JUMLAH HARGA
NO URAIAN PEKERJAAN
PEKERJAAN (Rp)

A. PEKERJAAN PERSIAPAN / UMUM 24,734,903.21


B. PEKERJAAN TANAH 48,462,648.09
C. PEKERJAAN BETON 508,157,948.47
D. PEKERJAAN PASANGAN 26,002,450.94
E. PEKERJAAN PLESTERAN DINDING DAN LANTAI 75,081,206.67
F. PEKERJAAN INSTALASI LISTRIK 17,636,605.00
G. PEKERJAAN PENGECATAN 19,006,912.06
H. PEKERJAAN ACCESSORIES DAN LAINNYA 190,000,000.00

I. JUMLAH PEKERJAAN NKONSTRUKSI 909,082,674.43


II. PPN 10% 90,908,267.44
III. JUMLAH 999,990,941.88
IV. JUMLAH DIBULATKAN 999,990,000.00

TERBILANG :

Sembilan Ratus Sembilan Puluh Sembilan Juta Sembilan Ratus Sembilan Puluh Ribu Rupiah

Namrole, …………………………..
Pejabat Pembuat Komitmen
PERENCANAAN

M. BARRY KING HUNGAN, ST


NIP. 19810319 2011011 1 005
SATUAN KERJA : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
PEKERJAAN : PEMBANGUNAN BUNDARAN DAN TUGU
LOKASI : KECAMATAN NAMROLE, KAB. BURU SELATAN
TH. ANGGARAN : 2019
HARGA JUMLAH
NO JENIS PEKERJAAN SAT. VOLUME SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6

A. PEKERJAAN PERSIAPAN 24,734,903.21


1 Management Dan Keselamatan Kerja ( K3 ) Ls 1.00 10,375,000.00 10,375,000.00
2 Papan nama Proyek Ls 1.00 500,000.00 500,000.00
3 Bouwplank Bangunan M' 53.38 86,360.12 4,609,903.21
4 Pagar Pengaman Sementara Dari Seng Rangka Kayu Ls 1.00 9,250,000.00 9,250,000.00

B. PEKERJAAN TANAH 48,462,648.09


1 Galian Pondasi Beton Lingkaran M3 25.01 80,850.00 2,021,749.25
2 Urug tanah bekas galian M3 8.34 59,400.00 495,122.27
3 Urug Pasir Di Bawah Pondasi Beton M3 4.12 316,866.00 1,305,884.00
4 Tanah Urug Dipadatkan M3 151.94 218,394.00 33,181,731.70
5 Timbunan Pilihan M3 35.21 325,446.00 11,458,160.87

C. PEKERJAAN BETON 508,157,948.47


1 Beton Foot Plate 173 kg/m3 M3 1.68 4,935,500.00 8,291,640.00
2 Beton Selimut Pondasi 81 kg/m3 M3 13.99 4,390,100.00 61,411,791.87
3 Beton Penutup Kolam 70 kg/m3 M3 10.30 4,276,600.00 44,045,558.72
4 Beton Lengkung Penyangga 40/60 83 kg/m3 M3 17.46 4,521,700.00 78,937,668.18
5 Betong Double Ring 169 kg/m3 M3 2.76 6,937,000.00 19,135,020.80
6 Beton Ring 1 142 kg/m3 M3 4.89 5,600,100.00 27,396,361.21
7 Beton Penutup Lingkaran 1 85 kg/m3 M3 7.67 4,699,000.00 36,053,500.41
8 Beton Penutup Lingkaran 2 122 kg/m3 M3 2.27 5,740,900.00 13,015,079.57
9 Beton Kolom Praktis 15/30 83 kg/m3 M3 0.20 4,521,700.00 895,296.60
10 Beton K. 175 M3 96.48 2,147,258.25 207,168,001.92
11 Tralis Besi Pelindung Lampu, Dia 22 Mm' Kg 314.88 37,500.00 11,808,029.18

D. PEKERJAAN PASANGAN 26,002,450.94


1 Pasangan Batako Pres , Camp. 1Pc : 5Ps M2 135.81 191,469.03 26,002,450.94

E. PEKERJAAN PLESTERAN DINDING DAN LANTAI 75,081,206.67


1 Plesteran Dinding, Camp. 1Pc : 3Ps M2 89.49 71,356.84 6,385,723.16
2 Acian Dinding M2 89.49 40,183.00 3,595,976.67
3 Plesteran Beton, Camp. 1Pc : 3Ps M2 97.99 71,356.84 6,991,913.75
4 Acian Beton M2 97.99 40,183.00 3,937,339.29
5 Lantai Koral Sikat M2 166.29 325,749.12 54,170,253.80

F. PEKERJAAN INSTALASI LISTRIK 17,636,605.00


1 Instalasi titik lampu dan stop kontak Ttk 11.00 176,055.00 1,936,605.00
2 Panel Grup + MCB 25 A Unit 1.00 2,000,000.00 2,000,000.00
3 LED Flood Light 100W - IP 66 Bh 8.00 1,200,000.00 9,600,000.00
4 Philip HPL-N250W/542EA Lampu Mercury Bh 2.00 210,000.00 420,000.00
5 Pompa Celup Air Bersih 1,5 Inchi Bh 1.00 1,500,000.00 1,500,000.00
6 Fitting Gantung Lampu Mercury Bh 1.00 80,000.00 80,000.00
7 Biaya Penyambungan Listrik 2200 Watt Ls 1.00 2,100,000.00 2,100,000.00
HARGA JUMLAH
NO JENIS PEKERJAAN SAT. VOLUME SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6

