ANALISA HARGA SATUAN BOW


PEKERJAAN KAYU
HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN
ANALISA
( Rp )
A. PEKERJAAN PONDASI KAYU
A.1.BOW SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 2,00 M
DICINCIN, DILANCIP DAN DITUMBUK

0.0200 M3 Balok ulin @ 1,537,571.94   30,751.44


0.5100 OH tukang kayu @ 55,000.00  
0.8750 OH pekerja @ 45,000.00  
0.0510 OH kepala tukang @ 60,000.00  
0.0440 OH mandor @ 60,000.00  
JUMLAH 30,751.44
A.2 SEBUAH TONGKAT ULIN UK.12/12 CM TINGGI 8,00 M
2 SAMBUNGAN DGN PIPA GALVANIS
0.0800 M3 Balok ulin @ 1,537,571.94   123,005.76
0.5100 OH tukang kayu @ 55,000.00  
0.8750 OH pekerja @ 45,000.00  
0.0510 OH kepala tukang @ 60,000.00  
0.0440 OH mandor @ 60,000.00  
JUMLAH 123,005.76
A.3 SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 4,00 M'
0.0400 M3 Balok ulin @ 1,537,571.94   61,502.88
0.5100 OH tukang kayu @ 55,000.00  
0.8750 OH pekerja @ 45,000.00  
0.0510 OH kepala tukang @ 60,000.00  
0.0440 OH mandor @ 60,000.00  
JUMLAH 61,502.88
A. 4 1 M3 MENGERJAKAN PAPAN SIRING KAYU ULIN
1.1000 M3 papan siring kayu ulin @ 1,737,571.94   1,911,329.13
3.0000 kg paku ulin @ 13,750.00   41,250.00
15.0000 OH tukang kayu @ 55,000.00  
4.0000 OH pekerja @ 45,000.00  
1.5000 OH kepala tukang @ 60,000.00  
0.2000 OH mandor @ 60,000.00  
JUMLAH 1,952,579.13 1,
A. 5 1 M3 RANGKA BAWAH KAYU ULIN ( tiang + kalang, sunduk )
1.1000 M3 balok ky ulin @ 1,537,571.94   1,691,329.13
15.0000 OH tukang kayu @ 55,000.00  
5.0000 OH pekerja @ 45,000.00  
1.5000 OH kepala tukang @ 60,000.00  
0.2500 OH mandor @ 60,000.00  
JUMLAH 1,691,329.13 1,

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 1/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

ANALISA HARGA SATUAN BOW


PEKERJAAN KAYU
HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN U
ANALISA
( Rp ) (
B. PEKERJAAN LANTAI KAYU
B. 1 1 M3 MENGERJAKAN SLOOF DAN GELAGAR KY ULIN
1.1000 M3 balok ky ulin @ 1,537,571.94   1,691,329.13
10.0000 Kg paku ulin @ 13,750.00   137,500.00
15.0000 OH tukang kayu @ 55,000.00   8
5.0000 OH pekerja @ 45,000.00   2
1.5000 OH kepala tukang @ 60,000.00  
0.2500 OH mandor @ 60,000.00  
JUMLAH 1,828,829.13 1,1
B. 2 1 M2 LANTAI PAPAN KAYU ULIN DIKETAM
0.0254 M3 papan kayu ulin @ 1,737,571.94   44,134.33
0.2500 Kg paku ulin @ 13,750.00   3,437.50
0.8000 OH tukang kayu @ 55,000.00  
0.2800 OH pekerja @ 45,000.00  
0.0800 OH kepala tukang @ 60,000.00  
0.0140 OH mandor @ 60,000.00  
JUMLAH 47,571.83
B. 3 1 M2 LANTAI PAPAN KAYU MERANTI DIKETAM
0.0254 M3 papan kayu meranti klas 1 @ 1,187,571.94   30,164.33
0.2500 Kg paku biasa @ 11,825.00   2,956.25
0.8000 OH tukang kayu @ 55,000.00  
0.2800 OH pekerja @ 45,000.00  
0.0800 OH kepala tukang @ 60,000.00  
0.0140 OH mandor @ 60,000.00  
JUMLAH 33,120.58
B. PEKERJAAN DINDING KAYU
B. 4 1 M3 MENGERJAKAN RANGKA RUMAH KAYU ULIN (termasuk kusen)
1.1000 M3 balok ky ulin @ 1,537,571.94   1,691,329.13
5.0000 Kg paku ulin @ 13,750.00   68,750.00
20.0000 OH tukang kayu @ 55,000.00   1,1
10.0000 OH pekerja @ 45,000.00   4
2.0000 OH kepala tukang @ 60,000.00   1
0.5000 OH mandor @ 60,000.00  
JUMLAH 1,760,079.13 1,7

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 2/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

ANALISA HARGA SATUAN BOW

HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN U
ANALISA
( Rp ) (
B. 5 1 M3 MENGERJAKAN RANGKA RUMAH KAYU MERANTI (termasuk kusen)
1.1000 M3 balok ky meranti @ 1,037,571.94   1,141,329.13
5.0000 Kg paku biasa @ 11,825.00   59,125.00

20.0000 OH tukang kayu @ 55,000.00   1,1


10.0000 OH pekerja @ 45,000.00   4
2.0000 OH kepala tukang @ 60,000.00   1
0.5000 OH mandor @ 60,000.00  
JUMLAH 1,200,454.13 1,7

B. 6 1 M2 DINDING PAPAN ULIN DIKETAM


0.0240 M3 papan kayu ulin @ 1,737,571.94   41,701.73
0.2000 Kg paku ulin @ 13,750.00   2,750.00
0.8000 OH tukang kayu @ 55,000.00  
0.2800 OH pekerja @ 45,000.00  
0.0800 OH kepala tukang @ 60,000.00  
0.0100 OH mandor @ 60,000.00  
JUMLAH 44,451.73

B. 7 1 M2 DINDING PAPAN MERANTI DIKETAM


0.0240 M3 papan kayu meranti @ 1,187,571.94   28,501.73
0.2000 Kg paku biasa @ 11,825.00   2,365.00
0.8000 OH tukang kayu @ 55,000.00  
0.2800 OH pekerja @ 45,000.00  
0.0800 OH kepala tukang @ 60,000.00  
0.0100 OH mandor @ 60,000.00  
JUMLAH 30,866.73

B. 8 1 M2 DINDING SUSUN SIRIH PAPAN MERANTI


0.0250 M3 papan kayu meranti @ 1,187,571.94   29,689.30
0.1500 Kg paku biasa @ 11,825.00   1,773.75
0.4000 OH tukang kayu @ 55,000.00  
0.1400 OH pekerja @ 45,000.00  
0.0400 OH kepala tukang @ 60,000.00  
0.0070 OH mandor @ 60,000.00  
JUMLAH 31,463.05

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 3/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

ANALISA HARGA SATUAN BOW

HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN U
ANALISA
( Rp ) (
B. 9 1 M2 DINDING PAPAN MERANTI SUSUN SIRIH DIKETAM
0.0250 M3 papan kayu meranti @ 1,187,571.94   29,689.30
0.2000 Kg paku biasa @ 11,825.00   2,365.00
0.8000 OH tukang kayu @ 55,000.00  
0.2800 OH pekerja @ 45,000.00  
0.0800 OH kepala tukang @ 60,000.00  
0.0100 OH mandor @ 60,000.00  
JUMLAH 32,054.30

B. 10 1 M2 MENGERJAKAN DINDING PARTISI KAYU


MERANTI DAN LAPISAN MULTIPLEK 9 MM
0.0210 M3 papan kayu meranti @ 1,187,571.94   24,939.01
0.7000 LBR Multiplek 9 mm @ 150,000.00   105,000.00
0.0400 KG Paku biasa @ 11,825.00   473.00
0.0400 KG Paku plywood @ 20,000.00   800.00
0.0150 OH Tukang kayu @ 55,000.00  
0.8000 OH Pekerja @ 45,000.00  
0.0150 OH kepala tukang @ 60,000.00  
0.0400 OH Mandor @ 60,000.00  
JUMLAH 131,212.01

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 4/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

DAFTAR ONGKOS ANGKUT MATERIAL

BIDANG : CIPTA KARYA


TAHUN : Juli 2006
JARAK ANGKUT JARAK ANGKUT
HARGA RATA-RATA 0 - 15 RATA-RATA 16 - 30
NO MATERIAL SAT
MATERIAL ONGKOS ONGKOS ONG
JUMLAH JUMLAH
ANGKUT ANGKUT ANG
1 Balok Klas I Bangkirai m3 1,700,000.00 123,950.58 1,823,950.58 154,938.22 1,854,938.22 185
2 Balok Klas I Ulin m3 1,300,000.00 123,950.58 1,423,950.58 154,938.22 1,454,938.22 185
3 Balok Kayu Meranti m3 800,000.00 123,950.58 923,950.58 154,938.22 954,938.22 185
4 Batu Gunung m3 65,000.00 35,945.67 100,945.67 66,933.31 131,933.31 97
5 Kayu Klas 2 m3 650,000.00 123,950.58 773,950.58 154,938.22 804,938.22 185
6 Kayu galam dia 10 - 12 cm btg 9,500.00 123,950.58 133,450.58 154,938.22 164,438.22 185
7 Kerikil Beton / Split ( 2-3 cm ) m3 165,000.00 35,945.67 200,945.67 66,933.31 231,933.31 97
8 Koral m3 165,000.00 35,945.67 200,945.67 66,933.31 231,933.31 97
9 Papan Kayu Bangkirai m3 1,900,000.00 123,950.58 2,023,950.58 154,938.22 2,054,938.22 185
10 Papan Kayu Ulin m3 1,500,000.00 123,950.58 1,623,950.58 154,938.22 1,654,938.22 185
11 Papan Kayu kelas 2 m3 800,000.00 123,950.58 923,950.58 154,938.22 954,938.22 185
12 Papan Kayu Meranti m3 950,000.00 123,950.58 1,073,950.58 154,938.22 1,104,938.22 185
13 Pasir Beton m3 175,000.00 35,945.67 210,945.67 66,933.31 241,933.31 97
14 Pasir Pasang sungai m3 175,000.00 35,945.67 210,945.67 66,933.31 241,933.31 97
15 Pasir pasang putih m3 100,000.00 35,945.67 135,945.67 66,933.31 166,933.31 97
16 Pasir Urug m3 50,000.00 35,945.67 85,945.67 66,933.31 116,933.31 97
17 Sirtu m3 60,000.00 35,945.67 95,945.67 66,933.31 126,933.31 97
18 Tanah Urug m3 13,500.00 35,139.99 48,639.99 66,127.63 79,627.63 97

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 5/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

DAFTAR HARGA SATUAN UPAH DAN BAHAN

BIDANG : Cipta Karya


TAHUN ANGGARAN : 2006

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

1  2 3 4 = 6+5 5 6

A UPAH KERJA
1 Pekerja ( Buruh semi terlatih ) Hari 45,000.00 -   45,000.00
2 Tukang Batu Hari 55,000.00 -   55,000.00
3 Tukang Kayu Hari 55,000.00 -   55,000.00
4 Tukang Besi Hari 55,000.00 -   55,000.00
5 Tukang Cat Hari 55,000.00 -   55,000.00
6 Kepala Tukang Hari 60,000.00 -   60,000.00
7 Mandor Hari 60,000.00 -   60,000.00
8 Sopir Hari 50,000.00 -   50,000.00
9 Pembantu Sopir Hari 40,000.00 -   40,000.00

B Harga Bahan
1 Aluminium foil single sided Roll 450,000.00 -   450,000.00
2 Ampelas Lbr 2,500.00 -   2,500.00
3 Atap Asbes Gelombang Besar Lbr 23,000.00 -   23,000.00
4 Atap Genteng Kodok Bh 1,550.00 -   1,550.00
5 Atap Metal Berkualitas ( 2 ssn, 8 daun ) Lbr 40,000.00 -   40,000.00
6 Atap Plastik gelombang 60 x 170 Lbr 14,500.00 -   14,500.00
7 Atap Sirap Ikat 50,000.00 -   50,000.00
8 Atap Tilux Bh 21,000.00 -   21,000.00
9 Bahan Plafond Asbes Semen 5 mm M2 21,000.00 -   21,000.00
10 Bahan Plafond eternit 4 mm M2 25,000.00 -   25,000.00

11 Bahan Plafond Hardplex 5 mm 120 x 130 Lbr 42,500.00 -   42,500.00


12 Bahan Politur ( sirlak ) India Kg 32,000.00 -   32,000.00
13 Bak Air Fiber (60 x 60 cm) Bh 145,000.00 -   145,000.00
14 Bak Air Fiber (60 x 80 cm) Bh 185,000.00 -   185,000.00
15 Bak Cuci Piring Stainles Lobang 1 Bh 195,000.00 -   195,000.00
16 Bak Cuci Piring Stainles Lobang 2 Bh 250,000.00 -   250,000.00
17 Bak Kontrol 50 x 50 x 40 cm Bh 75,000.00 -   75,000.00
18 Bak air Traso Besar Bh 185,000.00 -   185,000.00
19 Balok Klas I Bangkirai M3 1,937,571.94 237,571.94 1,700,000.00
20 Balok Klas I Ulin M3 1,537,571.94 237,571.94 1,300,000.00
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 6/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

21 Balok Kayu Meranti M3 1,037,571.94 237,571.94 800,000.0


22 Batako Bh 1,500.00 -   1,500.0
23 Batu alam M2 120,000.00 -   120,000.0
24 Batu Bata Bh 550.00 -   550.0
25 Batu apung Kg 15,125.00 -   15,125.0
26 Batu Gunung M3 214,567.03 149,567.03 65,000.0
27 Baut Bh 2,000.00 -   2,000.0
28 Bensin Lt 4,500.00 -   4,500.0
29 Besi Beton Polos Dia 6 - 22 mm Kg 11,000.00 -   11,000.0
30 Besi Beton Ulir Dia 6 - 22 mm Kg 16,000.00 -   16,000.0
31 Besi penggantung plafond Kg 11,000.00 -   11,000.0
32 Besi strip Kg 18,000.00 -   18,000.0
33 Box MCB 2 group Unit 150,000.00 -   150,000.0
34 Box MCB 4 group Unit 250,000.00 -   250,000.0

35 Breaker Bh 20,000.00 -   20,000.0


36 Buis Beton Dia 80 cm tanpa tulangan Bh 364,000.00 -   364,000.0
39 Buis Beton Dia 100 cm tanpa tulangan Bh 450,000.00 -   450,000.0
41 Cat Air / tembok Kg 15,400.00 -   15,400.0
42 Cat besi Kg 25,000.00 -   25,000.0
43 Cat Dasar / plamir Kg 22,500.00 -   22,500.0
44 Cat Kilap / Kayu Kg 35,000.00 -   35,000.0
45 Cat Menie kayu Kg 13,000.00 -   13,000.0
46 Closed Jongkok Keramik berkualitas Bh 120,000.00 -   120,000.0
47 Closed Jongkok Keramik Toto Bh 125,000.00 -   125,000.0
48 Closed Jongkok Teraso Bh 80,000.00 -   80,000.0
49 Closet Duduk Type Keramik Berkualitas Unit 1,200,000.00 -   1,200,000.0

50 Daun Jendela Uk. Besar (Fabrikasi) Kc 5 mm Bh 250,000.00 -   250,000.0


51 Daun Jendela Uk. Kecil (Fabrikasi) Kc 5 mm Bh 200,000.00 -   200,000.0
52 Daun Pintu Plywood Bag. Dlm Lapis Aluminium Foil Bh 350,000.00 -   350,000.0
53 Daun Ventilasi Bh 60,000.00 -   60,000.0
54 Dempul Halus ( INFRA ) Kg 25,000.00 -   25,000.0
55 Dempul kayu Kg 12,500.00 -   12,500.0
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 7/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

56 Dempul Politur Kg 12,500.00 -   12,500.0


57 Engsel Jendela Lokal 3 " Bh 20,000.00 -   20,000.0

58 Engsel Pintu Lokal 5 " Bh 25,000.00 -   25,000.0


59 Espagnolet Bh 125,000.00 -   125,000.0
60 Floor Drain Bh 17,500.00 -   17,500.0
61 Formika Ukuran Pintu Lbr 75,000.00 -   75,000.0
62 Genteng keramik Bh 8,500.00 -   8,500.0
63 Glass block Bh 18,500.00 -   18,500.0
64 Grendel Jendela Bh 7,500.00 -   7,500.0
65 Grendel Pintu Bh 12,500.00 -   12,500.0
66 Grendel tanam Pintu Bh 25,000.00 -   25,000.0
67 Gypsum board, t = 9 mm Lbr 45,000.00 -   45,000.0
68 Hak Angin Bh 8,000.00 -   8,000.0
69 Handle Jendela putih Bh 5,000.00 -   5,000.0
70 Handle Pintu Bh 16,500.00 -   16,500.0
71 Jalusi Atap Bh 425,000.00 -   425,000.0
72 Jalusi Kayu Bangkirai M' 15,000.00 -   15,000.0
73 Kabel NGA 2,5 Rol 155,000.00 -   155,000.0
74 Kaca Naco ( kerangka/daun ) 5 mm Set 150,000.00 -   150,000.0
75 Kaca polos 2 mm M2 32,000.00 -   32,000.0
76 Kaca polos 3 mm M2 48,000.00 -   48,000.0
77 Kaca polos 5 mm M2 80,000.00 -   80,000.0
78 Kaca Rayben 5 mm M2 95,000.00 -   95,000.0
79 Kanopi Atap Bh 325,000.00 -   325,000.0
80 Kawat Bendrat / Beton Kg 10,000.00 -   10,000.0
81 Kawat Bronjong Kg 27,500.00 -   27,500.0
82 Kawat Duri Kg 11,000.00 -   11,000.0
83 Kawat Harmonika m2 37,500.00 -   37,500.0
84 Kawat nyamuk besi m2 10,000.00 -   10,000.0
85 Kawat nyamuk plastik m2 5,000.00 -   5,000.0
86 Kayu Klas 2 M3 650,000.00 -   650,000.0
87 Kayu galam dia 10 - 12 cm Btg 9,500.00 -   9,500.0
88 Keramik 10 x 20 cm M2 35,000.00 -   35,000.0
89 Keramik 20 x 25 cm M2 44,000.00 -   44,000.0
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 8/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

90 Keramik 20 x 20 cm M2 44,000.00 -   44,000.0


91 Keramik 30 x 30 cm Halus M2 37,000.00 -   37,000.0

92 Keramik 30 x 30 cm Kasar M2 41,000.00 -   41,000.0


93 Keramik 40 x 40 anti slip M2 49,500.00 -   49,500.0
94 Karet Talang M' 5,500.00 -   5,500.0
95 Kerikil Beton / Split ( ukuran 2-3 cm ) M3 314,567.03 149,567.03 165,000.0
96 Koral M3 314,567.03 149,567.03 165,000.0
97 Kran Air Dia 1" Bh 25,000.00 -   25,000.0
98 Kran Air Dia 3/4 Bh 20,000.00 -   20,000.0
99 Kuas 3 " Bh 7,500.00 -   7,500.0
100 Kunci Pintu 2 Slag berkualitas Bh 150,000.00 -   150,000.0
101 Kunci Pintu Double Ex Cisa Bh 350,000.00 -   350,000.0
102 Kunci Pintu Double Lengkap Dgn Accecories Bh 750,000.00 -   750,000.0
103 Kunci Pintu Tanam antik Bh 125,000.00 -   125,000.0

104 Kusen aluminium 1 -   -


105 Kusen aluminium 2 -   -
106 Kusen aluminium 3 -   -
107 Lampu 2 - TL 40 Watt Double + Instalasi Bh 150,000.00 -   150,000.0
108 Lampu Merkury 250 wt Bh 165,000.00 -   165,000.0
109 Lampu Pijar 10 Watt Bh 3,500.00 -   3,500.0
110 Lampu Pijar 100 Watt Bh 15,000.00 -   15,000.0
111 Lampu Pijar 15 Watt Bh 3,850.00 -   3,850.0
112 Lampu Pijar 25 Watt Bh 4,500.00 -   4,500.0
113 Lampu Pijar 40 Watt Bh 10,000.00 -   10,000.0
114 Lampu Pijar 5 Watt Bh 3,500.00 -   3,500.0
115 Lampu Pijar 60 Watt Bh 5,500.00 -   5,500.0
116 Lampu Philip SL 20 Watt + Fitting Bh 50,000.00 -   50,000.0
117 Lampu TL Philip + Fitting 20 Watt Bh 37,000.00 -   37,000.0
118 Lampu TL 20 Watt Double (Trafo) Bh 125,000.00 -   125,000.0
119 Lampu TL 40 Watt (Trafo) Bh 85,000.00 -   85,000.0
120 Lampu TL 40 Watt Double (Trafo) Bh 160,000.00 -   160,000.0
121 Lem Kayu ( Fox ) Ltr 9,500.00 -   9,500.0
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 9/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

122 Lem Paralon Bh 5,000.00 -   5,000.0


123 List Cornice Gypsum M' 15,000.00 -   15,000.00

124 List Plafond Gypsum M' 30,000.00 -   30,000.00


125 List Plafond Plywood M' 1,500.00 -   1,500.0
126 List Profil Sudut 3/5 Ky Bangkirai M' 4,250.00 -   4,250.0
127 List Profil Sudut 3/5 Ky Meranti M' 3,750.00 -   3,750.0
128 Listplank kayu ukir M' 37,692.62 -   37,692.62
129 List plafond gypsum M' 31,250.00 -   31,250.00
130 Macam2 Sambungan PVC AW Dia 1 " Bh 3,500.00 -   3,500.0
131 Macam2 Sambungan PVC AW Dia 1/2 " Bh 2,000.00 -   2,000.0
132 Macam2 Sambungan PVC AW Dia 2 " Bh 5,000.00 -   5,000.0
133 Macam2 Sambungan PVC AW Dia 3/4 " Bh 6,500.00 -   6,500.0
134 Macam2 Sambungan PVC AW Dia 4 " Bh 11,000.00 -   11,000.00
135 Marmer lokal m2 -   -

136 Minyak cat Ltr 12,500.00 -   12,500.00


137 Minyak bekisting Ltr 5,000.00 -   5,000.0
138 Multiplek 4 mm Lbr 67,000.00 -   67,000.00
139 Multiplek 6 mm Lbr 100,000.00 -   100,000.00
140 Multiplek 9 mm Lbr 150,000.00 -   150,000.00
141 Multiplek 15 mm Lbr 250,000.00 -   250,000.00
142 Multiplek 18 mm Lbr 300,000.00 -   300,000.00
143 Multiplex 12 mm Lbr 200,000.00 -   200,000.00
144 Nok Genteng Kodok Bh 2,000.00 -   2,000.0
145 Nok Genteng keramik Bh 19,500.00 -   19,500.00
146 Nok Model U ukuran 110 x 5 x 6 cm M' 35,000.00 -   35,000.00
147 Nok Model U Verza Roof 40 x 12 cm Bh 18,000.00 -   18,000.00
148 Oker Kg 15,000.00 -   15,000.00
149 Oli / pelumas Ltr 24,750.00 -   24,750.00
150 Pagar besi motif BRC 1,2 x 2,4 m' M' 297,916.67 -   297,916.6
151 Pagar besi motif BRC 1,75 x 2,4 m' M' 343,750.00 -   343,750.00
152 Paku Asbes + Karet Kg 16,000.00 -   16,000.00
153 Paku Beton Bh 250.00 -   250.00
154 Paku bor Kg 25,000.00 -   25,000.00
155 Paku Genteng metal Kg 27,500.00 -   27,500.00
156 Paku Kayu / biasa Kg 11,825.00 -   11,825.00
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 10/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

157 Paku Keling Kg 25,000.00 -   25,000.0


158 Paku Seng Kg 14,300.00 -   14,300.0

159 Paku Ulin Kg 13,750.00 -   13,750.0


160 Paku Plywood Kg 20,000.00 -   20,000.0
161 Paku Sekrup Kg 14,300.00 -   14,300.0
162 Papan Kayu Bangkirai M3 2,137,571.94 237,571.94 1,900,000.0
163 Papan Kayu Ulin M3 1,737,571.94 237,571.94 1,500,000.0
164 Papan Kayu kelas 2 M3 1,037,571.94 237,571.94 800,000.00
165 Papan Kayu Meranti M3 1,187,571.94 237,571.94 950,000.00
166 Papan Nama Proyek Bh 350,000.00 -   350,000.00
167 Papan Reuter Bengkirai M' 26,900.00 -   26,900.0
168 Pas. Lampu Baret + Instalasi Unit 375,000.00 -   375,000.00
169 Pas. Lampu Gantung Unit 450,000.00 -   450,000.00
170 Pasir Beton M3 324,567.03 149,567.03 175,000.00

171 Pasir Pasang sungai M3 324,567.03 149,567.03 175,000.00


172 Pasir pasang putih M3 249,567.03 149,567.03 100,000.00
173 Pasir Urug M3 199,567.03 149,567.03 50,000.0
174 Paving blok biasa bh 2,000.00 -   2,000.0
175 Paving block K - 127 m2 75,000.00 -   75,000.0
176 Penangkal Petir + Instalasi unit 5,500,000.00 -   5,500,000.0
177 Pintu Panel Double ky Bangkirai Bh 700,000.00 -   700,000.00
178 Pintu Double Plywood Bh 250,000.00 -   250,000.00
179 Pintu Panel ky Bangkirai Uk. Besar L 80 cm Bh 425,000.00 -   425,000.00
180 Pintu Panel ky Bangkirai Uk. Kecil L 70 cm Bh 350,000.00 -   350,000.00
181 Pintu Panel kayu Ulin Ukuran Besar L 80 cm Bh 350,000.00 -   350,000.00
182 Pintu Panel kayu Ulin Ukuran Kecil L 70 cm Bh 300,000.00 -   300,000.00
183 Pintu Panel Lapis Formika (Fabrikasi) Bh 335,000.00 -   335,000.00
184 Pintu Skat Bh 200,000.00 -   200,000.00
185 Pipa Galvanis AW Dia 1 " M' 15,000.00 -   15,000.0
186 Pipa Galvanis AW Dia 2 " M' 30,000.00 -   30,000.0
187 Pipa Galvanis AW Dia 3 " M' 93,000.00 -   93,000.0
188 Pipa Galvanis AW Dia 4 " M' 110,000.00 -   110,000.00
189 Pipa PVC AW Dia 1 " Btg 25,000.00 - 25,000.0
190 Pipa PVC AW Dia 1/2 " Btg 12,500.00 - 12,500.0
191 Pipa PVC AW Dia 2 " Btg 45,000.00 - 45,000.0
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 11/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

192 Pipa PVC AW Dia 3/4 " Btg 15,000.00 - 15,000.0


193 Pipa PVC AW Dia 4 " Btg 85,000.00 - 85,000.0
194 Pipa stainless steel 2 " M' 30,250.00 -   30,250.0
195 Pipa stainless steel 3 " M' 37,812.00 -   37,812.0
196 Pitting Bh 6,000.00 -   6,000.0
197 Plamir Kg 28,000.00 -   28,000.0
198 Plitur Kg 8,500.00 -   8,500.0
199 Plint / list lantai keramik Bh 3,500.00 -   3,500.0
200 Plint marmer 10 x 40 cm Bh 12,500.00 -   12,500.0
201 Plywood 3 mm Lbr 46,000.00 -   46,000.0
202 Plywood 4 mm Lbr 61,500.00 -   61,500.0
203 Plywood 6 mm Lbr 92,000.00 -   92,000.0
204 Plywood 12 mm Lbr 184,000.00 -   184,000.00
205 Plywood 15 mm Lbr 230,000.00 -   230,000.00

206 Plywood 18 mm Lbr 276,000.00 -   276,000.00


207 Porselen 20 x 20 cm Bh 2,500.00 -   2,500.0
208 Polycarbonat -   -
209 Rangka besi hollow M' 60,000.00 -   60,000.0
210 Rol Cat Tembok Bh 20,000.00 -   20,000.0
211 Rolling door -   -
212 Roster beton 20 x 20 cm Bh 3,000.00 -   3,000.0
213 Roster beton 20 x 30 cm Bh 4,000.00 -   4,000.0
214 Roster kayu bangkirai 20 x 20 cm Bh 60,000.00 -   60,000.0
215 Rumput Hias M2 25,000.00 -   25,000.0
216 Saklar Ganda Bh 19,250.00 -   19,250.0
217 Saklar Tunggal Bh 16,500.00 -   16,500.0
218 Sekering Kas 3 Group + Instalasi Unit 100,000.00 -   100,000.00
219 Semen Abu - Abu / PC ( 50 kg/Zak ) Zak 43,000.00 -   43,000.0
220 Semen Warna Kg 1,600.00 -   1,600.0
221 Semen putih Kg 1,200.00 -   1,200.0
222 Seng gelombang Besar / kecil Lbr 30,000.00 -   30,000.0
223 Seng Plat Lbr 35,000.00 -   35,000.0
224 Septictank ( 3 x 1,5 )+Resapan (1,5 x 1,5 ) Unit 4,550,000.00 -   4,550,000.0
225 Septictank Kayu Unit 1,650,000.00 -   1,650,000.0
T. A 2006

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 12/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

 JUMLAH HARGA BIAYA HARGA DASAR


NO URAIAN SAT  
SATUAN  ANGKUT  TANPA PAJAK

226 Sirlak Kg 27,000.00 -   27,000.00


227 Sirtu m3 209,567.03 149,567.03 60,000.00

228 Solar Ltr 6,321.00 -   6,321.00


229 Spritus Ltr 5,000.00 -   5,000.00
230 Stop Kontak Bh 18,000.00 -   18,000.00
231 Talang Air PVC Maspion M' 25,000.00 -   25,000.00
232 Tambah daya Listrik Wt 2,500.00 -   2,500.00
233 Tanah Urug M3 162,261.35 148,761.35 13,500.00
234 Tandon Air 2 x 1200 ltr + Menara + Atap Unit 3,950,000.00 -   3,950,000.00
235 Tandon Air 1 x 1200 ltr + Menara + Atap Unit 1,975,000.00 -   1,975,000.00
236 Tangga Naik Tinggi 1 m Bh 210,000.00 -   210,000.00
237 Tanki Air Viberglass 1200 Ltr Bh 850,000.00 -   850,000.00
238 Tanki Air Viberglass 2500 Ltr Bh 1,850,000.00 -   1,850,000.00
239 Tanki Air Viberglass 550 Ltr Bh 650,000.00 -   650,000.00
240 Teakwood 3 mm Lbr 85,000.00 -   85,000.00
241 Teakwood 4 mm Lbr 113,500.00 -   113,500.00
242 Teakwood 6 mm Lbr 170,000.00 -   170,000.00
243 Ter / Residu Kg 5,000.00 -   5,000.00
244 Terpentin Ltr 2,500.00 -   2,500.00
245 Tiang Lampu Tunggal 11 m' Bt 1,950,000.00 -   1,950,000.00
246 Tiang Lampu Tunggal 9 m' Bt 1,280,000.00 -   1,280,000.00
247 Tiang Lampu Ganda 11 m' Bt 2,300,000.00 -   2,300,000.00
248 Tiang Lampu ganda 9 m' Bt 1,510,000.00 -   1,510,000.00
249 Tinner A Ltr 12,000.00 -   12,000.00
250 Titik Mata Lampu Ttk 130,000.00 -   130,000.00
251 Trap Depan Papan Tulis Bak Lapis Keramik Bh 130,000.00 -   130,000.00
252 Ukiran jamang pada puncak Bh 312,500.00 -   312,500.00

253 Ukiran jamang pada listplank Bh 250,000.00 -   250,000.00


254 Urinoir Bh 1,500,000.00 -   1,500,000.00
255 Washtafel + Cermin Bh 450,000.00 -   450,000.00
T. A 2006

Catatan :
1. Harga diatas adalah harga disumber material ( disungai, dilokasi penggalian) khusus utk bahan
2. Untuk bahan-bahan non lokal harga tersebut adalah harga toko / harga yang berlaku dipasaran
3. Harga sudah terrmasuk keuntungan kontraktor dan ongkos angkut
4. Ongkos angkut tergantung jarak lokasi pekerjaan ke Quary ( sampel jarak angkut 46 - 70 )
5. Harga belum termasuk PPn

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 13/160


5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 14/160


5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 15/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

ANALISA HARGA SATUAN SNI 2006

HAR
KODE
INDEK SATUAN URAIAN HARGA SATUAN ( Rp ) BAHAN
ANALISA
( Rp )
A. PEKERJAAN PERSIAPAN
A. 6.6.1 1 M' PAGAR SEMENTARA DARI KAYU TINGGI 2 M
1.2500 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   11,875.00
2.5000 kg Semen portland @ 860.00   2,150.00
0.0050 m3 Pasir beton @ 324,567.03   1,622.84
0.0090 m3 Koral beton @ 314,567.03   2,831.10
0.0720 m3 Kayu 5/7 @ 650,000.00   46,800.00
0.0600 kg Paku biasa 2'-5' @ 11,825.00   709.50
0.4000 lt Residu @ 5,000.00   2,000.00
0.2000 oh Tukang kayu @ 55,000.00
0.4000 oh Pekerja @ 45,000.00
0.0200 oh Kepala tukang @ 60,000.00
0.0200 oh Mandor @ 60,000.00
JUMLAH 67,988.44
A. 6.6.2 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M
1.2500 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   11,875.00
2.5000 kg Semen portland @ 860.00   2,150.00
1.2000 Lbr Seng gelombang 3" - 5 " @ 30,000.00   36,000.00
0.0050 m3 Pasir Beton @ 324,567.03   1,622.84
0.0090 m3 Koral beton @ 314,567.03   2,831.10
0.0720 kg Kayu 5/7 @ 650,000.00   46,800.00
0.0600 kg Paku biasa 2'-5' @ 11,825.00   709.50
0.4500 Kg Meni besi @ 25,000.00   11,250.00
0.2000 oh Tukang kayu @ 55,000.00
0.4000 oh Pekerja @ 45,000.00
0.0200 oh Kepala tukang @ 60,000.00
0.0200 oh Mandor @ 60,000.00
JUMLAH 113,238.44
A. 6.6.3 1 M' PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 M
1.2500 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   11,875.00
2.5000 kg Semen portland @ 860.00   2,150.00
25.0000 kg Kawat Duri @ 11,000.00   275,000.00
0.0050 m3 Pasir Beton @ 324,567.03   1,622.84
0.0090 m3 Koral beton @ 314,567.03   2,831.10
0.0720 kg Paku biasa 2'-5' @ 11,825.00   851.40
0.2000 oh Tukang kayu @ 55,000.00

