THN 2010
KONTRAK ORIGINAL
NO BLN MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER SKALA
URAIAN PEKERJAAN KETERANGAN
ITEM SAT KUANTITAS BOBOT MGG 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 (%)
(%) TGL 20-26 27-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-1 2-8 9-15 16-22 23-29 30-6 7-13 14-20 21-27 28-3 4-10 11-15
DIVISI 1. UMUM 100
1.2 Mobilisasi Ls 1.00 3.372 0.590 0.590 0.590 0.590 0.253 0.253 0.253 0.253 SPMK
DIVISI 2. DRAINASE 20 Mei 2010
2.3(3) Gorong-gorong pipa beton bertulang dia. Dalam 75-120 cm m3 6.00 0.316 0.053 0.053 0.053 0.053 0.053 0.053
DIVISI 3. PEKERJAAN TANAH Jangka Waktu
Rencana 75
3.2(3) Timbunan Pilihan m3 227.65 1.328 0.166 0.166 0.166 0.166 0.166 0.166 0.166 0.166 Pelaksanaan
3.3 Penyiapan Badan Jalan m2 9,000.00 1.327 0.166 0.166 0.166 0.166 0.166 0.166 0.166 0.166 180 HK
DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
DIVISI 5. PERKERASAN BERBUTIR
5.1(1) Lapis Pondasi Agregat Kelas A m3 1,080.00 24.610 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538 1.538
50
5.1(2) Lapis Pondasi Agregat Kelas B m3 810.00 18.539 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159 1.159
DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Ltr 5,760.00 3.083 0.617 0.617 0.617 0.617 0.617
6.3(6) Laston Lapis Antara (AC-BC) m3 360.00 45.025 9.005 9.005 9.005 9.005 9.005
DIVISI 7. STRUKTUR
25
7.9 Pasangan Batu m 3
69.00 2.400 Realisasi 0.800 0.800 0.800
DIVISI 8. PENGEMB. KONDISI DAN PEK. MINOR
DIVISI 9. PEKERJAAN HARIAN
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
0
Total Bobot Pekerjaan 100.00
Progress Rencana Mingguan % - - 0.590 0.590 0.643 0.643 3.081 3.081 3.081 3.081 3.829 3.829 3.829 3.029 2.697 2.697 2.697 2.697 2.697 12.318 12.318 12.318 9.875 9.875 0.253 0.253
Kumulatif Rencana Mingguan % - - 0.590 1.180 1.823 2.466 5.547 8.628 11.710 14.791 18.620 22.448 26.277 29.306 32.002 34.699 37.396 40.093 42.790 55.108 67.427 79.745 89.620 99.494 99.747 100.00
Progress Realisasi Mingguan % - - - - 0.505 0.507
Kumulatif Realisasi Mingguan % - - - - 0.505 1.012
Deviasi % - - - - (1.32) (1.45)
Diperiksa oleh :
Konsultan Supervisi
PT. INDAH KARYA (Persero) & Ass.
CV. Beuna Engineering Consultant