G. PEKERJAAN PENGECATAN 19,006,912.06


1 Cat Anti Lumut M2 174.59 108,864.86 19,006,912.06

H. PEKERJAAN ACCESSORIES DAN LAINNYA 190,000,000.00


1 Bunga Meranti Bahan Tembaga 2.50 x 3.00 Termasuk Pemasangan Bh 1.00 165,000,000.00 165,000,000.00
2 Huruf Pada Monumen Bahan Stainlees Steel Lengkap Ls 1.00 18,000,000.00 18,000,000.00
3 Lidah Api Bahan Stainles Steel Ls 1.00 2,500,000.00 2,500,000.00
4 Pelaporan Dan Dokumentasi Ls 1.00 1,500,000.00 1,500,000.00
5 Asbuilt Drawing Ls 1.00 1,500,000.00 1,500,000.00
6 Pembersihan Akhir Ls 1.00 1,500,000.00 1,500,000.00

REKAPITULASI :
A. PEKERJAAN PERSIAPAN 24,734,903.21
B. PEKERJAAN TANAH 48,462,648.09
C. PEKERJAAN BETON 508,157,948.47
D. PEKERJAAN PASANGAN 26,002,450.94
E. PEKERJAAN PASANGAN 75,081,206.67
F. PEKERJAAN INSTALASI LISTRIK 17,636,605.00
G. PEKERJAAN PENGECATAN 19,006,912.06
H. PEKERJAAN ACCESSORIES DAN LAINNYA 190,000,000.00
● JUMLAH HARGA KONSTRUKSI FISIK 909,082,674.43

Namrole, …………………………..
Pejabat Pembuat Komitmen
PERENCANAAN

M. BARRY KING HUNGAN, ST


NIP. 19810319 2011011 1 005
DAFTAR HARGA SATUAN UPAH
PEMBANGUNAN BUNDARAN DAN TUGU

NO. URAIAN SATUAN HARGA

I SATUAN UPAH

1 Pekerja /Hari 93,000.00


2 Pembantu (Mekanik, Operator, Supir) /Hari 93,000.00
3 Tukang Batu, Kayu, Besi dan Cat /Hari 100,000.00
4 Kepala Tukang /Hari 123,000.00
5 Operator /Hari 135,000.00
6 Mandor /Hari 150,000.00
DAFTAR HARGA SATUAN BAHAN
PEMBANGUNAN BUNDARAN DAN TUGU

NO. URAIAN SATUAN HARGA

II SATUAN BAHAN
BAHAN BETON

1 Tanah urug /M3 120,450.00


2 Pasir beton / pasang /M3 235,950.00
Pasir beton / pasang Kg 323.66
3 Pasir urug /M3 215,550.00
4 Sirtu /M3 201,550.00
5 Batu Belah /M3 231,750.00
6 Batu kali /M3 332,025.00
7 Batu karang /M3 347,625.00
8 Kerikil sungai / pantai (kerikil cor) /M3 299,325.00
Kerikil sungai / pantai (kerikil cor) Kg 298.62
9 Kerikil sungai / pantai (kerikil kacang) /M3 299,325.00
10 Batu pecah 2 - 3 cm (stone crusher) /M3 574,575.00
11 Batu bata merah /Bh 2,925.00
12 Batako 10 x 12 x 27 /Bh 3,840.00
13 Semen PC @ 50 KG /Sak 80,000.00
14 Semen PC /Kg 1,600.00
15 Semen warna /Kg 4,672.00
16 Semen putih @ 40 Kg /Kg 186,880.00
17 Batu alam type alur fress ukuran 20/40 /M2 240,814.20
18 Kerikil Koral Sikat /Kg 11,680.00
19 Granite tile ukuran 60x60 cm /M2 232,578.00
20 Tegel 40/40 (polos) /M2 101,160.00
21 Tegel 40/40 (warna) /M2 132,930.00
22 Tegel 40/40 (anti slip) /M2 151,650.00
23 Tegel 30/30 (polos) /M2 101,160.00
24 Tegel 30/30 (warna) /M2 132,930.00
25 Tegel 30/30 (anti slip) /M2 151,650.00
26 Tegel 20/20 (polos) /M2 101,160.00
27 Tegel 20/20 (warna) /M2 132,930.00
28 Tegel 20/20 (anti slip) /M2 151,650.00
29 Tegel 20/25 (polos) /M2 103,950.00
30 Tegel 20/25 (warna) /M2 132,930.00
31 Air kerja /Ltr 1,500.00
NO. URAIAN SATUAN HARGA

BAHAN KAYU

1 Balok kayu kls I (semua ukuran) /M3 4,500,000.00


2 Papan kayu kls I (semua ukuran) /M3 4,500,000.00
3 Balok kayu kls II semua ukuran (makila atau sejenis) /M3 2,115,000.00
4 Papan kayu kls II semua ukuran (makila atau sejenis) /M3 2,115,000.00
5 Kayu dolken /Btg 19,350.00
6 Gypsum board tebal 9 mm ukuran 120 x 240 cm /Lbr 112,769.01
7 Tripleks tebal 4 mm ukuran 120 x 240 cm /Lbr 83,000.00
8 Tripleks lapis alluminium ukuran pintu tebal 3 mm /Lbr 135,897.30
9 Muti tipleks tebal 9 mm /Lbr 292,500.00
10 Teakwood tebal 4 mm ukuran besar /Lbr 125,000.00
11 Lies profil gypsum 10 cm /M1 32,242.50
12 Lies kayu diprofil (kayu klas II) ukuran 6 x 6 cm /M1 19,620.00
13 Pintu Lapis HPL motif Kayu Bh 2,250,000.00
14 Pintu PVC + asesoris Bh 450,000.00

