RENCANA ANGGARAN BIAYA

ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA
NO. ITEM PEKERJAAN SATUAN VOLUME HARGA
SATUAN (Rp)
A. PEKERJAAN PERSIAPAN
1 MOBILISASI & DEMOBILISASI LS 1,00 5,000,000
2 PEMBERSIHAN AWAL & AKHIR M2 400,00 13,160
3 KANTOR DIREKSI KEET M2 10,00 1,534,193
4 GUDANG KERJA M2 10,00 1,250,732
5 PENGUKURAN PEMASANGAN PAPAN BOUWPLANK M' 120,00 78,837
6 PAPAN NAMA PROYEK LS 1,00 1,000,000
7 PENGADAAN AIR KERJA LS 1,00 3,000,000
8 ADMINISTRASI, DOKUMENTASI, & P3 - K LS 1,00 5,000,000
16,876,922
B. PEMBANGUNAN KANTOR PENGELOLA
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 61,460
2 URUGAN TANAH KEMBALI M3 3,47 44,520

II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 1,162,874
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 228,318

III PEKERJAAN PLESTERAN


1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 63,634
2 ACIAN DINDING M2 306,80 32,628
3 PLESTERAN DINDING MOTIF BH 46,00 63,634

IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND


1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 10,071,264
2 PINTU PANEL KAYU KLAS I M2 3,36 682,046
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 626,564
4 PASANG KACA MATI T = 5 MM M2 0,76 156,745
5 KUDA-KUDA BAJA RINGAN M2 124,00 235,950
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 253,523
7 PAS, NOK SPANDEK M' 43,38 139,059
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 104,927
10 PLAFOND TRIPLEKS 3 MM M2 140,00 51,694
11 LIST PLAFOND GYPSUM M' 253,79 91,750

V PEKERJAAN LANTAI DAN KERAMIK


1 MENGURUG TANAH DIBAWAH LANTAI M3 32,55 302,350
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 360,584
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 1,352,394
4 LANTAI KERAMIK 40/40 CM M2 66,39 158,283
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 158,283
6 LANTAI KERAMIK 20/20 CM M2 3,77 208,994
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 284,094

VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 4,255,239
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 7,035,297
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 6,373,190
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 6,836,856
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 7,474,398
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 5,095,968
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 5,984,662
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 5,095,968
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 5,881,551
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 7,736,217

VII PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 PASANG ENGSEL PINTU PSG 9,00 78,681
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 44,013
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 35,501
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 32,873
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 240,940

VIII PEKERJAAN LISTRIK


1 PASANG TITIK INSTALASI TTK 20,00 318,248
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 64,008
3 PASANG LAMPU DOWN LIGTH BH 16,00 176,008
4 PASANG PANEL MCB BH 1,00 272,328
5 PASANG SAKLAR TUNGGAL BH 2,00 29,848
6 PASANG SAKLAR GANDA BH 7,00 32,088
7 PASANG STOP KONTAK BH 6,00 28,728

IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 107,081
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 70,870
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 24,132
4 PASANG KRANK AIR 3/4" BH 2,00 25,004
5 PASANG KLOSET DUDUK BH 2,00 4,042,410
6 PASANG WASTAFEL + CERMIN BH 2,00 1,899,615
7 PASANG FLOOR DRAIN BH 2,00 95,340
8 SEPTICTANK UNIT 1,00 5,000,000
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000

X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 95,431
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 50,290

B PENGUMPUL KANTOR PENGELOLA


I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
III PEKERJAAN PLESTERAN
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
V PEKERJAAN LANTAI DAN KERAMIK
VI PEKERJAAN BETON
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
VIII PEKERJAAN LISTRIK
IX PEKERJAAN SANITASI
X PEKERJAAN FINISHING
JIMLAH TOTAL PENGUMPUL B
C. PEMBANGUNAN KANTOR UPT
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 61,460
2 URUGAN TANAH KEMBALI M3 3,47 44,520

II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 1,162,874
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 228,318

III PEKERJAAN PLESTERAN


1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 63,634
2 ACIAN DINDING M2 306,80 32,628
3 PLESTERAN DINDING MOTIF BH 46,00 63,634

IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND


1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 10,071,264
2 PINTU PANEL KAYU KLAS I M2 3,36 682,046
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 626,564
4 PASANG KACA MATI T = 5 MM M2 0,76 156,745
5 KUDA-KUDA BAJA RINGAN M2 124,00 235,950
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 253,523
7 PAS, NOK SPANDEK M' 43,38 139,059
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 104,927
10 PLAFOND TRIPLEKS 3 MM M2 140,00 51,694
11 LIST PLAFOND GYPSUM M' 253,79 91,750

V PEKERJAAN LANTAI DAN KERAMIK


1 MENGURUG TANAH DIBAWAH LANTAI M3 36,44 302,350
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 360,584
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 1,352,394
4 LANTAI KERAMIK 40/40 CM M2 66,39 158,283
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 158,283
6 LANTAI KERAMIK 20/20 CM M2 3,77 208,994
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 284,094

VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 4,255,239
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 7,035,297
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 6,373,190
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 6,836,856
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 7,474,398
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 5,095,968
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 5,984,662
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 5,095,968
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 5,881,551
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 7,736,217

VII PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 PASANG ENGSEL PINTU PSG 9,00 78,681
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 44,013
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 35,501
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 32,873
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 240,940

VIII PEKERJAAN LISTRIK


1 PASANG TITIK INSTALASI TTK 20,00 318,248
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 64,008
3 PASANG LAMPU DOWN LIGTH BH 16,00 176,008
4 PASANG PANEL MCB BH 1,00 272,328
5 PASANG SAKLAR TUNGGAL BH 2,00 29,848
6 PASANG SAKLAR GANDA BH 7,00 32,088
7 PASANG STOP KONTAK BH 6,00 28,728

IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 107,081
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 70,870
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 24,132
4 PASANG KRANK AIR 3/4" BH 2,00 25,004
5 PASANG KLOSET DUDUK BH 2,00 4,042,410
6 PASANG WASTAFEL + CERMIN BH 2,00 1,899,615
7 PASANG FLOOR DRAIN BH 2,00 95,340
8 SEPTICTANK UNIT 1,00 5,000,000
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000

X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 95,431
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 50,290

C PENGUMPUL KANTOR UPT


I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
III PEKERJAAN PLESTERAN
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
V PEKERJAAN LANTAI DAN KERAMIK
VI PEKERJAAN BETON
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
VIII PEKERJAAN LISTRIK
IX PEKERJAAN SANITASI
X PEKERJAAN FINISHING
JIMLAH TOTAL PENGUMPUL C
D. PEMBANGUNAN BAK PENAMPUNG AIR BERSIH DAN SUMUR
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 61,460
2 URUGAN TANAH KEMBALI M3 2,75 44,520

II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 6,11 1,162,874
2 PASANGAN BATAKO ad, 1 : 4 M2 35,00 228,318
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 190,00 63,634
2 ACIAN DINDING M2 190,00 32,628

IV PEKERJAAN BESI
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M2 5,81 10,071,264
2 PASANG TANGGA BESI UNIT 2,00 3,500,000

V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 15,84 302,350
2 MENGURUG PASIR DIBAWAH LANTAI M3 1,95 360,584
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 3,31 1,352,394

VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,50 4,970,058
2 BETON SLOOF 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 5,644,297
3 BETON SLOOF 15 x 40 CM ad, 1:2:3, 178 kg M3 0,37 6,030,686
4 BETON BALOK 20 x 40 CM ad, 1:2:3, 177 kg M3 0,67 7,203,926
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,54 7,474,398
6 BETON BALOK 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 6,836,856
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 0,94 5,984,662
8 BETON PLAT LANTAI T. 20 CM ad, 1:2:3, 123 kg M3 2,62 5,984,662
9 BETON DINDING T= 20 CM ad, 1:2:3, 119 kg M3 12,00 6,261,053
10 BETON KOLOM 30 x 30 CM ad, 1:2:3, 172 kg M3 3,40 7,060,036
11 BETON KOLOM 25 x 25 CM ad, 1:2:3, 139 kg M3 0,63 6,422,495

VII PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 PASANG ENGSEL PINTU PSG 4,50 78,681
5 PASANG KUNCI TANAM 2 SLAAG BH 3,00 240,940

VIII PEKERJAAN LISTRIK


1 PASANG TITIK INSTALASI TTK 2,00 318,248
2 PASANG LAMPU PHILIPS 18 WATT BH 2,00 64,008
4 PASANG PANEL MCB BH 1,00 272,328
5 PASANG SAKLAR TUNGGAL BH 2,00 29,848
7 PASANG STOP KONTAK BH 2,00 28,728

IX PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 2" M' 200,00 70,870
2 PASANG PIPA AIR BERSIH 3/4" M' 40,00 24,132
3 PASANG KRANK AIR 3/4" BH 2,00 25,004

X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 190,00 95,431
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 -

XI PEKERJAAN SUMUR
1 GALIAN TANAH SUMUR M' 40,00 500,000
2 BETON BUIS T= 15 CM, ad, 1:2:3, 60 kg M3 37,72 4,767,538
3 MESIN POMPA CELUP UNIT 3,00 4,700,000

D PENGUMPUL BAK PENAMPUNG AIR BERSIH DAN SUMUR


I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
III PEKERJAAN PLESTERAN
IV PEKERJAAN BESI
V PEKERJAAN LANTAI
VI PEKERJAAN BETON
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
VIII PEKERJAAN LISTRIK
IX PEKERJAAN SANITASI
X PEKERJAAN FINISHING
XI PEKERJAAN SUMUR
JIMLAH TOTAL PENGUMPUL D
E. PEMBANGUNAN BAK/TEMPAT SAMPAH
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 61,460
2 URUGAN TANAH KEMBALI M3 2,75 44,520

