Anda di halaman 1dari 135

BACK UP VOLUME GAZEBO

1 Pengukuran Pemasangan Bowplank

Lebar (m) Panjang (m) Banyaknya


Volume Keterangan SKETSA
a b Bh

3 4 2 14 m2

TOTAL 14 m2

2 Galian Pondasi

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a c b Bh
Pondasi Foot Plate
0.8 0.8 0.75 3 1.44 m3

Pondasi Menerus
1 10 0.75 7.5 m3

TOTAL 8.94 m3

3 Urug Kembali Bekas Galian

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

2.98 1/3 volume galian

TOTAL 2.98 m3

4 Urugan Pasir Bawah

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a c b Bh

0.8 10 0.1 0.8 m3

TOTAL 0.8 m3

5 Pasang Batu Kosong Aanstamping

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a c b Bh

0.8 10 0.2 1.6 m3

TOTAL 1.6 m3
6 Pasang Pondasi Poor Plate

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

7 Tulangan Utama

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.80 0.10 1.00 4.0 10 0.62 2.47 0.75
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -

7 Tulangan Beugel/Sengkang

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -
0.10 - 0.10 0.20 4.0 10 0.62 0.49 -

Bekisting

LEBAR (m) TINGGI (m) PANJANG (m) BANYAKNYA


VOLUME KET. SKETSA
a bh
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

7 Pasang Pondasi Menerus

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

8 Pasang Sloof 20x20 cm

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh
7 Tulangan Utama

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

Bekisting

LEBAR (m) TINGGI (m) PANJANG (m) BANYAKNYA


VOLUME KET. SKETSA
a bh
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

7 Tulangan Beugel/Sengkang

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

9 Pasang Kolom 20x20 cm

Lebar (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a c Bh

7 Tulangan Utama

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
7 Tulangan Beugel/Sengkang

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

Bekisting

LEBAR (m) TINGGI (m) PANJANG (m) BANYAKNYA


VOLUME KET. SKETSA
a bh
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

10 Pasang Ringbalk 20x20 cm

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

7 Tulangan Utama

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

7 Tulangan Beugel/Sengkang

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

Bekisting
LEBAR (m) TINGGI (m) PANJANG (m) BANYAKNYA
VOLUME KET. SKETSA
a bh
-
-
-
-
-
-
-

11 Pasang Plat Beton 12mm

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

7 Tulangan Utama

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

7 Tulangan Beugel/Sengkang

PANJANG
a b c d e n Ø berat/m' BERAT JML.
TOTAL
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -
0.10 0.10 0.20 4.0 10 0.62 0.49 -

Bekisting

LEBAR (m) TINGGI (m) PANJANG (m) BANYAKNYA


VOLUME KET. SKETSA
a bh
-
-
-
-
-
-
-

13 Pasang Bata

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
Volume Keterangan SKETSA
a b c Bh

13 Plesteran

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

13 Acian

Lebar (m) Panjang (m) Tinggi (m) Banyaknya


Volume Keterangan SKETSA
a b c Bh

Bekisting

LEBAR (m) TINGGI (m) PANJANG (m) BANYAKNYA


VOLUME KET. SKETSA
a bh
#VALUE! e PANJANG TOTAL #VALUE! -
0.20 - 0.20 - -
0.20 - 0.20 - -
0.20 - 0.20 - -
0.20 - 0.20 - -
0.20 - 0.20 - -
0.20 - 0.20 - -
AZEBO

SKETSA

SKETSA

SKETSA

SKETSA
SKETSA

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
1.85 #REF!
- #REF!
- #REF!
- #REF!

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

SKETSA

SKETSA

SKETSA
BERAT TOTAL KET. DESKRIPSI
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

SKETSA

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
BERAT TOTAL KET. DESKRIPSI
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

SKETSA

SKETSA

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
SKETSA

SKETSA

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

BERAT TOTAL KET. DESKRIPSI


- #REF!
- #REF!
- #REF!
- #REF!
- #REF!
- #REF!

SKETSA

SKETSA
SKETSA

SKETSA

SKETSA

SKETSA
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

SATUAN KERJA :
PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
TAHUN ANGGARAN :

I. AHSP - A.2.2.1 ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.1 AHSP - A.2.2.1


JENIS PEKERJAAN : Pembuatan Pagar Sementara dari Kayu Tinggi 2 Meter
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.400 81,000.00 32,400.00
Tukang Kayu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.020 105,000.00 2,100.00
JUMLAH TENAGA KERJA 61,769.00
B. BAHAN :
Dolken Kayu Ø 8-10/400 cm - Batang 1.250 8,000.00 10,000.00
Semen Portland - Kg 5.000 1,631.12 8,155.60
Pasir Beton - M3 0.005 267,000.00 1,335.00
Koral Beton - M3 0.009 267,000.00 2,403.00
Kayu 5/7 Kelas III/ Daerah - M3 0.072 1,573,000.00 113,256.00
Paku Biasa 2" - 5" - Kg 0.060 23,400.00 1,404.00
Residu - Liter 0.400 15,625.00 6,250.00
JUMLAH HARGA BAHAN 142,803.60
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 204,572.60
E. Overhead & Profit 10% x D 20,457.26
F. Harga Satuan Pekerjaan(D + E) 225,029.86

Halaman-24
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.2 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Pagar Sementara dari Seng Gelombang Tinggi 2 Meter
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 81,000.00 16,200.00
Tukang Kayu L.02 Org/Hari 0.400 122,000.00 48,800.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.020 105,000.00 2,100.00
JUMLAH TENAGA KERJA 69,969.00
B. BAHAN :
Dolken Kayu Ø 8-10/400 cm - Batang 1.250 8,000.00 10,000.00
Semen Portland - Kg 2.500 1,631.12 4,077.80
Seng Gelombang - Lbr 1.200 48,750.00 58,500.00
Pasir Beton - M3 0.005 267,000.00 1,335.00
Koral Beton - M3 0.009 267,000.00 2,403.00
Kayu 5/7 Kelas III/ Daerah - M3 0.072 1,573,000.00 113,256.00
Paku Biasa 2" - 5" - Kg 0.060 23,400.00 1,404.00
Cat Meny Besi - Liter 0.450 28,000.00 12,600.00
JUMLAH HARGA BAHAN 203,575.80
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 273,544.80
E. Overhead & Profit 10% x D 27,354.48
F. Harga Satuan Pekerjaan(D + E) 300,899.28

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.3 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pagar Sementara dari Kawat Duri Tinggi 1,8 Meter
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 81,000.00 16,200.00
Tukang Kayu L.02 Org/Hari 0.300 122,000.00 36,600.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.020 105,000.00 2,100.00
JUMLAH TENAGA KERJA 57,769.00
B. BAHAN :
Dolken Kayu Ø 8-10/400 cm - Batang 1.000 8,000.00 8,000.00
Semen Portland - Kg 2.000 1,631.12 3,262.24
Kawat Duri - M1 25.000 1,648.00 41,200.00
Pasir Beton - M3 0.005 267,000.00 1,335.00
Koral Beton - M3 0.009 267,000.00 2,403.00
Paku Biasa 2" - 5" - Kg 0.060 23,400.00 1,404.00
JUMLAH HARGA BAHAN 57,604.24
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 115,373.24
E. Overhead & Profit 10% x D 11,537.32
F. Harga Satuan Pekerjaan(D + E) 126,910.56

Halaman-25
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.4 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pengukuran dan Pemasangan Bouwplank
SATUAN PEMBAYARAN : 1 M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.100 81,000.00 8,100.00
Tukang Kayu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 22,259.50
B. BAHAN :
Kayu 5/7 Kelas III/ Daerah - M3 0.012 1,573,000.00 18,876.00
Paku Biasa 2" - 3" - Kg 0.020 23,400.00 468.00
Kayu Papan 2/30 - M1 0.007 1,648.00 11.54
JUMLAH HARGA BAHAN 19,355.54
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 41,615.04
E. Overhead & Profit 10% x D 4,161.50
F. Harga Satuan Pekerjaan(D + E) 45,776.54

Halaman-26
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.6 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Rumah Jaga (Konstruksi Kayu)
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Tukang Kayu L.02 Org/Hari 1.500 122,000.00 183,000.00
Kepala Tukang L.03 Org/Hari 0.150 143,450.00 21,517.50
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 290,767.50
B. BAHAN :
Dolken Kayu Ø 8-10/400 cm - Batang 3.0000 8,000.00 24,000.00
Kayu Kelas III - M3 0.276 1,573,000.00 434,148.00
Paku Biasa 2" - 5" - Kg 0.700 23,400.00 16,380.00
Seng Gelombang - Kg 1.500 48,750.00 73,125.00
JUMLAH HARGA BAHAN 547,653.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 838,420.50
E. Overhead & Profit 10% x D 83,842.05
F. Harga Satuan Pekerjaan(D + E) 922,262.55

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.7 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Gudang Semen dan Peralatan
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Tukang Kayu L.02 Org/Hari 2.000 122,000.00 244,000.00
Kepala Tukang L.03 Org/Hari 0.200 143,450.00 28,690.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 358,940.00
B. BAHAN :
Dolken Kayu Ø 8-10/400 cm - Batang 1.7000 8,000.00 13,600.00
Kayu Kelas III - M3 0.210 1,573,000.00 330,330.00
Paku Biasa 2" - 5" - Kg 0.300 23,400.00 7,020.00
Seng Gelombang - Kg 1.500 48,750.00 73,125.00
Semen Portland - Kg 10.500 1,631.12 17,126.76
Pasir Beton - M3 0.030 267,000.00 8,010.00
Koral Beton - M3 0.050 267,000.00 13,350.00
Seng Gelombang - Lbr 1.500 48,750.00 73,125.00
Seng Plat - Lbr 0.250 15,000.00 3,750.00
JUMLAH HARGA BAHAN 539,436.76
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 898,376.76
E. Overhead & Profit 10% x D 89,837.68
F. Harga Satuan Pekerjaan(D + E) 988,214.44

Halaman-27
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.8 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Bedeng Pekerja
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Tukang Kayu L.02 Org/Hari 2.000 122,000.00 244,000.00
Kepala Tukang L.03 Org/Hari 0.200 143,450.00 28,690.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 358,940.00
B. BAHAN :
Dolken Kayu Ø 8-10/400 cm - Batang 1.2500 8,000.00 10,000.00
Kayu Kelas III - M3 0.186 1,573,000.00 292,578.00
Paku Biasa 2" - 5" - Kg 0.300 23,400.00 7,020.00
Semen Portland - Kg 18.000 1,631.12 29,360.16
Pasir Beton - M3 0.030 267,000.00 8,010.00
Koral Beton - M3 0.050 267,000.00 13,350.00
Seng Gelombang - Lbr 1.500 48,750.00 73,125.00
Plywood Tebal 4 mm - Lbr 1.350 89,250.00 120,487.50
JUMLAH HARGA BAHAN 553,930.66
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 912,870.66
E. Overhead & Profit 10% x D 91,287.07
F. Harga Satuan Pekerjaan(D + E) 1,004,157.73

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.9 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembersihan Lapangan dan Perataan
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
A. TENAGA :
Pekerja L.01 Org/Hari 0.100 81,000.00 8,100.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 13,350.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 13,350.00
E. Overhead & Profit 10% x D 1,335.00
F. Harga Satuan Pekerjaan(D + E) 14,685.00

Halaman-28
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.10 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Stegger/ Perancah Dari Kayu Bulat
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Tukang Kayu L.02 Org/Hari 2.000 122,000.00 244,000.00
Kepala Tukang L.03 Org/Hari 0.200 143,450.00 28,690.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 358,940.00
B. BAHAN :
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 1.2500 8,000.00 10,000.00
Tali Ijuk - Kg 0.186 42,000.00 7,812.00
JUMLAH HARGA BAHAN 17,812.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 376,752.00
E. Overhead & Profit 10% x D 37,675.20
F. Harga Satuan Pekerjaan(D + E) 414,427.20

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.11 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Kotak Adukan 40 x 50 x 25 cm
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Tukang Kayu L.02 Org/Hari 0.300 122,000.00 36,600.00
Kepala Tukang L.03 Org/Hari 0.030 143,450.00 4,303.50
JUMLAH TENAGA KERJA 40,903.50
B. BAHAN :
Kayu Papan Kelas III/ Daerah - M3 0.036 1,573,000.00 56,628.00
Kayu 5/7 Kelas III/ Daerah - M3 0.014 1,573,000.00 22,022.00
Paku Biasa 2" - 5" - Kg 0.080 23,400.00 1,872.00
JUMLAH HARGA BAHAN 80,522.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 121,425.50
E. Overhead & Profit 10% x D 12,142.55
F. Harga Satuan Pekerjaan(D + E) 133,568.05

Halaman-29
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.12 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembuatan Jalan Sementara
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 86,250.00
B. BAHAN :
Batu Belah - M3 0.150 300,000.00 45,000.00
Batu Pecah - M3 0.090 300,000.00 27,000.00
Pasir Pasang - M3 0.010 267,000.00 2,670.00
JUMLAH HARGA BAHAN 74,670.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 160,920.00
E. Overhead & Profit 10% x D 16,092.00
F. Harga Satuan Pekerjaan(D + E) 177,012.00

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.13 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembongkaran Beton Bertulang
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 13.334 81,000.00 1,080,054.00
Mandor L.04 Org/Hari 0.666 105,000.00 69,930.00
JUMLAH TENAGA KERJA 1,149,984.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,149,984.00
E. Overhead & Profit 10% x D 114,998.40
F. Harga Satuan Pekerjaan(D + E) 1,264,982.40

Halaman-30
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.2.1.14 AHSP - A.2.2.1


KODE/ JENIS PEKERJAAN : Pembongkaran Dinding Tembok Bata
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.667 81,000.00 540,027.00
Mandor L.04 Org/Hari 0.333 105,000.00 34,965.00
JUMLAH TENAGA KERJA 574,992.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 574,992.00
E. Overhead & Profit 10% x D 57,499.20
F. Harga Satuan Pekerjaan(D + E) 632,491.20

Halaman-31
II. AHSP - A.2.3.1 ANALISA HARGA SATUAN PEKERJAAN TANAH

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.1 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Biasa Sedalam ≤ 1 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.563 81,000.00 45,603.00
Mandor L.04 Org/Hari 0.056 105,000.00 5,911.50
JUMLAH TENAGA KERJA 51,514.50
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 51,514.50
E. Overhead & Profit 10% x D 5,151.45
F. Harga Satuan Pekerjaan(D + E) 56,665.95

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.2 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Biasa Sedalam 2 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.675 81,000.00 54,675.00
Mandor L.04 Org/Hari 0.068 105,000.00 7,087.50
JUMLAH TENAGA KERJA 61,762.50
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 61,762.50
E. Overhead & Profit 10% x D 6,176.25
F. Harga Satuan Pekerjaan(D + E) 67,938.75

Halaman-32
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.3 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Biasa Sedalam 3 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.760 81,000.00 61,560.00
Mandor L.04 Org/Hari 0.076 105,000.00 7,980.00
JUMLAH TENAGA KERJA 69,540.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 69,540.00
E. Overhead & Profit 10% x D 6,954.00
F. Harga Satuan Pekerjaan(D + E) 76,494.00

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.3.4 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Biasa Sedalam > 3 Meter, untuk setiap penambahan kedalaman 1 m
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.075 81,000.00 6,075.00
Mandor L.04 Org/Hari 0.008 105,000.00 787.50
JUMLAH TENAGA KERJA 6,862.50
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 6,862.50
E. Overhead & Profit 10% x D 686.25
F. Harga Satuan Pekerjaan(D + E) 7,548.75

Halaman-33
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.4 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Keras Sedalam 1 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Mandor L.04 Org/Hari 0.032 105,000.00 3,360.00
JUMLAH TENAGA KERJA 84,360.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 84,360.00
E. Overhead & Profit 10% x D 8,436.00
F. Harga Satuan Pekerjaan(D + E) 92,796.00

Halaman-34
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.5 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Cadas Sedalam 1 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.250 81,000.00 101,250.00
Mandor L.04 Org/Hari 0.125 105,000.00 13,125.00
JUMLAH TENAGA KERJA 114,375.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 114,375.00
E. Overhead & Profit 10% x D 11,437.50
F. Harga Satuan Pekerjaan(D + E) 125,812.50

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.6 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Penggalian Tanah Lumpur Sedalam 1 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.830 81,000.00 67,230.00
Mandor L.04 Org/Hari 0.083 105,000.00 8,715.00
JUMLAH TENAGA KERJA 75,945.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 75,945.00
E. Overhead & Profit 10% x D 7,594.50
F. Harga Satuan Pekerjaan(D + E) 83,539.50

Halaman-35
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.7 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pengerjaan Stripping Tanah Tebing Setinggi 1 Meter
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.050 81,000.00 4,050.00
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 4,575.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,575.00
E. Overhead & Profit 10% x D 457.50
F. Harga Satuan Pekerjaan(D + E) 5,032.50