BAHAN BESI DAN ATAP

1 Besi beton standart (polos) /Kg 22,595.00


2 Besi beton (ulir) /Kg 23,260.00
3 Kawat bendrat /Kg 25,200.00
4 Teralis pintu besi /Bh 760,000.00
5 Teralis jendela besi /Bh 440,000.00
6 Relling Pagar/ Reling tangga, besi hollow tinggi 50 - 100 cm /M2 1,100,000.00
7 Pemasangan rangka atap baja ringan (complite) /M2 81,576,125.22
8 Spandek 0.30 /M2 39,200.00
9 Bubungan zink plat bjls 0.25 mm /Lbr 33,000.00
10 Bubungan zink plat bjls 0.25 mm /M1 33,000.00
11 Atap zink gelombang bjls 0.20 mm /Lbr 68,000.00
12 Bubungan zink plat bjls 0.20 mm /Lbr 33,000.00
13 Bubungan zink plat bjls 0.20 mm /M1 33,000.00
14 Atap genteng prima roof butiran ukuran 80 x 80 cm /Lbr 42,500.00
15 Bubungan genteng prima roof butiran (bulat) /Bh 32,750.00
16 Nok Samping genteng prima roof butiran (siku) /Bh 38,900.00
17 Besi hollow 4 x 4 cm x 0.30 mm /M1 86,120.00
18 Truss zam ukuran 75, L = 10 cm M1 34,339.18
19 Truss zam ukuran 75, L = 6 cm M1 29,069.50
18 Reng/G-DB roof battens Btg 22,482.50
19 LED Flood Light 200W - IP 66 Bh 1,200,000.00
20 Philip HPL-N250W/542EA Lampu Mercury Bh 210,000.00
21 Pompa Celup Air Bersih WD.101 EAF 1 Inchi M1 1,500,000.00
22 Bunga Meranti Bahan Tembaga 2,5 x 3,00 Bh 165,000,000.00
23 Lidah Api Stainles Steel Bh 2,500,000.00
24 Fitting Gantung Lampu Mercury Bh 80,000.00
ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN PERSIAPAN

A. 2.2.1.9. Pembersihan 1 M2 lapangan dan perataan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 93,000.00 9,300.00
Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 16,800.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 16,800.00


E Overhead & Profit 10% x D 1,680.00
F Harga Satuan Pekerjaan (D+E) 18,480.00

A. 2.2.1.10. Pemasangan 1 M Bowplank

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 93,000.00 9,300.00
Tukang Kayu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.005 150,000.00 750.00
JUMLAH TENAGA KERJA 21,050.00
B BAHAN
Papan kayu kls II M3 0.012 2,115,000.00 25,380.00
Kayu kelas II M3 0.007 2,365,600.00 16,559.20
Paku campur Kg 0.400 38,800.00 15,520.00
JUMLAH HARGA BAHAN 57,459.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 78,509.20


E Overhead & Profit (Contoh 15 %) 10% x D 7,850.92
F Harga Satuan Pekerjaan (D+E) 86,360.12

PEKERJAAN TANAH

A. 2.3.1.2. Penggalian 1 M3 tanah biasa sedalam 2 M

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 93,000.00 83,700.00
Mandor L.04 OH 0.450 150,000.00 67,500.00
JUMLAH TENAGA KERJA 151,200.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 151,200.00


E Overhead & Profit 10% x D 15,120.00
F Harga Satuan Pekerjaan (D+E) 166,320.00
A. 2.3.1.1. Penggalian 1 M3 tanah biasa sedalam 1 M

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.750 93,000.00 69,750.00
Mandor L.04 OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 73,500.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 73,500.00


E Overhead & Profit 10% x D 7,350.00
F Harga Satuan Pekerjaan (D+E) 80,850.00

A. 2.3.1.9. Pengurugan kembali 1 M3 galian tanah

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 93,000.00 46,500.00
Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 54,000.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 54,000.00
E Overhead & Profit (Contoh 15 %) 10% x D 5,400.00
F Harga Satuan Pekerjaan (D+E) 59,400.00

A. 2.3.1.11. Pengurugan 1 M3 dengan pasir urug

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 93,000.00 27,900.00
Mandor L.04 OH 0.010 150,000.00 1,500.00
JUMLAH TENAGA KERJA 29,400.00
B BAHAN
Pasir urug m3 1.200 215,550.00 258,660.00
JUMLAH HARGA BAHAN 258,660.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 288,060.00
E Overhead & Profit (Contoh 15 %) 10% x D 28,806.00
F Harga Satuan Pekerjaan (D+E) 316,866.00

A. 2.3.1.10. Pemadatan tanah 1 M3 tanah (per 20 cm)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 93,000.00 46,500.00
Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 54,000.00
B BAHAN
Tanah urug 1.200 120,450.00 144,540.00
JUMLAH HARGA BAHAN 144,540.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 198,540.00
E Overhead & Profit (Contoh 15 %) 10% x D 19,854.00
F Harga Satuan Pekerjaan (D+E) 218,394.00
PEKERJAAN PONDASI DAN PASANGAN DINDING

A. 3.2.13. Pemasangan 1 M3 pondasi batu kali campuran 1 SP : 5 PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 93,000.00 139,500.00
Tukang Batu L.02 OH 0.750 100,000.00 75,000.00
Kepala Tukang L.03 OH 0.075 123,000.00 9,225.00
Mandor L.04 OH 0.075 150,000.00 11,250.00
JUMLAH TENAGA KERJA 234,975.00
B BAHAN
Batu belah M3 1.200 231,750.00 278,100.00
Semen portland Kg 136.000 1,600.00 217,600.00
Pasir pasang M3 0.500 235,950.00 117,975.00
JUMLAH HARGA BAHAN 613,675.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 848,650.00


E Overhead & Profit 10% x D 84,865.00
F Harga Satuan Pekerjaan (D+E) 933,515.00

A. 3.2.1.4. Pemasangan 1 M3 pondasi batu kali campuran 1 SP : 4 PP


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 93,000.00 139,500.00
Tukang Batu L.02 OH 0.750 100,000.00 75,000.00
Kepala Tukang L.03 OH 0.075 123,000.00 9,225.00
Mandor L.04 OH 0.075 150,000.00 11,250.00
JUMLAH TENAGA KERJA 234,975.00
B BAHAN
Batu belah M3 1.200 231,750.00 278,100.00
Semen portland Kg 163.000 1,600.00 260,800.00
Pasir pasang M3 0.520 235,950.00 122,694.00
JUMLAH HARGA BAHAN 661,594.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 896,569.00