II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 7,30 1,162,874
2 PASANGAN BATAKO ad, 1 : 4 M2 65,00 228,318

III PEKERJAAN PLESTERAN


1 PLESTERAN TEMBOK ad, 1 : 4 M2 130,00 63,634
2 ACIAN DINDING M2 130,00 32,628

IV PEKERJAAN BESI
1 PASANG PINTU BESI KUSEN + DAUN PINTU + UPAH M' 9,20 700,000

V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 8,83 302,350
2 MENGURUG PASIR DIBAWAH LANTAI M3 2,42 360,584
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 6,06 1,352,394

VI PEKERJAAN BETON
1 BETON SLOOF 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 6,281,839
2 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,12 6,836,856
2 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 7,474,398
3 BETON KOLOM 15 x 15 CM ad, 1:2:3, 141 kg M3 0,61 6,461,134

VII PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 PASANG ENGSEL PINTU PSG 12,00 78,681
2 PASANG KUNCI TANAM 2 SLAAG BH 2,00 240,940

VIII PEKERJAAN SANITASI


1 PASANG PIPA AIR BERSIH 3/4" M' 20,00 24,132
2 PASANG KRANK AIR 3/4" BH 2,00 25,004

IX PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 130,00 95,431
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2

E PENGUMPUL BAK / TEMPAT SAMPAH


I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
III PEKERJAAN PLESTERAN
IV PEKERJAAN BESI
V PEKERJAAN LANTAI
VI PEKERJAAN BETON
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
VIII PEKERJAAN SANITASI
IX PEKERJAAN FINISHING
JIMLAH TOTAL PENGUMPUL E
F. PEMBANGUNAN BAK PENAMPUNG AIR KOTOR / IPAL
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 99,75 61,460
2 URUGAN TANAH KEMBALI M3 24,94 44,520

II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 2,04 1,162,874

III PEKERJAAN PLESTERAN


1 PLESTERAN TEMBOK ad, 1 : 4 M2 43,80 63,634
2 ACIAN DINDING M2 43,80 32,628

IV PEKERJAAN LANTAI
1 MENGURUG PASIR DIBAWAH LANTAI M3 2,40 302,350
2 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 1,20 1,352,394

V PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,40 4,255,239
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,96 7,035,297
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,52 7,474,398
4 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 3,71 7,568,856
5 BETON DINDING T= 12 CM ad, 1:2:3, 197 kg M3 8,64 7,767,969
6 BETON KOLOM 20 x 20 CM ad, 1:2:3, 223 kg M3 0,78 8,045,328

VI PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 4" M' 40,00 107,081

VII PEKERJAAN FINISHING


1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 43,80 95,431

F PENGUMPUL BAK PENAMPUNG AIR KOTOR / IPAL


I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
III PEKERJAAN PLESTERAN
IV PEKERJAAN LANTAI
V PEKERJAAN BETON
VI PEKERJAAN SANITASI
VII PEKERJAAN FINISHING
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 1 UNIT )
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 2 UNIT )
G. PEMBANGUNAN PINTU GERBANG DAN POS SATPAM
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 15,87 61,460
2 URUGAN TANAH KEMBALI M3 3,97 44,520

II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 12,22 1,162,874
2 PASANGAN BATAKO ad, 1 : 4 M2 44,00 228,318

III PEKERJAAN PLESTERAN


1 PLESTERAN TEMBOK ad, 1 : 4 M2 77,40 63,634
2 ACIAN DINDING M2 77,40 32,628
3 PLESTERAN DINDING MOTIF BH 46,00 63,634

IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND


1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 0,29 10,071,264
2 PINTU PANEL KAYU KLAS I M2 1,47 682,046
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 4,54 626,564
4 PASANG KACA MATI T = 5 MM M2 0,90 156,745
5 RANGKA PLAFOND KAYU KLAS II M2 19,00 104,927
6 PLAFOND TRIPLEKS 3 MM M2 19,00 51,694
7 LIST PLAFOND GYPSUM M' 5,04 91,750
8 PINTU SORONG, BESI HOLLOW T= 1,5 MM M2 36,50 700,000

V PEKERJAAN LANTAI DAN KERAMIK


1 MENGURUG TANAH DIBAWAH LANTAI M3 2,91 302,350
2 MENGURUG PASIR DIBAWAH LANTAI M3 0,81 360,584
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 1,21 1,352,394
4 LANTAI KERAMIK 40/40 CM M2 6,00 158,283
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 12,21 158,283
6 LANTAI KERAMIK 20/20 CM M2 2,00 208,994
7 DINDING KERAMIK 20/20 CM T = 2 M M2 10,60 284,094

VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,00 4,970,058
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,75 7,035,297
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,86 7,474,398
4 BETON BALOK 10 x 12 CM ad, 1:2:3, 244 kg M3 0,05 8,498,328
5 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 2,15 7,568,856
6 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 0,67 5,095,968
7 BETON CANOPI ad, 1:2:3, 77 kg M3 0,09 5,095,968
8 BETON KOLOM 30 x 50 CM ad, 1:2:3, 97 kg M3 2,60 5,611,078
9 BETON KOLOM 15 x 30 CM ad, 1:2:3, 165 kg M3 1,98 6,924,800
10 BETON KOLOM 12 x 30 CM ad, 1:2:3, 202 kg M3 0,95 7,639,620

VII PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 PASANG ENGSEL PINTU PSG 1,50 78,681
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 12,00 44,013
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 12,00 35,501
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 12,00 32,873
5 PASANG KUNCI TANAM 2 SLAAG BH 1,00 240,940

VIII PEKERJAAN LISTRIK


1 PASANG TITIK INSTALASI TTK 6,00 318,248
2 PASANG LAMPU PHILIPS 18 WATT BH 6,00 64,008
3 PASANG PANEL MCB BH 1,00 272,328
4 PASANG SAKLAR TUNGGAL BH 2,00 29,848
5 PASANG SAKLAR GANDA BH 2,00 32,088
6 PASANG STOP KONTAK BH 4,00 28,728

IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 8,00 107,081
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 70,870
3 PASANG PIPA AIR BERSIH 3/4" M' 20,00 24,132
4 PASANG KRANK AIR 3/4" BH 1,00 25,004
5 PASANG KLOSET DUDUK BH 1,00 4,042,410
6 PASANG WASTAFEL + CERMIN BH 1,00 1,899,615
7 PASANG FLOOR DRAIN BH 1,00 95,340
8 SEPTICTANK UNIT 1,00 5,000,000

X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 96,40 95,431
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 16,52 50,290

XI PEKERJAAN HURUF
1 PASANG HURUF BAHAN STAINLESS BH 30,00 300,000

G PENGUMPUL PINTU MASUK DAN POS SATPAM


I PEKERJAAN TANAH
II PEKERJAAN PASANGAN
III PEKERJAAN PLESTERAN
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
V PEKERJAAN LANTAI DAN KERAMIK
VI PEKERJAAN BETON
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
VIII PEKERJAAN LISTRIK
IX PEKERJAAN SANITASI
X PEKERJAAN FINISHING
XI PEKERJAAN HURUF
JIMLAH TOTAL PENGUMPUL G
JUMLAH HARGA
(Rp)

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
56,573,664

854,294
154,484
1,008,778

18,164,086
37,444,086
55,608,172

19,523,024
10,010,393
2,927,181
32,460,598

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
142,398,426

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
45,482,739

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
102,730,624

708,130
5,017,505
4,047,137
3,747,536
1,204,700
14,725,007

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
10,166,128

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
47,074,563

42,638,446
4,338,491
46,976,936

1,008,778
55,608,172
32,460,598
142,398,426
45,482,739
102,730,624
14,725,007
10,166,128
47,074,563
46,976,936
498,631,972

854,294
154,484
1,008,778

18,164,086
37,444,086
55,608,172

19,523,024
10,010,393
2,927,181
32,460,598

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
142,398,426

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
46,658,879

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
102,730,624

708,130
5,017,505
4,047,137
3,747,536
1,204,700
14,725,007

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
10,166,128

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
47,074,563

42,638,446
4,338,491
46,976,936

1,008,778
55,608,172
32,460,598
142,398,426
46,658,879
102,730,624
14,725,007
10,166,128
47,074,563
46,976,936
499,808,112

675,445
122,430
797,875

7,105,158
7,991,116
15,096,274
12,090,530
6,199,396
18,289,926

58,514,044
7,000,000
65,514,044

4,789,218
703,139
4,476,425
9,968,782

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
164,005,908

354,065
722,820
1,076,885

636,496
128,016
272,328
59,696
57,456
1,153,992

14,173,936
965,261
50,008
15,189,205

18,131,837

18,131,837

20,000,000
179,831,518
14,100,000
213,931,518

797,875
15,096,274
18,289,926
65,514,044
9,968,782
164,005,908
1,076,885
1,153,992
15,189,205
18,131,837
213,931,518
523,156,246

675,445
122,430
797,875
8,488,977
14,840,644
23,329,621

8,272,468
4,241,692
12,514,160

6,440,000
6,440,000

2,669,747
872,613
8,195,510
11,737,870

7,098,478
820,423
8,446,070
3,941,292
20,306,262

944,173
481,880
1,426,053

482,630
50,008
532,638

12,405,994

12,405,994

797,875
23,329,621
12,514,160
6,440,000
11,737,870
20,306,262
1,426,053
532,638
12,405,994
89,490,474

6,130,635
1,110,329
7,240,964

2,372,262
2,372,262

2,787,185
1,429,124
4,216,309

725,639
1,622,873
2,348,512

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
121,288,129
4,283,250
4,283,250

4,179,866
4,179,866

7,240,964
2,372,262
4,216,309
2,348,512
121,288,129
4,283,250
4,179,866
145,929,292
291,858,584

