Rencana (Jam) 12/04/2016 14/04/2016 16/04/2016 19/04/2016 21/04/2016 23/04/2016 26/04/2016 28/04/2016 30/04/2016 03/05/2016 05/05/2016 07/05/2016 10/05/2016

16 07/05/2016 10/05/2016 12/05/2016 14/05/2016 17/05/2016 19/05/2016 21/05/2016 24/05/2016 26/05/2016


No Jenis Pekerjaan
Realisasi (Jam) 22/04/2016
1 Pondasi Sumuran
6
• Galian Tanah
3 3
• Tulangan & Pemasangan 6
Cofferdam 4 2
5
• Pengecoran Beton cyclop
3,5
12
• Pile Cap

2 Abutment
18
• Pembesian

5
• Pembuatan Bekisting

5
• Pengecoran

3 Gelagar
• Penyediaan Gelagar Pra 3
Cetak
18
• Perakitan & Stressing

18
• Pemasangan Diafragma

4 Plat
16
• Pembesian Plat Jembatan

5
• Pengecoran Plat

Total Rencana (Jam) 117


Total Realita (Jam)
28/05/2016 31/05/2016 02/06/2016 04/06/2016 07/06/2016 09/06/2016 11/06/2016 14/06/2016 16/06/2016 18/06/2016 21/06/2016 23/06/2016 25/06/2016 28/06/2016 30/06/2016 02/07/2017