LIST DAFTAR HARGA BORONGAN BANGUNAN

AREA JAWA TENGAH


HARGA
NO. DESCRIPTION UNIT AMOUNT REMAKS
UPAH MATERIAL
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan - M2 10,000 - 10,000
2 Bowplang - M' 30,000 40,000 70,000

II PEKERJAAN TANAH
1 Cut & Fill (Kupas Tanah Dan Urug) - M³ 35,000 - 35,000
2 Suply Fill Area (Urugan Tanah Dari Luar) - M³ 35,000 50,000 85,000
2 Cut (Galian) - M³ 40,000 - 40,000 Alat / Volume Besar
- M³ 120,000 - 120,000 Manual Volume Kecil
3 Disposal (buang tanah) - M³ 35,000 - 35,000 Alat / Volume Besar
- M³ 100,000 100,000 Manual Volume Kecil
4 Back Fill) (Urug Kembali) - M³ 30,000 - 30,000 Alat / Volume Besar
- M³ 100,000 100,000 Manual Volume Kecil
III PEKERJAAN PONDASI
1 Psang Batukali Batu Pecah Hitam Non Exspouse M³ 150,000 500,000 650,000

IV PEKERJAAN STRUKTUR BETON


1 Roundbar (Pembesian) Krakatau Steel Kg 1,700 9,000 10,700
2 Formwork (Bekisting) Plywood 12 mm M² 55,000 70,000 125,000
3 Concrete (Pengecoran) Ready Mix 250 - 300 M³ 120,000 850,000 970,000 Ready Mix
Site Mix setara K-250 M³ 275,000 575,000 850,000 SiteMix
4 Suport / Soring Scafoldinng Dll M² 10,000 15,000 25,000
V PEKERJAAN DINDING
1 Conblock (Pasangan Dinding)
Pasang Bata Merah Ex lokal M² 35,000 75,000 110,000
Pasang Bata Ringan (hebel) Jaya Brik, focon M² 25,000 90,000 115,000
Pasang Batako Ex lokal M² 30,000 80,000 110,000
2 Plester Aci
Mortar Instant (plester aci hebel) Sun mortar, Sakti mortar dll M² 35,000 40,000 75,000
Pasir & Semen Hitam Pasir muntilan , Semen Holcim M² 40,000 30,000 70,000
3 Glasblok & Finish Ex lokal Unit 35,000 35,000 70,000
4 Pasang keramik dinding Asia Tile, Platinum, Roman M² 50,000 100,000 150,000
5 Pengecatan Catylac colour, Cat dasar sealer M² 10,000 17,000 27,000
VI Pekerjaan Lantai
1 Perataan Tanah Area + Pemadatan Area Stemper Jumping / Vibroroller M² 10,000 - 10,000
2 Urug Pasir Pasir Urug M³ 100,000 200,000 300,000
3 Keramik Asia Tile, Platinum, Roman M² 45,000 100,000 145,000
4 Pasang Paving K 250 -300 uk 20 x 10 x 6 Cm M² 30,000 90,000 120,000

Page 1 of 8
LIST DAFTAR HARGA BORONGAN BANGUNAN
AREA JAWA TENGAH
HARGA
NO. DESCRIPTION UNIT AMOUNT REMAKS
UPAH MATERIAL
VII Pekerjaan Atap
1 Baja ringan Truss 0,75 SNI M² 35,000 100,000 135,000
2 Foil Single paper, foil karung M² 5,000 15,000 20,000
3 Genteng Keramik Kia, M-klass M² 30,000 155,000 185,000
4 Nok/ Kerpus Kia, M-klass include finish waterprofing M' 100,000 150,000 250,000
VIII Pekerjaan Plafond

1 Pasang Plafond Include Cat Frame : Holow 2x4 cover : Knauf, Gyprock setara, cat : aries , sanalux M² 35,000 70,000 105,000

2 List plafond Shadowline, profil gypsum M' 10,000 15,000 25,000


IX Pekerjaan Finish
1 Finish Top & Opening M' 35,000 10,000 45,000
2 Finish Skonengan sudutan M' 15,000 5,000 20,000
5 Expouse Mortar instan M² 20,000 10,000 30,000
X Sanitary
1 Plumbing Lihat Desain - - - - Lihat Desain
2 Mainhole Lihat Desain - - - - Lihat Desain

Page 2 of 8
LIST DAFTAR HARGA BORONGAN BANGUNAN
AREA JAWA TENGAH
HARGA
NO. DESCRIPTION UNIT AMOUNT REMAKS
UPAH MATERIAL
3 Bak KM Finish Keramik Uk 70 x 70 x 70 cm Unit 350,000 500,000 850,000
4 Kloset Jongkok + Dudukan Ex Ina Unit 250,000 400,000 650,000
5 Septic tank Bio text Unit - - - Lihat Desain