975,370
176,744
1,152,115

14,210,315
10,045,974
24,256,290

4,925,300
2,525,438
2,927,181
10,377,919

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
35,897,152

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
9,120,024

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
72,802,954

118,022
528,158
426,014
394,477
240,940
1,707,612

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
2,804,648

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,968,607

9,199,521
830,786
10,030,307

9,000,000
9,000,000

1,152,115
24,256,290
10,377,919
35,897,152
9,120,024
72,802,954
1,707,612
2,804,648
12,968,607
10,030,307
9,000,000
190,117,628
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

A. PEKERJAAN PERSIAPAN
1 MOBILISASI & DEMOBILISASI LS 1,00 5,000,000 5,000,000
2 PEMBERSIHAN AWAL & AKHIR M2 400,00 11,750 #VALUE!
3 KANTOR DIREKSI KEET M2 10,00 1,293,615 #VALUE!
4 GUDANG KERJA M2 10,00 1,099,970 #VALUE!
5 PENGUKURAN PEMASANGAN PAPAN BOUWPLANK M' 120,00 70,270 #VALUE!
6 PAPAN NAMA PROYEK LS 1,00 1,000,000 #VALUE!
7 PENGADAAN AIR KERJA LS 1,00 3,000,000 #VALUE!
8 ADMINISTRASI, DOKUMENTASI, & P3 - K LS 1,00 5,000,000 #VALUE!
16,475,605 51,068,250
B. PEMBANGUNAN KANTOR PENGELOLA
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 54,875 762,763
2 URUGAN TANAH KEMBALI M3 3,47 39,750 137,933
900,695
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 718,450 11,222,189
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 159,665 26,185,060
37,407,249
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 53,658 16,462,274
2 ACIAN DINDING M2 306,80 27,800 8,529,040
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 8,984,700 10,601,946
2 PINTU PANEL KAYU KLAS I M2 3,36 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,76 139,951 #VALUE!
5 KUDA-KUDA BAJA RINGAN M2 124,00 197,920 #VALUE!
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 226,360 #VALUE!
7 PAS, NOK SPANDEK M' 43,38 124,160 #VALUE!
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000 #VALUE!
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 92,185 #VALUE!
10 PLAFOND TRIPLEKS 3 MM M2 140,00 46,155 #VALUE!
11 LIST PLAFOND GYPSUM M' 253,79 81,920 #VALUE!
124,165,086
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 32,55 269,955 8,787,035
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 66,39 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 3,77 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 238,930 #VALUE!
37,495,333
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 3,560,079 712,016
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 5,598,123 #VALUE!
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 5,306,356 #VALUE!
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 5,644,744 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 6,110,028 #VALUE!
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 4,345,530 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 4,994,107 #VALUE!
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 4,345,530 #VALUE!
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 4,939,843 #VALUE!
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 6,293,395 #VALUE!
84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 9,00 70,251 632,259
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 39,298 4,479,915
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 19,698 2,245,515
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 29,351 3,346,014
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 215,125 1,075,625
11,779,328
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 20,00 284,150 #VALUE!
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 57,150 #VALUE!
3 PASANG LAMPU DOWN LIGTH BH 16,00 157,150 #VALUE!
4 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
6 PASANG SAKLAR GANDA BH 7,00 26,150 #VALUE!
7 PASANG STOP KONTAK BH 6,00 25,650 #VALUE!
9,054,400
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 86,292 #VALUE!
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 2,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 2,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 2,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 2,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000 #VALUE!
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000 #VALUE!
44,139,186
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 87,666 39,169,169
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 48,408 4,176,115
43,345,284
B PENGUMPUL KANTOR PENGELOLA
I PEKERJAAN TANAH 900,695
II PEKERJAAN PASANGAN 37,407,249
III PEKERJAAN PLESTERAN 27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 124,165,086
V PEKERJAAN LANTAI DAN KERAMIK 37,495,333
VI PEKERJAAN BETON 84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 11,779,328
VIII PEKERJAAN LISTRIK 9,054,400
IX PEKERJAAN SANITASI 44,139,186
X PEKERJAAN FINISHING 43,345,284
JIMLAH TOTAL PENGUMPUL B 420,526,404
C. PEMBANGUNAN KANTOR UPT
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 54,875 762,763
2 URUGAN TANAH KEMBALI M3 3,47 39,750 137,933
900,695
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 718,450 11,222,189
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 159,665 26,185,060
37,407,249
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 53,658 16,462,274
2 ACIAN DINDING M2 306,80 27,800 8,529,040
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 8,984,700 10,601,946
2 PINTU PANEL KAYU KLAS I M2 3,36 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,76 139,951 #VALUE!
5 KUDA-KUDA BAJA RINGAN M2 124,00 197,920 #VALUE!
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 226,360 #VALUE!
7 PAS, NOK SPANDEK M' 43,38 124,160 #VALUE!
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000 #VALUE!
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 92,185 #VALUE!
10 PLAFOND TRIPLEKS 3 MM M2 140,00 46,155 #VALUE!
11 LIST PLAFOND GYPSUM M' 253,79 81,920 20,790,477
124,165,086
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 36,44 269,955 9,837,160
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 66,39 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 3,77 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 238,930 #VALUE!
38,545,458
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 3,560,079 712,016
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 5,598,123 #VALUE!
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 5,306,356 #VALUE!
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 5,644,744 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 6,110,028 #VALUE!
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 4,345,530 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 4,994,107 #VALUE!
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 4,345,530 #VALUE!
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 4,939,843 #VALUE!
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 6,293,395 #VALUE!
84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 9,00 70,251 632,259
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 39,298 4,479,915
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 19,698 2,245,515
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 29,351 3,346,014
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 215,125 1,075,625
11,779,328
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 20,00 284,150 5,683,000
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 57,150 #VALUE!
3 PASANG LAMPU DOWN LIGTH BH 16,00 157,150 #VALUE!
4 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
6 PASANG SAKLAR GANDA BH 7,00 26,150 #VALUE!
7 PASANG STOP KONTAK BH 6,00 25,650 #VALUE!
9,054,400
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 86,292 1,035,504
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 2,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 2,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 2,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 2,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000 #VALUE!
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000 #VALUE!
44,139,186
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 87,666 39,169,169
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 48,408 4,176,115
43,345,284
C PENGUMPUL KANTOR UPT
I PEKERJAAN TANAH 900,695
II PEKERJAAN PASANGAN 37,407,249
III PEKERJAAN PLESTERAN 27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 124,165,086
V PEKERJAAN LANTAI DAN KERAMIK 38,545,458
VI PEKERJAAN BETON 84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 11,779,328
VIII PEKERJAAN LISTRIK 9,054,400
IX PEKERJAAN SANITASI 44,139,186
X PEKERJAAN FINISHING 43,345,284
JIMLAH TOTAL PENGUMPUL C 421,576,529
D. PEMBANGUNAN BAK PENAMPUNG AIR BERSIH DAN SUMUR
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 54,875 603,076
2 URUGAN TANAH KEMBALI M3 2,75 39,750 109,313
712,389
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 6,11 718,450 4,389,730
2 PASANGAN BATAKO ad, 1 : 4 M2 35,00 159,665 5,588,275
9,978,005
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 190,00 53,658 10,195,020
2 ACIAN DINDING M2 190,00 27,800 5,282,000
15,477,020
IV PEKERJAAN BESI
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M2 5,81 8,984,700 52,201,107
2 PASANG TANGGA BESI UNIT 2,00 3,500,000 7,000,000
59,201,107
V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 15,84 269,955 4,276,087
2 MENGURUG PASIR DIBAWAH LANTAI M3 1,95 285,950 557,603
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 3,31 936,375 3,099,401
7,933,091
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,50 4,081,760 6,122,640
2 BETON SLOOF 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 4,582,959 #VALUE!
