PAKET PEKERJAAN :

REHABILITASI DI PEMALI PAKET II


KABUPATEN TEGAL DAN KABUPATEN BREBES
SNVT PELAKSANAAN JARINGAN PEMANFAATAN AIR PEMALI - JUANA

LAPORAN MINGGUAN
PERIODE MINGGU KE :
21 (dua Puluh Satu)

TANGGAL

11 November 2019 s/d 17 November 2019

WAKTU PELAKSANAAN : 188 HARI KALENDER

NOMOR KONTRAK : KU 0301/Ao7.9/Ao6.3/03/VI/2019


TANGGAL KONTRAK : 27 Juni 2019
NOMOR SPMK : 03/SPMK/IRWA-I-PJPAPJ/VI/2019

TANGGAL SPMK : 27 Juni 2019

KONSULTAN SUPERVISI :
PT. IKA ADYA PERKASA

KONTRAKTOR PELAKSANA :

PT. SANGKURIANG KARYA SEMESTA (KSO)


PT. RADIKS INSAN PERSADA
PAKET PEKERJAAN :
REHABILITASI DI PEMALI PAKET II
KABUPATEN TEGAL DAN KABUPATEN BREBES
SNVT PELAKSANAAN JARINGAN PEMANFAATAN AIR PEMALI - JUANA

LAPORAN HARIAN
PERIODE MINGGU KE :
21 (dua Puluh Satu)

TANGGAL
11 November 2019 s/d 17 November 2019

WAKTU PELAKSANAAN : 188 HARI KALENDER

NOMOR KONTRAK : KU 0301/Ao7.9/Ao6.3/03/VI/2019


TANGGAL KONTRAK : 27 Juni 2019
NOMOR SPMK : 03/SPMK/IRWA-I-PJPAPJ/VI/2019

TANGGAL SPMK : 27 Juni 2019

KONSULTAN SUPERVISI :
PT. IKA ADYA PERKASA

KONTRAKTOR PELAKSANA :

PT. SANGKURIANG KARYA SEMESTA (KSO)


PT. RADIKS INSAN PERSADA
LAPORAN MINGGUAN
Pekerjaaan : REHABILITASI DI PEMALI PAKET II Minggu Ke : 21 (dua Puluh Satu) Penyedia Jasa : PT. SANGKURIANG KARYA SEJATI
PPK : IRIGASI DAN RAWA I Priode s/d Tanggal : 11-Nov-19 s/d 17-Nov-19 PT. RADIKS INSAN PERSADA (KSO)
Satuan Kerja : SNVT PJPA Waktu Yang Telah Lewat : 144 hari Nomor Surat Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
Lokasi : KABUPATEN BREBES Komulatif Bobot Realisasi : 81.80 % Tanggal 27 Juni 2019
Tahun Anggaran : 2019 Komulatif Bobot Rencana : 81.27 % Nomor SPMK KU 03/SPMK/IRWA-I-PJPAPJ/VI/2019
Amandemn I : KU 0301/Ao7.9/Ao6.3/03/VII/AM I/2019 Deviasi Progress : 0.53 % Tanggal 27 Juni 2019
: 23 Juli 2019
Amandemn II : KU 0301/Ao7.9/Ao6.3/03/XI/AM II/2019,
: 6 November 2019 Waktu Pelaksana 188 hari kalender
Volume Bobot ( % )
Bobot
No. Uraian Pekerjaan Sat. Volume s/d Minggu s/d Minggu s/d Minggu Ket.
(%) Minggu ini s/d Minggu ini Minggu ini
Lalu Lalu ini
1 2 3 4 5 6 7 8=6+7 9 10 11 = 9 + 10 12
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 0.096 0.410 - 0.41 0.039 - 0.039
2 Kisdam m3 256.80 0.177 - - - - - -
3 Pengeringan / Dewatering jam 930.00 0.640 155.000 155.000 310.00 0.107 0.107 0.213
4 Dereksi Keet Ls 1.00 0.192 1.000 - 1.00 0.192 - 0.192
0 0 0 0.000
II DI PEMALI KANAN 0 0.000
1 Galian tanah dengan alat berat m3 29,667.35 2.206 12569.500 9369.500 21939.00 0.935 0.697 1.631
2 Galian tanah biasa m3 3,474.37 0.710 3175.490 - 3175.49 0.649 - 0.649
3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 3,319.56 0.388 - - - - - -
4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 16,366.09 1.389 440.000 590.400 1030.40 0.031 0.050 0.081
5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 14,404.55 2.185 - 999.600 999.60 0.067 0.152 0.218
6 perataan sisa galian m3 3,355.10 0.095 - - - - - -
7 Beton B0 m3 - 0.000 - - - - - -
8 Beton mutu K-175 Ready mix m3 5,192.53 21.592 4672.640 203.400 4876.04 19.430 0.846 20.276
9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 5,423.83 22.161 4567.845 609.600 5177.45 18.621 2.491 21.112
10 Pembesian kg 62,057.26 3.648 32814.420 3752.200 36566.62 1.929 0.221 2.150
11 Wiremesh M8 kg 382,755.89 18.398 365663.233 2300.400 367963.63 17.576 0.111 17.687
12 Besi angkur dia. 10 cm kg 2,271.38 0.145 196.350 - 196.35 0.013 - 0.013
13 Bekisting m2 20,882.96 12.225 18295.530 321.300 18616.83 10.710 0.188 10.898
14 Dilatasi aspal pasir t= 2cm m 7,191.52 4.529 3681.720 - 3681.72 2.319 - 2.319
15 Bongkaran pasangan batu m3 1,451.97 0.312 1123.230 - 1123.23 0.242 - 0.242
16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 661.82 2.498 - 150.000 150.00 1.516 0.566 2.082
17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 414.36 1.263 - 156.300 156.30 0.476 0.476 0.953
18 Plesteran 1 pc 3 ps m2 2,724.89 0.704 - - - 0.115 - 0.115
19 Pekerjaan Acian m2 2,724.89 0.389 - - - - - -
20 Siaran 1 Pc 2 Ps m2 - 0.000 - - - - - -
21 Pengadaan precast Slab 3000x400x100 bh - 0.000 - - - - - -
22 Pemasangan precas Slab 3000x400x100 bh - 0.000 - - - - - -
23 Langsiran material jarak angkut 100 m m 240.00 0.062 25.000 - 25.00 0.006 - 0.006
24 Langsiran material jarak angkut 300 m m 3,031.00 1.555 268.000 99.000 367.00 0.107 0.051 0.157
25 Langsiran material jarak angkut 500 m m 3,093.00 1.745 260.000 200.000 460.00 0.147 0.113 0.259
0 0 0
III BANGUNAN AIR 0
1 Galian tanah biasa m3 62.80 0.013 21.300 11.300 32.60 0.004 0.002 0.007
2 Timbunan tanah dipadatkan sederhana (Stamper) m3 - 0.000 - - - - - -
3 Perataan sisa galian m3 - 0.000 - - - - - -
4 Bongkaran pasangan batu m3 - 0.000 - - - - - -
5 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) m3 - 0.000 - - - - - -
6 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) m3 - 0.000 - - - - - -
7 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m3 66.86 0.273 27.700 15.200 42.90 0.113 0.062 0.175
8 Bekisting m2 260.65 0.153 195.000 - 195.00 0.114 - 0.114
10 Pembesian kg 2,916.23 0.140 1394.600 570.000 1964.60 0.067 0.027 0.094
11 Plesteran 1 Pc : 3 Ps tebal 15 mm m2 - 0.000 - - - - - -
12 Pekerjaan Acian m2 302.56 0.078 290.000 - 290.00 0.075 - 0.075
13 Siaran 1 Pc : 2 Ps m2 302.56 0.043 290.000 - 290.00 0.041 - 0.041
14 Langsiran Material jarak angkut sampai dengan 500 m m - 0.000 - - - - - -
100.000 75.64 6.16 81.80
Diajukan Oleh :
Diketahui, Diperiksa/Disetujui Oleh : Penyedia Jasa
SNVT PJPA Pemali- Juana Konsultan Supervisi PT. Sangkuriang Karya Semesta
PEMANFAATAN AIR PEMALI - JUANA PT IKA ADYA PERKASA PT. Radiks Insan Persada (KSO)
Koordinator Pelaksanaan

