Publication 347
December 1992
1
BUNDING GUIDELINES
The following are intended to ensure the integrity of Different Liquids – Where two or more liquids are
the bund. stored on site, they should be stored such that:
Materials – floor slabs and bund walls, must be * separate bunded areas are provided where
impervious to, and compatible with, the liquids to possible for each liquid to maximise collection
and re-use of uncontaminated spilled liquid;
be contained. Concrete is recommended as it is robust
and generally impervious; however, it should be of a * minimum separation distances for storage
standard, or provided with a coating (eg acid vessels containing chemicals belonging to
resistant), that ensures that it is impervious during different classes of dangerous goods, as set out
service. in the Dangerous Goods (Storage and Handling)
Regulations 2000, are strictly adhered to.
For large tank farms, impervious proprietary liner
systems may be used with the written approval of the Half Height Rule – Tanks and drums should be
EPA. In such cases, its permeability shall not be more separated from the inner edge of the bund crest by a
that 10-9m/s for the liquid to be contained. Also it distance of half the height of the tanks or stack of
must be installed and maintained in accordance with drums on flat ground.
the manufacturers specifications.
The above half-height rule may be waived where
Joints – concrete bunds should be poured integrally adequate restraint is provided to prevent drums from
with the slab. When joints are used in concrete or falling outside the bund, such as a cyclone wire fence
masonry systems, they should be sealed with a or a wall.
suitable sealant material, that is impervious to, and
Minor Storage – For sites where only a few drums are
compatible with, the liquids to be contained.
to be stored, say less than 1200 litres, it is generally
Pipes – may be installed through the bund or floor if it satisfactory to provide alternatives to a bund. The
is essential, provided that the junctions are sealed drums should be stored such that:
with a suitable sealant material, that is impervious to,
* recovery of spilt material is possible;
and compatible with, the liquids to be contained.
* they are undercover and on an impervious base;
Vehicles – where access is required into a bunded
* they are away from stormwater drains and pits;
area, ramps or roll-over bunds should be used to
maintain effective bund height. * good operational procedures are used; and
EPA Victoria
2
BUNDING GUIDELINES
BUND HEIGHT based upon the above criteria may be less than
150mm.
Tanks – The gross capacity of a bunded area should
Fire Water Allowance – Where an automatic fire
be sufficient to hold at least 100% of the capacity of
sprinkler system is installed in or over any bunded
the largest tank, plus 10% of the capacity of the
tank or drum storage compound, the capacity
second largest tank, plus any other major displaced
provided should be increased by a volume equal to
volumes below the bund crest, including other tanks
the output of the sprinkler system over a period of at
and raised foundations.
least twenty minutes. In addition, provision should be
Drums – The gross capacity of a bunded area should
made for containment of fire water on site by the
be sufficient to hold at least the volume of 25% of the
design and construction of adequate drainage
(maximum design number of) drums to be stored up to
controls and formulation of appropriate contingency
10kL, plus 10% of any volume in excess thereof.
plans.
If used empty drums are stored with other drums, then
the bund should be provided with a height which
STORMWATER CONTROL
assumes all drums to be full.
The preferred approach is that a bunded area be
Tank Vehicle Loading – The capacity of a bunded
located undercover. However, where this is not
area should at least equal the greater of:
practicable, the treatment and/or disposal of
* 100% of the largest compartment of any tank
stormwater collected in bunded areas should be
vehicle using the filling facility or 9000 L, which
determined on a site specific basis in consultation
ever is less; or
with an authorised EPA officer, in particular the
* the maximum quantity capable of being following points should be considered.
discharged from the two filling points having the
Bunds should be provided with facilities to transfer
greatest flow during a period of two minutes.
accumulated stormwater to:
Potentially Contaminated Areas – Areas designated
* the sewer (subject to approval of the local
for used drum storage or crushing, manifolds, pump
sewerage authority);
stands and materials transfer should be controlled in
* storage prior to disposal to a site licensed by the
accordance with this guideline.
EPA to accept this waste; or
Stormwater Allowance – Areas required to be bunded
* the stormwater drainage system, subject to
or controlled and which are not considered to be
written approval of the EPA, typically including
under cover, should be provided with a minimum bund
discharge licence requirements for on-site
height of 150mm.
primary treatment.
For example, for outdoor storage, transfer and
In some cases, it may be possible to incorporate a two
potentially contaminated areas the bund should be at
way valve system which will allow all contaminated
least 150mm high, even though the calculated height
Information Bulletin
3
BUNDING GUIDELINES
stormwater to be discharged to the sewerage system cases the written approval of the EPA should be
(subject to approval of the local sewerage authority). obtained prior to the commencement of works.
EPA Victoria
4
BUNDING GUIDELINES
Information Bulletin
5