Anda di halaman 1dari 3

PT.

TIRTA INDONESIA, BANYUWANGI - JAGAD KONSTRUKSI

PLAFON FLAT ST
asumsi lebar 600 cm LOKASI BWG 1 LANTAI

panjang 600 cm ESTIMASI VOL 1,500 M2


modul 60 x 120 NILAI PEKJ PER ITEM 72,590 M2 JUAL 108,884,997
harga unit
1 WALL ANGLE merk 6.00 lonjor 5,140 /lonjor 30,841 BIAYA EXPEDISI 4 rit 1,300,000 5,200,000
2 MAIN RUNNER merk UFC 030 6.00 lonjor 15,888 /lonjor 95,327 JASA LANGSIR DARI EXP KE GUDANG 4 LS 500,000 2,000,000
3 CROSS RUNNER merk UFC 030 11.00 lonjor 15,888 /lonjor 174,766 JASA LANGSIR DARI GUDANG KE POS 1 LS 1,000,000 1,000,000
4 REGEL -
5 DRYWALL merk 1,080.00 pcs 65 70,200 BIAYA TRANSPORT PEKERJA
6 PAKU BETON 1 INCH merk 0.50 dos 18,000 9,000 - TRANSPORT LOKAL KE SBY 1 LS 300,000 300,000
7 ANGLE CLIP + PAKU RAMPSET 11.00 set 3,000 pcs 33,000 - TIKET PESAWAT / KA / BIS 6 PP 200,000 1,200,000
8 KONEKTOR MR TO CR merk 24.00 pcs 1,121 pcs 26,916 - TRANPORT LOKAL 1 LS 300,000 300,000
9 U CLAMP 11.00 pcs 1,121 pcs 12,336
10 ROD L rod 125 11.00 set 2,875 pcs 31,625 BIAYA TRANSPORT STAF
11 BOARD merk knauf 9 ST 13.00 lembar 43,925 /lembar 571,028 - TRANSPORT LOKAL KE SBY LS -
12 TAPE + COMPOUND merk 36.00 m1 4,000 144,000 - TIKET PESAWAT / KA / BIS 2 PP 300,000 600,000
13 JASA INSTALL 36.00 m2 21,000 /m2 756,000 - TRANPORT LOKAL 1 LS 300,000 300,000
14 JASA GOSOK 36.00 m2 1,000 /m2 36,000
BIAYA AKOMODASI PEKERJA 1 /BULAN 800,000 800,000
total 1,991,040 BIAYA AKOMODASI STAF 1 /BULAN 800,000 800,000
waste 5.00% 99,552
TOTAL modal 2,090,592 BIAYA OVERHEAD KANTOR 1% 108,884,997 1,088,850
M2 modal 58,072 GAJI SPV STANDBY ( SPV + QS ) 1 BULAN 5,000,000 5,000,000
OVERHEAD SEBELUM SERAHTERIMA 1 LS 1,000,000 1,000,000
eskalasi jasa akibat tingkat kesulitan ketinggian m2
decoratif m2 SEWA SCAFFOLDING /SET PER BULAN
- BAYAR LISTRIK KERJA LS
ASURANSI PEKERJA LS
margin 25.00% 14,518 APD ( helm / rompi ) 3 Org 120,000 360,000