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.8 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pembuangan Tanah Sejauh 30 Meter
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.330 81,000.00 26,730.00
Mandor L.04 Org/Hari 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 27,780.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 27,780.00
E. Overhead & Profit 10% x D 2,778.00
F. Harga Satuan Pekerjaan(D + E) 30,558.00

Halaman-36
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.9 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pengurugan Kembali Galian Dihitung 1/3 Kali Dari Koefisien Galian
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
1. Penggalian 1 m3 Tanah Biasa Sedalam 1 Meter
0.333 56,665.95 18,888.65
2. Penggalian 1 m3 Tanah Biasa Sedalam 2 Meter
0.333 67,938.75 22,646.25
3. Penggalian 1 m3 Tanah Biasa Sedalam 3 Meter
0.333 76,494.00 25,498.00
4. Penggalian Tanah Keras Sedalam 1 Meter
0.333 92,796.00 30,932.00
5. Penggalian 1 m3 Tanah Cadas Sedalam 1 Meter
0.333 125,812.50 41,937.50
6. Penggalian 1 m3 Tanah Lumpur Sedalam 1 Meter
0.333 83,539.50 27,846.50

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : T.14.b1 T - 14


KODE/ JENIS PEKERJAAN : Pemadatan Tanah
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.500 81,000.00 40,500.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 45,750.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 45,750.00
E. Overhead & Profit 10% x D 4,575.00
F. Harga Satuan Pekerjaan(D + E) 50,325.00

Halaman-37
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : T.14.b T - 14


KODE/ JENIS PEKERJAAN : Pemadatan Tanah Menggunakan Alat (Per 20 cm)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.500 81,000.00 40,500.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 45,750.00
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
Pemadat Timbunan (Stamper) E.31 Sewa/ Perhari 0.050 Err:509 Err:509
JUMLAH HARGA ALAT Err:509
D. Jumlah (A+B+C) Err:509
E. Overhead & Profit 10% x D Err:509
F. Harga Satuan Pekerjaan(D + E) Err:509

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.11 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pengurugan Dengan Pasir Urug
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Mandor L.04 Org/Hari 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 25,350.00
B. BAHAN :
Pasir Urug - M3 1.200 183,150.00 219,780.00
JUMLAH HARGA BAHAN 219,780.00
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 245,130.00
E. Overhead & Profit 10% x D 24,513.00
F. Harga Satuan Pekerjaan(D + E) 269,643.00

Halaman-38
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.13 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pemasangan Lapisan Ijuk Tebal 10 cm Untuk Bidang Resapan
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.150 81,000.00 12,150.00
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 13,725.00
B. BAHAN :
Ijuk - M3 6.000 180,000.00 1,080,000.00
JUMLAH HARGA BAHAN 1,080,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,093,725.00
E. Overhead & Profit 10% x D 109,372.50
F. Harga Satuan Pekerjaan(D + E) 1,203,097.50

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.14 AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pengurugan Sirtu Padat
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.250 81,000.00 20,250.00
Mandor L.04 Org/Hari 0.025 105,000.00 2,625.00
JUMLAH TENAGA KERJA 22,875.00
B. BAHAN :
Sirtu - M3 1.200 233,300.00 279,960.00
JUMLAH HARGA BAHAN 279,960.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 302,835.00
E. Overhead & Profit 10% x D 30,283.50
F. Harga Satuan Pekerjaan(D + E) 333,118.50

Halaman-39
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.14.a AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pengurugan Tanah Timbunan
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.250 81,000.00 20,250.00
Mandor L.04 Org/Hari 0.025 105,000.00 2,625.00
JUMLAH TENAGA KERJA 22,875.00
B. BAHAN :
Tanah Timbunan - M3 1.200 120,000.00 144,000.00
JUMLAH HARGA BAHAN 144,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 166,875.00
E. Overhead & Profit 10% x D 16,687.50
F. Harga Satuan Pekerjaan(D + E) 183,562.50

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.2.3.1.14.b AHSP - A.2.3.1


KODE/ JENIS PEKERJAAN : Pengurugan Tanah Humus
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.250 81,000.00 20,250.00
Mandor L.04 Org/Hari 0.025 105,000.00 2,625.00
JUMLAH TENAGA KERJA 22,875.00
B. BAHAN :
Tanah Hitam - M3 1.200 200,000.00 240,000.00
JUMLAH HARGA BAHAN 240,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 262,875.00
E. Overhead & Profit 10% x D 26,287.50
F. Harga Satuan Pekerjaan(D + E) 289,162.50

Halaman-40
III. AHSP - A.3.2.1 ANALISA HARGA SATUAN PEKERJAAN PONDASI

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.3.2.1.1 AHSP - A.3.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Pondasi Batu Belah Campuran 1 SP : 3 PP
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.500 81,000.00 121,500.00
Tukang Batu L.02 Org/Hari 0.750 122,000.00 91,500.00
Kepala Tukang L.03 Org/Hari 0.075 143,450.00 10,758.75
Mandor L.04 Org/Hari 0.075 105,000.00 7,875.00
JUMLAH TENAGA KERJA 231,633.75
B. BAHAN :
Batu Kali/ Batu Gunung - M3 1.200 267,000.00 320,400.00
Semen Portland - Kg 202.000 1,631.12 329,486.24
Pasir Pasang - M3 0.485 267,000.00 129,495.00
JUMLAH HARGA BAHAN 779,381.24
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,011,014.99
E. Overhead & Profit 10% x D 101,101.50
F. Harga Satuan Pekerjaan(D + E) 1,112,116.49

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.3.2.1.2 AHSP - A.3.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Pondasi Batu Belah Campuran 1 SP : 4 PP
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.500 81,000.00 121,500.00
Tukang Batu L.02 Org/Hari 0.750 122,000.00 91,500.00
Kepala Tukang L.03 Org/Hari 0.075 143,450.00 10,758.75
Mandor L.04 Org/Hari 0.075 105,000.00 7,875.00
JUMLAH TENAGA KERJA 231,633.75
B. BAHAN :
Batu Kali/ Batu Gunung - M3 1.200 267,000.00 320,400.00
Semen Portland - Kg 163.000 1,631.12 265,872.56
Pasir Pasang - M3 0.520 267,000.00 138,840.00
JUMLAH HARGA BAHAN 725,112.56
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 956,746.31
E. Overhead & Profit 10% x D 95,674.63
F. Harga Satuan Pekerjaan(D + E) 1,052,420.94

Halaman-41
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.3.2.1.3 AHSP - A.3.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Pondasi Batu Belah Campuran 1 SP : 5 PP
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.500 81,000.00 121,500.00
Tukang Batu L.02 Org/Hari 0.750 122,000.00 91,500.00
Kepala Tukang L.03 Org/Hari 0.075 143,450.00 10,758.75
Mandor L.04 Org/Hari 0.075 105,000.00 7,875.00
JUMLAH TENAGA KERJA 231,633.75
B. BAHAN :
Batu Kali/ Batu Gunung - M3 1.200 267,000.00 320,400.00
Semen Portland - Kg 136.000 1,631.12 221,832.32
Pasir Pasang - M3 0.544 267,000.00 145,248.00
JUMLAH HARGA BAHAN 687,480.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 919,114.07
E. Overhead & Profit 10% x D 91,911.41
F. Harga Satuan Pekerjaan(D + E) 1,011,025.48

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.3.2.1.4 AHSP - A.3.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Pondasi Batu Belah Campuran 1 SP : 6 PP
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.500 81,000.00 121,500.00
Tukang Batu L.02 Org/Hari 0.750 122,000.00 91,500.00
Kepala Tukang L.03 Org/Hari 0.075 143,450.00 10,758.75
Mandor L.04 Org/Hari 0.075 105,000.00 7,875.00
JUMLAH TENAGA KERJA 231,633.75
B. BAHAN :
Batu Kali/ Batu Gunung - M3 1.200 267,000.00 320,400.00
Semen Portland - Kg 117.000 1,631.12 190,841.04
Pasir Pasang - M3 0.561 267,000.00 149,787.00
JUMLAH HARGA BAHAN 661,028.04
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 892,661.79
E. Overhead & Profit 10% x D 89,266.18
F. Harga Satuan Pekerjaan(D + E) 981,927.97

Halaman-42
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.3.2.1.9 AHSP - A.3.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Batu Kosong (Aanstamping)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Tukang Batu L.02 Org/Hari 0.500 122,000.00 61,000.00
Kepala Tukang L.03 Org/Hari 0.050 143,450.00 7,172.50
Mandor L.04 Org/Hari 0.100 105,000.00 10,500.00
JUMLAH TENAGA KERJA 159,672.50
B. BAHAN :
Batu Kali/ Batu Gunung - M3 1.200 267,000.00 320,400.00
Pasir Urug - M3 0.432 267,000.00 115,344.00
JUMLAH HARGA BAHAN 435,744.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 595,416.50
E. Overhead & Profit 10% x D 59,541.65
F. Harga Satuan Pekerjaan(D + E) 654,958.15

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.3.2.1.11 AHSP - A.3.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Pondasi Sumuran, Diameter 100 cm
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 2.400 81,000.00 194,400.00
Tukang Batu L.02 Org/Hari 0.800 122,000.00 97,600.00
Kepala Tukang L.03 Org/Hari 0.080 143,450.00 11,476.00
Mandor L.04 Org/Hari 0.119 105,000.00 12,495.00
JUMLAH TENAGA KERJA 315,971.00
B. BAHAN :
Batu Belah - M3 1.200 267,000.00 320,400.00
Semen Portland - Kg 194.000 1,631.12 316,437.28
Pasir Beton - M3 0.312 267,000.00 83,304.00
Kerikil - M3 0.468 267,000.00 124,956.00
JUMLAH HARGA BAHAN 845,097.28
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,161,068.28
E. Overhead & Profit 10% x D 116,106.83
F. Harga Satuan Pekerjaan(D + E) 1,277,175.11

Halaman-43
IV.1 AHSP - A.4.1.1 HARGA SATUAN PEKERJAAN BETON (Mutu Beton)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.1 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 7,4 MPa (K 100), Slump (12 ± 2) cm, W/C = 0,87
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.083 105,000.00 8,715.00
JUMLAH TENAGA KERJA 179,931.60
B. BAHAN :
Semen Portland - Kg 247.000 1,631.12 402,886.64
Pasir Beton - Kg 869.000 190.71 165,730.71
Kerikil Split (Maks 30 mm) - Kg 999.000 222.22 222,000.00
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 812,117.35
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 992,048.95
E. Overhead & Profit 10% x D 99,204.90
F. Harga Satuan Pekerjaan(D + E) 1,091,253.85

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.2 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 9,8 MPa (K 125), Slump (12 ± 2) cm, W/C = 0,78
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 276.000 1,631.12 450,189.12
Pasir Beton - Kg 828.000 190.71 157,911.43
Kerikil Split (Maks 30 mm) - Kg 1,012.000 222.22 224,888.89
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 854,489.44
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,043,031.04
E. Overhead & Profit 10% x D 104,303.10
F. Harga Satuan Pekerjaan(D + E) 1,147,334.14

Halaman-44
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.3 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 12,2 MPa (K 150), Slump (12 ± 2) cm, W/C = 0,72
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 299.000 1,631.12 487,704.88
Pasir Beton - Kg 799.000 190.71 152,380.71
Kerikil Split (Maks 30 mm) - Kg 1,017.000 222.22 226,000.00
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 887,585.59
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,076,127.19
E. Overhead & Profit 10% x D 107,612.72
F. Harga Satuan Pekerjaan(D + E) 1,183,739.91

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.4 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Lantai Kerja Beton Mutu f'c = 7,4 MPa (K 100), Slump (3-6) cm, W/C = 0,87
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.200 81,000.00 97,200.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.060 105,000.00 6,300.00
JUMLAH TENAGA KERJA 130,769.00
B. BAHAN :
Semen Portland - Kg 230.000 1,631.12 375,157.60
Pasir Beton - Kg 893.000 190.71 170,307.86
Kerikil Split (Maks 30 mm) - Kg 1,027.000 222.22 228,222.22
Air - Liter 200.000 100.00 20,000.00
JUMLAH HARGA BAHAN 793,687.68
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 924,456.68
E. Overhead & Profit 10% x D 92,445.67
F. Harga Satuan Pekerjaan(D + E) 1,016,902.35

Halaman-45
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.5 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Lantai Kerja Beton Mutu f'c = 14,5 MPa (K 175), Slump (12 ± 2) cm, W/C = 0,66
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 326.000 1,631.12 531,745.12
Pasir Beton - Kg 760.000 190.71 144,942.86
Kerikil Split (Maks 30 mm) - Kg 1,029.000 222.22 228,666.67
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 926,854.64
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,115,396.24
E. Overhead & Profit 10% x D 111,539.62
F. Harga Satuan Pekerjaan(D + E) 1,226,935.87

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.6 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 16,9 MPa (K 200), Slump (12 ± 2) cm, W/C = 0,61
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 352.000 1,631.12 574,154.24
Pasir Beton - Kg 731.000 190.71 139,412.14
Kerikil Split (Maks 30 mm) - Kg 1,031.000 222.22 229,111.11
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 964,177.49
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,152,719.09
E. Overhead & Profit 10% x D 115,271.91
F. Harga Satuan Pekerjaan(D + E) 1,267,991.00

Halaman-46
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.7 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 19,3 MPa (K 225), Slump (12 ± 2) cm, W/C = 0,58
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 371.000 1,631.12 605,145.52
Pasir Beton - Kg 698.000 190.71 133,118.57
Kerikil Split (Maks 30 mm) - Kg 1,047.000 222.22 232,666.67
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 992,430.76
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,180,972.36
E. Overhead & Profit 10% x D 118,097.24
F. Harga Satuan Pekerjaan(D + E) 1,299,069.59

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.8 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 21,7 MPa (K 250), Slump (12 ± 2) cm, W/C = 0,56
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 384.000 1,631.12 626,350.08
Pasir Beton - Kg 692.000 190.71 131,974.29
Kerikil Split (Maks 30 mm) - Kg 1,039.000 222.22 230,888.89
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,010,713.25
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,199,254.85
E. Overhead & Profit 10% x D 119,925.49
F. Harga Satuan Pekerjaan(D + E) 1,319,180.34

Halaman-47
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.9 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 24,0 MPa (K 275), Slump (12 ± 2) cm, W/C = 0,53
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 406.000 1,631.12 662,234.72
Pasir Beton - Kg 684.000 190.71 130,448.57
Kerikil Split (Maks 30 mm) - Kg 1,026.000 222.22 228,000.00
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,042,183.29
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,230,724.89
E. Overhead & Profit 10% x D 123,072.49
F. Harga Satuan Pekerjaan(D + E) 1,353,797.38

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.10 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 26,4 MPa (K 300), Slump (12 ± 2) cm, W/C = 0,52
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.650 81,000.00 133,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Kepala Tukang L.03 Org/Hari 0.028 143,450.00 4,016.60
Mandor L.04 Org/Hari 0.165 105,000.00 17,325.00
JUMLAH TENAGA KERJA 188,541.60
B. BAHAN :
Semen Portland - Kg 413.000 1,631.12 673,652.56
Pasir Beton - Kg 681.000 190.71 129,876.43
Kerikil Split (Maks 30 mm) - Kg 1,021.000 222.22 226,888.89
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,051,917.88
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,240,459.48
E. Overhead & Profit 10% x D 124,045.95
F. Harga Satuan Pekerjaan(D + E) 1,364,505.43

Halaman-48
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.11 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 28,8 MPa (K 325), Slump (12 ± 2) cm, W/C = 0,49
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 2.100 81,000.00 170,100.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.210 105,000.00 22,050.00
JUMLAH TENAGA KERJA 239,870.75
B. BAHAN :
Semen Portland - Kg 439.000 1,631.12 716,061.68
Pasir Beton - Kg 670.000 190.71 127,778.57
Kerikil Split (Maks 30 mm) - Kg 1,006.000 222.22 223,555.56
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,088,895.81
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,328,766.56
E. Overhead & Profit 10% x D 132,876.66
F. Harga Satuan Pekerjaan(D + E) 1,461,643.21

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.12 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 31,2 MPa (K 350), Slump (12 ± 2) cm, W/C = 0,48
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 2.100 81,000.00 170,100.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.105 105,000.00 11,025.00
JUMLAH TENAGA KERJA 228,845.75
B. BAHAN :
Semen Portland - Kg 448.000 1,631.12 730,741.76
Pasir Beton - Kg 667.000 190.71 127,206.43
Kerikil Split (Maks 30 mm) - Kg 1,000.000 222.22 222,222.22
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,101,670.41
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,330,516.16
E. Overhead & Profit 10% x D 133,051.62
F. Harga Satuan Pekerjaan(D + E) 1,463,567.78

