMARKS :
Fatalities = Number of Fatalities
Total Recordable Injury (TRI) = Number of Fatalities , LTI's (Lost time injuries), RWC's (Restricted Work Cases) and MTC (Medical Treatment Cases)
Total Recordable Injury Frequency (TRIF) = The number of Fatalities, Lost Time Injuries (LTI) , Restricted Work Cases (RWC) and Medical Treatment Cases (MTC)
Lost Time Injury (LTI) = Number of Lost Time Injuries
Lost Time Injury Frequency (LTIF) = Number of Fatalities and LTI's per million hours worked
Sickness Absence = Total Number of Sickness Absence hours as a percentage of the Planned Working Hours
Serious Incident Frequency = The number of serious incidents (including near misses) per million hours worked
CATATAN :
Fatalities = Jumlah kematian akibat kecelakaan
Total Recordable Injury (TRI) = Jumlah kematian akibat kecelakaan, LTI's (Jumlah cidera hilang waktu), RWC's (Kasus adanya keterbatasan untuk pergi bekerja)
dan MTC (Kasus Perawatan Medis)
Total Frekuensi Cedera yang Dapat Dicatat (TRIF) = Jumlah Kematian, Jumlah Cidera Hilang Waktu (LTI), Kasus adanya keterbatasan untuk pergi bekerja (RWC) dan Kasus
Perawatan Medis (MTC)
Lost Time Injury (LTI) = Jumlah Cidera Hilang Waktu
Lost Time Injury Frequency (LTIF) = Jumlah Kematian akibat kecelakaan, dan LTI (Jumlah Cidera Hilang Waktu) per satuan satu juta jam kerja
Tidak hadir akibat sakit = Jumlah Total jam tidak hadir karena sakit sebagai persentase dari Jam Kerja yang Direncanakan
Frekuensi Insiden Serius = Jumlah insiden serius (termasuk nyaris celaka) per juta jam bekerja
SECTION B.06 QUALITY MANAGEMENT SYSTEM / SISTEM MANAJEMEN KUALITAS
Please note that responses to all questions under Harap perhatikan bahwa semua pertanyaan di
Section B.06 are mandatory. bawah Bagian B.06 wajib dijawab.
Yes No
If your answer is “Yes”, please fill the following table and provide the copy of the certificate /
Jika jawaban Anda adalah "Ya", silakan isi tabel berikut dan berikan salinan sertifikatnya
Scope of Certification /
Lingkup Sertifikasi
Apakah perusahaan Anda memiliki Sistem Manajemen Mutu yang terdokumentasi untuk Manual dan
prosedur QA (prosedur NCR, prosedur Audit, CAR, PAR, NCR, dan prosedur Pengendalian
Dokumen)?
Yes No
- Does your company have periodic improvement program such as Process Objective or KPI as part of
the Quality Management System?
- Apakah perusahaan Anda memiliki program perbaikan berkala seperti Process Objective atau KPI
sebagai bagian dari Sistem Manajemen Mutu?
Yes No
Yes No
If yes, please fill the following table and provide the updated organization chart with names
B.06.4 - Has the subcontractor produced Inspection Testing Plan (ITP) / Method of Statement / Execution
Plan?
Sudahkah subkontraktor menghasilkan Rencana Pengujian Inspeksi (ITP) / Metode Pernyataan /
Rencana Eksekusi?
Yes No
If yes please provide the sample of ITP / Method of Statement / Execution Plan related to Scope of
Works or Services
Jika ya, harap berikan sampel ITP / Metode Pernyataan / Rencana Eksekusi yang terkait dengan
Lingkup Pekerjaan atau Layanan
SECTION B.07 INDUSTRIAL RELATIONS, GOVERNEMENT RELATIONS AND PUBLIC
AFFAIRS, LABOR RELATIONS AND WORKFORCE STABILITY / HUBUNGAN
INDUSTRI, HUBUNGAN PEMERINTAH DAN BIDANG PUBLIK, HUBUNGAN
TENAGA KERJA DAN STABILITAS PEKERJAAN
Does your company have experience in Apakah perusahaan Anda memiliki pengalaman
industrial relations in workshop and dalam hubungan industri di lingkungan bengkel
construction site environments, including dan lokasi konstruksi, termasuk berurusan dengan
dealing with appropriate local and otoritas lokal dan nasional yang sesuai dan serikat
national authorities and trades unions? pekerja?