M2 JUAL 72,590 128,833,847


85,889
BUNGA DISKONTO SKBDN / SCF 3.04 % 2,577
M2 JUAL FINAL 88,466

PLAFON FLAT WR
asumsi lebar 600 cm LOKASI BWG 1 LANTAI

panjang 600 cm ESTIMASI VOL 1,500 M2


modul 60 x 120 NILAI PEKJ PER ITEM 90,388 M2 JUAL 135,581,939
harga unit
1 WALL ANGLE merk 6.00 lonjor 5,500 /lonjor 33,000 BIAYA EXPEDISI 4 rit 1,300,000 5,200,000
2 MAIN RUNNER merk UFC 030 6.00 lonjor 17,000 /lonjor 102,000 JASA LANGSIR DARI EXP KE GUDANG 4 LS 500,000 2,000,000
3 CROSS RUNNER merk UFC 030 11.00 lonjor 17,000 /lonjor 187,000 JASA LANGSIR DARI GUDANG KE POS 1 LS 1,000,000 1,000,000
4 REGEL -
5 DRYWALL merk 1,080.00 pcs 65 70,200 BIAYA TRANSPORT PEKERJA
6 PAKU BETON 1 INCH merk 0.50 dos 18,000 9,000 - TRANSPORT LOKAL KE SBY 1 LS 300,000 300,000
7 ANGLE CLIP + PAKU RAMPSET 11.00 set 2,700 pcs 29,700 - TIKET PESAWAT / KA / BIS 6 PP 200,000 1,200,000
8 KONEKTOR MR TO CR merk 24.00 pcs 1,200 pcs 28,800 - TRANPORT LOKAL 1 LS 300,000 300,000
9 U CLAMP 11.00 pcs 1,200 pcs 13,200
10 ROD L rod 125 11.00 set 2,875 pcs 31,625 BIAYA TRANSPORT STAF
11 BOARD merk knauf 9 ST 13.00 lembar 83,000 /lembar 1,079,000 - TRANSPORT LOKAL KE SBY LS -
12 TAPE + COMPOUND merk 36.00 m1 4,000 144,000 - TIKET PESAWAT / KA / BIS 2 PP 300,000 600,000
13 JASA INSTALL 36.00 m2 21,000 /m2 756,000 - TRANPORT LOKAL 1 LS 300,000 300,000
14 JASA GOSOK 36.00 m2 1,000 /m2 36,000
BIAYA AKOMODASI PEKERJA 1 /BULAN 800,000 800,000
total 2,519,525 BIAYA AKOMODASI STAF 1 /BULAN 800,000 800,000
waste 5.00% 125,976
TOTAL modal 2,645,501 BIAYA OVERHEAD KANTOR 1% 135,581,939 1,355,819
M2 modal 73,486 GAJI SPV STANDBY ( SPV + QS ) 1 BULAN 5,000,000 5,000,000
OVERHEAD SEBELUM SERAHTERIMA 1 LS 1,000,000 1,000,000
eskalasi jasa akibat tingkat kesulitan ketinggian m2
decoratif m2 SEWA SCAFFOLDING /SET PER BULAN
- BAYAR LISTRIK KERJA LS
ASURANSI PEKERJA LS
margin 23.00% 16,902 APD ( helm / rompi ) 3 Org 120,000 360,000
M2 JUAL 90,388 155,797,758
103,865
BUNGA DISKONTO SKBDN / SCF 3.04 % 3,116
M2 JUAL FINAL 106,981

PARTISI GYPSUM 2 sisi 1 lapis


asumsi lebar 300 cm LOKASI BWG 1 LANTAI

panjang 300 cm ESTIMASI VOL 1,500 M2


modul NILAI PEKJ PER ITEM 169,303 M2 JUAL 253,955,100
harga unit
1 RUNNER unggul knauf 7550 2.5 lonjor 31,500 /lonjor 78,750 BIAYA EXPEDISI 4 rit 1,300,000 5,200,000
2 M. STUD unggul knauf 7550 7 lonjor 33,500 /lonjor 234,500 JASA LANGSIR DARI EXP KE GUDANG 4 LS 500,000 2,000,000
JASA LANGSIR DARI GUDANG KE POS 1 LS 1,000,000 1,000,000
3 REGEL
4 DRYWALL merk 270.00 pcs 65 17,550 BIAYA TRANSPORT PEKERJA
5 PAKU BETON 1 INCH merk 0.50 dos 18,000 9,000 - TRANSPORT LOKAL KE SBY 1 LS 300,000 300,000
6 Sekrup & Fischer 15.00 set 2,700 pcs 40,500 - TIKET PESAWAT / KA / BIS 6 PP 200,000 1,200,000
- - TRANPORT LOKAL 1 LS 300,000 300,000
Rockwool ex. Roxul 60kg/m3 - lembar /lembar -
7 BOARD 1 12mm st knauf 3.50 lembar 61,000 /lembar 213,500 BIAYA TRANSPORT STAF
8 BOARD 2 12mm st knauf 3.50 lembar 61,000 /lembar 213,500 - TRANSPORT LOKAL KE SBY LS -
9 TAPE + COMPOUND merk 21.00 m1 4,000 84,000 - TIKET PESAWAT / KA / BIS 2 PP 300,000 600,000
10 JASA INSTALL 9.00 m2 30,000 /m2 270,000 - TRANPORT LOKAL 1 LS 300,000 300,000
11 JASA GOSOK 9.00 m2 1,000 /m2 9,000
BIAYA AKOMODASI PEKERJA 1 /BULAN 800,000 800,000
total 1,170,300 BIAYA AKOMODASI STAF 1 /BULAN 800,000 800,000
waste 5.00% 58,515
TOTAL modal 1,228,815 BIAYA OVERHEAD KANTOR 1% 253,955,100 2,539,551
M2 modal 136,535 GAJI SPV STANDBY ( SPV + QS ) 1 BULAN 5,000,000 5,000,000
OVERHEAD SEBELUM SERAHTERIMA 1 LS 1,000,000 1,000,000
eskalasi jasa akibat tingkat kesulitan ketinggian m2
decoratif m2 SEWA SCAFFOLDING /SET PER BULAN
- BAYAR LISTRIK KERJA LS
ASURANSI PEKERJA LS
margin 24.00% 32,768 APD ( helm / rompi ) 3 Org 120,000 360,000