Rendra Arif Yudiarso, ST, MT Haryono, ST Endi Subandi, ST


NIP. 198409022010121002 Koordinator Pengawas Koordinator Pelaksana
LAPORAN HARIAN
Hari / Tanggal : Senin, Monday, November 11, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW

3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW


4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW

D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 46.55 PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 24.24 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 22,347.30 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 37.22 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 14,738.25 8 Beton mutu K-175 Ready mix m3 24.00 PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 68.55 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 8.95 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 1,789.66 11 Wiremesh M8 kg 1,789.66 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 61.64 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 2.88 13 Bekisting m2 205.46 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 51.37 14 Dilatasi aspal pasir t= 2cm m 302.55 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 41.09 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 26,167.55 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 9.08 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas

LAPORAN HARIAN
Hari / Tanggal : Selasa, Tuesday, November 12, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW
3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW
4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW

D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 53.45 PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 38.94 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 32,456.56 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 54.06 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 21,405.40 8 Beton mutu K-175 Ready mix m3 38.55 PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 99.56 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 12.82 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 2,564.22 11 Wiremesh M8 kg 2,564.22 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 90.77 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 4.24 13 Bekisting m2 302.55 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 75.64 14 Dilatasi aspal pasir t= 2cm m 268.55 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 60.51 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 23,226.89 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 8.06 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas
LAPORAN HARIAN
Hari / Tanggal : Rabu, Wednesday, November 13, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW

3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW


4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW
D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 - PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 24.91 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 35,423.16 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 59.00 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 23,361.90 8 Beton mutu K-175 Ready mix m3 24.66 PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 108.66 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 15.13 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 3,026.55 11 Wiremesh M8 kg 3,026.55 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 162.77 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 7.60 13 Bekisting m2 542.55 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 135.64 14 Dilatasi aspal pasir t= 2cm m 235.66 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 108.51 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 20,382.23 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 7.07 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas

LAPORAN HARIAN
Hari / Tanggal : Kamis, Thursday, November 14, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW
3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW
4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW

D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 - PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 22.52 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 43,211.30 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 71.97 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 28,498.25 8 Beton mutu K-175 Ready mix m3 22.30 PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 132.55 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 4.93 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 985.66 11 Wiremesh M8 kg 985.66 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 30.67 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 1.43 13 Bekisting m2 102.22 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 25.56 14 Dilatasi aspal pasir t= 2cm m 423.33 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 20.44 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 36,613.81 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 12.70 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas
LAPORAN HARIAN
Hari / Tanggal :Jumat, Friday, November 15, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW

3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW


4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW
D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 - PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 - 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 34,409.30 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 57.31 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 22,693.25 8 Beton mutu K-175 Ready mix m3 - PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 105.55 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 5.61 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 1,121.22 11 Wiremesh M8 kg 1,121.22 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 39.07 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 1.82 13 Bekisting m2 130.22 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 32.56 14 Dilatasi aspal pasir t= 2cm m 289.60 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 26.04 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 25,047.50 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 8.69 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas

LAPORAN HARIAN
Hari / Tanggal : Sabtu, Saturday, November 16, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW
3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW
4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW

D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 - PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 24.80 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 35,713.30 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 59.49 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 23,553.25 8 Beton mutu K-175 Ready mix m3 24.55 PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 109.55 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 2.84 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 568.55 11 Wiremesh M8 kg 568.55 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 26.90 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 1.26 13 Bekisting m2 89.66 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 22.42 14 Dilatasi aspal pasir t= 2cm m 46.55 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 17.93 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 4,026.11 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 1.40 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas
LAPORAN HARIAN
Hari / Tanggal :Minggu, Sunday, November 17, 2019

