BAB VII
PENJADWALAN MICROSOFT PROJECT
Berikut proses pemasukan data penjadwalan pada Microsoft project
Task
Mode
4

4
-
Task Name
PROYEK FLYOVER CIBITUNG -CILINCING
< Start
Duration

1 day
Start
734.42 days Mon 5/4/ 20
Mon 5/4/ 20
Finish
Fri 2/ 24/ 23
Mon 5/4/20
Predecess Cost
Rp503,458, 314,135
RpO

* Pekerjaan Start
* PEKERJAAN PERSIAPAN
1 day
45.65 days
Mon 5/4/ 20
Tue 5/ 5/ 20
Mon 5/4/ 20
Tue 7/ 7/ 20
RpO
Rp5,921,259, 799
4 Pembersihan Lapangan 3.31 days Tue 5/5/ 20 Fri 5/8/ 20 3 Rp3.246.926
4 Pembuatan Akses Jalan Kerja 25.24 days Fri 5/8/ 20 Fri 6/12/ 20 5 Rp3.130.137.03S

^4
-
-
Pembuatan Pagar Penutup Proyek
PEKERJAAN PEMANCANGAN
Pemancangan Tiang Pancang Section 1
17.1 days Fri 6/12/ 20
101.41 days Tue 7/ 7/ 20
101.41 days Tue 7/7/ 20
Tue 7/7/ 20
Thu 11/ 26/ 20
Thu 11/ 26/ 20
6

7
Rp 2 787 S75:835
? ;

Rp3.406,524,631
Rpl.S48r 523 r 817

4
- Pemancangan Tiang Pancang Section 2
PEKERJAAN GALIAN
GaHan Tanah Section 1
Galian Tanah Section 2
85.47 days
16.69 days
0.75 days
0.91 days
Tue 7/7/ 20 Wed 11/4/ 20
Wed 11/4/ 20 Thu 11/ 26/ 20
Thu 11/ 26/ 20 Thu 11/ 26/ 20
Wed 11/4/ 20 Thu 11/5/ 20
7

9
10
Rp 1.558.000.814
Rpll, 552,683
Rp5J22 446
Rp6.330.237
t

4 * PEKERJAAN PONDASI 91.79 days Thu 11/ 5/ 20 Fri 3/12/21 Rp21,375,861,192

* Pekeijaan Lantai Kerja Section 1 2.83 days Thu 11/ 26/ 20 Tue 12/1/ 20 12 Rpl 33:178:660
4 Pekeijaan Lantai Kerja Section 2 3.96 days Thu 11/5/ 20 Tue 11/10/ 20 13 RplS6:190.053
4 Pembesian Pile Cap Section 1 43.87 days Tue 12/1/ 20 Mon 2/1/ 21 15 Rp6,716,403.093

-» Pembesian Pile Cap Section 2 37.19 days Tue 11/10/ 20 Fri 1/1/ 21 16 Rp5.692.990.41S
4 Pemasangan Bekisting Pile Cap Section 1 13.71 days Mon 2/1/ 21 Fri 2/19/ 21 17 Rp392.717.679
4 Pekeijaan Bekisting Pile Cap Section 2 12.47 days Fri 1/1/ 21 Tue 1/19/ 21 18 Rp35 7.154.629
4 Pengecoran Pile Cap Section 1 15.6 days Fri 2/19/ 21 Fri 3/12/ 21 19 Rp4.643J 5S.544
Pengecoran Pile Cap Section 2 Rp3J 53:96S:116

-
4 10.94 days Tue 1/19/ 21 Wed 2/3/21 20

PEKERJAAN PIER 82.62 days Wed 2/ 3/ 21 Mon 5/31/ 21 Rp 38,186,644,191


Pembesian Pier Section 1 39.33 days Fri 3/12/ 21 Fri 5/ 7/ 21 21 Rpl 6.19S.846.415
Pembesian Pier Section 2 38.12 days Wed 2/3/ 21 Mon 3/ 29/ 21 22 Rp15.700.009.117
» Pemasangan Bekisting Pier Section 1 12.02 days Fri 5/7/ 21 Tue 5/ 25/21 24 Rp1.001.416.662
Pemasangan Bekisting Pier Section 2 11.24 days Mon 3/ 29/ 21 Tue 4/13/ 21 25 Rp935.S10.427
Pengecoran Pier Section 1 4.04 days Tue 5/ 25/ 21 Mon 5/ 31/ 21 26 Rp2.39S.178.975
Pengecoran Pier Section 2 3.29 days Tue 4/13/ 21 Mon 4/19/ 21 27 Rpl 952 3S2,595
; ;