Halaman-49
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.12 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Mutu f'c = 33,2 MPa (K 450), Slump (12 ± 2) cm, W/C = 0,48
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 2.100 81,000.00 170,100.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.105 105,000.00 11,025.00
JUMLAH TENAGA KERJA 228,845.75
B. BAHAN :
Semen Portland - Kg 466.852 1,631.12 761,491.63
Pasir Beton - Kg 664.000 190.71 126,634.29
Kerikil Split (Maks 30 mm) - Kg 994.000 222.22 220,888.89
Air - Liter 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 1,130,514.81
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,359,360.56
E. Overhead & Profit 10% x D 135,936.06
F. Harga Satuan Pekerjaan(D + E) 1,495,296.61

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.13 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Beton Kedap Air Dengan Storox - 100
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 2.100 81,000.00 170,100.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.105 105,000.00 11,025.00
JUMLAH TENAGA KERJA 228,845.75
B. BAHAN :
Semen Portland - Kg 400.000 1,631.12 652,448.00
Pasir Beton - M3 0.480 267,000.00 128,160.00
Kerikil Split (Maks 30 mm) - Kg 0.800 300,000.00 240,000.00
Strorox - 100 - Kg 1.200 30,000.00 36,000.00
JUMLAH HARGA BAHAN 1,056,608.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,285,453.75
E. Overhead & Profit 10% x D 128,545.38
F. Harga Satuan Pekerjaan(D + E) 1,413,999.13

Halaman-50
IV.2 AHSP - A.4.1.1 HARGA SATUAN PEKERJAAN BETON (Pembesian dan Bekisting)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.17 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pembesian 10 Kg Dengan Besi Polos atau Besi Ulir
SATUAN PEMBAYARAN : 10 Kg

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
1. Besi Beton (Polos/ Ulir) Ǿ 6 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 6 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 6 mm (Harga Satuan Pekerjaan / 10) 16,916.26
2. Besi Beton (Polos/ Ulir) Ǿ 8 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 8 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 8 mm (Harga Satuan Pekerjaan / 10) 16,916.26
3. Besi Beton (Polos/ Ulir) Ǿ 10 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15

Halaman-51
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)

B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 10 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 10 mm (Harga Satuan Pekerjaan / 10) 16,916.26
4. Besi Beton (Polos/ Ulir) Ǿ 12 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 12 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 12 mm (Harga Satuan Pekerjaan / 10) 16,916.26
5. Besi Beton (Polos/ Ulir) Ǿ 14 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 14 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 14 mm (Harga Satuan Pekerjaan / 10) 16,916.26
6. Besi Beton (Polos/ Ulir) Ǿ 16 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 16 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 16 mm (Harga Satuan Pekerjaan / 10) 16,916.26

Halaman-52
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
7. Besi Beton (Polos/ Ulir) Ǿ 19 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 19 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 19 mm (Harga Satuan Pekerjaan / 10) 16,916.26
8. Besi Beton (Polos/ Ulir) Ǿ 22 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 81,000.00 5,670.00
Tukang Besi L.02 Org/Hari 0.070 122,000.00 8,540.00
Kepala Tukang L.03 Org/Hari 0.007 143,450.00 1,004.15
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 15,634.15
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 22 mm - Kg 10.500 12,800.00 134,400.00
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,150.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 153,784.15
E. Overhead & Profit 10% x D 15,378.42
F. Harga Satuan Pekerjaan(D + E) 169,162.57
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 22 mm (Harga Satuan Pekerjaan / 10) 16,916.26

Halaman-53
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.18 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kabel Presstessed Polos/ Strands
SATUAN PEMBAYARAN : 10 Kg

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.050 81,000.00 4,050.00
Tukang Besi L.02 Org/Hari 0.050 122,000.00 6,100.00
Kepala Tukang L.03 Org/Hari 0.005 143,450.00 717.25
Mandor L.04 Org/Hari 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 11,182.25
B. BAHAN :
Besi Beton (Polos/ Ulir) - Kg 10.500 12,800.00 134,400.00
Kawat Beton - Kg 0.100 25,000.00 2,500.00
JUMLAH HARGA BAHAN 136,900.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 148,082.25
E. Overhead & Profit 10% x D 14,808.23
F. Harga Satuan Pekerjaan(D + E) 162,890.48

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.20 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Pondasi
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.520 81,000.00 42,120.00
Tukang Kayu L.02 Org/Hari 0.260 122,000.00 31,720.00
Kepala Tukang L.03 Org/Hari 0.026 143,450.00 3,729.70
Mandor L.04 Org/Hari 0.026 105,000.00 2,730.00
JUMLAH TENAGA KERJA 80,299.70
B. BAHAN :
Kayu Kelas III - M3 0.040 1,573,000.00 62,920.00
Paku 5 - 10 cm - Kg 0.300 23,400.00 7,020.00
Minyak Bekisting - Liter 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 70,940.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 151,239.70
E. Overhead & Profit 10% x D 15,123.97
F. Harga Satuan Pekerjaan(D + E) 166,363.67

Halaman-54
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.21 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Sloof
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.520 81,000.00 42,120.00
Tukang Kayu L.02 Org/Hari 0.260 122,000.00 31,720.00
Kepala Tukang L.03 Org/Hari 0.026 143,450.00 3,729.70
Mandor L.04 Org/Hari 0.026 105,000.00 2,730.00
JUMLAH TENAGA KERJA 80,299.70
B. BAHAN :
Kayu Kelas III - M3 0.045 1,573,000.00 70,785.00
Paku 5 - 10 cm - Kg 0.300 23,400.00 7,020.00
Minyak Bekisting - Liter 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 78,805.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 159,104.70
E. Overhead & Profit 10% x D 15,910.47
F. Harga Satuan Pekerjaan(D + E) 175,015.17

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.22 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Kolom
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.660 81,000.00 53,460.00
Tukang Kayu L.02 Org/Hari 0.330 122,000.00 40,260.00
Kepala Tukang L.03 Org/Hari 0.033 143,450.00 4,733.85
Mandor L.04 Org/Hari 0.033 105,000.00 3,465.00
JUMLAH TENAGA KERJA 101,918.85
B. BAHAN :
Kayu Kelas III - M3 0.040 1,573,000.00 62,920.00
Paku 5 - 12 cm - Kg 0.400 23,400.00 9,360.00
Minyak Bekisting - Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II - M3 0.015 1,815,000.00 27,225.00
Papan Mall - M3 0.020 1,573,000.00 31,460.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 2.000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 148,965.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 250,883.85
E. Overhead & Profit 10% x D 25,088.39
F. Harga Satuan Pekerjaan(D + E) 275,972.24

Halaman-55
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.23 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Balok
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.660 81,000.00 53,460.00
Tukang Kayu L.02 Org/Hari 0.330 122,000.00 40,260.00
Kepala Tukang L.03 Org/Hari 0.033 143,450.00 4,733.85
Mandor L.04 Org/Hari 0.033 105,000.00 3,465.00
JUMLAH TENAGA KERJA 101,918.85
B. BAHAN :
Kayu Kelas III - M3 0.040 1,573,000.00 62,920.00
Paku 5 - 12 cm - Kg 0.400 23,400.00 9,360.00
Minyak Bekisting - Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II - M3 0.018 1,815,000.00 32,670.00
Papan Mall - M3 0.020 1,573,000.00 31,460.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 2.000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 154,410.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 256,328.85
E. Overhead & Profit 10% x D 25,632.89
F. Harga Satuan Pekerjaan(D + E) 281,961.74

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.24 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Lantai
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.660 81,000.00 53,460.00
Tukang Kayu L.02 Org/Hari 0.330 122,000.00 40,260.00
Kepala Tukang L.03 Org/Hari 0.033 143,450.00 4,733.85
Mandor L.04 Org/Hari 0.033 105,000.00 3,465.00
JUMLAH TENAGA KERJA 101,918.85
B. BAHAN :
Kayu Kelas III - M3 0.040 1,573,000.00 62,920.00
Paku 5 - 12 cm - Kg 0.400 23,400.00 9,360.00
Minyak Bekisting - Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II - M3 0.015 1,815,000.00 27,225.00
Papan Mall - M3 0.020 1,573,000.00 31,460.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 6.000 8,000.00 48,000.00
JUMLAH HARGA BAHAN 180,965.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 282,883.85
E. Overhead & Profit 10% x D 28,288.39
F. Harga Satuan Pekerjaan(D + E) 311,172.24

Halaman-56
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.25 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Dinding
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.660 81,000.00 53,460.00
Tukang Kayu L.02 Org/Hari 0.330 122,000.00 40,260.00
Kepala Tukang L.03 Org/Hari 0.033 143,450.00 4,733.85
Mandor L.04 Org/Hari 0.033 105,000.00 3,465.00
JUMLAH TENAGA KERJA 101,918.85
B. BAHAN :
Kayu Kelas III - M3 0.030 1,573,000.00 47,190.00
Paku 5 - 12 cm - Kg 0.400 23,400.00 9,360.00
Minyak Bekisting - Liter 0.200 10,000.00 2,000.00
Balok Kayu Kelas II - M3 0.020 1,815,000.00 36,300.00
Plywood Tebal 9 mm - Lembar 0.350 114,975.00 40,241.25
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 3.000 8,000.00 24,000.00
Penjaga Jarak Bekisting/ Spacer - Buah 4.000 10,000.00 40,000.00
JUMLAH HARGA BAHAN 199,091.25
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 301,010.10
E. Overhead & Profit 10% x D 30,101.01
F. Harga Satuan Pekerjaan(D + E) 331,111.11

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.26 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Untuk Tangga
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.660 81,000.00 53,460.00
Tukang Kayu L.02 Org/Hari 0.330 122,000.00 40,260.00
Kepala Tukang L.03 Org/Hari 0.033 143,450.00 4,733.85
Mandor L.04 Org/Hari 0.033 105,000.00 3,465.00
JUMLAH TENAGA KERJA 101,918.85
B. BAHAN :
Kayu Kelas III - M3 0.030 1,573,000.00 47,190.00
Paku 5 - 12 cm - Kg 0.400 23,400.00 9,360.00
Minyak Bekisting - Liter 0.150 10,000.00 1,500.00
Balok Kayu Kelas II - M3 0.015 1,815,000.00 27,225.00
Plywood Tebal 9 mm - Lembar 0.350 114,975.00 40,241.25
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 2.000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 141,516.25
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 243,435.10
E. Overhead & Profit 10% x D 24,343.51
F. Harga Satuan Pekerjaan(D + E) 267,778.61

Halaman-57
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.27 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Bekisting Jembatan Untuk Pengecoran Beton
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.150 81,000.00 12,150.00
Tukang Kayu L.02 Org/Hari 0.050 122,000.00 6,100.00
Kepala Tukang L.03 Org/Hari 0.005 143,450.00 717.25
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 19,807.25
B. BAHAN :
Kayu Kelas III - M3 0.0264 1,573,000.00 41,527.20
Paku 5 - 12 cm - Kg 0.600 23,400.00 14,040.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 0.500 8,000.00 4,000.00
JUMLAH HARGA BAHAN 59,567.20
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 79,374.45
E. Overhead & Profit 10% x D 7,937.45
F. Harga Satuan Pekerjaan(D + E) 87,311.90

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Terapan AHSP - TERAPAN


KODE/ JENIS PEKERJAAN : Membongkar Bakesting
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 3.000 81,000.00 243,000.00
JUMLAH TENAGA KERJA 243,000.00
B. BAHAN :

JUMLAH HARGA BAHAN -


C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 243,000.00
E. Overhead & Profit 10% x D 24,300.00
F. Harga Satuan Pekerjaan(D + E) 267,300.00

Halaman-58
IV.3 AHSP - A.4.1.1 HARGA SATUAN PEKERJAAN BETON (Pekerjaan Beton)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.28 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Pondasi Beton Bertulang (150 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 5.300 81,000.00 429,300.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.300 122,000.00 158,600.00
Tukang Besi L.02 Org/Hari 1.050 122,000.00 128,100.00
Kepala Tukang L.03 Org/Hari 0.262 143,450.00 37,583.90
Mandor L.04 Org/Hari 0.265 105,000.00 27,825.00
JUMLAH TENAGA KERJA 814,958.90
B. BAHAN :
Kayu Kelas III - M3 0.200 1,573,000.00 314,600.00
Paku 5 - 12 cm - Kg 1.500 23,400.00 35,100.00
Minyak Bekisting - Liter 0.400 10,000.00 4,000.00
Besi Beton Polos - SNI - Kg 157.500 12,800.00 2,016,000.00
Kawat Beton - Kg 2.250 25,000.00 56,250.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 3,334,456.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,149,415.22
E. Overhead & Profit 10% x D 414,941.52
F. Harga Satuan Pekerjaan(D + E) 4,564,356.74

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.28.a AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Pondasi Telapak Beton Bertulang - P1 (180 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
Beton K-250 - M3 1.000 1,319,180.34 1,319,180.34
Besi Beton Polos Ø 16 - SNI - Kg 180.000 16,916.26 3,044,926.17
Bekisting Pondasi - M2 1.870 166,363.67 311,100.06
JUMLAH TENAGA + BAHAN 4,675,206.57

Halaman-59
FORMULIR STANDAR UNTUK

ITEM PEMBAYARAN NO. : A.4.1.1.29 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Sloof Beton Bertulang (200 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 5.650 81,000.00 457,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.560 122,000.00 190,320.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.323 143,450.00 46,334.35
Mandor L.04 Org/Hari 0.283 105,000.00 29,715.00
JUMLAH TENAGA KERJA 928,369.35
B. BAHAN :
Kayu Kelas III - M3 0.270 1,573,000.00 424,710.00
Paku 5 - 12 cm - Kg 2.000 23,400.00 46,800.00
Minyak Bekisting - Liter 0.600 10,000.00 6,000.00
Besi Beton Polos - SNI - Kg 210.000 12,800.00 2,688,000.00
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 4,149,016.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,077,385.67
E. Overhead & Profit 10% x D 507,738.57
F. Harga Satuan Pekerjaan(D + E) 5,585,124.24

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.29.a AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Sloof Beton Bertulang 15 x 20 cm
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 5.650 81,000.00 457,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.560 122,000.00 190,320.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.323 143,450.00 46,334.35
Mandor L.04 Org/Hari 0.283 105,000.00 29,715.00
JUMLAH TENAGA KERJA 928,369.35
B. BAHAN :
Kayu Kelas III - M3 0.267 1,573,000.00 419,991.00
Paku 5 - 12 cm - Kg 2.000 23,400.00 46,800.00
Minyak Bekisting - Liter 0.600 10,000.00 6,000.00
Besi Beton Polos SNI 6 Ø 12 (Tulangan Utama) - Kg 177.600 12,800.00 2,273,280.00
Besi Beton Polos SNI Ø 8 - 15 (Tulangan Sengkang) - Kg 87.809 12,800.00 1,123,948.80
Kawat Beton - Kg 3.420 25,000.00 85,500.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 4,864,026.12
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,792,395.47
E. Overhead & Profit 10% x D 579,239.55
F. Harga Satuan Pekerjaan(D + E) 6,371,635.02

Halaman-60
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.30 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kolom Beton Bertulang (300 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 7.050 81,000.00 571,050.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 2.100 122,000.00 256,200.00
Kepala Tukang L.03 Org/Hari 0.403 143,450.00 57,810.35
Mandor L.04 Org/Hari 0.353 105,000.00 37,065.00
JUMLAH TENAGA KERJA 1,156,975.35
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 4.000 23,400.00 93,600.00
Minyak Bekisting - Liter 2.000 10,000.00 20,000.00
Besi Beton Polos - SNI - Kg 315.000 12,800.00 4,032,000.00
Kawat Beton - Kg 4.500 25,000.00 112,500.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 5,795,806.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 6,952,781.67
E. Overhead & Profit 10% x D 695,278.17
F. Harga Satuan Pekerjaan(D + E) 7,648,059.84

Halaman-61
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.30.a AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kolom Beton Bertulang 15 x 25 CM
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 7.050 81,000.00 571,050.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 2.100 122,000.00 256,200.00
Kepala Tukang L.03 Org/Hari 0.403 143,450.00 57,810.35
Mandor L.04 Org/Hari 0.353 105,000.00 37,065.00
JUMLAH TENAGA KERJA 1,156,975.35
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 4.000 23,400.00 93,600.00
Minyak Bekisting - Liter 2.000 10,000.00 20,000.00
Besi Beton Polos SNI 6 Ø 12 (Tulangan Utama) - Kg 118.400 12,800.00 1,515,520.00
Besi Beton Polos SNI Ø 8 - 15 (Tulangan Sengkang) - Kg 70.839 12,800.00 906,743.04
Kawat Beton - Kg 2.196 25,000.00 54,900.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 4,128,469.36
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,285,444.71
E. Overhead & Profit 10% x D 528,544.47
F. Harga Satuan Pekerjaan(D + E) 5,813,989.18