1. Nama Proyek : REHABILITASI DI PEMALI PEMALI PAKET II


2. Nomer Kontrak : KU 0301/Ao7.9/Ao6.3/03/VI/2019
3. Tanggal Kontrak : 27 JUNI 2019

A. TENAGA KERJA B. CUACA C. PEKERJAAN


No. Nama Sat Jumlah No. Nama Jam (WIB) Lokasi No. Uraian Pekerjaan Sat Volume Lokasi
1 Pelaksana org 8.00 1 Cerah I PEKERJAAN PERSIAPAN
2 Survey org 3.00 1 Mobilisasi dan Demobilisasi m3 - PA, BJ , PM, TB, WD, WB, TW

3 Logistik org 1.00 2 Mendung 2 Kisdam m3 - PA, BJ , WD, WB, TW


4 Mandor org 25.00 3 Pengeringan / Dewatering m3 - PA, BJ , PM, TB, WD, WB, TW
5 Tukang org 48.00 3 Hujan 4 Dereksi Keet m3 - PA, BJ , PM, TB, WD, WB, TW
6 Pekerja org 365.00 m3 - PA, BJ , PM, TB, WD, WB, TW
7 Tenaga Harian org - 4 Hujan Deras - PEKERJAAN SALURAN DAN BANGUNAN AIR
1 Galian tanah dengan alat berat m3 - PA, BJ , PM, TB, WD, WB, TW
D. PERALATAN E. MATERIAL 2 Galian tanah biasa m3 - PA, BJ , PM, TB, WD, WB, TW

No. Nama Sat Volume No. Nama Bahan Sat Volume 3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 - PA, BJ , PM, TB, WD, WB, TW
1 Molen bh 8 1 Beton ( ready mix ) m3 10.04 4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 - PA, BJ , PM, TB, WD, WB, TW
2 Dolak bh 14 2 Semen kg 38,435.40 5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 - PA, BJ , PM, TB, WD, WB, TW
3 Cangkul bh 70 3 Pasir Beton/cor m3 64.02 6 perataan sisa galian m3 - PA, BJ , PM, TB, WD, WB, TW
4 Ember bh 200 4 Krikil Beton m3 - 7 Beton B0 m3 - PA, BJ , PM, TB, WD, WB, TW
5 Sendok Adukan bh 0 5 Air ltr 25,348.50 8 Beton mutu K-175 Ready mix m3 9.94 PA, BJ , PM, TB, WD, WB, TW
6 Waterpass bh 3 6 Besi Beton kg - 9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 117.90 BJ,TW, WD, WB,
7 Bak ukur bh 6 7 Kawat Bendrat kg 3.34 10 Pembesian kg - PA, BJ , WD, WB
8 Talang cor bh 0 8 Wiremesh kg 668.80 11 Wiremesh M8 kg 668.80 PA, BJ , PM, TB, WD, WB, TW
9 Linggis bh 9 9 Multiplek 12 Mm lbr 14.29 12 Besi angkur dia. 10 cm kg - PA, BJ , PM, TB, WD, WB, TW
10 10 Kaso 5/7 m3 0.67 13 Bekisting m2 47.64 PA, BJ , PM, TB, WD, WB, TW
11 11 Paku kg 11.91 14 Dilatasi aspal pasir t= 2cm m 114.06 PA, BJ , PM, TB, WD, WB, TW
12 Minyak Bekisting ltr 9.53 15 Bongkaran pasangan batu m3 - PA, BJ , PM, TB, WD, WB, TW
13 Aspal Curah kg 9,865.05 16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 - PA, BJ , PM, TB, WD, WB, TW
14 Pasir Pasang m3 3.42 17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 - PA, BJ , PM, TB, WD, WB, TW
18 Plesteran 1 pc 3 ps m2 - PA, BJ , PM, TB, WD, WB, TW
F. MULAI KERJA JAM : 08.00 - 17.00 WIB 19 Pekerjaan Acian m2 - PA, BJ , PM, TB, WD, WB, TW
20 Siaran 1 Pc 2 Ps m2 - PA, BJ , PM, TB, WD, WB, TW

G. INTRUKSI LAPANGAN H. TANDA TANGAN


Konsultan : Penyedia Jasa :
PT. Sangkuriang Karya Semesta
PT. Radiks Insan Persada (KSO)

Pelaksana
Konsultan Supervisi :
PT. IKA ADYA PERKASA

Pengawas Lapangan :

Pengawas
BBWS Pemali Juana
Pengawas Lapangan

I Made Aya Kendra


Pangawas
REKAPITULASI PROGRESS
REHABILITASI DI PEMALI PAKET II
VOLUME Volume Bobot ( % )
NO, URAIAN PEKERJAAN SAT. BOBOT SISA PROGRESS
KONTRAK MC 0 MC 1 (%) s/d Minggu Lalu Minggu ini s/d Minggu ini s/d Minggu Minggu ini s/d Minggu ini
Lalu
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 1.00 1.00 0.096 0.41 - 0.41 0.039 - 0.039 0.057
2 Kisdam m3 430.00 430.00 256.80 0.177 - - - - - - 0.177
3 Pengeringan / Dewatering jam 750.00 750.00 930.00 0.640 155.00 155.00 310.00 0.107 0.107 0.213 0.426
4 Dereksi Keet Ls 1.00 1.00 1.00 0.192 1.00 - 1.00 0.192 - 0.192 -