4 PEKERJAAN ABUTMENT 78.33 days Mon 4/19/ 21 Thu 8/5/ 21 Rp 5,563,411,831


4 Pembesian Abutmen Section 1 14.3 days Mon 5/ 31/ 21 Fri 6/18/ 21 28 Rp2, lSS.561.4 S6
4 Pembesian Abutmen Section 2 8.82 days Mon 4/19/ 21 Fri 4/ 30/ 21 29 Rp1.350.045.164
^
4 Pemasangan Bekisting Abutmen Section 1 6.59 days Fri 6/18/ 21 Tue 6/ 29/ 21 31 RplSS 6SS:169
;

'4 Pemasangan Bekisting Abutmen Section 2 4.64 days Fri 4/30/ 21 Thu 5/6/ 21 32 Rpl 32.919.439
Pengecoran Abutmen Section 1 2.01 days Tue 6/ 29/ 21 Thu 7/1/ 21 33 Rp6S 7.524.173
4

4 Pengecoran Abutmen Section 2 2.04 days Thu 5/6/21 Mon 5/10/ 21 34 Rp696.395 2 S9 _
*4 Urugan Abutmen Section 1 25.46 days Thu 7/1/ 21 Thu 8/5/21 35 RplS 7.331.545
4 Urugan Abutmen Section 2 17.93 days Mon 5/10/ 21 Thu 6/3/ 21 36 Rp131.946.566
4
' PEKERJAAN PIER HEAD 146.32 days Thu 6/ 3/ 21 Fri 12/24/ 21 Rp86,557,914,566
4 Pembesian Pier Had Section 1 57.5 days Thu 8/5/ 21 Tue 10/ 26/ 21 37 Rp29.604.364.740
“4 Pembesian Pier Had Section 2 48.97 days Thu 6/3/ 21 Wed 8/11/ 21 38 Rp25.212.144.S46
4 Pemasangan Bekisting Pier Had Section 1 25.5 days Tue 10/ 26/ 21 Tue 11/30/ 21 40 Rp6.369.S99.4S6
4 Pemasangan Bekisting Pier Had Section 2 27.08 days Wed 8/11/ 21 Fri 9/17/ 21 41 Rp6:765:S07.S66
4 Pengecoran Pier Section 1 18.42 days Tue 11/30/ 21 Fri 12/ 24/ 21 42 Rpl 0.92 S.384.135
•4 Pengecoran Pier Section 2 12.94 days Fri 9/17/ 21 Wed 10/6/ 21 43 Rp 7.677J 13.493
4 PEKERJAAN WINGWALL 59.19 days Wed 10/6/ 21 Tue 12/ 28/21 Rp241,294,949
4 Pembesian Wing Wall Section 1 1.13 days Fri 12/ 24/ 21 Tue 12/ 28/ 21 44 Rp57.778.731
4 Pembesian Wing Wall Section 2 1.05 days Wed 10/6/ 21 Thu 10/7/ 21 45 Rp53.594.37 S

24
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
115
Instltur
FAKULTAS VOKASI
INSTITUT TEKNOLOGI SEPULUH NOPEMBER
Tcknologi
SepuJuh Nopember

Task
Mode Task Name Duration Start Finish Predecess Cost
Pemasangan Bekisting Wing Wall Section 0.56 days Tue 12/ 28/ 21 TUG 12/ 28/ 21 47 Rpl 6.101.S06
1
-4
2
Pemasangan Bekisting Wing Wall Section 0.51 days Thu 10/7/ 21 Fri 10/8/ 21 48 Rp14,691,S26

