REVIEW PROGRESS BY EXATRA ENJINERING

KONTRAK REALISASI KEMAJUAN PEKERJAAN


MINGGU LALU MINGGU INI S/D MINGGU INI
No. ITEM PEKERJAAN PERSENTASE Keterangan
SAT VOLUME BOBOT PERSENTASE PERSENTASE
TERHADAP BOBOT YANG BOBOT YANG BOBOT YANG
VOLUME VOLUME TERHADAP UNIT VOLUME TERHADAP UNIT
UNIT DICAPAI DICAPAI DICAPAI
PEKERJAAN PEKERJAAN
PEKERJAAN
I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek unit 1 0.004% 1.00 100.00% 0.004% - 0.00% 0.000% 1.000 100.00% 0.004%
2 Mobilisasi Dan Demobilisasi ls 1 12.564% 0.50 50.00% 6.282% - 0.00% 0.000% 0.500 50.00% 6.282%
3 Direksi Keet, Barak Pekerja Dan Gudang Alat/Material m2 400 0.902% 400.00 100.00% 0.902% - 0.00% 0.000% 400.000 100.00% 0.902%
4 Pelaporan dan Dokumentasi Bln 7 0.269% 4.023 57.47% 0.155% 0.008 0.12% 0.000% 4.031 57.58% 0.155%
5 Penerangan Proyek ls 1 0.474% 0.436 43.59% 0.207% 0.014 1.44% 0.007% 0.450 45.02% 0.214%
6 Keamanan dan Keselamatan Kerja (K3) ls 1 1.058% 0.88 88.16% 0.933% 0.00% 0.000% 0.882 88.16% 0.933%
7 Pengujian Beton ls 1 0.115% 0.40 40.00% 0.046% - 0.00% 0.000% 0.400 40.00% 0.046%
8 PDA Test Titik 9 0.322% 9.00 100.00% 0.322% 0.00% 0.000% 9.000 100.00% 0.322%
9 Pengadaan Air Bersih ls 1 0.187% 1.00 100.00% 0.187% - 0.00% 0.000% 1.000 100.00% 0.187%
II. PEKERJAAN PEMBUATAN JETTY (105,04 m x 30,7 m)
1 Pengukuran dan Pemasangan Bowplank m 271.48 0.062% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000%
2 Pengadaan Tiang Pancang Ø 508 mm Tebal 12 mm, transportasi ton 663.693 27.734% 663.69 100.00% 27.734% - 0.00% 0.000% 663.69 100.00% 27.734%
3 Pengangkutan Tiang Pancang Ke Lokasi Titik Pancang m 5290 4.145% 5,230.00 98.87% 4.098% 0.00% 0.000% 5,230.00 98.87% 4.098%
4 Pengecatan Tiang Pancang m2 5436.326 0.572% 4,277.00 78.67% 0.450% 0.00% 0.000% 4,277.00 78.67% 0.450%
5 Pemancangan Tiang Tegak Ø 508 mm Tebal 12 mm P = 30 m m 2160 3.122% 2,130.00 98.61% 3.079% 0.00% 0.000% 2,130.00 98.61% 3.079%
6 Pemancangan Tiang Tegak Ø 508 mm Tebal 9 mm P = 25 m m 1900 2.746% 1,870.00 98.42% 2.703% 0.00% 0.000% 1,870.00 98.42% 2.703%
7 Pemancangan Tiang Tegak Ø 508 mm Tebal 9 mm P = 20 m m 640 0.925% 640.00 100.00% 0.925% 0.00% 0.000% 640.00 100.00% 0.925%
8 Pemancangan Tiang Tegak Ø 508 mm Tebal 9 mm P = 15 m m 360 0.520% 360.00 100.00% 0.520% - 0.00% 0.000% 360.00 100.00% 0.520%
9 Pemancangan Tiang Tegak Ø 508 mm Tebal 9 mm P = 10 m (Angkur) m 230 0.332% 230.00 100.00% 0.332% - 0.00% 0.000% 230.00 100.00% 0.332%
10 Penyambungan Tiang Pancang Titik 214 0.462% 214.00 100.00% 0.462% 0.00% 0.000% 214.00 100.00% 0.462%
11 Pemotongan Tiang Pancang Titik 204 0.293% 34.00 16.67% 0.049% 43.000 0.211 0.001 77.00 37.75% 0.111%
12 Pengadaan, pemasangan Tali Sling Baja Galvanis Ø 45 mm dan Assesories m 575 1.557% 287.50 50.00% 0.779% - 0.00% 0.000% 287.50 50.00% 0.779%