II DI PEMALI KANAN
1 Galian tanah dengan alat berat m3 15,462.18 - 29,667.35 2.206 12,569.50 9,369.50 21,939.00 0.935 0.697 1.631 0.575
2 Galian tanah biasa m3 3,935.01 5,135.69 3,474.37 0.710 3,175.49 - 3,175.49 0.649 - 0.649 0.061
3 Timbunan tanah dipadatkan sederhana ( stamper ) m3 1,165.76 1,165.76 3,319.56 0.388 - - - - - - 0.388
4 Houling + perataan sisa galian Jarak angkut 500 m s/d 1000 m m3 7,307.57 - 16,366.09 1.389 440.00 590.40 1,030.40 0.031 0.050 0.081 1.309
5 Houling + perataan sisa galian Jarak angkut 1000 m s/d 3000 m m3 4,705.45 - 14,404.55 2.185 - 999.60 999.60 0.067 0.152 0.218 1.966
6 perataan sisa galian m3 3,860.26 3,860.26 3,355.10 0.095 - - - - - - 0.095
7 Beton B0 m3 503.20 - - 0.000 - - - - - - -
8 Beton mutu K-175 Ready mix m3 8,315.99 6,281.82 5,192.53 21.592 4,672.64 203.40 4,876.04 19.430 0.846 20.276 1.316
9 Beton mutu K- 175 menggunakan molen (kapasitas =0,3 m3) m3 2,870.38 4,343.88 5,423.83 22.161 4,567.85 609.60 5,177.45 18.621 2.491 21.112 1.048
10 Pembesian kg 63,504.73 66,669.15 62,057.26 3.648 32,814.42 3,752.20 36,566.62 1.929 0.221 2.150 1.499
11 Wiremesh M8 kg 442,976.84 467,468.50 382,755.89 18.398 365,663.23 2,300.40 367,963.63 17.576 0.111 17.687 0.711
12 Besi angkur dia. 10 cm kg 2,232.28 252.62 2,271.38 0.145 196.35 - 196.35 0.013 - 0.013 0.132
13 Bekisting m2 17,693.85 28,372.65 20,882.96 12.225 18,295.53 321.30 18,616.83 10.710 0.188 10.898 1.327
14 Dilatasi aspal pasir t= 2cm m 874.59 10,116.68 7,191.52 4.529 3,681.72 - 3,681.72 2.319 - 2.319 2.210
15 Bongkaran pasangan batu m3 14,599.10 7,528.73 1,451.97 0.312 1,123.23 - 1,123.23 0.242 - 0.242 0.071
16 Pasangan batu kali 1 pc 4 ps (batu baru) m3 51.98 - 661.82 2.498 - 150.00 150.00 1.516 0.566 2.082 0.416
17 Pasangan batu kali 1 pc 4 ps (batu tersedia) m3 617.61 - 414.36 1.263 - 156.30 156.30 0.476 0.476 0.953 0.310
18 Plesteran 1 pc 3 ps m2 862.49 - 2,724.89 0.704 - - - 0.115 - 0.115 0.589
19 Pekerjaan Acian m2 862.49 - 2,724.89 0.389 - - - - - - 0.389
20 Siaran 1 Pc 2 Ps m2 1,735.08 - - 0.000 - - - - - - -
21 Pengadaan precast Slab 3000x400x100 bh 950.00 - - 0.000 - - - - - - -
22 Pemasangan precas Slab 3000x400x100 bh 950.00 - - 0.000 - - - - - - -
23 Langsiran material jarak angkut 100 m m 495.83 495.83 240.00 0.062 25.00 - 25.00 0.006 - 0.006 0.055
24 Langsiran material jarak angkut 300 m m 968.24 968.24 3,031.00 1.555 268.00 99.00 367.00 0.107 0.051 0.157 1.397
25 Langsiran material jarak angkut 500 m m 1,932.75 1,932.75 3,093.00 1.745 260.00 200.00 460.00 0.147 0.113 0.259 1.485

III BANGUNAN AIR


1 Galian tanah biasa m3 0.00 1,577.11 62.80 0.013 21.30 11.30 32.60 0.004 0.002 0.007 0.006
2 Timbunan tanah dipadatkan sederhana (Stamper) m3 0.00 271.06 - 0.000 - - - - - - -
3 Perataan sisa galian m3 0.00 1,118.40 - 0.000 - - - - - - -
4 Bongkaran pasangan batu m3 0.00 32.63 - 0.000 - - - - - - -
5 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) m3 0.00 51.98 - 0.000 - - - - - - -
6 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) m3 0.00 61.73 - 0.000 - - - - - - -
7 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m3 0.00 2.82 66.86 0.273 27.70 15.20 42.90 0.113 0.062 0.175 0.098
8 Bekisting m2 0.00 23.22 260.65 0.153 195.00 - 195.00 0.114 - 0.114 0.038
9 Wiremesh M8 kg 0.00 2,916.23 0.140 1,394.60 570.00 1,964.60 0.067 0.027 0.094 0.046
10 Pembesian kg 0.00 481.95 - 0.000 - - - - - - -
11 Plesteran 1 Pc : 3 Ps tebal 15 mm m2 0.00 221.38 302.56 0.078 290.00 - 290.00 0.075 - 0.075 0.003
12 Pekerjaan Acian m2 0.00 221.38 302.56 0.043 290.00 - 290.00 0.041 - 0.041 0.002
13 Siaran 1 Pc : 2 Ps m2 0.00 196.36 - 0.000 - - - - - - -
14 Langsiran Material jarak angkut sampai dengan 500 m m 0.00 90.46 - 0.000 - - - - - - -