Pengecoran Wing Wall Section 1 0.17 days Tue 12/ 28/ 21 Tue 12/ 28/ 21 49 Rp51, S37,727

* P engecoran Wing Wall Section 2 0.16 days Fri 10/8/ 21 Fri 10/8/21 50 Rp 47 290.4Sl
;

' PEKERJAAN ELASTOMER BEARING PAD 57.54 days Fri 10/8/ 21 Tue 12/ 28/ 21 Rpl,030,819,522
4 Pengecoran dudukan Elastomer 0.03 days Tue 12/ 28/ 21 Tue 12/ 28/ 21 51 Rp9.S0S.S74
Bearingpad Section 1
4 Pengecoran dudukan Elastomer 0.03 days Fri 10/8/ 21 Fri 10/8/ 21 52 RpS 596r 967
;

Bearingpad Section 2
Pemasangan Rubber Pad Section 1 0.04 days Tue 12/ 28/ 21 Tue 12/ 28/ 21 54 Rp552,412,333
4 Pemasangan Rubber Pad Section 2 0.03 days Fri 10/8/ 21 Fri 10/8/ 21 55 Rp460.001.34S
* PEKERJAAN GIRDER 17.93 days Tue 12/ 28/ 21 Fri 1/ 21/22 Rp86,013,808,600
Erection Girder Section 1 17.93 days Tue 12/ 28/ 21 Fri 1/ 21/ 22 56,57 Rp 46.932.4S3.SOO
4

4 Erection Girder Section 2 14.93 days Tue 12/ 28/ 21 Tue 1/18/ 22 56,57 Rp39.OSl 324.SOO_
"4 ' PEKERJAAN DIAFRAGMA 46.11 days Fri 1/ 21/ 22 Mon 3/ 28/22 Rpl2,753,634,714
4 Pembesian Diafragma Section 1 16.17 days Fri 1/ 21/ 22 Tue 2/15/ 22 59,60 Rpl.662.S09.944
4 Pembesian Diafragma Section 2 15.15 days Fri 1/ 21/ 22 Fri 2/11/ 22 59,60 Rpl ,55S,199,959
Pemasangan Bekisting Diafragma Section 17.91 days Tue 2/15/ 22 Thu 3/10/ 22 62,63 Rp3,S 56, SS0,245
1
Pemasangan Bekisting Diafragma Section 15.93 days Tue 2/15/ 22 Tue 3/8/ 22 62,63 Rp3,432,100,225
2
4 Pengecoran Diafragma Section 1 12.03 days Thu 3/10/ 22 Mon 3/ 28/ 22 64,65 Rpl , lS9,142,024
4 Pengecoran Diafragma Section 2 10.67 days Thu 3/10/ 22 Fri 3/ 25/ 22 64,65 Rp1.054.502.317
'4 ' PEKERJAAN DECK SLAB 84.67 days Mon 3/ 28/22 Mon 7/ 25/22 Rp41,688,481,062
4 Pembesian Deck Slab Section 1 70.5 days Mon 3/ 28/ 22 Tue 7/5/22 66.67 Rpl 4,3S9,S31,490
Pembesian Deck Slab Section 2 70.81 davs Mon 3 / 28 / 22 Tue 7/5/ 22 66.67 Rp 14,453,7 IS,676
4 Pengecoran Diafragma Section 1 12.03 days Thu 3/10/ 22 Mon 3/ 28/ 22 64,65 Rp 1.189.142.024
4 Pengecoran Diafragma Section 2 10.67 days Thu 3/10/ 22 Fri 3/ 25/ 22 64,65 Rp1,054,502,317
'4 ^ PEKERJAAN DECK SLAB 84.67 days Mon 3/28/ 22 Mon 7/ 25/22 Rp41,688,481,062
4 Pembesian Deck Slab Section 1 70.5 days Mon 3/ 28/ 22 Tue 7/5/ 22 66,67 Rpl4,3S9,S31,490

