JADWAL PELAKSANAAN PEKERJAAN

Pekerjaan : Review Rasionalisasi Jaringan Pos Hidrologi WS Sesayap


Waktu Pelaksanaan : 240 hari kalender
No. Kontrak :-
Tanggal :-
Tahun Anggaran : 2021 7 7 7 9 7 7 7 9 7 7 7 9 7 7 7 9 7 7 7 9 7 7 7 9 7 7 7 9 7 7 7 9 240

Periode
Bulan I Bulan II Bulan III Bulan IV Bulan V Bulan VI Bulan VII Bulan VIII
NO URAIAN PEKERJAAN 25 Feb - 26 Mar 27 Mar - 25 Apr 26 Apr - 25 May 26 May - 24 Jun 25 Jun - 24 Jul 25 Jul - 23 Aug 30 Aug - 22 Sep 23 Sep - 22 Okt KET
25-Feb 04-Mar 11-Mar 18-Mar 27-Mar 03-Apr 10-Apr 17-Apr 26-Apr 03-May 10-May 17-May 26-May 02-Jun 09-Jun 16-Jun 25-Jun 02-Jul 09-Jul 16-Jul 25-Jul 01-Aug 08-Aug 15-Aug 24-Aug 31-Aug 07-Sep 14-Sep 23-Sep 30-Sep 07-Oct 14-Oct

03-Mar 10-Mar 17-Mar 26-Mar 02-Apr 09-Apr 16-Apr 25-Apr 02-May 09-May 16-May 25-May 01-Jun 08-Jun 15-Jun 24-Jun 01-Jul 08-Jul 15-Jul 24-Jul 31-Jul 07-Aug 14-Aug 23-Aug 30-Aug 06-Sep 13-Sep 22-Sep 29-Sep 06-Oct 13-Oct 22-Oct

I. PEKERJAAN PERSIAPAN 6.66

1 Mobilisasi Personil & Alat 1.12 0.56 0.56

2 Koordinasi & Administrasi 1.68 0.84 0.84

3 Pengumpulan Data Sekunder & Studi Terdahulu 3.86 0.64 0.64 0.64 0.64 0.64 0.64

-Peta jaringan pos hidrologi


-Data Hidrologi dari seluruh pos di lokasi studi
-Peta infrastruktur sumber daya air yang sudah ada
-Peta wilayah sungai
-Peta administrasi
-Pola dan Rencana pengelolaan sumber daya air
-Rencana Tata Ruang Wilayah
-Peta rawan banjir dan kekeringan
-Data sosial ekonomi dari Badan Pusat Statistik
-data DEM dari BIG
-Studi Rasionalisasi Jaringan Pos Hidrologi WS. Sesayap Th. 2015

II. KEGIATAN LAPANGAN 14.81

1 Peninjauan titik koordinat pos Hidrologi yang sudah ada 7.86 1.97 1.97 1.97 1.97

2 Peninjauan kondisi dan peralatan pos Hidrologi 6.95 1.74 1.74 1.74 1.74

III. ANALISIS DAN EVALUASI SISTEM HIDROLOGI 32.21

1 Rasionalisasi Pos Curah Hujan 12.38 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24 0.00

2 Rasionalisasi Pos Duga Air 11.12 1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11

3 Rasionalisasi Pos Klimatologi 8.71 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87

IV. HASIL ANALISA RASIONALISASI 25.98

-Survai lokasi baru/lokasi yang diusulkan 5.22 1.31 1.31 1.31 1.31

-Pengolahan/pembuatan peta 6.32 1.58 1.58 1.58 1.58

-Perencanaan bangunan pos hidrologi 8.31 2.08 2.08 2.08 2.08

-Perhitungan RAB 6.13 1.53 1.53 1.53 1.53

V. PENYUSUNAN LAPORAN 12.56

1 Laporan Pendahuluan 2.08 2.08

2 Laporan Bulanan 5.47 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68

3 Laporan Antara 2.28 2.28

4 Laporan Akhir 2.73 2.73

VI. DISKUSI 7.78

1 Laporan Pendahuluan 2.16 2.16

2 Laporan Antara 2.34 2.34

3 Laporan Akhir 3.28 3.28

Total 100.00
Akumulasi Bobot Rencana (%) 1.40 0.84 0.64 1.33 4.88 0.64 0.64 1.33 3.70 3.70 3.70 4.39 3.22 3.22 3.22 6.24 3.22 3.22 3.22 3.90 3.22 5.50 4.96 5.65 4.96 4.96 1.53 2.22 1.53 1.53 3.28 3.97
Bobot Realisasi 1.40 2.24 2.88 4.21 9.09 9.74 10.38 11.71 15.41 19.11 22.82 27.20 30.42 33.64 36.86 43.11 46.33 49.55 52.77 56.68 59.90 65.40 70.36 76.01 80.97 85.93 87.47 89.68 91.21 92.75 96.03 100.00
Akumulasi Bobot Realisasi
Deviasi