100.00 75.64 6.16 81.80 18.20

RINCIAN PROGRESS
REHABILITASI DI PEMALI PAKET II
VOLUME Volume Bobot ( % )
BOB
NO, URAIAN PEKERJAAN SAT. SISA PROGRESS
KONTRAK MC 0 MC 1 s/d Minggu Lalu Minggu ini s/d Minggu ini Minggu ini s/d Minggu ini
I PEKERJAAN PERSIAPAN
1 Mobilisasi & Demobilisasi Ls 1.00 1.00 1.00 0.096 0.41 - 0.410 0.039 - 0.039 0.057
2 Kistdam m3 430.00 430.00 256.80 0.177 - - - - - - 0.177
3 Pengeringan/Dewatering Jam 750.00 750.00 930.00 0.640 155.00 155.00 310.00 0.107 0.107 0.213 0.426
4 Direksi Keet Ls 1.00 1.00 1.00 0.192 1.00 - 1.00 0.192 - 0.192 0.000
1.104 0.337 0.107 0.444 0.660
II PEKERJAAN SALURAN & BANGUNAN AIR
1 SALURAN SEKUNDER PEMALI KANAN
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 4,705.45 - - - - - - - - - 0.000
2 Galian tanah biasa m³ 174.24 174.24 169.60 0.035 155.38 - 155.38 0.032 - 0.032 0.003
3 Houling + Perataan sisa galian tanah jarak angkut 1.000 m s/d 3.000 m m³ - - - - - - - - - - 0.000
4 Beton B0 m³ - - - - - - - - - - 0.000
5 Beton mutu K-175 Ready mixed m³ 905.00 905.00 836.59 3.479 835.80 - 835.80 3.475 - 3.475 0.003
6 Pembesian Jaring Kawat (Wiremesh M8) kg 40,541.34 38,761.55 41,607.30 2.000 38,761.55 - 38,761.55 1.863 - 1.863 0.137
7 Besi Angkur dia. 10 mm kg 1,247.57 196.35 455.35 0.029 196.35 - 196.35 0.013 - 0.013 0.016
8 Bekisting m² 1,619.80 1,619.80 2,083.08 1.219 1,619.80 - 1,619.80 0.948 - 0.948 0.271
9 Dilatasi Aspal Pasir t = 2 cm m 549.82 549.82 672.86 0.424 549.82 - 549.82 0.346 - 0.346 0.077
10 Pengadaan precast Slab 3000x400x100 bh - - - - - - - - - - 0.000
11 Pemasangan precast Slab 3000x400x100 bh - - - - - - - - - - 0.000
12 Pembesian kg 9,130.02 4,955.42 8,941.84 0.526 6,401.42 1,456.00 7,857.42 0.376 0.086 0.462 0.064

III BANGUNAN AIR - - - -


1 Galian tanah biasa - - 13.94 0.003 10.00 - 10.00 0.002 - 0.002 0.001
2 Timbunan tanah dipadatkan sederhana (Stamper) - - - - - - - - - - 0.000
3 Perataan sisa galian - - - - - - - - - - 0.000
4 Bongkaran pasangan batu - - - - - - - - - - 0.000
5 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) - - - - - - - - - - 0.000
6 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) - - - - - - - - - - 0.000
7 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) - - 21.32 0.087 17.50 - 17.50 0.072 - 0.072 0.016
8 Bekisting - - 239.89 0.140 195.00 - 195.00 0.114 - 0.114 0.026
9 Wiremesh M8 - - 1,288.86 0.062 944.60 - 944.60 0.045 - 0.045 0.017
10 Pembesian - - - - - - - - - - 0.000
11 Plesteran 1 Pc : 3 Ps tebal 15 mm - - 302.56 0.078 290.00 - 290.00 0.075 - 0.075 0.003
12 Pekerjaan Acian - - 302.56 0.043 290.00 - 290.00 0.041 - 0.041 0.002
13 Siaran 1 Pc : 2 Ps - - - - - - - - - - 0.000
14 Langsiran Material jarak angkut sampai dengan 500 m - - - - - - - - - - 0.000
8.12 7.403 0.086 7.489 0.636
2 SALURAN SEKUNDER BOJONG
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 482.85 - - - - - - - - 0.000
2 Galian tanah biasa m³ 137.76 230.44 209.72 0.043 170.44 - 170.44 0.035 - 0.035 0.008
3 Timbunan tanah dipadatkan sederhana (Stamper) m³ - 130.53 - - - - - - - - 0.000
4 Perataan sisa galian m³ - 46.73 - - - - - - - - 0.000
5 Beton B0 m³ - - - - - - - - - - 0.000
6 Beton mutu K-175 Ready mixed m³ 374.06 374.06 271.63 1.130 264.52 - 264.52 1.100 - 1.100 0.030
7 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ - 110.57 231.03 0.944 153.21 45.00 198.21 0.626 0.184 0.810 0.134
8 Pembesian kg 2,684.35 2,990.20 5,701.96 0.335 3,639.38 550.30 4,189.68 0.214 0.032 0.246 0.089
9 Pembesian Jaring Kawat (Wiremesh M8) kg 10,589.12 17,136.68 19,179.97 0.922 16,478.78 - 16,478.78 0.792 - 0.792 0.130
10 Bekisting m² 946.20 1,210.20 1,097.16 0.642 1,041.10 - 1,041.10 0.609 - 0.609 0.033
11 Dilatasi Aspal Pasir t = 2 cm m² 313.08 398.88 286.60 0.180 - - - - - - 0.180
12 Bongkaran pasangan batu m³ 473.45 473.45 616.13 0.133 421.10 - 421.10 0.091 - 0.091 0.042
13 Besi Angkur dia. 10 mm kg 535.68 - 49.94 0.003 - - - - - - 0.003
4.33 - 3.467 0.216 3.683 0.649
3 SALURAN SEKUNDER TEGAL WULUNG
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 2,374.69 - 6,350.480 0.472 3,200.00 - 3,200.00 0.238 - 0.238 0.234
2 Galian tanah biasa m³ 529.78 529.78 429.278 0.088 290.00 - 290.00 0.059 - 0.059 0.028
3 Timbunan tanah dipadatkan sederhana (Stamper) m³ - 318.50 677.976 0.079 - - - - - - 0.079
Houling + Perataan sisa galian tanah jarak angkut 500 m s/d 1.000 m 2,440.713 0.207 360.00 360.00 720.00 0.031 0.031 0.061 0.146
4 Houling + Perataan sisa galian tanah jarak angkut 1000 m s/d 3.000 m m³ - - 3,050.891 0.463 440.00 440.00 880.00 0.067 0.067 0.133 0.329
5 Perataan sisa galian m³ - 456.40 610.178 0.017 - - - - - - 0.017
6 Beton B0 m³ - - - - - - - - - - 0.000
7 Beton mutu K-175 Ready mixed m³ 742.19 742.19 - - - - - - - - 0.000
8 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ 451.13 451.13 1,315.729 5.376 918.53 230.00 1,148.53 3.753 0.940 4.693 0.683
9 Pembesian Jaring Kawat (Wiremesh M8) kg 52,260.05 52,697.74 53,231.894 2.559 50,587.24 - 50,587.24 2.432 - 2.432 0.127
10 Bekisting m² 3,178.70 3,178.70 2,484.082 1.454 2,389.11 - 2,389.11 1.399 - 1.399 0.056
11 Dilatasi Aspal Pasir t = 2 cm m² 1,020.35 1,020.35 828.632 0.522 220.00 - 220.00 0.139 - 0.139 0.383
12 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) m³ - - - - - - - - - - 0.000
13 Bongkaran pasangan batu m³ - - - - - - - - - - 0.000
14 Plesteran 1 Pc : 3 Ps tebal 15 mm m² - - - - - - - - - - 0.000
15 Pekerjaan Acian m² - - - - - - - - - - 0.000
16 Siaran 1 Pc : 2 Ps m² - - - - - - - - - - 0.000
17 Langsiran Material jarak angkut sampai dengan 100 m m³ - 225.50 240.000 0.062 25.00 - 25.00 0.006 - 0.006 0.055
18 Langsiran Material jarak angkut sampai dengan 300 m m³ - 492.02 713.000 0.366 60.00 - 60.00 0.031 - 0.031 0.335
19 Langsiran Material jarak angkut sampai dengan 500 m m³ - - 1,280.000 0.722 200.00 200.00 400.00 0.113 0.113 0.226 0.496
20 Besi Angkur dia. 10 mm kg 2,451.58 - 410.30 0.026 - - - - - - 0.026