3 BETON SLOOF 15 x 40 CM ad, 1:2:3, 178 kg M3 0,37 4,864,949 #VALUE!
4 BETON BALOK 20 x 40 CM ad, 1:2:3, 177 kg M3 0,67 5,912,635 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,54 6,110,028 #VALUE!
6 BETON BALOK 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 5,644,744 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 0,94 4,994,107 #VALUE!
8 BETON PLAT LANTAI T. 20 CM ad, 1:2:3, 123 kg M3 2,62 4,994,107 #VALUE!
9 BETON DINDING T= 20 CM ad, 1:2:3, 119 kg M3 12,00 5,253,484 #VALUE!
10 BETON KOLOM 30 x 30 CM ad, 1:2:3, 172 kg M3 3,40 5,799,912 #VALUE!
11 BETON KOLOM 25 x 25 CM ad, 1:2:3, 139 kg M3 0,63 5,334,629 #VALUE!
136,267,430
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 4,50 70,251 316,130
5 PASANG KUNCI TANAM 2 SLAAG BH 3,00 215,125 645,375
961,505
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 2,00 284,150 568,300
2 PASANG LAMPU PHILIPS 18 WATT BH 2,00 57,150 114,300
4 PASANG PANEL MCB BH 1,00 243,150 243,150
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 48,300
7 PASANG STOP KONTAK BH 2,00 25,650 51,300
1,025,350
IX PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 2" M' 200,00 51,242 10,248,300
2 PASANG PIPA AIR BERSIH 3/4" M' 40,00 21,546 861,840
3 PASANG KRANK AIR 3/4" BH 2,00 22,325 44,650
11,154,790
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 190,00 87,666 16,656,540
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 -
16,656,540
XI PEKERJAAN SUMUR
1 GALIAN TANAH SUMUR M' 40,00 500,000 20,000,000
2 BETON BUIS T= 15 CM, ad, 1:2:3, 60 kg M3 37,72 4,105,838 154,872,209
3 MESIN POMPA CELUP UNIT 3,00 5,000,000 15,000,000
189,872,209
D PENGUMPUL BAK PENAMPUNG AIR BERSIH DAN SUMUR
I PEKERJAAN TANAH 712,389
II PEKERJAAN PASANGAN 9,978,005
III PEKERJAAN PLESTERAN 15,477,020
IV PEKERJAAN BESI 59,201,107
V PEKERJAAN LANTAI 7,933,091
VI PEKERJAAN BETON 136,267,430
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 961,505
VIII PEKERJAAN LISTRIK 1,025,350
IX PEKERJAAN SANITASI 11,154,790
X PEKERJAAN FINISHING 16,656,540
XI PEKERJAAN SUMUR 189,872,209
JIMLAH TOTAL PENGUMPUL D 449,239,435
E. PEMBANGUNAN BAK/TEMPAT SAMPAH
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 54,875 603,076
2 URUGAN TANAH KEMBALI M3 2,75 39,750 109,313
712,389
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 7,30 718,450 5,244,685
2 PASANGAN BATAKO ad, 1 : 4 M2 65,00 159,665 10,378,225
15,622,910
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 130,00 53,658 6,975,540
2 ACIAN DINDING M2 130,00 27,800 3,614,000
10,589,540
IV PEKERJAAN BESI
1 PASANG PINTU BESI KUSEN + DAUN PINTU + UPAH M' 9,20 700,000 6,440,000
6,440,000
V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 8,83 269,955 2,383,703
2 MENGURUG PASIR DIBAWAH LANTAI M3 2,42 285,950 691,999
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 6,06 936,375 5,674,433
8,750,134
VI PEKERJAAN BETON
1 BETON SLOOF 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 5,048,243 5,704,514
2 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,12 5,644,744 677,369
2 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 6,110,028 6,904,331
3 BETON KOLOM 15 x 15 CM ad, 1:2:3, 141 kg M3 0,61 5,362,828 3,271,325
16,557,539
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 12,00 70,251 843,012
2 PASANG KUNCI TANAM 2 SLAAG BH 2,00 215,125 430,250
1,273,262
VIII PEKERJAAN SANITASI
1 PASANG PIPA AIR BERSIH 3/4" M' 20,00 21,546 430,920
2 PASANG KRANK AIR 3/4" BH 2,00 22,325 44,650
475,570
IX PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 130,00 87,666 11,396,580
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2
11,396,580
E PENGUMPUL BAK / TEMPAT SAMPAH
I PEKERJAAN TANAH 712,389
II PEKERJAAN PASANGAN 15,622,910
III PEKERJAAN PLESTERAN 10,589,540
IV PEKERJAAN BESI 6,440,000
V PEKERJAAN LANTAI 8,750,134
VI PEKERJAAN BETON 16,557,539
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,273,262
VIII PEKERJAAN SANITASI 475,570
IX PEKERJAAN FINISHING 11,396,580
JIMLAH TOTAL PENGUMPUL E 71,817,924
F. PEMBANGUNAN BAK PENAMPUNG AIR KOTOR / IPAL
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 99,75 54,875 5,473,781
2 URUGAN TANAH KEMBALI M3 24,94 39,750 991,365
6,465,146
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 2,04 718,450 1,465,638
1,465,638
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 43,80 53,658 2,350,220
2 ACIAN DINDING M2 43,80 27,800 1,217,640
3,567,860
IV PEKERJAAN LANTAI
1 MENGURUG PASIR DIBAWAH LANTAI M3 2,40 269,955 647,892
2 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 1,20 936,375 1,123,650
1,771,542
V PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,40 3,560,079 #VALUE!
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,96 5,598,123 #VALUE!
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,52 6,110,028 #VALUE!
4 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 3,71 6,150,266 #VALUE!
5 BETON DINDING T= 12 CM ad, 1:2:3, 197 kg M3 8,64 6,353,245 #VALUE!
6 BETON KOLOM 20 x 20 CM ad, 1:2:3, 223 kg M3 0,78 6,518,987 #VALUE!
98,879,798
VI PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 4" M' 40,00 86,292 3,451,680
3,451,680
VII PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 43,80 87,666 3,839,771
3,839,771
F PENGUMPUL BAK PENAMPUNG AIR KOTOR / IPAL
I PEKERJAAN TANAH 6,465,146
II PEKERJAAN PASANGAN 1,465,638
III PEKERJAAN PLESTERAN 3,567,860
IV PEKERJAAN LANTAI 1,771,542
V PEKERJAAN BETON 98,879,798
VI PEKERJAAN SANITASI 3,451,680
VII PEKERJAAN FINISHING 3,839,771
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 1 UNIT ) 119,441,436
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 2 UNIT ) 238,882,871
G. PEMBANGUNAN PINTU GERBANG DAN POS SATPAM
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 15,87 54,875 870,866
2 URUGAN TANAH KEMBALI M3 3,97 39,750 157,808
1,028,674
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 12,22 718,450 8,779,459
2 PASANGAN BATAKO ad, 1 : 4 M2 44,00 159,665 7,025,260
15,804,719
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 77,40 53,658 4,153,129
2 ACIAN DINDING M2 77,40 27,800 2,151,720
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
8,773,117
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 0,29 8,984,700 2,605,563
2 PINTU PANEL KAYU KLAS I M2 1,47 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 4,54 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,90 139,951 #VALUE!
5 RANGKA PLAFOND KAYU KLAS II M2 19,00 92,185 #VALUE!
6 PLAFOND TRIPLEKS 3 MM M2 19,00 46,155 #VALUE!
7 LIST PLAFOND GYPSUM M' 5,04 81,920 #VALUE!
8 PINTU SORONG, BESI HOLLOW T= 1,5 MM M2 36,50 700,000 #VALUE!
34,438,187
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 2,91 269,955 785,569
2 MENGURUG PASIR DIBAWAH LANTAI M3 0,81 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 1,21 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 6,00 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 12,21 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 2,00 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 2 M M2 10,60 238,930 #VALUE!
7,469,667
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,00 4,081,760 4,081,760
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,75 5,598,123 #VALUE!
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,86 6,110,028 #VALUE!
4 BETON BALOK 10 x 12 CM ad, 1:2:3, 244 kg M3 0,05 6,857,301 #VALUE!
5 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 2,15 6,150,266 #VALUE!
6 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 0,67 4,345,530 #VALUE!
7 BETON CANOPI ad, 1:2:3, 77 kg M3 0,09 4,345,530 #VALUE!
8 BETON KOLOM 30 x 50 CM ad, 1:2:3, 97 kg M3 2,60 4,742,450 #VALUE!
9 BETON KOLOM 15 x 30 CM ad, 1:2:3, 165 kg M3 1,98 5,701,216 #VALUE!
10 BETON KOLOM 12 x 30 CM ad, 1:2:3, 202 kg M3 0,95 6,222,897 #VALUE!
59,934,042
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 1,50 70,251 105,377
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 12,00 39,298 471,570
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 12,00 19,698 236,370
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 12,00 29,351 352,212
5 PASANG KUNCI TANAM 2 SLAAG BH 1,00 215,125 215,125
1,380,654
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 6,00 284,150 #VALUE!
2 PASANG LAMPU PHILIPS 18 WATT BH 6,00 57,150 #VALUE!
3 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
4 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
5 PASANG SAKLAR GANDA BH 2,00 26,150 #VALUE!
6 PASANG STOP KONTAK BH 4,00 25,650 #VALUE!
2,494,150
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 8,00 86,292 690,336
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 20,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 1,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 1,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 1,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 1,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
11,406,683
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 96,40 87,666 8,451,002
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 16,52 48,408 799,692
9,250,694
XI PEKERJAAN HURUF
1 PASANG HURUF BAHAN STAINLESS BH 30,00 300,000 9,000,000
9,000,000
G PENGUMPUL PINTU MASUK DAN POS SATPAM
I PEKERJAAN TANAH 1,028,674
II PEKERJAAN PASANGAN 15,804,719
III PEKERJAAN PLESTERAN 8,773,117
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 34,438,187
V PEKERJAAN LANTAI DAN KERAMIK 7,469,667
VI PEKERJAAN BETON 59,934,042
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,380,654
VIII PEKERJAAN LISTRIK 2,494,150
IX PEKERJAAN SANITASI 11,406,683
X PEKERJAAN FINISHING 9,250,694
XI PEKERJAAN HURUF 9,000,000
JIMLAH TOTAL PENGUMPUL G 160,980,586
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

