Bouwsoom Rp 1,443,006,017.33
PPN 10 % Rp 144,300,601.73
Jumlah Animingsom Rp 1,587,306,619.06
Dibulatkan Rp 1,587,306,000.00
Terbilang : Satu Miliar Lima Ratus Delapan Puluh Tujuh Juta Rupiah.
DURASI : 20 MINGGU
BOBOT MINGGU KE
NO ITEM PEKERJAAN HARGA DUR.
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 PEKERJAAN PERSIAPAN Rp 3,416,782.5 0.237 1 0.24
2 PEKERJAAN TANAH Rp 9,695,767.5 0.672 1 0.67
3 PEKERJAAN PONDASI Rp 39,650,515.8 2.748 3 0.92 0.92 0.92
4 PEKERJAAN BETON Rp 158,005,603.1 10.950 12 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91
5 PEKERJAAN BESI DAN ALUMUNIUM Rp 18,212,486.0 1.262 2 0.63 0.63
6 PEKERJAAN PASANGAN DINDING Rp 116,915,354.9 8.102 7 1.16 1.16 1.16 1.16 1.16 1.16 1.16
7 PEKERJAAN PLESTERAN Rp 160,968,475.7 11.155 10 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12
8 PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 90,490,844.6 6.271 6 1.05 1.05 1.05 1.05 1.05 1.05
9 PEKERJAAN INSTALASI LISTRIK Rp 22,207,500.0 1.539 1 1.54
10 PEKERJAAN LAGIT-LANGIT ( PLAFOND) Rp 21,124,292.3 1.464 2 0.73 0.73
11 PEKERJAAN PENUTUP ATAP Rp 8,755,548.2 0.607 1 0.61
12 PEKERJAAN KAYU Rp 628,697,427.1 43.569 14 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11 3.11
13 PEKERJAAN KUNCI DAN KACA Rp 5,187,877.2 0.360 1 0.36
14 PEKERJAAN PENGECATAN Rp 131,983,987.9 9.146 7 1.31 1.31 1.31 1.31 1.31 1.31 1.31
15 PEKERJAAN SANITASI Rp 27,693,554.5 1.919 3 0.64 0.64 0.64
JUMLAH Rp 1,443,006,017.3 100.000
Bobot Komulatif Pekerjaan Tiap Minggu 0.24 1.59 2.46 3.62 5.18 6.30 7.34 7.95 8.07 8.98 8.13 7.49 7.49 6.45 5.53 4.42 3.75 3.11 1.54 0.36
Rencana Penyelesaian Terhadap Pekerjaan 0.24 1.82 4.28 7.90 13.08 19.38 26.72 34.67 42.75 51.72 59.85 67.35 74.84 81.28 86.82 91.24 94.99 98.10 99.64 100.00
Penyelesaian Terhadap Pekerjaan
DEVIASI : TERLAMBAT(-)/MENDAHULUI (+)
BOBOT
67.35
70.00
59.85
60.00 51.72
50.00 42.75
40.00 34.67
26.72
30.00
19.38
20.00 13.08
7.90
10.00 1.82 4.28
0.24
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Bobot Komulatif Pekerjaan Tiap Minggu 0.37 1.67 2.40 3.96 5.16 6.50 7.09 7.97 8.28 8.61 8.61 7.70 6.77 5.89 5.89 4.65 3.31 3.31 1.47 0.41
Rencana Penyelesaian Terhadap Pekerjaan 0.37 2.04 4.43 8.40 13.56 20.06 27.14 35.11 43.39 51.99 60.60 68.30 75.07 80.96 86.85 91.50 94.81 98.12 99.59 100.00
Penyelesaian Terhadap Pekerjaan
DEVIASI : TERLAMBAT(-)/MENDAHULUI (+)
I.2 1 m' 1 M' Pagar sementara dari seng gelombang tinggi 2 meter
Bahan
1.2500 Btg Kayu dolken Ø 8-10 / 400 cm @Rp. 42,000.00 = Rp. 52,500.00
2.5000 Kg Semen PC ( Portland Cement ) 4 @Rp. 1,900.00 = Rp. 4,750.00
0.0050 M3 Pasir pasang (kaliworo) @Rp. 147,000.00 = Rp. 735.00
0.0090 M3 Koral Beton @Rp. 260,000.00 = Rp. 2,340.00
1.2000 Lbr Seng BJLS 0,2 gelombang P = 1 @Rp. 43,000.00 = Rp. 51,600.00
0.0600 Kg Paku usuk @Rp. 18,000.00 = Rp. 1,080.00
0.4500 Kg Cat Meni Besi "altex" @Rp. 28,000.00 = Rp. 12,600.00
0.0250 M3 Kayu tahun/ lanan @Rp. 3,675,000.00 = Rp. 91,875.00
Rp. 217,480.00
Tenaga
0.4000 Oh Pekerja @Rp. 45,000.00 = Rp. 18,000.00
0.2000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,150.00
0.0200 Oh Mandor @Rp. 60,000.00 = Rp. 1,200.00
Rp. 31,350.00
I.4 1 m2 1 M2 Pembuatan bak adukan dari kayu tahun ukuran (40 x 50 x 20) cm
Bahan
0.0360 M3 Papan 3/20 kayu tahun @Rp. 3,675,000.00 = Rp. 132,300.00
0.0800 Kg Paku usuk @Rp. 14,000.00 = Rp. 1,120.00
0.0105 M3 Kayu 5/7 kayu tahun @Rp. 3,675,000.00 = Rp. 38,587.50
Rp. 172,007.50
Tenaga
0.3000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 16,500.00
0.0015 Oh Mandor @Rp. 60,000.00 = Rp. 90.00
Rp. 188,597.50
III.8 1 m3 Memasang pondasi siklop 60% beton campuran 1 PC : 3 PB : 3 KR dan 40% batu belah
Bahan
0.4800 m3 Batu belah 15 cm/20 cm @Rp. 195,000.00 = Rp. 93,600.00
194.0000 kg Portl'and Cement @Rp. 1,900.00 = Rp. 368,600.00
0.3120 m3 Pasir Beton @Rp. 157,500.00 = Rp. 49,140.00
0.4680 m3 Koral/Batu Pecah @Rp. 260,000.00 = Rp. 121,680.00
126.0000 kg Besi beton @Rp. 11,000.00 = Rp. 1,386,000.00
1.8000 kg Kawat Beton @Rp. 16,000.00 = Rp. 28,800.00
Rp. 2,047,820.00
Tenaga
3.0000 Oh Pekerja @Rp. 45,000.00 = Rp. 135,000.00
0.8500 Oh Tukang batu @Rp. 55,000.00 = Rp. 46,750.00
0.0850 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 4,887.50
0.1500 Oh Mandor @Rp. 60,000.00 = Rp. 9,000.00
Rp. 195,637.50
IV.1 1 m3 Membuat beton mutu F'c = 7,4 Mpa (K100), slump (12+2) cm, w/c= 0.87
Bahan
247.0000 kg Semen portland @Rp. 1,900.00 = Rp. 469,300.00
869.0000 kg Pasir beton @Rp. 112.50 = Rp. 97,762.50
999.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 192,400.00
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 974,462.50
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.2 1 m3 Membuat beton mutu F'c = 9,8 Mpa (K125), slump (12+2) cm, w/c= 0.78
Bahan
276.0000 kg Semen portland @Rp. 1,900.00 = Rp. 524,400.00
828.0000 kg Pasir beton @Rp. 112.50 = Rp. 93,150.00
1,012.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 194,903.70
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,027,453.70
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.3 1 m3 Membuat beton mutu F'c = 12,2 Mpa (K150), slump (12+2) cm, w/c= 0.72
Bahan
299.0000 kg Semen portland @Rp. 1,900.00 = Rp. 568,100.00
799.0000 kg Pasir beton @Rp. 112.50 = Rp. 89,887.50
1,017.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 195,866.67
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,068,854.17
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.4 1 m3 Membuat beton mutu F'c = 7,4 Mpa (K100), slump (3-6) cm, w/c= 0.87
Bahan
230.0000 kg Semen portland @Rp. 1,900.00 = Rp. 437,000.00
893.0000 kg Pasir beton @Rp. 112.50 = Rp. 100,462.50
1,027.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 197,792.59
200.0000 ltr Air @Rp. 1,000.00 = Rp. 200,000.00
Rp. 935,255.09
Tenaga
1.2000 Oh Pekerja @Rp. 45,000.00 = Rp. 54,000.00
0.2000 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.0600 Oh Mandor @Rp. 60,000.00 = Rp. 3,600.00
Rp. 69,750.00
IV.5 1 m3 Membuat beton mutu F'c = 14,5 Mpa (K175), slump (12 + 2) cm, w/c= 0.66
Bahan
326.0000 kg Semen portland @Rp. 1,900.00 = Rp. 619,400.00
760.0000 kg Pasir beton @Rp. 112.50 = Rp. 85,500.00
1,029.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 198,177.78
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,118,077.78
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.6 1 m3 Membuat beton mutu F'c = 16,9 Mpa (K200), slump (12 + 2) cm, w/c= 0.61
Bahan
352.0000 kg Semen portland @Rp. 1,900.00 = Rp. 668,800.00
731.0000 kg Pasir beton @Rp. 112.50 = Rp. 82,237.50
1,031.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 198,562.96
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,164,600.46
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.7 1 m3 Membuat beton mutu F'c = 19,3 Mpa (K225), slump (12 + 2) cm, w/c= 0.58
Bahan
371.0000 kg Semen portland @Rp. 1,900.00 = Rp. 704,900.00
698.0000 kg Pasir beton @Rp. 112.50 = Rp. 78,525.00
1,047.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 201,644.44
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,200,069.44
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.8 1 m3 Membuat beton mutu F'c = 21.7 Mpa (K250), slump (12+2) cm, w/c= 0.56
Bahan
384.0000 kg Semen portland @Rp. 1,900.00 = Rp. 729,600.00
692.0000 kg Pasir beton @Rp. 112.50 = Rp. 77,850.00
1,039.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 200,103.70
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,222,553.70
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.9 1 m3 Membuat beton mutu F'c = 24.0 Mpa (K275), slump (12+2) cm, w/c= 0.53
Bahan
406.0000 kg Semen portland @Rp. 1,900.00 = Rp. 771,400.00
684.0000 kg Pasir beton @Rp. 112.50 = Rp. 76,950.00
1,026.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 197,600.00
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,260,950.00
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.10 1 m3 Membuat beton mutu F'c = 26.4 Mpa (K300), slump (12+2) cm, w/c= 0.52
Bahan
413.0000 kg Semen portland @Rp. 1,900.00 = Rp. 784,700.00
681.0000 kg Pasir beton @Rp. 112.50 = Rp. 76,612.50
1,021.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 196,637.04
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,272,949.54
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.11 1 m3 Membuat beton mutu F'c = 28.8 Mpa (K325), slump (12+2) cm, w/c= 0.49
Bahan
439.0000 kg Semen portland @Rp. 1,900.00 = Rp. 834,100.00
670.0000 kg Pasir beton @Rp. 112.50 = Rp. 75,375.00
1,006.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 193,748.15
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,318,223.15
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.12 1 m3 Membuat beton mutu F'c = 31.2 Mpa (K350), slump (12+2) cm, w/c= 0.48
Bahan
448.0000 kg Semen portland @Rp. 1,900.00 = Rp. 851,200.00
667.0000 kg Pasir beton @Rp. 112.50 = Rp. 75,037.50
1,000.0000 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 192,592.59
215.0000 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 1,333,830.09
Tenaga
1.6500 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.2750 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.0280 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.0830 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
IV.13 1 kg Pekerjaan pembesian dengan besi polos
Bahan
1.050 kg Besi beton polos @Rp. 11,000.00 = Rp. 11,550.00
0.015 kg Kawat bendrat @Rp. 16,000.00 = Rp. 240.00
Rp. 11,790.00
Tenaga
0.0070 Oh Pekerja @Rp. 45,000.00 = Rp. 315.00
0.0070 Oh Tukang besi @Rp. 55,000.00 = Rp. 385.00
0.0007 Oh Kepala tukang besi @Rp. 57,500.00 = Rp. 40.25
0.0040 Oh Mandor @Rp. 60,000.00 = Rp. 240.00
Rp. 980.25
IV.17 1 m2 Pekerjaan bekisting untuk kolom mennggunakan cetakan teakwood dan perancah dolken
Bahan
0.020 m3 Kayu kelas III (kayu cetakan) 2x pakai @Rp. 735,000.00 = Rp. 14,700.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.008 m3 Balok kayu tahun 2x pakai @Rp. 3,675,000.00 = Rp. 27,562.50
0.180 lbr Teakwood
Dolken kayutebal 9 mm
galam 2x pakai
Ø 8-10 cm/4m, 2x @Rp. 60,000.00 = Rp. 10,800.00
1.000 btg pakai @Rp. 42,000.00 = Rp. 42,000.00
Rp. 100,662.50
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.18 1 m2 Pekerjaan bekisting untuk kolom menggunakan cetakan kayu tahun dan perancah bambu
Bahan
0.020 m3 Kayu kelas III (kayu cetakan), 2x pakai @Rp. 735,000.00 = Rp. 14,700.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.008 m3 Balok kayu tahun, 2x pakai @Rp. 3,675,000.00 = Rp. 27,562.50
2.500 lbr Papan kayu tahun 2/20x200 cm, 2x paka@Rp. 29,400.00 = Rp. 73,500.00
1.000 btg Bambu/4m, 2x pakai @Rp. 8,000.00 = Rp. 8,000.00
Rp. 129,362.50
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.19 1 m2 Pekerjaan bekisting untuk balok cetakan menggunakan teakwood dan perancah dolken
Bahan
0.020 m3 Kayu kelas III (kayu cetakan) 2x pakai @Rp. 735,000.00 = Rp. 14,700.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.009 m3 Balok kayu meranti 2x pakai @Rp. 3,675,000.00 = Rp. 33,075.00
0.180 lbr Teakwood
Dolken kayutebal 9 mm
galam 2x pakai
Ø 8-10 cm/4m, 2x @Rp. 60,000.00 = Rp. 10,800.00
1.000 btg pakai @Rp. 42,000.00 = Rp. 42,000.00
Rp. 106,175.00
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.20 1 m2 Pekerjaan bekisting untuk balok menggunakan cetakan kayu tahun dan perancah bambu
Bahan
0.020 m3 Kayu kelas III (kayu cetakan), 2x pakai @Rp. 735,000.00 = Rp. 14,700.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.009 m3 Balok kayu tahun, 2x pakai @Rp. 3,675,000.00 = Rp. 33,075.00
2.500 lbr Papan kayu tahun 2/20x200 cm, 2x paka@Rp. 29,400.00 = Rp. 73,500.00
1.000 btg Bambu/4m, 2x pakai @Rp. 8,000.00 = Rp. 8,000.00
Rp. 134,875.00
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.21 1 m2 Pekerjaan bekisting untuk plat lantai cetakan teakwood dan perancah dolken
Bahan
0.020 m3 Kayu kelas III (kayu cetakan) 2x pakai @Rp. 735,000.00 = Rp. 14,700.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.008 m3 Balok kayu meranti 2x pakai @Rp. 3,675,000.00 = Rp. 27,562.50
0.180 lbr Teakwood
Dolken kayutebal 9 mm
galam 2x pakai
Ø 8-10 cm/4m, 2x @Rp. 60,000.00 = Rp. 10,800.00
3.000 btg pakai @Rp. 42,000.00 = Rp. 126,000.00
Rp. 184,662.50
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.22 1 m2 Pekerjaan bekisting untuk plat lantai menggunakan cetakan kayu tahun dan perancah bambu
Bahan
0.020 m3 Kayu kelas III (kayu cetakan), 2x pakai @Rp. 735,000.00 = Rp. 14,700.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.008 m3 Balok kayu tahun, 2x pakai @Rp. 3,675,000.00 = Rp. 27,562.50
2.500 lbr Papan kayu tahun 2/20x200 cm, 2x paka@Rp. 29,400.00 = Rp. 73,500.00
3.000 btg Bambu/4m, 2x pakai @Rp. 8,000.00 = Rp. 24,000.00
Rp. 145,362.50
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.23 1 m2 Pekerjaan bekisting untuk dinding menggunakan cetakan teakwood dan perancah dolken
Bahan
0.015 m3 Kayu kelas III (kayu cetakan) 2x pakai @Rp. 735,000.00 = Rp. 11,025.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.010 m3 Balok kayu meranti 2x pakai @Rp. 3,675,000.00 = Rp. 36,750.00
0.180 lbr Teakwood
Dolken kayutebal 9 mm
galam 2x pakai
Ø 8-10 cm/4m, 2x @Rp. 60,000.00 = Rp. 10,800.00
1.500 btg pakai
Fornite/penjaga jarak/spacer (alat @Rp. 42,000.00 = Rp. 63,000.00
4.000 bh bantu) @Rp. 1,500.00 = Rp. 6,000.00
Rp. 133,175.00
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.24 1 m2 Pekerjaan bekisting untuk dinding menggunakan cetakan kayu tahun dan perancah bambu
Bahan
0.015 m3 Kayu kelas III (kayu cetakan), 2x pakai @Rp. 735,000.00 = Rp. 11,025.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.010 m3 Balok kayu tahun, 2x pakai @Rp. 3,675,000.00 = Rp. 36,750.00
2.500 lbr Papan kayu tahun 2/20x200 cm, 2x paka@Rp. 29,400.00 = Rp. 73,500.00
1.500 btg Bambu/4m, 2x pakai
Fornite/penjaga jarak/spacer (alat @Rp. 8,000.00 = Rp. 12,000.00
4.000 bh bantu) @Rp. 1,500.00 = Rp. 6,000.00
Rp. 144,875.00
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.25 1 m2 Pekerjaan bekisting untuk tangga menggunakan cetakan teakwood dan perancah dolken
Bahan
0.015 m3 Kayu kelas III (kayu cetakan) 2x pakai @Rp. 735,000.00 = Rp. 11,025.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.008 m3 Balok kayu meranti 2x pakai @Rp. 3,675,000.00 = Rp. 27,562.50