II PEKERJAAN BANGUNAN AIR


1 Galian tanah biasa m³ 82.27 82.27 12.24 0.003 - - - - - - 0.003
Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) 12.24 0.050 - - - - - - 0.050
Bekisting 3.60 0.002 - - - - - - 0.002
Pembesian Jaring Kawat (Wiremesh M8) 334.63 0.016 - - - - - - 0.016
2 Perataan sisa galian m³ 82.27 82.27 - - - - - - - - 0.000
3 Bongkaran pasangan batu m³ 29.10 12.10 - - - - - - - - 0.000
4 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) m³ 29.10 29.10 - - - - - - - - 0.000
5 Plesteran 1 Pc : 3 Ps tebal 15 mm m² 54.41 54.41 - - - - - - - - 0.000
6 Pekerjaan Acian m² 54.41 54.41 - - - - - - - - 0.000
7 Siaran 1 Pc : 2 Ps m² 25.80 25.80 - - - - - - - - 0.000
12.48 8.266 1.150 9.416 3.067
4 SALURAN SEKUNDER PAMENGGER
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 199.42 - 592.74 0.044 230.00 230.00 460.00 0.017 0.017 0.034 0.010
2 Galian tanah biasa m³ 73.42 73.42 77.22 0.016 73.42 - 73.42 0.015 - 0.015 0.001
3 Timbunan tanah dipadatkan sederhana (Stamper) m³ - 145.60 118.55 0.014 - - - - - - 0.014
4 Perataan sisa galian m³ - 29.10 474.19 0.013 - - - - - - 0.013
5 Beton B0 m³ - - - - - - - - - 0.000
6 Beton mutu K-175 Ready mixed m³ 164.44 164.44 183.58 0.763 164.44 - 164.44 0.684 - 0.684 0.080
7 Pembesian Jaring Kawat (Wiremesh M8) kg 6,924.75 6,900.61 8,553.60 0.411 6,866.11 - 6,866.11 0.330 - 0.330 0.081
8 Bekisting m² 440.54 440.54 463.29 0.271 440.54 - 440.54 0.258 - 0.258 0.013
9 Dilatasi Aspal Pasir t = 2 cm m² 167.90 167.90 128.88 0.081 57.90 - 57.90 0.036 - 0.036 0.045
10 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) m³ - - - - - - - - - - 0.000
11 Plesteran 1 Pc : 3 Ps tebal 15 mm m² - - - - - - - - - - 0.000
12 Pekerjaan Acian m² - - - - - - - - - - 0.000
13 Siaran 1 Pc : 2 Ps m² - - - - - - - - - - 0.000
Besi Angkur dia. 10 mm kg 364.39 - 79.40 0.005 - - - - - - 0.005

II PEKERJAAN BANGUNAN AIR


1 Galian tanah biasa m³ 12.71 12.71 - - - - - - - - 0.000
2 Timbunan tanah dipadatkan sederhana (Stamper) m³ 5.33 5.33 - - - - - - - - 0.000
3 Perataan sisa galian m³ 7.38 7.38 - - - - - - - - 0.000
4 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) m³ 2.65 2.65 - - - - - - - - 0.000
5 Plesteran 1 Pc : 3 Ps tebal 15 mm m² 6.38 6.38 - - - - - - - - 0.000
6 Pekerjaan Acian m² 6.38 6.38 - - - - - - - - 0.000
7 Beton mutu K-175 Ready mixed m³ 0.50 - - - - - - - - - 0.000
8 Bekisting m² 14.30 14.30 - - - - - - - - 0.000
9 Pembesian kg 30.24 30.24 - - - - - - - - 0.000
10 Siaran 1 Pc : 2 Ps m² 19.13 19.13 - - - - - - - - 0.000
1.62 1.340 0.017 1.357 0.262
5 SALURAN SEKUNDER TEMBELANG
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 279.00 - - - - - - - - - 0.000
2 Galian tanah biasa m³ 92.04 92.04 58.49 0.012 60.71 - 60.71 0.012 - 0.012 0.000
3 Timbunan tanah dipadatkan sederhana (Stamper) m³ - 85.95 - - - - - - - - 0.000
4 Perataan sisa galian m³ - 74.40 - - - - - - - - 0.000
5 Beton mutu K-175 Ready mixed m³ 135.30 135.30 141.97 0.590 135.30 - 135.30 0.563 - 0.563 0.028
6 Pembesian Jaring Kawat (Wiremesh M8) kg 6,076.73 6,050.82 7,036.05 0.338 6,050.81 - 6,050.81 0.291 - 0.291 0.047
7 Bekisting m² 368.16 368.16 350.95 0.205 287.56 - 287.56 0.168 - 0.168 0.037
8 Dilatasi Aspal Pasir t = 2 cm m² 118.46 118.46 98.55 0.062 88.00 - 88.00 0.055 - 0.055 0.007
9 Beton B0 m³ - - - - - - - - - 0.000
10 Besi angkur dia. 10 cm kg 283.94 - 59.73 0.004 - - - - - - 0.004

