Progress Kantor Palu 100%
Progress Kantor Palu 100%
I Pekerjaan Dinding
1.1 Kolom IWF 150 2.946 0% 100% 2.946
1.2 Ringbalk IWF150 3.367 0% 100% 3.367
1.3 Rangka Hollow 40x80 4.739 0% 100% 4.739
1.4 Rangka Hollow 50x100 0.561 0% 100% 0.561
1.5 Dinding Kalsiclad 8mm (dua sisi) 6.430 0% 100% 6.430
1.6 Sekrup Kalsi 0.252 0% 100% 0.252
1.7 Kolom 10x15 4D10 1.409 0% 100% 1.409
1.8 Sloef 10x15 4D10 0.626 0% 100% 0.626
1.9 Ringbalk 10x15 4D10 0.626 0% 100% 0.626
1.10 Pasangan 1/2 bata (Area WC) 2.755 0% 100% 2.755
1.11 Plesteran 2.104 0% 100% 2.104
1.12 Plamir 0.877 0% 100% 0.877
1.13 Pengecatan 3.653 0% 100% 3.653
II Pekerjaan Lantai 1
2.1 Perataan lantai, cor rabat 5cm 0.451 0% 100% 0.451
2.2 Pasangan keramik lantai ukuran 40x40 8.329 0% 100% 8.329
2.3 Pasangan keramik lantai ukuran 30x30 (Area Toilet) 0.357 0% 100% 0.357
2.4 Pasangan keramik dinding 30x60 (Area Toilet) 2.296 0% 100% 2.296
2.5 Pekerjaan wastafel beton + granit 60x60 0.699 0% 100% 0.699
2.6 Cor Meja Dudukan Brangkas 0.526 0% 100% 0.526
IV Pekerjaan Plafond
3.1 Pekerjaan Rangka plafond + gybsum 6.613 0% 100% 6.613
3.2 Kompon plafond 0.827 0% 100% 0.827
3.3 Pasangan list plafond 0.476 0% 100% 0.476
3.4 Pengecatan plafond 1.447 0% 100% 1.447
TOTAL 100
SABRI AHANDI
PT. SABANG JAYA KONSTRUKSI