0.180 lbr Teakwood
Dolken kayutebal 9 mm
galam 2x pakai
Ø 8-10 cm/4m, 2x @Rp. 60,000.00 = Rp. 10,800.00
1.000 btg pakai @Rp. 42,000.00 = Rp. 42,000.00
Rp. 96,987.50
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
IV.26 1 m2 Pekerjaan bekisting untuk tangga menggunakan cetakan kayu tahun dan perancah bambu
Bahan
0.015 m3 Kayu kelas III (kayu cetakan), 2x pakai @Rp. 735,000.00 = Rp. 11,025.00
0.400 kg Paku 2" - 5" @Rp. 14,000.00 = Rp. 5,600.00
0.008 m3 Balok kayu tahun, 2x pakai @Rp. 3,675,000.00 = Rp. 27,562.50
2.500 lbr Papan kayu tahun 2/20x200 cm, 2x paka@Rp. 29,400.00 = Rp. 73,500.00
1.000 btg Bambu/4m, 2x pakai @Rp. 8,000.00 = Rp. 8,000.00
Rp. 125,687.50
Tenaga
0.6600 Oh Pekerja @Rp. 45,000.00 = Rp. 29,700.00
0.3300 Oh Tukang kayu @Rp. 55,000.00 = Rp. 18,150.00
0.0330 Oh Kepala tukang kayu @Rp. 57,500.00 = Rp. 1,897.50
0.0330 Oh Mandor @Rp. 60,000.00 = Rp. 1,980.00
Rp. 51,727.50
V.2 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Pp tebal 1 Bata
Bahan
140.0000 m3 Batu bata @Rp. 700.00 = Rp. 98,000.00
32.9500 kg Semen PC @Rp. 1,900.00 = Rp. 62,605.00
0.0910 m3 Pasir pasang @Rp. 147,000.00 = Rp. 13,377.00
Rp. 173,982.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.2000 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 40,950.00
V.3 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 4Pp tebal 1 Bata
Bahan
140.0000 m3 Batu bata @Rp. 700.00 = Rp. 98,000.00
26.5500 kg Semen PC @Rp. 1,900.00 = Rp. 50,445.00
0.0930 m3 Pasir pasang @Rp. 147,000.00 = Rp. 13,671.00
Rp. 162,116.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.2000 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 40,950.00
V.4 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 5Pp tebal 1 Bata
Bahan
140.0000 m3 Batu bata @Rp. 700.00 = Rp. 98,000.00
22.2000 kg Semen PC @Rp. 1,900.00 = Rp. 42,180.00
0.1020 m3 Pasir pasang @Rp. 147,000.00 = Rp. 14,994.00
Rp. 155,174.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.2000 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 40,950.00
V.5 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 6Pp tebal 1 Bata
Bahan
140.0000 m3 Batu bata @Rp. 700.00 = Rp. 98,000.00
18.5000 kg Semen PC @Rp. 1,900.00 = Rp. 35,150.00
0.1220 m3 Pasir pasang @Rp. 147,000.00 = Rp. 17,934.00
Rp. 151,084.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.2000 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 40,950.00
V.6 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Kp : 10 Pp tebal 1 Bata
Bahan
140.0000 m3 Batu bata @Rp. 700.00 = Rp. 98,000.00
10.0800 kg Semen PC @Rp. 1,900.00 = Rp. 19,152.00
0.0925 m3 Pasir pasang @Rp. 147,000.00 = Rp. 13,597.50
0.0275 m3 Kapur @Rp. 6,300.00 = Rp. 173.25
Rp. 130,922.75
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.2000 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.0200 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 40,950.00
V.7 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 2Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
18.9500 kg Semen PC @Rp. 1,900.00 = Rp. 36,005.00
0.0380 m3 Pasir pasang @Rp. 147,000.00 = Rp. 5,586.00
Rp. 90,591.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.8 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
14.3700 kg Semen PC @Rp. 1,900.00 = Rp. 27,303.00
0.0400 m3 Pasir pasang @Rp. 147,000.00 = Rp. 5,880.00
Rp. 82,183.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.9 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 4Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
11.5000 kg Semen PC @Rp. 1,900.00 = Rp. 21,850.00
0.0430 m3 Pasir pasang @Rp. 147,000.00 = Rp. 6,321.00
Rp. 77,171.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.10 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 5Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
9.6800 kg Semen PC @Rp. 1,900.00 = Rp. 18,392.00
0.0450 m3 Pasir pasang @Rp. 147,000.00 = Rp. 6,615.00
Rp. 74,007.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.11 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 6Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
8.3200 kg Semen PC @Rp. 1,900.00 = Rp. 15,808.00
0.0490 m3 Pasir pasang @Rp. 147,000.00 = Rp. 7,203.00
Rp. 72,011.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.12 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 8Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
6.5000 kg Semen PC @Rp. 1,900.00 = Rp. 12,350.00
0.0500 m3 Pasir pasang @Rp. 147,000.00 = Rp. 7,350.00
Rp. 68,700.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.13 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Kp : 10Pp tebal 1/2 Bata
Bahan
70.0000 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
4.5000 kg Semen PC @Rp. 1,900.00 = Rp. 8,550.00
0.0500 m3 Pasir pasang @Rp. 147,000.00 = Rp. 7,350.00
0.0150 m3 Kapur @Rp. 6,300.00 = Rp. 94.50
Rp. 64,994.50
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.14 1 m2 Memasang dinding terawang (roster) ukuran (12x11x24) cm campuran spesl 1Pc: 3Pp
Bahan
30.0000 bh Terawang (roster) @Rp. 1,500.00 = Rp. 45,000.00
14.0000 kg Semen PC @Rp. 1,900.00 = Rp. 26,600.00
0.0320 m3 Pasir pasang @Rp. 147,000.00 = Rp. 4,704.00
Rp. 76,304.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
V.15 1 m2 Memasang dinding terawang (roster) ukuran (12x11x24) cm campuran spesl 1Pc: 4PP
Bahan
30.0000 bh Terawang (roster) @Rp. 1,500.00 = Rp. 45,000.00
11.0000 kg Semen PC @Rp. 1,900.00 = Rp. 20,900.00
0.0350 m3 Pasir pasang @Rp. 147,000.00 = Rp. 5,145.00
Rp. 71,045.00
Tenaga
0.3000 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1000 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Oh Kepala tukang @Rp. 57,500.00 = Rp. 575.00
0.0150 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
VII.2 1 m3 Membuat dan memasang kusen pintu dan daun jendela Kayu Bengkirai
Bahan
1.1000 m3 Balok kayu bengkirai @Rp. 11,025,000.00 = Rp. 12,127,500.00
1.2500 kg Paku 10 cm @Rp. 14,000.00 = Rp. 17,500.00
1.0000 kg Lem kayu @Rp. 14,000.00 = Rp. 14,000.00
Rp. 12,159,000.00
Tenaga
6.0000 Pekerja @Rp. 45,000.00 = Rp. 270,000.00
20.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 1,100,000.00
2.0000 Kepala Tukang @Rp. 57,500.00 = Rp. 115,000.00
0.3000 mandor @Rp. 60,000.00 = Rp. 18,000.00
Rp. 1,503,000.00
VII.3 1 m3 Membuat dan memasang kusen pintu dan daun jendela Kayu Kamper
Bahan
1.1000 m3 Balok kayu kamper @Rp. 8,925,000.00 = Rp. 9,817,500.00
1.2500 kg Paku 10 cm @Rp. 14,000.00 = Rp. 17,500.00
1.0000 kg Lem kayu @Rp. 14,000.00 = Rp. 14,000.00
Rp. 9,849,000.00
Tenaga
6.0000 Pekerja @Rp. 45,000.00 = Rp. 270,000.00
20.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 1,100,000.00
2.0000 Kepala Tukang @Rp. 57,500.00 = Rp. 115,000.00
0.3000 mandor @Rp. 60,000.00 = Rp. 18,000.00
Rp. 1,503,000.00
VII.4 1 m2 Membuat dan memasang pintu klam Kayu Kruing
Bahan
0.0400 m3 Papan kayu kamper @Rp. 5,775,000.00 = Rp. 231,000.00
0.0500 kg Paku 5 - 7 cm @Rp. 14,000.00 = Rp. 700.00
Rp. 231,700.00
Tenaga
0.3500 Pekerja @Rp. 45,000.00 = Rp. 15,750.00
1.0500 Tukang Kayu @Rp. 55,000.00 = Rp. 57,750.00
0.1050 Kepala Tukang @Rp. 57,500.00 = Rp. 6,037.50
0.0180 mandor @Rp. 60,000.00 = Rp. 1,080.00
Rp. 80,617.50
VII.10 1 m2 Membuat dan memasang pintu dan jendela kaca kayu Kruing
Bahan
0.0240 m3 Papan kayu kruing @Rp. 5,775,000.00 = Rp. 138,600.00
0.3000 kg Lem kayu @Rp. 14,000.00 = Rp. 4,200.00
Rp. 142,800.00
Tenaga
0.8000 Pekerja @Rp. 45,000.00 = Rp. 36,000.00
2.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2000 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.0400 mandor @Rp. 60,000.00 = Rp. 2,400.00
Rp. 159,900.00
VII.11 1 m2 Membuat dan memasang pintu dan jendela kaca kayu Bengkirai
Bahan
0.0240 m3 Papan kayu bengkirai @Rp. 11,550,000.00 = Rp. 277,200.00
0.3000 kg Lem kayu @Rp. 14,000.00 = Rp. 4,200.00
Rp. 281,400.00
Tenaga
0.8000 Pekerja @Rp. 45,000.00 = Rp. 36,000.00
2.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2000 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.0400 mandor @Rp. 60,000.00 = Rp. 2,400.00
Rp. 159,900.00
VII.12 1 m2 Membuat dan memasang pintu dan jendela kaca kayu Kamper
Bahan
0.0240 m3 Papan kayu kamper @Rp. 10,238,000.00 = Rp. 245,712.00
0.3000 kg Lem kayu @Rp. 14,000.00 = Rp. 4,200.00
Rp. 249,912.00
Tenaga
0.8000 Pekerja @Rp. 45,000.00 = Rp. 36,000.00
2.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2000 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.0400 mandor @Rp. 60,000.00 = Rp. 2,400.00
Rp. 159,900.00
VII.13 1 m2 Membuat dan memasang pintu dan jendela jalusi kayu Kruing
Bahan
0.0640 m3 Papan kayu kruing @Rp. 5,775,000.00 = Rp. 369,600.00
0.5000 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
Rp. 376,600.00
Tenaga
1.0000 Pekerja @Rp. 45,000.00 = Rp. 45,000.00
3.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 165,000.00
0.3000 Kepala Tukang @Rp. 57,500.00 = Rp. 17,250.00
0.0500 mandor @Rp. 60,000.00 = Rp. 3,000.00
Rp. 230,250.00
VII.14 1 m2 Membuat dan memasang pintu dan jendela jalusi kayu Bengkirai
Bahan
0.0640 m3 Papan kayu bengkirai @Rp. 11,550,000.00 = Rp. 739,200.00
0.5000 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
Rp. 746,200.00
Tenaga
1.0000 Pekerja @Rp. 45,000.00 = Rp. 45,000.00
3.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 165,000.00
0.3000 Kepala Tukang @Rp. 57,500.00 = Rp. 17,250.00
0.0500 mandor @Rp. 60,000.00 = Rp. 3,000.00
Rp. 230,250.00
VII.15 1 m2 Membuat dan memasang pintu dan jendela jalusi kayu Kamper
Bahan
0.0640 m3 Papan kayu kamper @Rp. 10,238,000.00 = Rp. 655,232.00
0.5000 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
Rp. 662,232.00
Tenaga
1.0000 Pekerja @Rp. 45,000.00 = Rp. 45,000.00
3.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 165,000.00
0.3000 Kepala Tukang @Rp. 57,500.00 = Rp. 17,250.00
0.0500 mandor @Rp. 60,000.00 = Rp. 3,000.00
Rp. 230,250.00
VII.16 1 m2 Membuat daun pintu lapis teakwood rangkap, rangka tertutup kayu kruing (lebar sampai 90 cm)
Bahan
0.0250 m3 Papan kayu kruing @Rp. 5,775,000.00 = Rp. 144,375.00
0.0300 kg Paku 1 - 2,5 cm @Rp. 18,000.00 = Rp. 540.00
0.5000 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
0.6944 lbr Teakwood 120 x 240 x 0,3 cm @Rp. 90,000.00 = Rp. 62,500.00
Rp. 214,415.00
Tenaga
0.6000 Pekerja @Rp. 45,000.00 = Rp. 27,000.00
2.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2000 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.0300 mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 150,300.00
VII.17 1 m2 Membuat daun pintu lapis teakwood rangkap, rangka tertutup kayu bengkirai (lebar sampai 90 cm)
Bahan
0.0250 m3 Papan kayu bengkirai @Rp. 11,550,000.00 = Rp. 288,750.00
0.0300 kg Paku 1 - 2,5 cm @Rp. 18,000.00 = Rp. 540.00
0.5000 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
0.6944 lbr Teakwood 120 x 240 x 0,3 cm @Rp. 90,000.00 = Rp. 62,500.00
Rp. 358,790.00
Tenaga
0.6000 Pekerja @Rp. 45,000.00 = Rp. 27,000.00
2.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2000 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.0300 mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 150,300.00
VII.18 1 m2 Membuat daun pintu lapis teakwood rangkap, rangka tertutup kayu kamper (lebar sampai 90 cm)
Bahan
0.0250 m3 Papan kayu kamper @Rp. 10,238,000.00 = Rp. 255,950.00
0.0300 kg Paku 1 - 2,5 cm @Rp. 18,000.00 = Rp. 540.00
0.5000 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
0.6944 lbr Teakwood 120 x 240 x 0,3 cm @Rp. 90,000.00 = Rp. 62,500.00
Rp. 325,990.00
Tenaga
0.6000 Pekerja @Rp. 45,000.00 = Rp. 27,000.00
2.0000 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2000 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.0300 mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 150,300.00
VII.31 1 m2 Memasang rangka atap genteng plentong dan Vlam, kayu kruing
Bahan
0.0088 m3 Usuk kayu kruing 5/7 @Rp. 5,775,000.00 = Rp. 50,820.00
0.0033 m3 Reng kayu kruing 2/3 @Rp. 5,775,000.00 = Rp. 19,057.50
0.2500 kg Paku 5 cm dan 10 cm @Rp. 14,000.00 = Rp. 3,500.00
Rp. 73,377.50
Tenaga
0.1000 Pekerja @Rp. 45,000.00 = Rp. 4,500.00
0.1000 Tukang Kayu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Kepala Tukang @Rp. 57,500.00 = Rp. 575.00
0.0050 mandor @Rp. 60,000.00 = Rp. 300.00
Rp. 10,875.00
VII.32 1 m2 Memasang rangka atap genteng glasur morando, kayu kruing
Bahan
0.0105 m3 Usuk kayu kruing 5/7 @Rp. 5,775,000.00 = Rp. 60,637.50
0.0030 m3 Reng kayu kruing 2/3 @Rp. 5,775,000.00 = Rp. 17,325.00
0.2500 kg Paku 5 cm dan 10 cm @Rp. 14,000.00 = Rp. 3,500.00
Rp. 81,462.50
Tenaga
0.1000 Pekerja @Rp. 45,000.00 = Rp. 4,500.00
0.1000 Tukang Kayu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Kepala Tukang @Rp. 57,500.00 = Rp. 575.00
0.0050 mandor @Rp. 60,000.00 = Rp. 300.00
Rp. 10,875.00
VII.35 1 m2 Memasang rangka atap genteng kodok dan vlam, kayu bengkirai
Bahan
0.0088 m3 Usuk kayu bengkirai 5/7 @Rp. 11,025,000.00 = Rp. 97,020.00
0.0033 m3 Reng kayu bengkirai 2/3 @Rp. 11,025,000.00 = Rp. 36,382.50
0.2500 kg Paku 5 cm dan 10 cm @Rp. 14,000.00 = Rp. 3,500.00
Rp. 136,902.50
Tenaga
0.1000 Pekerja @Rp. 45,000.00 = Rp. 4,500.00
0.1000 Tukang Kayu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Kepala Tukang @Rp. 57,500.00 = Rp. 575.00
0.0050 mandor @Rp. 60,000.00 = Rp. 300.00
Rp. 10,875.00
VII.36 1 m2 Memasang rangka atap genteng glasur morando, kayu bengkirai
Bahan
0.0105 m3 Usuk kayu bengkirai 5/7 @Rp. 11,025,000.00 = Rp. 115,762.50
0.0030 m3 Reng kayu bengkirai 2/3 @Rp. 11,025,000.00 = Rp. 33,075.00
0.2500 kg Paku 5 cm dan 10 cm @Rp. 14,000.00 = Rp. 3,500.00
Rp. 152,337.50
Tenaga
0.1000 Pekerja @Rp. 45,000.00 = Rp. 4,500.00
0.1000 Tukang Kayu @Rp. 55,000.00 = Rp. 5,500.00
0.0100 Kepala Tukang @Rp. 57,500.00 = Rp. 575.00
0.0050 mandor @Rp. 60,000.00 = Rp. 300.00
Rp. 10,875.00
VIII.3 1 m2 Pasang lantai keramik ukuran (30x30) cm, Putih Polos "Asia Tile"
Bahan
1.0101 dos Keramik Asia Tile Putih Polos @Rp. 49,000.00 = Rp. 49,494.90
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 94,609.90
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.4 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Muda "Mulia"
Bahan
1.0101 dos Keramik Mulia Motif Warna Muda @Rp. 35,000.00 = Rp. 35,353.50