E Overhead & Profit 10% x D 89,656.90
F Harga Satuan Pekerjaan (D+E) 986,225.90

A. 3.2.1.9. Pemasangan 1 M3 batu kosong (anstamping)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.780 93,000.00 72,540.00
Tukang Batu L.02 OH 0.390 100,000.00 39,000.00
Kepala Tukang L.03 OH 0.039 123,000.00 4,797.00
Mandor L.04 OH 0.039 150,000.00 5,850.00
JUMLAH TENAGA KERJA 122,187.00
B BAHAN
Batu belah M3 1.200 231,750.00 278,100.00
Pasir urug M3 0.432 231,750.00 100,116.00
JUMLAH HARGA BAHAN 378,216.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 500,403.00


E Overhead & Profit (Contoh 15 %) 10% x D 50,040.30
F Harga Satuan Pekerjaan (D+E) 550,443.30
A. 4.4.2.4. Pemasangan 1 M2 dinding batu bata merah 1/2 batu adukan 1 SP : 5 PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 93,000.00 27,900.00
Tukang Batu L.03 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 123,000.00 1,230.00
Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 41,380.00
B BAHAN
Semen portland Kg 9.680 1,600.00 15,488.00
Pasir pasang M3 0.050 235,950.00 11,797.50
Batu bata Merah Bh 70.000 2,925.00 204,750.00
JUMLAH HARGA BAHAN 232,035.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 273,415.50


E Overhead & Profit (Contoh 15%) 10% x D 27,341.55
F Harga Satuan Pekerjaan (D+E) 300,757.05

PEKERJAAN PLESTERAN DINDING

A. 4.4.2.5. 1 M2 Plesteran 1 SP : 5 PP tebal 15 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 93,000.00 27,900.00
Tukang Batu L.03 OH 0.150 100,000.00 15,000.00
Kepala Tukang L.03 OH 0.015 123,000.00 1,845.00
Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,995.00
B BAHAN
Semen portland Kg 5.184 1,600.00 8,294.40
Pasir pasang M3 0.026 235,950.00 6,134.70
JUMLAH HARGA BAHAN 14,429.10
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 61,424.10


E Overhead & Profit (Contoh 15%) 10% x D 6,142.41
F Harga Satuan Pekerjaan (D+E) 67,566.51

A. 4.4.2.3. 1 M2 Plesteran 1 SP : 3 PP tebal 15 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 93,000.00 27,900.00
Tukang Batu L.03 OH 0.150 100,000.00 15,000.00
Kepala Tukang L.03 OH 0.015 123,000.00 1,845.00
Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 46,995.00
B BAHAN
Semen portland Kg 7.780 1,600.00 12,448.00
Pasir pasang M3 0.023 235,950.00 5,426.85
JUMLAH HARGA BAHAN 17,874.85
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 64,869.85


E Overhead & Profit (Contoh 15%) 10% x D 6,486.99
F Harga Satuan Pekerjaan (D+E) 71,356.84
PEKERJAAN PENUTUP LANTAI DAN DINDING
A. 4.4.3.35. Pemasangan 1 M2 lantai keramik ukuran 40 x 40 cm polos

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 93,000.00 65,100.00
Tukang Batu L.02 OH 0.350 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.035 123,000.00 4,305.00
Mandor L.04 OH 0.035 150,000.00 5,250.00
JUMLAH TENAGA KERJA 109,655.00
B BAHAN
Lantai keramik 40 x 40 cm M2 1.100 101,160.00 111,276.00
Semen portland Kg 10.00 1,600.00 16,000.00
Pasir pasang M3 0.045 235,950.00 10,617.75
Semen warna Kg 1.500 4,672.00 7,008.00
JUMLAH HARGA BAHAN 144,901.75
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 254,556.75


E Overhead & Profit (Contoh 15%) 10% x D 25,455.68
F Harga Satuan Pekerjaan (D+E) 280,012.43

A. 4.4.3.35. Pemasangan 1 M2 lantai keramik ukuran 40 x 40 cm anti slip

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 93,000.00 65,100.00
Tukang Batu L.02 OH 0.350 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.035 123,000.00 4,305.00
Mandor L.04 OH 0.035 150,000.00 5,250.00
JUMLAH TENAGA KERJA 109,655.00
B BAHAN
Lantai keramik 40 x 40 cm M2 1.100 151,650.00 166,815.00
Semen portland Kg 10.000 1,600.00 16,000.00
Pasir pasang M3 0.045 235,950.00 10,617.75
Semen warna Kg 1.500 4,672.00 7,008.00
JUMLAH HARGA BAHAN 200,440.75
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 310,095.75


E Overhead & Profit (Contoh 15%) 10% x D 31,009.58
F Harga Satuan Pekerjaan (D+E) 341,105.33

A. 4.4.3.36. Pemasangan 1 M2 lantai keramik ukuran 20 x 20 cm anti slip

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 93,000.00 65,100.00
Tukang Batu L.02 OH 0.350 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.035 123,000.00 4,305.00
Mandor L.04 OH 0.035 150,000.00 5,250.00
JUMLAH TENAGA KERJA 109,655.00
B BAHAN
Lantai keramik 20 x 20 cm (anti slip) M2 1.100 151,650.00 166,815.00
Semen portland Kg 10.000 1,600.00 16,000.00
Pasir pasang M3 0.045 235,950.00 10,617.75
Semen warna Kg 1.620 4,672.00 7,568.64
JUMLAH HARGA BAHAN 201,001.39
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 310,656.39