0.3000 oh Pekerja @ 45,000.00


0.0200 oh Kepala tukang @ 60,000.00
0.0200 oh Mandor @ 60,000.00
JUMLAH 294,330.34

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 16/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

A. 6.6.4 1 M' MENGUKUR DAN MEMASANG BOUWPLANK


0.0120 m3 kayu meranti, balok @ 1,037,571.94   12,450.86
0.0200 kg Paku Biasa 2' - 5' @ 11,825.00   236.50
0.0070 m3 kayu papan 3/20 @ 1,037,571.94   7,263.00
0.1000 oh tukang kayu @ 55,000.00
0.1000 oh pekerja @ 45,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 19,950.37
A. 6.6.5 1 M2 PEMBUATAN KANTOR SEMENTARA DENGAN LANTAI PLESTERAN
1.2500 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   11,875.00
0.1800 kg Kayu @ 1,037,571.94   186,762.95
0.8500 m3 Kayu Biasa @ 1,037,571.94   881,936.15
1.1000 m3 Besi Strip @ 18,000.00   19,800.00
35.0000 kg Semen portland @ 860.00   30,100.00
0.1500 kg Pasir Pasang @ 249,567.03   37,435.05
0.1000 m3 Pasir Beton @ 324,567.03   32,456.70
0.1500 m3 Koral beton @ 314,567.03   47,185.05
30.0000 Bh Bata merah @ 550.00   16,500.00
0.2500 Lbr Seng Plat @ 30,000.00   7,500.00
2.0000 Bh Jendela Nako @ 150,000.00   300,000.00
0.0800 m2 Kaca Polos @ 80,000.00   6,400.00
0.0150 Bh Kunci Tanam @ 125,000.00   1,875.00
0.0600 Lbr Plywood 4 mm @ 61,500.00   3,690.00
2.0000 oh tukang kayu @ 55,000.00
1.0000 oh Tukang Batu @ 55,000.00
2.0000 oh pekerja @ 45,000.00
0.3000 oh Kepala tukang @ 60,000.00

0.0500 oh Mandor @ 60,000.00


JUMLAH 1,583,515.91
A. 6.6.6 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT - ALAT
1.7000 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   16,150.00
0.2100 kg Kayu @ 1,037,571.94   217,890.11
0.3000 kg Paku biasa 2'-5' @ 11,825.00   3,547.50
10.5000 kg Semen portland @ 860.00   9,030.00
0.0300 m3 Pasir Beton @ 324,567.03   9,737.01
0.0500 m3 Koral beton @ 314,567.03   15,728.35
1.5000 Lbr Seng gelombang @ 30,000.00   45,000.00
2.0000 oh Tukang kayu @ 55,000.00
1.0000 oh Pekerja @ 45,000.00
0.2000 oh Kepala tukang @ 60,000.00
0.0500 oh Mandor @ 60,000.00
JUMLAH 317,082.97

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 17/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

A. 6.6.7 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU


3.0000 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   28,500.00
0.2760 kg Kayu @ 1,037,571.94   286,369.85
0.7000 kg Paku biasa 2'-5' @ 11,825.00   8,277.50
1.5000 Lbr Seng gelombang bljs 32 @ 30,000.00   45,000.00
1.5000 oh Tukang kayu @ 55,000.00
1.0000 oh Pekerja @ 45,000.00
0.1500 oh Kepala tukang @ 60,000.00
0.0500 oh Mandor @ 60,000.00
JUMLAH 368,147.35
A. 6.6.8 1 M' MEMBERSIHKAN LAPANGAN DAN PERATAAN
0.1000 oh pekerja @ 45,000.00
0.0500 oh mandor @ 364,000.00
JUMLAH -
A. 6.6.9 1 M2 PEMBUATAN BEDENG BURUH
1.2500 btg Dolken kayu dia 8-10/4 m' @ 9,500.00   11,875.00
0.1860 kg Kayu @ 1,037,571.94   192,988.38
0.3000 Kg Paku biasa 2'-5' @ 11,825.00   3,547.50
18.0000 kg Semen portland @ 860.00   15,480.00
0.0300 m3 Pasir Beton @ 324,567.03   9,737.01
0.0500 m3 Koral beton @ 314,567.03   15,728.35
1.5000 Lbr Seng gelombang bljs 32 @ 30,000.00   45,000.00
1.3500 Lbr Plywood 4 mm @ 61,500.00   83,025.00
2.0000 oh Tukang kayu @ 55,000.00
1.0000 oh Pekerja @ 45,000.00
0.2000 oh Kepala tukang @ 60,000.00
0.0500 oh Mandor @ 60,000.00
JUMLAH 377,381.24

A. 6.6.10 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40 X 50 X 20) CM


0.0360 m3 Kayu Terentang @ 1,037,571.94   37,352.59
0.0800 kg Paku biasa 2'-5' @ 11,825.00   946.00
1.0000 btg kaso 5/7 @ 25,000.00   25,000.00
0.3000 oh Tukang kayu @ 55,000.00
0.0015 oh Mandor @ 60,000.00
JUMLAH 63,298.59
A. 6.6.11 1 M2 PEMBUATAN STEGGER DARI BAMBU,UKURAN (40X50X20) CM
1.0000 btg Bambu dia. 6 - 8 / 600 cm @ 10,000.00   10,000.00
0.2500 kg Tali Ijuk @ 25,000.00   6,250.00
0.0170 oh Tukang kayu @ 55,000.00
0.2500 oh Pekerja @ 45,000.00
0.0020 oh Kepala tukang @ 60,000.00
0.0130 oh Mandor @ 60,000.00
JUMLAH 16,250.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 18/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

A. 6.6.12 1 M2 PEMBUATAN JALAN SEMENTARA


0.1500 m3 Batu Belah 15/20 @ 165,000.00   24,750.00
0.0900 m3 Batu Pecah 5/7 @ 170,000.00   15,300.00
0.0100 m3 Pasir pasang @ 1,500,000.00   15,000.00
1.0000 oh pekerja @ 150,000.00
0.0500 oh mandor @ 10,000.00
JUMLAH 55,050.00
A. 6.6.13 1 M3 BONGKARAN BETON BERTULANG
6.6670 oh pekerja @ 45,000.00
0.3330 oh Mandor @ 60,000.00
JUMLAH -
A. 6.6.14 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH
6.6670 oh pekerja @ 45,000.00
0.3330 oh Mandor @ 60,000.00
JUMLAH -
A. 6.6.15 1 M' PASANG PAGAR KAWAT JARING GALVANIS.TINGGI 1,00 M
0.4340 m2 Pagar Kawat jaring @ 37,500.00   16,275.00
0.0420 oh Pekerja @ 45,000.00
0.0040 oh Kepala tukang @ 60,000.00
0.0420 oh Tukang @ 55,000.00
0.0020 oh Mandor @ 60,000.00
JUMLAH 16,275.00
A. 6.6.16 1 M' PASANG PAGAR BETON PRACETAK ( 5X50X213) CM
0.9860 lbr Panel Beton Pracetak @   -
0.5250 btg Kolom Beton Pracetak @   -
0.0740 m3 Pasir Beton @ 324,567.03   24,017.9601
0.1460 m3 Koral @ 314,567.03   45,926.7862
45.0000 kg Semen Abu- abu @ 43,000.00   1,935,000.0000

0.1250 oh Tukang batu @ 55,000.00


0.0120 oh Kepala tukang @ 60,000.00
0.3750 oh pekerja @ 45,000.00
0.0190 oh mandor @ 60,000.00
JUMLAH 2,004,944.75
B. PEKERJAAN TANAH
B. 6.6.1 1 M3 GALIAN TANAH BIASA SEDALAM 1 M'
0.4000 oh pekerja 92.4000 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 19/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

B. 6.6.2 1 M3 GALIAN TANAH BIASA SEDALAM 2 M'


0.5260 oh pekerja 45,000.00
- oh tukang gali 55,000.00
- oh kepala tukang @ 60,000.00
0.0520 oh mandor @ 60,000.00
JUMLAH
B. 6.6.3 1 M3 GALIAN TANAH BIASA SEDALAM 3 M'
0.7350 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0730 oh mandor @ 60,000.00
JUMLAH
B. 6.6.4 1 M3 GALIAN TANAH KERAS SEDALAM 1 M'
0.6250 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0620 oh mandor @ 60,000.00
JUMLAH
B. 6.6.5 1 M3 GALIAN TANAH CADAS SEDALAM 1 M
1.2500 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.1250 oh mandor @ 60,000.00
JUMLAH
B. 6.6.6 1 M3 GALIAN TANAH LUMPUR SEDALAM 1 M'
0.8230 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00

0.0830 oh mandor @ 60,000.00


JUMLAH
B. 6.6.7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 M
0.0500 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH
B. 6.6.8 1 M3 PEMBUANGAN TANAH SEJAUH 150 M
0.5160 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00

0.0500 oh mandor @ 60,000.00


JUMLAH

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 20/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

B. 6.6.9 1 M3 URUGAN KEMBALI


0.1920 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0190 oh mandor @ 60,000.00
JUMLAH
B. 6.6.10 PEMADATAN TANAH
0.5000 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0500 oh mandor @ 60,000.00
JUMLAH
B. 6.6.11 1 M3 URUGAN TANAH
1.2000 M3 Tanah urug @ 162,261.35   194,713.62
0.2500 oh pekerja @ 45,000.00
0.0250 oh mandor @ 60,000.00
1.0000 oh Ls biaya pemadatan @ 25,500.00
JUMLAH 194,713.62
B. 6.6.11.a 1 M3 URUGAN PASIR
1.2000 M3 pasir urug @ 199,567.03   239,480.43
0.3000 oh pekerja @ 45,000.00
0.0100 oh mandor @ 60,000.00
1.0000 oh Ls biaya pemadatan @ 25,500.00
JUMLAH 239,480.43
B. 6.6.12 1 M3 LAPISAN PUDEL CAMP 1 Kp : 3 Ps : 7 TL
0.3300 M3 pasir urug @ 199,567.03   65,857.12
0.1090 M3 kapur padam @
0.7630 M3 tanah liat @

0.8330 oh pekerja @ 45,000.00


0.4160 oh tukang batu @ 55,000.00
0.0400 oh kepala tukang @ 60,000.00
0.0830 oh mandor @ 60,000.00
JUMLAH 65,857.12
B. 6.6.13 1 M3 LAPISAN PUDEL CAMP 1 Kp : 5 TL
0.2000 M3 kapur padam @   -
1.0000 M3 tanah liat @   -
0.8330 oh pekerja @ 45,000.00
0.4160 oh tukang batu @ 55,000.00
0.0410 oh kepala tukang @ 60,000.00
0.0810 oh mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 21/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

B. 6.6.14 1 M3 PEMASANGAN LAPISAN IJUK


1.2000 m3 ijuk @
0.1500 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH -
B. 6.6.15 1 M3 URUGAN SIRTU
1.2000 M3 Sirtu @ 209,567.03   251,480.43
0.2500 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.0250 oh mandor @ 60,000.00
JUMLAH 251,480.43
B. 6.6.16 1 M2 PEMBUATAN JALAN SEMENTARA. TEBAL 25 CM
0.2750 m3 batu belah @ 214,567.03   59,005.9329
0.0300 m3 kerikil @ 314,567.03   9,437.0109
0.0500 m3 pasir @ 249,567.03   12,478.3514
1.0000 oh pekerja @ 45,000.00
- oh tukang gali @ 55,000.00
- oh kepala tukang @ 60,000.00
0.1000 oh mandor @ 60,000.00
JUMLAH 80,921.30
C. PEKERJAAN PONDASI
C.6.6.1 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 1 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.7318
392.0000 kg semen porland @ 860.00   337,120.0000
0.3140 m3 pasir pasang @ 249,567.03   78,364.0471

1.5000 oh pekerja @ 45,000.00


0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 651,507.78
C.6.6.2 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 2 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.7318
267.0000 kg semen porland @ 860.00   229,620.0000
0.4270 m3 pasir pasang @ 249,567.03   106,565.1213
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 572,208.85

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 22/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

C.6.6.3 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 2,5 Ps


1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
392.0000 kg semen porland @ 860.00   337,120.00
0.3140 m3 pasir pasang @ 249,567.03   78,364.05
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 651,507.78
C.6.6.4 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 3 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
202.0000 kg semen porland @ 860.00   173,720.00
0.4850 m3 pasir pasang @ 249,567.03   121,040.01
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 530,783.74
C.6.6.5 1 M3 PASANG PONDASI BATU KALI / GUNUNG / BELAH 1 Pc ; 4 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
163.0000 kg semen porland @ 860.00   140,180.00
0.5200 m3 pasir pasang @ 249,567.03   129,774.86
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 505,978.59
C.6.6.6 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 5 Ps

1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73


136.0000 kg semen porland @ 860.00   116,960.00
0.5440 m3 pasir pasang @ 249,567.03   135,764.46
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 488,748.20
C.6.6.7 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 6 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
117.0000 kg semen porland @ 860.00   100,620.00
0.5610 m3 pasir pasang @ 249,567.03   140,007.10
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 476,650.83

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 23/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

C.6.6.8 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 8 Ps


1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
91.0000 kg semen porland @ 860.00   78,260.00
0.5610 m3 pasir pasang @ 249,567.03   140,007.10
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 454,290.83
C.6.6.9 1 M3 PASANG PONDASI BATU KALI, 1 Kp ; 1 Sm ; 1 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
0.2290 kg kapur pasang @ 5,000.00   1,145.00
0.2290 m3 semen merah @ 1,600.00   366.40
0.5440 oh pasir pasang @ 249,567.03   135,764.46
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 373,299.60
C.6.6.10 1 M3 PASANG PONDASI BATU KALI, 1 Kp ; 1 Sm ; 2 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
0.1700 kg kapur pasang @ 5,000.00   850.00
0.1700 m3 semen merah @ 1,600.00   272.00
0.3400 oh pasir pasang @ 249,567.03   84,852.79
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00

JUMLAH 321,998.52
C.6.6.11 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 1/4 Kp ; 4 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
156.0000 kg semen portland @ 860.00   134,160.00
0.0320 m3 kapur pasang @ 5,000.00   160.00
0.5480 oh pasir pasang @ 249,567.03   136,762.73
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 507,106.46

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 24/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

C.6.6.12 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 3 Kp ; 10 Ps


1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
61.0000 kg semen portland @ 860.00   52,460.00
0.1470 m3 kapur pasang @ 5,000.00   735.00
0.4920 oh pasir pasang @ 249,567.03   122,786.98
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 412,005.71
C.6.6.13 1 M3 PASANG PONDASI BATU KALI, 1/4 Pc ; 1 Kp ; 4 Ps
1.1000 m3 batu belah 15/20 cm @ 214,567.03   236,023.73
41.0000 kg semen portland @ 860.00   35,260.00
0.1310 m3 kapur pasang @ 5,000.00   655.00
0.5230 oh pasir pasang @ 249,567.03   130,523.56
1.5000 oh pekerja @ 45,000.00
0.6000 oh tukang batu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 402,462.29
C. 6.6.14 1 M3 PASANGAN BATU KOSONG (AANSTAMPING)
1.2000 m3 batu gunung @ 214,567.03   257,480.43
0.3000 m3 pasir urug @ 199,567.03   59,870.11
0.7800 oh pekerja @ 45,000.00
0.3900 oh tukang batu @ 55,000.00
0.0390 oh kepala tukang @ 60,000.00
0.0390 oh mandor @ 60,000.00
JUMLAH 317,350.54

C. 6.6.15 1 M3 PASANG PONDASI SIKLOP 40 % BATU KALI


75.0000 kg besi beton @ 11,000.00   825,000.00
202.0000 kg semen portland @ 860.00   173,720.00
0.3200 m3 pasir beton @ 324,567.03   103,861.45
0.4900 m3 koral beton @ 314,567.03   154,137.84
0.8000 kg kawat beton @ 10,000.00   8,000.00
3.0000 oh pekerja @ 45,000.00
0.8500 oh tukang batu @ 55,000.00
0.0850 oh kepala tukang @ 60,000.00
0.1500 oh mandor @ 60,000.00
JUMLAH 1,264,719.29

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 25/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

C. 6.6.16 1 M3 PASANG PONDASI SUMURAN DIA 100 CM


0.4500 kg batu belah 15/20 @ 214,567.03   96,555.16
280.0000 kg semen portland @ 860.00   240,800.00
0.4500 m3 pasir beton @ 324,567.03   146,055.16
0.6700 m3 koral beton @ 314,567.03   210,759.91
2.3800 oh pekerja @ 45,000.00
0.3000 oh tukang batu @ 55,000.00
0.0300 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 694,170.24
C. 6.6.17 PEMBUATAN TIANG PANCANG (40X40) CM, BETON BERTULANG
0.0190 m3 pasir urug darat @ 199,567.03   3,791.77
0.0940 m3 pasir beton @ 324,567.03   30,509.30
0.1500 m3 koral beton @ 314,567.03   47,185.05
60.5000 kg semen portland @ 860.00   52,030.00
45.0000 kg besi beton @ 11,000.00   495,000.00
0.9000 kg kawat beton @ 10,000.00   9,000.00
0.0320 m3 kayu kaso 5/7 @ 1,037,571.94   33,202.30
0.1200 kg paku @ 11,825.00   1,419.00
0.0900 lt minyak bekisting @ 5,000.00   450.00
0.2400 kg plamur tembok @ 28,000.00   6,720.00
1.0000 oh pekerja @ 45,000.00
0.6700 oh tukang batu @ 55,000.00
0.0670 oh kepala tukang @ 60,000.00
0.0500 oh mandor @ 60,000.00
JUMLAH 679,307.43
C. 6.6.18 PEMBUATAN TIANG PANCANG (35X35) CM, BETON BERTULANG
0.0160 m3 pasir urug darat @ 199,567.03   3,193.07

0.0800 m3 pasir beton @ 324,567.03   25,965.36


0.1250 m3 koral beton @ 314,567.03   39,320.88
49.0000 kg semen portland @ 860.00   42,140.00
34.5000 kg besi beton @ 11,000.00   379,500.00
0.7000 kg kawat beton @ 10,000.00   7,000.00
0.0270 m3 kayu kaso 5/7 @ 1,037,571.94   28,014.44
0.1200 kg paku @ 11,825.00   1,419.00
0.0900 lt minyak bekisting @ 5,000.00   450.00
0.2000 kg plamur tembok @ 28,000.00   5,600.00
0.8000 oh pekerja @ 45,000.00
0.5000 oh tukang batu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH 532,602.76

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 26/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D. PEKERJAAN DINDING
D.6.6.1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 1 Ps
120.0000 bh bata merah @ 550.00   66,000.00
64.0300 kg semen portland @ 860.00   55,065.80
0.0590 m3 pasir pasang @ 249,567.03   14,724.45
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 135,790.25

D.6.6.2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 2 Ps


120.0000 bh bata merah @ 550.00   66,000.00
43.5000 kg semen portland @ 860.00   37,410.00
0.0800 m3 pasir pasang @ 249,567.03   19,965.36
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 123,375.36
D.6.6.3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 3 Ps
120.0000 bh bata merah @ 550.00   66,000.00
32.9500 kg semen portland @ 860.00   28,337.00
0.0910 m3 pasir pasang @ 249,567.03   22,710.60
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 117,047.60

D.6.6.4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 4 Ps


120.0000 bh bata merah @ 550.00   66,000.00
26.5500 kg semen portland @ 860.00   22,833.00
0.0930 m3 pasir pasang @ 249,567.03   23,209.73
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 112,042.73
D.6.6.5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 5 Ps
120.0000 bh bata merah @ 550.00   66,000.00
22.2000 kg semen portland @ 860.00   19,092.00
0.1020 m3 pasir pasang @ 249,567.03   25,455.84
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 110,547.84

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 27/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D.6.6.6 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 6 Ps


120.0000 bh bata merah @ 550.00   66,000.00
22.2000 kg semen portland @ 860.00   19,092.00
0.1020 m3 pasir pasang @ 249,567.03   25,455.84
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 110,547.84
D.6.6.7 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 3 Kp ; @
120.0000 bh bata merah @ 550.00   66,000.00
10.0800 kg semen portland @ 860.00   8,668.80
0.0925 m3 pasir pasang @ 249,567.03   23,084.95
0.0275 m3 kapur pasang @ 5,000.00   137.50
0.6500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 97,891.25
D.6.6.8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc ; 1 Ps
60.0000 bh bata merah @ 550.00   33,000.00
27.8000 kg semen portland @ 860.00   23,908.00
0.0280 m3 pasir pasang @ 249,567.03   6,987.88
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 63,895.88

D. 6.6.9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 2 ps


60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
18.9500 kg semen porland @ 860.00   16,297.00
0.0380 m3 pasir pasang @ 249,567.03   9,483.55
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 58,780.55
D. 6.6.10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 3 ps
60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
14.3700 kg semen porland @ 860.00   12,358.20
0.0400 m3 pasir pasang @ 249,567.03   9,982.68
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 55,340.88

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 28/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D. 6.6.11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps


60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
11.5000 kg semen porland @ 860.00   9,890.00
0.0430 m3 pasir pasang @ 249,567.03   10,731.38
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 53,621.38

D. 6.6.12 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 5 ps


60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
9.6800 kg semen porland @ 860.00   8,324.80
0.0450 m3 pasir pasang @ 249,567.03   11,230.52
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 52,555.32
D. 6.6.13 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 6 ps
60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
8.3200 kg semen porland @ 860.00   7,155.20
0.0490 m3 pasir pasang @ 249,567.03   12,228.78
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 52,383.98

D. 6.6.14 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 8 ps


60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
6.5000 kg semen porland @ 860.00   5,590.00
0.0500 m3 pasir pasang @ 249,567.03   12,478.35
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 51,068.35

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 29/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D. 6.6.15 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 3 Kp ; 10 ps


60.0000 bh bata merah 8 x 8 x 15 cm @ 550.00   33,000.00
4.5000 kg semen porland @ 860.00   3,870.00
0.0500 m3 pasir pasang @ 249,567.03   12,478.35
0.0150 m3 kapur padam @ 5,000.00
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 49,348.35

D. 6.6.16 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 1 Sm ; 1 ps


60.0000 bh bata merah @ 550.00   33,000.00
0.0180 kg semen merah/bata merah tumbu @ 1,600.00   28.80
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
0.0180 m3 kapur padam @ 5,000.00   90.00
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 37,611.01
D. 6.6.17 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp ; 1 Sm ; 2 Ps
60.0000 bh bata merah @ 550.00   33,000.00
0.0140 kg semen merah/bata merah tumbu @ 1,600.00   22.40
0.0280 m3 pasir pasang @ 249,567.03   6,987.88
0.0140 m3 kapur padam @ 5,000.00   70.00
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00

0.0100 oh kepala tukang @ 60,000.00


0.0150 oh mandor @ 60,000.00
JUMLAH 40,080.28

D. 6.6.18 1 M2 PASANGAN DINDING HOLLOW BLOCK (HB.20)


12.5000 bh Hollow block @ 6,000.00   75,000.00
13.5000 kg semen portland @ 860.00   11,610.00
0.0480 m3 pasir pasang @ 249,567.03   11,979.22
1.9500 m3 besi beton polos @ 11,000.00   21,450.00
0.3500 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0170 oh mandor @ 60,000.00
JUMLAH 120,039.22

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 30/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D. 6.6.19 1 M2 PASANGAN DINDING HOLLOW BLOCK (HB.15)


12.5000 bh Hollow block @ 5,000.00   62,500.00
10.4500 kg semen portland @ 860.00   8,987.00
0.0380 m3 pasir pasang @ 249,567.03   9,483.55
1.9500 m3 besi beton polos @ 11,000.00   21,450.00
0.3200 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 102,420.55

D. 6.6.20 1 M2 PASANGAN DINDING HOLLOW BLOCK (HB.10)


12.5000 bh Hollow block @ 3,000.00   37,500.00
7.5000 kg semen portland @ 860.00   6,450.00
0.0270 m3 pasir pasang @ 249,567.03   6,738.31
1.9500 m3 besi beton polos @ 11,000.00   21,450.00
0.3200 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 72,138.31
D. 6.6.21 1 M2 PASANGAN DINDING CON BLOCK (HB.20)
12.5000 bh concrete block @ 6,000.00   75,000.00
14.0500 kg semen portland @ 860.00   12,083.00
0.0040 m3 pasir beton @ 324,567.03   1,298.27
0.0420 m3 pasir pasang @ 249,567.03   10,481.82
3.8700 kg besi beton polos @ 11,000.00   42,570.00
0.0060 kg paku biasa 2" - 5" @ 11,825.00   70.95

0.0010 kg kayu terentang @ 55,000.00   55.00


0.0300 kg kawat beton @ 10,000.00   300.00
0.0050 kg koral beton @ 314,567.03   1,572.84
0.3700 oh pekerja @ 45,000.00
0.1570 oh tukang batu @ 55,000.00
0.0070 oh tukang besi @ 55,000.00
0.0164 oh kepala tukang @ 60,000.00
0.0185 oh mandor @ 60,000.00
JUMLAH 143,431.87

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 31/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D. 6.6.22 1 M2 PASANGAN DINDING CON BLOCK (HB.15)


12.5000 bh concrete block @ 5,000.00   62,500.00
10.4600 kg semen portland @ 860.00   8,995.60
0.0300 m3 pasir beton @ 324,567.03   9,737.01
0.0320 m3 pasir pasang @ 249,567.03   7,986.14
0.8700 kg besi beton polos @ 11,000.00   9,570.00
0.0040 kg paku biasa 2" - 5" @ 11,825.00   47.30
0.0010 kg kayu terentang @ 55,000.00   55.00
0.0200 kg kawat beton @ 10,000.00   200.00
0.0040 kg koral beton @ 314,567.03   1,258.27
0.3400 oh pekerja @ 45,000.00
0.1300 oh tukang batu @ 55,000.00
0.0070 oh tukang besi @ 55,000.00
0.0137 oh kepala tukang @ 60,000.00
0.0170 oh mandor @ 60,000.00
JUMLAH 100,349.32
D. 6.6.23 1 M2 PASANGAN DINDING CON BLOCK (HB.10)
12.5000 bh concrete block @ 3,000.00   37,500.00
7.2000 kg semen portland @ 860.00   6,192.00
0.0020 m3 pasir beton @ 324,567.03   649.13
0.0210 m3 pasir pasang @ 249,567.03   5,240.91
2.5400 kg besi beton polos @ 11,000.00   27,940.00
0.0030 kg paku biasa 2" - 5" @ 11,825.00   35.48
0.0010 kg kayu terentang @ 55,000.00   55.00
0.0150 kg kawat beton @ 10,000.00   150.00
0.0030 kg koral beton @ 314,567.03   943.70
0.3400 oh pekerja @ 45,000.00
0.1070 oh tukang batu @ 55,000.00

0.0070 oh tukang besi @ 55,000.00


0.0114 oh kepala tukang @ 60,000.00
0.0170 oh mandor @ 60,000.00
JUMLAH 78,706.22

D. 6.6.24 1 M2 PASANGAN DINDING LATAI


2.5000 bh bondbeam 40x20x20 cm @ -   -
5.1000 kg semen portland @ 860.00   4,386.00
0.0800 m3 pasir beton @ 324,567.03   25,965.36
1.5000 kg besi beton polos @ 11,000.00   16,500.00
0.1500 m3 koral beton @ 314,567.03   47,185.05
0.1000 oh pekerja @ 45,000.00

0.0300 oh tukang batu @ 55,000.00


0.0300 oh tukang besi @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
  0.005 oh mandor @ 60,000.00
JUMLAH 94,036.42

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 32/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

D. 6.6.25 1 M2 PASANGAN DINDING ROSTER 20 X 20


0.04 26.0000 bh roster / terawang @ 3,000.00   78,000.00
25 12.8000 kg semen porland @ 860.00   11,008.00
0.0350 m3 pasir pasang @ 249,567.03   8,734.85
0.3000 oh pekerja @ 45,000.00
0.1000 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 97,742.85
D. 6.6.26 1 M2 PASANG BATA BERONGGA UKURAN ( 5x11x24 ) cm
0.04 80.0000 bh bata berongga @ 550.00   44,000.00
25 23.6500 kg semen porland @ 860.00   20,339.00
0.5700 m3 pasir pasang @ 249,567.03   142,253.21
0.3200 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 206,592.21

D. 6.6.27 1 M2 PASANG DINDING ANYAMAN BAMBU RANGKA KAYU


0.04 1.5000 m2 bilik bambu @ 2,500.00   3,750.00
25 0.0140 m3 kayu @ 1,037,571.94   14,526.01
0.0120 kg paku @ 11,825.00   141.90
0.0030 m3 list kayu 2/4 @ 1,037,571.94   3,112.72
0.1000 oh pekerja @ 45,000.00
0.0500 oh tukang batu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00

21,530.62

D. 6.6.28 1 M2 PASANG DINDING PEMISAH PLYW OOD RANGKAP


RANGKA KAYU MERANTI
0.0195 m3 balok kayu meranti @ 1,037,571.94   20,232.65
0.0070 m3 papan kayu meranti @ 1,187,571.94   8,313.00
0.1000 kg paku biasa 2' - 5' @ 11,825.00   1,182.50
1.0000 lbr plywood 4 mm @ 61,500.00   61,500.00
0.2000 oh pekerja @ 45,000.00
0.6000 oh tukang kayu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 91,228.16

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 33/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. PEKERJAAN PLESTERAN
E. 6.6.1 1 M2 PLESTERAN 1 pc ; 1 ps, TEBAL 15 MM
12.9200 kg semen portland @ 860.00   11,111.20
0.0130 m3 pasir pasang @ 249,567.03   3,244.37
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
14,355.57
E. 6.6.2 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 15 MM
8.5200 kg semen portland @ 860.00   7,327.20
0.0170 m3 pasir pasang @ 249,567.03   4,242.64
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 11,569.84
E. 6.6.3 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 15 MM
6.4800 kg semen portland @ 860.00   5,572.80
0.0190 m3 pasir pasang @ 249,567.03   4,741.77
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 10,314.57
E. 6.6.4 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 15 MM
5.2000 kg semen portland @ 860.00   4,472.00
0.0200 m3 pasir pasang @ 249,567.03   4,991.34
0.2000 oh pekerja @ 45,000.00

0.1500 oh tukang batu @ 55,000.00


0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 9,463.34
E. 6.6.5 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 15 MM
4.3200 kg semen portland @ 860.00   3,715.20
0.0220 m3 pasir pasang putih @ 249,567.03   5,490.47
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 9,205.67

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 34/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.6 1 M2 PLESTERAN 1 pc ; 6 ps, TEBAL 15 MM


3.6800 kg semen portland @ 860.00   3,164.80
0.0230 m3 pasir pasang putih @ 249,567.03   5,740.04
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 8,904.84
E. 6.6.7 1 M2 PLESTERAN 1 pc ; 8 ps, TEBAL 15 MM
2.8800 kg semen portland @ 860.00   2,476.80
0.0240 m3 pasir pasang @ 249,567.03   5,989.61
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 8,466.41
E. 6.6.8 1 M2 PLESTERAN 1 pc ; 0,5 Kp ; 3 Ps, TEBAL 15 MM
5.7600 kg semen portland @ 860.00   4,953.60
0.0030 m3 Kapur padam @ 5,000.00   15.00
0.0130 m3 pasir pasang @ 249,567.03   3,244.37
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 8,212.97
E. 6.6.9 1 M2 PLESTERAN 1 pc ; 3 Kp ; 10 Ps, TEBAL 15 MM
1.8400 kg semen portland @ 860.00   1,582.40
0.0060 m3 Kapur padam @ 5,000.00   30.00

0.0140 m3 pasir pasang @ 249,567.03   3,493.94


0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 5,106.34
E. 6.6.10 1 M2 PLESTERAN 0,5 pc ; 1 Kp ; 4 Ps, TEBAL 15 MM
3.0000 kg semen portland @ 860.00   2,580.00
0.0050 m3 Kapur padam @ 5,000.00   25.00
0.0190 m3 pasir pasang @ 249,567.03   4,741.77
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 7,346.77

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 35/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.11 1 M2 PLESTERAN 1 Kp ; 1 Sm ; 1 Ps, TEBAL 15 MM


0.0090 kg semen merah @ 860.00   7.74
0.0090 m3 Kapur padam @ 5,000.00   45.00
0.0090 m3 pasir pasang @ 249,567.03   2,246.10
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 2,298.84
E. 6.6.12 1 M2 PLESTERAN 1 Kp ; 1 Sm ; 2 Ps, TEBAL 15 MM
0.0070 kg semen merah @ 860.00   6.02
0.0070 m3 Kapur padam @ 5,000.00   35.00
0.0150 m3 pasir pasang @ 249,567.03   3,743.51
0.2000 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 3,784.53
E. 6.6.13 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 20 MM
14.2800 kg semen portland @ 860.00   12,280.80
0.0230 m3 pasir pasang @ 249,567.03   5,740.04
0.2500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 18,020.84
E. 6.6.14 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 20 MM
10.8000 kg semen portland @ 860.00   9,288.00

0.0260 m3 pasir pasang @ 249,567.03   6,488.74


0.2500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 15,776.74
E. 6.6.15 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 20 MM
8.6800 kg semen portland @ 860.00   7,464.80
0.0280 m3 pasir pasang @ 249,567.03   6,987.88
0.2500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00

0.0125 oh mandor @ 60,000.00


JUMLAH 14,452.68

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 36/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.16 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 20 MM


7.2900 kg semen portland @ 860.00   6,269.40
0.0280 m3 pasir pasang @ 249,567.03   6,987.88
0.2500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 13,257.28
E. 6.6.17 1 M2 PLESTERAN 1 pc ; 6 ps, TEBAL 20 MM
6.2400 kg semen portland @ 860.00   5,366.40
0.0300 m3 pasir pasang putih @ 249,567.03   7,487.01
0.2500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 12,853.41
E. 6.6.18 1 M2 PLESTERAN 1 Kp ; 1 Sm ; 2 Ps, TEBAL 20 MM
0.0090 kg semen merah @ 860.00   7.74
0.0090 m3 Kapur padam @ 5,000.00   45.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
0.2500 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 4,544.95
E. 6.6.19 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 25 MM
15.5000 kg semen portland @ 860.00   13,330.00
0.0130 m3 pasir pasang @ 249,567.03   3,244.37

