LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

KEGIATAN : PEMBANGUNAN SISTEM PENYEDIAAN AIR MINUM DAN SANITASI NOMOR KONTRAK : 602/317/CK-IV/2020
PAKET : PENGEMBANGAN SPAM KECAMATAN PALARAN, KOTA SAMARINDA TANGGAL KONTRAK : 14 APRIL 2020
LOKASI : KECAMATAN PALARAN, KOTA SAMARINDA PERUSAHAAN : CV. TITANIUM INDONESIA
TAHUN : 2020 KONSULTAN : CV. JASA PRIBHUNI
MINGGU KE : 16 ( ENAM BELAS ) 03 AGUSTUS - 11 AGUSTUS 2020

Kontrak Awal Realisasi Fisik Pekerjaan


Harga Satuan Minggu Lalu Minggu Ini S/d Minggu Ini Jumlah Harga
No. Uraian Pekerjaan Satuan Jumlah Harga Bobot Keterangan
Volume Bobot Bobot Bobot
Volume Volume Volume
(Rupiah) (Rupiah) (%) (%) (%) (%) ( Rupiah )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

I. PEKERJAAN PENDAHULUAN
1 Mobilisasi-Demobilisasi, Pengukuran & Pematokan Ls 7,500,000.00 1.00 7,500,000.00 0.26 0.50 0.13 - 0.50 0.13 3,750,000.00
2 Pelaporan (Administrasi Proyek), Gambar (Shop Drawing
Asbuilt Drawing),Dokumentasi Ls 9,961,008.40 1.00 9,961,008.40 0.34 0.50 0.17 - 0.50 0.17 4,980,504.20
3 Keselamatan Dan Kesehatan Kerja ( K3 ) Ls 11,000,000.00 1.00 11,000,000.00 0.38 1.00 0.38 - 1.00 0.38 11,000,000.00

Jumlah Total I 28,461,008.40 0.98 0.68 - 0.68 19,730,504.20

II. PENGADAAN & PEMASANGAN PIPA DISTRIBUSI


II.1 Pipa HDPE Ø 200 mm, S 8 - SDR 17 (PN 10/PE100)
1 Pengadaan Pipa HDPE Ø 200 mm M' 445,000.00 1,720.00 765,400,000.00 26.26 1,670.32 25.50 20.88 0.32 1,691.20 25.82 752,584,000.00
2 Pemasangan Pipa HDPE Ø 200 mm
2.1 Galian Tanah dan Urugan Kembali M' 113,230.61 1,720.00 194,756,652.64 6.68 1,554.40 6.04 69.60 0.27 1,624.00 6.31 183,886,513.89
2.2 Pemasangan Pipa M' 25,858.80 1,720.00 44,477,136.00 1.53 1,554.40 1.38 69.60 0.06 1,624.00 1.44 41,994,691.20

II.1 Pipa HDPE Ø 160 mm, S 8 - SDR 17 (PN 10/PE100)


1 Pengadaan Pipa HDPE Ø 160 mm M' 280,000.00 3,322.00 930,160,000.00 31.91 2,520.28 24.21 19.14 0.18 2,539.42 24.39 711,037,600.00
2 Pemasangan Pipa HDPE Ø 160 mm
2.1 Galian Tanah dan Urugan Kembali M' 81,740.76 3,322.00 271,542,798.08 9.32 649.60 1.82 63.80 0.18 713.40 2.00 58,313,856.76
2.2 Pemasangan Pipa M' 16,926.80 3,322.00 56,230,829.60 1.93 649.60 0.38 63.80 0.04 713.40 0.41 12,075,579.12

II.2 Pipa HDPE Ø 90 mm, S 8 - SDR 17 (PN 10/PE100)