II PEKERJAAN BANGUNAN AIR


1 Galian tanah biasa m³ 11.59 11.59 - - - - - - - 0.000
2 Timbunan tanah dipadatkan sederhana (Stamper) m³ 1.90 1.90 - - - - - - - 0.000
3 Perataan sisa galian m³ 9.69 9.69 - - - - - - - 0.000
VOLUME Volume Bobot ( % )
BOBOT
NO, URAIAN PEKERJAAN SAT.
(%) s/d Minggu SISA PROGRESS
KONTRAK MC 0 MC 1 s/d Minggu Lalu Minggu ini s/d Minggu ini Minggu ini s/d Minggu ini
Lalu
4 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) m³ 7.98 7.98 - - - - - - - 0.000
5 Plesteran 1 Pc : 3 Ps tebal 15 mm m² 4.50 4.50 - - - - - - - 0.000
6 Pekerjaan Acian m² 4.50 4.50 - - - - - - - 0.000
7 Siaran 1 Pc : 2 Ps m² 13.50 13.50 - - - - - - - 0.000
8 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ 3.02 1.02 - - - - - - - 0.000
9 Pembesian kg 55.80 55.80 - - - - - - - 0.000
10 Bekisting m² 0.14 0.14 - - - - - - - 0.000
1.21 1.090 - 1.090 0.122
6 SALURAN SEKUNDER WANGAN BUI
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 3,600.12 - 7,900.91 0.587 3,550.00 3,550.00 7,100.00 0.264 0.264 0.528 0.060
2 Galian tanah biasa m³ 1,739.02 2,610.91 1,090.44 0.223 1,084.80 - 1,084.80 0.222 - 0.222 0.001
3 Timbunan tanah dipadatkan sederhana (Stamper) 896.75 0.105 - - - - - - 0.105
4 Houling + Perataan sisa galian tanah jarak angkut 500 m s/d 1.000 m m³ - - 8,070.75 0.685 - - - - - - 0.685
5 Houling + Perataan sisa galian tanah jarak angkut 1000 m s/d 3.000 m 4,035.38 0.612 - - - - - - 0.612
6 Perataan sisa galian m³ - 1,879.69 807.08 0.023 - - - - - - 0.023
7 Beton mutu K-175 Ready mixed m³ 1,874.69 1,874.69 2,388.11 9.930 1,907.14 203.40 2,110.54 7.930 0.846 8.776 1.154
8 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ 1,883.87 2,011.53 1,486.01 6.072 1,446.81 - 1,446.81 5.911 - 5.911 0.160
9 Pembesian Jaring Kawat (Wiremesh M8) kg 153,646.76 159,064.85 105,041.80 5.049 103,786.50 - 103,786.50 4.989 - 4.989 0.060
10 Bekisting m² 12,866.91 13,171.73 6,755.09 3.954 6,570.92 - 6,570.92 3.847 - 3.847 0.108
11 Pembesian kg 51,453.16 53,409.30 17,863.09 1.050 17,834.60 - 17,834.60 1.048 - 1.048 0.002
12 Beton B0 m³ - - - - - - - - - 0.000
13 Dilatasi Aspal Pasir t = 2 cm m² 4,183.21 4,282.28 2,949.60 1.858 1,754.40 - 1,754.40 1.105 - 1.105 0.753
14 Bongkaran pasangan batu m 7,055.28 7,055.28 835.84 0.180 702.13 - 702.13 0.151 - 0.151 0.029
15 Langsiran Material jarak angkut sampai dengan 300 m m³ - 800.25 1,300.00 0.667 60.00 - 60.00 0.031 - 0.031 0.636
16 Besi angkur dia. 10 cm kg 10,435.85 - 685.54 0.044 - - - - - - 0.044
17 Pasangan batu kali 1 pc 4 ps (batu baru) 661.82 2.498 401.65 150.00 551.65 1.516 0.566 2.082 0.416
18 Pasangan batu kali 1 pc 4 ps (batu tersedia) 414.36 1.263 156.30 156.30 312.60 0.476 0.476 0.953 0.310
19 Plesteran 1 pc 3 ps 2,724.89 0.704 444.30 - 444.30 0.115 - 0.115 0.589
20 Pekerjaan Acian 2,724.89 0.389 - - - - - - 0.389
-
II PEKERJAAN BANGUNAN AIR -
1 Galian tanah biasa m³ 151.35 151.35 10.20 0.002 - - - - - - 0.002
2 Perataan sisa galian m³ 151.35 151.35 - - - - - - - - 0.000
3 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) m³ 16.89 16.89 - - - - - - - - 0.000
4 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ 0.48 0.48 10.40 0.042 - 5.00 5.00 - 0.020 0.020 0.022
5 Bekisting m² 6.93 6.93 6.00 0.004 - - - - - - 0.004
6 Pembesian kg 87.81 87.81 - - - - - - - - 0.000
Pembesian Jaring Kawat (Wiremesh M8) kg - - 272.50 0.013 - 120.00 120.00 - 0.006 0.006 0.007
7 Plesteran 1 Pc : 3 Ps tebal 15 mm m² 81.68 81.68 - - - - - - - - 0.000
8 Pekerjaan Acian m² 81.68 81.68 - - - - - - - - 0.000
9 Siaran 1 Pc : 2 Ps m² 85.93 85.93 - - - - - - - - 0.000
10 Langsiran Material jarak angkut sampai dengan 500 m m³ 30.96 30.96 - - - - - - - - 0.000
35.95 27.605 2.178 29.783 6.170
7 SALURAN SEKUNDER WANGAN DALAM
I PEKERJAAN SALURAN
1 Galian tanah dengan alat berat m³ 3,820.65 - 14,823.22 1.102 5,589.50 5,589.50 11,179.00 0.416 0.416 0.831 0.271
2 Galian tanah biasa m³ 1,305.24 1,424.85 1,439.63 0.294 1,340.74 - 1,340.74 0.274 - 0.274 0.020
3 Houling + Perataan sisa galian tanah jarak angkut 500 m s/d 1.000 m m³ - - 5,854.62 0.497 - 230.40 230.40 - 0.020 0.020 0.477
Houling + Perataan sisa galian tanah jarak angkut 1000 m s/d 3.000 m 7,318.28 1.110 - 559.60 559.60 - 0.085 0.085 1.025
4 Timbunan tanah dipadatkan sederhana (Stamper) m³ - 64.86 1,626.28 0.190 - - - - - - 0.190
5 Perataan sisa galian m³ - 1,373.94 1,463.66 0.041 - - - - - - 0.041
6 Beton mutu K-175 Ready mixed m³ 1,909.04 2,086.14 1,370.65 5.699 1,365.44 - 1,365.44 5.678 - 5.678 0.022
7 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ 1,770.66 1,770.66 2,391.06 9.769 2,039.10 334.60 2,373.70 8.331 1.367 9.698 0.071
8 Pembesian Jaring Kawat (Wiremesh M8) kg 173,662.62 186,856.26 148,105.28 7.119 143,132.24 2,300.40 145,432.64 6.880 0.111 6.991 0.128
9 Bekisting m² 7,997.04 8,383.51 7,649.30 4.478 5,946.50 321.30 6,267.80 3.481 0.188 3.669 0.809
10 Pembesian kg 3,997.37 5,314.24 29,550.38 1.737 4,939.02 1,745.90 6,684.92 0.290 0.103 0.393 1.344
11 Beton B0 m³ - - - - - - - - - - 0.000
12 Dilatasi Aspal Pasir t = 2 cm m² 3,411.53 3,579.00 2,226.40 1.402 1,011.60 - 1,011.60 0.637 - 0.637 0.765
13 Langsiran Material jarak angkut sampai dengan 100 m m³ - 270.33 - - - - - - - - 0.000
14 Langsiran Material jarak angkut sampai dengan 300 m m³ - 476.22 1,018.00 0.522 148.00 99.00 247.00 0.076 0.051 0.127 0.395
15 Langsiran Material jarak angkut sampai dengan 500 m m³ - 1,132.50 1,813.00 1.023 - - - - - - 1.023
Besi angkur dia. 10 cm kg 5,913.43 56.27 531.13 0.034 - - - - - - 0.034
-
II PEKERJAAN BANGUNAN AIR - 0.003
1 Galian tanah biasa m³ 1,319.19 1,319.19 26.42 0.005 11.30 11.30 22.60 0.002 0.002 0.005 0.001
2 Timbunan tanah dipadatkan sederhana (Stamper) m³ 263.83 263.83 - - - - - - - - 0.000
3 Perataan sisa galian m³ 1,055.34 867.71 - - - - - - - - 0.000
4 Bongkaran pasangan batu m³ 32.63 20.53 - - - - - - - - 0.000
5 Pasangan batu kali 1 Pc : 4 Ps ( batu baru ) m³ 24.46 24.46 - - - - - - - - 0.000
6 Pasangan batu kali 1 Pc : 4 Ps ( batu tersedia 40%) m³ 32.63 32.63 - - - - - - - - 0.000
7 Beton mutu K-175 menggunakan molen (kapasitas = 0.35 m3) m³ 2.34 1.32 22.90 0.094 10.20 10.20 20.40 0.042 0.042 0.083 0.010
8 Bekisting m² 1.85 1.85 11.16 0.007 - - - - - - 0.007
Pembesian Jaring Kawat (Wiremesh M8) 1,020.24 0.049 450.00 450.00 900.00 0.022 0.022 0.043 0.006
9 Pembesian kg 308.10 308.10 - - - - - - - - 0.000
10 Plesteran 1 Pc : 3 Ps tebal 15 mm m² 74.41 74.41 - - - - - - - - 0.000
11 Pekerjaan Acian m² 74.41 74.41 - - - - - - - - 0.000
12 Siaran 1 Pc : 2 Ps m² 52.00 52.00 - - - - - - - - 0.000
13 Langsiran Material jarak angkut sampai dengan 500 m m³ 59.50 59.50 - - - - - - - - 0.000
35.17 26.129 2.405 28.537 6.636