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 80,468.50
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.5 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Tua "Mulia"
Bahan
1.0101 dos Keramik Mulia Motif Warna Tua @Rp. 41,000.00 = Rp. 41,414.10
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 86,529.10
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.6 1 m2 Pasang lantai keramik ukuran (30x30) cm, Putih Polos "Mulia"
Bahan
1.0101 dos Keramik Mulia Putih Polos @Rp. 44,000.00 = Rp. 44,444.40
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 89,559.40
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.7 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Muda "Arwana"
Bahan
1.0101 dos Keramik arwana Motif Warna Muda @Rp. 42,000.00 = Rp. 42,424.20
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 87,539.20
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.8 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Tua "Arwana"
Bahan
1.0101 dos Keramik Arwana Motif Warna Tua @Rp. 32,000.00 = Rp. 32,323.20
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 77,438.20
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.9 1 m2 Pasang lantai keramik ukuran (30x30) cm, Putih Polos "Arwana"
Bahan
1.0101 dos Keramik Arwana Putih Polos @Rp. 30,000.00 = Rp. 30,303.00
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 75,418.00
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.10 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Muda "KIA"
Bahan
1.0101 dos Keramik "KIA" Motif Warna Muda @Rp. 42,000.00 = Rp. 42,424.20
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 87,539.20
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.11 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Tua "KIA"
Bahan
1.0101 dos Keramik KIA Motif Warna Tua @Rp. 47,000.00 = Rp. 47,474.70
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 92,589.70
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.12 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Muda "Roman"
Bahan
1.0101 dos Keramik "Roman" Motif Warna Muda @Rp. 68,000.00 = Rp. 68,686.80
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 113,801.80
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.13 1 m2 Pasang lantai keramik ukuran (30x30) cm, Motif Warna Tua "Roman"
Bahan
1.0101 dos Keramik "Roman" Motif Warna Tua @Rp. 74,000.00 = Rp. 74,747.40
10.0000 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5000 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 119,862.40
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.14 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "Asia Tile"
Bahan
1.0417 dos Keramik Asia Tile Motif Warna Muda @Rp. 55,000.00 = Rp. 57,293.50
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 99,428.50
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.15 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "Asia Tile"
Bahan
1.0417 dos Keramik Asia Tile Motif Warna Tua @Rp. 61,000.00 = Rp. 63,543.70
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 105,678.70
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.16 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Putih Polos "Asia Tile"
Bahan
1.0417 dos Keramik Asia Tile Putih Polos @Rp. 50,000.00 = Rp. 52,085.00
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 94,220.00
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.17 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "Mulia"
Bahan
1.0417 dos Keramik "Mulia" Motif Warna Muda @Rp. 38,000.00 = Rp. 39,584.60
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 81,719.60
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.18 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "Mulia"
Bahan
1.0417 dos Keramik "Mulia" Tile Motif Warna Tua @Rp. 52,000.00 = Rp. 54,168.40
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 96,303.40
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.19 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Putih Polos "Mulia"
Bahan
1.0417 dos Keramik "Mulia" Putih Polos @Rp. 48,000.00 = Rp. 50,001.60
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 92,136.60
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.20 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "Arwana"
Bahan
1.0417 dos Keramik "Arwana" Motif Warna Muda @Rp. 48,000.00 = Rp. 50,001.60
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 92,136.60
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.21 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "Arwana"
Bahan
1.0417 dos Keramik "Arwana" Motif Warna Tua @Rp. 53,000.00 = Rp. 55,210.10
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 97,345.10
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.22 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Putih Polos"Arwana"
Bahan
1.0417 dos Keramik "Arwana" Putih Polos @Rp. 34,000.00 = Rp. 35,417.80
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 77,552.80
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.24 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "KIA"
Bahan
1.0417 dos Keramik "KIA" Motif Warna Muda @Rp. 47,000.00 = Rp. 48,959.90
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 91,094.90
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.25 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "KIA"
Bahan
1.0417 dos Keramik "KIA" Motif Warna Tua @Rp. 52,000.00 = Rp. 54,168.40
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 96,303.40
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.26 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "ROMAN"
Bahan
1.0417 dos Keramik "ROMAN" Motif Warna Muda @Rp. 87,000.00 = Rp. 90,627.90
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 132,762.90
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.27 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "ROMAN"
Bahan
1.0417 dos Keramik "ROMAN" Motif Warna Tua @Rp. 95,000.00 = Rp. 98,961.50
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 141,096.50
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.29 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "HERCULES"
Bahan
1.0417 dos Keramik "HERCULES" Motif Warna Mu @Rp. 56,000.00 = Rp. 58,335.20
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 100,470.20
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.30 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "HERCULES"
Bahan
1.0417 dos Keramik "HERCULES" Motif Warna Tua@Rp. 59,000.00 = Rp. 61,460.30
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 103,595.30
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.31 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Putih Polos""HERCULES"
Bahan
1.0417 dos Keramik "HERCULES" Putih Polos @Rp. 56,000.00 = Rp. 58,335.20
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 100,470.20
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.32 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "MILAN"
Bahan
1.0417 dos Keramik "MILAN" Motif Warna Muda @Rp. 58,000.00 = Rp. 60,418.60
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 102,553.60
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.33 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Tua "MILAN"
Bahan
1.0417 dos Keramik "MILAN" Motif Warna Tua @Rp. 69,000.00 = Rp. 71,877.30
9.8000 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3000 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 114,012.30
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.34 1 m2 Pasang lantai keramik ukuran (20x20) cm, Motif Warna Muda, "Asia Tile"
Bahan
1.0500 dos Keramik Asia Tile Motif Warna Muda @Rp. 50,000.00 = Rp. 52,500.00
10.4000 kg PC @Rp. 1,900.00 = Rp. 19,760.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.6200 kg Semen warna @Rp. 13,000.00 = Rp. 21,060.00
Rp. 99,935.00
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.35 1 m2 Pasang lantai keramik ukuran (20x20) cm, Motif Warna Tua, "Asia Tile"
Bahan
1.0500 dos Keramik Asia Tile Motif Warna Tua @Rp. 41,000.00 = Rp. 43,050.00
10.4000 kg PC @Rp. 1,900.00 = Rp. 19,760.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.6200 kg Semen warna @Rp. 13,000.00 = Rp. 585.00
Rp. 70,010.00
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.36 1 m2 Pasang lantai keramik ukuran (20x20) cm, Putih Polos, "Mulia"
Bahan
1.0500 dos Keramik Mulia Putih Polos @Rp. 48,000.00 = Rp. 50,400.00
10.4000 kg PC @Rp. 1,900.00 = Rp. 19,760.00
0.0450 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.6200 kg Semen warna @Rp. 13,000.00 = Rp. 21,060.00
Rp. 97,835.00
Tenaga
0.6200 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.3500 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.0350 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
VIII.45 1 m2 Pasang dinding keramik ukuran (20x20) cm, Motif Warna Muda "Asia Tile"
Bahan
1.0500 dos Keramik Asia Tile Motif Warna Muda @Rp. 50,000.00 = Rp. 52,500.00
9.3000 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.0180 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
1.9400 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 73,050.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.4500 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.0450 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
VIII.46 1 m2 Pasang dinding keramik ukuran (20x20) cm, Motif Warna Tua "Asia Tile"
Bahan
1.0500 dos Keramik Asia Tile Motif Warna Tua @Rp. 41,000.00 = Rp. 43,050.00
9.3000 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.0180 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
1.9400 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 63,600.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.4500 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.0450 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
VIII.58 1 m2 Pasang lis dinding keramik ukuran (10x30) cm asia tile motif warna muda
Bahan
1.2963 dos Keramik 30x30 motif warna muda @Rp. 48,000.00 = Rp. 62,222.40
9.3000 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.0180 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
2.7500 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 82,772.40
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.4500 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.0450 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
VIII.59 1 m2 Pasang lis dinding keramik ukuran (10x40) cm asia tile motif warna muda
Bahan
1.0938 dos Keramik 40x40 motif warna muda @Rp. 55,000.00 = Rp. 60,159.00
9.3000 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.0180 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
2.7500 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 80,709.00
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.4500 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.0450 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
VIII.60 1 m2 Pasang lis dinding keramik ukuran (10x30) cm mulia motif warna muda
Bahan
1.2963 dos Keramik 30x30 motif warna muda @Rp. 35,000.00 = Rp. 45,370.50
9.3000 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.0180 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
2.7500 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 65,920.50
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.4500 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.0450 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
VIII.61 1 m2 Pasang lis dinding keramik ukuran (10x40) cm mulia motif warna muda
Bahan
1.0938 dos Keramik 40x40 motif warna muda @Rp. 38,000.00 = Rp. 41,564.40
9.3000 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.0180 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
2.7500 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 62,114.40
Tenaga
0.6000 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.4500 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.0450 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.0300 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
IX.5 1 m2 Pasang langit-langit gypsum board "Elephant" ukuran (120x240x0,9) cm, tebal 9 mm rangka Hollow 20/40
dan 40/40 galvanis tebal 4 mm
Bahan
0.3470 lbr Gypsum board "Elephant" @Rp. 59,000.00 = Rp. 20,473.00
0.5000 btg Hollow 40/40 galvanis tebal 5 mm @Rp. 33,000.00 = Rp. 16,500.00
0.6250 btg Hollow 20/40 galvanis tebal 4 mm @Rp. 20,000.00 = Rp. 12,500.00
0.1500 kg kawat diameter 4 mm @Rp. 15,000.00 = Rp. 2,250.00
0.1100 kg Skrup @Rp. 24,000.00 = Rp. 2,640.00
0.0250 kg Cornis @Rp. 5,000.00 = Rp. 125.00
0.0020 rol Lakban @Rp. 11,000.00 = Rp. 22.00
Rp. 54,488.00
Tenaga
0.1500 Oh Pekerja @Rp. 45,000.00 = Rp. 6,750.00
0.5000 Oh Tukang kayu @Rp. 55,000.00 = Rp. 27,500.00
0.0500 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,875.00
0.0080 Oh Mandor @Rp. 60,000.00 = Rp. 480.00
Rp. 37,605.00
IX.6 1 m2 Pasang langit-langit gypsum board "Jaya Board" ukuran (120x240x0,9) cm, tebal 9 mm rangka Hollow
20/40 dan 40/40 galvanis tebal 4 mm
Bahan
0.3470 lbr Gypsum board "Jaya board" @Rp. 62,000.00 = Rp. 21,514.00
0.5000 btg Hollow 40/40 galvanis tebal 5 mm @Rp. 33,000.00 = Rp. 16,500.00
0.6250 btg Hollow 20/40 galvanis tebal 4 mm @Rp. 20,000.00 = Rp. 12,500.00
0.1500 kg kawat diameter 4 mm @Rp. 15,000.00 = Rp. 2,250.00
0.1100 kg Skrup @Rp. 24,000.00 = Rp. 2,640.00
0.0250 kg Cornis @Rp. 5,000.00 = Rp. 125.00
0.0020 rol Lakban @Rp. 11,000.00 = Rp. 22.00
Rp. 55,551.00
Tenaga
0.1500 Oh Pekerja @Rp. 45,000.00 = Rp. 6,750.00
0.5000 Oh Tukang kayu @Rp. 55,000.00 = Rp. 27,500.00
0.0500 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,875.00
0.0080 Oh Mandor @Rp. 60,000.00 = Rp. 480.00
Rp. 37,605.00
IX.7 1 m2 Pasang langit-langit GRC board ukuran (120x240x0,4) cm, tebal 4 mm rangka Hollow 20/40 dan 40/40
galvanis tebal 4 mm
Bahan
0.3470 lbr GRC Board ukuran (120x240x0,4) cm @Rp. 60,000.00 = Rp. 20,820.00
0.5000 btg Hollow 40/40 galvanis tebal 5 mm @Rp. 33,000.00 = Rp. 16,500.00
0.6250 btg Hollow 20/40 galvanis tebal 4 mm @Rp. 20,000.00 = Rp. 12,500.00
0.1500 kg kawat diameter 4 mm @Rp. 15,000.00 = Rp. 2,250.00
0.1100 kg Skrup @Rp. 24,000.00 = Rp. 2,640.00
0.0250 kg Cornis @Rp. 5,000.00 = Rp. 125.00
