Summary BQ
SUMMARY
RENCANA ANGGARAN BIAYA
PROJECT : Grand Wisata House
LOKASI : Bekasi
TAHUN : 2020
Page 1 of 1
B.1 BQ - Persiapan
SUMMARY
RENCANA ANGGARAN BIAYA - PRELIMINARIES
1 Site Cost
Sewa Kontrakan Pekerja 4.00 bln 1,765,250 7,061,000
Gudang Kerja 5.00 m³ 1,184,087 5,920,434
3 Akomodasi Proyek
Listrik dan Air Kerja 1.00 ls (by owner) -
Biaya Keamanan dan Izin Pekerjaan 1.00 ls (by owner) -
Biaya Kebersihan 1.00 ls (by owner) -
4 Safety - HSE
a. Peralatan K3 Safety Proyek 1.00 set 1,420,250 1,420,250
b. APAR 1.00 unit 256,450 256,450
5 Pekerjaan Bongkaran :
Bongkar Façade Dinding + Railling Perimeter Lantai 2 7.80 m² 37,451 292,117
Bongkar Dinding dan Jendela untuk Opening Pintu Lantai 2 2.50 m² 37,451 93,627
Bongkar Dinding dan Kisi-Kisi Hollow Lantai 2 19.50 m² 37,451 730,293
Bongkar Lantai Existing Lantai 2 49.02 m² 9,060 444,145
Bongkar Atap dan Rangka - Policarbonate / Spandek Lantai 2 140.85 m² 26,295 3,703,709
Bongkar Dak Atap Existing 4.80 m³ 736,858 3,536,917
6 Finalisasi Proyek
Permbersihan Proyek Final 1.00 ls 960,250 960,250
Page 1 of 1
B.2 Summary BQ Struktur
SUMMARY
RENCANA ANGGARAN BIAYA - STRUCTURAL WORKS
TOTAL
NO. URAIAN PEKERJAAN
HARGA
Page 1 of 1
B.2.a Detail BQ Struktur
RENCANA ANGGARAN BIAYA
STRUCTURAL WORKS
PROJECT : Grand Wisata House
LOKASI : Bekasi
TAHUN : 2020
Page 1 of 4
B.2.a Detail BQ Struktur
RENCANA ANGGARAN BIAYA
STRUCTURAL WORKS
PROJECT : Grand Wisata House
LOKASI : Bekasi
TAHUN : 2020
4 Pekerjaan Tangga :
Tangga Lantai 1 ke Lantai 2, 1 unit
- Beton K-225 1.26 m³ 1,323,200 1,666,888
- Besi Beton 138.73 kg 13,486 1,870,956
- Bekisting 12.30 m² 308,649 3,796,491
Page 2 of 4
B.2.a Detail BQ Struktur
RENCANA ANGGARAN BIAYA
STRUCTURAL WORKS
PROJECT : Grand Wisata House
LOKASI : Bekasi
TAHUN : 2020
4 Pekerjaan Tangga :
Tangga Lantai 2 ke Lantai 3, 1 unit
- Beton K-225 1.26 m³ 1,323,200 1,666,888
- Besi Beton 138.73 kg 13,486 1,870,956
- Bekisting 12.30 m² 308,649 3,796,491
Page 3 of 4
B.2.a Detail BQ Struktur
RENCANA ANGGARAN BIAYA
STRUCTURAL WORKS
PROJECT : Grand Wisata House
LOKASI : Bekasi
TAHUN : 2020
Page 4 of 4
7. II. a. BoQ STRUKTUR
Page 1 of 2
7. II. a. BoQ STRUKTUR
Page 2 of 2
B.3. Summary BQ Architectural
SUMMARY
RENCANA ANGGARAN BIAYA - ARCHITECTURAL WORKS
SUB- TOTAL
NO URAIAN PEKERJAAN
TOTAL HARGA
Page 1 of 1
B.3.A Detail BQ Architectural
3 Pek. Façade :
Façade Kisi - Kisi Partisi Kayu Area Balkon Belakang 8.10 m² 530,289 4,295,345
Façade Jendela Floor Glass 8.10 m² 594,208 4,813,081
4 Pek. Kolom dan Balok Praktis untuk Opening Pintu Jendela 10.70 m' 126,902 1,357,856
4 Pek. Kolom dan Balok Praktis untuk Opening Pintu Jendela 25.60 m' 126,902 3,248,701
Page 1 of 6
B.3.A Detail BQ Architectural
Pek. Homogeneous Tile uk. 60x60 cm, Area Kitchen & Dining Room 49.02 m² 300,698 14,740,195
Pek. Vinyl , Area Corridor 2.12 m² 294,460 624,255
Pek. Vinyl , Area Storage 6.63 m² 294,460 1,952,270
Pek. Vinyl , Area Balkon Belakang 5.83 m² 294,460 1,716,702
Pek. Lantai Conwood, Area Balkon Belakang 4.20 m² 443,321 1,861,947
Page 2 of 6
B.3.A Detail BQ Architectural
Page 3 of 6
B.3.A Detail BQ Architectural
1 -
Page 4 of 6
B.3.A Detail BQ Architectural
4 Pek. List Cornice Plafond Cornice Gypsum 54.78 m' 30,872 1,691,143
3 Pek. List Cornice Plafond Cornice Gypsum 45.84 m' 30,872 1,415,151
Page 5 of 6
B.3.A Detail BQ Architectural
1 Pek. Railling Balkon Belakang H = 900 mm Kaca Bening 12 mm 5.16 m' 990,473 5,110,840
2 Pek. Railling Sisi Tangga H = 900 mm Kaca Bening 12 mm 2.76 m' 990,473 2,733,705
3 Pek. Railling Tangga (2 sisi) Lantai 2 - 3 Kaca Bening 12 mm 10.24 m' 990,473 10,147,393
Page 6 of 6
B.4 Summary BQ MEP
SUMMARY
RENCANA ANGGARAN BIAYA - M.E.P. WORKS
Page 1 of 1
B.4.a Detail BQ MEP
Page 1 of 4
B.4.a Detail BQ MEP
PL.B.4 INSTALASI PIPA AIR KOTOR DAN AIR HUJAN LANTAI 3 5,125,127
Pengadaan dan pemasangan pipa air kotor dan hujan,
lengkap dengan fitting, support, joint, etc :
1 Pipa PVC D ex. Wavin, Pipa Ø 3" (80 mm) 24.59 m' 92,395 2,272,000
2 Pipa PVC D ex. Wavin, Pipa Ø 4" (100 mm) 20.60 m' 123,938 2,553,127
3 Fitting dan Aksesories 1.00 ls 300,000 300,000
Page 2 of 4
B.4.a Detail BQ MEP
Page 3 of 4
B.4.a Detail BQ MEP
Page 4 of 4