CATATAN :
1. Semua Ijin Kerja, Pembangunan & Kordinasi Lingkungan Menjadi Tanggung Jawab Pemberi Kerja
2. Arus Listrik Genset / PLN disedikan Oleh Pemberi Kerja
3. Volume dihitung berdasarkan actual yang dikerjakan
4. Item pekerjaan yang belum masuk dan tertera dalam penawaran termasuk pekerjaan tambahan
dan akan dihitung dan dibayar sesuai kesepakatan

IMAM MUSTAJIB

Page 3 of 8
CALCULATION
R. GENSET & SAMPAH
CALCULATION
NO JOB DESCRIPTION Qty Unit TOTAL VOLUME
a b c d
I Stone Mansory (a) Sandlayer Stone mansory
1 Sandlayer
Pot V 5.70 x 0.10 x 1.50 0.86 1.00 0.86 0.86
Pot W 58.30 x 0.10 x 0.90 5.25 1.00 5.25 5.25
Pot Y 121.56 x 0.10 x 0.90 10.94 1.00 10.94 10.94
Pot Z 25.00 x 0.10 x 1.50 3.75 1.00 3.75 3.75
2 Stone mansory
Pot V 5.70 x 0.80 x 1.15 5.24 1.00 5.24 5.24
Pot W 58.30 x 0.80 x 0.55 25.65 1.00 25.65 25.65
Pot Y 121.56 x 0.80 x 0.55 53.49 1.00 53.49 53.49
Pot Z 25.00 x 0.80 x 1.15 23.00 1.00 23.00 23.00
Total 20.79 107.38 - - - -
II Foundation Pilecap Sandlayer Formwork Roundbar Concrete
1 Sandlayer
P1 1.90 x 1.90 x 0.10 0.36 4.00 1.44 1.44
P2 1.30 x 1.30 x 0.10 0.17 10.00 1.69 1.69
P3 1.70 x 1.70 x 0.10 0.29 4.00 1.16 1.16
2 Formwork
P1 1.80 x 4.00 x 0.25 1.80 4.00 7.20 7.20
P2 1.20 x 4.00 x 0.20 0.96 10.00 9.60 9.60
P3 1.60 x 4.00 x 0.25 1.60 4.00 6.40 6.40
3 Roundbar
P1
Bottom D13 1.04 x 2.10 x 10.00 21.88 4.00 87.52 87.52
Top D 10 0.62 x 2.10 x 10.00 12.95 4.00 51.79 51.79
P2
Bottom D13 1.04 x 1.40 x 7.00 10.21 10.00 102.10 102.10
Top D 10 0.62 x 1.40 x 7.00 6.04 10.00 60.42 60.42
P3
Bottom D13 1.04 x 1.90 x 9.00 17.82 4.00 71.26 71.26
Top D 10 0.62 x 1.90 x 9.00 10.54 4.00 42.17 42.17
4 Concrete
P1 1.80 x 1.80 x 0.25 0.81 4.00 3.24 3.24
P2 1.20 x 1.20 x 0.20 0.29 10.00 2.88 2.88
P3 1.60 x 1.60 x 0.25 0.64 4.00 2.56 2.56
4.29 23.20 415.26 8.68 - -
III Foundation Mechine Sandlayer Formwork Roundbar Concrete
1 Sandlayer 1.60 x 3.85 x 0.10 0.62 3.00 1.85 1.85
2 Formwork 1.50 x 1.00 x 2.00 3.00 3.00 9.00 9.00
3.75 x 1.00 x 2.00 7.50 3.00 22.50 22.50
3 Roundbar
Bottom D16 1.58 x 3.20 x 19.00 95.96 3.00 287.87 287.87
1.58 x 5.45 x 8.00 68.81 3.00 206.43 206.43
Midle D13 1.04 x 10.50 x 3.00 32.82 3.00 98.46 98.46
Top D 16 1.58 x 2.20 x 19.00 65.97 3.00 197.91 197.91
1.58 x 4.45 x 8.00 56.19 3.00 168.56
4 Concrete 1.50 x 3.75 x 1.00 5.63 3.00 16.88 16.88
1.85 31.50 790.67 16.88 - -
IV Sloof Formwork Roundbar Concrete
1 Formwork
20/30 210.56 x 0.30 x 2.00 126.34 1.00 126.34 126.34
15/20 24.00 x 0.20 x 2.00 9.60 1.00 9.60 9.60
2 Roundbar
20/30
Mainbar 4D13 1.04 x 210.56 x 1.04 228.15 4.00 912.62 912.62
Midlebar 2D10 0.62 x 210.56 x 1.03 133.70 2.00 267.41 267.41
Ringbar D10-200 0.62 x 0.90 x 1.00 0.55 1,052.80 584.15 584.15
15/20
Mainbar 4D10 0.62 x 24.00 x 1.00 14.80 4.00 59.18 59.18
Ringbar D8-200 0.39 x 0.60 x 1.00 0.24 120.00 28.41 28.41
3 Concrete 0.30 x 0.20 x 90.00 5.40 1.00 5.40 5.40
20/30 210.56 x 0.30 x 0.20 12.63 1.00 12.63 12.63
15/20 24.00 x 0.20 x 0.15 0.72 1.00 0.72 0.72
135.94 1,857.17 13.35 - - -