Halaman-62
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.30.b AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kolom Beton Bertulang 15 x 15 CM
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 7.050 81,000.00 571,050.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 2.100 122,000.00 256,200.00
Kepala Tukang L.03 Org/Hari 0.403 143,450.00 57,810.35
Mandor L.04 Org/Hari 0.353 105,000.00 37,065.00
JUMLAH TENAGA KERJA 1,156,975.35
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 4.000 23,400.00 93,600.00
Minyak Bekisting - Liter 2.000 10,000.00 20,000.00
Besi Beton Polos SNI 4 Ø 10 (Tulangan Tengah) - Kg 61.700 12,800.00 789,760.00
Besi Beton Polos SNI Ø 8 - 15 (Tulangan Sengkang) - Kg 71.606 12,800.00 916,551.68
Kawat Beton - Kg 2.472 25,000.00 61,800.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 3,419,418.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,576,393.35
E. Overhead & Profit 10% x D 457,639.34
F. Harga Satuan Pekerjaan(D + E) 5,034,032.69

Halaman-63
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.30.c AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kolom Beton Bertulang 15 x 70 CM
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 7.050 81,000.00 571,050.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 2.100 122,000.00 256,200.00
Kepala Tukang L.03 Org/Hari 0.403 143,450.00 57,810.35
Mandor L.04 Org/Hari 0.353 105,000.00 37,065.00
JUMLAH TENAGA KERJA 1,156,975.35
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 4.000 23,400.00 93,600.00
Minyak Bekisting - Liter 2.000 10,000.00 20,000.00
Besi Beton Polos SNI 10 Ø 12 (Tulangan Utama) - Kg 21.143 12,800.00 270,628.57
Besi Beton Polos SNI Ø 8 - 15 (Tulangan Sengkang) - Kg 52.716 12,800.00 674,770.94
Kawat Beton - Kg 0.576 25,000.00 14,400.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 2,611,105.84
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 3,768,081.19
E. Overhead & Profit 10% x D 376,808.12
F. Harga Satuan Pekerjaan(D + E) 4,144,889.30

Halaman-64
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.30.d AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kolom Beton Bertulang (K5) 25 x 25 CM (142,186 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 7.050 81,000.00 571,050.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 2.100 122,000.00 256,200.00
Kepala Tukang L.03 Org/Hari 0.403 143,450.00 57,810.35
Mandor L.04 Org/Hari 0.353 105,000.00 37,065.00
JUMLAH TENAGA KERJA 1,156,975.35
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 4.000 23,400.00 93,600.00
Minyak Bekisting - Liter 2.000 10,000.00 20,000.00
Besi Beton Polos SNI 8 Ø 12 (Tulangan Utama) - Kg 113.536 12,800.00 1,453,260.80
Besi Beton Polos SNI Ø 8 - 20 (Tulangan Sengkang) - Kg 28.650 12,800.00 366,716.16
Kawat Beton - Kg 4.500 25,000.00 112,500.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 3,583,783.28
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,740,758.63
E. Overhead & Profit 10% x D 474,075.86
F. Harga Satuan Pekerjaan(D + E) 5,214,834.49

Halaman-65
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.30.e AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kolom Beton Bertulang (K6) L.15 x 65 CM/15 x 35 CM (121,287 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 7.050 81,000.00 571,050.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 2.100 122,000.00 256,200.00
Kepala Tukang L.03 Org/Hari 0.403 143,450.00 57,810.35
Mandor L.04 Org/Hari 0.353 105,000.00 37,065.00
JUMLAH TENAGA KERJA 1,156,975.35
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 4.000 23,400.00 93,600.00
Minyak Bekisting - Liter 2.000 10,000.00 20,000.00
Besi Beton Polos SNI Ø 12 (Tulangan Utama) - Kg 53.220 12,800.00 681,216.00
Besi Beton Polos SNI Ø 10 (Tulangan Tengah) - Kg 24.680 12,800.00 315,904.00
Besi Beton Polos SNI Ø 8 - 15 (Tulangan Sengkang) - Kg 43.387 12,800.00 555,356.16
Kawat Beton - Kg 4.500 25,000.00 112,500.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
JUMLAH HARGA BAHAN 3,316,282.48
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,473,257.83
E. Overhead & Profit 10% x D 447,325.78
F. Harga Satuan Pekerjaan(D + E) 4,920,583.61

Halaman-66
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Balok Beton Bertulang (200 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.320 1,573,000.00 503,360.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos - SNI - Kg 210.000 12,800.00 2,688,000.00
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Plywood Tebal 9 mm - Lembar 2.800 114,975.00 321,930.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 4,969,776.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,970,935.17
E. Overhead & Profit 10% x D 597,093.52
F. Harga Satuan Pekerjaan(D + E) 6,568,028.69

Halaman-67
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31.a AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Balok Beton Bertulang 15 x 20
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.367 1,573,000.00 577,291.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI 6 Ǿ 10 mm - Kg 123.400 12,800.00 1,579,520.00
Besi Beton Polos SNI Ǿ 8 mm - 15 - Kg 87.809 12,800.00 1,123,948.80
Kawat Beton - Kg 3.420 25,000.00 85,500.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 4,747,746.12
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,748,904.97
E. Overhead & Profit 10% x D 574,890.50
F. Harga Satuan Pekerjaan(D + E) 6,323,795.47

Halaman-68
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31.b AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan RingBalok Beton Bertulang 15 x 15
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.333 1,573,000.00 523,809.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI 4 Ǿ 10 mm - Kg 109.689 12,800.00 1,404,017.78
Besi Beton Polos SNI Ǿ 8 mm - 15 - Kg 105.828 12,800.00 1,354,603.52
Kawat Beton - Kg 4.728 25,000.00 118,200.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 4,782,116.62
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,783,275.47
E. Overhead & Profit 10% x D 578,327.55
F. Harga Satuan Pekerjaan(D + E) 6,361,603.01

Halaman-69
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31.c AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Balok Beton Bertulang (RB3) 20 x 30 (148,881 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.267 1,573,000.00 419,991.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI 6 Ǿ 12 mm - Kg 88.700 12,800.00 1,135,360.00
Besi Beton Polos SNI 2 Ǿ 10 mm - Kg 20.567 12,800.00 263,253.33
Besi Beton Polos SNI Ǿ 8 mm - 15 - Kg 39.614 12,800.00 507,064.32
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 3,782,154.97
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,783,313.82
E. Overhead & Profit 10% x D 478,331.38
F. Harga Satuan Pekerjaan(D + E) 5,261,645.21

Halaman-70
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31.d AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Balok Beton Bertulang (RB4) 15 x 15 (153,508 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.400 1,573,000.00 629,200.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI 4 Ǿ 10 mm - Kg 109.689 12,800.00 1,404,017.78
Besi Beton Polos SNI Ǿ 6 mm - 20 - Kg 43.820 12,800.00 560,889.60
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 4,050,593.70
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,051,752.55
E. Overhead & Profit 10% x D 505,175.25
F. Harga Satuan Pekerjaan(D + E) 5,556,927.80

Halaman-71
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31.e AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Balok Beton Bertulang (RB5) 30 x 30 (99,267 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.200 1,573,000.00 314,600.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI 4 Ǿ 12 mm (Tulangan Pokok) - Kg 39.422 12,800.00 504,604.44
Besi Beton Polos SNI 4 Ǿ 10 mm (Tulangan Tengah) - Kg 27.422 12,800.00 351,004.44
Besi Beton Polos SNI Ǿ 8 mm - 15 - Kg 32.423 12,800.00 415,008.00
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 3,041,703.21
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,042,862.06
E. Overhead & Profit 10% x D 404,286.21
F. Harga Satuan Pekerjaan(D + E) 4,447,148.26

Halaman-72
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.31.f AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Balok Beton Bertulang (RB6) 30 x 40 (79,255 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.350 81,000.00 514,350.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.650 122,000.00 201,300.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.333 143,450.00 47,768.85
Mandor L.04 Org/Hari 0.318 105,000.00 33,390.00
JUMLAH TENAGA KERJA 1,001,158.85
B. BAHAN :
Kayu Kelas III - M3 0.183 1,573,000.00 287,859.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI 4 Ǿ 12 mm (Tulangan Pokok) - Kg 29.567 12,800.00 378,453.33
Besi Beton Polos SNI 4 Ǿ 10 mm (Tulangan Tengah) - Kg 20.567 12,800.00 263,253.33
Besi Beton Polos SNI Ǿ 8 mm - 15 - Kg 29.121 12,800.00 372,752.64
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.140 1,815,000.00 254,100.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 16.000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 2,758,804.63
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 3,759,963.48
E. Overhead & Profit 10% x D 375,996.35
F. Harga Satuan Pekerjaan(D + E) 4,135,959.82

Halaman-73
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.33 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Beton Bertulang (150 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 5.300 81,000.00 429,300.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.300 122,000.00 158,600.00
Tukang Besi L.02 Org/Hari 1.050 122,000.00 128,100.00
Kepala Tukang L.03 Org/Hari 0.262 143,450.00 37,583.90
Mandor L.04 Org/Hari 0.265 105,000.00 27,825.00
JUMLAH TENAGA KERJA 814,958.90
B. BAHAN :
Kayu Kelas III - M3 0.240 1,573,000.00 377,520.00
Paku 5 - 12 cm - Kg 3.200 23,400.00 74,880.00
Minyak Bekisting - Liter 1.600 10,000.00 16,000.00
Besi Beton Polos SNI Ǿ 10 mm - Kg 157.500 12,800.00 2,016,000.00
Kawat Beton - Kg 2.250 25,000.00 56,250.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.160 1,815,000.00 290,400.00
Plywood Tebal 9 mm - Lembar 2.800 114,975.00 321,930.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 24.000 8,000.00 192,000.00
JUMLAH HARGA BAHAN 4,253,486.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,068,445.22
E. Overhead & Profit 10% x D 506,844.52
F. Harga Satuan Pekerjaan(D + E) 5,575,289.74

Halaman-74
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.34 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Beton Bertulang (200 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 5.650 81,000.00 457,650.00
Tukang Batu L.02 Org/Hari 0.275 122,000.00 33,550.00
Tukang Kayu L.02 Org/Hari 1.560 122,000.00 190,320.00
Tukang Besi L.02 Org/Hari 1.400 122,000.00 170,800.00
Kepala Tukang L.03 Org/Hari 0.323 143,450.00 46,334.35
Mandor L.04 Org/Hari 0.283 105,000.00 29,715.00
JUMLAH TENAGA KERJA 928,369.35
B. BAHAN :
Kayu Kelas III - M3 0.250 1,573,000.00 393,250.00
Paku 5 - 12 cm - Kg 3.000 23,400.00 70,200.00
Minyak Bekisting - Liter 1.200 10,000.00 12,000.00
Besi Beton Polos - SNI - Kg 210.000 12,800.00 2,688,000.00
Kawat Beton - Kg 3.000 25,000.00 75,000.00
Semen Portland - Kg 336.000 1,631.12 548,056.32
Pasir Beton - M3 0.540 267,000.00 144,180.00
Kerikil - M3 0.810 267,000.00 216,270.00
Kayu Kelas II Balok - M3 0.105 1,815,000.00 190,575.00
Plywood Tebal 9 mm - Lembar 2.500 114,975.00 287,437.50
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' - Batang 14.000 8,000.00 112,000.00
JUMLAH HARGA BAHAN 4,736,968.82
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,665,338.17
E. Overhead & Profit 10% x D 566,533.82
F. Harga Satuan Pekerjaan(D + E) 6,231,871.99

Halaman-75
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.35 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Kolom Praktis Beton Bertulang 12 x 12 cm (K1)
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.180 81,000.00 14,580.00
Tukang Batu L.02 Org/Hari 0.020 122,000.00 2,440.00
Tukang Kayu L.02 Org/Hari 0.020 122,000.00 2,440.00
Tukang Besi L.02 Org/Hari 0.020 122,000.00 2,440.00
Kepala Tukang L.03 Org/Hari 0.006 143,450.00 860.70
Mandor L.04 Org/Hari 0.009 105,000.00 945.00
JUMLAH TENAGA KERJA 23,705.70
B. BAHAN :
Kayu Kelas III - M3 0.005 1,573,000.00 7,865.00
Paku 5 - 12 cm - Kg 0.010 23,400.00 234.00
Minyak Bekisting - Liter - 10,000.00 -
Besi Beton Polos SNI 4 Ǿ 10 mm - Kg 2.468 12,800.00 31,590.40
Besi Beton Polos SNI Ǿ 8 mm - 20 cm - Kg 0.896 12,800.00 11,468.80
Kawat Beton - Kg 0.450 25,000.00 11,250.00
Semen Portland - Kg 4.000 1,631.12 6,524.48
Pasir Beton - M3 0.006 267,000.00 1,602.00
Kerikil - M3 0.009 267,000.00 2,403.00
JUMLAH HARGA BAHAN 72,937.68
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 96,643.38
E. Overhead & Profit 10% x D 9,664.34
F. Harga Satuan Pekerjaan(D + E) 106,307.72

Halaman-76
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.36 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Ring Balok Beton Bertulang (10 x 15) cm
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.297 81,000.00 24,057.00
Tukang Batu L.02 Org/Hari 0.033 122,000.00 4,026.00
Tukang Kayu L.02 Org/Hari 0.033 122,000.00 4,026.00
Tukang Besi L.02 Org/Hari 0.033 122,000.00 4,026.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,144.50
B. BAHAN :
Kayu Kelas III - M3 0.003 1,573,000.00 4,719.00
Paku 5 - 12 cm - Kg 0.020 23,400.00 468.00
Minyak Bekisting - Liter - 10,000.00 -
Besi Beton Polos - SNI - Kg 3.600 12,800.00 46,080.00
Kawat Beton - Kg 0.050 25,000.00 1,250.00
Semen Portland - Kg 5.500 1,631.12 8,971.16
Pasir Beton - M3 0.009 267,000.00 2,403.00
Kerikil - M3 0.015 267,000.00 4,005.00
JUMLAH HARGA BAHAN 67,896.16
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 107,040.66
E. Overhead & Profit 10% x D 10,704.07
F. Harga Satuan Pekerjaan(D + E) 117,744.73

Halaman-77
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.37 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Plat Lantai Beton Bertulang, Tebal = 12 cm (140 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
Beton K-225 - M3 1.000 1,299,069.59 1,299,069.59
Besi Beton Polos SNI Ø 10 - 15 - Kg 140.000 16,916.26 2,368,275.91
Bekisting Plat Lantai - M2 8.455 311,172.24 2,630,961.25
JUMLAH TENAGA + BAHAN 6,298,306.75

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.37.a AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Plat Atap Beton Bertulang, Tebal = 10 cm (120 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
Beton K-175 - M3 1.000 1,226,935.87 1,226,935.87
Besi Beton Polos SNI Ø 10 - 15 - Kg 120.000 16,916.26 2,029,950.78
Bekisting Plat Lantai - M2 8.455 311,172.24 2,630,961.25
JUMLAH TENAGA + BAHAN 5,887,847.90

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.37.b AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Plat Leufel Beton Bertulang, Tebal = 10 cm (105 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
Beton K-175 - M3 1.000 1,226,935.87 1,226,935.87
Besi Beton Polos SNI Ø 10 - 15 - Kg 105.000 16,916.26 1,776,206.93
Bekisting Plat Lantai - M2 8.455 311,172.24 2,630,961.25
JUMLAH TENAGA + BAHAN 5,634,104.05

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.1.1.38 AHSP - A.4.1.1


KODE/ JENIS PEKERJAAN : Membuat Plat Tangga Beton Bertulang (150 Kg Besi + Bekisting)
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
Beton K-225 - M3 1.000 1,299,069.59 1,299,069.59
Besi Beton Polos SNI Ø 10 - Kg 150.000 16,916.26 2,537,438.48
Bekisting Plat Tangga - M2 3.571 311,172.24 1,111,196.05
JUMLAH TENAGA + BAHAN 4,947,704.12

Halaman-78
V. AHSP - A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALLUMINIUM

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.2.1.2 AHSP - A.4.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Rangka Kuda-Kuda Baja IWF
SATUAN PEMBAYARAN : Kg

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.060 81,000.00 4,860.00
Tukang Las Konstruksi L.02 Org/Hari 0.060 122,000.00 7,320.00
Kepala Tukang L.03 Org/Hari 0.006 143,450.00 860.70
Mandor L.04 Org/Hari 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 13,355.70
B. BAHAN :
Besi Baja IWF - Kg 1.150 22,000.00 25,300.00
JUMLAH HARGA BAHAN 25,300.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 38,655.70
E. Overhead & Profit 10% x D 3,865.57
F. Harga Satuan Pekerjaan(D + E) 42,521.27

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.2.1.18 AHSP - A.4.2.1


KODE/ JENIS PEKERJAAN : Talang Datar/ Jurai Seng BJLS 28 Lebar 90 cm
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 81,000.00 16,200.00
Tukang L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.001 105,000.00 105.00
JUMLAH TENAGA KERJA 43,574.00
B. BAHAN :
Seng Plat - M1 1.050 30,000.00 31,500.00
Paku 1 cm - 2,5 cm - Kg 0.015 20,000.00 300.00
Papan Kayu Kelas II - M3 0.019 1,815,000.00 34,485.00
JUMLAH HARGA BAHAN 66,285.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 109,859.00
E. Overhead & Profit 10% x D 10,985.90
F. Harga Satuan Pekerjaan(D + E) 120,844.90