Yes No
Please provide examples below, (or on a Harap berikan contoh di bawah ini, (atau pada
separate sheet), from your previous lembar terpisah), dari proyek Anda sebelumnya.
projects.
B.07.2 - Describe the history of any substantial B.07.2 - Jelaskan sejarah pekerjaan penting yang telah
work you have performed within the Anda lakukan dalam batas pemerintah dari lokasi
governmental boundary of the proposed lokasi yang diusulkan untuk proyek CSTS JO ini
site location for this CSTS JO project or atau di lokasi terdekat atau yang serupa. Jelaskan
in locations nearby or similar. Describe juga pengalaman Anda dengan urusan publik dan
also your experience with public and komunitas di bidang ini.
community affairs in this area.
B.07.3 - Describe your experience with public and B.07.3 - Jelaskan pengalaman Anda dengan
community affairs in this area urusan publik dan komunitas di bidang ini
B.07.4 - LABOR RELATIONS AND WORKFORCE STABILITY
a) Describe the labor agreements in place at a) Jelaskan perjanjian kerja yang berlaku di
your company that are applicable to work perusahaan Anda yang berlaku untuk bekerja di
in the location of the described CSTS JO lokasi proyek JO CSTS yang dijelaskan. Berikan
project. Provide details and the detail dan tanggal kedaluwarsa perjanjian tersebut.
expiration date of such agreements.
b) Relative to work in the location of the b) Relatif untuk bekerja di lokasi proyek CSTS JO
described CSTS JO project, list any labor yang dijelaskan, buat daftar mogok kerja atau
strikes or other work stoppages at your penghentian kerja lainnya di perusahaan Anda atau
company or on a project you were pada proyek yang dikaitkan dengan Anda selama
associated with during the last five years. lima tahun terakhir. Jika penghentian telah terjadi
If stoppages have occurred during the selama dua tahun terakhir, identifikasi tindakan apa
past two years, identify what action has yang telah diambil untuk menghindari penghentian
been taken to avoid similar stoppages in serupa di masa depan.
the future.
c) For working in the location of the c) Untuk bekerja di lokasi proyek CSTS JO yang
described CSTS JO project, describe how dijelaskan, jelaskan bagaimana hubungan tenaga
labor relations are managed by your kerja dikelola oleh perusahaan Anda.
company.
SECTION B.08 INFORMATION TECHNOLOGY
a) Does your company utilize computer hardware and software programs for engineering and project
management, including procurement and construction management?
Yes No
i. Engineering
ii.Project Execution
Other ( )
Other ( )
Other ( )
iii. Construction
Material Control
Personnel Gate Control
Other ( )
Other ( )
Other ( )
b) Please provide details of the IT systems that your company utilizes under the above headings:
Annex I
(Work History & Current Projects)
(Page 1 of 2)
(Work History)
Company Name:
Location:
Projects Completed
Notes:
i. In entering data in the above table please use the following abbreviations:
Company Name:
Location:
Notes:
i. In entering data in the above table please use the following abbreviations:
Other ( ):
Other ( ):
Annex III / Lampiran III
(Estimated Future Workload / Estimasi kapasitas beban pekerjaan di masa depan)
Company Name:
Location:
Notes:
i. In entering data in the above table please use the following abbreviations:
Scope of Work Type of Contract
E: Engineering L: Lump Sum
P: Procurement C: Cost Plus
C: Construction U: Unit Price
O: Other
Annex IV / Lampiran IV
(Productivity: Overall / produktifitas secara keseluruhan)
Company Name:
Location:
Please indicate your company’s productive man- Harap tunjukkan jam kerja produktif perusahaan
hours for the various categories of work stated Anda untuk berbagai kategori pekerjaan yang
below for the last full year for which you have dinyatakan di bawah ini selama setahun penuh
records available. You should also indicate the terakhir yang tersedia untuk catatan Anda. Anda
breakdown of your figures (as percentages both in juga harus menunjukkan rincian angka Anda
terms of project types and locations) in the boxes (sebagai persentase baik dalam hal jenis proyek dan
provided. lokasi) dalam kotak yang disediakan.