V Floor Work Sandlayer Formwork Roundbar Concrete


a. Lt1
1 Sandlayer 7.50 x 19.00 x 0.10 - 1.67 12.59 1.00 12.59 12.59
3.85 x 45.00 x 0.10 17.33 1.00 17.33 17.33
2 Formwork Stop cor 140.60 x 0.10 14.06 1.00 14.06 14.06
3 Roundbar
S1
X-X 1D10-200 0.62 x 3.10 x 38.00 72.62 1.00 72.62 72.62
0.62 x 45.10 x 32.00 889.73 1.00 889.73 889.73
Y-Y 1D10-200 0.62 x 7.60 x 15.00 70.28 1.00 70.28 70.28
0.62 x 6.45 x 225.00 894.70 1.00 894.70 894.70
S2
X-X 2D10-150 0.62 x 16.10 x 50.00 496.28 2.00 992.57 992.57
Y-Y 2D10-150 0.62 x 7.60 x 106.00 496.65 2.00 993.30 993.30

5 Concrete S1 3.00 x 7.50 x 0.10 2.25 1.00 2.25 2.25


6.35 x 45.00 x 0.10 28.58 1.00 28.58 28.58
S2 16.00 x 7.50 x 0.15 - 2.53 15.47 1.00 15.47 15.47
29.91 14.06 3,913.20 46.29 - -
b. Lt2 Formwork Soring Roundbar Concrete
1 Formwork 9.70 x 20.20 195.94 1.00 195.94 195.94
2 Soring / Suport 9.70 x 10.10 x 4.35 426.17 1.00 426.17 426.17
3 Roundbar
X-X 2D10-200 0.62 x 20.30 x 48.50 606.98 2.00 1,213.95 1,213.95
Y-Y 2D10-200 0.62 x 9.80 x 101.00 610.21 2.00 1,220.42 1,220.42
4 Concrete 9.70 x 20.20 x 0.12 23.51 1.00 23.51 23.51

195.94 426.17 2,434.37 23.51 - -


VI Wall Work Bata Merah Roster Plester Aci Andang kerja Painting Opening
1 Bata Merah
Depan 45.00 x 5.30 - 33.54 204.96 1.00 204.96 204.96
19.00 x 4.25 - 22.19 58.56 1.00 58.56 58.56
Belakang 45.00 x 5.00 - 18.90 206.10 1.00 206.10 206.10
19.00 x 4.25 - 9.54 71.21 1.00 71.21 71.21
Skat 51.80 x 4.25 220.15 1.00 220.15 220.15
6.30 x 5.15 x 9.00 - 24.99 267.02 1.00 267.02 267.02
2 Roster
0.30 x 2.40 0.72 6.00 4.32 4.32
1.05 x 1.20 1.26 16.00 20.16 20.16
1.55 x 1.00 1.55 3.00 4.65 4.65
1.05 x 1.80 1.89 3.00 5.67 5.67
3 Plester Aci
Depan 45.00 x 5.30 - 33.54 204.96 2.00 409.92 409.92
19.00 x 4.25 - 22.19 58.56 2.00 117.12 117.12
Belakang 45.00 x 5.00 - 18.90 206.10 2.00 412.20 412.20
19.00 x 4.25 - 9.54 71.21 2.00 142.42 142.42
Skat 51.80 x 4.25 220.15 2.00 440.30 440.30
6.30 x 5.15 x 9.00 - 24.99 267.02 2.00 534.03 534.03
4 Andang Kerja
Depan 45.00 x 5.30 238.50 2.00 477.00 477.00
19.00 x 4.25 80.75 2.00 161.50 161.50
Belakang 45.00 x 5.00 225.00 2.00 450.00 450.00
19.00 x 4.25 80.75 2.00 161.50 161.50
Skat 51.80 x 4.25 220.15 2.00 440.30 440.30
6.30 x 5.15 x 9.00 292.01 2.00 584.01 584.01
5 Painting
Depan 45.00 x 5.30 - 33.54 204.96 2.00 409.92 409.92
19.00 x 4.25 - 22.19 58.56 2.00 117.12 117.12
Belakang 45.00 x 5.00 - 18.90 206.10 2.00 412.20 412.20
19.00 x 4.25 - 9.54 71.21 2.00 142.42 142.42
Skat 51.80 x 4.25 220.15 2.00 440.30 440.30
6.30 x 5.15 x 9.00 - 24.99 267.02 2.00 534.03 534.03
6 Finish Opening
PB1 2.50 + 2.50 + 4.00 9.00 1.00 9.00 9.00
PB2 2.10 + 2.10 + 2.10 6.30 5.00 31.50 31.50
JA1 1.10 + 1.10 + 1.10 + 1.10 4.40 16.00 70.40 70.40
Opening r. sampah 2.10 + 2.10 + 1.70 5.90 7.00 41.30 41.30
Top Finish Skat 8.50 x 1.00 9.50 9.00 85.50 85.50
Top Finish luar 45.00 45.00 2.00 90.00 90.00
1,028.00 34.80 2,055.99 2,274.31 2,055.99 327.70