Halaman-79
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.2.1.19 AHSP - A.4.2.1


KODE/ JENIS PEKERJAAN : Talang 1/2 Lingkaran D-15 cm, Seng Plat BJLS 30 Lebar 45 cm
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.150 81,000.00 12,150.00
Tukang L.02 Org/Hari 0.300 122,000.00 36,600.00
Kepala Tukang L.03 Org/Hari 0.030 143,450.00 4,303.50
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 53,893.50
B. BAHAN :
Seng Plat - M1 1.050 30,000.00 31,500.00
Paku 1 cm - 2,5 cm - Kg 0.010 20,000.00 200.00
Besi Strip - Kg 0.500 18,500.00 9,250.00
JUMLAH HARGA BAHAN 40,950.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 94,843.50
E. Overhead & Profit 10% x D 9,484.35
F. Harga Satuan Pekerjaan(D + E) 104,327.85

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.2.1.20 AHSP - A.4.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Rangka Besi Hollow 1 x 40.40.2 mm, Modul 60 x 120 cm, Untuk Dinding Partisi
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.250 81,000.00 20,250.00
Tukang Besi L.02 Org/Hari 0.250 122,000.00 30,500.00
Kepala Tukang L.03 Org/Hari 0.025 143,450.00 3,586.25
Mandor L.04 Org/Hari 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 55,701.25
B. BAHAN :
Rangka Metal Hollow 40.40.2 mm - M1 3.500 23,000.00 80,500.00
Peralatan dan Accesories (Perkuatan, Las, dll) - Ls 100 % x 80,500.00 80,500.00
Material
JUMLAH HARGA BAHAN 161,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 216,701.25
E. Overhead & Profit 10% x D 21,670.13
F. Harga Satuan Pekerjaan(D + E) 238,371.38

Halaman-80
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.2.1.21 AHSP - A.4.2.1


KODE/ JENIS PEKERJAAN : Pemasangan Rangka Besi Hollow 1 x 40.40.2 mm, Modul 60 x 60 cm, Untuk Plafond
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.350 81,000.00 28,350.00
Tukang Besi L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.018 105,000.00 1,890.00
JUMLAH TENAGA KERJA 77,960.75
B. BAHAN :
Rangka Metal Hollow 40.40.2 mm - M1 4.000 23,000.00 92,000.00
Peralatan dan Accesories (Perkuatan, Las, dll) - Ls 100 % x 23,000.00 23,000.00
Material
JUMLAH HARGA BAHAN 115,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 192,960.75
E. Overhead & Profit 10% x D 19,296.08
F. Harga Satuan Pekerjaan(D + E) 212,256.83

Halaman-81
VI. AHSP - A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.1 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1 Batu, Campuran 1 SP : 2 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.600 81,000.00 48,600.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 79,019.00
B. BAHAN :
Bata Merah - Buah 140.000 800.00 112,000.00
Semen Portland - Kg 43.500 1,631.12 70,953.72
Pasir Pasang - Kg 0.080 267,000.00 21,360.00
JUMLAH HARGA BAHAN 204,313.72
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 283,332.72
E. Overhead & Profit 10% x D 28,333.27
F. Harga Satuan Pekerjaan(D + E) 311,665.99

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.2 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1 Batu, Campuran 1 SP : 3 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.600 81,000.00 48,600.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 79,019.00
B. BAHAN :
Bata Merah - Buah 140.000 800.00 112,000.00
Semen Portland - Kg 32.950 1,631.12 53,745.40
Pasir Pasang - Kg 0.091 267,000.00 24,297.00
JUMLAH HARGA BAHAN 190,042.40
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 269,061.40
E. Overhead & Profit 10% x D 26,906.14
F. Harga Satuan Pekerjaan(D + E) 295,967.54

Halaman-82
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.3 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1 Batu, Campuran 1 SP : 4 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.600 81,000.00 48,600.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 79,019.00
B. BAHAN :
Bata Merah - Buah 140.000 800.00 112,000.00
Semen Portland - Kg 26.550 1,631.12 43,306.24
Pasir Pasang - Kg 0.093 267,000.00 24,831.00
JUMLAH HARGA BAHAN 180,137.24
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 259,156.24
E. Overhead & Profit 10% x D 25,915.62
F. Harga Satuan Pekerjaan(D + E) 285,071.86

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.4 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1 Batu, Campuran 1 SP : 5 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.600 81,000.00 48,600.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 79,019.00
B. BAHAN :
Bata Merah - Buah 140.000 800.00 112,000.00
Semen Portland - Kg 22.200 1,631.12 36,210.86
Pasir Pasang - Kg 0.102 267,000.00 27,234.00
JUMLAH HARGA BAHAN 175,444.86
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 254,463.86
E. Overhead & Profit 10% x D 25,446.39
F. Harga Satuan Pekerjaan(D + E) 279,910.25

Halaman-83
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.7 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1/2 Batu, Campuran 1 SP : 2 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,509.50
B. BAHAN :
Bata Merah - Buah 70.000 800.00 56,000.00
Semen Portland - Kg 18.950 1,631.12 30,909.72
Pasir Pasang - Kg 0.038 267,000.00 10,146.00
JUMLAH HARGA BAHAN 97,055.72
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 136,565.22
E. Overhead & Profit 10% x D 13,656.52
F. Harga Satuan Pekerjaan(D + E) 150,221.75

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.8 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1/2 Batu, Campuran 1 SP : 3 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,509.50
B. BAHAN :
Bata Merah - Buah 70.000 800.00 56,000.00
Semen Portland - Kg 14.370 1,631.12 23,439.19
Pasir Pasang - Kg 0.040 267,000.00 10,680.00
JUMLAH HARGA BAHAN 90,119.19
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 129,628.69
E. Overhead & Profit 10% x D 12,962.87
F. Harga Satuan Pekerjaan(D + E) 142,591.56

Halaman-84
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.9 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1/2 Batu, Campuran 1 SP : 4 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,509.50
B. BAHAN :
Bata Merah - Buah 70.000 800.00 56,000.00
Semen Portland - Kg 11.500 1,631.12 18,757.88
Pasir Pasang - Kg 0.043 267,000.00 11,481.00
JUMLAH HARGA BAHAN 86,238.88
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 125,748.38
E. Overhead & Profit 10% x D 12,574.84
F. Harga Satuan Pekerjaan(D + E) 138,323.22

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.9 AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Bata Merah (5 x 11 x 22) cm Tebal 1/2 Batu, Campuran 1 SP : 5 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,509.50
B. BAHAN :
Bata Merah - Buah 70.000 800.00 56,000.00
Semen Portland - Kg 9.680 1,631.12 15,789.24
Pasir Pasang - Kg 0.045 267,000.00 12,015.00
JUMLAH HARGA BAHAN 83,804.24
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 123,313.74
E. Overhead & Profit 10% x D 12,331.37
F. Harga Satuan Pekerjaan(D + E) 135,645.12

Halaman-85
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.1.21.a AHSP - A.4.4.1


KODE/ JENIS PEKERJAAN : Pemasangan 1 M2 Dinding Batako Cetak Ukuran 20 x 40 x 10 cm, Campuran 1 SP : 4 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,509.50
B. BAHAN :
Batako Cetak Ukuran 16 x 40 x 10 cm - Buah 12.300 4,000.00 49,200.00
Semen Portland - Kg 11.000 1,631.12 17,942.32
Pasir Pasang - Kg 0.035 267,000.00 9,345.00
JUMLAH HARGA BAHAN 76,487.32
C. PERALATAN :

JUMLAH HARGA ALAT -


D. Jumlah (A+B+C) 115,996.82
E. Overhead & Profit 10% x D 11,599.68
F. Harga Satuan Pekerjaan(D + E) 127,596.50

VII. AHSP - A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.2 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 2 PP Tebal 15 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 46,326.75
B. BAHAN :
Semen Portland - Kg 10.224 1,631.12 16,676.57
Pasir Pasang - Kg 0.020 267,000.00 5,340.00
JUMLAH HARGA BAHAN 22,016.57
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 68,343.32
E. Overhead & Profit 10% x D 6,834.33
F. Harga Satuan Pekerjaan(D + E) 75,177.65

Halaman-86
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.3 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 3 PP Tebal 15 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 46,326.75
B. BAHAN :
Semen Portland - Kg 7.776 1,631.12 12,683.59
Pasir Pasang - Kg 0.023 267,000.00 6,141.00
JUMLAH HARGA BAHAN 18,824.59
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,151.34
E. Overhead & Profit 10% x D 6,515.13
F. Harga Satuan Pekerjaan(D + E) 71,666.47

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.4 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 4 PP Tebal 15 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 46,326.75
B. BAHAN :
Semen Portland - Kg 6.240 1,631.12 10,178.19
Pasir Pasang - Kg 0.024 267,000.00 6,408.00
JUMLAH HARGA BAHAN 16,586.19
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 62,912.94
E. Overhead & Profit 10% x D 6,291.29
F. Harga Satuan Pekerjaan(D + E) 69,204.23

Halaman-87
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.5 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 5 PP Tebal 15 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 46,326.75
B. BAHAN :
Semen Portland - Kg 5.184 1,631.12 8,455.73
Pasir Pasang - Kg 0.026 267,000.00 6,942.00
JUMLAH HARGA BAHAN 15,397.73
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 61,724.48
E. Overhead & Profit 10% x D 6,172.45
F. Harga Satuan Pekerjaan(D + E) 67,896.92

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.14 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 3 PP Tebal 20 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.260 81,000.00 21,060.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 49,694.00
B. BAHAN :
Semen Portland - Kg 10.368 1,631.12 16,911.45
Pasir Pasang - Kg 0.031 267,000.00 8,277.00
JUMLAH HARGA BAHAN 25,188.45
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 74,882.45
E. Overhead & Profit 10% x D 7,488.25
F. Harga Satuan Pekerjaan(D + E) 82,370.70

Halaman-88
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.15 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 4 PP Tebal 20 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.400 81,000.00 32,400.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.022 105,000.00 2,310.00
JUMLAH TENAGA KERJA 61,979.00
B. BAHAN :
Semen Portland - Kg 8.320 1,631.12 13,570.92
Pasir Pasang - Kg 0.032 267,000.00 8,544.00
JUMLAH HARGA BAHAN 22,114.92
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 84,093.92
E. Overhead & Profit 10% x D 8,409.39
F. Harga Satuan Pekerjaan(D + E) 92,503.31

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.16 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran, Campuran 1 SP : 5 PP Tebal 20 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.400 81,000.00 32,400.00
Tukang Batu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.022 105,000.00 2,310.00
JUMLAH TENAGA KERJA 61,979.00
B. BAHAN :
Semen Portland - Kg 6.912 1,631.12 11,274.30
Pasir Pasang - Kg 0.035 267,000.00 9,345.00
JUMLAH HARGA BAHAN 20,619.30
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 82,598.30
E. Overhead & Profit 10% x D 8,259.83
F. Harga Satuan Pekerjaan(D + E) 90,858.13

Halaman-89
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.20 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran Skoning, Campuran 1 SP : 3 PP Lebar 10 cm
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.080 81,000.00 6,480.00
Tukang Batu L.02 Org/Hari 0.400 122,000.00 48,800.00
Kepala Tukang L.03 Org/Hari 0.040 143,450.00 5,738.00
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 61,438.00
B. BAHAN :
Semen Portland - Kg 0.500 1,631.12 815.56
Pasir Pasang - Kg 0.013 267,000.00 3,471.00
JUMLAH HARGA BAHAN 4,286.56
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 65,724.56
E. Overhead & Profit 10% x D 6,572.46
F. Harga Satuan Pekerjaan(D + E) 72,297.02

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.23 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Plesteran Ciprat, Campuran 1 SP : 2 PP
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.300 81,000.00 24,300.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.015 105,000.00 1,575.00
JUMLAH TENAGA KERJA 39,509.50
B. BAHAN :
Semen Portland - Kg 4.320 1,631.12 7,046.44
Pasir Pasang - Kg 0.006 267,000.00 1,602.00
JUMLAH HARGA BAHAN 8,648.44
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 48,157.94
E. Overhead & Profit 10% x D 4,815.79
F. Harga Satuan Pekerjaan(D + E) 52,973.73

Halaman-90
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.24 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Finishing Siar Pasangan Bata Merah
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.150 81,000.00 12,150.00
Tukang Batu L.02 Org/Hari 0.075 122,000.00 9,150.00
Kepala Tukang L.03 Org/Hari 0.008 143,450.00 1,147.60
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 23,287.60
B. BAHAN :
Semen Portland - Kg 3.108 1,631.12 5,069.52
JUMLAH HARGA BAHAN 5,069.52
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 28,357.12
E. Overhead & Profit 10% x D 2,835.71
F. Harga Satuan Pekerjaan(D + E) 31,192.83

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.2.27 AHSP - A.4.4.2


KODE/ JENIS PEKERJAAN : Pemasangan Acian
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 81,000.00 16,200.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 30,884.50
B. BAHAN :
Semen Portland - Kg 3.250 1,631.12 5,301.14
JUMLAH HARGA BAHAN 5,301.14
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 36,185.64
E. Overhead & Profit 10% x D 3,618.56
F. Harga Satuan Pekerjaan(D + E) 39,804.20

Halaman-91
VIII. AHSP - A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.3.13 AHSP - A.4.4.3


KODE/ JENIS PEKERJAAN : Pemasangan Lantai Granit Tile Ukuran 60 cm x 60 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.240 81,000.00 19,440.00
Tukang Batu L.02 Org/Hari 0.120 122,000.00 14,640.00
Kepala Tukang L.03 Org/Hari 0.012 143,450.00 1,721.40
Mandor L.04 Org/Hari 0.012 105,000.00 1,260.00
JUMLAH TENAGA KERJA 37,061.40
B. BAHAN :
Granit Tile Ukuran 60 cm x 60 cm - Buah 3.100 71,129.03 220,500.00
Semen Portland - Kg 9.600 1,631.12 15,658.75
Semen Warna - Kg 1.500 3,000.00 4,500.00
Pasir Pasang - M3 0.045 267,000.00 12,015.00
JUMLAH HARGA BAHAN 252,673.75
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 289,735.15
E. Overhead & Profit 10% x D 28,973.52
F. Harga Satuan Pekerjaan(D + E) 318,708.67

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.3.14 AHSP - A.4.4.3


KODE/ JENIS PEKERJAAN : Pemasangan Lantai Keramik Ukuran 40 cm x 40 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.700 81,000.00 56,700.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.035 105,000.00 3,675.00
JUMLAH TENAGA KERJA 108,095.75
B. BAHAN :
Keramik Ukuran 40 cm x 40 cm - Dos 1.050 75,000.00 78,750.00
Semen Portland - Kg 10.000 1,631.12 16,311.20
Semen Warna - Kg 0.500 3,000.00 1,500.00
Pasir Pasang - M3 0.045 267,000.00 12,015.00
JUMLAH HARGA BAHAN 108,576.20
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 216,671.95
E. Overhead & Profit 10% x D 21,667.20
F. Harga Satuan Pekerjaan(D + E) 238,339.15

Halaman-92
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.3.58 AHSP - A.4.4.3


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Batu Andesit Bintik 20 x 40 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.700 81,000.00 56,700.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.035 105,000.00 3,675.00
JUMLAH TENAGA KERJA 108,095.75
B. BAHAN :
Batu Andesit Bintik 20 x 40 cm - M2 1.100 Err:509 Err:509
Semen Portland - Kg 11.750 1,631.12 19,165.66
Pasir Pasang - M3 0.035 267,000.00 9,345.00
JUMLAH HARGA BAHAN Err:509
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) Err:509
E. Overhead & Profit 10% x D Err:509
F. Harga Satuan Pekerjaan(D + E) Err:509

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.3.58 AHSP - A.4.4.3


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Batu Susun Sirih 3 x 30 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.700 81,000.00 56,700.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.035 105,000.00 3,675.00
JUMLAH TENAGA KERJA 108,095.75
B. BAHAN :
Batu Susun Sirih 3 x 30 cm - M2 1.100 - -
Semen Portland - Kg 11.750 1,631.12 19,165.66
Pasir Pasang - M3 0.035 267,000.00 9,345.00
JUMLAH HARGA BAHAN 28,510.66
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 136,606.41
E. Overhead & Profit 10% x D 13,660.64
F. Harga Satuan Pekerjaan(D + E) 150,267.05

Halaman-93
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.4.3.58 AHSP - A.4.4.3


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Batu Acak Jember
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.700 81,000.00 56,700.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.035 105,000.00 3,675.00
JUMLAH TENAGA KERJA 108,095.75
B. BAHAN :
Batu Acak Jember - M2 1.100 Err:509 Err:509
Semen Portland - Kg 11.750 1,631.12 19,165.66
Pasir Pasang - M3 0.035 267,000.00 9,345.00
JUMLAH HARGA BAHAN Err:509
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) Err:509
E. Overhead & Profit 10% x D Err:509
F. Harga Satuan Pekerjaan(D + E) Err:509

