NO. URAIAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A. PEKERJAAN PERSIAPAN
1. Peninjauan dan pengambilan data Ls 1.00 Rp 525,000,000.00 Rp 525,000,000.00
lapangan
JUMLAH Rp 525,000,000.00
B. PEKERJAAN TANAH
1. Galian biasa m3 750.00 Rp 89,619.00 Rp 67,214,250.00
2. Urugan biasa m3 281.00 Rp 105,775.00 Rp 29,722,775.00
JUMLAH Rp 96,937,025.00
D. PEKERJAAN PERKERASAN
Lapis pondasi agregat kelas A m3 33.93 Rp 270,000.00 Rp 9,161,100.00
Lapis pondasi agregat kelas B m3 18.27 Rp 280,000.00 Rp 5,115,600.00
Prime coat ltr 83.52 Rp 21,000.00 Rp 1,753,920.00
Aspal m3 24.01 Rp 1,300,000.00 Rp 31,215,600.00
Tack coat ltr 36.54 Rp 17,500.00 Rp 639,450.00
JUMLAH Rp 47,885,670.00
TERBILANG :
EMPAT BELAS MILIYAR ENAM RATUS LIMA PULUH DUA JUTA TIGA RATUS EMPAT PULUH
ENAM RIBU SERATUS DELAPAN RUPIAH
EMPAT BELAS MILIYAR ENAM RATUS LIMA PULUH DUA JUTA TIGA RATUS EMPAT PULUH
ENAM RIBU SERATUS DELAPAN RUPIAH