E Overhead & Profit (Contoh 15%) 10% x D 31,065.64
F Harga Satuan Pekerjaan (D+E) 341,722.03
suplay an. A. 4.4.3.36. Pemasangan 1 M2 Dinding Granitile ukuran 60 x 60 cm (black)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 93,000.00 65,100.00
Tukang Batu L.02 OH 0.350 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.035 123,000.00 4,305.00
Mandor L.04 OH 0.035 150,000.00 5,250.00
JUMLAH TENAGA KERJA 109,655.00
B BAHAN
Granitile 60x60 cm M2 1.100 232,578.00 255,835.80
Semen portland Kg 11.000 1,600.00 17,600.00
Pasir pasang M3 0.045 235,950.00 10,617.75
JUMLAH HARGA BAHAN 284,053.55
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 393,708.55


E Overhead & Profit (Contoh 15%) 10% x D 39,370.86
F Harga Satuan Pekerjaan (D+E) 433,079.41

A. 4.4.3.53. Pemasangan 1 M2 dinding keramik 20 x 25 cm warna

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 93,000.00 83,700.00
Tukang Batu L.02 OH 0.450 100,000.00 45,000.00
Kepala Tukang L.03 OH 0.045 123,000.00 5,535.00
Mandor L.04 OH 0.045 150,000.00 6,750.00
JUMLAH TENAGA KERJA 140,985.00
B BAHAN
Dinding lapis keramik 20 x 25 cm M2 1.100 132,930.00 146,223.00
Semen portland Kg 9.300 1,600.00 14,880.00
Pasir pasang M3 0.018 235,950.00 4,247.10
Semen warna Kg 1.940 4,672.00 9,063.68
JUMLAH HARGA BAHAN 174,413.78
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 315,398.78


E Overhead & Profit (Contoh 15%) 10% x D 31,539.88
F Harga Satuan Pekerjaan (D+E) 346,938.66

A. 4.4.3.54. Pemasangan 1 M2 dinding keramik 20 x 25 cm polos

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 93,000.00 83,700.00
Tukang Batu L.02 OH 0.450 100,000.00 45,000.00
Kepala Tukang L.03 OH 0.045 123,000.00 5,535.00
Mandor L.04 OH 0.045 150,000.00 6,750.00
JUMLAH TENAGA KERJA 140,985.00
B BAHAN
Dinding lapis keramik 20 x 25 cm M2 1.100 103,950.00 114,345.00
Semen portland Kg 9.300 1,600.00 14,880.00
Pasir pasang M3 0.018 235,950.00 4,247.10
Semen warna Kg 1.940 4,672.00 9,063.68
JUMLAH HARGA BAHAN 142,535.78
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 283,520.78


E Overhead & Profit (Contoh 15%) 10% x D 28,352.08
F Harga Satuan Pekerjaan (D+E) 311,872.86
P. 01.1. Pemasangan 1 M 2 batu alam type alur fress ukuran 20 x 40 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.240 93,000.00 22,320.00
Tukang Batu L.02 OH 0.120 100,000.00 12,000.00
Kepala Tukang L.03 OH 0.010 123,000.00 1,230.00
Mandor L.04 OH 0.012 150,000.00 1,800.00
JUMLAH TENAGA KERJA 37,350.00
B BAHAN
Batu alam type alur fress M2 1.100 101,160.00 111,276.00
Semen portland Kg 10.000 1,600.00 16,000.00
Pasir pasang M3 0.05 235,950.00 11,797.50
JUMLAH HARGA BAHAN 139,073.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 176,423.50


E Overhead & Profit (Contoh 15%) 10% x D 17,642.35
F Harga Satuan Pekerjaan (D+E) 194,065.85

P. 01.1. Pemasangan 1 M 2 batu alam type Marmu Bakar ukuran 20 x 25 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.240 93,000.00 22,320.00
Tukang Batu L.02 OH 0.120 100,000.00 12,000.00
Kepala Tukang L.03 OH 0.010 123,000.00 1,230.00
Mandor L.04 OH 0.012 150,000.00 1,800.00
JUMLAH TENAGA KERJA 37,350.00
B BAHAN
Batu alam type Marmu Bakar M2 1.100 11,680.00 12,848.00
Semen portland Kg 10.000 1,600.00 16,000.00
Pasir pasang M3 0.05 235,950.00 11,797.50
JUMLAH HARGA BAHAN 40,645.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,995.50


E Overhead & Profit (Contoh 15%) 10% x D 7,799.55
F Harga Satuan Pekerjaan (D+E) 85,795.05

PEKERJAAN BETON BERTULANG

B.03. Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA Manual
Pekerja L.01 OH 1.650 93,000.00 153,450.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 123,000.00 3,444.00
Mandor L.04 OH 0.083 150,000.00 12,450.00
JUMLAH TENAGA KERJA 196,844.00
B BAHAN
Semen portland Kg 413.000 1,600.00 660,800.00
Pasir beton Kg 681.000 323.66 220,414.20
kerikil cor Kg 1,021.000 298.62 304,892.80
Air Ltr 215.000 1,500.00 322,500.00
JUMLAH HARGA BAHAN 1,508,607.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,705,451.00


E Overhead & Profit (Contoh 15 %) 10% x D 170,545.10
F Harga Satuan Pekerjaan (D+E) 1,875,996.10
B.05. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 93,000.00 153,450.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 123,000.00 3,444.00
Mandor L.04 OH 0.083 150,000.00 12,450.00
JUMLAH TENAGA KERJA 196,844.00
B BAHAN
Semen portland Kg 406.000 1,600.00 649,600.00
Pasir beton Kg 684.000 323.66 221,385.19
kerikil cor Kg 1,026.000 298.62 306,385.91
Air Ltr 215.000 1,500.00 322,500.00
JUMLAH HARGA BAHAN 1,499,871.10
C PERALATAN
Concrete mixer E.8 Hari 0.7179 69,249.00 49,713.86
JUMLAH HARGA ALAT 49,713.86