1 Pengadaan Pipa HDPE Ø 90 mm M' 90,000.00 3,272.00 294,480,000.00 10.10 2,290.40 7.07 403.68 1.25 2,694.08 8.32 242,467,200.00
2 Pemasangan Pipa HDPE Ø 90 mm
2.1 Galian Tanah dan Urugan Kembali M' 53,295.45 3,272.00 174,382,708.47 5.98 1,345.60 2.46 1,345.60 2.46 71,714,355.91
2.2 Pemasangan Pipa M' 11,498.30 3,272.00 37,622,437.60 1.29 1,345.60 0.53 1,345.60 0.53 15,472,112.48

Jumlah Total II 2,769,052,562.39 94.99 66.39 5.29 71.68 2,089,545,909.35

III. PENGADAAN & PEMASANGAN ACCESSORIES PIPA


III.1 PENGADAAN ACCESSORIES PIPA
1 Equal Tee (HDPE) Ø 160 x 160 mm Bh 820,000.00 2.00 1,640,000.00 0.06 1.00 0.03 - 1.00 0.03 820,000.00
2 Un Equal Tee (HDPE) Ø 160 x 110 mm Bh 780,000.00 2.00 1,560,000.00 0.05
3 Un Equal Tee (HDPE) Ø 160 x 90 mm Bh 740,000.00 5.00 3,700,000.00 0.13 2.00 0.05 - 2.00 0.05 1,480,000.00
4 Un Equal Tee (HDPE) Ø 110 x 90 mm Bh 370,000.00 1.00 370,000.00 0.01 1.00 0.01 1.00 0.01 370,000.00
Kontrak Awal Realisasi Fisik Pekerjaan
Harga Satuan Minggu Lalu Minggu Ini S/d Minggu Ini Jumlah Harga
No. Uraian Pekerjaan Satuan Jumlah Harga Bobot Keterangan
Volume Bobot Bobot Bobot
Volume Volume Volume
(Rupiah) (Rupiah) (%) (%) (%) (%) ( Rupiah )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
5 Stub Flange (HDPE) Ø 200 mm Bh 1,450,000.00 3.00 4,350,000.00 0.15
6 Stub Flange (HDPE) Ø 160 mm Bh 980,000.00 10.00 9,800,000.00 0.34 1.00 0.03 - 1.00 0.03 980,000.00
7 Stub Flange (HDPE) Ø 110 mm Bh 380,000.00 6.00 2,280,000.00 0.08 2.00 0.03 2.00 0.03 760,000.00
8 Stub Flange (HDPE) Ø 90 mm Bh 290,000.00 12.00 3,480,000.00 0.12 7.00 0.07 7.00 0.07 2,030,000.00
9 Flange Socket (PVC) Ø 160 mm Bh 440,000.00 1.00 440,000.00 0.02
10 Flange Socket (PVC) Ø 110 mm Bh 220,000.00 4.00 880,000.00 0.03 2.00 0.02 2.00 0.02 440,000.00
11 Gate Valve All Flange (CI) Ø 150 mm Bh 6,870,000.00 3.00 20,610,000.00 0.71
12 Gate Valve All Flange (CI) Ø 100 mm Bh 4,110,000.00 2.00 8,220,000.00 0.28
13 Gate Valve All Flange (CI) Ø 75 mm Bh 2,240,000.00 6.00 13,440,000.00 0.46 3.00 0.23 3.00 0.23 6,720,000.00
14 Bend 45º (HDPE) Ø 200 mm Bh 900,000.00 2.00 1,800,000.00 0.06
15 Bend 90º (HDPE) Ø 110 mm Bh 380,000.00 1.00 380,000.00 0.01
16 Bend 90º (HDPE) Ø 90 mm Bh 270,000.00 5.00 1,350,000.00 0.05 1.00 0.01 1.00 0.01 270,000.00
17 Street Box Ø 150 mm Bh 230,000.00 3.00 690,000.00 0.02
18 Street Box Ø 100 mm Bh 200,000.00 2.00 400,000.00 0.01
19 Street Box Ø 75 mm Bh 180,000.00 6.00 1,080,000.00 0.04
20 Doop (HDPE) Ø 90 mm Bh 160,000.00 6.00 960,000.00 0.03 2.00 0.01 2.00 0.01 320,000.00
21 Blind Flange Ø 160 mm Bh 140,000.00 3.00 420,000.00 0.01 1.00 0.00 - 1.00 0.00 140,000.00
22 Rubberpacking Ø 200 mm Bh 50,000.00 3.00 150,000.00 0.01
23 Rubberpacking Ø 160 mm Bh 30,000.00 8.00 240,000.00 0.01 1.00 0.00 - 1.00 0.00 30,000.00
24 Rubberpacking Ø 110 mm Bh 10,000.00 7.00 70,000.00 0.00 2.00 0.00 2.00 0.00 20,000.00
25 Rubberpacking Ø 90 mm Bh 10,000.00 10.00 100,000.00 0.00 7.00 0.00 7.00 0.00 70,000.00
26 Mur baut Bh 7,600.00 196.00 1,489,600.00 0.05 8.00 0.00 36.00 0.01 44.00 0.01 334,400.00
27 Trust Blok Bh 50,000.00 10.00 500,000.00 0.02