0.3000 oh pekerja @ 45,000.00


0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 16,574.37
E. 6.6.20 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 25 MM
11.7500 kg semen portland @ 860.00   10,105.00
0.0350 m3 pasir pasang @ 249,567.03   8,734.85
0.3000 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 18,839.85

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 37/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.21 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 25 MM


9.4800 kg semen portland @ 860.00   8,152.80
0.0380 m3 pasir pasang @ 249,567.03   9,483.55
0.3000 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 17,636.35
E. 6.6.22 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 25 MM
7.9400 kg semen portland @ 860.00   6,828.40
0.0390 m3 pasir pasang @ 249,567.03   9,733.11
0.3000 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 16,561.51
E. 6.6.23 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 30 MM
18.6500 kg semen portland @ 860.00   16,039.00
0.0350 m3 pasir pasang @ 249,567.03   8,734.85
0.3200 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 24,773.85
E. 6.6.24 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 30 MM
14.1500 kg semen portland @ 860.00   12,169.00
0.0390 m3 pasir pasang @ 249,567.03   9,733.11
0.3200 oh pekerja @ 45,000.00

0.2500 oh tukang batu @ 55,000.00


0.0250 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
21,902.11
E. 6.6.25 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 30 MM
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m3 pasir pasang @ 249,567.03   10,481.82
0.3200 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 20,268.62

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 38/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.26 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 30 MM


8.1900 kg semen portland @ 860.00   7,043.40
0.0450 m3 pasir pasang @ 249,567.03   11,230.52
0.3200 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0150 oh mandor @ 60,000.00
JUMLAH 18,273.92
E. 6.6.27 1 M2 BERAPEN 1 pc ; 3 ps, TEBAL 30 MM
7.0700 kg semen portland @ 860.00   6,080.20
0.0210 m3 pasir pasang @ 249,567.03   5,240.91
0.1500 oh pekerja @ 45,000.00
0.0700 oh tukang batu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 11,321.11
E. 6.6.28 1 M2 BERAPEN 1 pc ; 5 ps, TEBAL 15 MM
5.6700 kg semen portland @ 860.00   4,876.20
0.0230 m3 pasir pasang @ 249,567.03   5,740.04
0.1500 oh pekerja @ 45,000.00
0.0700 oh tukang batu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 10,616.24
E. 6.6.29 1 M2 PLESTERAN BETON 1 pc ; 2 ps, TEBAL 15 MM
9.3000 kg semen portland @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
0.0260 oh pekerja @ 45,000.00

0.2000 oh tukang batu @ 55,000.00


0.0200 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 12,490.21
E. 6.6.30 1 M2 PLESTERAN BETON 1 pc ; 3 ps, TEBAL 15 MM
7.0700 kg semen portland @ 860.00   6,080.20
0.0210 m3 pasir pasang @ 249,567.03   5,240.91
0.0260 oh pekerja @ 45,000.00
0.2000 oh tukang batu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 11,321.11

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 39/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.31 1 M2 PLESTERAN SKONING 1 pc ; 2ps


0.5000 kg semen portland @ 860.00   430.00
0.0020 m3 pasir pasang @ 249,567.03   499.13
0.0570 oh pekerja @ 45,000.00
0.0380 oh tukang batu @ 55,000.00
0.0380 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00
JUMLAH 929.13
E. 6.6.32 1 M2 PLESTERAN GRANITO 1 pc WARNA ; 2 GRANITO, TEBAL 10 MM
0.1440 kg Pc Warna 1,600.00   230.40
15.0000 kg Batu Granito 10,000.00   150,000.00
0.0500 oh pekerja 45,000.00
0.0200 oh tukang batu 55,000.00
0.0020 oh kepala tukang 60,000.00
0.0050 oh mandor 60,000.00
JUMLAH 150,230.40
E. 6.6.33 1 M2 PLESTERAN TERASO 1 pc WARNA ; 2 BATU TERASO, TEBAL 10 MM
0.4400 kg Pc Warna 1,600.00   704.00
11.5000 kg Batu teraso 7,500.00   86,250.00
0.4500 oh pekerja 45,000.00
0.2000 oh tukang batu 55,000.00
0.0200 oh kepala tukang 60,000.00
0.0250 oh mandor 60,000.00
JUMLAH 86,954.00
E. 6.6.34 1 M2 PLESTERAN CIPRAT 1 pc ; 2ps
4.3200 kg semen portland 860.00   3,715.20
0.0160 m3 pasir pasang 249,567.03   3,993.07
0.2500 oh pekerja 45,000.00

0.1000 oh tukang batu 55,000.00


0.0100 oh kepala tukang 60,000.00
0.0150 oh mandor 60,000.00
JUMLAH 7,708.27
E. 6.6.35 1 M2 PLESTERAN SIAR ADUKAN 1 pc ; 2ps
4.3200 kg semen portland 860.00   3,715.20
0.0160 m3 pasir pasang 249,567.03   3,993.07
0.0150 oh pekerja 45,000.00
0.0700 oh tukang batu 55,000.00
0.0070 oh kepala tukang 60,000.00
0.0080 oh mandor 60,000.00
JUMLAH 7,708.27

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 40/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

E. 6.6.36 1 M2 PLESTERAN WATERPROOF BATACOTE 3 LAPIS


0.5000 kg semen portland 860.00   430.00
2.9000 kg Batacote 1,500.00   4,350.00
0.0060 m3 pasir pasang 249,567.03   1,497.40
0.3000 oh pekerja 45,000.00
0.2000 oh tukang batu 55,000.00
0.0200 oh kepala tukang 60,000.00
0.0150 oh mandor 60,000.00
JUMLAH 6,277.40
F. PEKERJAAN KAYU
F.6.6.1 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU JATI
1.1000 m3 kayu jati, balok @ 5,000,000.00   5,500,000.00
6.0000 oh pekerja @ 45,000.00
20.0000 oh tukang kayu @ 55,000.00
2.0000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 5,500,000.00
F.6.6.2 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU BENGKIRAI
1.2000 m3 kayu bengkirai, balok @ 1,937,571.94   2,325,086.33
6.0000 oh pekerja @ 45,000.00
18.0000 oh tukang kayu @ 55,000.00
2.0000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 2,325,086.33
F.6.6.3 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU ULIN
1.2000 m3 kayu ulin, balok @ 1,537,571.94   1,845,086.33
6.0000 oh pekerja @ 45,000.00
18.0000 oh tukang kayu @ 55,000.00

2.0000 oh kepala tukang @ 60,000.00


0.3000 oh mandor @ 60,000.00
JUMLAH 1,845,086.33
F.6.6.4 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU MERANTI MERAH
1.2000 m3 kayu meranti, balok @ 1,037,571.94   1,245,086.33
6.0000 oh pekerja @ 45,000.00
18.0000 oh tukang kayu @ 55,000.00
2.0000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 1,245,086.33
F.6.6.5 1 M2 PASANG PINTU KLAMP KAYU BENGKIRAI
0.0360 m3 Kayu bengkirai, papan @ 2,137,571.94   76,952.59
0.0500 kg Paku Biasa 2" - 5" @ 11,825.00   591.2500
0.3500 oh pekerja @ 45,000.00
1.0500 oh tukang kayu @ 55,000.00
0.1050 oh kepala tukang @ 60,000.00
0.0180 oh mandor @ 60,000.00
JUMLAH 77,543.84

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 41/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.6 1 M2 PASANG PINTU KLAMP KAYU ULIN


0.0360 m3 Kayu ulin, papan @ 1,737,571.94   62,552.59
0.0500 kg Paku ulin @ 13,750.00 687.5
0.3500 oh pekerja @ 45,000.00
1.0500 oh tukang kayu @ 55,000.00
0.1050 oh kepala tukang @ 60,000.00
0.0180 oh mandor @ 60,000.00
JUMLAH 63,240.09
F.6.6.7 1 M2 PASANG PINTU PANEL KAYU JATI
0.0400 m3 Kayu Jati, papan @ 7,000,000.00   280,000.00
1.0000 oh pekerja @ 45,000.00
2.5000 oh tukang kayu @ 55,000.00
0.2500 oh kepala tukang @ 60,000.00
0.0500 oh mandor @ 60,000.00
JUMLAH 280,000.00
F.6.6.8 1 M2 PASANG PINTU PANEL KAYU BENGKIRAI
0.0400 m3 Kayu bengkirai, papan @ 2,137,571.94   85,502.88
1.0000 oh pekerja @ 45,000.00
2.5000 oh tukang kayu @ 55,000.00
0.2500 oh kepala tukang @ 60,000.00
0.0500 oh mandor @ 60,000.00
JUMLAH 85,502.88
F.6.6.9 1 M2 PASANG PINTU DAN JENDELA KACA KAYU JATI
0.0350 m3 Kayu Jati, papan @ 7,000,000.00   245,000.00
0.8000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00

JUMLAH 245,000.00
F.6.6.10 1 M2 PASANG PINTU DAN JENDELA KACA KAYU BENGKIRAI
0.0350 m3 Kayu Bengkirai, papan @ 2,137,571.94   74,815.02
0.8000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH 74,815.02
F.6.6.11 1 M2 PASANG PINTU DAN JENDELA KACA KAYU ULIN
0.0350 m3 Kayu Ulin, papan @ 1,737,571.94   60,815.02
0.8000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH 60,815.02

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 42/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.12 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU JATI


0.0640 m3 Kayu Jati, papan @ 7,000,000.00   448,000.00
1.0000 oh pekerja @ 45,000.00
3.0000 oh tukang kayu @ 55,000.00
0.3000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 448,000.00
F.6.6.13 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU BENGKIRAI
0.0640 m3 Kayu bengkirai, papan @ 2,137,571.94   136,804.60
1.0000 oh pekerja @ 45,000.00
3.0000 oh tukang kayu @ 55,000.00
0.3000 oh kepala tukang @ 60,000.00
0.0250 oh mandor @ 60,000.00
JUMLAH 136,804.60
F.6.6.14 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU JATI
0.0196 m3 Kayu jati, papan @ 7,000,000.00   137,200.00
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.3000 ltr lem kayu @ 9,500.00   2,850.00
1.0000 lbr plywood 4' x 3' x 4 mm @ 61,500.00   61,500.00
0.6000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 201,904.75
F.6.6.15 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU BENGKIRAI
0.0196 m3 Kayu bangkirai, papan @ 2,137,571.94   41,896.41
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.3000 ltr lem kayu @ 9,500.00   2,850.00

1.0000 lbr plywood 4' x 3' x 4 mm @ 61,500.00   61,500.00


0.6000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 106,601.16
F.6.6.16 1 M2 PASANG JALUSI MATI KUSEN KAYU JATI
0.0600 m3 Kayu jati, papan @ 7,000,000.00   420,000.00
0.1500 Kg paku biasa 1/2" - 1" @ 11,825.00   1,773.75
0.5000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0250 oh mandor @ 60,000.00
JUMLAH 421,773.75

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 43/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.17 1 M2 PASANG JALUSI MATI KUSEN KAYU BENGKIRAI


0.0600 m3 Kayu bengkirai, papan @ 2,137,571.94   128,254.32
0.1500 Kg paku biasa 1/2" - 1" @ 11,825.00   1,773.75
0.5000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0250 oh mandor @ 60,000.00
JUMLAH 130,028.07
F.6.6.18 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU ULIN
0.0196 m3 Kayu ulin, papan @ 1,737,571.94   34,056.41
0.0300 Kg paku ulin @ 13,750.00   412.50
0.3000 ltr lem kayu @ 9,500.00   2,850.00
1.0000 lbr plywood 4' x 3' x 4 mm @ 61,500.00   61,500.00
0.6000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 98,818.91
F.6.6.19 1 M2 PASANG PINTU TEAKWOOD RANGKAP, RANGKAP KAYU JATI
0.0196 m3 Kayu jati, papan @ 7,000,000.00   137,200.00
0.3000 Kg paku biasa 1/2" - 1" @ 11,825.00   3,547.50
0.3000 ltr lem kayu @ 9,500.00   2,850.00
1.0000 lbr teakwood 4 mm @ 113,500.00   113,500.00
0.6000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 257,097.50

F.6.6.20 1 M2 PASANG PINTU TEAKWOOD RANGKAP, RANGKAP KAYU BENGKIRAI


0.0196 m3 kayu Bengkirai, papan @ 2,137,571.94   41,896.41
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.3000 ltr lem kayu @ 9,500.00   2,850.00
1.0000 lbr teakwood 4 mm @ 113,500.00   113,500.00
0.6000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 158,601.16

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 44/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.21 1 M2 PASANG PINTU PLYWOOD & FORMIKA, RANGKA KAYU JATI


0.0196 m3 kayu jati, papan @ 7,000,000.00   137,200.00
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.8000 ltr lem kayu @ 9,500.00   7,600.00
1.0000 lbr plywood 4' x 3' x 4 mm @ 61,500.00   61,500.00
0.5000 lbr Formika @ 75,000.00   37,500.00
0.8000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2500 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH 244,154.75
F.6.6.22 1 M2 PASANG PINTU PLYWOOD & FORMIKA, RANGKA KAYU BENGKIRAI
0.0196 m3 kayu bengkirai, papan @ 2,137,571.94   41,896.41
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.8000 ltr lem kayu @ 9,500.00   7,600.00
1.0000 lbr plywood 4' x 3' x 4 mm @ 61,500.00   61,500.00
0.5000 lbr Formika @ 75,000.00   37,500.00
0.8000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2500 oh kepala tukang @ 60,000.00
0.0400 oh mandor 60,000.00
JUMLAH 148,851.16
F.6.6.23 1 M2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU JATI
0.0196 m3 kayu jati, papan @ 7,000,000.00   137,200.00
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.8000 ltr lem kayu @ 9,500.00   7,600.00
0.5000 lbr teakwood 4' x 8' x 4 mm @ 113,500.00   56,750.00
0.5000 lbr Formika 4' x 3' @ 75,000.00   37,500.00

0.8000 oh pekerja @ 45,000.00


2.0000 oh tukang kayu @ 55,000.00
0.2500 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH 239,404.75
F.6.6.24 1 M2 PASANG PINTU TEAKWOOD & FORMIKA, RANGKA KAYU BENGKIRAI
0.0196 m3 kayu bengkirai, papan @ 2,137,571.94   41,896.41
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.8000 ltr lem kayu @ 9,500.00   7,600.00
0.5000 lbr teakwood 4' x 8' x 4 mm @ 113,500.00   56,750.00
0.5000 ltr vernis @ 8,500.00   4,250.00
0.5000 lbr Formika 4' x 8' @ 75,000.00   37,500.00
0.8000 oh pekerja @ 45,000.00
2.0000 oh tukang kayu @ 55,000.00
0.2500 oh kepala tukang @ 60,000.00
0.0400 oh mandor @ 60,000.00
JUMLAH 148,351.16

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 45/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.25 1 M2 PASANG PINTU FORMIKA DOUBLE, RANGKA KAYU JATI


0.0196 m3 kayu jati, papan @ 7,000,000.00   137,200.00
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
1.2000 ltr lem kayu @ 9,500.00   11,400.00
1.0000 lbr plywood 4' x 8' x 4 mm @ 61,500.00   61,500.00
1.0000 lbr Formika 4' x 8' @ 75,000.00   75,000.00
1.0000 oh pekerja @ 45,000.00
2.6000 oh tukang kayu @ 55,000.00
0.2600 oh kepala tukang @ 60,000.00
0.0500 oh mandor @ 60,000.00
JUMLAH 285,454.75
F.6.6.26 1 M2 PASANG PINTU FORMIKA DOUBLE, RANGKA KAYU BENGKIRAI
0.0196 m3 kayu bengkirai, papan @ 2,137,571.94   41,896.41
0.0300 Kg paku biasa 1/2" - 1" @ 11,825.00   354.75
1.2000 ltr lem kayu @ 9,500.00   11,400.00
1.0000 lbr plywood 4' x 8' x 4 mm @ 61,500.00   61,500.00
1.0000 lbr Formika 4' x 8' @ 75,000.00   75,000.00
1.0000 oh pekerja @ 45,000.00
2.6000 oh tukang kayu @ 55,000.00
0.2600 oh kepala tukang @ 60,000.00
0.0500 oh mandor 60,000.00
JUMLAH 190,151.16
F.6.6.27 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU JATI
1.1000 m3 kayu jati, balok @ 5,000,000.00   5,500,000.00
15.0000 Kg besi strip @ 18,000.00   270,000.00
0.8000 Kg Paku Biasa 2" - 5" @ 11,825.00   9,460.00
4.0000 oh pekerja @ 45,000.00
12.0000 oh tukang kayu @ 55,000.00

1.2000 oh kepala tukang @ 60,000.00


0.2000 oh mandor @ 60,000.00
JUMLAH 5,779,460.00
F.6.6.28 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU BENGKIRAI
1.1000 m3 kayu bengkirai, balok @ 1,937,571.94   2,131,329.13
15.0000 Kg besi strip @ 18,000.00   270,000.00
0.8000 Kg Paku Biasa 2" - 5" @ 11,825.00   9,460.00
4.0000 oh pekerja @ 45,000.00
12.0000 oh tukang kayu @ 55,000.00
1.2000 oh kepala tukang @ 60,000.00
0.2000 oh mandor @ 60,000.00
JUMLAH 2,410,789.13

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 46/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.29 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU ULIN


1.1000 m3 kayu ulin, balok @ 1,537,571.94   1,691,329.13
15.0000 Kg besi strip @ 18,000.00   270,000.00
0.8000 Kg Paku ulin @ 13,750.00   11,000.00
4.0000 oh pekerja @ 45,000.00
12.0000 oh tukang kayu @ 55,000.00
1.2000 oh kepala tukang @ 60,000.00
0.2000 oh mandor @ 60,000.00
JUMLAH 1,972,329.13
F.6.6.30 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU MERANTI
1.1000 m3 kayu meranti, balok @ 1,037,571.94   1,141,329.13
15.0000 Kg besi strip @ 18,000.00   270,000.00
0.8000 Kg Paku Biasa 2" - 5" @ 11,825.00   9,460.00
4.0000 oh pekerja @ 45,000.00
12.0000 oh tukang kayu @ 55,000.00
1.2000 oh kepala tukang @ 60,000.00
0.2000 oh mandor @ 60,000.00
JUMLAH 1,420,789.13
F.6.6.31 1M2 PASANG KASO + RENG GENTENG KODOK KAYU BENGKIRAI
0.0120 m3 kayu bengkirai, balok @ 1,937,571.94   23,250.86
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 25,024.61
F.6.6.32 1M2 PASANG KASO + RENG GENTENG KODOK KAYU ULIN
0.0120 m3 kayu ulin, balok @ 1,537,571.94   18,450.86

0.1500 Kg Paku ulin @ 13,750.00   2,062.50


0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 20,513.36
F.6.6.33 1M2 PASANG KASO + RENG GENTENG MONIER KAYU JATI
0.0140 m3 kayu jati, balok @ 5,000,000.00   70,000.00
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 71,773.75

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 47/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.34 1M2 PASANG KASO + RENG GENTENG MONIER KAYU BENGKIRAI


0.0140 m3 kayu bengkirai, balok @ 1,937,571.94   27,126.01
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 28,899.76
F.6.6.35 1M2 PASANG KASO + RENG GENTENG BETON KAYU BENGKIRAI
0.0140 m3 kayu bengkirai, balok @ 1,937,571.94   27,126.01
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 28,899.76
F.6.6.36 1M2 PASANG KASO + RENG ATAP SIRAP KAYU BENGKIRAI
0.1650 m3 kayu bengkirai, balok @ 1,937,571.94   319,699.37
0.2000 Kg Paku Biasa 2" - 5" @ 11,825.00   2,365.00
0.1200 oh pekerja @ 45,000.00
0.1200 oh tukang kayu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 322,064.37
F.6.6.37 1M2 PASANG KASO + RENG ATAP SIRAP KAYU ULIN
0.1650 m3 kayu ulin, balok @ 1,537,571.94   253,699.37
0.2000 Kg Paku ulin @ 13,750.00   2,750.00
0.1200 oh pekerja @ 45,000.00

0.1200 oh tukang kayu @ 55,000.00


0.0120 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 256,449.37
F.6.6.38 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00X1.00) M, KAYU JATI
0.0120 m3 kayu jati, balok @ 5,000,000.00   60,000.00
0.1000 Kg Paku Biasa 2" - 5" @ 11,825.00   1,182.50
0.1500 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0750 oh mandor 60,000.00
JUMLAH 61,182.50

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 48/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.39 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00X1.00) M, KAYU BENGKIRAI


0.0120 m3 kayu bengkirai, balok @ 1,937,571.94   23,250.86
0.1000 Kg Paku Biasa 2" - 5" @ 11,825.00   1,182.50
0.1500 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 24,433.36
F.6.6.40 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00X1.00) M, KAYU ULIN
0.0120 m3 kayu ulin, balok @ 1,537,571.94   18,450.86
0.1000 Kg Paku ulin @ 13,750.00   1,375.00
0.1500 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 19,825.86
F.6.6.41 1 M2 PASANG RANGKA LANGIT-LANGIT (30x60) CM, KAYU JATI
0.0230 m3 Kayu jati, balok @ 5,000,000.00   115,000.00
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.2000 oh pekerja @ 45,000.00
0.3000 oh tukang kayu @ 55,000.00
0.0300 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 116,773.75
F.6.6.42 1 M2 PASANG RANGKA LANGIT-LANGIT (30x60) CM, KAYU BENGKIRAI
0.0230 m3 kayu bengkirai, balok @ 1,937,571.94   44,564.15
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.2000 oh pekerja @ 45,000.00

0.3000 oh tukang kayu @ 55,000.00


0.0300 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 46,337.90
F.6.6.43 1 M2 PASANG RANGKA LANGIT-LANGIT (30x60) CM, KAYU MERANTI
0.0230 m3 kayu meranti, balok @ 1,037,571.94   23,864.15
0.1500 Kg Paku Biasa 2" - 5" @ 11,825.00   1,773.75
0.2000 oh pekerja @ 45,000.00
0.3000 oh tukang kayu @ 55,000.00
0.0300 oh kepala tukang @ 60,000.00
0.0100 oh mandor 60,000.00
JUMLAH 25,637.90

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 49/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.44 1 M2 PASANG RANGKA LANGIT-LANGIT (30x30) CM, KAYU JATI


0.0270 m3 kayu jati, balok @ 5,000,000.00   135,000.00
0.2000 Kg Paku Biasa 2" - 5" @ 11,825.00   2,365.00
0.2500 oh pekerja @ 45,000.00
0.3500 oh tukang kayu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 137,365.00
F.6.6.45 1 M2 PASANG RANGKA LANGIT-LANGIT (30x30) CM, KAYU BENGKIRAI
0.0270 m3 kayu bengkirai, balok @ 1,937,571.94   52,314.44
0.2000 Kg Paku Biasa 2" - 5" @ 11,825.00   2,365.00
0.2500 oh pekerja @ 45,000.00
0.3500 oh tukang kayu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 54,679.44
F.6.6.46 1 M2 PASANG RANGKA LANGIT-LANGIT (30x30) CM, KAYU MERANTI
0.0270 m3 kayu meranti, balok @ 1,037,571.94   28,014.44
0.2000 Kg Paku Biasa 2" - 5" @ 11,825.00   2,365.00
0.2500 oh pekerja @ 45,000.00
0.3500 oh tukang kayu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 30,379.44
F.6.6.47 1M' PASANG LISPLANG UKURAN (3X20) CM, KAYU JATI
0.0072 m3 kayu jati, papan @ 7,000,000.00   50,400.00
0.0500 Kg Paku Biasa 2" - 5" @ 11,825.00   591.25
0.1000 oh pekerja @ 45,000.00

0.2000 oh tukang kayu @ 55,000.00


0.0250 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 50,991.25
F.6.6.48 1M' PASANG LISPLANG UKURAN (3X20) CM, KAYU BENGKIRAI
0.0072 m3 kayu bengkirai, papan @ 2,137,571.94   15,390.52
0.0500 Kg Paku Biasa 2" - 5" @ 11,825.00   591.25
0.1000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 15,981.77

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 50/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F.6.6.49 1M' PASANG LISPLANG UKURAN (3X30) CM, KAYU JATI


0.0110 m3 kayu jati, papan @ 7,000,000.00   77,000.00
0.0500 Kg Paku Biasa 2" - 5" @ 11,825.00   591.25
0.1100 oh pekerja @ 45,000.00
0.2200 oh tukang kayu @ 55,000.00
0.0220 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 77,591.25
F.6.6.50 1M' PASANG LISPLANG UKURAN (3X30) CM, KAYU BENGKIRAI
0.0110 m3 kayu bengkirai, papan @ 2,137,571.94   23,513.29
0.0500 Kg Paku Biasa 2" - 5" @ 11,825.00   591.25
0.1100 oh pekerja @ 45,000.00
0.2200 oh tukang kayu @ 55,000.00
0.0220 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 24,104.54
F.6.6.51 1M' PASANG LISPLANG UKURAN 2x(3X20) CM, KAYU BENGKIRAI
0.0145 m3 kayu bengkirai, papan @ 2,137,571.94   30,994.79
0.0600 Kg Paku Biasa 2" - 5" @ 11,825.00   709.50
0.1500 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 31,704.29
F.6.6.52 1M' PASANG LISPLANG UKURAN 2x(2X20) CM, KAYU BENGKIRAI
0.0086 m3 kayu bengkirai, papan @ 2,137,571.94   18,383.12
0.0600 Kg Paku Biasa 2" - 5" @ 11,825.00   709.50
0.1000 oh pekerja @ 45,000.00

0.1000 oh tukang kayu @ 55,000.00


0.0100 oh kepala tukang @ 60,000.00
0.0500 oh mandor 60,000.00
@ JUMLAH 19,092.62
F. 6.6.53. 1M' PASANG LISPLANG UKURAN 2x(2X20) CM, KAYU ULIN
0.0086 m3 kayu ulin, papan @ 1,737,571.94   14,943.12
0.0600 kg paku biasa 2' - 5' @ 11,825.00   709.50
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0500 oh mandor @ 60,000.00
JUMLAH 15,652.62

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 51/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F. 6.6.54 1M2 PASANG RANGKA DINDING PEMISAH KAYU BENGKIRAI


0.0195 m3 kayu bengkirai, balok @ 1,937,571.94   37,782.65
0.0070 m3 kayu bengkirai, papan @ 2,137,571.94   14,963.00
0.1000 kg paku biasa 2' - 5' @ 11,825.00   1,182.50
0.1500 oh pekerja @ 45,000.00
0.4500 oh tukang kayu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 53,928.16
F. 6.6.55 1M2 PASANG RANGKA DINDING PEMISAH KAYU ULIN
0.0195 m3 kayu ulin, balok @ 1,537,571.94   29,982.65
0.0070 m3 kayu ulin, papan @ 1,737,571.94   12,163.00
0.1000 kg paku biasa 2' - 5' @ 11,825.00   1,182.50
0.1500 oh pekerja @ 45,000.00
0.4500 oh tukang kayu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 43,328.16
F. 6.6.56 1M2 PASANG DINDING PEMISAH TEKWOOD RANGKAP, RANGKA KAYU BENGKIRAI
0.0195 m3 kayu bengkirai, balok @ 1,937,571.94   37,782.65
0.0070 m3 kayu bengkirai, papan @ 2,137,571.94   14,963.00
0.1000 kg paku biasa 2' - 5' @ 11,825.00   1,182.50
0.1500 oh pekerja @ 45,000.00
0.4500 oh tukang kayu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0750 oh mandor @ 60,000.00
JUMLAH 53,928.16
F. 6.6.57 1M2 PASANG DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KAMPER

0.0195 m3 kayu bengkirai, balok @ 1,937,571.94   37,782.65


0.0070 m3 kayu bengkirai, papan @ 2,137,571.94   14,963.00
0.1000 lt paku biasa 2' - 5' @ 11,825.00   1,182.50
0.5600 lbr lem kayu @ 9,500.00   5,320.00
1.0000 kg plywood 4' x 8' x 4 mm @ 61,500.00   61,500.00
0.2000 oh pekerja @ 45,000.00
0.6000 oh tukang kayu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0100 oh mandor 60,000.00
JUMLAH 120,748.16

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 52/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

F. 6.6.58 1M2 PASANG DINDING LAMBRISIRING DARI PAPAN JATI


0.0070 m3 kayu jati, balok @ 5,000,000.00   35,000.00
0.1000 kg paku biasa 2' - 5' @ 11,825.00   1,182.50
0.1500 kg paku skrup 3,5" @ 14,300.00   2,145.00
0.6000 oh pekerja @ 45,000.00
1.8000 oh tukang kayu @ 55,000.00
0.1800 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
JUMLAH 38,327.50
F. 6.6.59 1M2 PASANG PLYWOOD TEBAL 3 MM, UNTUK DINDING
0.4000 lbr plywood 4 mm @ 61,500.00   24,600.00
0.0500 kg paku biasa 1/2" - 1" @ 11,825.00   591.25
0.0250 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0075 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 25,191.25
F. 6.6.60 1M2 PASANG LIST PLAFOND, KAYU PROFIL
1.0500 m' kayu profil @ 4,250.00   4,462.50
0.0210 oh pekerja @ 45,000.00
0.0210 oh tukang kayu @ 55,000.00
0.0210 oh kepala tukang @ 60,000.00
0.0010 oh mandor @ 60,000.00
JUMLAH 4,462.50

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 53/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. PEKERJAAN BETON
G.6.6.1 1 M3 BETON TUMBUK 1 pc ; 3 ps ; 5 kr 
218.0000 kg semen portland @ 860.00   187,480.00
0.5200 m3 pasir beton @ 324,567.03   168,774.86
0.8700 m3 kerikil beton @ 314,567.03   273,673.32
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
629,928.17
G.6.6.2 1 M3 BETON TUMBUK 1 pc ; 3 ps ; 6 kr 
197.0000 kg semen portland @ 860.00   169,420.00
0.4700 m3 pasir beton @ 324,567.03   152,546.50
0.9400 m3 kerikil beton @ 314,567.03   295,693.01
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
617,659.51

G.6.6.3 1 M3 BETON TUMBUK 1 pc ; 4 ps ; 6 kr 


173.0000 kg semen portland @ 860.00   148,780.00
0.5700 m3 pasir beton @ 324,567.03   185,003.21
0.8700 m3 kerikil beton @ 314,567.03   273,673.32
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
607,456.52
G.6.6.4 1 M3 MEMBUAT LANTAI KERJA BETON TUMBUK 1 pc ; 3 ps ; 5 kr 
10.0000 kg semen portland @ 860.00   8,600.00
0.0260 m3 pasir beton @ 324,567.03   8,438.74

0.0440 m3 Koral beton @ 314,567.03   13,840.95


1.1500 oh pekerja @ 45,000.00
0.0200 oh tukang batu @ 55,000.00
0.0020 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
30,879.69

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 54/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G.6.6.5. 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 3 kr)


336.0000 kg semen portland @ 860.00   288,960.00
0.5400 m3 pasir beton @ 324,567.03   175,266.20
0.8100 m3 Koral beton @ 314,567.03   254,799.29
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor @ 60,000.00
JUMLAH 719,025.49
G.6.6.6 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 4 kr)
280.0000 kg semen portland @ 860.00   240,800.00
0.4500 m3 pasir beton @ 324,567.03   146,055.16
0.9000 m3 Koral beton @ 314,567.03   283,110.33
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 669,965.49

G.6.6.7 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ;2,5 kr)


352.0000 kg semen portland @ 860.00   302,720.00
0.5600 m3 pasir beton @ 324,567.03   181,757.54
0.7000 m3 Koral beton @ 314,567.03   220,196.92
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 704,674.46
G.6.6.8 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ; 3 kr)
357.0000 kg semen portland @ 860.00   307,020.00
0.4200 m3 pasir beton @ 324,567.03   136,318.15

0.5400 m3 Koral beton @ 314,567.03   169,866.20


1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 613,204.35
G.6.6.9 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ;2,5 kr)
386.0000 kg semen portland @ 860.00   331,960.00
0.4700 m3 pasir beton @ 324,567.03   152,546.50
0.7800 m3 Koral beton @ 314,567.03   245,362.28
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 729,868.79

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 55/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G.6.6.10 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1 ps ; 2 kr)


479.0000 kg semen portland @ 860.00   411,940.00
0.3700 m3 pasir beton @ 324,567.03   120,089.80
0.7400 m3 Koral beton @ 314,567.03   232,779.60
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 764,809.40
G.6.6.11 1M3 MEMBUAT TIANG PANCANG PRESTRESSED BETON
440.0000 kg semen portland @ 860.00   378,400.00
0.5000 m3 pasir beton @ 324,567.03   162,283.51
0.8000 m3 Koral beton @ 314,567.03   251,653.62
2.4600 galon Rapidrant @   -
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00

JUMLAH 792,337.14
G.6.6.12 1M3 MEMBUAT BETON DENGAN PUZZDITH - 100 XR
336.0000 kg semen portland @ 860.00   288,960.00
0.5400 m3 pasir beton @ 324,567.03   175,266.20
0.8100 m3 Koral beton @ 314,567.03   254,799.29
1.0000 ltr puzzdith - 100 XR @   -
1.6500 oh pekerja @ 45,000.00
0.2500 oh tukang batu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0800 oh mandor @ 60,000.00
JUMLAH 719,025.49
G.6.6.13 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ;3 kr)

336.0000 kg semen portland @ 860.00   288,960.00


0.5400 m3 pasir beton @ 324,567.03   175,266.20
0.8100 m3 Koral beton @ 314,567.03   254,799.29
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor @ 60,000.00
JUMLAH 719,025.49
G.6.6.14 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 4 kr)
291.0000 kg semen portland @ 860.00   250,260.00
0.4700 m3 pasir beton @ 324,567.03   152,546.50
0.9300 m3 Koral beton @ 314,567.03   292,547.34
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor @ 60,000.00
JUMLAH 695,353.84

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 56/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G.6.6.15 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ;3kr)


