Essentials of Validation
Project Management
Part I
William Garvey
T
he qualification and validation of complex pharmaceutical
manufacturing facilities requires the careful coordination
VECTOR CORPORATION
• piping and instrumentation diagrams; qualification. Column headings and subheadings usually consist
• utility-flow diagrams; of the following:
• equipment lists. • document collection and review (to develop protocols and SOPs);
These four types of documents are common and essential to • calibration and metrology;
all validation projects, although the level of detail and content • protocol preparation (installation qualification [IQ], operational
may vary. Design-document quality is usually closely associated qualification [OQ], performance qualification [PQ], and clean-
with cost; the greater the upfront engineering costs, the more ing);
detail that can be found in drawings and lists. Because facility • protocol execution (IQ, OQ, PQ, and cleaning);
construction and protocol preparation require drawings that are • final reports;
detailed, accurate, and thoroughly checked, increased funding • turnover packages (contain construction test reports, as-built
for engineering services is usually money well spent. In general, drawings);
one can expect that the cost of facility-design services will be ap- • SOPs (operation, maintenance, cleaning).
proximately 10–12% of the facility’s total installed cost. A checkmark is placed in each cell for which a specific activity
It is useful to identify project activities on a spreadsheet when is required. This checkmark may be replaced eventually with the
establishing project scope. Systems and equipment requiring name of the individual responsible for the activity. Assigning labor
qualification and validation are first determined by reviewing the hours to each checkmark is even more useful because this provides
project documents described previously. Then, the spreadsheet an estimate of the labor required for each activity and for the en-
is created and the first column is reserved for each identified sys- tire project (see Table I).
tem and piece of equipment. Adjacent columns become a ma-
trix of activities necessary to complete system and equipment
4
Figure 4: Typical air-flow diagram for an API facility.
Project labor requirements and budgeting thus requiring that outside validation services be contracted. As-
By revising the spreadsheet to include labor hours, and then total- signing a dollar amount (e.g., $75) to each hour of labor provides
ing each row and column, a project labor estimate per activity and an estimate of validation project costs, which often is used to jus-
system can be derived (7). Dividing total project hours by 2080 tify requests for financial resources and to support the annual budg-
h/year provides an estimate of personnel required to complete all eting process.
activities. Total project headcount will vary depending on project Industry experience has shown that validation costs (excluding
duration, however. Anticipating the number of labor hours is im- commissioning and process validation) typically range from 2.5–5%
portant because the labor involved may exceed available resources, of the total installed cost of the facility. Aseptic-filling and biotech-
5
DATA AND REVIEW
nology facilities frequently have the highest validation cost, whereas portation into corresponding protocols);
API facilities tend to be the least expensive. Care must be taken not • preliminary acceptance criteria (for each system and piece of
to apply these guidelines too tightly because the percentage vali- equipment);
dation cost will vary with project size. As an example, the purchase • SOP listing;
and installation of a small steam sterilizer might have a total in- • other GMP-required activities (document control, training, en-
stalled cost of $150,000; however, the validation costs may exceed vironmental monitoring, and so forth);
$50,000 (33%), when protocol preparation and implementation, • drawings, particularly facility layouts, piping and instrumenta-
SOP development, and laboratory supplies are considered. tion diagrams, and air-flow diagrams.
On validation projects, personnel are often subdivided into If possible, special or unique features should be emphasized
teams, with one team preparing SOPs, another team preparing in the master plan, especially those that ensure product unifor-
protocols, and so forth. Alternately, one person may be assigned mity or the elimination of contamination and cross-contami-
to a specific system, taking full responsibility for protocol and SOP nation. These features might include a description of extract
preparation, implementation, and final-report development. The booths, personnel showers, and isolators used during toxic ma-
spreadsheet described previously helps with this decision. Either terials processing. Room air-change rates, personnel gowning
method is satisfactory, but the one chosen must account for per- practices, and decontamination with formaldehyde or vapor-
sonnel availability and future operational needs. Often, contrac- ized hydrogen peroxide also are worth mentioning. It is impor-
tors are employed to prepare protocols and SOPs only, while im- tant to convey quality and attention to detail in the master plan
plementation is reserved for company personnel. This approach because this document is approved by the Quality Assurance
has several benefits. First, the contractor travel expenses are min- department and often is reviewed by FDA.
imized because all document development can occur in the con- Other programs to describe in the validation master plan are
tractor’s home office. Second, protocol implementation is per- the facility revalidation program, turnover package develop-
formed by those who will ultimately operate and maintain the ment, and system or equipment commissioning. With the pub-
validated equipment and systems. This process may reduce the lication of the International Society for Pharmaceutical Engi-
transition time from start-up to manufacturing, and if properly neering’s Baseline Pharmaceutical Engineering Guide:
documented, can satisfy GMP training requirements. Commissioning and Qualification in March 2001, greater em-
phasis has been placed on system and equipment commission-
Validation master plan development ing (8). Until recently, commissioning was an activity often per-
The validation master plan complements the project scope. Al- formed without any involvement of quality assurance or
though master plans are not officially required by some regulatory validation personnel. The construction team or an agent hired
agencies, these documents may be submitted to FDA as part of the by the project manager usually performed system commission-
preoperational review program (FMD 135) discussed previously. ing. Commissioning documents were often prepared and exe-
Master plans typically describe the project scope in detail and in- cuted without any review or oversight by the Quality Assurance
clude preliminary validation acceptance criteria. They also con- department. In many instances, validation often repeated com-
tain a description of all programs that collectively make the facil- mon commissioning tests and verifications, thereby increasing
ity GMP compliant. A well-conceived and well-written master plan costs and creating inefficiencies. In addition, systems often were
reduces the likelihood that a critical activity or program will be commissioned and validated where commissioning would have
omitted and provides regulators with a sense that the company is satisfied operational requirements. It is worthwhile to identify
quality-minded and operating in a state of control. and describe the interaction between commissioning and val-
Once the project scope is determined and reduced to spread- idation in the master plan. The plan may include a description
sheet format, the spreadsheet may be imported into the draft val- of required commissioning documents and how they support
idation master plan. Master plans usually are focused on project the validation effort. In general, systems that have no product
deliverables, not costs. Therefore, estimated costs and labor hours contact are good candidates for commissioning only, although
do not need to be presented. There is no standard format for val- there are occasional exceptions to this rule.
