Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

Pekerjaan : Pembangunan Jembatan Rangka Baja

NO. URAIAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A. PEKERJAAN PERSIAPAN
1. Peninjauan dan pengambilan data Ls 1.00 Rp 525,000,000.00 Rp 525,000,000.00
lapangan
JUMLAH Rp 525,000,000.00

B. PEKERJAAN TANAH
1. Galian biasa m3 750.00 Rp 89,619.00 Rp 67,214,250.00
2. Urugan biasa m3 281.00 Rp 105,775.00 Rp 29,722,775.00
JUMLAH Rp 96,937,025.00

C. PEKERJAAN STRUKTUR JEMBATAN


1. Pengadaan struktur jembatan rangka kg 409,249.02 Rp 25,849.80 Rp 10,579,005,317.20
60 m
2. Pemasangan struktur jembatan rangka kg 409,249.02 Rp 3,108.00 Rp 1,271,945,954.16
60 m
3. Dinding sumuran silinder terpasang m 12.00 Rp 9,047,437.31 Rp 108,569,247.71
diameter 350 cm
4. Dinding sumuran silinder terpasang m 12.00 Rp 11,442,934.09 Rp 137,315,209.06
diameter 400
5. Abutment
a. Baja Tulangan U 24 Polos kg 961.72 Rp 14,225.26 Rp 13,680,717.05
b. Baja tulangan U 32 Ulir kg 8,025.10 Rp 20,544.59 Rp 164,872,389.21
c. Beton mutu sedang Fc' 25 Mpa m3 116.06 Rp 1,525,738.68 Rp 177,077,231.20
d. Beton mutu rendah Fc' 15 Mpa m3 6.29 Rp 1,058,707.53 Rp 6,659,270.36
6. Bearing perletakan jembatan bh 4.00 Rp 10,000.00 Rp 40,000.00
7. Slab beton Fc' 350 Mpa m3 131.79 Rp 1,451,742.63 Rp 191,326,612.95
JUMLAH Rp 12,650,491,948.90

D. PEKERJAAN PERKERASAN
Lapis pondasi agregat kelas A m3 33.93 Rp 270,000.00 Rp 9,161,100.00
Lapis pondasi agregat kelas B m3 18.27 Rp 280,000.00 Rp 5,115,600.00
Prime coat ltr 83.52 Rp 21,000.00 Rp 1,753,920.00
Aspal m3 24.01 Rp 1,300,000.00 Rp 31,215,600.00
Tack coat ltr 36.54 Rp 17,500.00 Rp 639,450.00
JUMLAH Rp 47,885,670.00

JUMLAH KESELURUHAN PEKERJAAN Rp 13,320,314,643.90


PPN (10%) Rp 1,332,031,464.39
JUMLAH KESELURUHAN PEKERJAAN +
Rp 14,652,346,108.30
PPN (10%)

TERBILANG :
EMPAT BELAS MILIYAR ENAM RATUS LIMA PULUH DUA JUTA TIGA RATUS EMPAT PULUH
ENAM RIBU SERATUS DELAPAN RUPIAH
EMPAT BELAS MILIYAR ENAM RATUS LIMA PULUH DUA JUTA TIGA RATUS EMPAT PULUH
ENAM RIBU SERATUS DELAPAN RUPIAH

Anda mungkin juga menyukai