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.4.3 AHSP - A.4.4.3


KODE/ JENIS PEKERJAAN : Pemasangan 1 m2 Paving Block mutu K-225, tebal = 8 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.5000 81,000.00 40,500.00
Tukang Batu L.02 Org/Hari 0.5000 122,000.00 61,000.00
Kepala Tukang L.03 Org/Hari 0.0500 143,450.00 7,172.50
Mandor L.04 Org/Hari 0.0013 105,000.00 136.50
JUMLAH TENAGA KERJA 108,809.00
B. BAHAN :
Paving Block t = 8 cm - m2 1.010 125,000.00 126,250.00
Pasir Pasang - m3 0.070 267,000.00 18,690.00
JUMLAH HARGA BAHAN 144,940.00
C. PERALATAN :
Peralatan - % 10,000 9,701.05 9,701.05
JUMLAH HARGA ALAT 9,701.05
D. Jumlah (A+B+C) 263,450.05
E. Overhead & Profit 10% x D 26,345.01
F. Harga Satuan Pekerjaan(D + E) 289,795.06

Halaman-94
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : An- Ter An- Ter


KODE/ JENIS PEKERJAAN : Pemasangan Lantai Batu Alam (sikat/Peble)
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.700 81,000.00 56,700.00
Tukang Batu L.02 Org/Hari 0.350 122,000.00 42,700.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.035 105,000.00 3,675.00
JUMLAH TENAGA KERJA 108,095.75
B. BAHAN :
Batu Sikat Motif Kecil/ Besar - M2 1.100 150,000.00 165,000.00
Semen Portland - Kg 9.800 1,631.12 15,984.98
Pasir Pasang - M3 0.045 267,000.00 12,015.00
JUMLAH HARGA BAHAN 192,999.98
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 301,095.73
E. Overhead & Profit 10% x D 30,109.57
F. Harga Satuan Pekerjaan(D + E) 331,205.30

Halaman-95
IX. AHSP - A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.5.1.5 AHSP - A.4.5.1


KODE/ JENIS PEKERJAAN : Pemasangan Langit-langit Tripleks Ukuran (120 x 240) cm, Tebal 3 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.100 81,000.00 8,100.00
Tukang Kayu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 22,259.50
B. BAHAN :
Tripleks Tebal 3 mm - Lbr 0.375 49,500.00 18,562.50
Paku Tripleks - Kg 0.030 27,300.00 819.00
JUMLAH HARGA BAHAN 19,381.50
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 41,641.00
E. Overhead & Profit 10% x D 4,164.10
F. Harga Satuan Pekerjaan(D + E) 45,805.10

Halaman-96
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.5.2.38 AHSP - A.4.5.2


KODE/ JENIS PEKERJAAN : Pemasangan Atap Seng Gelombang
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.120 81,000.00 9,720.00
Tukang Alumunium L.02 Org/Hari 0.060 122,000.00 7,320.00
Kepala Tukang L.03 Org/Hari 0.006 143,450.00 860.70
Mandor L.04 Org/Hari 0.006 105,000.00 630.00
JUMLAH TENAGA KERJA 18,530.70
B. BAHAN :
Atap Seng Gelombang BJLS 0,20 - Lbr 0.700 48,750.00 34,125.00
Paku Biasa 1/2" - 1" - Kg 0.020 20,000.00 400.00
JUMLAH HARGA BAHAN 34,525.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 53,055.70
E. Overhead & Profit 10% x D 5,305.57
F. Harga Satuan Pekerjaan(D + E) 58,361.27

Halaman-97
XI. AHSP - A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.1.1 AHSP - A.4.6.1


KODE/ JENIS PEKERJAAN : Pembuatan dan Pemasangan Kusen Pintu dan Kusen Jendela, Kayu Kelas II
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 6.000 81,000.00 486,000.00
Tukang Kayu L.02 Org/Hari 18.000 122,000.00 2,196,000.00
Kepala Tukang L.03 Org/Hari 1.800 143,450.00 258,210.00
Mandor L.04 Org/Hari 0.300 105,000.00 31,500.00
JUMLAH TENAGA KERJA 2,971,710.00
B. BAHAN :
Balok Kayu Kelas II - M3 1.200 1,815,000.00 2,178,000.00
Paku 10 cm - Kg 1.250 21,450.00 26,812.50
Lem Kayu - Kg 1.000 18,810.00 18,810.00
JUMLAH HARGA BAHAN 2,223,622.50
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,195,332.50
E. Overhead & Profit 10% x D 519,533.25
F. Harga Satuan Pekerjaan(D + E) 5,714,865.75

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.1.5 AHSP - A.4.6.1


KODE/ JENIS PEKERJAAN : Pembuatan dan Pemasangan Daun Pintu Panil, Kayu Kelas II
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 1.000 81,000.00 81,000.00
Tukang Kayu L.02 Org/Hari 3.000 122,000.00 366,000.00
Kepala Tukang L.03 Org/Hari 0.300 143,450.00 43,035.00
Mandor L.04 Org/Hari 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 495,285.00
B. BAHAN :
Papan Kayu Kelas II - M3 0.040 1,815,000.00 72,600.00
Lem Kayu - Kg 0.500 18,810.00 9,405.00
JUMLAH HARGA BAHAN 82,005.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 577,290.00
E. Overhead & Profit 10% x D 57,729.00
F. Harga Satuan Pekerjaan(D + E) 635,019.00

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

Halaman-98
ITEM PEMBAYARAN NO. : AHSP - A.4.6.1.13 AHSP - A.4.6.1
KODE/ JENIS PEKERJAAN : Pemasangan Konstruksi Kuda-kuda Konvensional, Kayu Kelas II
SATUAN PEMBAYARAN : M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 4.000 81,000.00 324,000.00
Tukang Kayu L.02 Org/Hari 12.000 122,000.00 1,464,000.00
Kepala Tukang L.03 Org/Hari 1.200 143,450.00 172,140.00
Mandor L.04 Org/Hari 0.200 105,000.00 21,000.00
JUMLAH TENAGA KERJA 1,981,140.00
B. BAHAN :
Balok Kayu Kelas II - M3 1.100 1,815,000.00 1,996,500.00
Besi Strip Tebal 5 mm - Kg 15.000 6,503.33 97,550.00
Paku 12 cm - Kg 5.600 21,450.00 120,120.00
JUMLAH HARGA BAHAN 2,214,170.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 4,195,310.00
E. Overhead & Profit 10% x D 419,531.00
F. Harga Satuan Pekerjaan(D + E) 4,614,841.00

Halaman-99
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.1.20 AHSP - A.4.6.1


KODE/ JENIS PEKERJAAN : Pemasangan Rangka Langit-langit (60 x 60 cm), Kayu Kelas II
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 81,000.00 16,200.00
Tukang Kayu L.02 Org/Hari 0.300 122,000.00 36,600.00
Kepala Tukang L.03 Org/Hari 0.030 143,450.00 4,303.50
Mandor L.04 Org/Hari 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 58,153.50
B. BAHAN :
Balok 5/7 cm Kayu Kelas II - 0 0.0163 1,815,000.00 29,584.50
Paku 7 - 10 cm - Kg 0.250 21,450.00 5,362.50
JUMLAH HARGA BAHAN 34,947.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 93,100.50
E. Overhead & Profit 10% x D 9,310.05
F. Harga Satuan Pekerjaan(D + E) 102,410.55

Halaman-100
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.1.22 AHSP - A.4.6.1


KODE/ JENIS PEKERJAAN : Pemasangan Listplank Ukuran (3 x 30) cm, Kayu Kelas II
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.100 81,000.00 8,100.00
Tukang Kayu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 35,894.00
B. BAHAN :
Papan Kayu Kelas II - M3 0.011 1,815,000.00 19,965.00
Paku 5 dan 7 cm - Kg 0.050 23,400.00 1,170.00
JUMLAH HARGA BAHAN 21,135.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 57,029.00
E. Overhead & Profit 10% x D 5,702.90
F. Harga Satuan Pekerjaan(D + E) 62,731.90

Halaman-101
XII. AHSP - A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.1 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Kunci Tanam Antik
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.060 81,000.00 4,860.00
Tukang Kayu L.02 Org/Hari 0.600 122,000.00 73,200.00
Kepala Tukang L.03 Org/Hari 0.060 143,450.00 8,607.00
Mandor L.04 Org/Hari 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 86,982.00
B. BAHAN :
Kunci Tanam Antik - Bh 1.000 234,300.00 234,300.00
JUMLAH HARGA BAHAN 234,300.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 321,282.00
E. Overhead & Profit 10% x D 32,128.20
F. Harga Satuan Pekerjaan(D + E) 353,410.20

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.2 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Kunci Tanam Biasa 2 Slaag
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.010 81,000.00 810.00
Tukang Kayu L.02 Org/Hari 0.500 122,000.00 61,000.00
Kepala Tukang L.03 Org/Hari 0.050 143,450.00 7,172.50
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 69,507.50
B. BAHAN :
Kunci Tanam Kualitas Baik (Stainless) - Bh 1.000 180,000.00 180,000.00
JUMLAH HARGA BAHAN 180,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 249,507.50
E. Overhead & Profit 10% x D 24,950.75
F. Harga Satuan Pekerjaan(D + E) 274,458.25

Halaman-102
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.3 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Kunci Kamar Mandi
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.005 81,000.00 405.00
Tukang Kayu L.02 Org/Hari 0.500 122,000.00 61,000.00
Kepala Tukang L.03 Org/Hari 0.050 143,450.00 7,172.50
Mandor L.04 Org/Hari 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 68,892.50
B. BAHAN :
Kunci Pintu Bulat Ex. Muller - Bh 1.000 104,500.00 104,500.00
JUMLAH HARGA BAHAN 104,500.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 173,392.50
E. Overhead & Profit 10% x D 17,339.25
F. Harga Satuan Pekerjaan(D + E) 190,731.75

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.5 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Engsel Pintu
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.0008 105,000.00 84.00
JUMLAH TENAGA KERJA 21,750.75
B. BAHAN :
Engsel Pintu - Bh 1.000 17,500.00 17,500.00
JUMLAH HARGA BAHAN 17,500.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,250.75
E. Overhead & Profit 10% x D 3,925.08
F. Harga Satuan Pekerjaan(D + E) 43,175.83

Halaman-103
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.6 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Engsel Jendela
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.010 81,000.00 810.00
Tukang Kayu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.0005 105,000.00 52.50
JUMLAH TENAGA KERJA 14,497.00
B. BAHAN :
Engsel Jendela - Bh 1.000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 26,497.00
E. Overhead & Profit 10% x D 2,649.70
F. Harga Satuan Pekerjaan(D + E) 29,146.70

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.7 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Engsel Angin
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.100 81,000.00 8,100.00
Tukang Kayu L.02 Org/Hari 0.200 122,000.00 24,400.00
Kepala Tukang L.03 Org/Hari 0.020 143,450.00 2,869.00
Mandor L.04 Org/Hari 0.0005 105,000.00 52.50
JUMLAH TENAGA KERJA 35,421.50
B. BAHAN :
Engsel Angin - Bh 1.000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 47,421.50
E. Overhead & Profit 10% x D 4,742.15
F. Harga Satuan Pekerjaan(D + E) 52,163.65

Halaman-104
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.8 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Spring Knip Jendela
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 22,506.75
B. BAHAN :
Spring Knip - Bh 1.000 27,000.00 27,000.00
JUMLAH HARGA BAHAN 27,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 49,506.75
E. Overhead & Profit 10% x D 4,950.68
F. Harga Satuan Pekerjaan(D + E) 54,457.43

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.8.a AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Grendel Pintu
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 22,506.75
B. BAHAN :
Grendel Pintu - Bh 1.000 10,400.00 10,400.00
JUMLAH HARGA BAHAN 10,400.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 32,906.75
E. Overhead & Profit 10% x D 3,290.68
F. Harga Satuan Pekerjaan(D + E) 36,197.43

Halaman-105
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.8.b AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Grendel Jendela
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 22,506.75
B. BAHAN :
Grendel Jendela - Bh 1.000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 8,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 30,506.75
E. Overhead & Profit 10% x D 3,050.68
F. Harga Satuan Pekerjaan(D + E) 33,557.43

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.9 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Kait Angin
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 22,506.75
B. BAHAN :
Kait Angin - Bh 1.000 17,160.00 17,160.00
JUMLAH HARGA BAHAN 17,160.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,666.75
E. Overhead & Profit 10% x D 3,966.68
F. Harga Satuan Pekerjaan(D + E) 43,633.43

Halaman-106
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.9.a AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Handle Pintu dan Jendela Biasa
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 22,506.75
B. BAHAN :
Gagang Pintu dan Jendela - Bh 1.000 7,000.00 7,000.00
JUMLAH HARGA BAHAN 7,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 29,506.75
E. Overhead & Profit 10% x D 2,950.68
F. Harga Satuan Pekerjaan(D + E) 32,457.43

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.9.b AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Pemasangan Handle Pintu Stainless Steel 40 cm
SATUAN PEMBAYARAN : Set (2 Sisi Bidang Pintu)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.008 105,000.00 840.00
JUMLAH TENAGA KERJA 22,506.75
B. BAHAN :
Handle Pintu Stailess Steel 40 cm - Set 1.000 262,500.00 262,500.00
JUMLAH HARGA BAHAN 262,500.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 285,006.75
E. Overhead & Profit 10% x D 28,500.68
F. Harga Satuan Pekerjaan(D + E) 313,507.43

Halaman-107
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.16 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Memasang Kaca Bening, Tebal 3 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.0008 105,000.00 84.00
JUMLAH TENAGA KERJA 21,750.75
B. BAHAN :
Kaca Bening Tebal 3 mm - m2 1.100 108,000.00 118,800.00
Sealant - Kg 0.050 25,000.00 1,250.00
JUMLAH HARGA BAHAN 120,050.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 141,800.75
E. Overhead & Profit 10% x D 14,180.08
F. Harga Satuan Pekerjaan(D + E) 155,980.83

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.17 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Memasang Kaca Bening, Tebal 5 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.015 81,000.00 1,215.00
Tukang Kayu L.02 Org/Hari 0.150 122,000.00 18,300.00
Kepala Tukang L.03 Org/Hari 0.015 143,450.00 2,151.75
Mandor L.04 Org/Hari 0.0008 105,000.00 84.00
JUMLAH TENAGA KERJA 21,750.75
B. BAHAN :
Kaca Bening Tebal 5 mm - m2 1.100 185,600.00 204,160.00
Sealant - Kg 0.050 25,000.00 1,250.00
JUMLAH HARGA BAHAN 205,410.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 227,160.75
E. Overhead & Profit 10% x D 22,716.08
F. Harga Satuan Pekerjaan(D + E) 249,876.83

Halaman-108
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.6.2.18 AHSP - A.4.6.2


KODE/ JENIS PEKERJAAN : Memasang Kaca Bening, Tebal 8 mm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.017 81,000.00 1,377.00
Tukang Kayu L.02 Org/Hari 0.170 122,000.00 20,740.00
Kepala Tukang L.03 Org/Hari 0.017 143,450.00 2,438.65
Mandor L.04 Org/Hari 0.0009 105,000.00 94.50
JUMLAH TENAGA KERJA 24,650.15
B. BAHAN :
Kaca Bening Tebal 8 mm - m2 1.100 194,250.00 213,675.00
Sealant - Kg 0.050 25,000.00 1,250.00
JUMLAH HARGA BAHAN 214,925.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 239,575.15
E. Overhead & Profit 10% x D 23,957.52
F. Harga Satuan Pekerjaan(D + E) 263,532.67

Halaman-109
XIV. AHSP - A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.1 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kloset Duduk Monoblock
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 3.300 81,000.00 267,300.00
Tukang Pipa L.02 Org/Hari 1.100 122,000.00 134,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.160 105,000.00 16,800.00
JUMLAH TENAGA KERJA 419,734.50
B. BAHAN :
Kloset Duduk Monoblock (Komplit) - Unit 1.000 1,642,400.00 1,642,400.00
Perlengkapan 6 % Harga Kloset - Ls 0.060 98,544.00 5,912.64
JUMLAH HARGA BAHAN 1,648,312.64
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 2,068,047.14
E. Overhead & Profit 10% x D 206,804.71
F. Harga Satuan Pekerjaan(D + E) 2,274,851.85

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.14 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Floor Drain
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.010 81,000.00 810.00
Tukang Pipa L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 14,969.50
B. BAHAN :
Floor Drain Stainless - Bh 1.000 35,200.00 35,200.00
JUMLAH HARGA BAHAN 35,200.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 50,169.50
E. Overhead & Profit 10% x D 5,016.95
F. Harga Satuan Pekerjaan(D + E) 55,186.45