367.0000 kg semen portland @ 860.00   315,620.00
0.4400 m3 pasir beton @ 324,567.03   142,809.49
0.8800 m3 Koral beton 2/3 @ 314,567.03   276,818.99
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor @ 60,000.00
JUMLAH 735,248.48
G.6.6.16 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ; 2,5 kr)
400.0000 kg semen portland @ 860.00   344,000.00
0.4800 m3 pasir beton @ 324,567.03   155,792.17
0.8000 m3 Koral beton 2/3 @ 314,567.03   251,653.62
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor @ 60,000.00
JUMLAH 751,445.80

G.6.6.17 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1 ps ;1kr)


615.0000 kg semen portland @ 860.00   528,900.00
0.5200 m3 pasir beton @ 324,567.03   168,774.86
0.5200 m3 Koral beton @ 314,567.03   163,574.86
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor @ 60,000.00
JUMLAH 861,249.71
G.6.6.18 1M3 MEMBUAT BETON KEDAP AIR DENGAN STROROX - 100
400.0000 kg semen portland @ 860.00   344,000.00
0.4800 m3 pasir beton @ 324,567.03   155,792.17

0.8000 m3 Koral beton @ 314,567.03   251,653.62


1.2000 Kg Strorox - 100 @   -
2.0000 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
1.0000 oh mandor 60,000.00
JUMLAH 751,445.80
G.6.6.19 1M' MEMASANG PVC WATERSTOP LEBAR 150 MM
1.0500 m' waterstop lebar 150 mm @   -
0.0500 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 57/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G.6.6.20 1M' MEMASANG PVC WATERSTOP LEBAR 200 MM


1.0500 m' waterstop lebar 200 mm @   -
0.0500 oh pekerja @ 45,000.00
0.0350 oh tukang batu @ 55,000.00
0.0035 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00
JUMLAH -
G.6.6.21 1M' MEMASANG PVC WATERSTOP LEBAR 230 MM
1.0500 m' waterstop lebar 230 mm @ -   -
0.5500 oh pekerja @ 45,000.00
0.0350 oh tukang batu @ 55,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH -
G.6.6.22 1M' MEMASANG PVC WATERSTOP LEBAR 250 MM
1.0500 m' waterstop lebar 250 mm @ -   -
0.5500 oh pekerja @ 45,000.00
0.0350 oh tukang batu @ 55,000.00
0.0030 oh mandor @ 60,000.00

JUMLAH -
G.6.6.23 1M' MEMASANG PVC WATERSTOP LEBAR 300 MM
1.0500 m' waterstop lebar 300 mm @   -
0.5500 oh pekerja @ 45,000.00
0.0350 oh tukang batu @ 55,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH -
G.6.6.24 1M' MEMASANG PVC WATERSTOP LEBAR 320 MM
1.0500 m' waterstop lebar 320 mm @   -
0.0500 oh pekerja @ 45,000.00
0.0350 oh tukang batu @ 55,000.00
0.0020 oh mandor @ 60,000.00

JUMLAH -
G.6.6.25 1 KG PEMBESIAN DG BESI POLOS
1.0500 Kg Besi beton @ 11,000.00   11,550.00
0.0150 Kg Kawat beton @ 10,000.00   150.00
0.0070 OH pekerja @ 45,000.00
0.0070 OH tukang besi @ 55,000.00
0.0007 OH kepala tukang @ 60,000.00
0.0003 OH mandor @ 60,000.00
@ JUMLAH 11,700.00
G.6.6.25 1 KG PEMBESIAN DG BESI ULIR
1.0500 Kg Besi beton @ 16,000.00   16,800.00
0.0150 Kg Kawat beton @ 10,000.00   150.00
0.0070 OH pekerja @ 45,000.00
0.0070 OH tukang besi @ 55,000.00
0.0007 OH kepala tukang @ 60,000.00
0.0003 OH mandor @ 60,000.00
@ JUMLAH 16,950.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 58/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G.6.6.26 1 KG KABEL PRESSTRESSED POLOS/STRANDS


1.0500 Kg besi presstressed polos @ 11,000.00   11,550.00
0.0100 Kg Kawat beton @ 10,000.00   100.00
0.0050 OH pekerja @ 45,000.00
0.0050 OH tukang besi @ 55,000.00
0.0005 OH kepala tukang @ 60,000.00
0.0003 OH mandor @ 60,000.00
JUMLAH 11,650.00
G.6.6.27 1 KG JARING KAWAT BAJA
1.0200 Kg Besi jaring kawat baja @ 11,000.00   11,220.00
0.8050 Kg Kawat beton @ 10,000.00   8,050.00
0.0250 OH pekerja @ 45,000.00
0.0250 OH tukang besi @ 55,000.00
0.0025 OH kepala tukang @ 60,000.00
0.0015 OH mandor @ 60,000.00
JUMLAH 19,270.00
G.6.6.28 1M2 PASANG BEKISTING UNTUK PONDASI
0.0400 M3 kayu terentang @ 1,037,571.94   41,502.88
0.3000 Kg paku biasa 2' - 5' @ 11,825.00   3,547.50
0.1000 lt minyak bekisting @ 5,000.00   500.00
0.3000 OH pekerja @ 45,000.00
0.2600 OH tukang besi @ 55,000.00
0.0260 OH kepala tukang @ 60,000.00
0.0050 OH mandor @ 60,000.00
JUMLAH 45,550.38
G. 6.6.29 1 M2 PASANG BEKISTING UNTUK SLOOF ( 2 x pakai )
0.0450 m3 papan kayu kelas 2 @ 1,037,571.94   46,690.74
0.3000 kg paku biasa 2' - 5' @ 11,825.00   3,547.50
0.1000 lt minyak bekisting @ 5,000.00   500.00
0.3000 OH pekerja @ 45,000.00

0.2600 OH tukang kayu @ 55,000.00


0.0260 OH kepala tukang @ 60,000.00
0.0050 OH mandor @ 60,000.00
JUMLAH 50,738.24
G. 6.6.30 1 M2 PASANG BEKISTING UNTUK KOLOM ( 2 x pakai )
0.0400 m3 papan kayu kelas 2 @ 1,037,571.94   41,502.88
0.4000 kg paku biasa 2' - 5' @ 11,825.00   4,730.00
0.2000 lt minyak bekisting @ 5,000.00   1,000.00
0.0150 m3 balok kayu meranti @ 1,037,571.94   15,563.58
0.3500 lbr plywood tebal 9 mm @ 150,000.00   52,500.00
2.0000 btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   19,000.00
0.3000 oh pekerja @ 45,000.00
0.3300 oh tukang kayu @ 55,000.00
0.0330 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 134,296.46

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 59/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.31 1 M2 PASANG BEKISTING UNTUK BALOK ( 2 x pakai )


0.0400 m3 papan kayu kelas 2 @ 1,037,571.94   41,502.88
0.4000 kg paku biasa 2' - 5' @ 11,825.00   4,730.00
0.2000 lt minyak bekisting @ 5,000.00   1,000.00
0.0180 m3 balok kayu meranti @ 1,037,571.94   18,676.29
0.3500 lbr plywood tebal 9 mm @ 150,000.00
2.0000 btg dolken kayu galam dia 8 - 10/4 @ 9,500.00
0.3200 oh pekerja @ 45,000.00
0.3300 oh tukang kayu @ 55,000.00
0.0330 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
65,909.17
G. 6.6.32 1 M2 PASANG BEKISTING UNTUK LANTAI ( 2 x pakai )
0.0400 m3 papan kayu kelas 2 @ 1,037,571.94   41,502.88
0.4000 kg paku biasa 2' - 5' @ 11,825.00   4,730.00
0.2000 lt minyak bekisting @ 5,000.00   1,000.00
0.0150 m3 balok kayu meranti @ 1,037,571.94   15,563.58
0.3500 lbr plywood tebal 9 mm @ 150,000.00
6.0000 btg dolken kayu galam dia 8 - 10/4 @ 9,500.00
0.3200 oh pekerja @ 45,000.00
0.3300 oh tukang kayu @ 55,000.00
0.0330 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 62,796.46
G. 6.6.33 1 M2 PASANG BEKISTING UNTUK DINDING ( 2 x pakai )
0.0300 m3 papan kayu kelas 2 @ 1,037,571.94   31,127.16
0.4000 kg paku biasa 2' - 5' @ 11,825.00   4,730.00
0.2000 lt minyak bekisting @ 5,000.00   1,000.00
0.0200 m3 balok kayu meranti @ 1,037,571.94   20,751.44
0.3500 lbr plywood tebal 9 mm @ 150,000.00   52,500.00

3.0000 btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   28,500.00


4.0000 bh formtie/penjaga jarak/spacer  @ 1,500.00   6,000.00
0.3200 oh pekerja @ 45,000.00
0.3300 oh tukang kayu @ 55,000.00
0.0330 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 144,608.60

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 60/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.34 1 M2 PASANG BEKISTING UNTUK TANGGA


0.0300 m3 kayu terentang @ 1,037,571.94   31,127.16
0.4000 kg paku biasa 2' - 5' @ 11,825.00   4,730.00
0.1500 lt minyak bekisting @ 5,000.00   750.00
0.0150 m3 balok kayu meranti @ 1,037,571.94   15,563.58
0.3500 lbr plywood tebal 9 mm @ 150,000.00   52,500.00
2.0000 btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   19,000.00
0.3200 oh pekerja @ 45,000.00
0.3300 oh tukang kayu @ 55,000.00
0.0330 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 123,670.74
G. 6.6.35 1M3 MEMBUAT BETON DENGAN MUTU K 225
338.0000 m3 Semen portland @ 860.00   290,680.00
0.6500 kg Pasir beton @ 324,567.03   210,968.57
0.6500 lt Koral Beton @ 314,567.03   204,468.57
6.0000 oh pekerja @ 45,000.00
1.0000 oh tukang kayu @ 55,000.00
0.1000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 706,117.14
G. 6.6.36 1M3 MEMBUAT BETON DENGAN MUTU K 275
400.0000 m3 Semen portland @ 860.00   344,000.00
0.4000 kg Pasir beton @ 324,567.03   129,826.81
0.8200 lt Koral Beton @ 314,567.03   257,944.96
6.0000 oh pekerja @ 45,000.00
1.0000 oh tukang kayu @ 55,000.00
0.1000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 731,771.78

G. 6.6.37 1 M2 PASANG JEMBATAN COR


0.0264 m3 kayu terentang @ 1,037,571.94   27,391.90
0.6000 kg paku biasa 2' - 5' @ 11,825.00   7,095.00
0.5000 btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   4,750.00
0.1500 oh pekerja @ 45,000.00
0.0500 oh tukang kayu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 39,236.90

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 61/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.38 1M3 MEMBUAT PONDASI BETON BERTULANG (150KG BESI + BEKISTING)


0.2000 m3 kayu terentang @ 1,037,571.94   207,514.39
1.5000 kg paku biasa 2' - 5' @ 11,825.00   17,737.50
0.4000 lt minyak bekisting @ 5,000.00   2,000.00
150.0000 kg besi beton polos @ 11,000.00   1,650,000.00
2.2500 kg kawat beton @ 10,000.00   22,500.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
3.9000 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
1.0400 oh tukang kayu @ 55,000.00
1.0500 oh Tukang Besi @ 55,000.00
0.2450 oh kepala tukang @ 60,000.00
0.1650 oh mandor @ 60,000.00
JUMLAH 2,591,669.03
G. 6.6.39 1M3 MEMBUAT SLOOF BETON BERTULANG (200KG BESI + BEKISTING)
0.2700 m3 kayu terentang @ 1,037,571.94   280,144.42
2.0000 kg paku biasa 2' - 5' @ 11,825.00   23,650.00
0.6000 lt minyak bekisting @ 5,000.00   3,000.00
200.0000 kg besi beton polos @ 11,000.00   2,200,000.00
3.0000 kg kawat beton @ 10,000.00   30,000.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
4.8500 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
1.5600 oh tukang kayu @ 55,000.00
1.4000 oh Tukang Besi @ 55,000.00
0.3310 oh kepala tukang @ 60,000.00

0.1700 oh mandor @ 60,000.00


JUMLAH 3,228,711.56

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 62/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.40 1M3 MEMBUAT KOLOM BETON BERTULANG (300KG BESI + BEKISTING)


0.4000 m3 kayu terentang @ 1,037,571.94   415,028.78
4.0000 kg paku biasa 2' - 5' @ 11,825.00   47,300.00
2.0000 lt minyak bekisting @ 5,000.00   10,000.00
300.0000 kg besi beton polos @ 11,000.00   3,300,000.00
4.5000 kg kawat beton @ 10,000.00   45,000.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
0.1500 m3 Kayu meranti balok  @ 1,037,571.94   155,635.79
3.5000 lbr  Plywood 9 mm @ 150,000.00   525,000.00
20.0000 Btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   190,000.00
7.3000 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
3.3000 oh tukang kayu @ 55,000.00
2.1000 oh Tukang Besi @ 55,000.00
0.5700 oh kepala tukang @ 60,000.00
0.2500 oh mandor @ 60,000.00
JUMLAH 5,379,881.70
G. 6.6.41 1M3 MEMBUAT BALOK BETON BERTULANG (200KG BESI + BEKISTING)
0.3200 m3 kayu terentang @ 1,037,571.94   332,023.02
3.2000 kg paku biasa 2' - 5' @ 11,825.00   37,840.00
1.6000 lt minyak bekisting @ 5,000.00   8,000.00
200.0000 kg besi beton polos @ 11,000.00   2,200,000.00
3.0000 kg kawat beton @ 10,000.00   30,000.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
0.1400 m3 Kayu meranti balok  @ 1,037,571.94   145,260.07
2.8000 lbr  Plywood 9 mm @ 150,000.00   420,000.00
16.0000 Btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   152,000.00
5.9600 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
2.8000 oh tukang kayu @ 55,000.00
1.4000 oh Tukang Besi @ 55,000.00
0.4550 oh kepala tukang @ 60,000.00
0.2080 oh mandor @ 60,000.00
JUMLAH 4,017,040.23

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 63/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.42 1M3 MEMBUAT BALOK BETON BERTULANG (150KG BESI + BEKISTING)


0.3200 m3 kayu terentang @ 1,037,571.94   332,023.02
3.2000 kg paku biasa 2' - 5' @ 11,825.00   37,840.00
1.6000 lt minyak bekisting @ 5,000.00   8,000.00
150.0000 kg besi beton polos @ 11,000.00   1,650,000.00
2.2500 kg kawat beton @ 10,000.00   22,500.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
0.1200 m3 Kayu meranti balok  @ 1,037,571.94   124,508.63
2.8000 lbr  Plywood 9 mm @ 150,000.00   420,000.00
32.0000 Btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   304,000.00
5.8000 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
2.8000 oh tukang kayu @ 55,000.00
1.0500 oh Tukang Besi @ 55,000.00
0.4200 oh kepala tukang @ 60,000.00
0.1850 oh mandor @ 60,000.00
JUMLAH 3,590,788.79
G. 6.6.43 1M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING)
0.2400 m3 kayu terentang @ 1,037,571.94   249,017.27
3.2000 kg paku biasa 2' - 5' @ 11,825.00   37,840.00
1.6000 lt minyak bekisting @ 5,000.00   8,000.00
150.0000 kg besi beton polos @ 11,000.00   1,650,000.00
2.2500 kg kawat beton @ 10,000.00   22,500.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
0.1600 m3 Kayu meranti balok  @ 1,037,571.94   166,011.51
2.8000 lbr  Plywood 9 mm @ 150,000.00   420,000.00
24.0000 Btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   228,000.00
5.6000 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
2.6400 oh tukang kayu @ 55,000.00
1.0500 oh Tukang Besi @ 55,000.00
0.4000 oh kepala tukang @ 60,000.00
0.1930 oh mandor @ 60,000.00
JUMLAH 3,473,285.91

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 64/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.44 1M3 MEMBUAT TANGGA BETON BERTULANG (200KG BESI + BEKISTING)


0.2500 m3 kayu terentang @ 1,037,571.94   259,392.98
3.0000 kg paku biasa 2' - 5' @ 11,825.00   35,475.00
1.2000 lt minyak bekisting @ 5,000.00   6,000.00
200.0000 kg besi beton polos @ 11,000.00   2,200,000.00
3.0000 kg kawat beton @ 10,000.00   30,000.00
323.0000 kg Semen portland @ 860.00   277,780.00
0.5200 m3 Pasir beton @ 324,567.03   168,774.86
0.7800 m3 Koral Beton @ 314,567.03   245,362.28
0.1050 m3 Kayu meranti balok  @ 1,037,571.94   108,945.05
2.5000 lbr  Plywood 9 mm @ 150,000.00   375,000.00
14.0000 Btg dolken kayu galam dia 8 - 10/4 @ 9,500.00   133,000.00
5.6000 oh pekerja @ 45,000.00
0.3500 oh Tukang batu @ 55,000.00
2.3000 oh tukang kayu @ 55,000.00
1.4000 oh Tukang Besi @ 55,000.00
0.4050 oh kepala tukang @ 60,000.00
0.2020 oh mandor @ 60,000.00
JUMLAH 3,839,730.18
G. 6.6.45 1M3 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11x11) CM
0.0020 m3 kayu terentang @ 1,037,571.94   2,075.14
0.0100 kg paku biasa 2' - 5' @ 11,825.00   118.25
3.0000 kg besi beton polos @ 11,000.00   33,000.00
0.4500 kg kawat beton @ 10,000.00   4,500.00
4.0000 kg Semen portland @ 860.00   3,440.00
0.0060 m3 Pasir beton @ 324,567.03   1,947.40
0.0090 m3 Koral Beton @ 314,567.03   2,831.10
0.0600 oh pekerja @ 45,000.00
0.0200 oh Tukang batu @ 55,000.00
0.0200 oh tukang kayu @ 55,000.00

0.0200 oh Tukang Besi @ 55,000.00


0.0060 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 47,911.90

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 65/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

G. 6.6.46 1M' MEMBUAT RING BALOK BETON BERTULANG (10X15) CM


0.0030 m3 Kayu meranti, balok @ 1,037,571.94   3,112.72
0.0200 kg paku biasa 2' - 5' @ 11,825.00   236.50
3.6000 kg besi beton polos @ 11,000.00   39,600.00
0.0500 kg kawat beton @ 10,000.00   500.00
5.5000 kg Semen portland @ 860.00   4,730.00
0.0090 m3 Pasir beton @ 324,567.03   2,921.10
0.0150 m3 Koral Beton @ 314,567.03   4,718.51
0.1000 oh pekerja @ 45,000.00
0.0330 oh Tukang batu @ 55,000.00
0.0330 oh tukang kayu @ 55,000.00
0.0330 oh Tukang Besi @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 55,818.82
H. PEKERJAAN PENUTUP ATAP
H. 6.6.1 1M2 PASANG ATAP GENTENG PALENTONG KECIL
25.0000 bh genteng palentong @   -
0.1500 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0080 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH -
H. 6.6.2 1M2 PASANG ATAP GENTENG KODOK /GLAZZUR
25.0000 bh genteng kodok @ 1,550.00   38,750.00
0.1500 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0080 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 38,750.00

H. 6.6.3 1M2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR


12.0000 bh genteng palentong super @ -   -
0.1500 oh pekerja @ 45,000.00
0.0600 oh tukang kayu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH -
H. 6.6.4 1M2 PASANG ATAP GENTENG BUBUNG PALENTONG
5.0000 bh genteng bubung palentong @ -   -
8.0000 kg Semen Portland @ 860.00   6,880.00
0.0320 m3 Pasir pasang @ 249,567.03   7,986.14
0.4000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00
JUMLAH 14,866.14

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 66/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.5 1M' PASANG BUBUNG GENTENG KODOK


5.0000 bh genteng bubung kodok @ 2,000.00   10,000.00
8.0000 kg Semen Portland @ 860.00   6,880.00
0.0320 m3 Pasir pasang @ 249,567.03   7,986.14
0.4000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00
JUMLAH 24,866.14
H. 6.6.6 1M2 PASANG BUBUNG GENTENG PALENTONG BESAR
4.0000 bh genteng bubung palentong @ -   -
8.0000 kg Semen Portland @ 860.00   6,880.00
0.0320 m3 Pasir pasang @ 249,567.03   7,986.14
0.4000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0020 oh mandor @ 60,000.00
JUMLAH 14,866.14

H. 6.6.7 1M2 PASANG ROOFLIGHT FIBREGLASS (180X90) CM


0.6000 bh Roof light fibreglass @ -   -
0.0500 kg paku biasa 1/2" - 1" @ 11,825.00   591.25
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 591.25
H. 6.6.8 1m2 PASANG ATAP ASBES GELOMBANG (2,50X0,92)X5MM
0.5000 lbr asbes gelombang @ 23,000.00   11,500.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00

0.0750 oh tukang kayu @ 55,000.00


0.0080 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 13,420.00
H. 6.6.9 1m2 PASANG ATAP ASBES GELOMBANG (2,25X0,92)X5MM
0.6000 lbr asbes gelombang @ 23,000.00   13,800.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0080 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 15,720.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 67/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.10 1m2 PASANG ATAP ASBES GELOMBANG (2,00X0,92)X5MM


0.6000 lbr asbes gelombang @ 23,000.00   13,800.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 15,720.00
H. 6.6.11 1m2 PASANG ATAP ASBES GELOMBANG (1,80X0,92)X5MM
0.7500 lbr asbes gelombang @ 23,000.00   17,250.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 19,170.00
H. 6.6.12 1m2 PASANG ATAP ASBES GELOMBANG (3,00X1,05)X4 MM
0.3500 lbr asbes gelombang @ 23,000.00   8,050.00

0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00


0.1400 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 9,970.00
H. 6.6.13 1m2 PASANG ATAP ASBES GELOMBANG (2,70X1,05)X4 MM
0.4200 lbr asbes gelombang @ 23,000.00   9,660.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0750 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00

0.0070 oh mandor @ 60,000.00


JUMLAH 11,580.00
H. 6.6.14 1m2 PASANG ATAP ASBES GELOMBANG (2,40X1,05)X4 MM
0.4400 lbr asbes gelombang @ 23,000.00   10,120.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 12,040.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 68/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.15 1m2 PASANG ATAP ASBES GELOMBANG (2,10X1,05)X4 MM


0.5100 lbr asbes gelombang @ 23,000.00   11,730.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 13,650.00
H. 6.6.16 1m2 PASANG ATAP ASBES GELOMBANG (1,5X1,05)X4 MM
0.8000 lbr asbes gelombang @ 23,000.00   18,400.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 20,320.00
H. 6.6.17 1m2 PASANG ATAP ASBES GELOMBANG (3,00X1,08)X6 MM
0.3700 lbr asbes gelombang @ 23,000.00   8,510.00

0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00


0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 10,430.00
H. 6.6.18 1m2 PASANG ATAP ASBES GELOMBANG (2,70X1,08)X6 MM
0.3800 lbr asbes gelombang @ 23,000.00   8,740.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00

0.0070 oh mandor @ 60,000.00


JUMLAH 10,660.00
H. 6.6.19 1m2 PASANG ATAP ASBES GELOMBANG (2,40X1,08)X6 MM
0.4600 lbr asbes gelombang @ 23,000.00   10,580.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 12,500.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 69/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.20 1m2 PASANG ATAP ASBES GELOMBANG (2,10X1,08)X6 MM


0.4900 lbr asbes gelombang @ 23,000.00   11,270.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 13,190.00
H. 6.6.21 1m2 PASANG ATAP ASBES GELOMBANG (1,80X1,08)X6 MM
0.5700 lbr asbes gelombang @ 23,000.00   13,110.00
0.1200 kg paku pancing 60 x 230 @ 16,000.00   1,920.00
0.1400 oh pekerja @ 45,000.00
0.0670 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00
JUMLAH 15,030.00
H. 6.6.22 1M' PASANG BUBUNG STEL GELOMBANG 0,92 M
2.4000 lbr bubung stel gelombang @ -   -

6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00


0.0840 oh pekerja @ 45,000.00
0.1250 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 85,800.00
H. 6.6.23 1M' PASANG NOK STEL GELOMBANG 1,05 M
2.1000 lbr nok stel gelombang @ -   -
6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00
0.0840 oh pekerja @ 45,000.00
0.1250 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00

0.0040 oh mandor @ 60,000.00


JUMLAH 85,800.00
H. 6.6.24 1M' PASANG NOK STEL GELOMBANG 1,08 M
2.0500 lbr nok stel gelombang @ -   -
6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00
0.0840 oh pekerja @ 45,000.00
0.1250 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 85,800.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 70/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.25 1M' PASANG NOK paten 0,92 m


1.2000 lbr nok paten @ -   -
6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00
0.0840 oh pekerja @ 45,000.00
0.1250 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 85,800.00
H. 6.6.26 1M' PASANG NOK PATEN 1,05 M
1.2000 lbr nok paten @ -   -
6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00
0.0840 oh pekerja @ 45,000.00
0.1250 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 85,800.00
H. 6.6.27 1M' PASANG NOK PATEN 1,08 M
1.2000 lbr nok paten @ -   -

6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00


0.0840 oh pekerja @ 45,000.00
0.1250 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 85,800.00
H. 6.6.28 1M' PASANG NOK STEL RATA 0,92 M
1.1000 lbr nok stel rata @ -   -
6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00
0.1000 oh pekerja @ 45,000.00
0.1500 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00

0.0040 oh mandor @ 60,000.00


JUMLAH 85,800.00
H. 6.6.29 1M' PASANG NOK STEL RATA 1,05 M
1.1000 lbr nok stel rata @ -   -
6.0000 bh paku skrup 3,5" @ 14,300.00   85,800.00
0.1000 oh pekerja @ 45,000.00
0.1500 oh tukang kayu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 85,800.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 71/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.30 1M2 PASANG ATAP GENTENG BETON


11.0000 bh genteng beton @ 3,500.00   38,500.00
0.0300 kg Paku biasa 2" - 5" @ 11,825.00   354.75
0.2000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 38,854.75
H. 6.6.31 1M2 PASANG ATAP GENTENG ASPAL
6.9000 lbr genteng aspal @ 2,500.00   17,250.00
0.3500 lbr Plywood 4" x 8" x 6 mm @ 92,000.00   32,200.00
0.0300 kg paku biasa 1/2" - 1" @ 11,825.00   354.75
0.5000 bh Plastic aerator @ 1,000.00   500.00
0.2000 oh pekerja @ 45,000.00
0.3000 oh tukang kayu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 50,304.75

H. 6.6.32 1M2 PASANG ATAP GENTENG METAL


1.4200 lbr genteng metal @ 40,000.00   56,800.00
0.2000 kg Paku paku atap metal @ 27,500.00   5,500.00
0.2000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0010 oh mandor @ 60,000.00
JUMLAH 62,300.00
H. 6.6.33 1M' PASANG ATAP SIRAP
60.0000 bh genteng sirap @ 500.00   30,000.00
0.2000 kg paku biasa 1/2" - 1" @ 11,825.00   2,365.00
0.1660 oh pekerja @ 45,000.00

0.2500 oh tukang kayu @ 55,000.00


0.0250 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 32,365.00
H. 6.6.34 1M' PASANG NOK GENTENG BETON
3.5000 bh nok genteng beton @ 5,000.00   17,500.00
0.0500 kg Paku pancing @ 16,000.00   800.00
10.8000 kg Semen abu - abu @ 860.00   9,288.00
0.0320 m3 Pasir pasang @ 249,567.03   7,986.14
1.0000 kg Semen warna @ 1,600.00   1,600.00
0.4000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0200 oh mandor @ 60,000.00
JUMLAH 37,174.14

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 72/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.35 1M' PASANG NOK GENTENG ASPAL


2.0000 bh genteng aspal @ 2,500.00   5,000.00
0.0500 kg paku seng @ 14,300.00   715.00
0.0035 m3 kayu meranti, balok @ 1,037,571.94   3,631.50
0.1250 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 9,346.50
H. 6.6.36 1M' PASANG NOK GENTENG METAL
1.1000 bh genteng decra bond @ -   -
0.0500 kg paku biasa 1/2" - 1" @ 11,825.00   591.25
0.2500 oh pekerja @ 45,000.00
0.1500 oh tukang kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 591.25
H. 6.6.37 1 M' MEMASANG BUBUNGAN ATAP SIRAP L 40 cm

0.4000 lbr seng plat @ 35,000.00   14,000.00


0.1100 kg paku seng @ 14,300.00   1,573.00
0.0040 oh kayu meranti papan 3 cm @ 1,187,571.94   4,750.29
0.1250 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 20,323.29
H. 6.6.38 1 M2 MEMASANG ATAP SENG
0.7000 lbr seng gelombang bjls @ 30,000.00   21,000.00
0.0200 kg paku seng @ 14,300.00   286.00
0.1200 oh pekerja @ 45,000.00

0.0600 oh tukang kayu @ 55,000.00


0.0060 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 21,286.00
H. 6.6.39 1 M2 MEMASANG BUBUNGAN ATAP SENG
1.1000 lbr seng plat @ 35,000.00   38,500.00
0.0500 kg paku seng @ 14,300.00   715.00
0.1500 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 39,215.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 73/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

H. 6.6.40 1 M2 PASANG ATAP ALUMUNIUM


1.0500 m2 atap alumunium gelombang tebal 0,55 @ -   -
0.0200 kg paku hak panjang 15 cm @ 25,000.00   500.00
0.1500 oh pekerja @ 45,000.00
0.7500 oh tukang kayu @ 55,000.00
0.0080 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH 500.00
H. 6.6.41 1 M2 PASANG NOK ALUMUNIUM
1.2000 m2 Nok standar 40 cm 18, swg 22 @ -   -
0.0400 kg paku hak panjang 15 cm @ 25,000.00   1,000.00
0.1000 oh pekerja @ 45,000.00
1.0000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 1,000.00
H. 6.6.42 1 M2 PASANG ALUMUNIUM FOIL /SISALATION
1.0500 lbr Sisalation / alumunium foil @ 450,000.00   472,500.00

0.1500 oh pekerja @ 45,000.00


0.0500 oh tukang kayu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00
0.0080 oh mandor @ 60,000.00
JUMLAH 472,500.00

I. PEKERJAAN PLAFOND
I. 6.6.1 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 6 MM
1.1000 lbr pelat asbes tebal 6 mm @ 29,400.00   32,340.00
0.0100 kg paku plywood @ 20,000.00   200.00
0.0300 oh pekerja @ 45,000.00
0.0700 oh tukang kayu @ 55,000.00

0.0070 oh kepala tukang @ 60,000.00


0.0015 oh mandor @ 60,000.00
JUMLAH 32,540.00
I. 6.6.2 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 5 MM
1.1000 lbr pelat asbes tebal 5 mm @ 21,000.00   23,100.00
0.0100 kg paku plywood @ 20,000.00   200.00
0.0300 oh pekerja @ 45,000.00
0.0700 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0015 oh mandor @ 60,000.00
JUMLAH 23,300.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 74/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

I. 6.6.3 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 4 MM


1.1000 lbr pelat asbes tebal 4 mm @ 22,000.00   24,200.00
0.0100 kg paku plywood @ 20,000.00   200.00
0.0300 oh pekerja @ 45,000.00
0.0700 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0015 oh mandor @ 60,000.00
JUMLAH 24,400.00
I. 6.6.4 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 3,5 MM
1.1000 lbr pelat asbes tebal 5 mm @ 21,000.00   23,100.00
0.0100 kg paku plywood @ 20,000.00   200.00
0.0300 oh pekerja @ 45,000.00
0.0700 oh tukang kayu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0015 oh mandor @ 60,000.00
JUMLAH 23,300.00
I. 6.6.5 1 M2 PLAFOND AKUSTIK (30 X 30) CM
11.5000 lbr akustik ukuran 30 x 30 cm @   -

0.0500 kg paku plywood @ 20,000.00   1,000.00


0.0600 oh pekerja @ 45,000.00
0.1200 oh tukang kayu @ 55,000.00
0.1200 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 1,000.00
I. 6.6.6 1 M2 PLAFOND AKUSTIK (30 X 60) CM
5.8000 lbr akustik ukuran 30 x 60 cm @   -
0.0500 kg paku plywood @ 20,000.00   1,000.00
0.0600 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00

0.0030 oh mandor @ 60,000.00


JUMLAH 1,000.00
I. 6.6.7 1 M2 PLAFOND AKUSTIK (60 X 120) CM
1.5000 lbr akustik arm strong 60 x 120 cm @   -
0.0500 kg paku plywood @ 20,000.00   1,000.00
0.0600 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 1,000.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 75/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

I. 6.6.8 1 M2 PLAFOND PLYWOOD ( 30 X 60 ) cm, TEBAL 4 MM


0.3600 lbr Plywood 4mm @ 61,500.00   22,140.00
0.0300 kg paku plywood @ 20,000.00   600.00
0.0700 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0035 oh mandor @ 60,000.00
JUMLAH 22,740.00
I. 6.6.9 1 M2 PLAFOND PLYWOOD ( 30 X 60 ) cm, TEBAL 6 MM
0.3600 lbr Plywood 6mm @ 92,000.00   33,120.00
0.0300 kg paku plywood @ 20,000.00   600.00
0.0700 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0035 oh mandor @ 60,000.00
JUMLAH 33,720.00
I. 6.6.10 1 M2 PLAFOND PLYWOOD ( 60 X 120 ) cm, TEBAL 2 MM
0.3750 lbr Plywood 2mm @ 30,666.67   11,500.00

0.0300 kg paku plywood @ 20,000.00   600.00


0.0700 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0035 oh mandor @ 60,000.00
JUMLAH 12,100.00
I. 6.6.11 1 M2 PLAFOND PLYWOOD ( 60 X 120 ) cm, TEBAL 6 MM
0.3750 lbr Plywood 6mm @ 92,000.00   34,500.00
0.0300 kg paku plywood @ 20,000.00   600.00
0.0700 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00

0.0035 oh mandor @ 60,000.00


JUMLAH 35,100.00
I. 6.6.12 1 M2 PLAFOND TEAKWOOD ( 30 x 60 ) cm, TEBAL 4 MM
0.3600 lbr Teakwood 4 mm @ 113,500.00   40,860.00
0.0300 kg paku plywood @ 20,000.00   600.00
0.0700 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0035 oh mandor @ 60,000.00
JUMLAH 41,460.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 76/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