0.0020 rol Lakban @Rp. 11,000.00 = Rp. 22.00
Rp. 54,857.00
Tenaga
0.1500 Oh Pekerja @Rp. 45,000.00 = Rp. 6,750.00
0.5000 Oh Tukang kayu @Rp. 55,000.00 = Rp. 27,500.00
0.0500 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,875.00
0.0080 Oh Mandor @Rp. 60,000.00 = Rp. 480.00
Rp. 37,605.00
IX.8 1 m2 Pasang langit-langit Kalsiboard ukuran (120x240x0,35) cm, tebal 3,5 mm rangka Hollow 20/40 dan 40/40
galvanis tebal 4 mm
Bahan
0.3470 lbr Kalsiboard ukuran (120x240x0,35) cm @Rp. 57,000.00 = Rp. 19,779.00
0.5000 btg Hollow 40/40 galvanis tebal 5 mm @Rp. 33,000.00 = Rp. 16,500.00
0.6250 btg Hollow 20/40 galvanis tebal 4 mm @Rp. 20,000.00 = Rp. 12,500.00
0.1500 kg kawat diameter 4 mm @Rp. 15,000.00 = Rp. 2,250.00
0.1100 kg Skrup @Rp. 24,000.00 = Rp. 2,640.00
0.0250 kg Cornis @Rp. 5,000.00 = Rp. 125.00
0.0020 rol Lakban @Rp. 11,000.00 = Rp. 22.00
Rp. 53,816.00
Tenaga
0.1500 Oh Pekerja @Rp. 45,000.00 = Rp. 6,750.00
0.5000 Oh Tukang kayu @Rp. 55,000.00 = Rp. 27,500.00
0.0500 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,875.00
0.0080 Oh Mandor @Rp. 60,000.00 = Rp. 480.00
Rp. 37,605.00
X.3 1 m2 Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Bahan
15.0000 kg Besi siku L 30.30.3 @Rp. 8,000.00 = Rp. 120,000.00
32.8000 kg Besi plat baja @Rp. 9,000.00 = Rp. 295,200.00
0.0500 kg kawat las @Rp. 28,000.00 = Rp. 1,400.00
Rp. 416,600.00
Tenaga
1.0500 Oh Pekerja @Rp. 45,000.00 = Rp. 47,250.00
1.0500 Oh Tukang besi @Rp. 55,000.00 = Rp. 57,750.00
0.1050 Oh Kepala tukang @Rp. 57,500.00 = Rp. 6,037.50
0.0520 Oh Mandor @Rp. 60,000.00 = Rp. 3,120.00
Rp. 114,157.50
X.9 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 4" Alexsindo natural
Bahan
1.1000 m' Kusen Alumunium 4" Alexsindo natural @Rp. 63,000.00 = Rp. 69,300.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 73,160.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.10 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 4" Alexsindo coklat"
Bahan
1.1000 m' Kusen Alumunium 4" Alexsindo coklat @Rp. 74,000.00 = Rp. 81,400.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 85,260.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.11 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 4" Alko natural"
Bahan
1.1000 m' Kusen Alumunium 4" Alko natural @Rp. 58,000.00 = Rp. 63,800.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 67,660.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.12 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 4" Alko coklat"
Bahan
1.1000 m' Kusen Alumunium 4" Alko coklat @Rp. 69,000.00 = Rp. 75,900.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 79,760.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.13 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 4" YKK natural"
Bahan
1.1000 m' Kusen Alumunium 4" YKK natural @Rp. 126,000.00 = Rp. 138,600.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 142,460.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.14 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 4" YKK coklat
Bahan
1.1000 m' Kusen Alumunium 4" YKK coklat @Rp. 147,000.00 = Rp. 161,700.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 165,560.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.15 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 3" Alexsindo natural"
Bahan
1.1000 m' Kusen Alumunium 3" Alexsindo natural @Rp. 48,000.00 = Rp. 52,800.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 56,660.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.16 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 3" Alexsindo coklat"
Bahan
1.1000 m' Kusen Alumunium 3" Alexsindo coklat @Rp. 63,000.00 = Rp. 69,300.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 73,160.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.17 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 3" Alko natural"
Bahan
1.1000 m' Kusen Alumunium 3" Alko natural @Rp. 42,000.00 = Rp. 46,200.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 50,060.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.18 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 3" Alko coklat"
Bahan
1.1000 m' Kusen Alumunium 3" Alko coklat @Rp. 58,000.00 = Rp. 63,800.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 67,660.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.19 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 3" YKK natural"
Bahan
1.1000 m' Kusen Alumunium 3" YKK natural @Rp. 95,000.00 = Rp. 104,500.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 108,360.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
X.20 1 m' Memasang 1 m kusen pintu alluminium - "Kusen Alumunium 3" YKK coklat"
Bahan
1.1000 m' Kusen Alumunium 3" YKK coklat @Rp. 126,000.00 = Rp. 138,600.00
2.0000 buah skrup fixer @Rp. 1,000.00 = Rp. 2,000.00
0.0600 tube Sealant @Rp. 31,000.00 = Rp. 1,860.00
Rp. 142,460.00
Tenaga
0.0430 Oh Pekerja @Rp. 45,000.00 = Rp. 1,935.00
0.0430 Oh Tukang besi konstruksi @Rp. 55,000.00 = Rp. 2,365.00
0.0043 Oh Kepala tukang @Rp. 57,500.00 = Rp. 247.25
0.0021 Oh Mandor @Rp. 60,000.00 = Rp. 126.00
Rp. 4,673.25
XI.11 1 m' 1 M' Pasang atap genteng bubung palentong/ vlampress super/ besar
Bahan
- 4.0000 Bh Nok Genteng Plenthong / Vlampress be @Rp. 5,250.00 = Rp. 21,000.00
- 8.0000 Kg Semen PC ( Portland Cement ) 40 kg @Rp. 1,900.00 = Rp. 15,200.00
- 0.0320 M3 Pasir pasang (kaliworo) @Rp. 147,000.00 = Rp. 4,704.00
Rp. 40,904.00
Tenaga
- 0.4000 Oh Pekerja @Rp. 45,000.00 = Rp. 18,000.00
- 0.2000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 11,000.00
- 0.0200 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,150.00
- 0.0020 Oh Mandor @Rp. 60,000.00 = Rp. 120.00
Rp. 30,270.00
XI.12 1 m' 1 M' Pasang atap genteng bubung kodok
Bahan
- 5.0000 Bh Nok genteng kodok @Rp. 5,250.00 = Rp. 26,250.00
- 8.0000 Kg Semen PC ( Portland Cement ) 40 kg @Rp. 1,900.00 = Rp. 15,200.00
- 0.0320 M3 Pasir pasang (kaliworo) @Rp. 147,000.00 = Rp. 4,704.00
Rp. 46,154.00
Tenaga
- 0.4000 Oh Pekerja @Rp. 45,000.00 = Rp. 18,000.00
- 0.2000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 11,000.00
- 0.0200 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,150.00
- 0.0020 Oh Mandor @Rp. 60,000.00 = Rp. 120.00
Rp. 30,270.00
XI.15 1 m2 1 M2 Pasang atap asbes gelombang gelombang besar (200 x 102 x 0,5 ) cm
Bahan
- 0.5250 Lbr Asbes Gelombang besar (200 x 102 x 0,@Rp. 73,500.00 = Rp. 38,587.50
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 41,347.50
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.16 1 m2 1 M2 Pasang atas asbes gelombang gelombang besar (225 x 102 x 0,5) cm
Bahan
- 0.4667 Lbr Asbes Gelombang besar (225 x 102 x 0,@Rp. 73,500.00 = Rp. 34,302.45
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 37,062.45
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.17 1 m2 1 M2 Pasang atas asbes gelombang gelombang besar (250 x 102 x 0,5 ) cm
Bahan
- 0.4200 Lbr Asbes Gelombang besar (250 x 102 x 0,@Rp. 92,000.00 = Rp. 38,640.00
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 41,400.00
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.18 1 m2 1 M2 Pasang atap asbes gelombang gelombang besar (200 x 102 x 0,6 ) cm
Bahan
- 0.5250 Lbr Asbes Gelombang besar (200 x 102 x 0,@Rp. 85,000.00 = Rp. 44,625.00
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 47,385.00
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.19 1 m2 1 M2 Pasang atas asbes gelombang gelombang besar (225 x 102 x 0,6) cm
Bahan
- 0.4667 Lbr Asbes Gelombang besar (225 x 102 x 0,@Rp. 92,500.00 = Rp. 43,169.75
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 45,929.75
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.20 1 m2 1 M2 Pasang atas asbes gelombang gelombang besar (250 x 102 x 0,6 ) cm
Bahan
- 0.4200 Lbr Asbes Gelombang besar (250 x 102 x 0,@Rp. 105,000.00 = Rp. 44,100.00
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 46,860.00
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.21 1 m2 1 M2 Pasang atas asbes gelombang gelombang kecil (300 x 105 x 0,4) cm
Bahan
- 0.3500 Lbr Asbes Gelombang kecil (300 x 105 x 0,4@Rp. 87,000.00 = Rp. 30,450.00
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 33,210.00
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0700 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,850.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,972.50
XI.22 1 m2 1 M2 Pasang atas asbes gelombang gelombang kecil (240 x 105 x 0,4) cm
Bahan
- 0.4375 Lbr Asbes Gelombang kecil (240 x 105 x 0,4@Rp. 69,500.00 = Rp. 30,406.25
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 33,166.25
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0670 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,685.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,807.50
XI.23 1 m2 1 M2 Pasang atas asbes gelombang gelombang kecil (210 x 105 x 0,4) cm
Bahan
- 0.5000 Lbr Asbes Gelombang kecil (210 x 105 x 0,4@Rp. 60,500.00 = Rp. 30,250.00
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 33,010.00
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0670 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,685.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,807.50
XI.24 1 m2 1 M2 Pasang atas asbes gelombang gelombang kecil (180 x 105 x 0,4) cm
Bahan
- 0.5833 Lbr Asbes Gelombang kecil (180 x 105 x 0,4@Rp. 52,000.00 = Rp. 30,331.60
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 33,091.60
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0670 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,685.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,807.50
XI.25 1 m2 1 M2 Pasang atas asbes gelombang gelombang kecil (150 x 105 x 0,4) cm
Bahan
- 0.7000 Lbr Asbes Gelombang kecil (150 x 105 x 0,4@Rp. 43,000.00 = Rp. 30,100.00
- 0.1200 Kg Paku asbes @Rp. 23,000.00 = Rp. 2,760.00
Rp. 32,860.00
Tenaga
- 0.1400 Oh Pekerja @Rp. 45,000.00 = Rp. 6,300.00
- 0.0670 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 3,685.00
- 0.0070 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 402.50
- 0.0070 Oh Mandor @Rp. 60,000.00 = Rp. 420.00
Rp. 10,807.50
XI.33 1 m' 1 M' Pasang talang datar, seng bjls 0,3 Lebar 60 cm
Bahan
- 1.1000 M' Seng BJLS 0,30 L = 60 cm @Rp. 27,000.00 = Rp. 29,700.00
- 0.0150 Kg Paku usuk @Rp. 14,000.00 = Rp. 210.00
- 0.0096 M3 Papan kayu meranti @Rp. 5,775,000.00 = Rp. 55,440.00
- 0.2500 Kg Cat Meni Besi "altex" @Rp. 28,000.00 = Rp. 7,000.00
Rp. 92,350.00
Tenaga
- 0.1500 Oh Pekerja @Rp. 45,000.00 = Rp. 6,750.00
- 0.4000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 22,000.00
- 0.0250 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,437.50
- 0.0013 Oh Mandor @Rp. 60,000.00 = Rp. 75.00
Rp. 30,262.50
XI.34 1 m' 1 M' Pasang talang miring, seng bjls 0,3 Lebar 60 cm
Bahan
- 1.1000 M' Seng BJLS 0,30 L = 60 cm @Rp. 27,000.00 = Rp. 29,700.00
- 0.0150 Kg Paku usuk @Rp. 14,000.00 = Rp. 210.00
- 0.0100 M3 Papan kayu meranti @Rp. 5,775,000.00 = Rp. 57,750.00
- 0.3000 Kg Cat Meni Besi "altex" @Rp. 28,000.00 = Rp. 8,400.00
Rp. 96,060.00
Tenaga
- 0.0400 Oh Pekerja @Rp. 45,000.00 = Rp. 1,800.00
- 0.4000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 22,000.00
- 0.0250 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,437.50
- 0.0013 Oh Mandor @Rp. 60,000.00 = Rp. 75.00
Rp. 25,312.50
XI.37 1 m' 1 M' Pasang atap genteng bubung keramik KIA/M Klas
Bahan
- 4.0000 Bh Genteng keramik bubungan @Rp. 20,000.00 = Rp. 80,000.00
- 10.8000 Kg Semen PC ( Portland Cement ) 40 kg @Rp. 1,900.00 = Rp. 20,520.00
- 0.0320 M3 Pasir pasang (kaliworo) @Rp. 147,000.00 = Rp. 4,704.00
Rp. 105,224.00
Tenaga
- 0.4000 Oh Pekerja @Rp. 45,000.00 = Rp. 18,000.00
- 0.2000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 11,000.00
- 0.0200 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,150.00
- 0.0020 Oh Mandor @Rp. 60,000.00 = Rp. 120.00
Rp. 30,270.00
XI.38 1 m' 1 M' Pasang atap genteng bubung keramik glasur morando
Bahan
- 4.0000 Bh Genteng keramik bubungan @Rp. 7,350.00 = Rp. 29,400.00
- 10.8000 Kg Semen PC ( Portland Cement ) 40 kg @Rp. 1,900.00 = Rp. 20,520.00
- 0.0320 M3 Pasir pasang (kaliworo) @Rp. 147,000.00 = Rp. 4,704.00
Rp. 54,624.00
Tenaga
- 0.4000 Oh Pekerja @Rp. 45,000.00 = Rp. 18,000.00
- 0.2000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 11,000.00
- 0.0200 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 1,150.00
- 0.0020 Oh Mandor @Rp. 60,000.00 = Rp. 120.00
Rp. 30,270.00
XII.28 1 m' Memasang 1 M' pipa PVC tipe AW diameter 3/4" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 3/4" @Rp. 5,500.00 = Rp. 6,600.00
- 0.3500 Perlengkapan @Rp. 5,500.00 = Rp. 1,925.00
Rp. 8,525.00
Tenaga
- 0.0360 Oh Tukang Gali @Rp. 50,000.00 = Rp. 1,800.00
- 0.0600 Oh Tukang @Rp. 55,000.00 = Rp. 3,300.00
- 0.0060 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 345.00
- 0.0018 Oh Mandor @Rp. 60,000.00 = Rp. 108.00
Rp. 5,553.00
XII.29 1 m' Memasang 1 M' pipa PVC tipe AW diameter 1" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 1" @Rp. 7,000.00 = Rp. 8,400.00
- 0.3500 Perlengkapan @Rp. 7,000.00 = Rp. 2,450.00
Rp. 10,850.00
Tenaga
- 0.0360 Oh Tukang Gali @Rp. 50,000.00 = Rp. 1,800.00
- 0.0600 Oh Tukang @Rp. 55,000.00 = Rp. 3,300.00
- 0.0060 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 345.00
- 0.0018 Oh Mandor @Rp. 60,000.00 = Rp. 108.00
Rp. 5,553.00
XII.30 1 m' Memasang 1 M' pipa PVC tipe AW diameter 1 1/2" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 1 1/2" @Rp. 13,250.00 = Rp. 15,900.00
- 0.3500 Perlengkapan @Rp. 13,250.00 = Rp. 4,637.50
Rp. 20,537.50
Tenaga
- 0.0360 Oh Tukang Gali @Rp. 50,000.00 = Rp. 1,800.00
- 0.0600 Oh Tukang @Rp. 55,000.00 = Rp. 3,300.00
- 0.0060 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 345.00
- 0.0018 Oh Mandor @Rp. 60,000.00 = Rp. 108.00
Rp. 5,553.00
XII.31 1 m' Memasang 1 M' pipa PVC tipe AW diameter 2" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 2" @Rp. 18,750.00 = Rp. 22,500.00
- 0.3500 Perlengkapan @Rp. 18,750.00 = Rp. 6,562.50
Rp. 29,062.50
Tenaga
- 0.0540 Oh Tukang Gali @Rp. 50,000.00 = Rp. 2,700.00
- 0.0900 Oh Tukang @Rp. 55,000.00 = Rp. 4,950.00
- 0.0090 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 517.50