A. PEKERJAAN PERSIAPAN
1 MOBILISASI & DEMOBILISASI LS 1,00 5,000,000 5,000,000
2 PEMBERSIHAN AWAL & AKHIR M2 400,00 11,750 #VALUE!
3 KANTOR DIREKSI KEET M2 10,00 1,293,615 #VALUE!
4 GUDANG KERJA M2 10,00 1,099,970 #VALUE!
5 PENGUKURAN PEMASANGAN PAPAN BOUWPLANK M' 120,00 70,270 #VALUE!
6 PAPAN NAMA PROYEK LS 1,00 1,000,000 #VALUE!
7 PENGADAAN AIR KERJA LS 1,00 3,000,000 #VALUE!
8 ADMINISTRASI, DOKUMENTASI, & P3 - K LS 1,00 5,000,000 #VALUE!
16,475,605 51,068,250
B. PEMBANGUNAN KANTOR PENGELOLA
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 54,875 762,763
2 URUGAN TANAH KEMBALI M3 3,47 39,750 137,933
900,695
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 718,450 11,222,189
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 159,665 26,185,060
37,407,249
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 53,658 16,462,274
2 ACIAN DINDING M2 306,80 27,800 8,529,040
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 8,984,700 10,601,946
2 PINTU PANEL KAYU KLAS I M2 3,36 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,76 139,951 #VALUE!
5 KUDA-KUDA BAJA RINGAN M2 124,00 197,920 #VALUE!
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 226,360 #VALUE!
7 PAS, NOK SPANDEK M' 43,38 124,160 #VALUE!
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000 #VALUE!
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 92,185 #VALUE!
10 PLAFOND TRIPLEKS 3 MM M2 140,00 46,155 #VALUE!
11 LIST PLAFOND GYPSUM M' 253,79 81,920 #VALUE!
124,165,086
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 32,55 269,955 8,787,035
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 66,39 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 3,77 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 238,930 #VALUE!
37,495,333
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 3,560,079 712,016
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 5,598,123 #VALUE!
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 5,306,356 #VALUE!
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 5,644,744 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 6,110,028 #VALUE!
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 4,345,530 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 4,994,107 #VALUE!
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 4,345,530 #VALUE!
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 4,939,843 #VALUE!
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 6,293,395 #VALUE!
84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 9,00 70,251 632,259
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 39,298 4,479,915
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 19,698 2,245,515
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 29,351 3,346,014
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 215,125 1,075,625
11,779,328
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 20,00 284,150 #VALUE!
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 57,150 #VALUE!
3 PASANG LAMPU DOWN LIGTH BH 16,00 157,150 #VALUE!
4 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
6 PASANG SAKLAR GANDA BH 7,00 26,150 #VALUE!
7 PASANG STOP KONTAK BH 6,00 25,650 #VALUE!
9,054,400
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 86,292 #VALUE!
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 2,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 2,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 2,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 2,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000 #VALUE!
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000 #VALUE!
44,139,186
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 87,666 39,169,169
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 48,408 4,176,115
43,345,284
B PENGUMPUL KANTOR PENGELOLA
I PEKERJAAN TANAH 900,695
II PEKERJAAN PASANGAN 37,407,249
III PEKERJAAN PLESTERAN 27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 124,165,086
V PEKERJAAN LANTAI DAN KERAMIK 37,495,333
VI PEKERJAAN BETON 84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 11,779,328
VIII PEKERJAAN LISTRIK 9,054,400
IX PEKERJAAN SANITASI 44,139,186
X PEKERJAAN FINISHING 43,345,284
JIMLAH TOTAL PENGUMPUL B 420,526,404
C. PEMBANGUNAN KANTOR UPT
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 54,875 762,763
2 URUGAN TANAH KEMBALI M3 3,47 39,750 137,933
900,695
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 718,450 11,222,189
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 159,665 26,185,060
37,407,249
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 53,658 16,462,274
2 ACIAN DINDING M2 306,80 27,800 8,529,040
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 8,984,700 10,601,946
2 PINTU PANEL KAYU KLAS I M2 3,36 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,76 139,951 #VALUE!
5 KUDA-KUDA BAJA RINGAN M2 124,00 197,920 #VALUE!
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 226,360 #VALUE!
7 PAS, NOK SPANDEK M' 43,38 124,160 #VALUE!
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000 #VALUE!
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 92,185 #VALUE!
10 PLAFOND TRIPLEKS 3 MM M2 140,00 46,155 #VALUE!
11 LIST PLAFOND GYPSUM M' 253,79 81,920 20,790,477
124,165,086
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 36,44 269,955 9,837,160
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 66,39 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 3,77 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 238,930 #VALUE!
38,545,458
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 3,560,079 712,016
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 5,598,123 #VALUE!
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 5,306,356 #VALUE!
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 5,644,744 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 6,110,028 #VALUE!
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 4,345,530 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 4,994,107 #VALUE!
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 4,345,530 #VALUE!
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 4,939,843 #VALUE!
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 6,293,395 #VALUE!
84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 9,00 70,251 632,259
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 39,298 4,479,915
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 19,698 2,245,515
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 29,351 3,346,014
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 215,125 1,075,625
11,779,328
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 20,00 284,150 5,683,000
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 57,150 #VALUE!
3 PASANG LAMPU DOWN LIGTH BH 16,00 157,150 #VALUE!
4 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
6 PASANG SAKLAR GANDA BH 7,00 26,150 #VALUE!
7 PASANG STOP KONTAK BH 6,00 25,650 #VALUE!
9,054,400
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 86,292 1,035,504
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 2,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 2,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 2,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 2,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000 #VALUE!
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000 #VALUE!
44,139,186
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 87,666 39,169,169
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 48,408 4,176,115
43,345,284
C PENGUMPUL KANTOR UPT
I PEKERJAAN TANAH 900,695
II PEKERJAAN PASANGAN 37,407,249
III PEKERJAAN PLESTERAN 27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 124,165,086
V PEKERJAAN LANTAI DAN KERAMIK 38,545,458
VI PEKERJAAN BETON 84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 11,779,328
VIII PEKERJAAN LISTRIK 9,054,400
IX PEKERJAAN SANITASI 44,139,186
X PEKERJAAN FINISHING 43,345,284
JIMLAH TOTAL PENGUMPUL C 421,576,529
D. PEMBANGUNAN BAK PENAMPUNG AIR BERSIH DAN SUMUR
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 54,875 603,076
2 URUGAN TANAH KEMBALI M3 2,75 39,750 109,313
712,389
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 6,11 718,450 4,389,730
2 PASANGAN BATAKO ad, 1 : 4 M2 35,00 159,665 5,588,275
9,978,005
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 190,00 53,658 10,195,020
2 ACIAN DINDING M2 190,00 27,800 5,282,000
15,477,020
IV PEKERJAAN BESI
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M2 5,81 8,984,700 52,201,107
2 PASANG TANGGA BESI UNIT 2,00 3,500,000 7,000,000
59,201,107
V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 15,84 269,955 4,276,087
2 MENGURUG PASIR DIBAWAH LANTAI M3 1,95 285,950 557,603
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 3,31 936,375 3,099,401
7,933,091
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,50 4,081,760 6,122,640
2 BETON SLOOF 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 4,582,959 #VALUE!
3 BETON SLOOF 15 x 40 CM ad, 1:2:3, 178 kg M3 0,37 4,864,949 #VALUE!
4 BETON BALOK 20 x 40 CM ad, 1:2:3, 177 kg M3 0,67 5,912,635 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,54 6,110,028 #VALUE!
6 BETON BALOK 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 5,644,744 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 0,94 4,994,107 #VALUE!
