Anda di halaman 1dari 3

Perhitungan Volume Panjang 69 M

Vol 1 0.73 m3
w1 30 cm Vol 2 0.285 m3
Vol Tot 1.015

H1 100 cm Vol Talud 1


H2 40 cm wa 30 ((W3 x H2)+(W1 x H1)+(1/2 x W4 x H1))xPanjang Talud
((0,7 x 0,4) + (0,3 x 1) + (1/2 x 0,3 x 1))x69
50.37 Meter3
Ha 50 Cm
Hb 40 cm Vol Talud 2
((Wc x Hb)+(Wa x Ha)+(1/2 x Wd x Ha))xPanjang Talud
((0,4 x 0,4) + (0,3 x 0,5) + (1/2 x 0,06 x 0,5))x69
19.665

Volume Total
Vol Talud 1 + Vol Talud 2
w2 60 cm Wb 35 cm 70.035 Meter3
w3 70 cm Wc 40 cm
w4 30 cm Wd 6 cm

Berapen atau Perapihan

Luas Permukaan 2x Luas = 41.4


Lebar 0.3 M
Panjang 69 M
TOS
KODE HARGA SATUAN PEKERJAAN
ANALISA JENIS & URAIAN PEKERJAN KOEFISIEN SAT. Volume
HRG SAT(Rp) HARGA (Rp)
SNI - C.6.3 Pas. Pondasi Batu Belah 1 PC : 5 Psr M3 70.035
Batu Kali Belah 1.2 M3 84.042 195,000.00 16,388,190.00
Portland Cement 136 Kg 9524.76 1,480.00 14,096,644.80
Pasir Pasang 0.544 M3 38.09904 185,000.00 7,048,322.40
Pekerja 1.5 OH 42,000.00
Tukang Batu 0.75 OH 47,000.00
Kepala Tukang 0.075 OH 52,000.00
Mandor 0.075 OH 52,000.00
SNI - E.6.19 Berapen 1 PC : 5 PP tb. 1,5 cm M2 41.4
Portland Cement 5.184 Kg 214.6176 1,480.00 317,634.05
Pasir Pasang 0.026 M3 1.0764 185,000.00 199,134.00
Pekerja 0.15 OH 42,000.00
Tukang Batu 0.075 OH 47,000.00
Kepala Tukang 0.008 OH 52,000.00
Mandor 0.008 OH 52,000.00
Total Biaya 38,049,925.25
Pembulatan 38,000,000,-

Kebutuhan
PC 9739.3776 Kg 194.78755
Batu Belah 84.042 M3
Pasir Pasang 39.17544 M3
83.4 195000 16263000
39.5 185000 7307500
195 74000 14430000

38000500