a) Overall Work Volumes and Man-Hours a) Keseluruhan Volume Kerja dan Jam Kerja
You should provide the work volumes and
man-hours expended per work category Anda harus memberikan volume pekerjaan dan jam
specified in the table below for the last full kerja yang dikeluarkan untuk setiap kategori
year for which you have figures available pekerjaan yang ditentukan dalam tabel di bawah ini
(please indicate the year in the box provided): untuk tahun penuh terakhir yang tersedia angka
Anda (harap cantumkan tahun dalam kotak yang
disediakan):
Year of Data:
Overall Work Volumes and Man-Hours per Work Category for Full Year
Work Category Unit Work Volume Man-Hours
Piling: Number (piles)
Civil Works: m3 (concrete)
Buildings: m2 (floor area)
Furnace Steel: Ton (steel)
Structural Steel: Pre-Fabrication: Ton (steel)
Structural Steel: Installation: Ton (steel)
Equipment Installation: Ton (equipment)
Piping: Pre-Fabrication: Dia. Inch (pipe)
Piping: Installation: Dia. Inch (pipe)
Electrical Installation: Linear Meter (cable)
Instrumentation Installation: Linear Meter (cable)
Painting: m2 (painting)
Insulation: m2 (insulation)
b) Project Type & Project Location b) Jenis Proyek & Lokasi Proyek
You should provide a breakdown of the work Anda harus memberikan rincian pekerjaan yang
that the above figures represent as percentages ditunjukkan oleh angka-angka di atas sebagai
per project type and project location: persentase per jenis proyek dan lokasi proyek:
Company Name:
Location:
Please indicate your company’s productive man- Harap tunjukkan jam kerja produktif perusahaan
hours for the various categories of work stated Anda untuk berbagai kategori pekerjaan yang
below for the last five completed projects for which dinyatakan di bawah ini untuk lima proyek terakhir
you have records available. You should also yang telah diselesaikan yang tersedia catatannya
indicate the project type and location in the untuk Anda. Anda juga harus menunjukkan jenis
appropriate boxes. proyek dan lokasi di kotak yang sesuai.
a) Project #1
i. Please indicate the project name and construction period / i. Harap sebutkan nama proyek dan periode
konstruksi::
Project Name:
Start (month/year):
Finish (month/year):
ii. Please indicate the project type / ii. Harap cantumkan jenis proyek::
Chemical Plant
Gas Plant (LNG/NGL)
Power Plant
Petrochemical Plant
Petroleum Refinery
Other Industrial Plant ( )
Industrial Building
Commercial Building
Land Infrastructure
Marine Infrastructure
Other Infrastructure ( )
Other Construction ( )
iii. Please provide the work volumes and man-hours expended per work category specified in the table
below for the above project
iii. Harap berikan volume kerja dan jam kerja yang dikeluarkan per kategori pekerjaan yang ditentukan
dalam tabel di bawah untuk proyek di atas::
Overall Work Volumes and Man-Hours per Work Category for the Project /
Volume Kerja Keseluruhan dan Jam Kerja per Kategori Pekerjaan untuk Proyek
Work Category Unit Work Volume Man-Hours
Piling: Number (piles)
Civil Works: m3 (concrete)
Buildings: m2 (floor area)
Furnace Steel: Ton (steel)
Structural Steel: Pre-Fabrication: Ton (steel)
Structural Steel: Installation: Ton (steel)
Equipment Installation: Ton (equipment)
Piping: Pre-Fabrication: Dia. Inch (pipe)
Piping: Installation: Dia. Inch (pipe)
Electrical Installation: Linear Meter (cable)
Instrumentation Installation: Linear Meter (cable)
Painting: m2 (painting)
Insulation: m2 (insulation)
QUESTIONNAIRE COMPLIANCE CHECKLIST / DAFTAR PERIKSA KUESIONER KESESUAIAN
Annex I work volumes and productive man-hours / Lampiran I volume kerja dan jam kerja
produktif
Annex II work volumes and productive man-hours for the various categories of works for the
last five completed projects. / Lampiran II volume kerja dan jam kerja produktif untuk berbagai
kategori pekerjaan untuk lima proyek terakhir yang diselesaikan.
Annex III Work History and current projects / Lampiran III Sejarah Kerja dan proyek saat ini
Annex IV Construction Equipment List / Lampiran IV Daftar Peralatan Konstruksi
Annex V Estimated Future Workload / Lampiran V Diperkirakan Beban Kerja Di Masa Depan