8 BETON PLAT LANTAI T. 20 CM ad, 1:2:3, 123 kg M3 2,62 4,994,107 #VALUE!
9 BETON DINDING T= 20 CM ad, 1:2:3, 119 kg M3 12,00 5,253,484 #VALUE!
10 BETON KOLOM 30 x 30 CM ad, 1:2:3, 172 kg M3 3,40 5,799,912 #VALUE!
11 BETON KOLOM 25 x 25 CM ad, 1:2:3, 139 kg M3 0,63 5,334,629 #VALUE!
136,267,430
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 4,50 70,251 316,130
5 PASANG KUNCI TANAM 2 SLAAG BH 3,00 215,125 645,375
961,505
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 2,00 284,150 568,300
2 PASANG LAMPU PHILIPS 18 WATT BH 2,00 57,150 114,300
4 PASANG PANEL MCB BH 1,00 243,150 243,150
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 48,300
7 PASANG STOP KONTAK BH 2,00 25,650 51,300
1,025,350
IX PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 2" M' 200,00 51,242 10,248,300
2 PASANG PIPA AIR BERSIH 3/4" M' 40,00 21,546 861,840
3 PASANG KRANK AIR 3/4" BH 2,00 22,325 44,650
11,154,790
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 190,00 87,666 16,656,540
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 -
16,656,540
XI PEKERJAAN SUMUR
1 GALIAN TANAH SUMUR M' 40,00 500,000 20,000,000
2 BETON BUIS T= 15 CM, ad, 1:2:3, 60 kg M3 37,72 4,105,838 154,872,209
3 MESIN POMPA CELUP UNIT 3,00 5,000,000 15,000,000
189,872,209
D PENGUMPUL BAK PENAMPUNG AIR BERSIH DAN SUMUR
I PEKERJAAN TANAH 712,389
II PEKERJAAN PASANGAN 9,978,005
III PEKERJAAN PLESTERAN 15,477,020
IV PEKERJAAN BESI 59,201,107
V PEKERJAAN LANTAI 7,933,091
VI PEKERJAAN BETON 136,267,430
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 961,505
VIII PEKERJAAN LISTRIK 1,025,350
IX PEKERJAAN SANITASI 11,154,790
X PEKERJAAN FINISHING 16,656,540
XI PEKERJAAN SUMUR 189,872,209
JIMLAH TOTAL PENGUMPUL D 449,239,435
E. PEMBANGUNAN BAK/TEMPAT SAMPAH
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 54,875 603,076
2 URUGAN TANAH KEMBALI M3 2,75 39,750 109,313
712,389
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 7,30 718,450 5,244,685
2 PASANGAN BATAKO ad, 1 : 4 M2 65,00 159,665 10,378,225
15,622,910
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 130,00 53,658 6,975,540
2 ACIAN DINDING M2 130,00 27,800 3,614,000
10,589,540
IV PEKERJAAN BESI
1 PASANG PINTU BESI KUSEN + DAUN PINTU + UPAH M' 9,20 700,000 6,440,000
6,440,000
V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 8,83 269,955 2,383,703
2 MENGURUG PASIR DIBAWAH LANTAI M3 2,42 285,950 691,999
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 6,06 936,375 5,674,433
8,750,134
VI PEKERJAAN BETON
1 BETON SLOOF 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 5,048,243 5,704,514
2 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,12 5,644,744 677,369
2 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 6,110,028 6,904,331
3 BETON KOLOM 15 x 15 CM ad, 1:2:3, 141 kg M3 0,61 5,362,828 3,271,325
16,557,539
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 12,00 70,251 843,012
2 PASANG KUNCI TANAM 2 SLAAG BH 2,00 215,125 430,250
1,273,262
VIII PEKERJAAN SANITASI
1 PASANG PIPA AIR BERSIH 3/4" M' 20,00 21,546 430,920
2 PASANG KRANK AIR 3/4" BH 2,00 22,325 44,650
475,570
IX PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 130,00 87,666 11,396,580
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2
11,396,580
E PENGUMPUL BAK / TEMPAT SAMPAH
I PEKERJAAN TANAH 712,389
II PEKERJAAN PASANGAN 15,622,910
III PEKERJAAN PLESTERAN 10,589,540
IV PEKERJAAN BESI 6,440,000
V PEKERJAAN LANTAI 8,750,134
VI PEKERJAAN BETON 16,557,539
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,273,262
VIII PEKERJAAN SANITASI 475,570
IX PEKERJAAN FINISHING 11,396,580
JIMLAH TOTAL PENGUMPUL E 71,817,924
F. PEMBANGUNAN BAK PENAMPUNG AIR KOTOR / IPAL
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 99,75 54,875 5,473,781
2 URUGAN TANAH KEMBALI M3 24,94 39,750 991,365
6,465,146
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 2,04 718,450 1,465,638
1,465,638
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 43,80 53,658 2,350,220
2 ACIAN DINDING M2 43,80 27,800 1,217,640
3,567,860
IV PEKERJAAN LANTAI
1 MENGURUG PASIR DIBAWAH LANTAI M3 2,40 269,955 647,892
2 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 1,20 936,375 1,123,650
1,771,542
V PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,40 3,560,079 #VALUE!
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,96 5,598,123 #VALUE!
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,52 6,110,028 #VALUE!
4 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 3,71 6,150,266 #VALUE!
5 BETON DINDING T= 12 CM ad, 1:2:3, 197 kg M3 8,64 6,353,245 #VALUE!
6 BETON KOLOM 20 x 20 CM ad, 1:2:3, 223 kg M3 0,78 6,518,987 #VALUE!
98,879,798
VI PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 4" M' 40,00 86,292 3,451,680
3,451,680
VII PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 43,80 87,666 3,839,771
3,839,771
F PENGUMPUL BAK PENAMPUNG AIR KOTOR / IPAL
I PEKERJAAN TANAH 6,465,146
II PEKERJAAN PASANGAN 1,465,638
III PEKERJAAN PLESTERAN 3,567,860
IV PEKERJAAN LANTAI 1,771,542
V PEKERJAAN BETON 98,879,798
VI PEKERJAAN SANITASI 3,451,680
VII PEKERJAAN FINISHING 3,839,771
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 1 UNIT ) 119,441,436
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 2 UNIT ) 238,882,871
G. PEMBANGUNAN PINTU GERBANG DAN POS SATPAM
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 15,87 54,875 870,866
2 URUGAN TANAH KEMBALI M3 3,97 39,750 157,808
1,028,674
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 12,22 718,450 8,779,459
2 PASANGAN BATAKO ad, 1 : 4 M2 44,00 159,665 7,025,260
15,804,719
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 77,40 53,658 4,153,129
2 ACIAN DINDING M2 77,40 27,800 2,151,720
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
8,773,117
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 0,29 8,984,700 2,605,563
2 PINTU PANEL KAYU KLAS I M2 1,47 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 4,54 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,90 139,951 #VALUE!
5 RANGKA PLAFOND KAYU KLAS II M2 19,00 92,185 #VALUE!
6 PLAFOND TRIPLEKS 3 MM M2 19,00 46,155 #VALUE!
7 LIST PLAFOND GYPSUM M' 5,04 81,920 #VALUE!
8 PINTU SORONG, BESI HOLLOW T= 1,5 MM M2 36,50 700,000 #VALUE!
34,438,187
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 2,91 269,955 785,569
2 MENGURUG PASIR DIBAWAH LANTAI M3 0,81 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 1,21 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 6,00 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 12,21 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 2,00 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 2 M M2 10,60 238,930 #VALUE!
7,469,667
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,00 4,081,760 4,081,760
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,75 5,598,123 #VALUE!
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,86 6,110,028 #VALUE!
4 BETON BALOK 10 x 12 CM ad, 1:2:3, 244 kg M3 0,05 6,857,301 #VALUE!
5 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 2,15 6,150,266 #VALUE!
6 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 0,67 4,345,530 #VALUE!
7 BETON CANOPI ad, 1:2:3, 77 kg M3 0,09 4,345,530 #VALUE!
8 BETON KOLOM 30 x 50 CM ad, 1:2:3, 97 kg M3 2,60 4,742,450 #VALUE!
9 BETON KOLOM 15 x 30 CM ad, 1:2:3, 165 kg M3 1,98 5,701,216 #VALUE!
10 BETON KOLOM 12 x 30 CM ad, 1:2:3, 202 kg M3 0,95 6,222,897 #VALUE!
59,934,042
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 1,50 70,251 105,377
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 12,00 39,298 471,570
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 12,00 19,698 236,370
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 12,00 29,351 352,212
5 PASANG KUNCI TANAM 2 SLAAG BH 1,00 215,125 215,125
1,380,654
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 6,00 284,150 #VALUE!
2 PASANG LAMPU PHILIPS 18 WATT BH 6,00 57,150 #VALUE!
3 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
4 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
5 PASANG SAKLAR GANDA BH 2,00 26,150 #VALUE!
6 PASANG STOP KONTAK BH 4,00 25,650 #VALUE!
2,494,150
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 8,00 86,292 690,336
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 20,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 1,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 1,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 1,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 1,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
11,406,683
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 96,40 87,666 8,451,002
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 16,52 48,408 799,692
9,250,694
XI PEKERJAAN HURUF
1 PASANG HURUF BAHAN STAINLESS BH 30,00 300,000 9,000,000
9,000,000
G PENGUMPUL PINTU MASUK DAN POS SATPAM
I PEKERJAAN TANAH 1,028,674
II PEKERJAAN PASANGAN 15,804,719
III PEKERJAAN PLESTERAN 8,773,117
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 34,438,187
V PEKERJAAN LANTAI DAN KERAMIK 7,469,667
VI PEKERJAAN BETON 59,934,042
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,380,654
VIII PEKERJAAN LISTRIK 2,494,150
IX PEKERJAAN SANITASI 11,406,683
X PEKERJAAN FINISHING 9,250,694
XI PEKERJAAN HURUF 9,000,000
JIMLAH TOTAL PENGUMPUL G 160,980,586
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