Sub Jumlah 100.00 75.64 6.16 81.80 18.20


MONITORING PROGRESS
REHABILITASI DI PEMALI PAKET II

PROGRESS
PROGRESS MINGGU PROGRESS MINGGU SAMPAI DENGAN PROGRESS
RENCANA
NO, URAIAN PEKERJAAN LALU INI MINGGU INI TERTINGGAL
(%) (%) (%) (%)
(%)
I PEKERJAAN PERSIAPAN 1.104 0.34 0.11 0.44 (0.66)

II PEKERJAAN SALURAN
SALURAN
### SEKUNDER PEMALI KANAN 8.125 7.403 0.086 7.489 (0.636)

SALURAN
### SEKUNDER BOJONG 4.332 3.467 0.216 3.683 (0.649)

SALURAN
### SEKUNDER TEGAL WULUNG 12.483 8.266 1.150 9.416 (3.067)

SALURAN
### SEKUNDER PAMENGGER 1.619 1.340 0.017 1.357 (0.262)

SALURAN
### SEKUNDER TEMBELANG 1.212 1.090 - 1.090 (0.122)

SALURAN
### SEKUNDER WANGAN BUI 35.953 27.605 2.178 29.783 (6.170)

SALURAN
### SEKUNDER WANGAN DALAM 35.173 26.129 2.405 28.534 (6.639)

100.00 75.637 6.158 81.795 (18.205)