I. 6.6.13 1 M2 PLAFOND TEAKWOOD ( 60 x 120 ) cm, TEBAL 4 MM


0.3750 lbr Teakwood 4 mm @ 113,500.00   42,562.50
0.0300 kg paku plywood @ 20,000.00   600.00
0.0700 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0035 oh mandor @ 60,000.00
JUMLAH 43,162.50
I. 6.6.14 1M2 PLAFOND LAT KAYU JATI, PAPAN
0.0240 lbr Kayu jati, papan @ 7,000,000.00   168,000.00
0.0100 Kg paku biasa @ 11,825.00   118.25
0.0500 kg paku sekrup @ 14,300.00   715.00
0.2000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 168,833.25
I. 6.6.15 1M2 PLAFOND LAT KAYU MERANTI

0.0240 lbr Kayu meranti, papan @ 1,187,571.94   28,501.73


0.0100 Kg paku biasa @ 11,825.00   118.25
0.0500 kg paku sekrup @ 14,300.00   715.00
0.2000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 29,334.98
I. 6.6.16 1M2 PLAFOND LAT KAYU BENGKIRAI
0.0240 lbr Kayu bengkirai, papan @ 2,137,571.94   51,301.73
0.0100 Kg paku biasa @ 11,825.00   118.25
0.0500 kg paku sekrup @ 14,300.00   715.00

0.2000 oh pekerja @ 45,000.00


0.2000 oh tukang kayu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH 52,134.98
I. 6.6.17 1M2 PLAFOND SOFTBOARD
0.3500 lbr Softboard 4' x 8' x 4 mm @   -
0.0300 Kg paku biasa @ 11,825.00   354.75
0.6000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 354.75

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 77/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

I. 6.6.18 1M2 PLAFOND AKUSTIK 60 X 120 CM + RANGKA ALUMUNIUM


3.6000 M' Profil alumunium T @   -
0.1500 kg Kawat seng polos @   -
1.0000 bh Ramset / dina bold @   -
1.5000 lbr akustik arm strong 60 x 120 cm @ -   -
0.1500 oh pekerja @ 45,000.00
0.5000 oh tukang kayu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0075 oh mandor @ 60,000.00
JUMLAH -
I. 6.6.19 1M2 PLAFOND KAYU PROFIL
1.1000 lbr List kayu profil bengkirai @ 4,250.00   4,675.00
0.0100 Kg paku biasa @ 11,825.00   118.25
0.0500 oh pekerja @ 45,000.00
0.0500 oh tukang kayu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 4,793.25

I. 6.6.20 1M2 PLAFOND ASBES ( 1,00 X 1,00 ) M, TEBAL 3,2MM RANGKA MERANTI
0.0120 m3 kayu meranti @ 1,037,571.94   12,450.86
0.0600 Kg paku biasa @ 11,825.00   709.50
1.1000 lbr asbes 1,00 x 1,00 m @   21,000.00
0.1800 oh pekerja @ 45,000.00
0.3200 oh tukang kayu @ 55,000.00
0.0320 oh kepala tukang @ 60,000.00
0.0090 oh mandor @ 60,000.00
JUMLAH 13,160.36
I. 6.6.21 1M2 PLAFOND PLYWOOD 4 MM + RANGKA KAYU MERANTI
0.0230 m3 kayu meranti @ 1,037,571.94   23,864.15
0.0600 kg paku biasa @ 11,825.00   709.50

0.3900 lbr Plywood 4' x 8' x 4mm @ 61,500.00   23,985.00


0.2700 oh pekerja @ 45,000.00
0.4000 oh tukang kayu @ 55,000.00
0.0400 oh kepala tukang @ 60,000.00
0.0135 oh mandor @ 60,000.00
JUMLAH 48,558.65
I. 6.6.22 1M2 PLAFOND AKUSTIK (30 X 60 ) CM + RANGKA KAYU MERANTI
0.0230 m3 kayu meranti @ 1,037,571.94   23,864.15
0.0600 kg paku biasa @ 11,825.00   709.50
5.8000 bh akustik 30 x 60 cm @ -   -
0.2600 oh pekerja @ 45,000.00
0.4000 oh tukang kayu @ 55,000.00
0.0400 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 24,573.65

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 78/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

I. 6.6.23 1M2 PLAFOND AKUSTIK (30 X 30 ) CM + RANGKA KAYU MERANTI


0.0270 m3 kayu meranti, balok @ 1,037,571.94   28,014.44
0.0600 kg paku @ 11,825.00   709.50
11.5000 bh akustik 30 x30 cm @ -   -
0.3100 oh pekerja @ 45,000.00
0.4700 oh tukang kayu @ 55,000.00
0.0470 oh kepala tukang @ 60,000.00
0.0155 oh mandor @ 60,000.00
JUMLAH 28,723.94
I. 6.6.24 1M2 PLAFOND GYPSUM BOARD, TEBAL 9 MM
0.3640 lbr Gypsum board ( 120 x 240 x 9 ) mm @ 45,000.00   16,380.00
0.1100 kg paku sekrup @ 14,300.00   1,573.00
0.1000 oh pekerja @ 45,000.00
0.0500 oh tukang kayu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 17,953.00
J. PEKERJAAN SANITAIR

J. 6.6.1 MEMASANG 1 BH CLOSED DUDUK / MONOBLOK


1.0000 bh closed duduk monoblok @ 1,200,000.00   1,200,000.00
6.0000 % perlengkapan (6 % harga klosed) @ 72,000.00   72,000.00
3.3000 oh pekerja @ 45,000.00
1.1000 oh tukang kayu @ 55,000.00
0.0010 oh kepala tukang @ 60,000.00
0.1600 oh mandor @ 60,000.00
JUMLAH 1,272,000.00

J. 6.6.2 MEMASANG 1 BH CLOSED JONGKOK KERAMIK


1.0000 bh closed jongkok keramik @ 120,000.00   120,000.00
6.0000 kg semen portland @ 860.00   5,160.00

0.0100 m3 pasir pasang @ 249,567.03   2,495.67


1.0000 oh pekerja @ 45,000.00
1.5000 oh tukang kayu @ 55,000.00
1.5000 oh kepala tukang @ 60,000.00
0.1600 oh mandor @ 60,000.00
JUMLAH 127,655.67
J. 6.6.3 MEMASANG 1 BH CLOSED JONGKOK TERASO
1.0000 bh closed jongkok teraso @ 80,000.00   80,000.00
7.0000 bh Bata Merah @ 550.00   3,850.00
6.0000 Kg semen portland @ 860.00   5,160.00
0.0100 m3 pasir pasang @ 249,567.03   2,495.67
1.0000 oh Pekerja @ 45,000.00
1.5000 oh Tukang Batu @ 55,000.00
0.3000 oh kepala tukang @ 60,000.00
0.1100 oh mandor @ 60,000.00
JUMLAH 91,505.67

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 79/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.4 MEMASANG 1 BH URINOIR


1.0000 bh urinoir @ 1,500,000.00   1,500,000.00
30.0000 % Perlengkapan @ 450,000.00   450,000.00
6.0000 Kg Semen Portland @ 860.00   5,160.00
0.0100 m3 Pasir Pasang @ 249,567.03   2,495.67
1.0000 oh pekerja @ 45,000.00
1.0000 oh Tukang Batu @ 55,000.00
0.1000 oh kepala tukang @ 60,000.00
0.1000 oh mandor @ 60,000.00
JUMLAH 1,957,655.67
J. 6.6.5 MEMASANG 1 BH WASTAFEL
1.0000 bh Wastafel @ 450,000.00   450,000.00
12.0000 % Perlengkapan @ 54,000.00   648,000.00
6.0000 Kg Semen Portland @ 860.00   5,160.00
0.0100 m3 pasir pasang @ 249,567.03   2,495.67
1.2000 oh pekerja @ 45,000.00
1.4500 oh Tukang Batu @ 55,000.00
0.1500 oh kepala tukang @ 60,000.00
0.1000 oh mandor @ 60,000.00
JUMLAH 1,105,655.67
J. 6.6.6 MEMASANG 1 BH BAK MANDI TERASO VOLUME 0.30 M3
1.0000 bh Bak Teraso @ 185,000.00   185,000.00
6.0000 Kg semen portland @ 860.00   5,160.00
0.0100 m3 pasir pasang @ 249,567.03   2,495.67
2.1000 oh pekerja @ 45,000.00
0.7500 oh Tukang Batu @ 55,000.00
0.0700 oh kepala tukang @ 60,000.00
0.1100 oh mandor @ 60,000.00
JUMLAH 192,655.67
J. 6.6.7 MEMASANG 1 BH BAK MANDI FIBREGLASS VOLUME 0,30 M3
1.0000 bh Bak Fiberglass @ 145,000.00   145,000.00

18.0000 % Perlengkapan @ 26,100.00   469,800.00


1.8000 oh pekerja @ 45,000.00
2.7000 oh Tukang Batu @ 55,000.00
0.5400 oh kepala tukang @ 60,000.00
0.1100 oh mandor @ 60,000.00
JUMLAH 614,800.00
J. 6.6.8 MEMASANG 1 BH BAK AIR BATU BATA VOLUME 0,3 M3 ( 60 x 60 )
  2.4000 0.4000 bh batu bata @ 550.00   220.00
0.012 120.0000 kg semen portland @ 860.00   103,200.00
0.3000 m3 pasir pasang @ 249,567.03   74,870.11
360.0000 Bh Porselen ( 11x11)cm @ 2,500.00   900,000.00
6.0000 kg Semen nat @ 1,600.00   9,600.00

6.0000 oh pekerja @ 45,000.00


3.0000 oh tukang batu @ 55,000.00
0.3000 oh kepala tukang @ 60,000.00
0.3000 oh mandor @ 60,000.00
JUMLAH 1,087,890.11

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 80/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.9 MEMASANG 1 BH BADKIP PORSELEN


1.0000 bh Badkip @   -
6.0000 % Perlengkapan @ -   -
- oh pekerja @ 45,000.00
0.0750 oh Tukang Batu @ 55,000.00
0.7500 oh kepala tukang @ 60,000.00
0.2500 oh mandor @ 60,000.00
JUMLAH -
J. 6.6.9 MEMASANG 1 BH BADKIP PORSELEN
1.0000 bh Badkip @ -   -
6.0000 % Perlengkapan @ -   -
- oh pekerja @ 45,000.00
0.0750 oh Tukang Batu @ 55,000.00
0.7500 oh kepala tukang @ 60,000.00
0.2500 oh mandor @ 60,000.00
JUMLAH -
J. 6.6.9 MEMASANG 1 BH BADKIP PORSELEN
1.0000 bh Badkip @ -   -

6.0000 % Perlengkapan @ -   -
- oh pekerja @ 45,000.00
0.0750 oh Tukang Batu @ 55,000.00
0.7500 oh kepala tukang @ 60,000.00
0.2500 oh mandor @ 60,000.00
JUMLAH -
J. 6.6.10 MEMASANG 1 BH BAK BETON VOLUME 1 M3 AIR
0.9000 m3 Beton 1 : 1,5 : 2,5 @ 922,795.80   830,516.22
180.0000 kg Besi Beton @ 11,000.00   1,980,000.00
8.0000 m3 kayu cetakan @ 1,037,571.94   8,300,575.51
5.0000 m2 Ubin Porselen @ 62,500.00   312,500.00
10.0000 % Perlengkapan @ 6,250.00   62,500.00

3.5000 oh pekerja @ 45,000.00


4.5000 oh Tukang Batu @ 55,000.00
0.9000 oh kepala tukang @ 60,000.00
0.9000 oh mandor @ 60,000.00
JUMLAH 11,486,091.72
J. 6.6.11 MEMASANG 1 BH BAK FIBERGLASS VOLUME 1 M3 AIR
1.0000 bh Bak Fiberglass @ 450,000.00   450,000.00
12.0000 % Perlengkapan @ 54,000.00   648,000.00
3.0000 oh pekerja @ 45,000.00
4.5000 oh Tukang Batu @ 55,000.00
0.9000 oh kepala tukang @ 60,000.00
0.9000 oh mandor @ 60,000.00
JUMLAH 1,098,000.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 81/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.12 MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.15 CM
1.6000 bh Pipa tanah @   -
0.6800 kg Semen Portland @ 860.00   584.80
0.0130 m3 pasir pasang @ 249,567.03   3,244.37
0.0110 m3 pasir urug @ 199,567.03   2,195.24
0.0600 oh pekerja @ 45,000.00
0.0300 oh Tukang Batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 6,024.41
J. 6.6.13 MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.20 CM
1.6000 bh Pipa tanah @   -
0.8700 kg Semen Portland @ 860.00   748.20
0.0140 m3 pasir pasang @ 249,567.03   3,493.94
0.0140 m3 pasir urug @ 199,567.03   2,793.94
0.0800 oh pekerja @ 45,000.00
0.0400 oh Tukang Batu @ 55,000.00
0.0040 oh kepala tukang @ 60,000.00

0.0070 oh mandor @ 60,000.00


JUMLAH 7,036.08
J. 6.6.14 MEMASANG 1M' PIPA BETON, DIAMETER 15 - 20 CM
1.1000 bh p ipa beton @   -
0.0270 m3 Batu bata @ 550.00   14.85
3.9200 kg Semen Portland @ 860.00   3,371.20
0.0560 m3 pasir pasang @ 249,567.03   13,975.75
0.0240 m3 pasir urug @ 199,567.03   4,789.61
0.1400 oh pekerja @ 45,000.00
0.0700 oh Tukang Batu @ 55,000.00
0.0070 oh kepala tukang @ 60,000.00
0.0070 oh mandor @ 60,000.00

JUMLAH 22,151.41
J. 6.6.15 MEMASANG 1M' PIPA BETON, DIAMETER 30 - 100 CM
1.1000 bh p ipa beton @   -
0.5500 m3 Batu bata @ 550.00   302.50
10.3000 kg Semen Portland @ 860.00   8,858.00
0.0610 m3 pasir pasang @ 249,567.03   15,223.59
0.0690 m3 pasir urug @ 199,567.03   13,770.12
0.3800 oh pekerja @ 45,000.00
0.1900 oh Tukang Batu @ 55,000.00
0.0190 oh kepala tukang @ 60,000.00
0.0190 oh mandor @ 60,000.00
JUMLAH 38,154.21

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 82/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.16 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (30X30)CM TINGGI 35 CM
0.1450 bh Batu bata @ 550.00   79.75
44.0000 m3 Semen Portland @ 860.00   37,840.00
0.0700 kg pasir pasang @ 249,567.03   17,469.69
0.0700 m3 Batu kerikil @ 314,567.03   22,019.69
1.6000 kg Besi Beton @ 11,000.00   17,600.00
0.0600 m3 Pasir Beton @ 324,567.03
3.2000 oh pekerja @ 45,000.00
1.0150 oh Tukang Batu @ 55,000.00
0.0015 oh kepala tukang @ 60,000.00
0.0160 oh mandor @ 60,000.00
JUMLAH 95,009.13
J. 6.6.17 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (45X45)CM TINGGI 50 CM
0.2500 bh Batu bata @ 550.00   137.50
77.0000 m3 Semen Portland @ 860.00   66,220.00
0.1300 kg pasir pasang @ 249,567.03   32,443.71
0.0200 m3 Batu kerikil @ 314,567.03   6,291.34
2.6000 kg Besi Beton @ 11,000.00   28,600.00

0.0900 m3 Pasir Beton @ 324,567.03   29,211.03


1.4200 oh pekerja @ 45,000.00
0.4730 oh Tukang Batu @ 55,000.00
0.0470 oh kepala tukang @ 60,000.00
0.0710 oh mandor @ 60,000.00
JUMLAH 162,903.59
J. 6.6.18 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (60 x 60)CM TINGGI 65 CM
0.3710 bh Batu bata @ 550.00   204.05
114.0000 m3 Semen Portland @ 860.00   98,040.00
0.1840 kg pasir pasang @ 249,567.03   45,920.33
0.0330 m3 Batu koral @ 314,567.03   10,380.71
4.8500 kg Besi Beton @ 11,000.00   53,350.00

0.1200 m3 Pasir Beton @ 324,567.03   38,948.04


2.1600 oh pekerja @ 45,000.00
0.7200 oh Tukang Batu @ 55,000.00
0.0720 oh kepala tukang @ 60,000.00
0.1080 oh mandor @ 60,000.00
0.1000 oh Tukang gali @ 45,000.00
JUMLAH 246,843.14
J. 6.6.19 MEMASANG 1M' PIPA GALVANIS DIAMETER 1/2"
1.2000 m' Pipa galvanis @ 7,500.00   9,000.00
35.0000 % Perlengkapan @ 2,625.00   91,875.00
0.0540 oh pekerja @ 45,000.00
0.0900 oh Tukang Batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0270 oh mandor @ 60,000.00
JUMLAH 100,875.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 83/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.20 MEMASANG 1M' PIPA GALVANIS DIAMETER 3/4"


1.2000 m' Pipa galvanis @ 11,250.00   13,500.00
35.0000 % Perlengkapan @ 3,937.50   137,812.50
0.0540 oh pekerja @ 45,000.00
0.0900 oh Tukang Batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0270 oh mandor @ 60,000.00
JUMLAH 151,312.50
J. 6.6.21 MEMASANG 1M' PIPA GALVANIS DIAMETER 1 "
1.2000 m' Pipa galvanis @ 15,000.00   18,000.00
35.0000 % Perlengkapan @ 5,250.00   183,750.00
0.0540 oh pekerja @ 45,000.00
0.0900 oh Tukang Batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0270 oh mandor @ 60,000.00
JUMLAH 201,750.00
J. 6.6.22 MEMASANG 1M' PIPA GALVANIS DIAMETER 1 1/2 "
1.2000 m' Pipa galvanis @ 22,500.00   27,000.00

35.0000 % Perlengkapan @ 7,875.00   275,625.00


0.1080 oh pekerja @ 45,000.00
0.1800 oh Tukang Batu @ 55,000.00
0.0180 oh kepala tukang @ 60,000.00
0.0054 oh mandor @ 60,000.00
JUMLAH 302,625.00
J. 6.6.23 MEMASANG 1M' PIPA GALVANIS DIAMETER 3"
1.2000 m' Pipa galvanis @ 93,000.00   111,600.00
35.0000 % Perlengkapan @ 32,550.00   1,139,250.00
0.1080 oh pekerja @ 45,000.00
0.1800 oh Tukang Batu @ 55,000.00
0.0180 oh kepala tukang @ 60,000.00

0.0054 oh mandor @ 60,000.00


JUMLAH 1,250,850.00
J. 6.6.24 MEMASANG 1M' PIPA GALVANIS DIAMETER 4 "
1.2000 m' Pipa galvanis @ 110,000.00   132,000.00
35.0000 % Perlengkapan @ 38,500.00   1,347,500.00
0.1350 oh pekerja @ 45,000.00
0.2250 oh Tukang Batu @ 55,000.00
0.0225 oh kepala tukang @ 60,000.00
0.0068 oh mandor @ 60,000.00
JUMLAH 1,479,500.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 84/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.25 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1/2 "


1.2000 m' Pipa PVC @ 3,125.00   3,750.00
35.0000 % Perlengkapan @ 1,093.75   38,281.25
0.0360 oh pekerja @ 45,000.00
0.0600 oh Tukang Batu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH 42,031.25
J. 6.6.26 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4"
1.2000 m' Pipa PVC @ 3,750.00   4,500.00
35.0000 % Perlengkapan @ 1,312.50   45,937.50
0.0360 oh pekerja @ 45,000.00
0.0600 oh Tukang Batu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH 50,437.50
J. 6.6.27 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1 "
1.2000 m' Pipa PVC @ 6,250.00   7,500.00

35.0000 % Perlengkapan @ 2,187.50   76,562.50


0.0360 oh pekerja @ 45,000.00
0.0600 oh Tukang Batu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH 84,062.50
J. 6.6.28 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1 1/2 "
1.2000 m' Pipa PVC @ 9,375.00   11,250.00
35.0000 % Perlengkapan @ 3,281.25   114,843.75
0.0360 oh pekerja @ 45,000.00
0.0600 oh Tukang Batu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00

0.0018 oh mandor @ 60,000.00


JUMLAH 126,093.75
J. 6.6.29 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2"
1.2000 m' Pipa PVC @ 12,500.00   15,000.00
35.0000 % Perlengkapan @ 4,375.00   153,125.00
0.0360 oh pekerja @ 45,000.00
0.0600 oh Tukang Batu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH 168,125.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 85/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.30 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2 1/2"


1.2000 m' Pipa PVC @ 15,625.00   18,750.00
35.0000 % Perlengkapan @ 5,468.75   191,406.25
0.0360 oh pekerja @ 45,000.00
0.0600 oh Tukang Batu @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH 210,156.25
J. 6.6.31 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3"
1.2000 m' Pipa PVC @ 18,750.00   22,500.00
35.0000 % Perlengkapan @ 6,562.50   229,687.50
0.0810 oh pekerja @ 45,000.00
0.1350 oh Tukang Batu @ 55,000.00
0.0135 oh kepala tukang @ 60,000.00
0.0041 oh mandor @ 60,000.00
JUMLAH 252,187.50
J. 6.6.32 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 4"
1.2000 m' Pipa PVC @ 21,250.00   25,500.00

35.0000 % Perlengkapan @ 7,437.50   260,312.50


0.0810 oh pekerja @ 45,000.00
0.1350 oh Tukang Batu @ 55,000.00
0.0135 oh kepala tukang @ 60,000.00
0.0041 oh mandor @ 60,000.00
JUMLAH 285,812.50
J. 6.6.33 MEMASANG 1BH BAK CUCI PIRING STAINLES STEEL
1.0000 bh Bak cuci stainless steel @ 195,000.00   195,000.00
1.0000 set Water drain + Asseories @ 35,000.00   35,000.00
0.0300 oh pekerja @ 45,000.00
0.3000 oh Tukang Batu @ 55,000.00
0.0300 oh kepala tukang @ 60,000.00

0.0015 oh mandor @ 60,000.00


JUMLAH 230,000.00
J. 6.6.34 MEMASANG 1 BH BAK CUCI PIRING TERASO
1.0000 bh bak cuci teraso @ 150,000.00   150,000.00
1.0000 set Water drain + Asseories @ 35,000.00   35,000.00
20.0000 Kg Semen Portland @ 860.00   17,200.00
0.0500 m3 Pasir @ 249,567.03   12,478.35
0.0500 oh Pekerja @ 45,000.00
0.5000 oh Tukang Batu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 214,678.35

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 86/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

J. 6.6.35 MEMASANG 1BH KRAN DIAMETER 3/4" ATAU 1/2"


1.0000 Bh Kran Air @ 20,000.00   20,000.00
0.0250 Bh Seal Tape @ 3,500.00   87.50
0.0100 oh pekerja @ 45,000.00
0.1000 oh Tukang Batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 20,087.50
J. 6.6.36 MEMASANG 1BH FLOOR DRAIN
1.0000 Bh Floor drain @ 17,500.00   17,500.00
0.0100 oh pekerja @ 45,000.00
0.1000 oh Tukang Batu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 17,500.00
K. PEKERJAAN BESI
K. 6.6.1 1 KG PASANG RANGKA ATAP BAJA
1.1000 Kg Besi Profil WF @   -

0.0800 Kg Meni Besi @ 25,000.00   2,000.00


0.0060 oh Tukang Besi @ 55,000.00
0.0600 oh Pekerja @ 45,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0003 oh mandor @ 60,000.00
JUMLAH 2,000.00
K. 6.6.2 1 M2 PASANG PINTU BESI BAJA
1.1000 m2 Pintu Besi Baja @   -
0.0060 oh Tukang Besi Konstruksi @ 55,000.00
0.0600 oh Pekerja @ 45,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0003 oh mandor @ 60,000.00

JUMLAH -
K. 6.6.3 1 M2 PASANG JENDELA BESI
1.0000 m2 Jendela Besi @   -
1.0500 oh Tukang Besi Konstruksi @ 55,000.00
1.0500 oh Pekerja @ 45,000.00
0.1050 oh kepala tukang @ 60,000.00
0.0053 oh mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 87/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

K. 6.6.4 1 M2 PASANG JENDELA BESI TAHAN API


1.0000 m2 Jendela Besi tahan api @   -
1.2000 oh Tukang Besi Konstruksi @ 55,000.00
1.0220 oh Pekerja @ 45,000.00
0.1200 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.5 1 M2 PASANG PINTU GULUNG BESI
1.0000 m2 Pintu Gulung besi @   -
1.2000 oh Tukang Besi Konstruksi @ 55,000.00
1.2000 oh Pekerja @ 45,000.00
0.1200 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.6 1 M2 PASANG PINTU LIPAT
1.1000 m2 Pintu Lipat @   -
0.0060 oh Tukang Besi Konstruksi @ 55,000.00
0.0600 oh Pekerja @ 45,000.00

0.0060 oh kepala tukang @ 60,000.00


0.0003 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.7 1 M2 PASANG PINTU SUNSCREEN ALLUMUNIUM
1.0000 m2 Sunscreen Allumunium @   -
0.8000 oh Tukang Besi Konstruksi @ 55,000.00
0.0800 oh Pekerja @ 45,000.00
0.0800 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.8 1 M2 PASANG ROLLING DOOR
1.0000 m2 Roll Door @   -

1.5000 oh Tukang Besi Konstruksi @ 55,000.00


1.0500 oh Pekerja @ 45,000.00
0.1050 oh kepala tukang @ 60,000.00
0.0052 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.9 1 M2 PASANG PINTU ALLUMUNIUM
1.0000 m2 Pintu Allumunium @   -
1.0500 oh Tukang Besi Konstruksi @ 55,000.00
1.0500 oh Pekerja @ 45,000.00
0.1050 oh kepala tukang @ 60,000.00
0.0052 oh mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 88/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

K. 6.6.10 1 M2 PASANG VENETIONS BLINDS


1.0000 m2 Venetions Blinds @   -
0.3500 oh Tukang kayu @ 55,000.00
0.3500 oh Pekerja @ 45,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.11 1 M2 PASANG VERTIKALS BLINDS
1.0000 m2 Vertikals blinds @   -
0.3500 oh Tukang Kayu @ 55,000.00
0.3500 oh Pekerja @ 45,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0018 oh mandor @ 60,000.00
JUMLAH -
K. 6.6.12 1 M2 PASANG TERALI BESI
11.5000 m2 Besi Strip 2 x 3 @ 18,000.00   207,000.00
1.2000 oh Tukang Besi Konstruksi @ 55,000.00
1.2000 oh Pekerja @ 45,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0006 oh mandor @ 60,000.00
JUMLAH 207,000.00
K. 6.6.13 1 M2 PASANG KAWAT HARMONIKA
1.1000 m2 kawat harmonika @ 37,500.00   41,250.00
0.0200 kg paku biasa 1/2" - 1" @ 11,825.00   236.50
0.0018 m3 papan ky meranti @ 1,187,571.94   2,137.63
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0005 oh mandor @ 60,000.00
JUMLAH 43,624.13
K. 6.6.14 1 M2 PASANG KAWAT NYAMUK
1.1000 m2 kawat nyamuk @ 10,000.00   11,000.00
0.0200 kg paku biasa 1/2" - 1" @ 11,825.00   236.50
0.0018 m3 papan ky meranti @ 1,187,571.94   2,137.63
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0005 oh mandor @ 60,000.00
JUMLAH 13,374.13
K. 6.6.15 1 M2 PASANG KAWAT KASSA
1.1000 m2 kawat kassa @ 10,000.00   11,000.00
0.0200 kg paku biasa 1/2" - 1" @ 11,825.00   236.50
0.0018 m3 kayu bengkirai papan @ 2,137,571.94   3,847.63

0.1000 oh pekerja @ 45,000.00


0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
. , .
JUMLAH 15,084.13

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 89/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

K. 6.6.16 1 M2 PASANG KAWAT BURUNG


1.1000 m2 kawat Burung @ 15,000.00   16,500.00
0.0200 kg paku biasa 1/2" - 1" @ 11,825.00   236.50
0.0018 m3 kayu bengkirai papan @ 2,137,571.94   3,847.63
0.1000 oh pekerja @ 45,000.00
0.1000 oh tukang kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0005 oh mandor @ 60,000.00
JUMLAH 20,584.13
K. 6.6.17 1 M2 PASANG JENDELA NAKO & TRALIS
1.1000 m2 Jendela Nako @ 150,000.00   165,000.00
0.0200 kg paku biasa 1/2" - 1" @ 11,825.00   236.50
0.0250 m3 Besi Strip @ 18,000.00   450.00
0.2000 oh pekerja @ 45,000.00
0.2000 oh tukang kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0010 oh mandor @ 60,000.00
JUMLAH 165,686.50

K. 6.6.18 1 M' PASANG TALANG DATAR, SENG BLJS 28


0.5000 Lbr Seng plat 3' x 6' bljs 28 @ 35,000.00   17,500.00
0.0150 kg paku biasa 1/2" - 1" @ 11,825.00   177.38
0.0096 m3 Kayu ulin, papan @ 1,737,571.94   16,680.69
0.2500 kg Flincote / Meni Besi @ 25,000.00   6,250.00
0.1500 oh pekerja @ 45,000.00
0.4000 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 40,608.07
K. 6.6.19 1 M' PASANG TALANG MIRING, SENG BLJS 28
0.5000 Lbr Seng plat 3' x 6' bljs 28 @ 35,000.00   17,500.00
0.0150 kg paku biasa 1/2" - 1" @ 11,825.00   177.38
0.0190 m3 Kayu ulin, papan @ 1,737,571.94   33,013.87
0.3000 kg Flincote / Meni Besi @ 25,000.00   7,500.00
0.0400 oh pekerja @ 45,000.00
0.4000 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 58,191.24
K. 6.6.20 1 M' PASANG TALANG 1/2 LINGKARAN D-10 CM. SENG BJLS 28
0.3000 lbr Seng plat 3' x 6' bljs 28 @ 35,000.00   10,500.00
0.1000 kg paku biasa 1/2" - 1" @ 11,825.00   1,182.50
0.0190 m3 Kayu ulin, papan @ 1,737,571.94   33,013.87
0.5000 kg besi Strip @ 18,000.00   9,000.00
0.1500 oh pekerja @ 45,000.00
0.2500 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 53,696.37

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 90/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

K. 6.6.21 1 M' PASANG TALANG 1/2 LINGKARAN D-10 CM. SENG BJLS 24
0.5000 m2 Seng plat 3' x 6' bljs 28 @ 35,000.00   17,500.00
0.0150 kg paku biasa 1/2" - 1" @ 11,825.00   177.38
0.0190 m3 Kayu ulin, papan @ 1,737,571.94   33,013.87
0.3000 kg besi Strip @ 18,000.00   5,400.00
0.0400 oh pekerja @ 45,000.00
0.4000 oh tukang kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 56,091.24
L. PEKERJAAN KUNCI DAN KACA
L. 6.6.1 1 BUAH PASANG KUNCI TANAM ANTIK
1.0000 Bh Kunci tanam antik @ 125,000.00   125,000.00
0.0600 oh Pekerja @ 45,000.00
0.6000 oh Tukang Kayu @ 55,000.00
0.0600 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 125,000.00

L. 6.6.2 1 BUAH PASANG KUNCI TANAM BIASA


1.0000 Bh Kunci tanam biasa @ 150,000.00   150,000.00
0.0100 oh Pekerja @ 45,000.00
0.0500 oh Tukang Kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0050 oh mandor @ 60,000.00
JUMLAH 150,000.00
L. 6.6.3 1 BUAH PASANG KUNCI KAMAR MANDI
1.0000 Bh Kunci tanam kamar mandi @ 65,000.00   65,000.00
0.0050 oh Pekerja @ 45,000.00
0.5000 oh Tukang Kayu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00

0.0025 oh mandor @ 60,000.00


JUMLAH 65,000.00
L. 6.6.4 1 BUAH PASANG KUNCI SILINDER
1.0000 Bh Kunci Silinder @   -
0.0050 oh Pekerja @ 45,000.00
0.5000 oh Tukang Kayu @ 55,000.00
0.0050 oh kepala tukang @ 60,000.00
0.0003 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.5 1 BUAH PASANG ENGSEL PINTU
1.0000 Bh Engsel Pintu @ 25,000.00   25,000.00
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 25,000.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 91/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

L. 6.6.6 1 BUAH PASANG ENGSEL JENDELA KUPU - KUPU


1.0000 Bh Engsel Jendela @ 20,000.00   20,000.00
0.0100 oh Pekerja @ 45,000.00
0.1000 oh Tukang Kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0005 oh mandor @ 60,000.00
JUMLAH 20,000.00
L. 6.6.7 1 BUAH PASANG ENGSEL ANGIN
1.0000 Bh Engsel angin @   -
0.0200 oh Pekerja @ 45,000.00
0.2000 oh Tukang Kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0100 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.8 1 BUAH PASANG SPRING KNIP/GRNDEL JENDELA
1.0000 Bh Spring Knip @   -
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00

0.0150 oh kepala tukang @ 60,000.00


0.0008 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.9 1 BUAH PASANG KAIT ANGIN
1.0000 Bh Kait angin @ 8,000.00   8,000.00
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 8,000.00
L. 6.6.10 1 BUAH PASANG DOOR CLOSER
1.0000 Bh Door Closer @   -

0.0500 oh Pekerja @ 45,000.00


0.5000 oh Tukang Kayu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.11 1 BUAH PASANG KUNCI SELOT
1.0000 Bh Kunci selot @   -
0.0200 oh Pekerja @ 45,000.00
0.2000 oh Tukang Kayu @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0010 oh mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 92/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

L. 6.6.12 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER


1.0000 Bh Door Holder @   -
0.0500 oh Pekerja @ 45,000.00
0.5000 oh Tukang Kayu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.13 1 BUAH PASANG DOOR STOP
1.0000 Bh Door Stop @   -
0.0100 oh Pekerja @ 45,000.00
0.1000 oh Tukang Kayu @ 55,000.00
0.0100 oh kepala tukang @ 60,000.00
0.0005 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.14 1 BUAH PASANG REL PINTU DORONG
1.0000 Bh Rel pintu dorong @   -
0.0600 oh Pekerja @ 45,000.00
0.6000 oh Tukang Kayu @ 55,000.00