Halaman-110
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.18 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Pipa GIP 1/2"
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.054 81,000.00 4,374.00
Tukang Pipa L.02 Org/Hari 0.090 122,000.00 10,980.00
Kepala Tukang L.03 Org/Hari 0.009 143,450.00 1,291.05
Mandor L.04 Org/Hari 0.027 105,000.00 2,835.00
JUMLAH TENAGA KERJA 19,480.05
B. BAHAN :
Pipa Gip 1/2" - M1 1.200 13,016.67 15,620.00
Perlengkapan 35% Harga Pipa - Ls 0.350 5,467.00 1,913.45
JUMLAH HARGA BAHAN 17,533.45
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 37,013.50
E. Overhead & Profit 10% x D 3,701.35
F. Harga Satuan Pekerjaan(D + E) 40,714.85

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.19 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Kran ø 1/2" atau ø 3/4"
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.010 81,000.00 810.00
Tukang Pipa L.02 Org/Hari 0.400 122,000.00 48,800.00
Kepala Tukang L.03 Org/Hari 0.040 143,450.00 5,738.00
Mandor L.04 Org/Hari 0.005 105,000.00 525.00
JUMLAH TENAGA KERJA 55,873.00
B. BAHAN :
Kran Air Stainless - Buah 1.000 35,750.00 35,750.00
Seal Tape - Bh 0.0025 3,300.00 8.25
JUMLAH HARGA BAHAN 35,758.25
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 91,631.25
E. Overhead & Profit 10% x D 9,163.13
F. Harga Satuan Pekerjaan(D + E) 100,794.38

Halaman-111
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.31 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Pipa PVC Type AW Diameter 2,5"
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.081 81,000.00 6,561.00
Tukang Pipa L.02 Org/Hari 0.135 122,000.00 16,470.00
Kepala Tukang L.03 Org/Hari 0.0135 143,450.00 1,936.58
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 25,387.58
B. BAHAN :
Pipa PVC 2,5" - M1 1.200 26,785.00 32,142.00
Perlengkapan 35% Harga Pipa - Ls 0.350 11,249.70 3,937.40
JUMLAH HARGA BAHAN 36,079.40
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 61,466.97
E. Overhead & Profit 10% x D 6,146.70
F. Harga Satuan Pekerjaan(D + E) 67,613.67

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.31 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Pipa PVC Type AW Diameter 3"
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.081 81,000.00 6,561.00
Tukang Pipa L.02 Org/Hari 0.135 122,000.00 16,470.00
Kepala Tukang L.03 Org/Hari 0.0135 143,450.00 1,936.58
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 25,387.58
B. BAHAN :
Pipa PVC 3" - M1 1.200 40,777.00 48,932.40
Perlengkapan 35% Harga Pipa - Ls 0.350 17,126.34 5,994.22
JUMLAH HARGA BAHAN 54,926.62
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 80,314.19
E. Overhead & Profit 10% x D 8,031.42
F. Harga Satuan Pekerjaan(D + E) 88,345.61

Halaman-112
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.5.1.1.32 AHSP - A.5.1.1


KODE/ JENIS PEKERJAAN : Pemasangan Pipa PVC Type AW Diameter 4"
SATUAN PEMBAYARAN : M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.081 81,000.00 6,561.00
Tukang Batu L.02 Org/Hari 0.135 122,000.00 16,470.00
Kepala Tukang L.03 Org/Hari 0.0135 143,450.00 1,936.58
Mandor L.04 Org/Hari 0.004 105,000.00 420.00
JUMLAH TENAGA KERJA 25,387.58
B. BAHAN :
Pipa PVC 4" - M1 1.200 55,352.00 66,422.40
Perlengkapan 35% Harga Pipa - Ls 0.350 23,247.84 8,136.74
JUMLAH HARGA BAHAN 74,559.14
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 99,946.72
E. Overhead & Profit 10% x D 9,994.67
F. Harga Satuan Pekerjaan(D + E) 109,941.39

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 09 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Memasang Shower Basuh (Pelengkap Kloset Monoblock)
SATUAN PEMBAYARAN : Buah

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.010 81,000.00 810.00
Tukang Pipa L.02 Org/Hari 0.005 122,000.00 610.00
Kepala Tukang L.03 Org/Hari 0.100 143,450.00 14,345.00
Mandor L.04 Org/Hari 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 16,815.00
B. BAHAN :
Shower Basuh - Bh 1.000 86,250.00 86,250.00
Seal Tape - Bh 0.0025 3,300.00 8.25
JUMLAH HARGA BAHAN 86,258.25
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 103,073.25
E. Overhead & Profit 10% x D 10,307.33
F. Harga Satuan Pekerjaan(D + E) 113,380.58

Halaman-113
XIII. AHSP - A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : AHSP - A.4.7.1.10.a AHSP - A.4.7.1


KODE/ JENIS PEKERJAAN : Pengecatan Tembok Baru (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup), Exterior
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.020 81,000.00 1,620.00
Tukang Kayu L.02 Org/Hari 0.063 122,000.00 7,686.00
Kepala Tukang L.03 Org/Hari 0.0063 143,450.00 903.74
Mandor L.04 Org/Hari 0.003 105,000.00 315.00
JUMLAH TENAGA KERJA 10,524.74
B. BAHAN :
Plamur - Kg 0.100 32,670.00 3,267.00
Cat Dasar Setara Metrolite - Kg 0.100 23,550.00 2,355.00
Cat Penutup Setara Metrolite - Kg 0.260 23,550.00 6,123.00
JUMLAH HARGA BAHAN 11,745.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 22,269.74
E. Overhead & Profit 10% x D 2,226.97
F. Harga Satuan Pekerjaan(D + E) 24,496.71

Halaman-114
XV. ANL. TERAPAN HARGA SATUAN PEKERJAAN TAMBAHAN

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 01 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pemasangan Lantai Keramik Ukuran 25 cm x 40 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.250 81,000.00 20,250.00
Tukang Batu L.02 Org/Hari 0.125 122,000.00 15,250.00
Kepala Tukang L.03 Org/Hari 0.013 143,450.00 1,864.85
Mandor L.04 Org/Hari 0.013 105,000.00 1,365.00
JUMLAH TENAGA KERJA 38,729.85
B. BAHAN :
Keramik Ukuran 25 cm x 40 cm - Buah 10.000 7,500.00 75,000.00
Semen Portland - Kg 9.300 1,631.12 15,169.42
Semen Warna - Kg 1.940 3,000.00 5,820.00
Pasir Pasang - M3 0.018 267,000.00 4,806.00
JUMLAH HARGA BAHAN 100,795.42
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 139,525.27
E. Overhead & Profit 10% x D 13,952.53
F. Harga Satuan Pekerjaan(D + E) 153,477.79

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Terapan - 02 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pemasangan Dinding Keramik Ukuran 25 cm x 40 cm
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.600 81,000.00 48,600.00
Tukang Batu L.02 Org/Hari 0.450 122,000.00 54,900.00
Kepala Tukang L.03 Org/Hari 0.035 143,450.00 5,020.75
Mandor L.04 Org/Hari 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 111,670.75
B. BAHAN :
Keramik Ukuran 25 cm x 40 cm - Buah 10.000 7,500.00 75,000.00
Semen Portland - Kg 9.300 1,631.12 15,169.42
Semen Warna - Kg 1.940 3,000.00 5,820.00
Pasir Pasang - M3 0.018 267,000.00 4,806.00
JUMLAH HARGA BAHAN 100,795.42
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 212,466.17
E. Overhead & Profit 10% x D 21,246.62
F. Harga Satuan Pekerjaan(D + E) 233,712.78

Halaman-115
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Terapan AHSP - A.4.4.2.27 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pemasangan Acian Dinding 1 PC : 7 KPR
SATUAN PEMBAYARAN : M2

URAIAN KODE HARGA SATUAN JUMLAH HARGA


No. SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 81,000.00 16,200.00
Tukang Batu L.02 Org/Hari 0.100 122,000.00 12,200.00
Kepala Tukang L.03 Org/Hari 0.010 143,450.00 1,434.50
Mandor L.04 Org/Hari 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 30,884.50
B. BAHAN :
Semen Portland - Kg 0.800 1,631.12 1,304.90
Kapur Mil - Kg 0.070 1,700.00 119.00
JUMLAH HARGA BAHAN 1,423.90
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 32,308.40
E. Overhead & Profit 10% x D 3,230.84
F. Harga Satuan Pekerjaan(D + E) 35,539.24

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 04 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pengecatan Pelapis Kedap Air (Water Proofing)
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.020 81,000.00 1,620.00
Tukang Kayu L.02 Org/Hari 0.063 122,000.00 7,686.00
Kepala Tukang L.03 Org/Hari 0.0063 143,450.00 903.74
Mandor L.04 Org/Hari 0.0025 105,000.00 262.50
JUMLAH TENAGA KERJA 10,472.24
B. BAHAN :
Polimer Mortar - Kg 2.000 30,000.00 60,000.00
JUMLAH HARGA BAHAN 60,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 70,472.24
E. Overhead & Profit 10% x D 7,047.22
F. Harga Satuan Pekerjaan(D + E) 77,519.46

Halaman-116
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 01 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pemasangan Rangka Atap Baja Ringan
SATUAN PEMBAYARAN : M2

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.180 81,000.00 14,580.00
Tukang Alumunium L.02 Org/Hari 0.240 122,000.00 29,280.00
Kepala Tukang L.03 Org/Hari 0.018 143,450.00 2,582.10
Mandor L.04 Org/Hari 0.024 105,000.00 2,520.00
JUMLAH TENAGA KERJA 48,962.10
B. BAHAN :
Cord - Kanal C Tebal = 1 mm - Btg 0.367 87,000.00 31,929.00
Reng - Kanal U Tebal = 0,6 mm - Btg 0.733 55,000.00 40,315.00
L. Braket 1,5 mm - Bh 0.025 2,000.00 50.00
Screw 12 - 14 x 20 - Bh 2.000 980.00 1,960.00
Screw 10 - 16 x 16 - Bh 8.000 700.00 5,600.00
JUMLAH HARGA BAHAN 79,854.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 128,816.10
E. Overhead & Profit 10% x D 12,881.61
F. Harga Satuan Pekerjaan(D + E) 141,697.71

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 06 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pekerjaan Kusen Pintu dan Jendela
SATUAN PEMBAYARAN : Unit

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
1. Pekerjaan Kusen Pintu Kaca + Jendela Kaca Mati (TYPE PJ) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Pintu dan Kusen Jendela, Kayu Kelas II A.4.6.1.1 M3 0.147 5,714,865.75 840,085.27
Daun Pintu Kaca A.4.6.1.6 M2 3.432 Err:509 Err:509
Memasang Kaca Bening Pintu, Tebal 8 mm A.4.6.2.18 M2 2.364 263,532.67 622,991.22
Memasang Kaca Bening Jendela Mati, Tebal 5 mm A.4.6.2.17 M2 2.884 249,876.83 720,644.76
Kunci Pintu Tanam Ex. Muller A.4.6.2.2.b Set 1.000 180,000.00 180,000.00
Handle Pintu Stainless Steel 40 Cm A.4.6.2.9.d Set 2.000 313,507.43 627,014.85
Engsel Pintu A.4.6.2.5 Bh 6.000 43,175.83 259,054.95
Grendel Pintu A.4.6.2.8.a Bh 2.000 36,197.43 72,394.85
JUMLAH HARGA PER UNIT Err:509
2. Pekerjaan Kusen Pintu Panil Kaca (TYPE P1) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Pintu, Kayu Kelas II A.4.6.1.1 M3 #REF! 5,714,865.75 #REF!
Daun Pintu Panil A.4.6.1.5 M2 #REF! 635,019.00 #REF!
Kunci Pintu Tanam Ex. Muller A.4.6.2.2.b Set 1.000 180,000.00 180,000.00
Handle Pintu Stainless Steel 40 Cm A.4.6.2.9.d Set 1.000 313,507.43 313,507.43
Engsel Pintu A.4.6.2.5 Bh 6.000 43,175.83 259,054.95
Grendel Pintu A.4.6.2.9 Bh 2.000 43,633.43 87,266.85
JUMLAH HARGA PER UNIT #REF!

Halaman-117
3. Pekerjaan Kusen Pintu Panil Kaca (TYPE P2) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Pintu, Kayu Kelas II A.4.6.1.1 M3 #REF! 5,714,865.75 #REF!
Daun Pintu Panil A.4.6.1.5 M2 #REF! 635,019.00 #REF!
Kunci Pintu Tanam 2 Slaag A.4.6.2.2 Bh 1.000 274,458.25 274,458.25
Handle Pintu Stainless Steel 40 Cm A.4.6.2.9.d Set 1.000 313,507.43 313,507.43
Engsel Pintu A.4.6.2.5 Bh 3.000 43,175.83 129,527.48
Grendel Pintu A.4.6.2.9 Bh 2.000 43,633.43 87,266.85
JUMLAH HARGA PER UNIT #REF!
4. Pekerjaan Kusen Pintu Panil (TYPE P3) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Pintu, Kayu Kelas II A.4.6.1.1 M3 0.056 5,714,865.75 320,032.48
Daun Pintu Panil A.4.6.1.5 M2 1.730 635,019.00 1,098,582.87
Daun Ventilasi Kaca A.4.6.1.6 M2 0.426 Err:509 Err:509
Memasang Kaca Bening Ventilasi, Tebal 5 mm A.4.6.2.17 M2 0.198 249,876.83 49,475.61
Kunci Pintu Tanam 2 Slaag A.4.6.2.2 Bh 1.000 274,458.25 274,458.25
Engsel Pintu A.4.6.2.5 Bh 3.000 43,175.83 129,527.48
Engsel Ventilasi A.4.6.2.6 Bh 2.000 29,146.70 58,293.40
Grendel Ventilasi A.4.6.2.8.b Bh 1.000 33,557.43 33,557.43
Kait Angin Ventilasi A.4.6.2.9 Bh 2.000 43,633.43 87,266.85
Gagang/ Handel Ventilasi A.4.6.2.9.b Bh 1.000 32,457.43 32,457.43
JUMLAH HARGA PER UNIT Err:509
5. Pekerjaan Kusen Pintu Panil Lapis Kulit Jeruk (TYPE P4) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Pintu, Kayu Kelas II A.4.6.1.1 M3 0.046 5,714,865.75 262,883.82
Daun Pintu Panil Lapis Kulit Jeruk A.4.6.1.5.a M2 1.519 Err:509 Err:509
Kunci Pintu Tanam 2 Slaag A.4.6.2.2 Bh 1.000 274,458.25 274,458.25
Engsel Pintu A.4.6.2.5 Bh 3.000 43,175.83 129,527.48
JUMLAH HARGA PER UNIT Err:509
6. Pekerjaan Kusen Jendela Bingkai Kaca (TYPE J1) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Jendela, Kayu Kelas II A.4.6.1.1 M3 #REF! 5,714,865.75 #REF!
Daun Jendela Kaca A.4.6.1.6 M2 #REF! Err:509 #REF!
Memasang Kaca Bening Jendela, Tebal 5 mm A.4.6.2.17 M2 #REF! 249,876.83 #REF!

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
Engsel Jendela A.4.6.2.6 Bh 2.000 29,146.70 58,293.40
Grendel Jendela A.4.6.2.8.b Bh 1.000 33,557.43 33,557.43
Kait Angin Jendela A.4.6.2.9 Bh 2.000 43,633.43 87,266.85
Gagang/ Handel Jendela A.4.6.2.9.b Bh 1.000 32,457.43 32,457.43
JUMLAH HARGA PER UNIT #REF!