D Jumlah (A+B+C) 1,746,428.95


E Overhead & Profit (Contoh 15 %) 10% x D 174,642.90
F Harga Satuan Pekerjaan (D+E) 1,921,071.85
B.05. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 93,000.00 111,600.00
Tukang Batu L.02 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 123,000.00 2,460.00
Mandor L.04 OH 0.060 150,000.00 9,000.00
JUMLAH TENAGA KERJA 143,060.00
B BAHAN
Semen portland Kg 230.000 1,600.00 368,000.00
Pasir beton Kg 893.000 323.66 289,030.66
Air Ltr 200.000 1,500.00 300,000.00
JUMLAH HARGA BAHAN 957,030.66
C PERALATAN
Concrete mixer E.8 Hari 0.7179 69,249.00 49,713.86
JUMLAH HARGA ALAT 49,713.86

D Jumlah (A+B+C) 1,149,804.52


E Overhead & Profit (Contoh 15 %) 10% x D 114,980.45
F Harga Satuan Pekerjaan (D+E) 1,264,784.97

A. 4.1.1.17. Pembesian 10 kg dengan besi polos

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 93,000.00 6,510.00
Tukang Besi L.02 OH 0.070 100,000.00 7,000.00
Kepala Tukang L.03 OH 0.007 123,000.00 861.00
Mandor L.04 OH 0.004 150,000.00 600.00
JUMLAH TENAGA KERJA 14,971.00
B BAHAN
Besi beton (polos) Kg 10.500 22,595.00 237,247.50
Kawat beton Kg 0.150 25,200.00 3,780.00
JUMLAH HARGA BAHAN 241,027.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 255,998.50


E Overhead & Profit (Contoh 15 %) 10% x D 25,599.85
F Harga Satuan Pekerjaan (D+E) 281,598.35
G 1 Kg besi polos 28,159.84
A. 3.4.4 B.34 Pemasangan 1 M2 bekisting untuk sloof dengan papan ukuran 3/20

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 93,000.00 61,380.00
Tukang Kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala Tukang L.03 OH 0.033 123,000.00 4,059.00
Mandor L.04 OH 0.033 150,000.00 4,950.00
JUMLAH TENAGA KERJA 103,389.00
B BAHAN
Papan 3/20 kayu kls II M3 0.03 2,115,000.00 63,450.00
Balok kayu 5/7 cm M54 M3 0.011 2,115,000.00 23,265.00
Paku campur M.95 Kg 0.400 38,800.00 15,520.00
JUMLAH HARGA BAHAN 102,235.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 205,624.00


E Overhead & Profit (Contoh 15 %) 10% x D 20,562.40
F Harga Satuan Pekerjaan (D+E) 226,186.40

A. 3.4.4 B.30 Pemasangan 1 M2 bekisting untuk kolom dengan papan ukuran 3/20

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 93,000.00 61,380.00
Tukang Kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala Tukang L.03 OH 0.033 123,000.00 4,059.00
Mandor L.04 OH 0.033 150,000.00 4,950.00
JUMLAH TENAGA KERJA 103,389.00
B BAHAN
Paku campur Kg 0.400 38,800.00 15,520.00
Balok kayu kelas II M3 0.017 2,115,000.00 35,955.00
Papan 3/20 kayu kls II M3 0.040 2,115,000.00 84,600.00
JUMLAH HARGA BAHAN 136,075.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 239,464.00


E Overhead & Profit (Contoh 15 %) 10% x D 23,946.40
F Harga Satuan Pekerjaan (D+E) 263,410.40

A.4.1.1.23. Pemasangan 1 M2 bekisting untuk balok

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 93,000.00 61,380.00
Tukang Kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala Tukang L.03 OH 0.033 123,000.00 4,059.00
Mandor L.04 OH 0.033 150,000.00 4,950.00

JUMLAH TENAGA KERJA 103,389.00
B BAHAN
Paku campur Kg 0.250 38,800.00 9,700.00
Balok kayu kelas II M3 0.017 2,115,000.00 35,955.00
Papan 3/20 kayu kls II M3 0.040 2,115,000.00 84,600.00
JUMLAH HARGA BAHAN 130,255.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 233,644.00
E Overhead & Profit (Contoh 15 %) 10% x D 23,364.40
F Harga Satuan Pekerjaan (D+E) 257,008.40
B. 4.1.1.34. Pemasangan 1 M 2 bekisting untuk pondasi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 93,000.00 48,360.00
Tukang Kayu L.02 OH 0.260 100,000.00 26,000.00
Kepala Tukang L.03 OH 0.026 123,000.00 3,198.00
Mandor L.04 OH 0.026 150,000.00 3,900.00
JUMLAH TENAGA KERJA 81,458.00
B BAHAN
Balok kayu kelas II M3 0.011 2,115,000.00 23,265.00
Papan 3/20 kayu kls II M3 0.024 2,115,000.00 50,760.00
Paku campur Kg 0.400 38,800.00 15,520.00
JUMLAH HARGA BAHAN 89,545.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 171,003.00


E Overhead & Profit (Contoh 15 %) 10% x D 17,100.30
F Harga Satuan Pekerjaan (D+E) 188,103.30

B. 22. Pemasangan 1 M2 bekisting plat dengan papan ukuran 3/20 cm (dengan perancah)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 93,000.00 61,380.00
Tukang Kayu L.06 OH 0.330 100,000.00 33,000.00
Kepala Tukang L.05 OH 0.033 123,000.00 4,059.00
Mandor L.15 OH 0.033 150,000.00 4,950.00
JUMLAH TENAGA KERJA 103,389.00
B 