0.0600 oh kepala tukang @ 60,000.00


0.0030 oh mandor @ 60,000.00
JUMLAH -
L. 6.6.15 1 BUAH PASANG KUNCI LEMARI
1.0000 Bh Kunci Lemari @ 25,000.00   25,000.00
0.0250 oh Pekerja @ 45,000.00
0.2500 oh Tukang Kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 25,000.00
L. 6.6.16 1 M2 PASANG KACA, TEBAL 3 MM
1.1000 m2 kaca @ 48,000.00   52,800.00

0.0150 oh Pekerja @ 45,000.00


0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 52,800.00
L. 6.6.17 1 M2 PASANG KACA, TEBAL 5 MM
1.1000 m2 Kaca @ 80,000.00   88,000.00
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 88,000.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 93/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

L. 6.6.18 1 M2 PASANG KACA, TEBAL 8 MM   16,000.00


1.1000 m2 Kaca @ 128,000.00   140,800.00
0.0165 oh Pekerja @ 45,000.00
0.1650 oh Tukang Kayu @ 55,000.00
0.0165 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 140,800.00
L. 6.6.19 1 M2 PASANG KACA GELAP, TEBAL 5 MM
1.1000 m2 kaca gelap @ 95,000.00   104,500.00
0.0500 kg Sealent @   -
0.0250 oh Pekerja @ 45,000.00
0.2500 oh Tukang Kayu @ 55,000.00
0.0250 oh kepala tukang @ 60,000.00
0.0013 oh mandor @ 60,000.00
JUMLAH 104,500.00
L. 6.6.20 1 M2 PASANG KACA CERMIN, TEBAL 5 MM
1.1000 m2 Kaca cermin @ 95,000.00   104,500.00
0.0150 oh Pekerja @ 45,000.00

0.1500 oh Tukang Kayu @ 55,000.00


0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 104,500.00
L. 6.6.21 1 M2 PASANG KACA CERMIN, TEBAL 6 MM
1.1000 m2 Kaca cermin @ 114,000.00   125,400.00
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 125,400.00
L. 6.6.22 1 M2 PASANG KACA CERMIN, TEBAL 8 MM

1.0000 m2 Kaca cermin @ 152,000.00   152,000.00


0.0165 oh Pekerja @ 45,000.00
0.1650 oh Tukang Kayu @ 55,000.00
0.0165 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 152,000.00
L. 6.6.23 1 M2 PASANG KACA " WIREGLASS", TEBAL 5 MM
1.1000 m2 Kaca Wireglass @   -
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 94/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

L. 6.6.24 1 M2 PASANG KACA PATRI, TEBAL 5 MM


1.1000 m2 Kaca Patri @ 250,000.00   275,000.00
0.0150 oh Pekerja @ 45,000.00
0.1500 oh Tukang Kayu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0008 oh mandor @ 60,000.00
JUMLAH 275,000.00

M. PEKERJAAN PENUTUP LANTAI & D INDING


M.6.6.1 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 40 X 40 CM
0.04 6.6300 Bh Ubin abu-abu 40 x 40 cm @ 7,466.06   49,500.00
9.8000 kg Semen portland @ 860.00   8,428.00
0.0215 m3 Pasir pasang @ 249,567.03   5,365.69
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 63,293.69

M.6.6.2 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 30 X 30 CM


0.09 11.8700 Bh Ubin abu-abu 30 x 30 cm @ 3,454.09   41,000.00
10.0000 kg semen portland @ 860.00   8,600.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
0.2600 oh pekerja @ 45,000.00
0.1250 oh tukang batu @ 55,000.00
0.0125 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 54,965.69

M.6.6.3 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 20 X 20 CM

0.09 26.5000 Bh Ubin abu-abu 20 x 20 cm @ 1,660.38   44,000.00


10.4000 kg semen portland @ 860.00   8,944.00
0.0135 m3 pasir pasang @ 249,567.03   3,369.15
0.2700 oh pekerja @ 45,000.00
0.1300 oh tukang batu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0135 oh mandor @ 60,000.00
JUMLAH 56,313.15

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 95/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.4 1 M2 PASANG LANTAI UBIN WARNA UKURAN 40 X 40 CM


0.09 6.6300 Bh Ubin Warna 40 x 40 cm @ 7,466.06   49,500.00
8.1600 kg semen portland @ 860.00   7,017.60
0.0230 m3 pasir pasang @ 249,567.03   5,740.04
0.9000 kg Semen warna @ 1,600.00   1,440.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 63,697.64
M.6.6.5 1 M2 PASANG LANTAI UBIN WARNA UKURAN 30 x 30 CM
0.09 11.8700 Bh Ubin Warna 30 x 30 cm @ 3,117.10   37,000.00
8.3600 kg semen portland @ 860.00   7,189.60
0.0230 m3 pasir pasang @ 249,567.03   5,740.04
0.9000 kg Semen warna @ 1,600.00   1,440.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00

0.0125 oh mandor @ 60,000.00


JUMLAH 51,369.64
M.6.6.6 1 M2 PASANG LANTAI UBIN WARNA UKURAN 20 x 20 CM
0.09 26.5000 Bh Ubin Warna 20 x 20 cm @ 1,660.38   44,000.00
8.7600 kg semen portland @ 860.00   7,533.60
0.0230 m3 pasir pasang @ 249,567.03   5,740.04
0.9000 kg Semen warna @ 1,600.00   1,440.00
0.2700 oh pekerja @ 45,000.00
0.1300 oh tukang batu @ 55,000.00
0.0130 oh kepala tukang @ 60,000.00
0.0135 oh mandor @ 60,000.00
JUMLAH 58,713.64

M.6.6.7 1 M2 PASANG LANTAI UBIN TERASO UKURAN 40 x 40 CM


0.09 6.2500 Bh Ubin teraso 40 x 40 cm @ 10,000.00   62,500.00
8.8000 kg semen portland @ 860.00   7,568.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
0.9000 kg Semen warna @ 1,600.00   1,440.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 76,873.69

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 96/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.8 1 M2 PASANG LANTAI UBIN TERASO UKURAN 30 x 30 CM


0.09 11.8700 Bh Ubin teraso 30 x 30 cm @ 6,000.00   71,220.00
10.0000 kg semen portland @ 860.00   8,600.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
1.5400 kg Semen warna @ 1,600.00   2,464.00
0.2600 oh pekerja @ 45,000.00
0.1250 oh tukang batu @ 55,000.00
0.0125 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 87,649.69
M.6.6.9 1 M2 PASANG LANTAI UBIN GRANITO UKURAN 40 X 40 CM
0.09 6.9300 Bh Ubin granito 40 x 40 cm @ 15,000.00   103,950.00
9.8000 kg semen portland @ 860.00   8,428.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
1.3000 kg Semen warna @ 1,600.00   2,080.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00

0.0125 oh mandor @ 60,000.00


JUMLAH 119,823.69
M.6.6.10 1 M2 PASANG LANTAI UBIN GRANITO UKURAN 30 X 30 CM
0.09 11.8700 Bh Ubin granito 30 x 30 cm @ 9,000.00   106,830.00
10.0000 kg semen portland @ 860.00   8,600.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.2600 oh pekerja @ 45,000.00
0.1250 oh tukang batu @ 55,000.00
0.0125 oh kepala tukang @ 60,000.00
0.0130 oh mandor @ 60,000.00
JUMLAH 123,195.69

M.6.6.11 1 M2 PASANG LANTAI UBIN TERALUX KERANG UKURAN 40 X 40 CM


0.09 6.2500 Bh Ubin teralux terang 40 x 40 cm @   -
8.8000 kg semen portland @ 860.00   7,568.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
1.3000 kg Semen warna @ 1,600.00   2,080.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 15,013.69

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 97/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.12 1 M2 PASANG LANTAI UBIN TERALUX TERANG UKURAN 30 X 30 CM


0.09 11.8070 Bh Ubin teralux terang 30 x 30 cm @   -
10.0000 kg semen portland @ 860.00   8,600.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
1.1250 kg Semen warna @ 1,600.00   1,800.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0125 oh mandor @ 60,000.00
JUMLAH 15,765.69
M.6.6.13 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 60 X 60 CM
0.09 5.6000 Bh Ubin teralux marmer 60 x 60 cm @   -
8.1900 kg semen portland @ 860.00   7,043.40
0.0450 m3 pasir pasang @ 249,567.03   11,230.52
1.0000 kg Semen warna @ 1,600.00   1,600.00
0.2500 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00

0.0125 oh mandor @ 60,000.00


JUMLAH 19,873.92
M.6.6.14 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 40 X 40 CM
0.09 6.2500 Bh Ubin teralux marmer 40 x 40 cm @   -
8.8000 kg semen portland @ 860.00   7,568.00
0.0215 m3 pasir pasang @ 249,567.03   5,365.69
1.3000 kg Semen warna @ 1,600.00   2,080.00
0.6720 oh pekerja @ 45,000.00
0.2240 oh tukang batu @ 55,000.00
0.0220 oh kepala tukang @ 60,000.00
0.0340 oh mandor @ 60,000.00
JUMLAH 15,013.69

M.6.6.15 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 30 X 30 CM


0.09 11.8700 Bh Ubin teralux marmer 30 x 30 cm @   -
10.0000 kg semen portland @ 860.00   8,600.00
0.0250 m3 pasir pasang @ 249,567.03   6,239.18
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.7000 oh pekerja @ 45,000.00
0.3400 oh tukang batu @ 55,000.00
0.0340 oh kepala tukang @ 60,000.00
0.0350 oh mandor @ 60,000.00
JUMLAH 17,239.18

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 98/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.16 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 15 X 20 CM


0.09 5.3000 Bh Plint Ubin 15 x 20 cm @ 1,660.38   8,800.00
1.5600 kg semen portland @ 860.00   1,341.60
0.0040 m3 pasir pasang @ 249,567.03   998.27
0.0600 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 11,139.87
M.6.6.17 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 10 X 30 CM
0.09 3.5300 Bh Plint Ubin 10 x 30 cm @ 1,151.36   4,064.31
1.5600 kg semen portland @ 860.00   1,341.60
0.0030 m3 pasir pasang @ 249,567.03   748.70
0.0600 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 6,154.61

M.6.6.18 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 10 X 40 CM


0.09 2.6500 Bh Plint Ubin 10 x 40 cm @ 1,866.52   4,946.27
1.5600 kg semen portland @ 860.00   1,341.60
0.0030 m3 pasir pasang @ 249,567.03   748.70
0.0600 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 7,036.57
M.6.6.19 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 20 CM
0.09 5.3000 Bh Plint Ubin Pc Warna 10 x 20 cm @ 830.19   4,400.00
1.2000 kg semen portland @ 860.00   1,032.00

0.0030 m3 pasir pasang @ 249,567.03   748.70


0.1900 kg Semen warna @ 1,600.00   304.00
0.0600 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 6,484.70
M.6.6.20 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 30 CM
0.09 3.3300 Bh Plint Ubin Pc Warna 10 x 30 cm @ 1,039.03   3,459.98
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.0600 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 5,837.60

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 99/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.21 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 40 CM


0.09 2.6500 Bh Plint Ubin Pc Warna 10 x 40 cm @ 1,866.52   4,946.27
1.2000 kg semen portland @ 860.00   1,032.00
0.0030 m3 pasir pasang @ 249,567.03   748.70
0.1000 kg Semen warna @ 1,600.00   160.00
0.0800 oh pekerja @ 45,000.00
0.0400 oh tukang batu @ 55,000.00
0.0040 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 6,886.97
M.6.6.22 1 M' PASANG PLINT UBIN TERASO UKURAN 10 X 30 CM
0.09 3.5300 Bh Plint Ubin Teraso 10 x 30 cm @ 2,000.00   7,060.00
1.5600 kg semen portland @ 860.00   1,341.60
0.0030 m3 pasir pasang @ 249,567.03   748.70
0.1900 kg Semen warna @ 1,600.00   304.00
0.0800 oh pekerja @ 45,000.00
0.0400 oh tukang batu @ 55,000.00
0.0040 oh kepala tukang @ 60,000.00

0.0040 oh mandor @ 60,000.00


JUMLAH 9,454.30
M.6.6.23 1 M' PASANG PLINT UBIN TERASO UKURAN 10 X 40 CM
0.09 2.6500 Bh Plint Ubin Teraso 10 x 40 cm @ 2,500.00   6,625.00
1.2000 kg semen portland @ 860.00   1,032.00
0.0030 m3 pasir pasang @ 249,567.03   748.70
1.0000 kg Semen warna @ 1,600.00   1,600.00
0.0800 oh pekerja @ 45,000.00
0.0400 oh tukang batu @ 55,000.00
0.0040 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
JUMLAH 10,005.70

M.6.6.24 1 M' PASANG PLINT UBIN GRANITO UKURAN 10 X 40 CM


0.09 2.6500 Bh Plint Ubin Granito 10 x 40 cm @ 3,750.00   9,937.50
1.2000 kg semen portland @ 860.00   1,032.00
0.0030 m3 pasir pasang @ 249,567.03   748.70
1.0000 kg Semen warna @ 1,600.00   1,600.00
0.0600 oh pekerja @ 45,000.00
0.0300 oh tukang batu @ 55,000.00
0.0030 oh kepala tukang @ 60,000.00
0.0030 oh mandor @ 60,000.00
JUMLAH 13,318.20

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 100/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.25 1 M' PASANG PLINT UBIN GRANITO UKURAN 10 X 30 CM


0.09 3.3300 Bh Plint Ubin Granito 10 x 30 cm @ 3,000.00   9,990.00
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
JUMLAH 12,367.61
M.6.6.26 1M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 X 40 CM
0.09 2.5000 Bh plint Ubin teralux kerang 10 x 40 cm @ -   -
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00

0.0045 oh mandor @ 60,000.00


JUMLAH 2,377.61
M.6.6.27 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 X 30 CM
0.09 3.3300 Bh plint Ubin teralux kerang 10 x 30 cm @ -   -
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
JUMLAH 2,377.61

M.6.6.28 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 60 CM


0.09 1.7000 Bh Plint Ubin teralux marmer 10 x 60 cm @ -   -
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
JUMLAH 2,377.61

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 101/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.29 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 40 CM


0.09 2.5000 Bh Plint Ubin teralux marmer 10 x 40 cm @ -   -
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
JUMLAH 2,377.61
M.6.6.30 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 30 CM
0.09 3.3000 Bh Plint Ubin teralux marmer 10 x 30 cm @ -   -
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m3 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00

0.0045 oh mandor @ 60,000.00


JUMLAH 2,377.61
M.6.6.31 1 M2 PASANG TERASO COR DITEMPAT
0.09 0.0036 m3 Bahan Teraso Cor @   -
0.9000 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
JUMLAH -
M.6.6.32 1 M2 PASANG TERALUC COR DITEMPAT, TEBAL 3 CM
0.09 0.0036 m3 Bahan Teraluc cor @   -
0.9000 oh pekerja @ 45,000.00

0.0900 oh tukang batu @ 55,000.00


0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
JUMLAH -
M.6.6.33 1 M2 PASANG UBIN TAHAN ASAM
0.09 1.0500 m2 Ubin tahan asam @   -
14.1400 kg semen tahan asam @   -
0.0400 m2 pasir pasang @ 249,567.03   9,982.68
0.2700 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0135 oh mandor @ 60,000.00
JUMLAH 9,982.68

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 102/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.34 1 M2 PASANG LANTAI KERAMIK ARTISTIK 10 X 20 CM


0.09 50.0000 bh ubin keramik artistik 10 x 20 cm @ 1,200.00   60,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 82,668.62
M.6.6.35 1 M2 PASANG LANTAI KERAMIK ARTISTIK 10 X 10 CM
0.09 100.0000 bh ubin keramik artistik 10 x 10 cm @ 750.00   75,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
2.0000 kg Semen warna @ 1,600.00   3,200.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00

0.0300 oh mandor @ 60,000.00


0.09 JUMLAH 98,468.62
M.6.6.36 1 M2 PASANG LANTAI KERAMIK ARTISTIK 5 X 20 CM
0.09 100.0000 m2 ubin keramik artistik 5 x 20 cm @ 600.00   60,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 82,668.62

M.6.6.37 1 M2 PASANG PLINT KERAMIK ARTISTIK 10 X 20 CM


0.09 5.0000 m2 Plint keramik artistik 10 x 20 cm @ 1,200.00   6,000.00
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m2 pasir pasang @ 249,567.03   798.61
0.1000 kg Semen warna @ 1,600.00   160.00
0.0900 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
0.09 JUMLAH 8,377.61

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 103/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.38 1 M2 PASANG PLINT KERAMIK ARTISTIK 10 X 10 CM


0.09 5.0000 m2 Plint keramik artistik 10 x 10 cm @ 750.00   3,750.00
1.6500 kg semen portland @ 860.00   1,419.00
0.0032 m2 pasir pasang @ 249,567.03   798.61
0.1200 kg Semen warna @ 1,600.00   192.00
0.0900 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00
0.09 JUMLAH 6,159.61
M.6.6.39 1 M2 PASANG PLINT KERAMIK ARTISTIK 5 X 20 CM
0.09 5.0000 m2 Plint keramik artistik 5 x 20 cm @ 600.00   3,000.00
0.8500 kg semen portland @ 860.00   731.00
0.0022 m2 pasir pasang @ 249,567.03   549.05
0.0800 kg Semen warna @ 1,600.00   128.00
0.0900 oh pekerja @ 45,000.00
0.0900 oh tukang batu @ 55,000.00
0.0090 oh kepala tukang @ 60,000.00
0.0045 oh mandor @ 60,000.00

0.09 JUMLAH 4,408.05


M.6.6.40 1 M' INTERNAL COVE ARTISTIK ( 5 X 5 X 20 ) CM
0.09 10.0000 m2 Interval cove ( 5 x 5 x 20 ) cm @   -
1.4150 kg semen portland @ 860.00   1,216.90
0.0390 m2 pasir pasang @ 249,567.03   9,733.11
1.2000 kg Semen warna @ 1,600.00   1,920.00
0.7500 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0375 oh mandor @ 60,000.00
0.09 JUMLAH 12,870.01
M.6.6.41 1 M' PASANG PLINT VINYL TANPA ADUKAN

0.09 3.5000 Bh Lt vinyl karet 30 x 30 kwl @   -


0.0800 kg Lem vinyl @   -
0.0800 oh pekerja @ 45,000.00
0.0800 oh tukang batu @ 55,000.00
0.0080 oh kepala tukang @ 60,000.00
0.0040 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.42 1 M2 PASANG LANTAI KERAMIK 10 X 20 CM
50.0000 Bh Ubin keramik artistik 10 x 20 cm @ 700.00   35,000.00
11.3000 kg semen portland @ 860.00   9,718.00
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 57,599.82

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 104/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.43 1 M2 PASANG LANTAI KERAMIK 15 X 15 CM


0.09 44.0000 Bh Ubin keramik 15 x 15 cm @ 850.00   37,400.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 60,068.62
M.6.6.44 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM
0.09 25.0000 Bh Ubin keramik 20 x 20 cm @ 1,760.00   44,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00

0.0300 oh mandor @ 60,000.00


0.09 JUMLAH 66,668.62
M.6.6.45 1 M2 PASANG LANTAI KERAMIK 25 X 25 CM
0.09 16.0000 Bh Ubin keramik 25 x 25 cm @ 2,750.00   44,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 66,668.62

M.6.6.46 1 M2 PASANG LANTAI KERAMIK 15 X 20 CM


0.09 35.0000 Bh Ubin keramik 15 x 20 cm @ 1,257.14   44,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 66,668.62

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 105/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.47 1 M2 PASANG LANTAI KERAMIK 30 x 30 CM


0.09 11.1111 Bh Ubin keramik 30 x 30 cm @ 3,330.00   37,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 59,668.62
M.6.6.48 1 M2 PASANG LANTAI KERAMIK 30 x 30 CM ANTI SLIP
0.09 11.1111 Bh Ubin keramik 30 X 30 cm Anti slip @ 3,690.00   41,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00

0.0300 oh mandor @ 60,000.00


0.09 JUMLAH 63,668.62
M.6.6.49 1 M2 PASANG LANTAI KERAMIK 10 x 33 CM
0.09 33.0000 Bh Ubin keramik 10 x 33 cm @ 1,121.21   37,000.00
11.3800 kg semen portland @ 860.00   9,786.80
0.0420 m2 pasir pasang @ 249,567.03   10,481.82
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 59,668.62

M.6.6.50 1 M2 PASANG LANTAI MOSAIK 30 X 30 CM, EX. LOKAL


0.09 12.0000 Bh Mosaik 30 x 30 cm @   -
14.1500 kg semen portland @ 860.00   12,169.00
0.0390 m2 pasir pasang @ 249,567.03   9,733.11
2.0000 kg Semen warna @ 1,600.00   3,200.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 25,102.11

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 106/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.51 1 M2 PASANG LANTAI MARMER


0.09 1.0520 Bh Marmer @ -   -
14.1500 kg semen portland @ 860.00   12,169.00
0.0390 m2 pasir pasang @ 249,567.03   9,733.11
2.0000 kg Semen warna @ 1,600.00   3,200.00
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 25,102.11
M.6.6.52 1 M2 PASANG LANTAI KARPET 100 % WOOL
0.09 1.0500 Bh Feltex carpet 100% wool T-21 @   -
0.3500 kg Lem Vinyl @ -   -
0.1700 oh pekerja @ 45,000.00
0.1700 oh tukang batu @ 55,000.00
0.0170 oh kepala tukang @ 60,000.00
0.0085 oh mandor @ 60,000.00
0.09 JUMLAH -

M.6.6.53 1 M2 PASANG LANTAI KARPET 80 % WOOL, 20% NYLON


0.09 1.0500 Bh Carpet 80%, 20% nylon @   -
0.3500 kg Lem Vinyl @ -   -
0.1700 oh pekerja @ 45,000.00
0.1700 oh tukang batu @ 55,000.00
0.0170 oh kepala tukang @ 60,000.00
0.0085 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.54 1 M2 PASANG UNDRLYER, TEBAL 6 MM
0.09 1.0500 Bh Underlyer tebal 6 mm / rubber corrugated @   -
0.1200 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00

0.0120 oh kepala tukang @ 60,000.00


0.0060 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.55 1 M2 PASANG LANTAI KARPET
0.09 1.0500 Bh Carpet @   -
0.3500 kg Lem Vinyl @ -   -
0.1700 oh pekerja @ 45,000.00
0.1700 oh tukang batu @ 55,000.00
0.0170 oh kepala tukang @ 60,000.00
0.0085 oh mandor @ 60,000.00
0.09 JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 107/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.56 1 M2 PASANG LANTAI PARQUET JATI


0.09 1.0500 Bh Parquet jati @   -
0.3500 kg Lem Vinyl @ -   -
0.1700 oh pekerja @ 45,000.00
0.1700 oh tukang batu @ 55,000.00
0.0170 oh kepala tukang @ 60,000.00
0.0085 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.57 1 M2 PASANG GYMFLOOR
0.09 1.0500 Bh Gymfloor @   -
0.6000 kg Lem Vinyl @ -   -
0.6500 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0325 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.58 1 M2 PASANG DINDING PORSELIN 11 X 11 CM, PUTIH
0.09 83.0000 Bh porselin 11 x 11 cm @ 1,250.00   103,750.00

9.3000 kg Semen abu-abu @ 860.00   7,998.00


0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 Kg Semen warna @ 1,600.00   2,400.00
0.6200 oh pekerja @ 45,000.00
0.5000 oh tukang batu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 111,748.00
M.6.6.59 1 M2 PASANG DINDING PORSELIN 11 X 11 CM, WARNA
0.09 83.0000 Bh porselin 11 x 11 cm warna @ 1,750.00   145,250.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21

1.5000 kg Semen warna @ 1,600.00   2,400.00


0.6200 oh pekerja @ 45,000.00
0.5000 oh tukang batu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 160,140.21
M.6.6.60 1 M2 PASANG DINDING PORSELIN 15 X 15 CM, PUTIH
0.09 45.0000 Bh porselin 15 x 15 cm putih @ 2,300.00   103,500.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 118,390.21

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 108/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.61 1 M2 PASANG DINDING PORSELIN 15 X 15 CM, WARNA


0.09 45.0000 Bh porselin 15 x 15 cm putih @ 2,800.00   126,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 140,890.21
M.6.6.62 1 M2 PASANG DINDING PORSELIN 10 X 20 CM, WARNA
0.09 50.0000 Bh porselin 10 x 20 cm, warna @ 2,500.00   125,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00

0.0300 oh mandor @ 60,000.00


0.09 JUMLAH 139,890.21
M.6.6.63 1 M2 PASANG DINDING PORSELIN 20 X 20 CM, WARNA
0.09 25.0000 Bh porselin 20 x 20 cm, warna @ 3,000.00   75,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.1800 m3 pasir pasang @ 249,567.03   44,922.07
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 130,320.07

M.6.6.64 1 M2 PASANG DINDING KERAMIK ARTISTIK 10 X 20 CM


0.09 100.0000 Bh Keramik artistik 10 x 20 cm @ 1,000.00   100,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 114,890.21

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 109/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.65 1 M2 PASANG DINDING KERAMIK ARTISTIK 5 X 20 CM


0.09 100.0000 Bh Keramik artistik 5 x 20 cm @ 500.00   50,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 64,890.21
M.6.6.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM
0.09 50.0000 Bh Keramik 10 x 20 cm @ 700.00   35,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00

0.0300 oh mandor @ 60,000.00


0.09 JUMLAH 49,890.21
M.6.6.67 1 M2 PASANG DINDING KERAMIK 15 x 15 CM
0.09 45.0000 Bh Keramik 15 x 15 cm @ 850.00   38,250.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 53,140.21

M.6.6.68 1 M2 PASANG DINDING KERAMIK 20 x 20 CM


0.09 25.0000 Bh Keramik 20 x 20 cm @ 1,760.00   44,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.4500 oh tukang batu @ 55,000.00
0.0450 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 58,890.21

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 110/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.69 1 M2 PASANG DINDING KERAMIK 10 x 20 CM


0.09 50.0000 Bh Keramik 10 x 20 cm @ 700.00   35,000.00
9.3000 Kg Semen abu-abu @ 860.00   7,998.00
0.0180 m3 pasir pasang @ 249,567.03   4,492.21
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.6000 oh pekerja @ 45,000.00
0.1250 oh tukang batu @ 55,000.00
0.0125 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 49,890.21
M.6.6.70 1 M2 PASANG DINDING MARMER
0.09 1.0200 m2 marmer @ -   -
2.0000 Kg Pacu Pancing 60 x 230 @ 25,000.00   50,000.00
12.4400 Kg Semen abu-abu @ 860.00   10,698.40
0.0250 m3 pasir pasang @ 249,567.03   6,239.18
1.5000 kg Semen warna @ 1,600.00   2,400.00
0.7200 oh pekerja @ 45,000.00
0.6500 oh tukang batu @ 55,000.00
0.0650 oh kepala tukang @ 60,000.00

0.0350 oh mandor @ 60,000.00


0.09 JUMLAH 69,337.58
M.6.6.71 1 M2 PASANG DINDING BATA PELAPIS 7 X 3 X 24 CM
0.09 60.0000 Bh Bata Pelapis dinding @ 550.00   33,000.00
12.4400 Kg Semen abu-abu @ 860.00   10,698.40
0.0250 m3 pasir pasang @ 249,567.03   6,239.18
0.6500 oh pekerja @ 45,000.00
0.5000 oh tukang batu @ 55,000.00
0.0500 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 49,937.58
M.6.6.72 1 M2 PASANG DINDING BATA KLINKER 5 X 5 X 24 CM

0.09 80.0000 Bh Bata Pelapis klinker @ 550.00   44,000.00


12.4400 Kg Semen abu-abu @ 860.00   10,698.40
0.0250 m3 pasir pasang @ 249,567.03   6,239.18
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0350 oh mandor @ 60,000.00
0.09 JUMLAH 60,937.58
M.6.6.73 1 M2 PASANG DINDING BATU PAROS
0.09 1.0500 m2 Batu paros @   -
11.7500 Kg Semen abu-abu @ 860.00   10,105.00
0.0350 m3 pasir pasang @ 249,567.03   8,734.85
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 18,839.85

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 111/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.74 1 M2 PASANG DINDING BATU TEMPEL HITAM


0.09 1.0500 m2 Batu tempel hitam @   -
11.7500 Kg Semen abu-abu @ 860.00   10,105.00
0.0350 m3 pasir pasang @ 249,567.03   8,734.85
0.6200 oh pekerja @ 45,000.00
0.3500 oh tukang batu @ 55,000.00
0.0350 oh kepala tukang @ 60,000.00
0.0300 oh mandor @ 60,000.00
0.09 JUMLAH 18,839.85
M.6.6.75 1 M2 PASANG LANTAI VINYL KARET 30 X 30 CM KL I
0.09 11.0500 m2 Vinyl karet 30 x 30 cm KL I @   -
0.3500 Kg Lem Vinyl @ -   -
0.1500 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0075 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.76 1 M2 PASANG LANTAI VINYL KARET 30 X 30 CM KL II

0.09 11.0500 m2 Vinyl karet 30 x 30 cm KL II @   -


0.3500 Kg Lem Vinyl @ -   -
0.1500 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0075 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.77 1 M2 PASANG LANTAI VINYL ASBES 30 X 30 CM
0.09 11.0500 m2 Vinyl asbes 30 x 30 cm @   -
0.3500 Kg Lem Vinyl @ -   -
0.1500 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00

0.0150 oh kepala tukang @ 60,000.00


0.0075 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.78 1 M2 PASANG LANTAI VINYL MOTIF KEMBANG 30 X 30 CM
0.09 11.0500 m2 Vinyl motif kembang 30 x 30 cm @   -
0.3500 Kg Lem Vinyl @ -   -
0.1500 oh pekerja @ 45,000.00
0.1500 oh tukang batu @ 55,000.00
0.0150 oh kepala tukang @ 60,000.00
0.0075 oh mandor @ 60,000.00
0.09 JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 112/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

M.6.6.79 1 M2 PASANG WALL COVERING LEBAR 50 CM


0.09 1.1000 m2 Vinyl Wall covering, lebar 50 cm @   -
0.2500 Kg Lem @ -   -
0.7500 oh pekerja @ 45,000.00
0.1700 oh tukang batu @ 55,000.00
0.0170 oh kepala tukang @ 60,000.00
0.0085 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.80 1 M2 FLOOR HARDENER FERROVAX
0.09 3.0000 Kg Floor hardener ferrovax @   -
0.1200 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.81 1 M2 FLOOR HARDENER MASTERCRON
0.09 5.0000 Kg Mastercron "S" @   -
0.1200 oh pekerja @ 45,000.00

0.1200 oh tukang batu @ 55,000.00


0.0120 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
0.09 JUMLAH -
M.6.6.82 1 M2 PLINT KAYU 2 X 10 CM
0.09 0.0024 m3 kayu Jati papan @ 7,000,000.00   16,800.00
0.0500 Kg Paku skrup 3,5 " @ 14,300.00
0.1200 oh pekerja @ 45,000.00
0.1200 oh tukang batu @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0060 oh mandor @ 60,000.00
0.09 JUMLAH 16,800.00

N. PEKERJAAN CAT - CATAN


N. 6.6.1 1 M2 MENGIKIS/MENGEROK PERMUKAAN CAT TEMBOK LAMA
0.0500 kg Soda Api @   -
0.1500 oh pekerja @ 45,000.00
0.0750 oh tukang cat @ 55,000.00
0.0075 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH -
N. 6.6.2 1 M2 MENCUCI BIDANG PERMUKAAN TEMBOK YANG PERNAH DICAT
0.0500 kg Sabun @ 10,500.00   525.00
0.1500 oh pekerja @ 45,000.00
0.0750 oh tukang cat @ 55,000.00
0.0075 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 525.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 113/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

N. 6.6.3 1 M2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL
0.0500 kg Sabun @ 10,500.00   525.00
0.1500 oh pekerja @ 45,000.00
0.0750 oh tukang cat @ 55,000.00
0.0075 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 525.00
N. 6.6.4 1 M2 MENYABUN PERMUKAAN TEMBOK LAMA
0.0500 kg Sabun @ 10,500.00   525.00
0.1500 oh pekerja @ 45,000.00
0.0750 oh tukang cat @ 55,000.00
0.0075 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 525.00
N. 6.6.5 1 M2 MENGEROK KARAT ATAU CAT LAMA PERMUKAAN BAJA DENGAN PANCAR
PASIR ( SANBLASTING ) DENGAN TINGKAT KEBERSIHAN Sa 2 1/2
40.0000 kg Pasir silika @   -
10.0000 Ltr BBM, solar @ 6,321.00

1.0000 Hr Kompressor, blasting pot @ 425,197.11


Selang dan Nozzle
1.6000 oh pekerja @ 45,000.00
1.6000 oh tukang cat @ 55,000.00
0.8000 oh kepala tukang @ 60,000.00
0.5000 oh mandor @ 60,000.00
JUMLAH -
N. 6.6.6 1 M2 MENDEMPUL DAN MENGGOSOK KAYU
0.0800 kg Dempul jadi @ 12,500.00   1,000.00
0.0200 kg Minyak cat @ 12,500.00   250.00
0.0100 kg Batu apung @ 15,125.00   151.25
0.0400 oh pekerja @ 45,000.00

0.0400 oh tukang cat @ 55,000.00


0.0040 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 1,401.25
N. 6.6.7 1 M2 PENGECATAN BIDANG KAYU LAMA
0.1500 kg plamir @ 22,500.00   3,375.00
0.1700 kg cat dasar @ 22,500.00   3,825.00
0.1700 kg cat penutup/kilap @ 35,000.00   5,950.00
0.0700 oh pekerja @ 45,000.00
0.0750 oh tukang cat @ 55,000.00
0.0075 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 13,150.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 114/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

N. 6.6.8 1 M2 PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR ), 1 LAPIS CAT DASAR,
2 LAPIS CAT PENUTUP
0.2000 kg cat meni @ 13,000.00   2,600.00
0.1200 kg Plamir @ 22,500.00   2,700.00
0.1700 kg cat dasar @ 22,500.00   3,825.00
0.2600 kg cat penutup 2 kali @ 35,000.00   9,100.00
0.0700 oh pekerja @ 45,000.00
0.0090 oh tukang cat @ 55,000.00
0.0060 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 18,225.00
N. 6.6.9 1 M2 PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR )
1 LAPIS CAT DASAR, 3 LAPIS CAT PENUTUP
0.2000 kg cat meni @ 13,000.00   2,600.00
0.1500 kg plamir @ 22,500.00   3,375.00
0.1700 kg cat dasar @ 22,500.00   3,825.00
0.3500 oh cat penutup 3 kali @ 35,000.00   12,250.00
0.0700 oh pekerja @ 45,000.00