* Pembesian Deck Slab Section 2 70.81 days Mon 3/ 28/ 22 Tue 7/5/ 22 66,67 Rp 14,453,7 IS,676
4 Pemasangan Bekisting Deck Slab Section 3.27 days Tue 7/5/ 22 Mon 7/11/ 22 70,69 Rpl 35.05S.lSS
1
4 Pemasangan Bekisting Deck Slab Section 3.51 days Tue 7/5/ 22 Mon 7/11/ 22 70,69 Rpl 45.171.750
2
4 Pengecoran Deck Slab Section 1 10.17 days Mon 7/11/ 22 Mon 7/ 25/ 22 72, 71
_
Rp6 229.671 369 _
4 Pengecoran Deck Slab Section 2 10.35 days Mon 7/11/ 22 Mon 7/25/ 22 72, 71 Rp6,335,029.589
4
' PEKERJAAN PELAT INJAK 26.56 days Mon 7/ 25/ 22 Wed 8/ 31/ 22 Rp 330,807,077
- 4 Pembesian Pelat Injak Section 1 0.07 days Mon 7/ 25/ 22 Mon 7/ 25/22 74, 73 Rp3.596.S65
4 Pembesian Pelat Injak Section 2 0.05 days Mon 7/ 25/ 22 Mon 7/ 25/ 22 74, 73 Rp2,646,321
Pemasangan Bekisting Pelat Injak Section 24.86 days Mon 7/ 25/ 22 Mon 8/29/22 76, 77 Rp103.503,693
1
Pemasangan Bekisting Pelat Injak Section 17.38 days Mon 7/ 25/ 22 Thu 8/18/ 22 76, 77 Rp72,370,595
2
4 Pengecoran Pelat Injak Section 1 1.63 days Mon 8/ 29/ 22 Wed 8/31/ 22 78, 79 RpS7.505.24?
4

4
-
-
4

4
- Pengecoran Pelat Injak Section 2
PEKERJAAN PARAPET & BARIER
Pembesian Parapet & Barrier Section 1
Pembesian Parapet & Barrier Section 2
1.14 days
32.92 days
0.1 days
0.11 days
Mon 8/ 29/ 22 Tue 8/ 30/ 22
Wed 8/ 31/ 22 Mon 10/17/ 22
Wed 8/31/22 Wed 8/31/ 22
Wed 8/31/ 22 Wed 8/31/ 22
78, 79

80,81
80,81
Rp61.1S4.356
Rpl95,456, 077,172
RpS72 217
Rp934,5 IS
_
- 4 Pekerjaan Bekisting Parapet & Barrier
Section 1
5.81 days Wed 8/31/ 22 Thu 9/8/ 22 84,83 Rp313,477,045

- 4 Pekerjaan Bekisting Parapet & Barrier


Section 2
6.23 days Wed 8/31/ 22 Thu 9/8/ 22 84,83 Rp335,S6S,262

25
Pabrikasi Tulangan Pile Cap
Pabrikasi Tulangan Bored Pile Section 1
Section 1

Pekerjaan Tiang Pekerjaan


Pancang Galian Tanah
Section 1 Section 1

Pekerjaan Pembersihan Pembuatan Akses Pagar Penutup


Persiapan Lapangan Jalan Kerja Proyek

START Pekerjaan Tiang Pekerjaan


Pancang Galian Tanah
Section 2 Section 2

Pabrikasi Tulangan Pile Cap


Section 2
Pabrikasi Tulangan Bored Pile
Section 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 1 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pabrikasi Bekisting Pabrikasi Tulangan Pabrikasi Bekisting Pabrikasi Tulangan
Pier (Kolom) P1-17 Pier (Kolom) P1-17 Pier (Kolom) P1-17 Abutment A
Section 1 Section 1 Section 1 Section 1

Pekerjaan Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting
Lantai Kerja Pile Cap Pile Cap Pile Cap Pier (Kolom) P1-17 Pier (Kolom) P1-17
Section 1 Section 1 Section 1 Section 1 Section 1 Section 1

Pekerjaan Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting
Lantai Kerja Pile Cap Pile Cap Pile Cap Pier (Kolom) P18-33 Pier (Kolom) P18-33
Section 2 Section 2 Section 2 Section 2 Section 2 Section 2

