DEPARTEMEN POM & PROJECT

Bill of Quantity

PEKERJAAN : PEMBONGKARAN WAREHOUSE - BOGOR


LUAS AREA : 3@25 X 78 M2
LOKASI : BOGOR

HARGA SAT JUMLAH HARGA


No. D E S C R I P T I O N Qty Unit
( Rp ) ( Rp )
A. PEKERJAAN PERSIAPAN
1 Local Permit 1.00 Ls 20,000,000 20,000,000
2 Pek. Mob dan Demobilisasi Alat dan Pekerja 1.00 Ls 70,000,000 70,000,000
3 Pek. Listrik dan Air Kerja 1.00 Ls 40,000,000 40,000,000
4 Pek. Administrasi, Dokumentasi 1.00 Ls 7,000,000 7,000,000
5 Pek. Rental Alat Berat -
- Crane 30T (2 Unit) 1.00 Ls 400,000,000 400,000,000
- Jack Hammer 1.00 Ls 5,700,000 5,700,000
Sub Total A 542,700,000
B. PEKERJAAN PEMBONGAKARAN STEEL STRUCTURE, ROOFING & BRICK WALL
1 Pek. Bongkar Atap 7,830.00 m2 25,000 195,750,000
2 Pek. Bongkar Sagrod, bracing & Purlin 120,968.27 Kg 1,900 229,839,705
3 Pek. Bongkar Talang 324.00 m; 25,000 8,100,000
4 Pek. Bongkar Brick Wall 8,236.80 m2 22,000 181,209,600
5 Pek. Bongkar Rafter, Kolom, Tie Beam & Canopy 139,080.80 kg 1,900 264,253,520
6 Pek. Biaya Handling (penyusunan bongkaran disusun berdasakan keputusan direksi) 260,049.07 Kg 400.00 104,019,626
7 Pek. Bongkar Pintu Besi (4x5m2) 3.00 Unit 2,250,000 6,750,000
8 Pek Bongkar canopy area loading dock 1.00 Ls 28,080,000 28,080,000
Sub Total B 1,018,002,451
C. PEKERJAAN PEMBONGAKARAN STEEL STRUCTURE, (Area Mezanin)
1 Pekerjaan Bongkar Mezanin 1.00 ls 105,701,408 105,701,408
Sub Total C 105,701,408
D. PEKERJAAN PEMBONGAKARAN GUDANG KECIL (DISAMPING GUDANG INDUK)
1 Pek. Bongkar gudang kecil (disamping gudang induk) dan bekas kantin 1.00 Ls 58,610,188 58,610,188
Sub Total D 58,610,188
TOTAL BIAYA 1,725,014,047

Page 1 of 1