0.1050 oh tukang cat @ 55,000.00


0.0040 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 22,050.00
N. 6.6.10 1 M2 PELABURAN BIDANG KAYU DENGAN OLI BEKAS
0.3600 ltr oli bekas @ 5,000.00   1,800.00
0.0400 oh pekerja @ 45,000.00
0.0630 oh tukang cat @ 55,000.00
0.0630 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 1,800.00
N. 6.6.11 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR

0.1500 ltr plitur @ 8,500.00   1,275.00


0.3720 ltr plitur jadi @ 8,500.00   3,162.00
2.0000 lbr ampelas @ 2,500.00   5,000.00
- oh pekerja @
0.0600 oh tukang cat @ 55,000.00
0.0160 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 9,437.00
N. 6.6.12 1 M2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER
0.3500 ltr Residu atau ter @ 5,000.00   1,750.00
0.1000 oh pekerja @ 45,000.00   4,500.00
- oh tukang cat @
- oh kepala tukang @
0.0060 oh mandor @ 60,000.00
JUMLAH 6,250.00

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 115/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

N. 6.6.13 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS


0.1500 ltr Vernis @ 10,000.00   1,500.00
0.0500 Kg Dempul @ 25,000.00   1,250.00
0.1000 Ltr ampelas @ 2,500.00   250.00
0.0100 bh Kuas @ 7,500.00   75.00
0.1600 oh pekerja @ 45,000.00
0.1600 oh tukang cat @ 55,000.00
0.0160 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 3,075.00
N. 6.6.14 1 M2 PENGECATAN TEMBOK BARU ( 1 lapis plamir,
1 lapis cat dasar, 2 lapis cat penutup )
0.1000 kg plamir @ 22,500.00   2,250.00
0.1000 kg cat dasar @ 22,500.00   2,250.00
0.2600 kg cat penutup @ 15,400.00   4,004.00
0.0200 oh pekerja @ 45,000.00
0.0630 oh tukang cat @ 55,000.00
0.0063 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 8,504.00
N. 6.6.15 1 M2 PENGECATAN TEMBOK LAMA
( 1 lapis cat dasar, 2 lapis cat penutup )
  0.1200 kg cat dasar @ 22,500.00   2,700.00
  0.1800 kg cat penutup 2 x @ 15,400.00   2,772.00
  0.0280 oh pekerja @ 45,000.00
  0.0420 oh tukang cat @ 55,000.00
  0.0042 oh kepala tukang @ 60,000.00
  0.0025 oh mandor @ 60,000.00
JUMLAH 5,472.00
N. 6.6.16 1 M2 MELABUR TEMBOK DENGAN KALKARIUM

0.1000 ltr Kalkarium @   -


0.0280 oh pekerja @ 45,000.00
0.0420 oh tukang cat @ 55,000.00
0.0042 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH -
N. 6.6.17 1 M2 MELABUR TEMBOK DENGAN KAPUR SIRIH
0.1000 lbr Ampelas @ 2,500.00   250.00
0.2500 Ikat Alang-alang @ 500.00   125.00
0.0020 m3 Perancah kayu @ 1,037,571.94   2,075.14
0.1500 kg kapur sirih @ 10,000.00   1,500.00
0.1500 oh pekerja @ 45,000.00
0.0010 oh tukang cat @ 55,000.00
0.0001 oh kepala tukang @ 60,000.00
0.0025 oh mandor @ 60,000.00
JUMLAH 3,950.14

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 116/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

N. 6.6.18 1 M2 MELABUR TEMBOK LAMA DENGAN KAPUR SIRIH ( UNTUK PEMELILHARAAN )


0.0020 lbr Perancah kayu @ 1,037,571.94   2,075.14
0.3000 kg kapur sirih @ 10,000.00   3,000.00
0.0400 oh pekerja @ 45,000.00
0.0050 oh tukang cat @ 55,000.00
0.0005 oh kepala tukang @ 60,000.00
0.0025 oh Mandor @ 60,000.00
JUMLAH 5,075.14
N. 6.6.19 1 M2 PEMASANGAN WALL PAPER
1.2000 lbr Wall paper @ 30,000.00   36,000.00
0.2000 kg Perekat @ 10,000.00   2,000.00
0.0200 oh pekerja @ 45,000.00
0.2000 oh tukang cat @ 55,000.00
0.0020 oh kepala tukang @ 60,000.00
0.0025 oh Mandor @ 60,000.00
JUMLAH 38,000.00
N. 6.6.20 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI
0.1000 kg meni besi @ 25,000.00   2,500.00

0.0100 Ikat Kuas @ 7,500.00   75.00


0.0200 oh pekerja @ 45,000.00
0.2000 oh tukang cat @ 55,000.00
0.0200 oh kepala tukang @ 60,000.00
0.0100 oh Mandor @ 60,000.00
JUMLAH 2,575.00
N. 6.6.21 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH
0.1000 kg meni besi @ 25,000.00   2,500.00
0.0100 Ikat Kuas @ 7,500.00   75.00
0.0020 m3 Perancah kayu @ 1,037,571.94   2,075.14
0.2500 oh pekerja @ 45,000.00
0.2250 oh tukang cat @ 55,000.00

0.0225 oh kepala tukang @ 60,000.00


0.0075 oh Mandor @ 60,000.00
JUMLAH 4,650.14
N. 6.6.22 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL
SISTEM 4 LAPIS CAT KONVENSIONAL DENGAN TEBAL 200 UM
0.1000 kg meni ( read lead ) A @   -
0.1000 kg meni ( read lead ) B @   -
0.0400 kg Alumunium C @   -
0.0400 kg Alumunium C @   -
0.0100 Ltr Pengencer @   -
0.0020 m3 Perancah kayu @ 1,037,571.94   2,075.14
0.0060 oh pekerja @ 45,000.00
0.0060 oh tukang cat @ 55,000.00
0.0225 oh kepala tukang @ 60,000.00
0.0075 oh Mandor @ 60,000.00
JUMLAH 2,075.14

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 117/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

N. 6.6.23 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL


SISTEM 1 LAPIS CAT MUTAKHIR DENGAN TEBAL 200 UM
0.3000 kg cat @   -
0.0060 oh pekerja @ 45,000.00
0.0600 oh tukang cat @ 55,000.00
0.0120 oh kepala tukang @ 60,000.00
0.0060 oh Mandor @ 60,000.00
JUMLAH -
N. 6.6.24 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL
SISTEM 3 LAPIS CAT KONVENSIONAL DENGAN TEBAL 200 UM
0.1100 Kg Cat dasar @   -
0.1700 kg cat antara @   -
0.0800 kg cat penutup @   -
0.5000 oh pekerja @ 45,000.00
0.8000 oh tukang cat @ 55,000.00
0.3000 oh kepala tukang @ 60,000.00
0.2000 oh Mandor @ 60,000.00
JUMLAH -

N. 6.6.25 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA SEMPROT


( AIRLESS SPRAY ) SISTEM 1 LAPIS CAT MUTAKHIR DENGAN TEBAL 200 UM
0.3000 kg cat dasar @   -
0.4000 oh pekerja @ 45,000.00
0.7000 oh tukang cat @ 55,000.00
0.2000 oh kepala tukang @ 60,000.00
0.2000 oh Mandor @ 60,000.00
JUMLAH -

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 118/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

G. PEKERJAAN BETON

G.6.6.1 1 M3 BETON TUMBUK 1 pc ; 3 ps ; 5 kr   724,228.17


G.6.6.2 1 M3 BETON TUMBUK 1 pc ; 3 ps ; 6 kr   711,959.51
G.6.6.3 1 M3 BETON TUMBUK 1 pc ; 4 ps ; 6 kr   701,756.52

G.6.6.4 1 M3 MEMBUAT LANTAI KERJA BETON TUMBUK 1 pc ; 3 ps ; 5 kr   84,209.69


G.6.6.5. 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 3 kr)   890,375.49
G.6.6.6 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 4 kr)   764,265.49
G.6.6.7 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ;2,5 kr)   798,974.46
G.6.6.8 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ; 3 kr)   707,504.35
G.6.6.9 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ;2,5 kr)   824,168.79
G.6.6.10 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1 ps ; 2 kr)   859,109.40
G.6.6.11 1M3 MEMBUAT TIANG PANCANG PRESTRESSED BETON   886,637.14
G.6.6.12 1M3 MEMBUAT BETON DENGAN PUZZDITH - 100 XR   813,325.49
G.6.6.13 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ;3 kr)   890,375.49

G.6.6.14 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 4 kr)   866,703.84


G.6.6.15 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ;3kr)   906,598.48
G.6.6.16 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ; 2,5 kr)   922,795.80
G.6.6.17 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1 ps ;1kr)   1,032,599.71
G.6.6.18 1M3 MEMBUAT BETON KEDAP AIR DENGAN STROROX - 100   922,795.80
G.6.6.19 1M' MEMASANG PVC WATERSTOP LEBAR 150 MM   4,200.00
G.6.6.20 1M' MEMASANG PVC WATERSTOP LEBAR 200 MM   4,505.00
G.6.6.21 1M' MEMASANG PVC WATERSTOP LEBAR 230 MM   26,855.00
G.6.6.22 1M' MEMASANG PVC WATERSTOP LEBAR 250 MM   26,855.00
G.6.6.23 1M' MEMASANG PVC WATERSTOP LEBAR 300 MM   26,855.00

G.6.6.24 1M' MEMASANG PVC WATERSTOP LEBAR 320 MM   4,295.00


G.6.6.25 1 KG PEMBESIAN DG BESI POLOS   12,460.00
G.6.6.25 1 KG PEMBESIAN DG BESI ULIR   17,710.00
G.6.6.26 1 KG KABEL PRESSTRESSED POLOS/STRANDS   12,198.00
G.6.6.27 1 KG JARING KAWAT BAJA   22,010.00
G.6.6.28 1M2 PASANG BEKISTING UNTUK PONDASI   75,210.38
G. 6.6.29 1 M2 PASANG BEKISTING UNTUK SLOOF ( 2 x pakai )   80,398.24
G. 6.6.30 1 M2 PASANG BEKISTING UNTUK KOLOM ( 2 x pakai )   168,286.46

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 119/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


G. 6.6.31 1 M2 PASANG BEKISTING UNTUK BALOK ( 2 x pakai )   172,299.17
G. 6.6.32 1 M2 PASANG BEKISTING UNTUK LANTAI ( 2 x pakai )   207,186.46
G. 6.6.33 1 M2 PASANG BEKISTING UNTUK DINDING ( 2 x pakai )   179,498.60
G. 6.6.34 1 M2 PASANG BEKISTING UNTUK TANGGA   158,560.74
G. 6.6.35 1M3 MEMBUAT BETON DENGAN MUTU K 225   1,055,117.14
G. 6.6.36 1M3 MEMBUAT BETON DENGAN MUTU K 275   1,080,771.78
G. 6.6.37 1 M2 PASANG JEMBATAN COR   49,456.90
G. 6.6.38 1M3 MEMBUAT PONDASI BETON BERTULANG (150KG BESI + BEKISTING)   2,925,969.03
G. 6.6.39 1M3 MEMBUAT SLOOF BETON BERTULANG (200KG BESI + BEKISTING)   3,659,071.56
G. 6.6.40 1M3 MEMBUAT KOLOM BETON BERTULANG (300KG BESI + BEKISTING)   6,073,831.70
G. 6.6.41 1M3 MEMBUAT BALOK BETON BERTULANG (200KG BESI + BEKISTING)   4,575,270.23
G. 6.6.42 1M3 MEMBUAT BALOK BETON BERTULANG (150KG BESI + BEKISTING)   4,119,088.79
G. 6.6.43 1M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING)   3,983,065.91
G. 6.6.44 1M3 MEMBUAT TANGGA BETON BERTULANG (200KG BESI + BEKISTING)   4,350,900.18
G. 6.6.45 1M3 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11x11) CM   54,451.90
G. 6.6.46 1M' MEMBUAT RING BALOK BETON BERTULANG (10X15) CM   66,663.82
H. PEKERJAAN PENUTUP ATAP

H. 6.6.1 1M2 PASANG ATAP GENTENG PALENTONG KECIL   11,835.00


H. 6.6.2 1M2 PASANG ATAP GENTENG KODOK /GLAZZUR   50,585.00
H. 6.6.3 1M2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR   10,890.00
H. 6.6.4 1M2 PASANG ATAP GENTENG BUBUNG PALENTONG   45,186.14
H. 6.6.5 1M' PASANG BUBUNG GENTENG KODOK   55,186.14
H. 6.6.6 1M2 PASANG BUBUNG GENTENG PALENTONG BESAR   45,186.14
H. 6.6.7 1M2 PASANG ROOFLIGHT FIBREGLASS (180X90) CM   11,416.25
H. 6.6.8 1m2 PASANG ATAP ASBES GELOMBANG (2,50X0,92)X5MM   24,805.00
H. 6.6.9 1m2 PASANG ATAP ASBES GELOMBANG (2,25X0,92)X5MM   27,105.00
H. 6.6.10 1m2 PASANG ATAP ASBES GELOMBANG (2,00X0,92)X5MM   26,985.00
H. 6.6.11 1m2 PASANG ATAP ASBES GELOMBANG (1,80X0,92)X5MM   30,435.00
H. 6.6.12 1m2 PASANG ATAP ASBES GELOMBANG (3,00X1,05)X4 MM   21,235.00
H. 6.6.13 1m2 PASANG ATAP ASBES GELOMBANG (2,70X1,05)X4 MM   22,845.00
H. 6.6.14 1m2 PASANG ATAP ASBES GELOMBANG (2,40X1,05)X4 MM   22,865.00
H. 6.6.15 1m2 PASANG ATAP ASBES GELOMBANG (2,10X1,05)X4 MM   24,475.00
H. 6.6.16 1m2 PASANG ATAP ASBES GELOMBANG (1,5X1,05)X4 MM   31,145.00

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 120/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


H. 6.6.17 1m2 PASANG ATAP ASBES GELOMBANG (3,00X1,08)X6 MM   21,255.00
H. 6.6.18 1m2 PASANG ATAP ASBES GELOMBANG (2,70X1,08)X6 MM   21,485.00
H. 6.6.19 1m2 PASANG ATAP ASBES GELOMBANG (2,40X1,08)X6 MM   23,325.00
H. 6.6.20 1m2 PASANG ATAP ASBES GELOMBANG (2,10X1,08)X6 MM   24,015.00
H. 6.6.21 1m2 PASANG ATAP ASBES GELOMBANG (1,80X1,08)X6 MM   25,855.00
H. 6.6.22 1M' PASANG BUBUNG STEL GELOMBANG 0,92 M   97,475.00
H. 6.6.23 1M' PASANG NOK STEL GELOMBANG 1,05 M   97,475.00
H. 6.6.24 1M' PASANG NOK STEL GELOMBANG 1,08 M   97,475.00
H. 6.6.25 1M' PASANG NOK paten 0,92 m   97,475.00
H. 6.6.26 1M' PASANG NOK PATEN 1,05 M   97,475.00
H. 6.6.27 1M' PASANG NOK PATEN 1,08 M   97,475.00
H. 6.6.28 1M' PASANG NOK STEL RATA 0,92 M   99,570.00
H. 6.6.29 1M' PASANG NOK STEL RATA 1,05 M   99,570.00
H. 6.6.30 1M2 PASANG ATAP GENTENG BETON   54,554.75
H. 6.6.31 1M2 PASANG ATAP GENTENG ASPAL   76,584.75
H. 6.6.32 1M2 PASANG ATAP GENTENG METAL   77,460.00
H. 6.6.33 1M' PASANG ATAP SIRAP   55,565.00
H. 6.6.34 1M' PASANG NOK GENTENG BETON   68,574.14
H. 6.6.35 1M' PASANG NOK GENTENG ASPAL   30,581.50
H. 6.6.36 1M' PASANG NOK GENTENG METAL   21,771.25
H. 6.6.37 1 M' MEMASANG BUBUNGAN ATAP SIRAP L 40 cm   41,558.29
H. 6.6.38 1 M2 MEMASANG ATAP SENG   30,706.00
H. 6.6.39 1 M2 MEMASANG BUBUNGAN ATAP SENG   61,395.00
H. 6.6.40 1 M2 PASANG ATAP ALUMUNIUM   49,340.00
H. 6.6.41 1 M2 PASANG NOK ALUMUNIUM   61,700.00
H. 6.6.42 1 M2 PASANG ALUMUNIUM FOIL /SISALATION   482,780.00
I. PEKERJAAN PLAFOND

I. 6.6.1 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 6 MM   38,250.00


I. 6.6.2 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 5 MM   29,010.00
I. 6.6.3 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 4 MM   30,110.00
I. 6.6.4 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 3,5 MM   29,010.00
I. 6.6.5 1 M2 PLAFOND AKUSTIK (30 X 30) CM   17,680.00
I. 6.6.6 1 M2 PLAFOND AKUSTIK (30 X 60) CM   9,980.00

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 121/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


I. 6.6.7 1 M2 PLAFOND AKUSTIK (60 X 120) CM   9,980.00
I. 6.6.8 1 M2 PLAFOND PLYWOOD ( 30 X 60 ) cm, TEBAL 4 MM   32,200.00
I. 6.6.9 1 M2 PLAFOND PLYWOOD ( 30 X 60 ) cm, TEBAL 6 MM   43,180.00
I. 6.6.10 1 M2 PLAFOND PLYWOOD ( 60 X 120 ) cm, TEBAL 2 MM   21,560.00
I. 6.6.11 1 M2 PLAFOND PLYWOOD ( 60 X 120 ) cm, TEBAL 6 MM   44,560.00
I. 6.6.12 1 M2 PLAFOND TEAKWOOD ( 30 x 60 ) cm, TEBAL 4 MM   50,920.00
I. 6.6.13 1 M2 PLAFOND TEAKWOOD ( 60 x 120 ) cm, TEBAL 4 MM   52,622.50
I. 6.6.14 1M2 PLAFOND LAT KAYU JATI   193,033.25
I. 6.6.15 1M2 PLAFOND LAT KAYU MERANTI   53,534.98
I. 6.6.16 1M2 PLAFOND LAT KAYU BENGKIRAI   76,334.98
I. 6.6.17 1M2 PLAFOND SOFTBOARD   33,634.75
I. 6.6.18 1M2 PLAFOND AKUSTIK 60 X 120 CM + RANGKA ALUMUNIUM   37,700.00
I. 6.6.19 1M2 PLAFOND KAYU PROFIL   10,273.25
I. 6.6.20 1M2 PLAFOND ASBES ( 1,00 X 1,00 ) M, TEBAL 3,2MM RANGKA MERANTI   41,320.36
I. 6.6.21 1M2 PLAFOND PLYWOOD 4 MM + RANGKA KAYU MERANTI   85,918.65
I. 6.6.22 1M2 PLAFOND AKUSTIK (30 X 60 ) CM + RANGKA KAYU MERANTI   61,453.65
I. 6.6.23 1M2 PLAFOND AKUSTIK (30 X 30 ) CM + RANGKA KAYU MERANTI   72,273.94
I. 6.6.24 1M2 PLAFOND GYPSUM BOARD, TEBAL 9 MM   25,803.00
J. PEKERJAAN SANITAIR

 J. 6.6.1 MEMASANG 1 BH CLOSED DUDUK / MONOBLOK   1,490,660.00


 J. 6.6.2 MEMASANG 1 BH CLOSED JONGKOK KERAMIK   354,755.67
 J. 6.6.3 MEMASANG 1 BH CLOSED JONGKOK TERASO   243,605.67
 J. 6.6.4 MEMASANG 1 BH URINOIR   2,069,655.67
 J. 6.6.5 MEMASANG 1 BH WASTAFEL   1,254,405.67
 J. 6.6.6 MEMASANG 1 BH BAK MANDI TERASO VOLUME 0.30 M3   339,205.67
 J. 6.6.7 MEMASANG 1 BH BAK MANDI FIBREGLASS VOLUME 0,30 M3   883,300.00
 J. 6.6.8 MEMASANG 1 BH BAK AIR BATU BATA VOLUME 0,3 M3 ( 60 x 60 )   1,558,890.11
 J. 6.6.9 MEMASANG 1 BH BADKIP PORSELEN   64,125.00
 J. 6.6.10 MEMASANG 1 BH BAK BETON VOLUME 1 M3 AIR   11,999,091.72
 J. 6.6.11 MEMASANG 1 BH BAK FIBERGLASS VOLUME 1 M3 AIR   1,588,500.00
 J. 6.6.12 MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.15 CM   10,704.41
 J. 6.6.13 MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.20 CM   13,496.08
 J. 6.6.14 MEMASANG 1M' PIPA BETON, DIAMETER 15 - 20 CM   33,141.41

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 122/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


 J. 6.6.15 MEMASANG 1M' PIPA BETON, DIAMETER 30 - 100 CM   67,984.21
 J. 6.6.16 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (30X30)CM TINGGI 35   315,358.16
 J. 6.6.17 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (45X45)CM TINGGI 50   259,898.59
 J. 6.6.18 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (60 x 60)CM TINGGI 6   398,943.14
 J. 6.6.19 MEMASANG 1M' PIPA GALVANIS DIAMETER 1/2"   110,415.00
 J. 6.6.20 MEMASANG 1M' PIPA GALVANIS DIAMETER 3/4"   160,852.50
 J. 6.6.21 MEMASANG 1M' PIPA GALVANIS DIAMETER 1 "   211,290.00
 J. 6.6.22 MEMASANG 1M' PIPA GALVANIS DIAMETER 1 1/2 "   318,789.00
 J. 6.6.23 MEMASANG 1M' PIPA GALVANIS DIAMETER 3"   1,267,014.00
 J. 6.6.24 MEMASANG 1M' PIPA GALVANIS DIAMETER 4 "   1,499,708.00
 J. 6.6.25 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1/2 "   47,419.25
 J. 6.6.26 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4"   55,825.50
 J. 6.6.27 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1 "   89,450.50
 J. 6.6.28 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1 1/2 "   131,481.75
 J. 6.6.29 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2"   173,513.00
 J. 6.6.30 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2 1/2"   215,544.25
 J. 6.6.31 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3"   264,313.50
 J. 6.6.32 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 4"   297,938.50
 J. 6.6.33 MEMASANG 1BH BAK CUCI PIRING STAINLES STEEL   249,740.00
 J. 6.6.34 MEMASANG 1 BH BAK CUCI PIRING TERASO   247,578.35
 J. 6.6.35 MEMASANG 1BH KRAN DIAMETER 3/4" ATAU 1/2"   26,937.50
 J. 6.6.36 MEMASANG 1BH FLOOR DRAIN   24,350.00
K. PEKERJAAN BESI

K. 6.6.1 1 KG PASANG RANGKA ATAP BAJA   5,408.00


K. 6.6.2 1 M2 PASANG PINTU BESI BAJA   3,408.00
K. 6.6.3 1 M2 PASANG JENDELA BESI   111,615.00
K. 6.6.4 1 M2 PASANG JENDELA BESI TAHAN API   119,550.00
K. 6.6.5 1 M2 PASANG PINTU GULUNG BESI   127,560.00
K. 6.6.6 1 M2 PASANG PINTU LIPAT   3,408.00
K. 6.6.7 1 M2 PASANG PINTU SUNSCREEN ALLUMUNIUM   52,640.00
K. 6.6.8 1 M2 PASANG ROLLING DOOR   136,362.00
K. 6.6.9 1 M2 PASANG PINTU ALLUMUNIUM   111,612.00
K. 6.6.10 1 M2 PASANG VENETIONS BLINDS   37,205.00

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 123/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


K. 6.6.11 1 M2 PASANG VERTIKALS BLINDS   37,205.00
K. 6.6.12 1 M2 PASANG TERALI BESI   327,756.00
K. 6.6.13 1 M2 PASANG KAWAT HARMONIKA   54,254.13
K. 6.6.14 1 M2 PASANG KAWAT NYAMUK   24,004.13
K. 6.6.15 1 M2 PASANG KAWAT KASSA   25,714.13
K. 6.6.16 1 M2 PASANG KAWAT BURUNG   31,214.13
K. 6.6.17 1 M2 PASANG JENDELA NAKO & TRALIS   186,946.50
K. 6.6.18 1 M' PASANG TALANG DATAR, SENG BLJS 28   70,933.07
K. 6.6.19 1 M' PASANG TALANG MIRING, SENG BLJS 28   83,566.24
K. 6.6.20 1 M' PASANG TALANG 1/2 LINGKARAN D-10 CM. SENG BJLS 28   75,771.37
K. 6.6.21 1 M' PASANG TALANG 1/2 LINGKARAN D-10 CM. SENG BJLS 24   81,466.24
L. PEKERJAAN KUNCI DAN KACA

L. 6.6.1 1 BUAH PASANG KUNCI TANAM ANTIK   164,480.00


L. 6.6.2 1 BUAH PASANG KUNCI TANAM BIASA   154,100.00
L. 6.6.3 1 BUAH PASANG KUNCI KAMAR MANDI   93,175.00
L. 6.6.4 1 BUAH PASANG KUNCI SILINDER   28,040.00
L. 6.6.5 1 BUAH PASANG ENGSEL PINTU   34,870.00
L. 6.6.6 1 BUAH PASANG ENGSEL JENDELA KUPU - KUPU   26,580.00
L. 6.6.7 1 BUAH PASANG ENGSEL ANGIN   13,700.00
L. 6.6.8 1 BUAH PASANG SPRING KNIP   9,870.00
L. 6.6.9 1 BUAH PASANG KAIT ANGIN   17,870.00
L. 6.6.10 1 BUAH PASANG DOOR CLOSER   32,900.00
L. 6.6.11 1 BUAH PASANG KUNCI SELOT   13,160.00
L. 6.6.12 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER   32,900.00
L. 6.6.13 1 BUAH PASANG DOOR STOP   6,580.00
L. 6.6.14 1 BUAH PASANG REL PINTU DORONG   39,480.00
L. 6.6.15 1 BUAH PASANG KUNCI LEMARI   41,450.00
L. 6.6.16 1 M2 PASANG KACA, TEBAL 3 MM   62,670.00
L. 6.6.17 1 M2 PASANG KACA, TEBAL 5 MM   97,870.00
L. 6.6.18 1 M2 PASANG KACA, TEBAL 8 MM   151,652.50
L. 6.6.19 1 M2 PASANG KACA GELAP, TEBAL 5 MM   120,950.00
L. 6.6.20 1 M2 PASANG KACA CERMIN, TEBAL 5 MM   114,370.00
L. 6.6.21 1 M2 PASANG KACA CERMIN, TEBAL 6 MM   135,270.00

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 124/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


L. 6.6.22 1 M2 PASANG KACA CERMIN, TEBAL 8 MM   162,855.50
L. 6.6.23 1 M2 PASANG KACA " WIREGLASS", TEBAL 5 MM   9,870.00
L. 6.6.24 1 M2 PASANG KACA PATRI, TEBAL 5 MM   284,870.00
M. PEKERJAAN PENUTUP LANTAI & DINDING

M.6.6.1 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 40 X 40 CM   82,613.69


M.6.6.2 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 30 X 30 CM   75,070.69
M.6.6.3 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 20 X 20 CM   65,053.15
M.6.6.4 1 M2 PASANG LANTAI UBIN WARNA UKURAN 40 X 40 CM   83,017.64
M.6.6.5 1 M2 PASANG LANTAI UBIN WARNA UKURAN 30 x 30 CM   70,689.64
M.6.6.6 1 M2 PASANG LANTAI UBIN WARNA UKURAN 20 x 20 CM   79,603.64
M.6.6.7 1 M2 PASANG LANTAI UBIN TERASO UKURAN 40 x 40 CM   96,193.69
M.6.6.8 1 M2 PASANG LANTAI UBIN TERASO UKURAN 30 x 30 CM   107,754.69
M.6.6.9 1 M2 PASANG LANTAI UBIN GRANITO UKURAN 40 X 40 CM   139,143.69
M.6.6.10 1 M2 PASANG LANTAI UBIN GRANITO UKURAN 30 X 30 CM   143,300.69
M.6.6.11 1 M2 PASANG LANTAI UBIN TERALUX TERANG UKURAN 40 X 40 CM   34,333.69
M.6.6.12 1 M2 PASANG LANTAI UBIN TERALUX TERANG UKURAN 30 X 30 CM   35,085.69
M.6.6.13 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 60 X 60 CM   39,193.92
M.6.6.14 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 40 X 40 CM   60,933.69
M.6.6.15 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 30 X 30 CM   71,579.18
M.6.6.16 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 15 X 20 CM   15,849.87
M.6.6.17 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 10 X 30 CM   10,864.61
M.6.6.18 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 10 X 40 CM   11,746.57
M.6.6.19 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 20 CM   11,194.70
M.6.6.20 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 30 CM   10,547.60
M.6.6.21 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 40 CM   13,166.97
M.6.6.22 1 M' PASANG PLINT UBIN TERASO UKURAN 10 X 30 CM   15,734.30
M.6.6.23 1 M' PASANG PLINT UBIN TERASO UKURAN 10 X 40 CM   16,285.70
M.6.6.24 1 M' PASANG PLINT UBIN GRANITO UKURAN 10 X 40 CM   18,028.20
M.6.6.25 1 M' PASANG PLINT UBIN GRANITO UKURAN 10 X 30 CM   58,627.61
M.6.6.26 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 X 40 CM   48,637.61
M.6.6.27 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 X 30 CM   48,637.61
M.6.6.28 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 60 CM   48,637.61
M.6.6.29 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 40 CM   48,637.61

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 125/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


M.6.6.30 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 30 CM   48,637.61
M.6.6.31 1 M2 PASANG TERASO COR DITEMPAT   46,260.00
M.6.6.32 1 M2 PASANG TERALUC COR DITEMPAT, TEBAL 3 CM   46,260.00
M.6.6.33 1 M2 PASANG UBIN TAHAN ASAM   32,092.68
M.6.6.34 1 M2 PASANG LANTAI KERAMIK ARTISTIK 10 X 20 CM   133,718.62
M.6.6.35 1 M2 PASANG LANTAI KERAMIK ARTISTIK 10 X 10 CM   149,518.62
M.6.6.36 1 M2 PASANG LANTAI KERAMIK ARTISTIK 5 X 20 CM   133,718.62
M.6.6.37 1 M2 PASANG PLINT KERAMIK ARTISTIK 10 X 20 CM   18,187.61
M.6.6.38 1 M2 PASANG PLINT KERAMIK ARTISTIK 10 X 10 CM   15,969.61
M.6.6.39 1 M2 PASANG PLINT KERAMIK ARTISTIK 5 X 20 CM   14,218.05
M.6.6.40 1 M' INTERNAL COVE ARTISTIK ( 5 X 5 X 20 ) CM   76,320.01
M.6.6.41 1 M' PASANG PLINT VINYL TANPA ADUKAN   8,720.00
M.6.6.42 1 M2 PASANG LANTAI KERAMIK 10 X 20 CM   108,649.82
M.6.6.43 1 M2 PASANG LANTAI KERAMIK 15 X 15 CM   111,118.62
M.6.6.44 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM   117,718.62
M.6.6.45 1 M2 PASANG LANTAI KERAMIK 25 X 25 CM   117,718.62
M.6.6.46 1 M2 PASANG LANTAI KERAMIK 15 X 20 CM   117,718.62
M.6.6.47 1 M2 PASANG LANTAI KERAMIK 30 x 30 CM   110,718.62
M.6.6.48 1 M2 PASANG LANTAI KERAMIK 30 x 30 CM ANTI SLIP   114,718.62
M.6.6.49 1 M2 PASANG LANTAI KERAMIK 10 x 33 CM   110,718.62
M.6.6.50 1 M2 PASANG LANTAI MOSAIK 30 X 30 CM, EX. LOKAL   76,152.11
M.6.6.51 1 M2 PASANG LANTAI MARMER   76,152.11
M.6.6.52 1 M2 PASANG LANTAI KARPET 100 % WOOL   18,530.00
M.6.6.53 1 M2 PASANG LANTAI KARPET 80 % WOOL, 20% NYLON   18,530.00
M.6.6.54 1 M2 PASANG UNDRLYER, TEBAL 6 MM   13,080.00
M.6.6.55 1 M2 PASANG LANTAI KARPET   18,530.00
M.6.6.56 1 M2 PASANG LANTAI PARQUET JATI   18,530.00
M.6.6.57 1 M2 PASANG GYMFLOOR   52,550.00
M.6.6.58 1 M2 PASANG DINDING PORSELIN 11 X 11 CM, PUTIH   171,948.00
M.6.6.59 1 M2 PASANG DINDING PORSELIN 11 X 11 CM, WARNA   220,340.21
M.6.6.60 1 M2 PASANG DINDING PORSELIN 15 X 15 CM, PUTIH   174,640.21
M.6.6.61 1 M2 PASANG DINDING PORSELIN 15 X 15 CM, WARNA   197,140.21
M.6.6.62 1 M2 PASANG DINDING PORSELIN 10 X 20 CM, WARNA   196,140.21

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 126/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


M.6.6.63 1 M2 PASANG DINDING PORSELIN 20 X 20 CM, WARNA   186,570.07
M.6.6.64 1 M2 PASANG DINDING KERAMIK ARTISTIK 10 X 20 CM   171,140.21
M.6.6.65 1 M2 PASANG DINDING KERAMIK ARTISTIK 5 X 20 CM   121,140.21
M.6.6.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM   106,140.21
M.6.6.67 1 M2 PASANG DINDING KERAMIK 15 x 15 CM   109,390.21
M.6.6.68 1 M2 PASANG DINDING KERAMIK 20 x 20 CM   115,140.21
M.6.6.69 1 M2 PASANG DINDING KERAMIK 10 x 20 CM   86,315.21
M.6.6.70 1 M2 PASANG DINDING MARMER   143,487.58
M.6.6.71 1 M2 PASANG DINDING BATA PELAPIS 7 X 3 X 24 CM   111,487.58
M.6.6.72 1 M2 PASANG DINDING BATA KLINKER 5 X 5 X 24 CM   112,287.58
M.6.6.73 1 M2 PASANG DINDING BATU PAROS   69,889.85
M.6.6.74 1 M2 PASANG DINDING BATU TEMPEL HITAM   69,889.85
M.6.6.75 1 M2 PASANG LANTAI VINYL KARET 30 X 30 CM KL I   16,350.00
M.6.6.76 1 M2 PASANG LANTAI VINYL KARET 30 X 30 CM KL II   16,350.00
M.6.6.77 1 M2 PASANG LANTAI VINYL ASBES 30 X 30 CM   16,350.00
M.6.6.78 1 M2 PASANG LANTAI VINYL MOTIF KEMBANG 30 X 30 CM   16,350.00
M.6.6.79 1 M2 PASANG WALL COVERING LEBAR 50 CM   44,630.00
M.6.6.80 1 M2 FLOOR HARDENER FERROVAX   13,080.00
M.6.6.81 1 M2 FLOOR HARDENER MASTERCRON   13,080.00
M.6.6.82 1 M2 PLINT KAYU 2 X 10 CM   30,595.00
N. PEKERJAAN CAT - CATAN