- 0.0027 Oh Mandor @Rp. 60,000.00 = Rp. 162.00
Rp. 8,329.50
XII.32 1 m' Memasang 1 M' pipa PVC tipe AW diameter 2 1/2" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 2 1/2" @Rp. 24,500.00 = Rp. 29,400.00
- 0.3500 Perlengkapan @Rp. 24,500.00 = Rp. 8,575.00
Rp. 37,975.00
Tenaga
- 0.0540 Oh Tukang Gali @Rp. 50,000.00 = Rp. 2,700.00
- 0.0900 Oh Tukang @Rp. 55,000.00 = Rp. 4,950.00
- 0.0090 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 517.50
- 0.0027 Oh Mandor @Rp. 60,000.00 = Rp. 162.00
Rp. 8,329.50
XII.33 1 m' Memasang 1 M' pipa PVC tipe AW diameter 3" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 3" @Rp. 34,750.00 = Rp. 41,700.00
- 0.3500 Perlengkapan @Rp. 34,750.00 = Rp. 12,162.50
Rp. 53,862.50
Tenaga
- 0.0810 Oh Tukang Gali @Rp. 50,000.00 = Rp. 4,050.00
- 0.1350 Oh Tukang @Rp. 55,000.00 = Rp. 7,425.00
- 0.0135 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 776.25
- 0.0041 Oh Mandor @Rp. 60,000.00 = Rp. 246.00
Rp. 12,497.25
XII.34 1 m' Memasang 1 M' pipa PVC tipe AW diameter 4" Maspion
Bahan
- 1.2000 M' Pipa PVC class AW 4" @Rp. 54,750.00 = Rp. 65,700.00
- 0.3500 Perlengkapan @Rp. 54,750.00 = Rp. 19,162.50
Rp. 84,862.50
Tenaga
- 0.0810 Oh Tukang Gali @Rp. 50,000.00 = Rp. 4,050.00
- 0.1350 Oh Tukang @Rp. 55,000.00 = Rp. 7,425.00
- 0.0135 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 776.25
- 0.0041 Oh Mandor @Rp. 60,000.00 = Rp. 246.00
Rp. 12,497.25
XII.35 1 bh Memasang 1 bh bak cuci piring / Kitchen zinc / Washbak - "Royal kecil"
Bahan
- 1.0000 Bh Washbak "Royal Kecil" @Rp. 179,000.00 = Rp. 179,000.00
- 1.0000 Set Water drain + asesoris @Rp. 37,000.00 = Rp. 37,000.00
Rp. 216,000.00
Tenaga
- 0.0300 Oh Pekerja @Rp. 45,000.00 = Rp. 1,350.00
- 0.3000 Oh Tukang @Rp. 55,000.00 = Rp. 16,500.00
- 0.0300 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 1,725.00
- 0.0015 Oh Mandor @Rp. 60,000.00 = Rp. 90.00
Rp. 19,665.00
XII.36 1 bh Memasang 1 bh bak cuci piring / Kitchen zinc / Washbak - "Royal besar"
Bahan
- 1.0000 Bh Washbak "Royal besar" @Rp. 302,000.00 = Rp. 302,000.00
- 1.0000 Set Water drain + asesoris @Rp. 37,000.00 = Rp. 37,000.00
Rp. 339,000.00
Tenaga
- 0.0300 Oh Pekerja @Rp. 45,000.00 = Rp. 1,350.00
- 0.3000 Oh Tukang @Rp. 55,000.00 = Rp. 16,500.00
- 0.0300 Oh Kepala Tukang @Rp. 57,500.00 = Rp. 1,725.00
- 0.0015 Oh Mandor @Rp. 60,000.00 = Rp. 90.00
Rp. 19,665.00
XIV. 4 1 m2 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup - "Emco"
Bahan
- 0.2000 Kg Cat Meni Kayu "altex" @Rp. 28,000.00 = Rp. 5,600.00
- 0.1500 Kg Plamir @Rp. 27,000.00 = Rp. 4,050.00
- 0.1700 Kg Cat dasar "emco" @Rp. 53,000.00 = Rp. 9,010.00
- 0.2600 Kg Cat Besi/ Kayu "Emco" warna sta@Rp. 53,000.00 = Rp. 13,780.00
Rp. 32,440.00
Tenaga
- 0.0700 Oh Pekerja @Rp. 45,000.00 = Rp. 3,150.00
- 0.0090 Oh Tukang Cat @Rp. 55,000.00 = Rp. 495.00
- 0.0060 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 345.00
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 4,140.00
XIV. 5 1 m2 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup - "Emco"
Bahan
- 0.2000 Kg Cat Meni Kayu "altex" @Rp. 28,000.00 = Rp. 5,600.00
- 0.1500 Kg Plamir @Rp. 27,000.00 = Rp. 4,050.00
- 0.1700 Kg Cat dasar "emco" @Rp. 53,000.00 = Rp. 9,010.00
- 0.3500 Kg Cat Besi/ Kayu "Emco" warna sta@Rp. 53,000.00 = Rp. 18,550.00
Rp. 37,210.00
Tenaga
- 0.0700 Oh Pekerja @Rp. 45,000.00 = Rp. 3,150.00
- 0.1050 Oh Tukang Cat @Rp. 55,000.00 = Rp. 5,775.00
- 0.0040 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 230.00
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 9,305.00
XIV. 7 1 m2 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup - "dulux"
Bahan
- 0.2000 Kg Cat Meni Kayu "altex" @Rp. 28,000.00 = Rp. 5,600.00
- 0.1500 Kg Plamir @Rp. 27,000.00 = Rp. 4,050.00
- 0.1700 Kg Cat dasar "dulux" @Rp. 71,000.00 = Rp. 12,070.00
- 0.2600 Kg Cat Besi/ Kayu "dulux" warna sta @Rp. 71,000.00 = Rp. 18,460.00
Rp. 40,180.00
Tenaga
- 0.0700 Oh Pekerja @Rp. 45,000.00 = Rp. 3,150.00
- 0.0090 Oh Tukang Cat @Rp. 55,000.00 = Rp. 495.00
- 0.0060 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 345.00
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 4,140.00
XIV. 8 1 m2 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup - "dulux"
Bahan
- 0.2000 Kg Cat Meni Kayu "altex" @Rp. 28,000.00 = Rp. 5,600.00
- 0.1500 Kg Plamir @Rp. 27,000.00 = Rp. 4,050.00
- 0.1700 Kg Cat dasar "dulux" @Rp. 71,000.00 = Rp. 12,070.00
- 0.3500 Kg Cat Besi/ Kayu "dulux" warna sta @Rp. 71,000.00 = Rp. 24,850.00
Rp. 46,570.00
Tenaga
- 0.0700 Oh Pekerja @Rp. 45,000.00 = Rp. 3,150.00
- 0.1050 Oh Tukang Cat @Rp. 55,000.00 = Rp. 5,775.00
- 0.0040 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 230.00
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 9,305.00
XIV. 10 1 m2 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup - "Mowilex"
Bahan
- 0.2000 Kg Cat Meni Kayu "altex" @Rp. 28,000.00 = Rp. 5,600.00
- 0.1500 Kg Plamir @Rp. 27,000.00 = Rp. 4,050.00
- 0.1700 Kg Cat dasar "Mowilex" @Rp. 69,000.00 = Rp. 11,730.00
- 0.2600 Kg Cat Besi/ Kayu "Mowilex" warna @Rp. 69,000.00 = Rp. 17,940.00
Rp. 39,320.00
Tenaga
- 0.0700 Oh Pekerja @Rp. 45,000.00 = Rp. 3,150.00
- 0.0090 Oh Tukang Cat @Rp. 55,000.00 = Rp. 495.00
- 0.0060 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 345.00
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 4,140.00
XIV. 11 1 m2 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup - "Mowilex"
Bahan
- 0.2000 Kg Cat Meni Kayu "altex" @Rp. 28,000.00 = Rp. 5,600.00
- 0.1500 Kg Plamir @Rp. 27,000.00 = Rp. 4,050.00
- 0.1700 Kg Cat dasar "Mowilex" @Rp. 69,000.00 = Rp. 11,730.00
- 0.3500 Kg Cat Besi/ Kayu "Mowilex" warna @Rp. 69,000.00 = Rp. 24,150.00
Rp. 45,530.00
Tenaga
- 0.0700 Oh Pekerja @Rp. 45,000.00 = Rp. 3,150.00
- 0.1050 Oh Tukang Cat @Rp. 55,000.00 = Rp. 5,775.00
- 0.0040 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 230.00
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 9,305.00
XIV. 16 1 m2 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) - "Decolith"
Bahan
- 0.1000 Kg Plamur Tembok @Rp. 37,000.00 = Rp. 3,700.00
- 0.1000 Kg Cat dasar @Rp. 16,000.00 = Rp. 1,600.00
- 0.2600 Kg Cat tembok "Decolith" warna sta @Rp. 16,000.00 = Rp. 4,160.00
Rp. 9,460.00
Tenaga
- 0.0200 Oh Pekerja @Rp. 45,000.00 = Rp. 900.00
- 0.0630 Oh Tukang Cat @Rp. 55,000.00 = Rp. 3,465.00
- 0.0063 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 362.25
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 4,877.25
XIV. 17 1 m2 1 M2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
Bahan
- 0.1200 Kg Cat dasar @Rp. 16,000.00 = Rp. 1,920.00
- 0.1800 Kg Cat tembok "Decolith" warna sta @Rp. 16,000.00 = Rp. 2,880.00
Rp. 4,800.00
Tenaga
- 0.0280 Oh Pekerja @Rp. 45,000.00 = Rp. 1,260.00
- 0.0420 Oh Tukang Cat @Rp. 55,000.00 = Rp. 2,310.00
- 0.0042 Oh Kepala Tukang Cat @Rp. 57,500.00 = Rp. 241.50
- 0.0025 Oh Mandor @Rp. 60,000.00 = Rp. 150.00
Rp. 3,961.50
XV. 10 1 m3 1 M3 Membongkar kayu balok loteng/ kuda-kuda/ dlurung/ jembatan untuk dipakai lagi
Bahan
Tenaga
- 4.0000 Oh Pekerja @Rp. 45,000.00 = Rp. 180,000.00
- 6.0000 Oh Tukang Kayu @Rp. 55,000.00 = Rp. 330,000.00
- 0.6000 Oh Kepala Tukang Kayu @Rp. 57,500.00 = Rp. 34,500.00
- 0.2000 Oh Mandor @Rp. 60,000.00 = Rp. 12,000.00
Rp. 556,500.00
WALIKOTA SALATIGA,
YULIYANTO
Rp. 361,755.00
Rp. 248,830.00
Rp. 7,500.00
Rp. 360,605.00
Rp. 137,880.00
Rp. 41,370.00
Rp. 35,250.00
Rp. 43,200.00
Rp. 51,270.00
Rp. 46,920.00
Rp. 71,100.00
Rp. 56,700.00
Rp. 2,550.00
Rp. 15,450.00
Rp. 11,748.00
Rp. 25,500.00
Rp. 176,100.00
Rp. 108,750.00
Rp. 367,650.00
Rp. 353,452.50
Rp. 797,545.00
Rp. 728,590.00
Rp. 680,818.00
Rp. 647,217.00
Rp. 601,198.00
Rp. 531,600.10
Rp. 2,243,457.50
Rp. 757,295.00
1.43
Rp. 1,070,427.50
Rp. 1,123,418.70
Rp. 1,164,819.17 Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %
Rp. 1,005,005.09
Rp. 1,214,042.78
Rp. 1,260,565.46
Rp. 1,296,034.44
Rp. 1,318,518.70
Rp. 1,356,915.00
Rp. 1,368,914.54
Rp. 1,414,188.15
Rp. 1,429,795.09
Rp. 12,770.25
Rp. 12,770.25
Rp. 59,655.00
Rp. 61,492.50
0.18 0.012
0.35
Rp. 152,390.00
0.0080
833,333.333
1,187,500.000
Rp. 181,090.00
Rp. 157,902.50
Rp. 186,602.50
Rp. 236,390.00
Rp. 197,090.00
Rp. 184,902.50
Rp. 196,602.50
Rp. 148,715.00
Rp. 177,415.00
Rp. 38,869.50
Rp. 64,245.00
Rp. 77,835.00
Rp. 233,360.00
Rp. 214,932.00
Rp. 203,066.00
Rp. 196,124.00
Rp. 192,034.00
Rp. 171,872.75
Rp. 111,066.00
Rp. 102,658.00
Rp. 97,646.00
Rp. 94,482.00
Rp. 92,486.00
Rp. 89,175.00
Rp. 85,469.50
Rp. 96,779.00
Rp. 91,520.00
Rp. 41,078.10
Rp. 37,167.90
Rp. 34,396.50
Rp. 32,684.10
Rp. 31,371.90
Rp. 30,606.90
Rp. 29,841.90
Rp. 54,499.80
Rp. 48,886.20
Rp. 45,142.00
Rp. 42,907.80
Rp. 41,109.20
Rp. 25,154.10
Rp. 28,691.00
Rp. 27,195.00
Rp. 17,387.70
Rp. 8,810.00
Rp. 36,715.00
Rp. 19,480.00
Rp. 7,887,000.00
Rp. 13,662,000.00
Rp. 11,352,000.00
Rp. 312,317.50
Rp. 543,317.50
Rp. 490,837.50
Rp. 437,875.00
Rp. 668,875.00
Rp. 616,395.00
Rp. 302,700.00
Rp. 441,300.00
Rp. 409,812.00
Rp. 606,850.00
Rp. 976,450.00
Rp. 892,482.00
Rp. 364,715.00
Rp. 509,090.00
Rp. 476,290.00
Rp. 494,700.00
Rp. 841,200.00
Rp. 762,480.00
Rp. 371,515.00
Rp. 515,890.00
Rp. 483,090.00
Rp. 7,486,900.00
Rp. 13,839,400.00
Rp. 6,947,100.00
Rp. 13,299,600.00
3.00 0.40
4.50 3.64
0.0105
6.00
0.0054 0.20
4.55
Rp. 106,197.50
0.0105 0.25
0.0048
Rp. 106,197.50
0.0088
0.0033 20,212.5
0.0033 80,850.00
Rp. 84,252.50
0.0088
0.0030
0.2000
Rp. 92,337.50
Rp. 189,672.50
Rp. 189,672.50
Rp. 147,777.50
Rp. 163,212.50
0.0126 3.00
0.03
Rp. 121,847.50
0.0123
Rp. 77,747.50
0.0099
166.6667
0.0090
1.500
Rp. 43,760.00
Rp. 56,465.00
Rp. 75,522.50
Rp. 69,170.00
Rp. 94,580.00
Rp. 132,695.00
Rp. 198,367.50
35.71
0.3472
0.69
Rp. 240,929.72
2.88
0.694
Rp. 247,874.17
Rp. 183,575.00
Rp. 214,816.00
Rp. 42,659.25
Rp. 144,562.30
Rp. 138,501.70
Rp. 145,572.40
Rp. 131,431.00
Rp. 137,491.60
Rp. 140,521.90
Rp. 138,501.70
Rp. 128,400.70
Rp. 126,380.50
Rp. 138,501.70
Rp. 143,552.20
Rp. 164,764.30
Rp. 170,824.90
Rp. 150,391.00
Rp. 156,641.20
Rp. 145,182.50
Rp. 132,682.10
Rp. 147,265.90
Rp. 143,099.10
Rp. 143,099.10
Rp. 148,307.60
Rp. 128,515.30
Rp. 157,682.90
Rp. 142,057.40
Rp. 147,265.90
Rp. 183,725.40
Rp. 192,059.00
Rp. 175,391.80
Rp. 151,432.70
Rp. 154,557.80
Rp. 151,432.70
Rp. 153,516.10
Rp. 164,974.80
Rp. 150,897.50
Rp. 120,972.50
Rp. 148,797.50
Rp. 257,686.10
Rp. 246,227.40
Rp. 246,227.40
Rp. 246,227.40
Rp. 212,190.50
Rp. 193,441.70
Rp. 193,441.70
Rp. 193,441.70
Rp. 129,187.50
Rp. 119,737.50
Rp. 217,032.50
Rp. 223,632.50
Rp. 234,632.50
Rp. 165,332.50
Rp. 165,332.50
Rp. 170,832.50
Rp. 170,832.50
Rp. 217,032.50
0.21
Rp. 229,132.50
Rp. 165,332.50
Rp. 170,832.50
0.0300
35.0000
27.0000
1.2963
Rp. 138,909.90
0.0400
26.2500
24.0000
1.0938
Rp. 136,846.50
Rp. 122,058.00
Rp. 118,251.90
Rp. 22,902.50
0.347
Rp. 27,355.00
Rp. 30,825.00
Rp. 183,900.00
6.00
0.17
Rp. 92,093.00
Rp. 93,156.00
Rp. 92,462.00
Rp. 91,421.00
Rp. 30,256.50
Rp. 10,332.50
Rp. 15,542.50
Rp. 15,325.00
Rp. 18,625.00
Rp. 530,757.50
Rp. 2,541.50
Rp. 306,260.00
Rp. 572,850.00
Rp. 73,440.00
Rp. 371,750.00
Rp. 77,833.25
Rp. 89,933.25
Rp. 72,333.25
Rp. 84,433.25
Rp. 147,133.25
Rp. 170,233.25
Rp. 61,333.25
Rp. 77,833.25
Rp. 54,733.25
Rp. 72,333.25
Rp. 113,033.25
Rp. 147,133.25
Rp. 748,407.50
Rp. 170,092.50
Rp. 305,999.32
Rp. 123,232.50
Rp. 51,815.00
Rp. 51,815.00
Rp. 57,675.00
Rp. 50,875.00
Rp. 48,675.00
Rp. 42,675.00
Rp. 47,175.00
Rp. 42,675.00
Rp. 56,175.00
Rp. 76,424.00
Rp. 71,174.00
Rp. 76,424.00
Rp. 73,869.00
Rp. 77,544.00
Rp. 52,320.00
0.4200
Rp. 48,034.95
Rp. 52,372.50
1.05
2
0.5250
Rp. 58,357.50
Rp. 56,902.25
Rp. 57,832.50
0.3500
Rp. 44,182.50
0.4375
Rp. 43,973.75
0.5
Rp. 43,817.50
0.7
Rp. 43,899.10
Rp. 43,667.50
Rp. 45,555.00
Rp. 67,135.00
2.5000
0.4
0.424
0.0004896073903
Rp. 190,405.00
0.52632
1.9
Rp. 120,139.60
Rp. 49,062.50
Rp. 75,352.50
Rp. 125,173.36
Rp. 122,612.50
0.005
0.0100
Rp. 121,372.50
Rp. 112,375.00
Rp. 60,375.00
Rp. 135,494.00
Rp. 84,894.00
Rp. 17,362.50
Rp. 1,366,305.00
Rp. 199,332.50
Rp. 1,460,220.00
Rp. 816,175.00
Rp. 927,475.00
Rp. 566,015.00
Rp. 622,195.00
Rp. 704,875.00
Rp. 538,455.00
Rp. 454,715.00
Rp. 482,275.00
Rp. 427,155.00
Rp. 454,715.00
Rp. 510,895.00
Rp. 538,455.00
Rp. 369,245.00
Rp. 448,245.00
Rp. 59,585.88
Rp. 65,585.88
Rp. 33,295.83
Rp. 39,237.50
Rp. 45,695.83
Rp. 65,225.67
Rp. 71,425.67
Rp. 81,242.33
Rp. 105,043.42
Rp. 12,140.50
Rp. 14,078.00
Rp. 16,403.00
Rp. 26,090.50
Rp. 37,392.00
Rp. 46,304.50
Rp. 66,359.75
Rp. 97,359.75
Rp. 235,665.00
Rp. 358,665.00
Rp. 240,665.00
Rp. 203,665.00
Rp. 101,900.00
Rp. 111,900.00
Rp. 43,900.00
Rp. 69,900.00
Rp. 27,900.00
Rp. 71,900.00
Rp. 159,900.00
Rp. 85,900.00
Rp. 64,900.00
Rp. 48,900.00
Rp. 153,825.00
Rp. 75,825.00
Rp. 48,825.00
Rp. 22,825.00
Rp. 48,825.00
Rp. 12,825.00
Rp. 11,825.00
Rp. 200,825.00
Rp. 133,825.00
Rp. 343,825.00
Rp. 181,825.00
Rp. 238,825.00
Rp. 202,825.00
Rp. 126,825.00
Rp. 86,825.00
Rp. 91,825.00
Rp. 118,825.00
Rp. 133,825.00
Rp. 32,832.50
Rp. 33,832.50
Rp. 36,832.50
Rp. 25,832.50
Rp. 23,832.50
Rp. 26,832.50
Rp. 23,832.50
Rp. 17,832.50
Rp. 23,832.50
Rp. 38,832.50
Rp. 51,832.50
Rp. 44,832.50
Rp. 30,832.50
Rp. 28,832.50
Rp. 38,832.50
Rp. 28,832.50
Rp. 19,832.50
Rp. 28,832.50
Rp. 20,832.50
Rp. 17,832.50
Rp. 14,832.50
Rp. 156,775.00
Rp. 400,775.00
Rp. 140,775.00
Rp. 164,775.00
Rp. 137,775.00
Rp. 111,775.00
Rp. 164,775.00
Rp. 249,330.00
Rp. 223,330.00
Rp. 144,330.00
Rp. 73,632.50
Rp. 96,732.50
Rp. 212,232.50
Rp. 299,132.50
Rp. 82,432.50
Rp. 117,632.50
Rp. 79,132.50
Rp. 106,632.50
Rp. 299,132.50
Rp. 7,800.00
Rp. 7,300.00
Rp. 29,926.25
Rp. 36,580.00
Rp. 46,515.00
Rp. 36,046.25
Rp. 44,320.00
Rp. 55,875.00
Rp. 35,366.25
Rp. 43,460.00
Rp. 54,835.00
Rp. 19,477.50
Rp. 35,566.00
Rp. 8,710.00
Rp. 24,300.00
Rp. 14,337.25
Rp. 8,761.50
Rp. 16,530.00
Rp. 52,248.75
Rp. 238,000.00
Rp. 287,000.00
Rp. 114,500.00
Rp. 9,600.00
Rp. 2,400.00
Rp. 9,600.00
Rp. 7,500.00
Rp. 13,245.00
Rp. 9,600.00
Rp. 556,500.00
Rp. 57,000.00
Rp. 37,600.00
0.8333
Rp. 101,866.67
Rp. 84,050.00
Rp. 81,050.00
Rp. 84,050.00
Rp. 81,050.00
Rp. 94,050.00
Rp. 97,050.00
Rp. 147,592.60
KOTA SALATIGA,
YULIYANTO
ESTIMASI KEBUTUHAN BAHAN / UPAH
PERENCANAAN RUMAH BERTINGKAT
Kepala tukang
Tukang kayu
paku 2"-4"
Mandor
Pekerja
I PEKERJAAN PERSIAPAN VOLUME AN.