13 Balok/Plank Beton Bertulang -
- Beton m3 413.322 6.591% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000% Material di p.gag 16 january 2021
- Pembesian Kg 13918.75 1.205% 5,240.46 37.65% 0.454% - 0.00% 0.000% 5,240.46 37.65% 0.454%
- Bekisting/Perancah m2 1658.4 2.371% 443.08 26.72% 0.633% - 0.00% 0.000% 443.08 26.72% 0.633%
14 Balok Beton Bertulang Uk. 80/81 (Angkur) -
- Beton m3 21.576 0.344% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000% Material di p.gag 16 january 2021
- Pembesian Kg 1414 0.122% 707.00 50.00% 0.061% - 0.00% 0.000% 707.00 50.00% 0.061%
- Bekisting/Perancah m2 125 0.179% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000%
15 Beton Isian Tiang (Turap) -
- Beton m3 62.672 0.999% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000% Material di p.gag 16 january 2021
- Pembesian Kg 16477.5 1.427% 11,756.70 71.35% 1.018% - 0.00% 0.000% 11,756.70 71.35% 1.018%
- Bottom Plate t = 10 mm Kg 3405 0.344% 1,702.50 50.00% 0.172% - 0.00% 0.000% 1,702.50 50.00% 0.172%
16 Beton Isian Tiang (Angkur) -
- Beton m3 6.51 0.104% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000% Material di p.gag 16 january 2021
- Pembesian Kg 1165.375 0.101% 815.76 70.00% 0.071% - 0.00% 0.000% 815.76 70.00% 0.071%
- Bottom Plate t = 10 mm Kg 351.9 0.036% 175.95 50.00% 0.018% - 0.00% 0.000% 175.95 50.00% 0.018%
17 Kanstin -
- Beton m3 21.732 0.347% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000% Material di p.gag 16 january 2021
- Pembesian Kg 2086.5 0.201% 834.60 40.00% 0.081% - 0.00% 0.000% 834.60 40.00% 0.081%
- Bekisting m2 25.157 0.020% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000%
18 Pengadaan, pasangan Batu Kosong Ø 50 cm - Ø 80 cm m3 3051.444 11.032% 1,525.72 50.00% 5.516% - 0.00% 0.000% 1,525.72 50.00% 5.516% Material di p.gag 16 january 2021
19 Pengadaan, pemasangan Geotextile Non Woven m2 1562.415 1.027% 703.09 45.00% 0.462% - 0.00% 0.000% 703.09 45.00% 0.462%
20 Pengadaan, pemasangan Bollard Kap. 70 Ton Type Straight unit 7 0.539% 3.00 42.86% 0.231% - 0.00% 0.000% 3.00 42.86% 0.231%
21 Pengadaan, pemasangan Tiang dan Lampu Solar Cell (1 Mata), P = 12 m unit 2 0.283% 1.00 50.00% 0.142% - 0.00% 0.000% 1.00 50.00% 0.142%
22 Pengadaan, pemasangan Tiang dan Lampu Solar Cell (2 Mata), P = 12 m unit 4 0.753% 2.00 50.00% 0.377% - 0.00% 0.000% 2.00 50.00% 0.377%
III. RENTAL UNIT (Ponton, Tugboat, batching plant, truck, dan LCT)
1 Unit operasional dilaut dan pekerjaan sipil ls 1 7.560% 0.64 64.19% 4.853% 0.048 4.81% 0.364% 0.69 69.00% 5.217%
2 Fuel / bahan bakar solar (seluruh alat berat dan armada laut) ls 1 5.930% 0.70 70.23% 4.165% - 0.00% 0.000% 0.70 70.23% 4.165%
IV. PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir ls 1 0.118% - 0.00% 0.000% - 0.00% 0.000% - 0.00% 0.000%
`
100.00% 68.421% 0.433% 68.854%