BAHAN
Papan 3/20 kayu kls II M3 0.040 2,115,000.00 84,600.00
Balok kayu kelas II M3 0.020 2,115,000.00 42,300.00
Perancah balok 5/7 M3 0.049 2,115,000.00 103,635.00
Paku campur Kg 0.400 38,800.00 15,520.00
JUMLAH HARGA BAHAN 246,055.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 349,444.00
E Overhead & Profit (Contoh 15 %) 10% x D 34,944.40
F Harga Satuan Pekerjaan (D+E) 384,388.40

1 M3 PEKERJAAN PONDASI/DINDING
Kg/M3 Beton
Pembesian Bakesting (m3) Jumlah Jumlah Total
Beton ad. K175
81 2,280,946.64 1,921,071.85 188,103.30 4,390,121.78 4,390,100.00
168 4,730,852.28 1,921,071.85 188,103.30 6,840,027.43 6,840,000.00
200 5,631,967.00 1,921,071.85 188,103.30 7,741,142.15 7,741,100.00

1 M3 PEKERJAAN SLOOF

Kg/M3 Beton
Pembesian Bakesting (m3) Jumlah Jumlah Total
Beton ad. K275
100 2,815,983.50 1,921,071.85 226,186.40 4,963,241.75 4,963,200.00
200 5,631,967.00 1,921,071.85 226,186.40 7,779,225.25 7,779,200.00
205 5,772,766.18 1,921,071.85 226,186.40 7,920,024.42 7,920,000.00
1 M3 PEKERJAAN KOLOM

Kg/M3 Beton
Pembesian Bakesting (m3) Jumlah Jumlah Total
Beton ad. K275
85 2,393,585.98 1,921,071.85 263,410.40 4,578,068.22 4,578,000.00
95 2,675,184.33 1,921,071.85 263,410.40 4,859,666.57 4,859,600.00
121 3,407,340.04 1,921,071.85 263,410.40 5,591,822.28 5,591,800.00
145 4,083,176.08 1,921,071.85 263,410.40 6,267,658.32 6,267,600.00
147 4,139,495.75 1,921,071.85 263,410.40 6,323,977.99 6,323,900.00
83 2,337,266.31 1,921,071.85 263,410.40 4,521,748.55 4,521,700.00
187 5,265,889.15 1,921,071.85 263,410.40 7,450,371.39 7,450,300.00
216 6,082,524.36 1,921,071.85 263,410.40 8,267,006.61 8,267,000.00
203 5,716,446.51 1,921,071.85 263,410.40 7,900,928.75 7,900,900.00
236 6,645,721.06 1,921,071.85 263,410.40 8,830,203.31 8,830,200.00
250 7,039,958.75 1,921,071.85 263,410.40 9,224,441.00 9,224,400.00

1 M3 PEKERJAAN BALOK

Kg/M3 Beton
Pembesian Bakesting (m3) Jumlah Jumlah Total
Beton ad. K275
85 2,393,585.98 1,921,071.85 257,008.40 4,571,666.22 4,571,600.00
95 2,675,184.33 1,921,071.85 257,008.40 4,853,264.57 4,853,200.00
121 3,407,340.04 1,921,071.85 257,008.40 5,585,420.28 5,585,400.00
145 4,083,176.08 1,921,071.85 257,008.40 6,261,256.32 6,261,200.00
155 4,364,774.43 1,921,071.85 257,008.40 6,542,854.67 6,542,800.00
169 4,759,012.12 1,921,071.85 257,008.40 6,937,092.36 6,937,000.00
175 4,927,971.13 1,921,071.85 257,008.40 7,106,051.37 7,106,000.00
200 5,631,967.00 1,921,071.85 257,008.40 7,810,047.25 7,810,000.00

1 M3 PEKERJAAN PLAT

Kg/M3 Beton
Pembesian Bakesting (m3) Jumlah Jumlah Total
Beton ad. K275
50 1,407,991.75 1,921,071.85 384,388.40 3,713,452.00 3,713,400.00
70 1,971,188.45 1,921,071.85 384,388.40 4,276,648.70 4,276,600.00
85 2,393,585.98 1,921,071.85 384,388.40 4,699,046.22 4,699,000.00
110 3,097,581.85 1,921,071.85 384,388.40 5,403,042.10 5,403,000.00
115 3,238,381.03 1,921,071.85 384,388.40 5,543,841.27 5,543,800.00
117 3,294,700.70 1,921,071.85 384,388.40 5,600,160.94 5,600,100.00
122 3,435,499.87 1,921,071.85 384,388.40 5,740,960.12 5,740,900.00
200 5,631,967.00 1,921,071.85 384,388.40 7,937,427.25 7,937,400.00

1 M3 PEKERJAAN FOOT PLAT

Kg/M3 Beton
Pembesian Bakesting (m3) Jumlah Jumlah Total
Beton ad. K300
50 1,407,991.75 1,875,996.10 384,388.40 3,668,376.25 3,668,300.00
95 2,675,184.33 1,875,996.10 384,388.40 4,935,568.82 4,935,500.00
100 2,815,983.50 1,921,071.85 384,388.40 5,121,443.75 5,121,400.00
110 3,097,581.85 1,921,071.85 384,388.40 5,403,042.10 5,403,000.00
115 3,238,381.03 1,875,996.10 384,388.40 5,498,765.52 5,498,700.00
161 4,533,733.44 1,921,071.85 384,388.40 6,839,193.68 6,839,100.00
154 4,336,614.59 1,875,996.10 384,388.40 6,596,999.09 6,596,900.00
168 4,730,852.28 1,875,996.10 263,410.40 6,870,258.78 6,870,200.00
PEKERJAAN PENGECATAN

An. 6. 14. (SNI 2838), Pengecatan 1 M2 tembok luar/dalam dan plafond baru
(1 lapis plamir, 1 lapis dasar, 2 lapis cat penutup) cat metrolite