m3 kg m3 OH OH OH OH
1 Pengukuran/Uitzet bouwplank 37.250 m' II.1 0.04 0.75 0.26 3.73 3.73 0.37 0.19
2 Pembersihan Lahan 250.100 m2 I.3 25.01 12.51
JUMLAH 0.04 0.75 0.26 28.74 3.73 0.37 12.69
pasir urug
mandor
pekerja
II PEKERJAAN TANAH VOLUME ANALISA
m3 OH OH
1 Penggalian tanah biasa sedalam 1 m 150.104 m3 II.2 112.58 3.75
2 Pengurugan kembali galian tanah 85.126 m3 II.10 21.28 0.71
3 Pengurugan dengan pasir urug 19.333 m3 II.12 23.20 5.80 0.19
JUMLAH 23.20 139.66 4.65
Batu belah 15 cm/20 cm
Pasir Pasang
Tukang batu
Pasir urug
Mandor
Pekerja
III PEKERJAAN PONDASI VOLUME ANALISA
m3 kg m3 m3 OH OH OH OH
1 Pemasangan pondasi batu belah campuran 1 SP : 8 PP 54.624 m3 III.6 65.55 4970.8 31.90 81.94 32.77 3.28 4.10
2 Pemasangan batu kosong ( anstamping ) 19.269 m3 III.1 23.12 8.32 15.03 7.51 0.75 0.75
JUMLAH 88.67 4970.8 31.90 8.32 96.97 40.29 4.03 4.85
Kerikil (maks 30 mm)
kerikil beton
Pasir Beton
Air
IV PEKERJAAN BETON VOLUME ANALISA
kg kg kg Liter kg kg m3 kg kg
1 Membuat Beton mutu, f'c = 7,4 Mpa (K 100), slump (12±2) cm, w/c = 0,87
59.712 m3 IV.1 14749 51890 59652 12838
2 Pembesian Dengan Besi Polos 4851.6 kg IV.13 5094 72.77
3 Begesting Untuk Pondasi 355.51 m2 IV.29 1955 3 1280 17.78 0.53 7.11 5.33
4 Membuat Balok Beton Bertulang 140.35 m1 IV.15 3.16 42.11
JUMLAH 16704 51893 59652 12838 6374 90.55 3.69 49.22 5.33
Tukang kayu
Tukang besi
mandor
pekerja
OH OH OH OH OH OH OH OH
98.52 16.42 1.67 4.96
33.96 33.96 3.40 19.41
105.59 11.73 11.73 3.56 11.73 5.33
72.98 36.49 3.65 3.65
311.05 28.15 1.67 11.73 37.52 51.62 3.65 33.34
Kepala Tukang
Besi baja IWF
Tukang Besi
Tukang las
Besi siku
Mandor
Pekerja
V PEKERJAAN BESI DAN ALUMUNIUM VOLUME ANALISA
kg kg m2 OH OH OH OH OH
1 Pemasangan strip 604.800 kg X.2 665.28 36.29 36.29 3.63 1.81
2 Pemasangan begel 321.300 kg X.2
3 Pemasangan baut 14.380 m1 X.1 15.82 0.86 0.86 0.09 0.04
4 Pemasangan reling tangga 2.000 unit X.8 2.00 2.00 2.00 0.20 0.10
JUMLAH 665.28 15.82 2.00 39.15 2.00 37.15 3.92 1.96
Semen Portland
Kepala Tukang
Tukang Batu
Pasir Pasang
Bata Rooster
Bata Merah
mandor
pekerja
VI PEKERJAAN PASANGAN DINDING VOLUME ANALISA
m3 kg m3 m3 OH OH OH OH
1 Pas. dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 3 162.53 m2 V.2 22754.1 7070.0 13.00 97.52 32.51 3.25 4.88
2 Pas, 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu cam. 1 SP : 831.44 m2 V.12 58201 5404.4 41.57 249.43 83.14 8.31 12.47
3 Pemasangan dinding terawang (rooster) 12 x 11 x 24 campuran 1 SP : 3 81.000 bh V.14 891.0 2.59 2430.0 24.30 8.10 0.81 1.22
JUMLAH 80955 13365.4 57.17 2430.0 371.25 123.75 12.37 18.56
Semen Portland
Kepala Tukang
Tukang Batu
Pasir Pasang
mandor
pekerja
VII PEKERJAAN PLESTERAN VOLUME ANALISA
kg m3 OH OH OH OH
1 Pemasangan plesteran 1 SP : 3 PP tebal 15 mm 509.174 m2 VI.2 5205.8 10.2 101.83 76.38 7.64 5.09
2 Pemasangan plesteran 1 SP : 5 PP tebal 15 mm ### m2 VI.4 10553.6 52.9 407.16 305.37 30.54 30.54
3 Pemasangan plesteran skooning 1 SP : 3 PP lebar 10 cm ### m1 VI.14 1314.9 34.2 149.90 999.34 99.93 7.89
4 Pemasangan Acian 2.688 m2 VI.19 8.7 0.40 0.27 0.03 0.02
Kepala Tukang
Tukang Batu
Semen warna
Pasir pasang
mandor
pekerja
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING VOLUME ANALISA
bh bh bh bh
1 Titik Lampu 26.000 ls ls 26.00
2 Stop Kontak Type Inbow 13.000 ls ls 13.00
3 Sekring 1.000 ls ls 1.00
4 Kabel NYA 3 x 25 mm2 113.250 m1 ls 113.25
JUMLAH 26.00 13.00 1.00 113.25
Hollow 40/40 galvanis tebal 5 mm
kawat diameter 4 mm
Kepala Tukang
Tukang Kayu
mandor
Lakban
pekerja
Cornis
skrup
X PEKERJAAN LANGIT - LANGIT (PLAFOND) VOLUME ANALISA
Kepala Tukang
Tukang Kayu
Paku asbes
mandor
pekerja
XI PEKERJAAN PENUTUP ATAP VOLUME ANALISA
bh bh kg OH OH OH OH
1 Pemasangan genteng beton 205.13 m2 XI.6 1846.16 41.03 20.51 2.05 2.05
2 Pemasangan nok genteng beton 0.034 m1 XI.30 0.0374 0.001 0.00 0.00 0.00 0.00
JUMLAH 1846.16 0.04 0.001 41.03 20.52 2.05 2.05
Paku 5 - 7 cm
Paku 10 cm
Paku 12 cm
Lem kayu
XII PEKERJAAN KAYU VOLUME ANALISA
m3 kg kg m3 kg m3 kg kg m3 m3 m3
1 Pembuatan dan pas. kusen pintu dan kusen jendela, kayu kelas 1 10.821 m3 VII.1 11.90 13.53 10.82
2 Pembuatan dan pemasangan daun pintu panel, kayu kelas I atau II 35.790 m2 VII.4 1.43 1.79
3 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kelas I atau I 21.677 m2 VII.10 6.50 0.52
4 Pembuatan dan pas. pintu dan jendela jalusi kayu, kayu kelas I atau II 22.704 m2 VII.13 11.35 1.45
5 Pemasangan konstruksi kuda - kuda expose, kayu kelas I 61.641 m3 VII.25 67.81 924.62 345.19
6 Pemasangan konstruksi gordeng, kayu kelas II 0.540 m3 VII.27 0.59 1.62
7 Pemasangan rangka atap genteng beton, kayu kelas II 229.38 m3 VII.30 57.35 2.41 1.24
8 Pemasangan rangka langit - langit (60 x 60) cm, kayu kelas II atau III 205.13 m2 VII.38 41.03 1.72
9 Pemasangan listplank ukuran (3 x 20) cm, kayu kelas I atau kelas II 111.140 m1 VII.40 11.11 0.73
JUMLAH 80.30 111.90 28.68 1.43 12.90 2.71 924.62 346.81 2.41 1.24 1.72
Kepala Tukang
Tukang Kayu
mandor
Pekerja
OH OH OH OH
64.93 216.42 21.64 3.25
12.53 37.58 3.76 0.64
17.34 43.35 4.34 0.87
22.70 68.11 6.81 1.14
246.56 739.69 73.97 12.33
1.30 3.89 0.39 0.06
22.94 22.94 2.29 1.15
30.77 51.28 5.13 15.38
11.11 22.23 2.22 0.56
430.18 1205.49 120.55 35.37
Kaca riben 3 mm
Kaca es 3 mm
Tukang Kayu
Mandor
Pekerja
XIII PEKERJAAN KUNCI DAN KACA VOLUME ANALISA
Bh ps Bh M2 M2 M2 Oh Oh Oh Oh
1 Pemasangan kunci tanam biasa 3 bh XIII.1 3.00 0.03 1.50 0.03 0.02
2 Pemasangan engsel pintu 30 bh XIII.12 30.00 0.45 4.50 0.45 0.02
3 Pemasangan engsel jendela kupu - kupu dan almari 30 bh XIII.12 30.00 0.45 4.50 0.45 0.02
4 Pemasangan kait angin 30 bh XIII.32 30.00 0.45 4.50 0.45 0.02
5 Pemasangan kaca tebal 5 mm 15.5858 m2 XIII.44 17.14 0.23 2.34 0.23 0.01
6 Pemasangan kaca patri 1.2596 m2 XIII.47 1.39 0.02 0.19 0.02 0.001
7 Pemasangan kaca tebal 5 mm 0.24 m2 XIII.49 0.26 0.004 0.04 0.004 0.00
JUMLAH 3.00 60.00 30.00 17.14 1.39 0.26 1.64 17.56 1.64 0.10
Plamur Tembok
Plamur Kayu
Residu/ ter
Plamir
XIV PEKERJAAN PENGECATAN VOLUME ANALISA
Ltr Kg Kg Kg Kg kg kg kg kg kg
1 Pelaburan bidang kayu dengan cat residu dan ter 205.1 m2 XIV.14 71.80
2 Pengec. bidang tembok baru (1 lap. plamuur, 1 lap. cat dasar, 2 lap, ca 2304.5 m2 XIV.7 460.90 345.67 391.76 599.17
3 Pengecatan bidang kayu kusen dan daun pintu jendela 936.0 m2 XIV.3 140.41 159.13 159.13
4 Pengecatan bidang kayu daun almari 3.532 m2 XIV.16 0.35 0.35 0.92
JUMLAH 71.80 460.90 345.67 392.11 599.17 140.41 159.13 159.13 0.35 0.92
Mandor
Pekerja
OH OH OH OH
20.51 0.00 0.00 1.23
161.31 20.74 13.83 5.76
Perlengkapan
XV PEKERJAAN SANITASI DALAM GEDUNG VOLUME ANALISA
Bh % Bh % Bh Kg M3 Bh Set Bh Bh
1 Pemasangan closet duduk/monoblock 5.000 bh XII.1 5.00 0.30
2 Pemasangan Wastafel 1.000 bh XII.4 1.00 0.06
3 Pemasangan bak mandi batu bata vol 0,30 m 5.000 bh XII.16 5.00 30.00 0.05
4 Pemasangan bak cuci piring stainlesstell 1.000 bh XII.37 1.00 1.00
5 Pemasangan floor drain 5.000 bh XII.50 5.00
6 Pemasangan kran diameter 1/2" atau 3/4" 7.000 bh XII.43 7.00
7 Pemasangan pipa PVC tipe AW diameter 1 1/2" 12.110 m' XII.30
Pemasangan pipa PVC tipe AW diameter 2" 66.350 m' XII.31
Pemasangan pipa PVC tipe AW diameter 4" 54.820 m' XII.34
8 Pemasangan pipa ledeng dia 1/2 16.860 m' XII.29
9 Pemasangan pipa ledeng dia 3/4 61.990 m' XII.29
10 Memasang Pipa Beton Saluran ( U-20 ) cm, Panjang = 100 cm 78.850 m' XII.18
11 Memasang Bak Kontrol Pasangan Batu Bata ( 35 x 35 ) cm, Tinggi = 4 16.000 bh XII.38
JUMLAH 5.00 0.30 1.00 0.06 5.00 30.00 0.05 1.00 1.00 5.00 7.00
Pipa PVC class AW 1 1/2"
Washbak "Banco"
Sealtape kecil
Perlengkapan
Perlengkapan
Perlengkapan
Perlengkapan
Tukang Batu
Tukang Gali
Mandor
Pekerja
Bh M' % M' % M' % M' % M3 Bh Bh Set OH OH OH OH OH
5.50 5.50 0.55 0.55
1.20 1.45 0.15 0.10
10.50 3.75 0.35 0.55
0.03 0.30 0.03 0.00
0.05 0.50 0.05 0.03
0.18 0.07 0.70 0.07 0.04
14.53 4.24 0.44 0.73 0.07 0.02
79.62 23.22 3.58 5.97 0.60 0.18
65.78 19.187 4.44 7.40 0.74 0.22
20.23 5.901 0.61 1.01 0.10 0.03
74.39 21.697 2.23 3.72 0.37 0.11
0.47 78.85 78.85
16.00 16.0 0.48 4.80 0.48 0.02
0.18 14.53 4.24 79.62 23.22 65.78 19.19 94.62 27.60 0.47 78.85 16.00 16.0 96.68 11.30 35.83 3.56 1.85
TENAGA
Tukang batu
Tukang besi
Tukang gali
Tukang cat
Tukang las
Mandor
Pekerja
NO URAIAN PEKERJAAN
OH OH OH OH OH OH OH OH OH OH OH OH
1 PEKERJAAN PERSIAPAN 28.74 3.73 0.37 12.69
2 PEKERJAAN TANAH 139.66 4.85
3 PEKERJAAN PONDASI 96.97 40.29 4.03 4.85
4 PEKERJAAN BETON 311.05 51.62 3.65 28.15 1.67 11.73 37.52 33.34
5 PEKERJAAN BESI DAN ALUMUNIUM 39.15 2.00 3.92 37.15 1.96
6 PEKERJAAN PASANGAN DINDING 371.25 123.75 12.37 18.56
7 PEKERJAAN PLESTERAN 659.30 1381.36 138.14 43.54
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 347.22 237.20 23.72 17.16
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND) 34.41 114.69 11.47 1.84
11 PEKERJAAN PENUTUP ATAP 41.03 20.52 2.05 2.05
12 PEKERJAAN KAYU 430.18 1205.49 120.55 35.37
13 PEKERJAAN KUNCI DAN KACA 1.64 17.56 1.64 0.10
14 PEKERJAAN PENGECATAN 247.42 91.17 20.87 9.34
15 PEKERJAAN SANITASI DALAM GEDUNG 96.68 35.83 3.56 11.30 0.02
JUMLAH 2844.68 1413.61 139.73 1846.58 183.49 13.73 41.43 37.15 91.17 20.87 11.30 185.67
BAHAN
Kerikil ( max. 30 mm )
kayu papan 2/20 tahun
Portl'and Cement
Pasir Pasang
Pasir beton
paku 2"-4"
Pasir urug
Pasir urug
NO URAIAN PEKERJAAN
Air
m3 kg m3 m3 m3 kg m3 m3 m3 kg liter
1 PEKERJAAN PERSIAPAN 0.04 0.75 0.26
2 PEKERJAAN TANAH 23.20
3 PEKERJAAN PONDASI 88.67 4970.78 31.90 8.32
4 PEKERJAAN BETON 16704.17 51892.93 59652.29 12838.08
5 PEKERJAAN BESI DAN ALUMUNIUM
6 PEKERJAAN PASANGAN DINDING 13365.37 57.17
7 PEKERJAAN PLESTERAN 17083.01 97.30
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 5464.59 15.72
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND)
11 PEKERJAAN PENUTUP ATAP
12 PEKERJAAN KAYU
13 PEKERJAAN KUNCI DAN KACA
14 PEKERJAAN PENGECATAN
15 PEKERJAAN SANITASI DALAM GEDUNG 30.00 0.05
JUMLAH 0.04 0.75 0.26 23.20 88.67 57617.92 202.14 8.32 51892.93 59652.29 12838.08
BAHAN
kerikil beton
kawat beton
bata rooster
bata merah
besi siku
NO URAIAN PEKERJAAN
kg kg m3 kg kg kg kg m2 m3 m3 dos
1 PEKERJAAN PERSIAPAN
2 PEKERJAAN TANAH
3 PEKERJAAN PONDASI
4 PEKERJAAN BETON 6374.02 90.55 3.69 49.22 5.33
5 PEKERJAAN BESI DAN ALUMUNIUM 665.28 15.82 2.00
6 PEKERJAAN PASANGAN DINDING 80954.79 2430.00
7 PEKERJAAN PLESTERAN
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 206.42
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND)
11 PEKERJAAN PENUTUP ATAP
