Nama Mahasiswa: Ilyas Jafar Ashidiq

NIM: 5190911101 (Ganjil)


Mata Kuliah: Rencana Anggaran Biaya
Kelas: E
Minggu ke: UTS
Judul Tugas: Volume Pekerjaan Galian

NO. URAIAN GAMBAR KERJA

3
3

5
6

7
PERHITUNGAN VOLUME PEKERJAAN

Volume Pekerjaan Galian Tanah Pondasi


Va = h x w x P
= 0.8 x 1 x 44.5
= 35.6 m3

Volume Pekerjaan Pasir Pondasi


Va = h x w x p
= 0.1 x 1 x 44.5
= 4.45 m3

Volume Pekerjaan Bouwplank


Vps = ( 900 + 900 +
+ 300 + 300 +
+ 350 + 125 +
+ 350 + 250 +
= 5723 cm
= 57.23 m

Volume Pekerjaan Urugan Pasir Dibawah Lantai


Vc = h x 1 x p
= 0.1 x 1 x 80.75
= 8.075 m3

Volume Pekerjaan Pasangan Pondasi


Va = a + b x h
2
= 0.3 + 0.7 x 0.7
2
= 0.5 x 0.7 x 44.5
= 15.58 m3
Volume Pekerjaan Urugan Tanah Kembali ke Sisi Pondasi
Vd = V galian tanah - V pasangan batu kali
V urungan pasir dibawah pondasi

= 35.6 - 15.58 + 8.075


= 28.1 m3

Volume Pekerjaan Urugan Tanah Untuk Peninggian Lantai


Ve = ( h x L )
= ( 0.3 x 80.75 )
( 35.6 m3 - 28.1
= 24.225 - (
= 16.725 m3

NB : Peninggian Lantai 30 cm
N

asi

600
125
250
1273 )
Lantai

si
x p

x 44.5
Sisi Pondasi
+

ggian Lantai
- St
-
m3 )
7.5 )
Nama Mahasiswa: Ilyas Jafar Ashidiq
NIM: 5190911101 (Ganjil)
Mata Kuliah: Rencana Anggaran Biaya
Kelas: E
Minggu ke: UTS
Judul Tugas: Volume Pekerjaan Beton

NO. URAIAN GAMBAR KERJA

1
2
PERHITUNGAN VOLUME PEKERJAAN

Pekerjaan beton
A.SLOOF
VA= b x h x
= 0.15 x 0.2 x
= 1.335 m³

v beton= 0.15 x 0.2 x


kebutuhan besi ꬿ10= 44m/12 = 3,6 m
= 3.6 x 4bh
= 15.6 = 16bh
kebutuhan besi ꬿ8= 1 buah cincin memerlukan 75 cm besi ꬿ8
= untuk 44 m sloof memerlukan
= atau 193 bh x0,75mx12m=

B.KOLOM
VA= b x h x
= 0.12 X 0.12 X
= 0.756 m3

C.VOLUME RING BALOK


VA= b x h x
= 0.15 x 0.12 x
= 0.801 m3
D.VOLUME RING BALOK LATAI
VB= b x h x
= 0.15 x 0.12 x
= 0.387 m3

E.VOLUME BETON LANTAI KERJA


Vlk = t x L
= 0.05 x 80.75
= 4.0375 m3

F. VOLUME RABAT BETON


VR = b x t
= 0.1 x 0.1
= 0.066 m3
E PEKERJAAN

ton

p
44.5

44.5 = 1,32m3

44/0,15 = 293bh cincin


19 btg

ƩK
3.5 X 15

BALOK
p
44.5
LOK LATAI
p
21.5

NTAI KERJA

T BETON
x p
x 6.6
Nama Mahasiswa: Ilyas Jafar Ashidiq
NIM: 5190911101 (Ganjil)
Mata Kuliah: Rencana Anggaran Biaya
Kelas: E
Minggu ke: UTS
Judul Tugas: Volume Pekerjaan Atap

NO. URAIAN GAMBAR KERJA PERHITUNGAN VOLUME PEKERJ

Nok, Gording, Jurai, Murplat, Drack Balk, ka


NOK = 3
GORDING = 3
3
MURPLAT = 9
3
JURAI = √  ( ( 0.5 L tan α)2 + 0.5 (L2)  )
= √  ( ( 0.5x6x tan 30)2 + 0.5 (62)  )
= 3.875
= 4.95
Drack Balk = 1.5

Panjang total (kelipatan 4m kayu)


Luas Penampang kayu 8/12
Volume = luas penampang x panjang tot

Kuda-Kuda 8/12

p = 6
= 4.738
= 20.186
= 80.744

p ikatan angin =
=
Panjang total (kelipatan 4m kayu)
Luas Penampang kayu 8/12
Volume = luas penampang x panjang total

Volume Total Kebutuhan Kayu 8

v = Volume Nok, Gording, Jurai, Murplat, Drack Balk


= 1.06272
= 1.9050624

1
Usuk dan Reng
1

Luas datar atap =


=
=
Sudut miring atap =
Cosinus sudut atap =
Luas Bidang Atap (miring) =

Volume = Luas Bidang Atap =

Penutup Atap / Genteng

Volume = Luas Bidang Atap =

Genteng Bubungan

Volume = Panjang Nok + Panjang Jurai Luar

Papan Ruiter

Volume = Panjang Genteng Bubungan

Papan Lisplang

Volume = panjang keliling tepi atap =


=
=

Kayu Bengkirai 8/12 Usuk Bengkirai 5/7


5

7
7

8
9
PERHITUNGAN VOLUME PEKERJAAN

Gording, Jurai, Murplat, Drack Balk, kayu 8/12


+ 3 = 6
+ 6 + 6 +
+ 3 + 3 = 24
+ 9 + 6 +
+ 3 + 6 = 36
2 2
.5 L tan α)  + 0.5 (L )  ) + Panjang Tritisan
2 2
5x6x tan 30)  + 0.5 (6 )  ) + √  ( ( 0.5x1x tan 30)2 + 0.5 (12)  )
3.875 + 1.075
4.95 x 6 (Jumlah Jurai) = 29.7
+ 1.5 x 5 = 15

Panjang total (kelipatan 4m kayu) = 110.7 m


Luas Penampang kayu 8/12 = 0.0096 m2
Volume = luas penampang x panjang total = 1.06272 m3

Kuda-Kuda 8/12

+ 1.732 + 4.738 +
+ 1.489 + 1.489
x 4 Jumlah Kuda-kuda
m

3.5 x 2 Jumlah Ikatan Angin


7 m
kelipatan 4m kayu) = 87.744 m
mpang kayu 8/12 = 0.0096 m2
ampang x panjang total = 0.8423424 m3

Volume Total Kebutuhan Kayu 8/12

k, Gording, Jurai, Murplat, Drack Balk + Volume Kuda-kuda


1.06272 + 0.8423424
1.9050624 m3
Usuk dan Reng

11 x 8 +
8 x 4
120 m2
30 °
0.155
774.2 m2

775 m2

Penutup Atap / Genteng

775 m2

Genteng Bubungan

= 6+ 24.75
= 30.75 m

Papan Ruiter

= 30.75 m

Papan Lisplang

8+ 11 + 11 +
8 + 4 + 4
46 m

Reng Bengkirai 3/4 Bubungan Keramik Genteng Keramik