III.2 PEMASANGAN ACCESSORIES PIPA


1 Un Equal Tee (HDPE) Ø 160 mm M² 24,376.00 9.00 219,384.00 0.01 3.00 0.00 - - 3.00 0.00 73,128.00
2 Gate Valve All Flange (CI) Ø 160 mm Bh 306,449.00 3.00 919,347.00 0.03
3 Gate Valve All Flange (CI) Ø 110 mm Bh 239,981.50 2.00 479,963.00 0.02
4 Gate Valve All Flange (CI) Ø 90 mm Bh 181,214.00 6.00 1,087,284.00 0.04 3.00 0.02 3.00 0.02 543,642.00

Jumlah Total III 83,105,578.00 2.85 0.12 0.41 0.53 15,401,170.00


Kontrak Awal Realisasi Fisik Pekerjaan
Harga Satuan Minggu Lalu Minggu Ini S/d Minggu Ini Jumlah Harga
No. Uraian Pekerjaan Satuan Jumlah Harga Bobot Keterangan
Volume Bobot Bobot Bobot
Volume Volume Volume
(Rupiah) (Rupiah) (%) (%) (%) (%) ( Rupiah )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

IV PEKERJAAN JEMBATAN PIPA & UTILITAS


1 Perlintasan Gorong2 Pipa GI Ø 150 mm L = 3 M' Unit 14,916,400.00 1.00 14,916,400.00 0.51
2 Boring jalan Ø 100 mm M' 539,000.00 8.00 4,312,000.00 0.15
3 Pipa Selubung CI Ø 100 mm M' 600,000.00 8.00 4,800,000.00 0.16
4 Cor Beton 1 : 2 : 3 M³ 1,486,430.00 5.33 7,922,671.90 0.27
5 Bongkaran Cor Beton 1 : 2 : 3 M³ 129,305.00 5.33 689,195.65 0.02 0.96 0.00 1.34 0.01 2.30 0.01 297,401.50
6 Interkoneksi pipa baru dengan pipa Exsisting Titik 449,691.00 4.00 1,798,764.00 0.06 1.00 0.02 1.00 0.02 449,691.00

Jumlah Total IV 34,439,031.55 1.18 0.00 0.02 0.03 747,092.50

Jumlah Total Sebelum PPn 2,915,058,180.34 100.00 67.20 5.71 72.91 2,125,424,676.05
PPn 10 % 291,505,818.03
Jumlah Total Setelah PPn 3,206,563,998.37

Samarinda, 11 Agustus 2020


Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :
Staf Pembantu PPTK Konsultan Supervisi Kontraktor Pelaksana
Pembangunan Sistem Penyediaan Air Minum Dan Sanitasi CV. Jasa Pribhuni CV. Titanium Indonesia

H. Noviansyah, ST Hasfiansyah, ST Emaylda Ratria Wibowo, ST


NIP : 19821108 200912 1 001 Inspector Site Manager