12 PEKERJAAN KAYU
13 PEKERJAAN KUNCI DAN KACA
14 PEKERJAAN PENGECATAN
15 PEKERJAAN SANITASI DALAM GEDUNG
JUMLAH 6374.016 90.5495 3.69114 49.2152 5.33265 665.28 15.818 2 80954.79 2430 206.4233
BAHAN
Titik Lampu
NO URAIAN PEKERJAAN
Sekring
kg dos dos m2 bh bh bh bh lmbr btg btg
1 PEKERJAAN PERSIAPAN
2 PEKERJAAN TANAH
3 PEKERJAAN PONDASI
4 PEKERJAAN BETON
5 PEKERJAAN BESI DAN ALUMUNIUM
6 PEKERJAAN PASANGAN DINDING
7 PEKERJAAN PLESTERAN
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 1312.16 399.97 0.67 2.48
9 PEKERJAAN INSTALASI LISTRIK 26.00 13.00 1.00 113.25
10 PEKERJAAN LANGIT - LANGIT (PLAFOND) 79.59 114.69 143.36
11 PEKERJAAN PENUTUP ATAP
12 PEKERJAAN KAYU
13 PEKERJAAN KUNCI DAN KACA
14 PEKERJAAN PENGECATAN
15 PEKERJAAN SANITASI DALAM GEDUNG
JUMLAH 1312.157 399.972 0.67278 2.4827 26 13 1 113.25 79.59486 114.69 143.3625
BAHAN
Paku 10 cm
Paku asbes
Lem kayu
Lakban
NO URAIAN PEKERJAAN
Cornis
skrup
kg kg kg rol bh bh kg m3 kg jg m3
1 PEKERJAAN PERSIAPAN
2 PEKERJAAN TANAH
3 PEKERJAAN PONDASI
4 PEKERJAAN BETON
5 PEKERJAAN BESI DAN ALUMUNIUM
6 PEKERJAAN PASANGAN DINDING
7 PEKERJAAN PLESTERAN
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND) 34.41 25.23 5.73 0.46
11 PEKERJAAN PENUTUP ATAP 1846.16 0.04 0.00068
12 PEKERJAAN KAYU 80.30 111.90 28.68 1.43
13 PEKERJAAN KUNCI DAN KACA
14 PEKERJAAN PENGECATAN
15 PEKERJAAN SANITASI DALAM GEDUNG
JUMLAH 34.407 25.2318 5.7345 0.45876 1846.161 0.0374 0.00068 80.3022 111.8971 28.6761 1.4316
BAHAN
Paku 12 cm
NO URAIAN PEKERJAAN
kg m3 kg kg m3 m3 m3 bh ps bh
1 PEKERJAAN PERSIAPAN
2 PEKERJAAN TANAH
3 PEKERJAAN PONDASI
4 PEKERJAAN BETON
5 PEKERJAAN BESI DAN ALUMUNIUM
6 PEKERJAAN PASANGAN DINDING
7 PEKERJAAN PLESTERAN
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND)
11 PEKERJAAN PENUTUP ATAP
12 PEKERJAAN KAYU 12.90 2.71 924.62 346.81 2.41 1.24 1.72
13 PEKERJAAN KUNCI DAN KACA 3.00 60.00 30.00
14 PEKERJAAN PENGECATAN
15 PEKERJAAN SANITASI DALAM GEDUNG
JUMLAH 12.9035 2.706828 924.615 346.8096 2.40849 1.238652 1.723084 3 60 30
BAHAN
Plamur Kayu
Residu/ ter
NO URAIAN PEKERJAAN
Plamir
M2 M2 M2 ltr kg kg kg kg kg kg kg
1 PEKERJAAN PERSIAPAN
2 PEKERJAAN TANAH
3 PEKERJAAN PONDASI
4 PEKERJAAN BETON
5 PEKERJAAN BESI DAN ALUMUNIUM
6 PEKERJAAN PASANGAN DINDING
7 PEKERJAAN PLESTERAN
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND)
11 PEKERJAAN PENUTUP ATAP
12 PEKERJAAN KAYU
13 PEKERJAAN KUNCI DAN KACA 17.14 1.39 0.26
14 PEKERJAAN PENGECATAN 71.80 460.90 345.67 392.11 599.17 140.41 159.13 159.13
15 PEKERJAAN SANITASI DALAM GEDUNG
JUMLAH 17.14438 1.38556 0.264 71.79515 460.8962 345.6722 392.115 599.1651 140.4056 159.1263 159.1263
BAHAN
Sealtape kecil
Perlengkapan
NO URAIAN PEKERJAAN
kg kg bh % bh % bh bh set bh bh bh
1 PEKERJAAN PERSIAPAN
2 PEKERJAAN TANAH
3 PEKERJAAN PONDASI
4 PEKERJAAN BETON
5 PEKERJAAN BESI DAN ALUMUNIUM
6 PEKERJAAN PASANGAN DINDING
7 PEKERJAAN PLESTERAN
8 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
9 PEKERJAAN INSTALASI LISTRIK
10 PEKERJAAN LANGIT - LANGIT (PLAFOND)
11 PEKERJAAN PENUTUP ATAP
12 PEKERJAAN KAYU
13 PEKERJAAN KUNCI DAN KACA
14 PEKERJAAN PENGECATAN 0.35 0.92
15 PEKERJAAN SANITASI DALAM GEDUNG 5.00 0.30 1.00 0.06 5.00 1.00 1.00 5.00 7.00 0.18
JUMLAH 0.3532 0.91832 5 0.3 1 0.06 5 1 1 5 7 0.175
BAHAN
Buis beton U 20 cm
Washbak "Banco"
NO URAIAN PEKERJAAN
BOUWSOOM Rp 1,443,005,121.38
PPN 10 % Rp 144,300,512.14
JUMLAH ANIMINGSOM Rp 1,587,305,633.52
DIBULATKAN Rp 1,587,305,000.00
Terbilang : Satu Miliar Lima Ratus Delapan Puluh Tujuh Juta Rupiah.
HARGA SATUAN
NO URAIAN PEKERJAAN SAT.
(Rp)
I PEKERJAAN PERSIAPAN
I.1 1 M' Pagar sementara dari kayu tinggi 2 meter 1 m' 361,755.00
I.2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter 1 m' 248,830.00
I.3 1 M2 Membersihkan lapangan dan perataan 1 m2 7,500.00
I.4 1 M2 Pembuatan bak adukan dari kayu tahun ukuran (40 x 50 x 20) cm 1 m2 360,605.00
I.5 1 M2 Pembuatan jalan sementara 1 m2 137,880.00
II PEKERJAAN TANAH
II.1 Pengukuran Bouplank SNI - 03-28352- 2002 1 m' 41,370.00
II.2 Galian tanah biasa kedalaman 1 m 1 m3 35,250.00
II.3 Galian tanah biasa kedalaman 2 m 1 m3 43,200.00
II.4 Galian tanah biasa kedalaman 3 m 1 m3 51,270.00
II.5 Galian tanah keras kedalaman 1 m 1 m3 46,920.00
II.6 Galian tanah cadas kedalaman 1 m 1 m3 71,100.00
II.7 Galian tanah lumpur kedalaman 1 m 1 m3 56,700.00
II.8 Stripping tebing setinggi 1 meter 1 m2 2,550.00
II.9 Membuang tanah sejauh 30 m 1 m3 15,450.00
II.10 Timbunan tanah kembali (tanah biasa dalam 1 m3) 1 m3 11,748.00
II.11 Memadatkan tanah(per 20 cm) 1 m3 25,500.00
II.12 Urugan pasir urug 1 m3 176,100.00
II.13 Urugan sirtu padat untuk peninggian lantai bangunan 1 m3 108,750.00
II.14 Memasang lapisan ijuk tebal 10 cm 1 m3 367,650.00
IV PEKERJAAN BETON
IV.1 Membuat beton mutu F'c = 7,4 Mpa (K100), slump (12+2) cm, w/c= 0.87 1 m3 1,070,427.50
IV.2 Membuat beton mutu F'c = 9,8 Mpa (K125), slump (12+2) cm, w/c= 0.78 1 m3 1,123,418.70
IV.3 Membuat beton mutu F'c = 12,2 Mpa (K150), slump (12+2) cm, w/c= 0.72 1 m3 1,164,819.17
IV.4 Membuat beton mutu F'c = 7,4 Mpa (K100), slump (3-6) cm, w/c= 0.87 1 m3 1,005,005.09
IV.5 Membuat beton mutu F'c = 14,5 Mpa (K175), slump (12 + 2) cm, w/c= 0.66 1 m3 1,214,042.78
IV.6 Membuat beton mutu F'c = 16,9 Mpa (K200), slump (12 + 2) cm, w/c= 0.61 1 m3 1,260,565.46
IV.7 Membuat beton mutu F'c = 19,3 Mpa (K225), slump (12 + 2) cm, w/c= 0.58 1 m3 1,296,034.44
IV.8 Membuat beton mutu F'c = 21.7 Mpa (K250), slump (12+2) cm, w/c= 0.56 1 m3 1,318,518.70
IV.9 Membuat beton mutu F'c = 24.0 Mpa (K275), slump (12+2) cm, w/c= 0.53 1 m3 1,356,915.00
IV.10 Membuat beton mutu F'c = 26.4 Mpa (K300), slump (12+2) cm, w/c= 0.52 1 m3 1,368,914.54
IV.11 Membuat beton mutu F'c = 28.8 Mpa (K325), slump (12+2) cm, w/c= 0.49 1 m3 1,414,188.15
IV.12 Membuat beton mutu F'c = 31.2 Mpa (K350), slump (12+2) cm, w/c= 0.48 1 m3 1,429,795.09
IV.13 Pekerjaan pembesian dengan besi polos 1 kg 12,770.25
IV.14 Pekerjaan pembesian dengan besi ulir 1 kg 12,770.25
IV.15 Pekerjaan bekisting untuk pondasi 1 m2 59,655.00
IV.16 Pekerjaan bekisting untuk sloof 1 m2 61,492.50
IV.17 Pekerjaan bekisting untuk kolom mennggunakan cetakan teakwood dan perancah dolke 1 m2 152,390.00
IV.18 Pekerjaan bekisting untuk kolom menggunakan cetakan kayu tahun dan perancah bamb 1 m2 181,090.00
IV.19 Pekerjaan bekisting untuk balok cetakan menggunakan teakwood dan perancah dolken 1 m2 157,902.50
IV.20 Pekerjaan bekisting untuk balok menggunakan cetakan kayu tahun dan perancah bambu1 m2 186,602.50
IV.21 Pekerjaan bekisting untuk plat lantai cetakan teakwood dan perancah dolken 1 m2 236,390.00
IV.22 Pekerjaan bekisting untuk plat lantai menggunakan cetakan kayu tahun dan perancah 1 m2 197,090.00
IV.23 Pekerjaan bekisting untuk dinding menggunakan cetakan teakwood dan perancah dolke 1 m2 184,902.50
IV.24 Pekerjaan bekisting untuk dinding menggunakan cetakan kayu tahun dan perancah bam 1 m2 196,602.50
IV.25 Pekerjaan bekisting untuk tangga menggunakan cetakan teakwood dan perancah dolken1 m2 148,715.00
IV.26 Pekerjaan bekisting untuk tangga menggunakan cetakan kayu tahun dan perancah bam 1 m2 177,415.00
IV.27 Pekerjaan bekisting untuk jembatan 1 m2 38,869.50
IV.28 Membuat kolom praktis beton bertulang (11X11) cm 1 m1 64,245.00
IV.29 Membuat ring balok beton bertulang (10X15) cm 1 m1 77,835.00
V PEKERJAAN DINDING
V.1 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 2Pp tebal 1 Bata 1 m2 233,360.00
V.2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Pp tebal 1 Bata 1 m2 214,932.00
V.3 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 4Pp tebal 1 Bata 1 m2 203,066.00
V.4 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 5Pp tebal 1 Bata 1 m2 196,124.00
V.5 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 6Pp tebal 1 Bata 1 m2 192,034.00
V.6 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Kp : 10 Pp tebal 1 1 m2 171,872.75
V.7 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 2Pp tebal 1/2 Bata 1 m2 111,066.00
V.8 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Pp tebal 1/2 Bata 1 m2 102,658.00
V.9 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 4Pp tebal 1/2 Bata 1 m2 97,646.00
V.10 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 5Pp tebal 1/2 Bata 1 m2 94,482.00
V.11 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 6Pp tebal 1/2 Bata 1 m2 92,486.00
V.12 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 8Pp tebal 1/2 Bata 1 m2 89,175.00
V.13 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Kp : 10Pp tebal 1/1 m2 85,469.50
V.14 Memasang dinding terawang (roster) ukuran (12x11x24) cm campuran spesl 1Pc: 3Pp 1 m2 96,779.00
V.15 Memasang dinding terawang (roster) ukuran (12x11x24) cm campuran spesl 1Pc: 4PP 1 m2 91,520.00
VI PEKERJAAN PLESTERAN
VI.1 Plesteran dinding tebal 15 mm dengan 1Pc : 2Pp 1 m2 41,078.10
VI.2 Plesteran dinding tebal 15 mm dengan 1Pc : 3Pp 1 m2 37,167.90
VI.3 Plesteran dinding tebal 15 mm dengan 1Pc : 4Pp 1 m2 34,396.50
VI.4 Plesteran dinding tebal 15 mm dengan 1Pc : 5Pp 1 m2 32,684.10
VI.5 Plesteran dinding tebal 15 mm dengan 1Pc : 6Pp 1 m2 31,371.90
VI.6 Plesteran dinding tebal 15 mm dengan 1Pc : 7Pp 1 m2 30,606.90
VI.7 Plesteran dinding tebal 15 mm dengan 1Pc : 8Pp 1 m2 29,841.90
VI.8 Plesteran dinding tebal 20 mm dengan 1Pc : 2Pp 1 m2 54,499.80
VI.9 Plesteran dinding tebal 20 mm dengan 1Pc : 3Pp 1 m2 48,886.20
VI.10 Plesteran dinding tebal 20 mm dengan 1Pc : 4Pp 1 m2 45,142.00
VI.11 Plesteran dinding tebal 20 mm dengan 1Pc : 5Pp 1 m2 42,907.80
VI.12 Plesteran dinding tebal 20 mm dengan 1Pc : 6Pp 1 m2 41,109.20
VI.13 Memasang berapen 1Pc : 5Pp tebal 15 mm 1 m2 25,154.10
VI.14 Plesteran skoning 1Pc : 2Pp, lebar 10 mm 1 m1 28,691.00
VI.15 Plesteran ciprat 1Pc : 2Pp 1 m2 27,195.00
VI.16 Finishing siar dinding pasangan bata merah (=20 m') 1 m2 17,387.70
VI.17 Finishing siar pasangan dinding conblock ekpose (=8 m') 1 m2 8,810.00
VI.18 Finishing siar pasangan batu kali adukan 1Pc : 2Pp 1 m2 36,715.00
VI.19 Memasang acian 1 m2 19,480.00
IX PEKERJAAN LANGIT-LANGIT
IX.1 Pasang langit-langit asbes semen, tebal 3 mm 1 m2 22,902.50
IX.2 Pasang langit-langit tripleks ukuran (120x240) cm, tebal 3 mm 1 m2 27,355.00
IX.3 Pasang langit-langit tripleks ukuran (120x240) cm, tebal 4 mm 30,825.00
IX.4 Pasang langit-langit lambriziring kayu Jati Lokal, tebal 9 mm 1 m2 183,900.00
IX.5 Pasang langit-langit gypsum board "Elephant" ukuran (120x240x0,9) cm, tebal 9 mm 1 m2 92,093.00