idation master plans, although the concept has evolved so that The facility revalidation program also should be described in
many features are standard from company to company. Each mas- the master plan because the validation life cycle continues long
ter plan is an analysis and evaluation of a manufacturing facility’s after the facility is mechanically complete and handed over for op-
validation and compliance requirements. Typical master plan con- eration. Revalidation usually takes two forms: time or event based
tents include the following: (9). Time-based revalidation is the practice in which a system or
• approval page (quality-assurance approval is required); process is recertified at a specified interval. Time-based assessments
• introduction and facility description; also can include a review of historical system performance data.
• project organizational chart (optional); Event-based revalidation is implemented whenever physical or op-
• descriptions of component and material storage areas, produc- erational changes are made to the system outside the scope of the
tion areas, quality assurance areas, critical utility systems (HVAC, original validation. All such modifications are the subject of the
purified water, water-for-injection, building management sys- facility’s change control program, which also should be described
tem); in detail in the master plan.
• spreadsheet (described previously); Turnover package (TOP) development also can be described
• system and equipment descriptions (in sufficient detail for im- in the master plan. Turnover package is a system for organiz-
6
ing all documents related to facility and system design, con- municates expectations, and conveys a quality mindset and state
struction, and start-up relevant to the eventual commissioning of control to regulators. Each of these project components, in con-
and qualification of systems and equipment (10). Turnover junction with the guidelines and programs described in Part 2 that
packages are usually prepared by the construction manager and follows, helps assure that the project is completed on time and
turned over to the owner at project completion. TOP docu- within budget. More importantly, quality is built into the project
ments construction activities and contributes to system IQ, OQ, from the start, regulatory compliance is realized, and the transi-
and PQ and usually is a prospective or concurrent activity (i.e., tion from start-up to operation is optimized. In the current envi-
design, construction and start-up documents are compiled as ronment of cost control, expedited product introductions, and in-
system construction proceeds). Turnover packages will be dis- creased regulatory oversight, the benefits of efficient validation
cussed in detail in Part 2 of this article. project management should be evident.
Summary References
This article provides a basic introduction to four components that 1. US Food and Drug Administration, Code of Federal Regulations, Title 21
are fundamental to all successful validation projects. Part 2 will de- (FDA, Washington, DC, April 1, 2005), pp. 120–141.
2. W. Garvey,“Integrated Validation Programs for Solid Dosage Facilities—
scribe three additional programs that should be considered and Part 1,” Am. Pharm. Rev. 2 (2), 33–39 (1999).
implemented. Before undertaking any validation project, careful 3. The Construction Specifications Institute (Alexandria, VA).
planning to arrive at a logical, uncomplicated approach is required. 4. Department of Health, Education and Welfare, “Human Drugs—Cur-
All projects are labor and capital intensive, and incorrect or inef- rent Good Manufacturing Practice in Manufacture, Processing, Packing
ficient use of either resource ultimately escalates cost and extends or Holding of Large Volume Parenterals, and Request for Comments Re-
garding Small Volume Parenterals,” Fed. Regist. 41 (106), 22022–22115
the schedule. (June 1, 1976).
All validation projects must begin with a comprehensive design 5. 3-A Sanitary Standards Inc., McClean, VA.
review and include FDA assistance if necessary. Once a compliant 6. FDA, “ORA Field Management Directive 135, Pre-Operational Reviews
design is finalized, validation project scope must be established of Manufacturing Facilities” (FDA, Washington, DC, Dec. 4, 1995).
and properly communicated to all project stakeholders. Concur- 7. W. Garvey,“Effective Validation Project Management,” oral presentation
given at Interphex Conference 2005, New York, NY, April 26–28, 2005.
rent with project-scope definition is the development of a labor 8. ISPE Baseline Pharmaceutical Engineering Guide, Pharmaceutical Engi-
estimate, and by extension, a cost estimate. Knowing labor require- neering Guides for New and Renovated Facilities, Vol. 5, Commissioning
ments and costs early helps identify potential shortfalls in person- and Qualification, (International Society for Pharmaceutical Engineer-
nel and permits appropriation of sufficient funding to complete ing [ISPE], March 2001), pp. 11–15.
the project. Accurately defining project scope also avoids misun- 9. ISPE Baseline Pharmaceutical Engineering Guide, Pharmaceutical Engi-
neering Guides for New and Renovated Facilities, Vol. 5, Commissioning
derstandings, errors, and omissions when work is assigned to con- and Qualification, (ISPE, March 2001), p. 111.
tractors and company personnel. A comprehensive validation mas- 10. M. Chin,“TOP: A Rational Approach For Ensuring Proper Biopharma-
ter plan follows design review and scope definition in the project ceutical Plant Construction,” in proceedings from PharmTech Confer-
timeline. The master plan identifies critical project activities, com- ence ’87 (Aster Publishing Corporation, Eugene, OR, 1987), p. 73. PT