Pabrikasi Bekisting Pabrikasi Tulangan Pabrikasi Bekisting Pabrikasi Tulangan


Pier (Kolom) P18-33 Pier (Kolom) P18-33 Pier (Kolom) P18-33 Abutment B
Section 2 Section 2 Section 2 Section 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 2 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pabrikasi Bekisting Pabrikasi Tulangan Pabrikasi Bekisting
Abutment A Pier Head P1-17 Pier Head P1-17
Section 1 Section 1 Section 1

Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Urugan
Pier (Kolom) P1-17 Abutment A Abutmen A Abutmen A Abutmen A
Section 1 Section 1 Section 1 Section 1 Section 1

Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Urugan
Pier (Kolom) P18-33 Abutment B Abutmen B Abutmen B Abutmen B
Section 2 Section 2 Section 2 Section 2 Section 2

Pabrikasi Bekisting Pabrikasi Tulangan Pabrikasi Bekisting


Abutment B Pier Head P18-33 Pier Head P18-33
Section 2 Section 2 Section 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 3 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pabrikasi Tulangan
Wing Wall Pabrikasi Tulangan Diafragma
Section 1 Section 1 & 2

Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting
Pier Head P1-17 Pier Head P1-17 Pier Head P1-17 Wing Wall Wing Wall
Seaction 1 Seaction 1 Seaction 1 Section 1 Section 1

Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting
Pier Head P18-33 Pier Head P18-33 Pier Head Wing Wall Wing Wall
Section 2 Section 2 Section 2 Section 2 Section 2

Pabrikasi Tulangan
Wing Wall Pabrikasi Bekisting Diafragma
Section 2 Section 1 & 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 4 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pabrikasi Tulangan Diafragma Pabrikasi Tulangan Deck Slab
Section 1 & 2 Section 1 & 2

Pekerjaan Pengecoran
Pekerjaan Pengecoran Dudukan Elastomer Pekerjaan Pemasangan
Wing Wall Bearing Pad Rubber Pad
Section 1 Section 1 Section 1

Pekerjaan Pekerjaan
Erection Girder Pembesian Diafragma
Section 1 & 2 Section 1 & 2

Pekerjaan Pengecoran
Pekerjaan Pengecoran Dudukan Elastomer Pekerjaan Pemasangan
Wing Wall Bearing Pad Rubber Pad
Section 2 Section 2 Section 2

Pabrikasi Bekisting Diafragma


Section 1 & 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 5 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pabrikasi Tulangan Pelat Injak
Section 1 & 2

Pekerjaan
Pekerjaan Pekerjaan Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran Pembesian
Bekisting Diafragma Bekisting Diafragma Deck Slab Deck Slab Deck Slab Pelat Injak
Section 1 & 2 Section 1 & 2 Section 1 & 2 Section 1 & 2 Section 1 & 2 Section 1 & 2

Pabrikasi Bekisting Deck Slab Pabrikasi Bekisting Pelat Injak


Section 1 & 2 Section 1 & 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 6 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pabrikasi Tulangan
Parapet & Barrier
Section 1 & 2

Pekerjaan Bekisting Pekerjaan Pengecoran Pekerjaan Pembesian Pekerjaan Bekisting Pekerjaan Pengecoran
Pelat Injak Pelat Injak Parapet & Barrier Parapet & Barrier Parapet & Barrier
Section 1 & 2 Section 1 & 2 Section 1 & 2 Section 1 & 2 Section 1 & 2

Pabrikasi Bekisting
Parapet & Barrier
Section 1 & 2

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 7 8
INSTITUT TEKNOLOGI SEPULUH NOPEMBER PELAKSANAAN KONSTRUKSI DR. MACHSUS, ST., MT.
Pekerjaan Pengaspalan
Section 1 & 2
FINISH

MATA KULIAH DOSEN PENGAJAR NAMA MAHASISWA NAMA GAMBAR NO. GBR JML. GBR
DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL
FAKULTAS VOKASI PROYEK MANAJEMEN IR. ACHMAD FAIZ HADI P., MS.
KELOMPOK 5 NETWORK PLANNING 8 8