VII Coloum & Ring Praktis 10 x 15 cm Formwork Roundbar Concrete Soring


1 Formwork
Coloum 0.15 x 2.00 x 5.30 1.59 16.00 25.44 25.44
0.15 x 3.00 x 2.10 0.95 7.00 6.62 6.62
0.15 x 2.00 x 4.25 1.28 14.00 17.85 17.85
Beam 0.15 x 2.00 x 236.50 70.95 1.00 70.95 70.95
2 Roundbar
Coloum Mainbar D10 0.62 x 4.00 x 5.30 13.07 16.00 209.12 209.12
0.62 x 4.00 x 2.10 5.18 7.00 36.25 36.25
0.62 x 4.00 x 4.25 10.48 14.00 146.73 146.73
Ringbar ᴓ 8 - 150 0.39 x 0.40 x 5.30 x 7.00 5.86 16.00 93.68 93.68
0.39 x 0.40 x 2.10 x 7.00 2.32 7.00 16.24 16.24
0.39 x 0.40 x 4.25 x 7.00 4.70 14.00 65.73 65.73
Beam Mainbar D10 0.62 x 4.00 x 236.50 583.21 1.00 583.21 583.21
Ringbar ᴓ 8 - 150 0.39 x 0.40 x 1,655.50 261.28 1.00 261.28 261.28
3 Concrete -
Coloum 0.15 x 0.10 x 5.30 0.08 16.00 1.27 1.27
0.15 x 0.10 x 2.10 0.03 7.00 0.22 0.22
0.15 x 0.10 x 4.25 0.06 14.00 0.89 0.89
Beam 0.15 x 0.10 x 236.50 3.55 1.00 3.55 3.55
120.86 1,412.24 5.93 - - -