rangka Hollow 20/40 dan 40/40 galvanis tebal 4 mm
IX.6 Pasang langit-langit gypsum board "Jaya Board" ukuran (120x240x0,9) cm, tebal 9 mm
1 m2 93,156.00
rangka Hollow 20/40 dan 40/40 galvanis tebal 4 mm
IX.7 Pasang langit-langit GRC board ukuran (120x240x0,4) cm, tebal 4 mm rangka Hollow
1 m2 92,462.00
20/40 dan 40/40 galvanis tebal 4 mm
IX.8 Pasang langit-langit Kalsiboard ukuran (120x240x0,35) cm, tebal 3,5 mm rangka Hollow
1 m2 91,421.00
20/40 dan 40/40 galvanis tebal 4 mm
IX.9 Pasang langit-langit kalsiboard ukuran (120x240x0,35) cm, tebal 3,5 mm 1 m2 30,256.50
IX.10 List langit-langit kayu profil 1 m' 10,332.50
IX.11 List langit-langit gypsum 10 cm 1 m' 15,542.50
IV.1 1 m3 Membuat beton mutu F'c = 7,4 Mpa (K100), slump (12+2) cm, w/c= 0.87
Bahan
247 kg Semen portland @Rp. 1,900.00 = Rp. 469,300.00
869 kg Pasir beton @Rp. 112.50 = Rp. 97,762.50
999 kg Kerikil (maksimum 30 mm) @Rp. 192.59 = Rp. 192,400.00
215 ltr Air @Rp. 1,000.00 = Rp. 215,000.00
Rp. 974,462.50
Tenaga
1.65 Oh Pekerja @Rp. 45,000.00 = Rp. 74,250.00
0.275 Oh Tukang batu @Rp. 55,000.00 = Rp. 15,125.00
0.028 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,610.00
0.083 Oh Mandor @Rp. 60,000.00 = Rp. 4,980.00
Rp. 95,965.00
Rp. 1,070,427.50
V
V.2 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 3Pp tebal 1 Bata
Bahan
140 m3 Batu bata @Rp. 700.00 = Rp. 98,000.00
32.95 kg Semen PC @Rp. 1,900.00 = Rp. 62,605.00
0.091 m3 Pasir pasang @Rp. 147,000.00 = Rp. 13,377.00
Rp. 173,982.00
Tenaga
0.6 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.2 Oh Tukang batu @Rp. 55,000.00 = Rp. 11,000.00
0.02 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 1,150.00
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 40,950.00
Rp. 214,932.00
V.12 1 m2 Memasang dinding bata merah uk (5x11x22) cm campuran spesl 1Pc: 8Pp tebal 1/2 Bata
Bahan
70 m3 Batu bata @Rp. 700.00 = Rp. 49,000.00
6.5 kg Semen PC @Rp. 1,900.00 = Rp. 12,350.00
0.05 m3 Pasir pasang @Rp. 147,000.00 = Rp. 7,350.00
Rp. 68,700.00
Tenaga
0.3 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.01 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 575.00
0.015 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
Rp. 89,175.00
V.14 1 m2 Memasang dinding terawang (roster) ukuran (12x11x24) cm campuran spesl 1Pc: 3Pp
Bahan
30 bh Terawang (roster) @Rp. 1,500.00 = Rp. 45,000.00
14 kg Semen PC @Rp. 1,900.00 = Rp. 26,600.00
0.032 m3 Pasir pasang @Rp. 147,000.00 = Rp. 4,704.00
Rp. 76,304.00
Tenaga
0.3 Oh Pekerja @Rp. 45,000.00 = Rp. 13,500.00
0.1 Oh Tukang batu @Rp. 55,000.00 = Rp. 5,500.00
0.01 Oh Kepala tukang @Rp. 57,500.00 = Rp. 575.00
0.015 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 20,475.00
Rp. 96,779.00
VI
VI.2 1 m2 Plesteran dinding tebal 15 mm dengan 1Pc : 3Pp
Bahan
7.776 kg Semen PC @Rp. 1,900.00 = Rp. 14,774.40
0.023 m3 Pasir pasang @Rp. 147,000.00 = Rp. 3,381.00
Rp. 18,155.40
Tenaga
0.2 Oh Pekerja @Rp. 45,000.00 = Rp. 9,000.00
0.15 Oh Tukang batu @Rp. 55,000.00 = Rp. 8,250.00
0.015 Oh Kepala tukang @Rp. 57,500.00 = Rp. 862.50
0.015 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 19,012.50
Rp. 37,167.90
VI.4 1 m2 Plesteran dinding tebal 15 mm dengan 1Pc : 5Pp
Bahan
5.184 kg Semen PC @Rp. 1,900.00 = Rp. 9,849.60
0.026 m3 Pasir pasang @Rp. 147,000.00 = Rp. 3,822.00
Rp. 13,671.60
Tenaga
0.2 Oh Pekerja @Rp. 45,000.00 = Rp. 9,000.00
0.15 Oh Tukang batu @Rp. 55,000.00 = Rp. 8,250.00
0.015 Oh Kepala tukang @Rp. 57,500.00 = Rp. 862.50
0.015 Oh Mandor @Rp. 60,000.00 = Rp. 900.00
Rp. 19,012.50
Rp. 32,684.10
VI.14 1 m1 Plesteran skoning 1Pc : 2Pp, lebar 10 mm
Bahan
0.5 kg Semen PC @Rp. 1,900.00 = Rp. 950.00
0.013 m3 Pasir pasang @Rp. 147,000.00 = Rp. 1,911.00
Rp. 2,861.00
Tenaga
0.057 Oh Pekerja @Rp. 45,000.00 = Rp. 2,565.00
0.38 Oh Tukang batu @Rp. 55,000.00 = Rp. 20,900.00
0.038 Oh Kepala tukang batu @Rp. 57,500.00 = Rp. 2,185.00
0.003 Oh Mandor @Rp. 60,000.00 = Rp. 180.00
Rp. 25,830.00
Rp. 28,691.00
VI.19 1 m2 Memasang acian
Bahan
3.25 kg Portland Cement @Rp. 1,900.00 = Rp. 6,175.00
Rp. 6,175.00
Tenaga
0.15 Pekerja @Rp. 45,000.00 = Rp. 6,750.00
0.1 Tukang Batu @Rp. 55,000.00 = Rp. 5,500.00
0.01 Kepala Tukang batu @Rp. 57,500.00 = Rp. 575.00
0.008 mandor @Rp. 60,000.00 = Rp. 480.00
Rp. 13,305.00
Rp. 19,480.00
VII
VII.1 1 m3 Membuat dan memasang kusen pintu dan daun jendela Kayu Kruing
Bahan
1.1 m3 Balok kayu kruing @Rp. 5,775,000.00 = Rp. 6,352,500.00
1.25 kg Paku 10 cm @Rp. 14,000.00 = Rp. 17,500.00
1 kg Lem kayu @Rp. 14,000.00 = Rp. 14,000.00
Rp. 6,384,000.00
Tenaga
6 Pekerja @Rp. 45,000.00 = Rp. 270,000.00
20 Tukang Kayu @Rp. 55,000.00 = Rp. 1,100,000.00
2 Kepala Tukang @Rp. 57,500.00 = Rp. 115,000.00
0.3 mandor @Rp. 60,000.00 = Rp. 18,000.00
Rp. 1,503,000.00
Rp. 7,887,000.00
VII.4 1 m2 Membuat dan memasang pintu klam Kayu Kruing
Bahan
0.04 m3 Papan kayu kamper @Rp. 5,775,000.00 = Rp. 231,000.00
0.05 kg Paku 5 - 7 cm @Rp. 14,000.00 = Rp. 700.00
Rp. 231,700.00
Tenaga
0.35 Pekerja @Rp. 45,000.00 = Rp. 15,750.00
1.05 Tukang Kayu @Rp. 55,000.00 = Rp. 57,750.00
0.105 Kepala Tukang @Rp. 57,500.00 = Rp. 6,037.50
0.018 mandor @Rp. 60,000.00 = Rp. 1,080.00
Rp. 80,617.50
Rp. 312,317.50
VII.10 1 m2 Membuat dan memasang pintu dan jendela kaca kayu Kruing
Bahan
0.024 m3 Papan kayu kruing @Rp. 5,775,000.00 = Rp. 138,600.00
0.3 kg Lem kayu @Rp. 14,000.00 = Rp. 4,200.00
Rp. 142,800.00
Tenaga
0.8 Pekerja @Rp. 45,000.00 = Rp. 36,000.00
2 Tukang Kayu @Rp. 55,000.00 = Rp. 110,000.00
0.2 Kepala Tukang @Rp. 57,500.00 = Rp. 11,500.00
0.04 mandor @Rp. 60,000.00 = Rp. 2,400.00
Rp. 159,900.00
Rp. 302,700.00
VII.13 1 m2 Membuat dan memasang pintu dan jendela jalusi kayu Kruing
Bahan
0.064 m3 Papan kayu kruing @Rp. 5,775,000.00 = Rp. 369,600.00
0.5 kg Lem kayu @Rp. 14,000.00 = Rp. 7,000.00
Rp. 376,600.00
Tenaga
1 Pekerja @Rp. 45,000.00 = Rp. 45,000.00
3 Tukang Kayu @Rp. 55,000.00 = Rp. 165,000.00
0.3 Kepala Tukang @Rp. 57,500.00 = Rp. 17,250.00
0.05 mandor @Rp. 60,000.00 = Rp. 3,000.00
Rp. 230,250.00
Rp. 606,850.00
VIII.1 1 m2 Pasang lantai keramik ukuran (30x30) cm, motif warna muda "Asia Tile"
Bahan
1.0101 dos Keramik Asia Tile Motif Warna Mu @Rp. 48,000.00 = Rp. 48,484.80
10 kg PC @Rp. 1,900.00 = Rp. 19,000.00
0.045 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.5 kg Semen warna @Rp. 13,000.00 = Rp. 19,500.00
Rp. 93,599.80
Tenaga
0.62 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.35 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.035 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
Rp. 144,562.30
VIII.14 1 m2 Pasang lantai keramik ukuran (40 x 40) cm, Motif Warna Muda "Asia Tile"
Bahan
1.0417 dos Keramik Asia Tile Motif Warna Mu @Rp. 55,000.00 = Rp. 57,293.50
9.8 kg PC @Rp. 1,900.00 = Rp. 18,620.00
0.045 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.3 kg Semen warna @Rp. 13,000.00 = Rp. 16,900.00
Rp. 99,428.50
Tenaga
0.62 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.35 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.035 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
Rp. 150,391.00
VIII.34 1 m2 Pasang lantai keramik ukuran (20x20) cm, Motif Warna Muda, "Asia Tile"
Bahan
1.05 dos Keramik Asia Tile Motif Warna Mu @Rp. 50,000.00 = Rp. 52,500.00
10.4 kg PC @Rp. 1,900.00 = Rp. 19,760.00
0.045 m3 PP @Rp. 147,000.00 = Rp. 6,615.00
1.62 kg Semen warna @Rp. 13,000.00 = Rp. 21,060.00
Rp. 99,935.00
Tenaga
0.62 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.35 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.035 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
Rp. 150,897.50
VIII.45 1 m2 Pasang dinding keramik ukuran (20x20) cm, Motif Warna Muda "Asia Tile"
Bahan
1.05 dos Keramik Asia Tile Motif Warna Mu @Rp. 50,000.00 = Rp. 52,500.00
9.3 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.018 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
1.94 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 73,050.00
Tenaga
0.6 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.45 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.045 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
Rp. 129,187.50
VIII.47 1 m2 Pasang dinding batu ANDESIT ALUR 10 x 20 cm
Bahan
1.1 m2 Batu Andesit Alur 10 x 20 cm @Rp. 126,000.00 = Rp. 138,600.00
11.75 kg PC @Rp. 1,900.00 = Rp. 22,325.00
0.035 m3 PP @Rp. 147,000.00 = Rp. 5,145.00
Rp. 166,070.00
Tenaga
0.62 Oh Pekerja @Rp. 45,000.00 = Rp. 27,900.00
0.35 Oh Tukang batu @Rp. 55,000.00 = Rp. 19,250.00
0.035 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,012.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 50,962.50
Rp. 217,032.50
VIII.58 1 m2 Pasang lis dinding keramik ukuran (10x30) cm asia tile motif warna muda
Bahan
1.2963 dos Keramik 30x30 motif warna muda @Rp. 48,000.00 = Rp. 62,222.40
9.3 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.018 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
2.75 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 82,772.40
Tenaga
0.6 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.45 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.045 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
Rp. 138,909.90
VIII.61 1 m2 Pasang lis dinding keramik ukuran (10x40) cm mulia motif warna muda
Bahan
1.0938 dos Keramik 40x40 motif warna muda @Rp. 38,000.00 = Rp. 41,564.40
9.3 kg PC @Rp. 1,900.00 = Rp. 17,670.00
0.018 m3 PP @Rp. 147,000.00 = Rp. 2,646.00
2.75 kg Semen warna @Rp. 13,000.00 = Rp. 234.00
Rp. 62,114.40
Tenaga
0.6 Oh Pekerja @Rp. 45,000.00 = Rp. 27,000.00
0.45 Oh Tukang batu @Rp. 55,000.00 = Rp. 24,750.00
0.045 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,587.50
0.03 Oh Mandor @Rp. 60,000.00 = Rp. 1,800.00
Rp. 56,137.50
Rp. 118,251.90
IX
IX.5 1 m2 Pas. Langit" gypsum board "Elephant" (120x240x0,9) cm, t 9 mm Hollow 20/40 & 40/40 gal. 4MM
Bahan
0.347 lbr Gypsum board "Elephant" @Rp. 59,000.00 = Rp. 20,473.00
0.5 btg Hollow 40/40 galvanis tebal 5 mm @Rp. 33,000.00 = Rp. 16,500.00
0.625 btg Hollow 20/40 galvanis tebal 4 mm @Rp. 20,000.00 = Rp. 12,500.00
0.15 kg kawat diameter 4 mm @Rp. 15,000.00 = Rp. 2,250.00
0.11 kg Skrup @Rp. 24,000.00 = Rp. 2,640.00
0.025 kg Cornis @Rp. 5,000.00 = Rp. 125.00
0.002 rol Lakban @Rp. 11,000.00 = Rp. 22.00
Rp. 54,488.00
Tenaga
0.15 Oh Pekerja @Rp. 45,000.00 = Rp. 6,750.00
0.5 Oh Tukang kayu @Rp. 55,000.00 = Rp. 27,500.00
0.05 Oh Kepala tukang @Rp. 57,500.00 = Rp. 2,875.00
0.008 Oh Mandor @Rp. 60,000.00 = Rp. 480.00
Rp. 37,605.00
Rp. 92,093.00
XII.
XIV.