A. PEKERJAAN PERSIAPAN
1 MOBILISASI & DEMOBILISASI LS 1,00 5,000,000 5,000,000
2 PEMBERSIHAN AWAL & AKHIR M2 400,00 11,750 #VALUE!
3 KANTOR DIREKSI KEET M2 10,00 1,293,615 #VALUE!
4 GUDANG KERJA M2 10,00 1,099,970 #VALUE!
5 PENGUKURAN PEMASANGAN PAPAN BOUWPLANK M' 120,00 70,270 #VALUE!
6 PAPAN NAMA PROYEK LS 1,00 1,000,000 #VALUE!
7 PENGADAAN AIR KERJA LS 1,00 3,000,000 #VALUE!
8 ADMINISTRASI, DOKUMENTASI, & P3 - K LS 1,00 5,000,000 #VALUE!
16,475,605 51,068,250
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

B. PEMBANGUNAN KANTOR PENGELOLA


I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 54,875 762,763
2 URUGAN TANAH KEMBALI M3 3,47 39,750 137,933
900,695
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 718,450 11,222,189
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 159,665 26,185,060
37,407,249
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 53,658 16,462,274
2 ACIAN DINDING M2 306,80 27,800 8,529,040
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 8,984,700 10,601,946
2 PINTU PANEL KAYU KLAS I M2 3,36 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,76 139,951 #VALUE!
5 KUDA-KUDA BAJA RINGAN M2 124,00 197,920 #VALUE!
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 226,360 #VALUE!
7 PAS, NOK SPANDEK M' 43,38 124,160 #VALUE!
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000 #VALUE!
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 92,185 #VALUE!
10 PLAFOND TRIPLEKS 3 MM M2 140,00 46,155 #VALUE!
11 LIST PLAFOND GYPSUM M' 253,79 81,920 #VALUE!
124,165,086
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 32,55 269,955 8,787,035
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 66,39 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 3,77 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 238,930 #VALUE!
37,495,333
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 3,560,079 712,016
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 5,598,123 #VALUE!
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 5,306,356 #VALUE!
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 5,644,744 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 6,110,028 #VALUE!
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 4,345,530 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 4,994,107 #VALUE!
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 4,345,530 #VALUE!
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 4,939,843 #VALUE!
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 6,293,395 #VALUE!
84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 9,00 70,251 632,259
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 39,298 4,479,915
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 19,698 2,245,515
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 29,351 3,346,014
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 215,125 1,075,625
11,779,328
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 20,00 284,150 #VALUE!
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 57,150 #VALUE!
3 PASANG LAMPU DOWN LIGTH BH 16,00 157,150 #VALUE!
4 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
6 PASANG SAKLAR GANDA BH 7,00 26,150 #VALUE!
7 PASANG STOP KONTAK BH 6,00 25,650 #VALUE!
9,054,400
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 86,292 #VALUE!
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 2,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 2,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 2,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 2,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000 #VALUE!
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000 #VALUE!
44,139,186
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 87,666 39,169,169
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 48,408 4,176,115
43,345,284
B PENGUMPUL KANTOR PENGELOLA
I PEKERJAAN TANAH 900,695
II PEKERJAAN PASANGAN 37,407,249
III PEKERJAAN PLESTERAN 27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 124,165,086
V PEKERJAAN LANTAI DAN KERAMIK 37,495,333
VI PEKERJAAN BETON 84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 11,779,328
VIII PEKERJAAN LISTRIK 9,054,400
IX PEKERJAAN SANITASI 44,139,186
X PEKERJAAN FINISHING 43,345,284
JIMLAH TOTAL PENGUMPUL B 420,526,404
C. PEMBANGUNAN KANTOR UPT
I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 13,90 54,875 762,763
2 URUGAN TANAH KEMBALI M3 3,47 39,750 137,933
900,695
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 15,62 718,450 11,222,189
2 PASANGAN BATAKO ad, 1 : 4 M2 164,00 159,665 26,185,060
37,407,249
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 306,80 53,658 16,462,274
2 ACIAN DINDING M2 306,80 27,800 8,529,040
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 1,18 8,984,700 10,601,946
2 PINTU PANEL KAYU KLAS I M2 3,36 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 23,50 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,76 139,951 #VALUE!
5 KUDA-KUDA BAJA RINGAN M2 124,00 197,920 #VALUE!
6 ATAP BAHAN SPANDEK 0.40 M2 124,00 226,360 #VALUE!
7 PAS, NOK SPANDEK M' 43,38 124,160 #VALUE!
8 LISPLANK BAHAN FIBER 2/40 M' 48,00 30,000 #VALUE!
9 RANGKA PLAFOND KAYU KLAS II M2 140,00 92,185 #VALUE!
10 PLAFOND TRIPLEKS 3 MM M2 140,00 46,155 #VALUE!
11 LIST PLAFOND GYPSUM M' 253,79 81,920 20,790,477
124,165,086
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 36,44 269,955 9,837,160
2 MENGURUG PASIR DIBAWAH LANTAI M3 4,33 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 6,49 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 66,39 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 50,44 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 3,77 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 1,5 M M2 21,20 238,930 #VALUE!
38,545,458
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,20 3,560,079 712,016
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 2,06 5,598,123 #VALUE!
3 BETON BALOK 12 x 20 CM ad, 1:2:3, 134 kg M3 1,20 5,306,356 #VALUE!
4 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,86 5,644,744 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 3,28 6,110,028 #VALUE!
6 BETON CANOPI ad, 1:2:3, 77 kg M3 0,07 4,345,530 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 4,29 4,994,107 #VALUE!
8 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 2,20 4,345,530 #VALUE!
9 BETON KOLOM 30 x 30 CM ad, 1:2:3, 111 kg M3 0,90 4,939,843 #VALUE!
10 BETON KOLOM 12 x 12 CM ad, 1:2:3, 207 kg M3 0,88 6,293,395 #VALUE!
84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 9,00 70,251 632,259
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 114,00 39,298 4,479,915
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 114,00 19,698 2,245,515
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 114,00 29,351 3,346,014
5 PASANG KUNCI TANAM 2 SLAAG BH 5,00 215,125 1,075,625
11,779,328
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 20,00 284,150 5,683,000
2 PASANG LAMPU PHILIPS 18 WATT BH 4,00 57,150 #VALUE!
3 PASANG LAMPU DOWN LIGTH BH 16,00 157,150 #VALUE!
4 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
6 PASANG SAKLAR GANDA BH 7,00 26,150 #VALUE!
7 PASANG STOP KONTAK BH 6,00 25,650 #VALUE!
9,054,400
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 12,00 86,292 1,035,504
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 60,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 2,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 2,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 2,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 2,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
9 SALURAN / GOT KELILING BANGUNAN M' 41,00 400,000 #VALUE!
10 GRIIL PENUTUP SALURAN / GOT DALAM BANGUNAN BAHAN STAINLESS M' 41,00 250,000 #VALUE!
44,139,186
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 446,80 87,666 39,169,169
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 86,27 48,408 4,176,115
43,345,284
C PENGUMPUL KANTOR UPT
I PEKERJAAN TANAH 900,695
II PEKERJAAN PASANGAN 37,407,249
III PEKERJAAN PLESTERAN 27,459,582
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 124,165,086
V PEKERJAAN LANTAI DAN KERAMIK 38,545,458
VI PEKERJAAN BETON 84,780,261
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 11,779,328
VIII PEKERJAAN LISTRIK 9,054,400
IX PEKERJAAN SANITASI 44,139,186
X PEKERJAAN FINISHING 43,345,284
JIMLAH TOTAL PENGUMPUL C 421,576,529
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

D. PEMBANGUNAN BAK PENAMPUNG AIR BERSIH DAN SUMUR


I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 54,875 603,076
2 URUGAN TANAH KEMBALI M3 2,75 39,750 109,313
712,389
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 6,11 718,450 4,389,730
2 PASANGAN BATAKO ad, 1 : 4 M2 35,00 159,665 5,588,275
9,978,005
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 190,00 53,658 10,195,020
2 ACIAN DINDING M2 190,00 27,800 5,282,000
15,477,020
IV PEKERJAAN BESI
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M2 5,81 8,984,700 52,201,107
2 PASANG TANGGA BESI UNIT 2,00 3,500,000 7,000,000
59,201,107
V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 15,84 269,955 4,276,087
2 MENGURUG PASIR DIBAWAH LANTAI M3 1,95 285,950 557,603
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 3,31 936,375 3,099,401
7,933,091
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,50 4,081,760 6,122,640
2 BETON SLOOF 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 4,582,959 #VALUE!
3 BETON SLOOF 15 x 40 CM ad, 1:2:3, 178 kg M3 0,37 4,864,949 #VALUE!
4 BETON BALOK 20 x 40 CM ad, 1:2:3, 177 kg M3 0,67 5,912,635 #VALUE!
5 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,54 6,110,028 #VALUE!
6 BETON BALOK 25 x 40 CM ad, 1:2:3, 158 kg M3 1,68 5,644,744 #VALUE!
7 BETON PLAT LANTAI T. 10 CM ad, 1:2:3, 123 kg M3 0,94 4,994,107 #VALUE!
8 BETON PLAT LANTAI T. 20 CM ad, 1:2:3, 123 kg M3 2,62 4,994,107 #VALUE!
9 BETON DINDING T= 20 CM ad, 1:2:3, 119 kg M3 12,00 5,253,484 #VALUE!
10 BETON KOLOM 30 x 30 CM ad, 1:2:3, 172 kg M3 3,40 5,799,912 #VALUE!
11 BETON KOLOM 25 x 25 CM ad, 1:2:3, 139 kg M3 0,63 5,334,629 #VALUE!
136,267,430
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 4,50 70,251 316,130
5 PASANG KUNCI TANAM 2 SLAAG BH 3,00 215,125 645,375
961,505
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 2,00 284,150 568,300
2 PASANG LAMPU PHILIPS 18 WATT BH 2,00 57,150 114,300
4 PASANG PANEL MCB BH 1,00 243,150 243,150
5 PASANG SAKLAR TUNGGAL BH 2,00 24,150 48,300
7 PASANG STOP KONTAK BH 2,00 25,650 51,300
1,025,350
IX PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 2" M' 200,00 51,242 10,248,300
2 PASANG PIPA AIR BERSIH 3/4" M' 40,00 21,546 861,840
3 PASANG KRANK AIR 3/4" BH 2,00 22,325 44,650
11,154,790
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 190,00 87,666 16,656,540
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 -
16,656,540
XI PEKERJAAN SUMUR
1 GALIAN TANAH SUMUR M' 40,00 500,000 20,000,000
2 BETON BUIS T= 15 CM, ad, 1:2:3, 60 kg M3 37,72 4,105,838 154,872,209
3 MESIN POMPA CELUP UNIT 3,00 5,000,000 15,000,000
189,872,209
D PENGUMPUL BAK PENAMPUNG AIR BERSIH DAN SUMUR
I PEKERJAAN TANAH 712,389
II PEKERJAAN PASANGAN 9,978,005
III PEKERJAAN PLESTERAN 15,477,020
IV PEKERJAAN BESI 59,201,107
V PEKERJAAN LANTAI 7,933,091
VI PEKERJAAN BETON 136,267,430
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 961,505
VIII PEKERJAAN LISTRIK 1,025,350
IX PEKERJAAN SANITASI 11,154,790
X PEKERJAAN FINISHING 16,656,540
XI PEKERJAAN SUMUR 189,872,209
JIMLAH TOTAL PENGUMPUL D 449,239,435
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

E. PEMBANGUNAN BAK/TEMPAT SAMPAH


I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 10,99 54,875 603,076
2 URUGAN TANAH KEMBALI M3 2,75 39,750 109,313
712,389
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 7,30 718,450 5,244,685
2 PASANGAN BATAKO ad, 1 : 4 M2 65,00 159,665 10,378,225
15,622,910
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 130,00 53,658 6,975,540
2 ACIAN DINDING M2 130,00 27,800 3,614,000
10,589,540
IV PEKERJAAN BESI
1 PASANG PINTU BESI KUSEN + DAUN PINTU + UPAH M' 9,20 700,000 6,440,000
6,440,000
V PEKERJAAN LANTAI
1 MENGURUG TANAH DIBAWAH LANTAI M3 8,83 269,955 2,383,703
2 MENGURUG PASIR DIBAWAH LANTAI M3 2,42 285,950 691,999
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 6,06 936,375 5,674,433
8,750,134
VI PEKERJAAN BETON
1 BETON SLOOF 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 5,048,243 5,704,514
2 BETON BALOK 10 x 20 CM ad, 1:2:3, 158 kg M3 0,12 5,644,744 677,369
2 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,13 6,110,028 6,904,331
3 BETON KOLOM 15 x 15 CM ad, 1:2:3, 141 kg M3 0,61 5,362,828 3,271,325
16,557,539
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 12,00 70,251 843,012
2 PASANG KUNCI TANAM 2 SLAAG BH 2,00 215,125 430,250
1,273,262
VIII PEKERJAAN SANITASI
1 PASANG PIPA AIR BERSIH 3/4" M' 20,00 21,546 430,920
2 PASANG KRANK AIR 3/4" BH 2,00 22,325 44,650
475,570
IX PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 130,00 87,666 11,396,580
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2
11,396,580
E PENGUMPUL BAK / TEMPAT SAMPAH
I PEKERJAAN TANAH 712,389
II PEKERJAAN PASANGAN 15,622,910
III PEKERJAAN PLESTERAN 10,589,540
IV PEKERJAAN BESI 6,440,000
V PEKERJAAN LANTAI 8,750,134
VI PEKERJAAN BETON 16,557,539
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,273,262
VIII PEKERJAAN SANITASI 475,570
IX PEKERJAAN FINISHING 11,396,580
JIMLAH TOTAL PENGUMPUL E 71,817,924
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