VIII Structure Work Formwork Roundbar Concrete Soring


a. Main Coloum
20 x 20 Cm
1 Formwork 0.20 x 4.00 x 5.15 4.12 24.00 98.88 98.88
2 Roundbar
Mainbar D13 1.04 x 4.00 x 5.15 21.46 24.00 515.11 515.11
Ringbar ᴓ 8 - 150 0.39 x 0.70 x 34.00 9.39 24.00 225.37 225.37
3 Concrete 0.20 x 0.20 x 5.15 0.21 24.00 4.94 4.94
30 x 30 Cm
1 Formwork 0.30 x 4.00 x 4.25 5.10 12.00 61.20 61.20
2 Roundbar
Mainbar 8D16 1.58 x 8.00 x 4.25 53.66 12.00 643.92 643.92
Midlebar 2D10-150 0.62 x 0.35 x 57.00 12.30 12.00 147.59 147.59
Ringbar D10- 100 0.62 x 1.10 x 43.00 29.16 12.00 349.93 349.93
3 Concrete 0.30 x 0.30 x 4.25 0.38 12.00 4.59 4.59
35 x 45 Cm
1 Formwork 0.40 x 4.00 x 4.25 6.80 6.00 40.80 40.80
2 Roundbar
Mainbar 12D16 1.58 x 12.00 x 4.25 80.49 6.00 482.94 482.94
Midlebar 2D10-150 0.62 x 0.45 x 57.00 15.81 6.00 94.88 94.88
Ringbar D10- 100 0.62 x 1.50 x 43.00 39.76 6.00 238.59 238.59
3 Concrete 0.35 x 0.45 x 4.25 0.67 6.00 4.02 4.02
200.88 2,698.32 13.55 - - -
b. Beam
15 x 30
1 Formwork 0.24 x 2.00 x 29.90 14.35 1.00 14.35 14.35
2 Roundbar
Mainbar 4D13 1.04 x 4.00 x 29.90 124.61 1.00 124.61 124.61
Midlebar 2D10 0.62 x 2.00 x 29.90 36.87 1.00 36.87 36.87
Ringbar D10- 150/200 0.62 x 0.80 x 176.00 86.80 1.00 86.80 86.80
3 Concrete 0.15 x 0.30 x 29.90 1.35 1.00 1.35 1.35
20 x 35 Cm
1 Formwork 0.23 x 2.00 x 99.40 45.72 1.00 45.72 45.72
2 Roundbar
Mainbar 4D13 1.04 x 4.00 x 99.40 414.25 1.00 414.25 414.25
Midlebar 2D10 0.62 x 2.00 x 99.40 122.56 1.00 122.56 122.56
Ringbar D10- 100/150 0.62 x 1.00 x 828.00 510.46 1.00 510.46 510.46
3 Concrete 0.20 x 0.35 x 99.40 6.96 1.00 6.96 6.96
30 x 65 Cm
1 Formwork 0.53 x 2.00 x 29.10 30.85 1.00 30.85 30.85
2 Roundbar
Mainbar 4D16 1.58 x 4.00 x 29.10 183.71 1.00 183.71 183.71
Midlebar 2D10 0.62 x 2.00 x 29.10 35.88 1.00 35.88 35.88
Ringbar D10- 100/150 0.62 x 1.80 x 242.00 268.55 1.00 268.55 268.55
3 Concrete 0.30 x 0.65 x 29.10 5.67 1.00 5.67 5.67
90.92 1,783.69 13.98 - - -
c. Balok BR & Kuda-kuda
1 Formwork Kuda-kuda 0.70 x 8.83 6.18 9.00 55.64 55.64
BR 0.70 x 45.00 31.50 2.00 63.00 63.00
2 Roundbar
Mainbar 4D13 Kuda2 1.04 x 4.00 x 8.83 36.80 9.00 331.19 331.19
BR 1.04 x 4.00 x 45.00 x 1.04 195.04 2.00 390.08 390.08
Ringbar ᴓ 8 - 150/200 0.39 x 0.80 x 51.00 16.10 9.00 144.88 144.88
0.39 x 0.80 x 265.00 83.65 2.00 167.29 167.29
3 Concrete 0.20 x 0.25 x 8.83 0.44 9.00 3.97 3.97
0.20 x 0.25 x 45.00 2.25 2.00 4.50 4.50
4 Soring / Suport Overlap 5.15 x 2.20 11.33 9.00 101.97 101.97
118.64 1,033.45 8.47 101.97 - -
d. Lisplang 10 x 55 Cm
1 Formwork 1.08 x 1.00 x 50.10 54.11 1.00 54.11 54.11
2 Roundbar
Mainbar 1D10 0.62 x 0.95 x 501.00 293.42 1.00 293.42 293.42
3 Concrete 0.10 x 0.55 x 50.10 2.76 1.00 2.76 2.76
4 Soring / Suport 4.00 x 50.10 200.40 1.00 200.40 200.40
54.11 293.42 2.76 200.40 - -

IX Structure Work Formwork Roundbar Concrete Soring


1 Formwork Wall 0.55 x 2.00 x 11.65 12.82 2.00 25.63 25.63
2 Roundbar
Slab 2D10 - 150 0.62 x 0.70 x 78.00 33.66 2.00 67.32 67.32
0.62 x 11.65 x 5.00 35.91 2.00 71.82 71.82
Wall 2D10 - 150 0.62 x 0.60 x 85.00 31.44 4.00 125.77 125.77
0.62 x 12.35 x 3.00 22.84 4.00 91.37 91.37
3 Concrete
Slab 0.70 x 0.15 x 11.65 1.22 1.00 1.22 1.22
Wall 0.40 x 0.15 x 12.35 0.74 2.00 1.48 1.48
4 Exspouse Slab 0.40 x 11.65 4.66 1.00 4.66 4.66
Wall 0.40 x 12.35 4.94 2.00 9.88 9.88
25.63 356.28 2.71 14.54 - -