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 93,000.00 1,860.00
Tukang Cat L.02 OH 0.063 100,000.00 6,300.00
Kepala Tukang L.03 OH 0.006 123,000.00 774.90
Mandor L.04 OH 0.003 150,000.00 375.00
JUMLAH TENAGA KERJA 9,309.90
B BAHAN
Plamir tembok Kg 0.250 16,500.00 4,125.00
Cat dasar tembok Kg 0.100 21,300.00 2,130.00
Cat penutup 2 kali (cat metrolite) Kg 0.260 56,500.00 14,690.00
JUMLAH HARGA BAHAN 20,945.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 30,254.90


E Overhead & Profit (Contoh 15%) 10% x D 3,025.49
F Harga Satuan Pekerjaan (D+E) 33,280.39

An. 6. 9. (SNI 2836), 1 M2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup) cat glotex

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 93,000.00 6,510.00
Tukang Cat L.02 OH 0.105 100,000.00 10,500.00
Kepala Tukang L.03 OH 0.004 123,000.00 492.00
Mandor L.04 OH 0.003 150,000.00 375.00
JUMLAH TENAGA KERJA 17,877.00
B BAHAN
Mennie kayu Kg 0.200 24,350.00 4,870.00
Cat dasar kayu Kg 0.170 21,500.00 3,655.00
Cat penutup 3 kali (cat glotex) Kg 0.350 53,500.00 18,725.00
JUMLAH HARGA BAHAN 27,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 45,127.00


E Overhead & Profit (Contoh 15%) 10% x D 4,512.70
F Harga Satuan Pekerjaan (D+E) 49,639.70

A. 4.7.4.14. Pengecatan 1 M2 batu alam

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 93,000.00 1,860.00
Tukang Cat L.02 OH 0.063 100,000.00 6,300.00
Kepala Tukang L.03 OH 0.006 123,000.00 774.90
Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 9,384.90
B BAHAN
Minyak cat batu alam Ltr 0.600 25,750.00 15,450.00
Kuas sapu 3" bh 0.200 15,000.00 3,000.00
JUMLAH HARGA BAHAN 18,450.00

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,834.90


E Overhead & Profit (Contoh 15%) 10% x D 2,783.49
F Harga Satuan Pekerjaan (D+E) 30,618.39
A. 4.7.1. Pemakaian waterproofing (MU) 1,8 M2 permukaan beton/dinding

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2500 93,000.00 23,250.00
Tukang Cat L.02 OH 0.0250 100,000.00 2,500.00
Kepala Tukang L.03 OH 0.0225 123,000.00 2,767.50
Mandor L.04 OH 0.0075 150,000.00 1,125.00
JUMLAH TENAGA KERJA 29,642.50
B BAHAN
Waterproofing MU Kg 3.300 45,000.00 148,500.00
JUMLAH HARGA BAHAN 148,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 178,142.50


E Overhead & Profit (Contoh 15%) 10% x D 17,814.25
F Harga Satuan Pekerjaan (D+E) 195,956.75
G Untuk 1 M2 Waterproofing 108,864.86

An. 6 .27 (SNI 2837), Pekerjaan 1 M2 acian permukaan dinding dan beton

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.200 93,000.00 18,600.00
Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
Kepala Tukang L.03 OH 0.010 123,000.00 1,230.00
Mandor L.04 OH 0.010 150,000.00 1,500.00
JUMLAH TENAGA KERJA 31,330.00
B BAHAN
Semen portland Kg 3.250 1,600.00 5,200.00
JUMLAH HARGA BAHAN 5,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 36,530.00
E Biaya tidak langsung (mak 15%) 10% x D 3,653.00
F Jumlah (D+E) 40,183.00

A. 4.4.2.4. Pemasangan 1 M², Dinding Batako Press 1/2 Batu Adukan 1SP : 5PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 0.300 93,000.00 27,900.00
2 Tukang Batu L.02 OH 0.100 100,000.00 10,000.00
3 Kepala Tukang L.03 OH 0.010 123,000.00 1,230.00
4 Mandor L.04 OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 41,380.00
B BAHAN
1 Batako Press 10x12x27 Bh 31.000 3,840.00 119,040.00
2 Semen ( PC ) Kg 4.840 1,600.00 7,744.00
3 Pasir Pasang M3 0.025 235,950.00 5,898.75
JUMLAH HARGA BAHAN 132,682.75
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 174,062.75


E Overhead & Profit (Contoh 15%) 10% x D 17,406.28
F Harga Satuan Pekerjaan (D+E) 191,469.03
An. 6 .27 (SNI 2837), Pekerjaan 1 M 2 Pasang Lantai Koral Sikat

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.620 93,000.00 57,660.00
Tukang Batu L.02 OH 0.350 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.035 123,000.00 4,305.00
Mandor L.04 OH 0.030 150,000.00 4,500.00
JUMLAH TENAGA KERJA 101,465.00
B BAHAN
Koral Sikat Kg 16.667 11,680.00 194,670.56
Semen portland Kg 0.235 1,600.00 376.00
Pasir Pasang M3 0.035 323.66 11.33
JUMLAH HARGA BAHAN 194,670.56
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 296,135.56
E Biaya tidak langsung (mak 15%) 10% x D 29,613.56
F Jumlah (D+E) 325,749.12

A. 2.3.1.10. Pemadatan Sirtu 1 M3 (per 20 cm)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 93,000.00 46,500.00
Mandor L.04 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 54,000.00
B BAHAN
Sirtu 1.200 201,550.00 241,860.00
JUMLAH HARGA BAHAN 241,860.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 295,860.00
E Overhead & Profit (Contoh 15 %) 10% x D 29,586.00
F Harga Satuan Pekerjaan (D+E) 325,446.00