F. PEMBANGUNAN BAK PENAMPUNG AIR KOTOR / IPAL


I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 99,75 54,875 5,473,781
2 URUGAN TANAH KEMBALI M3 24,94 39,750 991,365
6,465,146
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 2,04 718,450 1,465,638
1,465,638
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 43,80 53,658 2,350,220
2 ACIAN DINDING M2 43,80 27,800 1,217,640
3,567,860
IV PEKERJAAN LANTAI
1 MENGURUG PASIR DIBAWAH LANTAI M3 2,40 269,955 647,892
2 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 10 CM M3 1,20 936,375 1,123,650
1,771,542
V PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 89 kg M3 0,40 3,560,079 #VALUE!
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,96 5,598,123 #VALUE!
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 1,52 6,110,028 #VALUE!
4 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 3,71 6,150,266 #VALUE!
5 BETON DINDING T= 12 CM ad, 1:2:3, 197 kg M3 8,64 6,353,245 #VALUE!
6 BETON KOLOM 20 x 20 CM ad, 1:2:3, 223 kg M3 0,78 6,518,987 #VALUE!
98,879,798
VI PEKERJAAN SANITASI
1 PASANG PIPA AIR KOTOR PVC 4" M' 40,00 86,292 3,451,680
3,451,680
VII PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 43,80 87,666 3,839,771
3,839,771
F PENGUMPUL BAK PENAMPUNG AIR KOTOR / IPAL
I PEKERJAAN TANAH 6,465,146
II PEKERJAAN PASANGAN 1,465,638
III PEKERJAAN PLESTERAN 3,567,860
IV PEKERJAAN LANTAI 1,771,542
V PEKERJAAN BETON 98,879,798
VI PEKERJAAN SANITASI 3,451,680
VII PEKERJAAN FINISHING 3,839,771
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 1 UNIT ) 119,441,436
JIMLAH TOTAL PENGUMPUL F, ( UNTUK 2 UNIT ) 238,882,871
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE ( E E )

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PENDUKUNG SIKIM KOTA TUAL


LOKASI : KECAMATAN DULLAH SELATAN KOTA TUAL
TAHUN ANGGARAN : 2017
VOLUME : 1 PAKET

ANALISA HARGA JUMLAH HARGA


NO. ITEM PEKERJAAN SATUAN VOLUME SATUAN (Rp) (Rp)

G. PEMBANGUNAN PINTU GERBANG DAN POS SATPAM


I PEKERJAAN TANAH
1 GALIAN TANAH PONDASI M3 15,87 54,875 870,866
2 URUGAN TANAH KEMBALI M3 3,97 39,750 157,808
1,028,674
II PEKERJAAN PASANGAN
1 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 12,22 718,450 8,779,459
2 PASANGAN BATAKO ad, 1 : 4 M2 44,00 159,665 7,025,260
15,804,719
III PEKERJAAN PLESTERAN
1 PLESTERAN TEMBOK ad, 1 : 4 M2 77,40 53,658 4,153,129
2 ACIAN DINDING M2 77,40 27,800 2,151,720
3 PLESTERAN DINDING MOTIF BH 46,00 53,658 2,468,268
8,773,117
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND
1 PAS. KUSEN PINTU DAN VENTILASI KAYU KLAS I 6/12 M3 0,29 8,984,700 2,605,563
2 PINTU PANEL KAYU KLAS I M2 1,47 532,750 #VALUE!
3 PINTU, JENDELA / VENTILASI KACA KAYU KLAS I M2 4,54 513,700 #VALUE!
4 PASANG KACA MATI T = 5 MM M2 0,90 139,951 #VALUE!
5 RANGKA PLAFOND KAYU KLAS II M2 19,00 92,185 #VALUE!
6 PLAFOND TRIPLEKS 3 MM M2 19,00 46,155 #VALUE!
7 LIST PLAFOND GYPSUM M' 5,04 81,920 #VALUE!
8 PINTU SORONG, BESI HOLLOW T= 1,5 MM M2 36,50 700,000 #VALUE!
34,438,187
V PEKERJAAN LANTAI DAN KERAMIK
1 MENGURUG TANAH DIBAWAH LANTAI M3 2,91 269,955 785,569
2 MENGURUG PASIR DIBAWAH LANTAI M3 0,81 285,950 #VALUE!
3 LANTAI RABAT BETON ad, 1 : 3 : 6 T = 6 CM M3 1,21 936,375 #VALUE!
4 LANTAI KERAMIK 40/40 CM M2 6,00 134,231 #VALUE!
5 LANTAI KERAMIK 40/40 CM, UNTUK TERAS DAN RABAT M2 12,21 134,231 #VALUE!
6 LANTAI KERAMIK 20/20 CM M2 2,00 171,230 #VALUE!
7 DINDING KERAMIK 20/20 CM T = 2 M M2 10,60 238,930 #VALUE!
7,469,667
VI PEKERJAAN BETON
1 BETON FOOT PLAT ad, 1:2:3, 126 kg M3 1,00 4,081,760 4,081,760
2 BETON SLOOF 15 x 20 CM ad, 1:2:3, 230 kg M3 0,75 5,598,123 #VALUE!
3 BETON BALOK 15 x 25 CM ad, 1:2:3, 191 kg M3 0,86 6,110,028 #VALUE!
4 BETON BALOK 10 x 12 CM ad, 1:2:3, 244 kg M3 0,05 6,857,301 #VALUE!
5 BETON PLAT LANTAI T. 12 CM ad, 1:2:3, 205 kg M3 2,15 6,150,266 #VALUE!
6 BETON LISPLANK T. 8 CM ad, 1:2:3, 77 kg M3 0,67 4,345,530 #VALUE!
7 BETON CANOPI ad, 1:2:3, 77 kg M3 0,09 4,345,530 #VALUE!
8 BETON KOLOM 30 x 50 CM ad, 1:2:3, 97 kg M3 2,60 4,742,450 #VALUE!
9 BETON KOLOM 15 x 30 CM ad, 1:2:3, 165 kg M3 1,98 5,701,216 #VALUE!
10 BETON KOLOM 12 x 30 CM ad, 1:2:3, 202 kg M3 0,95 6,222,897 #VALUE!
59,934,042
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 PASANG ENGSEL PINTU PSG 1,50 70,251 105,377
2 PASANG ENGSEL JENDELA DAN VENTILASI PSG 12,00 39,298 471,570
3 PASANG GRENDEL JENDELA DAN VENTILASI BH 12,00 19,698 236,370
4 PASANG KAIT ANGIN JENDELA DAN VENTILASI BH 12,00 29,351 352,212
5 PASANG KUNCI TANAM 2 SLAAG BH 1,00 215,125 215,125
1,380,654
VIII PEKERJAAN LISTRIK
1 PASANG TITIK INSTALASI TTK 6,00 284,150 #VALUE!
2 PASANG LAMPU PHILIPS 18 WATT BH 6,00 57,150 #VALUE!
3 PASANG PANEL MCB BH 1,00 243,150 #VALUE!
4 PASANG SAKLAR TUNGGAL BH 2,00 24,150 #VALUE!
5 PASANG SAKLAR GANDA BH 2,00 26,150 #VALUE!
6 PASANG STOP KONTAK BH 4,00 25,650 #VALUE!
2,494,150
IX PEKERJAAN SANITASI
1 PASANG PIPA TINJA PVC 4" M' 8,00 86,292 690,336
2 PASANG PIPA AIR KOTOR PVC 2" M' 8,00 51,242 #VALUE!
3 PASANG PIPA AIR BERSIH 3/4" M' 20,00 21,546 #VALUE!
4 PASANG KRANK AIR 3/4" BH 1,00 22,325 #VALUE!
5 PASANG KLOSET DUDUK BH 1,00 3,609,295 #VALUE!
6 PASANG WASTAFEL + CERMIN BH 1,00 1,158,750 #VALUE!
7 PASANG FLOOR DRAIN BH 1,00 85,125 #VALUE!
8 SEPTICTANK UNIT 1,00 5,000,000 #VALUE!
11,406,683
X PEKERJAAN FINISHING
1 PENGECATAN BIDANG-BIDANG TEMBOKDAN PLAFOND DENGAN DELUXE M2 96,40 87,666 8,451,002
2 PENGECATAN BIDANG KAYU DENGAN CAT KAYU M2 16,52 48,408 799,692
9,250,694
XI PEKERJAAN HURUF
1 PASANG HURUF BAHAN STAINLESS BH 30,00 300,000 9,000,000
9,000,000
G PENGUMPUL PINTU MASUK DAN POS SATPAM
I PEKERJAAN TANAH 1,028,674
II PEKERJAAN PASANGAN 15,804,719
III PEKERJAAN PLESTERAN 8,773,117
IV PEKERJAAN ALLUMUNIUM , KAYU , ATAP DAN PLAFOND 34,438,187
V PEKERJAAN LANTAI DAN KERAMIK 7,469,667
VI PEKERJAAN BETON 59,934,042
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,380,654
VIII PEKERJAAN LISTRIK 2,494,150
IX PEKERJAAN SANITASI 11,406,683
X PEKERJAAN FINISHING 9,250,694
XI PEKERJAAN HURUF 9,000,000
JIMLAH TOTAL PENGUMPUL G 160,980,586