MINGGU KE - 11 (Sepuluh)

( 12 April S/D 18 April 2021 )

HARI KE-
NO URAIAN PEKERJAAN 1 2 3 4 5 6 7
12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr
1 PEMASANGGAN BIKISTING MALL RING BALOK 20X50, 15X30, 10X40
2 BIKISTING PLAT LANTAI TALANG AIR, LANTAI RING BALOK
3 PABRIKASI DAN PEMASANGAN WERMESH PLAT LANTAI, STAK TALANG
4 PEMASANGAN PERANCA DAN BIKISTING RING BALOK 20X50 DAN TALANG AIR
5 PEMASANGAN STUT MALL RING BALOK
6 PERSIAPAN PENGECORAN DAN PENGECEKAN
7 PENGECORAN RING BALOK DAN TALANG AIR
8 PENGECORAN RING BALOK DAN TALANG AIR
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24