N. 6.6.1 1 M2 MENGIKIS/MENGEROK PERMUKAAN CAT TEMBOK LAMA   11,475.00


N. 6.6.2 1 M2 MENCUCI BIDANG PERMUKAAN TEMBOK YANG PERNAH DICAT   12,000.00
N. 6.6.3 1 M2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL   12,000.00
N. 6.6.4 1 M2 MENYABUN PERMUKAAN TEMBOK LAMA   12,000.00
N. 6.6.5 1 M2 MENGEROK KARAT ATAU CAT LAMA PERMUKAAN BAJA DENGAN PANCAR   726,407.11
N. 6.6.6 1 M2 MENDEMPUL DAN MENGGOSOK KAYU   5,791.25
N. 6.6.7 1 M2 PENGECATAN BIDANG KAYU LAMA   21,025.00
N. 6.6.8 1 M2 PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR ), 1 LAPIS CAT DASAR,   22,380.00
N. 6.6.9 1 M2 PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR )   31,365.00
N. 6.6.10 1 M2 PELABURAN BIDANG KAYU DENGAN TEAK OIL   10,995.00
N. 6.6.11 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR   13,847.00
N. 6.6.12 1 M2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER   6,610.00

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 127/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


N. 6.6.13 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS   20,185.00
N. 6.6.14 1 M2 PENGECATAN TEMBOK BARU ( 1 lapis plamir,   13,397.00
N. 6.6.15 1 M2 PENGECATAN TEMBOK LAMA   9,444.00
N. 6.6.16 1 M2 MELABUR TEMBOK DENGAN KALKARIUM   3,972.00
N. 6.6.17 1 M2 MELABUR TEMBOK DENGAN KAPUR SIRIH   10,911.14
N. 6.6.18 1 M2 MELABUR TEMBOK LAMA DENGAN KAPUR SIRIH ( UNTUK PEMELILHARAAN )   7,330.14
N. 6.6.19 1 M2 PEMASANGAN WALL PAPER   50,170.00
N. 6.6.20 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI   16,275.00
N. 6.6.21 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH   30,075.14
N. 6.6.22 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL   4,475.14
N. 6.6.23 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL   4,650.00
N. 6.6.24 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL   96,500.00
N. 6.6.25 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA SEMPROT   80,500.00

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 128/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

724,228.17 TRUE
711,959.51 TRUE
701,756.52 TRUE

84,209.69 TRUE
890,375.49 TRUE
764,265.49 TRUE
798,974.46 TRUE
707,504.35 TRUE
824,168.79 TRUE
859,109.40 TRUE
886,637.14 TRUE
813,325.49 TRUE
890,375.49 TRUE

866,703.84 TRUE
906,598.48 TRUE
922,795.80 TRUE
1,032,599.71 TRUE
922,795.80 TRUE
4,200.00 TRUE
4,505.00 TRUE
26,855.00 TRUE
26,855.00 TRUE
26,855.00 TRUE

4,295.00 TRUE
12,460.00 TRUE
17,710.00 TRUE
12,198.00 TRUE
22,010.00 TRUE
75,210.38 TRUE
80,398.24 TRUE
168,286.46 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 129/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
172,299.17 TRUE
207,186.46 TRUE
179,498.60 TRUE
158,560.74 TRUE
1,055,117.14 TRUE
1,080,771.78 TRUE
49,456.90 TRUE
2,925,969.03 TRUE
3,659,071.56 TRUE
6,073,831.70 TRUE
4,575,270.23 TRUE
4,119,088.79 TRUE
3,983,065.91 TRUE
4,350,900.18 TRUE
54,451.90 TRUE
66,663.82 TRUE
TRUE
11,835.00 TRUE
50,585.00 TRUE
10,890.00 TRUE
45,186.14 TRUE
55,186.14 TRUE
45,186.14 TRUE
11,416.25 TRUE
24,805.00 TRUE
27,105.00 TRUE
26,985.00 TRUE
30,435.00 TRUE
21,235.00 TRUE
22,845.00 TRUE
22,865.00 TRUE
24,475.00 TRUE
31,145.00 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 130/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
FALSE
21,255.00 TRUE
21,485.00 TRUE
23,325.00 TRUE
24,015.00 TRUE
25,855.00 TRUE
97,475.00 TRUE
97,475.00 TRUE
97,475.00 TRUE
97,475.00 TRUE
97,475.00 TRUE
97,475.00 TRUE
99,570.00 TRUE
99,570.00 TRUE
54,554.75 TRUE
76,584.75 TRUE
77,460.00 TRUE
55,565.00 TRUE
68,574.14 TRUE
30,581.50 TRUE
21,771.25 TRUE
41,558.29 TRUE
30,706.00 TRUE
61,395.00 TRUE
49,340.00 TRUE
61,700.00 TRUE
482,780.00 TRUE
TRUE
38,250.00 TRUE
29,010.00 TRUE
30,110.00 TRUE
29,010.00 TRUE
17,680.00 TRUE
9,980.00 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 131/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
FALSE
9,980.00 TRUE
32,200.00 TRUE
43,180.00 TRUE
21,560.00 TRUE
44,560.00 TRUE
50,920.00 TRUE
52,622.50 TRUE
193,033.25 TRUE
53,534.98 TRUE
76,334.98 TRUE
33,634.75 TRUE
37,700.00 TRUE
10,273.25 TRUE
41,320.36 TRUE
85,918.65 TRUE
61,453.65 TRUE
72,273.94 TRUE
25,803.00 TRUE
TRUE
1,490,660.00 TRUE
354,755.67 TRUE
243,605.67 TRUE
2,069,655.67 TRUE
1,254,405.67 TRUE
339,205.67 TRUE
883,300.00 TRUE
1,558,890.11 TRUE
64,125.00 TRUE
11,999,091.72 TRUE
1,588,500.00 TRUE
10,704.41 TRUE
13,496.08 TRUE
33,141.41 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 132/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
67,984.21 TRUE
315,358.16 TRUE
259,898.59 TRUE
398,943.14 TRUE
110,415.00 TRUE
160,852.50 TRUE
211,290.00 TRUE
318,789.00 TRUE
1,267,014.00 TRUE
1,499,708.00 TRUE
47,419.25 TRUE
55,825.50 TRUE
89,450.50 TRUE
131,481.75 TRUE
173,513.00 TRUE
215,544.25 TRUE
264,313.50 TRUE
297,938.50 TRUE
249,740.00 TRUE
247,578.35 TRUE
26,937.50 TRUE
24,350.00 TRUE
TRUE
5,408.00 TRUE
3,408.00 TRUE
111,615.00 TRUE
119,550.00 TRUE
127,560.00 TRUE
3,408.00 TRUE
52,640.00 TRUE
136,362.00 TRUE
111,612.00 TRUE
37,205.00 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 133/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
37,205.00 TRUE
327,756.00 TRUE
54,254.13 TRUE
24,004.13 TRUE
25,714.13 TRUE
31,214.13 TRUE
186,946.50 TRUE
70,933.07 TRUE
83,566.24 TRUE
75,771.37 TRUE
81,466.24 TRUE
TRUE
164,480.00 TRUE
154,100.00 TRUE
93,175.00 TRUE
28,040.00 TRUE
34,870.00 TRUE
26,580.00 TRUE
13,700.00 TRUE
9,870.00 TRUE
17,870.00 TRUE
32,900.00 TRUE
13,160.00 TRUE
32,900.00 TRUE
6,580.00 TRUE
39,480.00 TRUE
41,450.00 TRUE
62,670.00 TRUE
97,870.00 TRUE
151,652.50 TRUE
120,950.00 TRUE
114,370.00 TRUE
135,270.00 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 134/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
162,855.50 TRUE
9,870.00 TRUE
284,870.00 TRUE
TRUE
82,613.69 TRUE
75,070.69 TRUE
65,053.15 TRUE
83,017.64 TRUE
70,689.64 TRUE
79,603.64 TRUE
96,193.69 TRUE
107,754.69 TRUE
139,143.69 TRUE
143,300.69 TRUE
34,333.69 TRUE
35,085.69 TRUE
39,193.92 TRUE
60,933.69 TRUE
71,579.18 TRUE
15,849.87 TRUE
10,864.61 TRUE
11,746.57 TRUE
11,194.70 TRUE
10,547.60 TRUE
13,166.97 TRUE
15,734.30 TRUE
16,285.70 TRUE
18,028.20 TRUE
58,627.61 TRUE
48,637.61 TRUE
48,637.61 TRUE
48,637.61 TRUE
48,637.61 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 135/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
FALSE
48,637.61 TRUE
46,260.00 TRUE
46,260.00 TRUE
32,092.68 TRUE
133,718.62 TRUE
149,518.62 TRUE
133,718.62 TRUE
18,187.61 TRUE
15,969.61 TRUE
14,218.05 TRUE
76,320.01 TRUE
8,720.00 TRUE
108,649.82 TRUE
111,118.62 TRUE
117,718.62 TRUE
117,718.62 TRUE
117,718.62 TRUE
110,718.62 TRUE
114,718.62 TRUE
110,718.62 TRUE
76,152.11 TRUE
76,152.11 TRUE
18,530.00 TRUE
18,530.00 TRUE
13,080.00 TRUE
18,530.00 TRUE
18,530.00 TRUE
52,550.00 TRUE
171,948.00 TRUE
220,340.21 TRUE
174,640.21 TRUE
197,140.21 TRUE
196,140.21 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 136/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
186,570.07 TRUE
171,140.21 TRUE
121,140.21 TRUE
106,140.21 TRUE
109,390.21 TRUE
115,140.21 TRUE
86,315.21 TRUE
143,487.58 TRUE
111,487.58 TRUE
112,287.58 TRUE
69,889.85 TRUE
69,889.85 TRUE
16,350.00 TRUE
16,350.00 TRUE
16,350.00 TRUE
16,350.00 TRUE
44,630.00 TRUE
13,080.00 TRUE
13,080.00 TRUE
30,595.00 TRUE
TRUE
11,475.00 TRUE
12,000.00 TRUE
12,000.00 TRUE
12,000.00 TRUE
726,407.11 TRUE
5,791.25 TRUE
21,025.00 TRUE
22,380.00 TRUE
31,365.00 TRUE
10,995.00 TRUE
13,847.00 TRUE
6,610.00 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 137/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
20,185.00 TRUE
13,397.00 TRUE
9,444.00 TRUE
3,972.00 TRUE
10,911.14 TRUE
7,330.14 TRUE
50,170.00 TRUE
16,275.00 TRUE
30,075.14 TRUE
4,475.14 TRUE
4,650.00 TRUE
96,500.00 TRUE
80,500.00 TRUE
TRUE

Hal : 515

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 138/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

REKAPITULASI ANALISA SNI

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

A. PEKERJAAN PERSIAPAN

A. 6.6.1 1 M' PAGAR SEMENTARA DARI KAYU TINGGI 2 M   99,388.44

A. 6.6.2 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M   144,638.44


A. 6.6.3 1 M' PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 M   321,230.34
A. 6.6.4 1 M' MENGUKUR DAN MEMASANG BOUWPLANK   30,850.37
A. 6.6.5 1 M2 PEMBUATAN KANTOR SEMENTARA DENGAN LANTAI PLESTERAN   1,859,515.91
A. 6.6.6 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT - ALAT   487,082.97
A. 6.6.7 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU   507,647.35
A. 6.6.8 1 M' MEMBERSIHKAN LAPANGAN DAN PERATAAN   22,700.00
A. 6.6.9 1 M2 PEMBUATAN BEDENG BURUH   547,381.24
A. 6.6.10 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40 X 50 X 20) CM   79,888.59
A. 6.6.11 1 M2 PEMBUATAN STEGGER DARI BAMBU,UKURAN (40X50X20) CM   29,335.00
A. 6.6.12 1 M2 PEMBUATAN JALAN SEMENTARA   205,550.00
A. 6.6.13 1 M3 BONGKARAN BETON BERTULANG   319,995.00
A. 6.6.14 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH   319,995.00
A. 6.6.15 1 M' PASANG PAGAR KAWAT JARING GALVANIS.TINGGI 1,00 M   20,835.00
A. 6.6.16 1 M' PASANG PAGAR BETON PRACETAK ( 5X50X213) CM   2,030,554.75
B. PEKERJAAN TANAH

B. 6.6.1 1 M3 GALIAN TANAH BIASA SEDALAM 1 M'   20,400.00


B. 6.6.2 1 M3 GALIAN TANAH BIASA SEDALAM 2 M'   26,790.00
B. 6.6.3 1 M3 GALIAN TANAH BIASA SEDALAM 3 M'   37,455.00
B. 6.6.4 1 M3 GALIAN TANAH KERAS SEDALAM 1 M'   31,845.00
B. 6.6.5 1 M3 GALIAN TANAH CADAS SEDALAM 1 M   63,750.00
B. 6.6.6 1 M3 GALIAN TANAH LUMPUR SEDALAM 1 M'   42,015.00
B. 6.6.7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 M   2,550.00
B. 6.6.8 1 M3 PEMBUANGAN TANAH SEJAUH 150 M   26,220.00
B. 6.6.9 1 M3 URUGAN KEMBALI   9,780.00

B. 6.6.10 PEMADATAN TANAH   25,500.00


B. 6.6.11 1 M3 URUGAN TANAH   232,963.62
B. 6.6.11.a 1 M3 URUGAN PASIR   279,080.43

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 139/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

B. 6.6.12 1 M3 LAPISAN PUDEL CAMP 1 Kp : 3 Ps : 7 TL   133,602.12

B. 6.6.13 1 M3 LAPISAN PUDEL CAMP 1 Kp : 5 TL   67,685.00

B. 6.6.14 1 M3 PEMASANGAN LAPISAN IJUK   7,650.00


B. 6.6.15 1 M3 URUGAN SIRTU   264,230.43

B. 6.6.16 1 M2 PEMBUATAN JALAN SEMENTARA. TEBAL 25 CM   131,921.30

C. PEKERJAAN PONDASI

C.6.6.1 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 1 Ps   760,107.78


C.6.6.2 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 2 Ps   680,808.85

C.6.6.3 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 2,5 Ps   760,107.78


C.6.6.4 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 3 Ps   639,383.74

C.6.6.5 1 M3 PASANG PONDASI BATU KALI / GUNUNG / BELAH 1 Pc ; 4 Ps   614,578.59


C.6.6.6 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 5 Ps   597,348.20

C.6.6.7 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 6 Ps   585,250.83


C.6.6.8 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 8 Ps   562,890.83
C.6.6.9 1 M3 PASANG PONDASI BATU KALI, 1 Kp ; 1 Sm ; 1 Ps   481,899.60

C.6.6.10 1 M3 PASANG PONDASI BATU KALI, 1 Kp ; 1 Sm ; 2 Ps   430,598.52


C.6.6.11 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 1/4 Kp ; 4 Ps   615,706.46

C.6.6.12 1 M3 PASANG PONDASI BATU KALI, 1 Pc ; 3 Kp ; 10 Ps   520,605.71


C.6.6.13 1 M3 PASANG PONDASI BATU KALI, 1/4 Pc ; 1 Kp ; 4 Ps   511,062.29

C. 6.6.14 1 M3 PASANGAN BATU KOSONG (AANSTAMPING)   378,580.54

C. 6.6.15 1 M3 PASANG PONDASI SIKLOP 40 % BATU KALI   1,460,569.29


C. 6.6.16 1 M3 PASANG PONDASI SUMURAN DIA 100 CM   824,370.24

C. 6.6.17 PEMBUATAN TIANG PANCANG (40X40) CM, BETON BERTULANG   768,177.43


C. 6.6.18 PEMBUATAN TIANG PANCANG (35X35) CM, BETON BERTULANG   601,502.76

D. PEKERJAAN DINDING

D.6.6.1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 1 Ps   179,040.25

D.6.6.2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 2 Ps   166,625.36

D.6.6.3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 3 Ps   160,297.60


D.6.6.4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 4 Ps   155,292.73

D.6.6.5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 5 Ps   153,797.84

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 140/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

D.6.6.6 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 6 Ps   153,797.84

D.6.6.7 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 3 Kp ; 10 Ps   141,141.25

D.6.6.8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc ; 1 Ps   85,295.88


D. 6.6.9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 2 ps   80,180.55

D. 6.6.10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 3 ps   76,740.88


D. 6.6.11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps   75,021.38

D. 6.6.12 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 5 ps   73,955.32


D. 6.6.13 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 6 ps   73,783.98

D. 6.6.14 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 8 ps   72,468.35

D. 6.6.15 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 3 Kp ; 10 ps   70,823.35


D. 6.6.16 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 1 Sm ; 1 ps   59,011.01

D. 6.6.17 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp ; 1 Sm ; 2 Ps   61,480.28

D. 6.6.18 1 M2 PASANGAN DINDING HOLLOW BLOCK (HB.20)   145,959.22


D. 6.6.19 1 M2 PASANGAN DINDING HOLLOW BLOCK (HB.15)   125,040.55
D. 6.6.20 1 M2 PASANGAN DINDING HOLLOW BLOCK (HB.10)   93,538.31

D. 6.6.21 1 M2 PASANGAN DINDING CON BLOCK (HB.20)   171,195.87

D. 6.6.22 1 M2 PASANGAN DINDING CON BLOCK (HB.15)   125,026.32


D. 6.6.23 1 M2 PASANGAN DINDING CON BLOCK (HB.10)   101,980.22

D. 6.6.24 1 M2 PASANGAN DINDING LATAI   102,496.42


D. 6.6.25 1 M2 PASANGAN DINDING ROSTER 20 X 20   118,542.85

D. 6.6.26 1 M2 PASANG BATA BERONGGA UKURAN ( 5x11x24 ) cm   231,042.21


D. 6.6.27 1 M2 PASANG DINDING ANYAMAN BAMBU RANGKA KAYU   29,200.62
D. 6.6.28 1 M2 PASANG DINDING PEMISAH PLYWOOD RANGKAP   137,428.16

E. PEKERJAAN PLESTERAN

E. 6.6.1 1 M2 PLESTERAN 1 pc ; 1 ps, TEBAL 15 MM   33,105.57

E. 6.6.2 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 15 MM   30,319.84


E. 6.6.3 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 15 MM   29,064.57

E. 6.6.4 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 15 MM   28,213.34

E. 6.6.5 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 15 MM   27,955.67


E. 6.6.6 1 M2 PLESTERAN 1 pc ; 6 ps, TEBAL 15 MM   27,654.84

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 141/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

E. 6.6.7 1 M2 PLESTERAN 1 pc ; 8 ps, TEBAL 15 MM   27,216.41

E. 6.6.8 1 M2 PLESTERAN 1 pc ; 0,5 Kp ; 3 Ps, TEBAL 15 MM   26,962.97

E. 6.6.9 1 M2 PLESTERAN 1 pc ; 3 Kp ; 10 Ps, TEBAL 15 MM   23,856.34


E. 6.6.10 1 M2 PLESTERAN 0,5 pc ; 1 Kp ; 4 Ps, TEBAL 15 MM   26,096.77

E. 6.6.11 1 M2 PLESTERAN 1 Kp ; 1 Sm ; 1 Ps, TEBAL 15 MM   21,048.84

E. 6.6.12 1 M2 PLESTERAN 1 Kp ; 1 Sm ; 2 Ps, TEBAL 15 MM   22,534.53


E. 6.6.13 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 20 MM   42,220.84

E. 6.6.14 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 20 MM   39,976.74


E. 6.6.15 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 20 MM   38,652.68

E. 6.6.16 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 20 MM   37,457.28


E. 6.6.17 1 M2 PLESTERAN 1 pc ; 6 ps, TEBAL 20 MM   37,053.41

E. 6.6.18 1 M2 PLESTERAN 1 Kp ; 1 Sm ; 2 Ps, TEBAL 20 MM   28,744.95

E. 6.6.19 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 25 MM   43,054.37


E. 6.6.20 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 25 MM   45,319.85

E. 6.6.21 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 25 MM   44,116.35


E. 6.6.22 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 25 MM   43,041.51
E. 6.6.23 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 30 MM   55,323.85
E. 6.6.24 1 M2 PLESTERAN 1 pc ; 3 ps, TEBAL 30 MM   52,452.11

E. 6.6.25 1 M2 PLESTERAN 1 pc ; 4 ps, TEBAL 30 MM   50,818.62

E. 6.6.26 1 M2 PLESTERAN 1 pc ; 5 ps, TEBAL 30 MM   48,823.92


E. 6.6.27 1 M2 BERAPEN 1 pc ; 3 ps, TEBAL 30 MM   22,821.11

E. 6.6.28 1 M2 BERAPEN 1 pc ; 5 ps, TEBAL 15 MM   22,116.24

E. 6.6.29 1 M2 PLESTERAN BETON 1 pc ; 2 ps, TEBAL 15 MM   26,640.21


E. 6.6.30 1 M2 PLESTERAN BETON 1 pc ; 3 ps, TEBAL 15 MM   25,471.11
E. 6.6.31 1 M2 PLESTERAN SKONING 1 pc ; 2ps   7,984.13

E. 6.6.32 1 M2 PLESTERAN GRANITO 1 pc WARNA ; 2 GRANITO, TEBAL 10 MM   154,000.40

E. 6.6.33 1 M2 PLESTERAN TERASO 1 pc WARNA ; 2 BATU TERASO, TEBAL 10 MM   120,904.00


E. 6.6.34 1 M2 PLESTERAN CIPRAT 1 pc ; 2ps   25,958.27

E. 6.6.35 1 M2 PLESTERAN SIAR ADUKAN 1 pc ; 2ps   13,133.27

E. 6.6.36 1 M2 PLESTERAN WATERPROOF BATACOTE 3 LAPIS   32,877.40

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 142/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


F. PEKERJAAN KAYU

F.6.6.1 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU JATI   7,008,000.00

F.6.6.2 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU BENGKIRAI   3,723,086.33


F.6.6.3 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU ULIN   3,243,086.33

F.6.6.4 1 M³ PASANG KUSEN PINTU DAN JENDELA KAYU MERANTI MERAH   2,643,086.33
F.6.6.5 1 M2 PASANG PINTU KLAMP KAYU BENGKIRAI   158,423.84

F.6.6.6 1 M2 PASANG PINTU KLAMP KAYU ULIN   144,120.09


F.6.6.7 1 M2 PASANG PINTU PANEL KAYU JATI   480,500.00

F.6.6.8 1 M2 PASANG PINTU PANEL KAYU BENGKIRAI   286,002.88

F.6.6.9 1 M2 PASANG PINTU DAN JENDELA KACA KAYU JATI   405,400.00


F.6.6.10 1 M2 PASANG PINTU DAN JENDELA KACA KAYU BENGKIRAI   235,215.02

F.6.6.11 1 M2 PASANG PINTU DAN JENDELA KACA KAYU ULIN   221,215.02


F.6.6.12 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU JATI   694,000.00

F.6.6.13 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU BENGKIRAI   382,804.60


F.6.6.14 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU JATI   352,704.75

F.6.6.15 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU BENGKIRAI   257,401.16

F.6.6.16 1 M2 PASANG JALUSI MATI KUSEN KAYU JATI   567,773.75


F.6.6.17 1 M2 PASANG JALUSI MATI KUSEN KAYU BENGKIRAI   276,028.07

F.6.6.18 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU ULIN   249,618.91


F.6.6.19 1 M2 PASANG PINTU TEAKWOOD RANGKAP, RANGKAP KAYU JATI   407,897.50

F.6.6.20 1 M2 PASANG PINTU TEAKWOOD RANGKAP, RANGKAP KAYU BENGKIRAI   309,401.16

F.6.6.21 1 M2 PASANG PINTU PLYWOOD & FORMIKA, RANGKA KAYU JATI   407,554.75

F.6.6.22 1 M2 PASANG PINTU PLYWOOD & FORMIKA, RANGKA KAYU BENGKIRAI   312,251.16
F.6.6.23 1 M2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU JATI   402,804.75
F.6.6.24 1 M2 PASANG PINTU TEAKWOOD & FORMIKA, RANGKA KAYU BENGKIRAI   311,751.16

F.6.6.25 1 M2 PASANG PINTU FORMIKA DOUBLE, RANGKA KAYU JATI   492,054.75


F.6.6.26 1 M2 PASANG PINTU FORMIKA DOUBLE, RANGKA KAYU BENGKIRAI   396,751.16

F.6.6.27 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU JATI   6,703,460.00

F.6.6.28 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU BENGKIRAI   3,334,789.13


F.6.6.29 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU ULIN   2,896,329.13

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 143/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

F.6.6.30 1M3 PASANG KONSTRUKSI KUDA-KUDA KAYU MERANTI   2,344,789.13


F.6.6.31 1M2 PASANG KASO + RENG GENTENG KODOK KAYU BENGKIRAI   35,924.61

F.6.6.32 1M2 PASANG KASO + RENG GENTENG KODOK KAYU ULIN   31,413.36
F.6.6.33 1M2 PASANG KASO + RENG GENTENG MONIER KAYU JATI   82,673.75

F.6.6.34 1M2 PASANG KASO + RENG GENTENG MONIER KAYU BENGKIRAI   39,799.76

F.6.6.35 1M2 PASANG KASO + RENG GENTENG BETON KAYU BENGKIRAI   39,799.76
F.6.6.36 1M2 PASANG KASO + RENG ATAP SIRAP KAYU BENGKIRAI   335,144.37

F.6.6.37 1M2 PASANG KASO + RENG ATAP SIRAP KAYU ULIN   269,529.37
F.6.6.38 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00X1.00) M, KAYU JATI   87,682.50

F.6.6.39 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00X1.00) M, KAYU BENGKIRAI   50,933.36

F.6.6.40 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00X1.00) M, KAYU ULIN   46,325.86


F.6.6.41 1 M2 PASANG RANGKA LANGIT-LANGIT (30x60) CM, KAYU JATI   144,673.75

F.6.6.42 1 M2 PASANG RANGKA LANGIT-LANGIT (30x60) CM, KAYU BENGKIRAI   74,237.90


F.6.6.43 1 M2 PASANG RANGKA LANGIT-LANGIT (30x60) CM, KAYU MERANTI   53,537.90
F.6.6.44 1 M2 PASANG RANGKA LANGIT-LANGIT (30x30) CM, KAYU JATI   170,715.00

F.6.6.45 1 M2 PASANG RANGKA LANGIT-LANGIT (30x30) CM, KAYU BENGKIRAI   88,029.44

F.6.6.46 1 M2 PASANG RANGKA LANGIT-LANGIT (30x30) CM, KAYU MERANTI   63,729.44


F.6.6.47 1M' PASANG LISPLANG UKURAN (3X20) CM, KAYU JATI   68,291.25
F.6.6.48 1M' PASANG LISPLANG UKURAN (3X20) CM, KAYU BENGKIRAI   33,281.77
F.6.6.49 1M' PASANG LISPLANG UKURAN (3X30) CM, KAYU JATI   96,261.25

F.6.6.50 1M' PASANG LISPLANG UKURAN (3X30) CM, KAYU BENGKIRAI   60,844.54

F.6.6.51 1M' PASANG LISPLANG UKURAN 2x(3X20) CM, KAYU BENGKIRAI   58,204.29
F.6.6.52 1M' PASANG LISPLANG UKURAN 2x(2X20) CM, KAYU BENGKIRAI   32,692.62

F. 6.6.53. 1M' PASANG LISPLANG UKURAN 2x(2X20) CM, KAYU ULIN   29,252.62

F. 6.6.54 1M2 PASANG RANGKA DINDING PEMISAH KAYU BENGKIRAI   92,628.16


F. 6.6.55 1M2 PASANG RANGKA DINDING PEMISAH KAYU ULIN   82,028.16

F. 6.6.56 1M2 PASANG DINDING PEMISAH TEKWOOD RANGKAP, RANGKA KAYU BENGKIRAI   92,628.16
F. 6.6.57 1M2 PASANG DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KAMPER   166,948.16

F. 6.6.58 1M2 PASANG DINDING LAMBRISIRING DARI PAPAN JATI   176,927.50

F. 6.6.59 1M2 PASANG PLYWOOD TEBAL 3 MM, UNTUK DINDING   30,969.25


F. 6.6.60 1M2 PASANG LIST PLAFOND, KAYU PROFIL   7,882.50

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 144/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 145/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 146/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 147/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 148/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

99,388.44 TRUE

144,638.44 TRUE

321,230.34 TRUE

30,850.37 TRUE
########## TRUE

487,082.97 TRUE

507,647.35 TRUE

22,700.00 TRUE
547,381.24 TRUE

79,888.59 TRUE

29,335.00 TRUE

205,550.00 TRUE

319,995.00 TRUE

319,995.00 TRUE

20,835.00 TRUE
########## TRUE

TRUE
20,400.00 TRUE

26,790.00 TRUE

37,455.00 TRUE

31,845.00 TRUE
63,750.00 TRUE

42,015.00 TRUE

2,550.00 TRUE
26,220.00 TRUE

9,780.00 TRUE

25,500.00 TRUE

232,963.62 TRUE

279,080.43 TRUE

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 149/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
133,602.12 TRUE
67,685.00 TRUE

7,650.00 TRUE

264,230.43 TRUE

131,921.30 TRUE

TRUE

760,107.78 TRUE

680,808.85 TRUE

760,107.78 TRUE
639,383.74 TRUE

614,578.59 TRUE

597,348.20 TRUE

585,250.83 TRUE
562,890.83 TRUE

481,899.60 TRUE

430,598.52 TRUE

615,706.46 TRUE
520,605.71 TRUE

511,062.29 TRUE
378,580.54 TRUE

########## TRUE

824,370.24 TRUE

768,177.43 TRUE
601,502.76 TRUE

TRUE
179,040.25 TRUE

166,625.36 TRUE

160,297.60 TRUE

155,292.73 TRUE

153,797.84 TRUE

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 150/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE

153,797.84 TRUE

141,141.25 TRUE

85,295.88 TRUE
80,180.55 TRUE

76,740.88 TRUE

75,021.38 TRUE

73,955.32 TRUE
73,783.98 TRUE

72,468.35 TRUE

70,823.35 TRUE

59,011.01 TRUE

61,480.28 TRUE

145,959.22 TRUE
125,040.55 TRUE
93,538.31 TRUE

171,195.87 TRUE
125,026.32 TRUE

101,980.22 TRUE

102,496.42 TRUE

118,542.85 TRUE

231,042.21 TRUE

29,200.62 TRUE

137,428.16 TRUE
TRUE

33,105.57 TRUE

30,319.84 TRUE

29,064.57 TRUE

28,213.34 TRUE

27,955.67 TRUE

27,654.84 TRUE

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 151/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
27,216.41 TRUE
26,962.97 TRUE

23,856.34 TRUE

26,096.77 TRUE

21,048.84 TRUE

22,534.53 TRUE

42,220.84 TRUE

39,976.74 TRUE

38,652.68 TRUE
37,457.28 TRUE

37,053.41 TRUE

28,744.95 TRUE

43,054.37 TRUE
45,319.85 TRUE

44,116.35 TRUE

43,041.51 TRUE

55,323.85 TRUE
52,452.11 TRUE

50,818.62 TRUE
48,823.92 TRUE

22,821.11 TRUE

22,116.24 TRUE

26,640.21 TRUE
25,471.11 TRUE

7,984.13 TRUE
154,000.40 TRUE

120,904.00 TRUE

25,958.27 TRUE

13,133.27 TRUE

32,877.40 TRUE

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 152/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE

TRUE

########## TRUE

########## TRUE

########## TRUE

########## TRUE

158,423.84 TRUE

144,120.09 TRUE
480,500.00 TRUE

286,002.88 TRUE

405,400.00 TRUE

235,215.02 TRUE

221,215.02 TRUE

694,000.00 TRUE
382,804.60 TRUE
352,704.75 TRUE

257,401.16 TRUE
567,773.75 TRUE

276,028.07 TRUE

249,618.91 TRUE

407,897.50 TRUE

309,401.16 TRUE

407,554.75 TRUE

312,251.16 TRUE
402,804.75 TRUE

311,751.16 TRUE

492,054.75 TRUE

396,751.16 TRUE

########## TRUE

########## TRUE

########## TRUE

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 153/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE

FALSE
########## TRUE

35,924.61 TRUE

31,413.36 TRUE

82,673.75 TRUE

39,799.76 TRUE

39,799.76 TRUE

335,144.37 TRUE
269,529.37 TRUE
87,682.50 TRUE

50,933.36 TRUE

46,325.86 TRUE

144,673.75 TRUE

74,237.90 TRUE
53,537.90 TRUE

170,715.00 TRUE

88,029.44 TRUE

63,729.44 TRUE
68,291.25 TRUE

33,281.77 TRUE

96,261.25 TRUE

60,844.54 TRUE

58,204.29 TRUE

32,692.62 TRUE

29,252.62 TRUE

92,628.16 TRUE
82,028.16 TRUE

92,628.16 TRUE

166,948.16 TRUE

176,927.50 TRUE

30,969.25 TRUE

7,882.50 TRUE

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
Hal : 505
TRUE
TRUE

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 154/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
Hal : 505
TRUE
TRUE

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 155/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
Hal : 505
TRUE
TRUE

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 156/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
Hal : 505
TRUE
TRUE

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 157/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE

TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 158/160


 

5/11/2018 SNI LENGKAP 2006 - slide pdf.c om

Hal : 505

http://slide pdf.c om/re a de r/full/sni-le ngka p-2006 159/160


 