Halaman-118
7. Pekerjaan Kusen Jendela Bingkai Kaca (TYPE J2) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Jendela, Kayu Kelas II A.4.6.1.1 M3 0.080 5,714,865.75 457,189.26
Daun Jendela Kaca A.4.6.1.6 M2 1.757 Err:509 Err:509
Daun Ventilasi Kaca A.4.6.1.6 M2 0.749 Err:509 Err:509
Memasang Kaca Bening Jendela, Tebal 5 mm A.4.6.2.17 M2 1.187 249,876.83 296,603.79
Memasang Kaca Bening Ventilasi, Tebal 5 mm A.4.6.2.17 M2 0.403 249,876.83 100,700.36
Engsel Jendela A.4.6.2.6 Bh 4.000 29,146.70 116,586.80
Engsel Ventilasi A.4.6.2.6 Bh 4.000 29,146.70 116,586.80
Grendel Jendela A.4.6.2.8.b Bh 2.000 33,557.43 67,114.85
Grendel Ventilasi A.4.6.2.8.b Bh 2.000 33,557.43 67,114.85
Kait Angin Jendela A.4.6.2.9 Bh 4.000 43,633.43 174,533.70
Kait Angin Ventilasi A.4.6.2.9 Bh 4.000 43,633.43 174,533.70
Gagang/ Handel Jendela A.4.6.2.9.b Bh 2.000 32,457.43 64,914.85
Gagang/ Handel Ventilasi A.4.6.2.9.b Bh 2.000 32,457.43 64,914.85
JUMLAH HARGA PER UNIT Err:509
8. Pekerjaan Kusen Jendela Mati (TYPE V1) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Jendela, Kayu Kelas II A.4.6.1.1 M3 #REF! 5,714,865.75 #REF!
Memasang Kaca Bening, Tebal 5 mm A.4.6.2.17 M2 #REF! 249,876.83 #REF!
JUMLAH HARGA PER UNIT #REF!
9. Pekerjaan Kusen Jendela Mati (TYPE V2) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Jendela, Kayu Kelas II A.4.6.1.1 M3 #REF! 5,714,865.75 #REF!
Memasang Kaca Bening, Tebal 5 mm A.4.6.2.17 M2 #REF! 249,876.83 #REF!
JUMLAH HARGA PER UNIT #REF!
10. Pekerjaan Kusen Ventilasi (TYPE V3) Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Ventilasi, Kayu Kelas II A.4.6.1.1 M3 #REF! 5,714,865.75 #REF!
Memasang Kaca Bening, Tebal 5 mm A.4.6.2.17 M2 #REF! 249,876.83 #REF!
JUMLAH HARGA PER UNIT #REF!
11. Pekerjaan Kusen Ventilasi Kisi-kisi Kap, Include Terpasang - Lihat Analisa + Gbr. Detail
Kusen Ventilasi, Kayu Kelas II A.4.6.1.1 M3 0.151 5,714,865.75 862,944.73
Jalusi Papan, Kayu Kelas II A.4.6.1.10 M2 1.872 Err:509 Err:509
Memasang Kaca Bening, Tebal 5 mm A.4.6.2.17 M2 1.738 249,876.83 434,285.92
JUMLAH HARGA PER UNIT Err:509

Halaman-119
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 07 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pemasangan Saklar Lampu
SATUAN PEMBAYARAN : Titik

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
1. Pemasangan Saklar Engkel
A. TENAGA :
Tukang Instalasi Listrik L.02 Ls 1.000 5,000.00 5,000.00
JUMLAH TENAGA KERJA 5,000.00
B. BAHAN :
Saklar Tunggal - Bh 1.000 28,750.00 28,750.00
JUMLAH HARGA BAHAN 28,750.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 33,750.00
E. Overhead & Profit 10% x D 3,375.00
F. Harga Satuan Pekerjaan(D + E) 37,125.00
2. Pemasangan Saklar Double
A. TENAGA :
Tukang Instalasi Listrik L.02 Ls 1.000 5,000.00 5,000.00
JUMLAH TENAGA KERJA 5,000.00
B. BAHAN :
Saklar Seri - Bh 1.000 38,500.00 38,500.00
JUMLAH HARGA BAHAN 38,500.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 43,500.00
E. Overhead & Profit 10% x D 4,350.00
F. Harga Satuan Pekerjaan(D + E) 47,850.00
3. Pemasangan Saklar Triple
A. TENAGA :
Tukang Instalasi Listrik L.02 Ls 1.000 5,000.00 5,000.00
JUMLAH TENAGA KERJA 5,000.00
B. BAHAN :
Saklar Seri - Bh 1.000 38,500.00 38,500.00
JUMLAH HARGA BAHAN 38,500.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 43,500.00
E. Overhead & Profit 10% x D 4,350.00
F. Harga Satuan Pekerjaan(D + E) 47,850.00

Halaman-120
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : Analisa Praktis - 08 ANALISA TERAPAN


KODE/ JENIS PEKERJAAN : Pemasangan Stop Kontak
SATUAN PEMBAYARAN : Titik

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
1. Pemasangan Stop Kontak Daya 200 Watt 2 Phase
A. TENAGA :
Tukang Instalasi Listrik L.02 Ls 1.000 12,000.00 12,000.00
JUMLAH TENAGA KERJA 12,000.00
B. BAHAN :
Stop Kontak Daya 200 Watt 2 Phase - Bh 1.000 30,800.00 30,800.00
JUMLAH HARGA BAHAN 30,800.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 42,800.00
E. Overhead & Profit 10% x D 4,280.00
F. Harga Satuan Pekerjaan(D + E) 47,080.00
2. Pemasangan Stop Kontak AC Daya 200 Watt 1 Phase
A. TENAGA :
Tukang Instalasi Listrik L.02 Ls 1.000 15,000.00 15,000.00
JUMLAH TENAGA KERJA 15,000.00
B. BAHAN :
Stop Kontak AC Daya 200 Watt 1 Phase - Bh 1.000 25,850.00 25,850.00
JUMLAH HARGA BAHAN 25,850.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 40,850.00
E. Overhead & Profit 10% x D 4,085.00
F. Harga Satuan Pekerjaan(D + E) 44,935.00

Luwuk, Maret 2016


Di Periksa : Dibuat Oleh :
KEPALA SEKSI BANGUNAN GEDUNG STAF BIDANG CIPTA KARYA

SURADJONO WAWAN G SAIDAN


NIP. 19621107 198703 1 014 NIP. 19750824 200902 1 002

MENYETUJUI :
KEPALA BIDANG CIPTA KARYA
DINAS PEKERJAAN UMUM KAB. BANGGAI

SYAHBUDIN DAYANUN, ST, M.Eng


NIP. 19750614 200604 1 017

Halaman-121
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : A.4.7.1.15

KODE/ JENIS PEKERJAAN : Pemasangan 1 M² Wallpaper


SATUAN PEMBAYARAN : M2

No. URAIAN KODE SATUAN KOEFISIEN


1 2 3 4 5
A. TENAGA :
Pekerja L.01 Org/Hari 0.020
Tukang Batu L.02 Org/Hari 0.200
Kepala Tukang L.03 Org/Hari 0.020
Mandor L.04 Org/Hari 0.003
JUMLAH TENAGA KERJA
B. BAHAN :
Wall Paper - m² 1.200
Lem - Kg 0.200
JUMLAH HARGA BAHAN
C. PERALATAN :
- - -
JUMLAH HARGA ALAT
D. Jumlah (A+B+C)
E. Overhead & Profit 10% x D
F. Harga Satuan Pekerjaan(D + E)

ITEM PEMBAYARAN NO. : An - Ter


KODE/ JENIS PEKERJAAN : Pemasangan 1 m2 dinding Gypsum Board 9 mm + Wallpaper
SATUAN PEMBAYARAN : M2

No. URAIAN KODE SATUAN KOEFISIEN


1 2 3 4 5
A. TENAGA :
Pekerja L.01 Org/Hari 0.020
Tukang Batu L.02 Org/Hari 0.200
Kepala Tukang L.03 Org/Hari 0.020
Mandor L.04 Org/Hari 0.003
JUMLAH TENAGA KERJA
B. BAHAN :
Wall Paper - m² 1.200
Lem - Kg 0.200
JUMLAH HARGA BAHAN
C. PERALATAN :
- - -
JUMLAH HARGA ALAT
D. Jumlah (A+B+C)
E. Overhead & Profit 10% x D
F. Harga Satuan Pekerjaan(D + E)
NTUK
NG HARGA SATUAN

AHSP - A.4.7.1.15 An. Ter. Pemasangan 1 m2 dinding Gypsum Board 9 mm + Wallpaper

No. Uraian Kode Satuan Koefesien

A TENAGA
Pekerja L.01 Oh 0.5000
HARGA SATUAN JUMLAH HARGA Tukang kayu L.02 Oh 0.1700
(Rp). (Rp). Kepala tukan L.03 Oh 0.0170
6 7 = (5x6) Mandor L.04 Oh 0.0040
JUMLAH TENAGA KERJA
81,000.00 1,620.00 B BAHAN
122,000.00 24,400.00 Wallpaper, lebar 50 cm m' 2.2000
143,450.00 2,869.00 Lem Wallpaper Kg 0.2500
105,000.00 262.50 Gypsumboard 120x240, t Lbr 0.3640
JUMLAH TENAGA KERJA 29,151.50 Skrup gypsum bh 21.0000
Textile tape rol 0.0240
75,000.00 90,000.00 Compound zak 0.0200
20,400.00 4,080.00 Amplas lbr 0.1000
JUMLAH HARGA BAHAN 94,080.00 JUMLAH HARGA BAHAN
C PERALATAN
- -
JUMLAH HARGA ALAT - JUMLAH HARGA PERALATAN
123,231.50 D. Jumlah ( A + B + C )
12,323.15 E. Overheead & P 0% x D
135,554.65 F. Harga Satuan Pekerjaan

An. Ter. Pemasangan 1 m2 dinding plywood 9mm + HPL (High Pressure Laminate

No. Uraian Kode Satuan Koefesien

An - Ter A TENAGA
Pekerja L.01 Oh 0.5000
Tukang kayu L.02 Oh 0.1700
Kepala tukan L.03 Oh 0.0170
HARGA SATUAN JUMLAH HARGA Mandor L.04 Oh 0.0040
(Rp). (Rp). JUMLAH TENAGA KERJA
6 7 = (5x6) B BAHAN
HPL (High Pressure Lamina Lbr 0.3360
81,000.00 1,620.00 Lem HPL Kg 0.2500
122,000.00 24,400.00 Plywood 122 Cm x 244 C Lbr 0.3360
143,450.00 2,869.00 Paku Sekrup Dos 0.0300
105,000.00 262.50 JUMLAH HARGA BAHAN
JUMLAH TENAGA KERJA 29,151.50 C PERALATAN
98,500.00 118,200.00 JUMLAH HARGA PERALATAN
- - D. Jumlah ( A + B + C )
JUMLAH HARGA BAHAN 118,200.00 E. Overheead & P 0% x D
F. Harga Satuan Pekerjaan
- -
JUMLAH HARGA ALAT -
147,351.50
14,735.15
162,086.65
ard 9 mm + Wallpaper

Jumlah
Harga Satuan (Rp.)
Harga (Rp.)

81,000.00 40,500.00
125,000.00 21,250.00
148,500.00 2,524.50
115,000.00 460.00
ENAGA KERJA 64,734.50

75,000.00 165,000.00
20,400.00 5,100.00
106,100.00 38,620.40
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
ARGA BAHAN #NAME?

ARGA PERALATAN
#NAME?
#NAME?
#NAME?

mm + HPL (High Pressure Laminateed)

Jumlah
Harga Satuan (Rp.)
Harga (Rp.)

81,000.00 40,500.00
125,000.00 21,250.00
148,500.00 2,524.50
115,000.00 460.00
ENAGA KERJA 64,734.50

#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
ARGA BAHAN #NAME?
ARGA PERALATAN
#NAME?
#NAME?
#NAME?
DAFTAR HARGA SATUAN UPAH DAN BAHAN

Halaman - 01
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
I. UPAH KERJA
1 Mandor Hari 105,000.00 15,000.00
2 Kepala Tukang Hari 143,450.00 20,492.86
3 Tukang Kayu, Batu, Besi, Cat Hari 122,000.00 17,428.57
4 Pekerja Hari 81,000.00 11,571.43

II. BAHAN MATERIAL

1. Tanah dan Pasir


Pasir Urug M3 183,150.00
Pasir Pasang M3 267,000.00
Pasir Beton/ Cor M3 267,000.00 190.714 /Kg
Sirtu M3 233,300.00
Pasir Plester M3 267,000.00
Tanah Timbunan M3 120,000.00
Tanah Humus (Tanah Hitam) M3 200,000.00

2. Kerikil
Kerikil Split M3 300,000.00 222.222 /Kg
Kerikil Sungai Pilihan/ Koral M3 267,000.00
Kerikil Sungai Tak Tersaring M3 233,300.00
Batu Pecah 5 - 7 M3 300,000.00
Batu Pecah 3 - 5 M3 300,000.00
Batu Pecah 2 - 3 M3 300,000.00
Batu Pecah 1 - 2 M3 300,000.00
Batu Pecah 0,5 - 1 Cm Spilt M3 300,000.00

3. Batu - Batuan
Batu Utuh, Batu Kali, Batu Gunung M3 267,000.00
Batu Karang M3 200,000.00
Batu Alam M3 250,000.00
Batu Sikat Motif Besar/ Kecil ktg 30 X 50 (M1) 150,000.00
Batu Alam Mega Bendung m2 250,000.00

4. Batu Cetak :
Batu Bata Ukuran 5 x 11 x 22 cm Bh 800.00
Batu Bata Ukuran 5 x 9 x 22 cm Bh 600.00
Batu Bata Ukuran 5 x 7 x 22 cm Bh 500.00
Batako Ukuran 16 x 40 x 10 Bh 4,000.00
Paving Block Kualitas I M2 96,050.00 2,668.06 Bh
Profil Beton Jadi 30 cm M1 250,000.00 700 Bh
Paving Block Segi Enam Tebal 8 cm K-250 M2 135,000.00
Paving Block Tebal 8 cm, mutu K-225 m2 125,000.00
bh 2,500.00

III. BAHAN BANGUNAN

1. Kapur
Kapur Pasang (Mil) Kg 1,700.00 85,000 Zak
Kapur Bakar Kg 1,350.00 120,000

2. Semen
Semen Pc (50 Kg) Zak 81,556.00 1,631 /Kg
Semen Warna/ Putih Kg 3,000.00 108,000 /Zak
Nat (Mortar Flex) Kg 12,000.00
Perekat Bata Ringan Lemkra LBM - 116 Zak 185,000.00 4,625
Perekat Bata Ringan MU - 380 - 40 Kg/Zak Zak 185,000.00 4,625
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
3. Bahan Atap
Seng Gelombang BJLS 0.20 Lbr 48,750.00
Seng Gelombang BJLS 0.18 Lbr 40,600.00
Genteng Metal 0,800 x 0,770 - T= 0,25 mm Lbr 55,000.00
Genteng Metal (Sakura Roof) 0,3 mm Lbr 31,200.00
Metal Zincalume`(Soka Jempol 0,22) 74 x 160 cm Lbr 85,000.00
Atap Galvalum Spandeck Lbr 49,500.00
Atap galvanis (Spandex Tebal 0,3 mm) M1 62,500.00
Polycarbonate Twinlite 2,1mx11,8m Lbr 2,300,000.00
4. Bahan Bubungan/ Nok
Seng Plat Lebar 90 Cm M1 30,000.00
Seng Plat Lebar 45 Cm M1 19,500.00
Seng Plat Lebar 30 Cm M1 15,000.00
Genteng Metal (Multi Roof) 0,3 mm Lbr 32,000.00
Genteng Metal (Sakura Roof) 0,25 mm Lbr 31,000.00
Metal Zincalume 0,25 mm Lbr 32,000.00
5. Bahan Kayu
Balok 6/16 x 4 m (Kayu Kelas I) M3 2,617,560.00
Balok 6/16 x 4 m (Kayu Kelas II) M3 1,815,000.00
Balok 8/12 x 4 m (Kayu Kelas II) M3 1,815,000.00
Balok 6/10 x 4 m (Kayu Kelas II) M3 1,815,000.00
Balok 5/7 x 4 m (Kayu Kelas II) M3 1,815,000.00
Balok 5/7 x 4 m (Kayu Kelas III) M3 1,573,000.00
Reng 2/3 x 4 m (Kayu Kelas II) M3 1,815,000.00
Kayu Bakesting (Kayu Kelas III) M3 1,573,000.00
Papan Palapi M3 1,960,200.00
Papan (Kayu Kelas II) M3 1,815,000.00
Papan Mall M3 1,573,000.00
Papan Lembar Seri 8 Cm Lbr 29,040.00
Papan Lembar Seri 10 Cm Lbr 31,040.00
List Profil Kayu 10 Cm Btg 44,600.00 11,150.00 /M1
List Profil Kayu 3 Cm Btg 25,000.00 6,250.00 /M1
List Profil Kayu 5 Cm Btg 26,900.00 6,725.00 /M1
Listplank Ornament Jadi Bh 10,000.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' Btg 8,000.00
Gymfloor M2 300,800.00
Penjaga Jarak Bekisting/ Spacer Buah 10,000.00
Bambu

7. Bahan Lantai dan Dinding/ Keramik


Tegel Keramik Uk. 10 x 20 Cm Dos 68,000.00 1,283.02 /Bh
Tegel Keramik Uk. 10 x 30 Cm Dos 60,500.00 1,769.17 /Bh
Tegel Keramik Uk. 10 x 40 Cm Dos 55,000.00 2,828.05 /Bh
Tegel Keramik Uk. 20 x 20 Cm Dos 64,800.00 2,445.28 /Bh
Tegel Wafel Uk. 20 x 20 Cm Dos 61,600.00 2,464.00 /Bh
Tegel Keramik Uk. 20 x 25 Cm Dos 75,000.00 3,750.00 /Bh
Tegel Keramik Uk. 25 x 40 Cm Dos 75,000.00 7,500.00 /Bh
Tegel Keramik Uk. 20 x 40 Cm Dos 75,000.00 6,000.00 /Bh
Tegel Keramik Uk. 30 x 30 Cm Dos 63,000.00 5,307.50 /Bh
Tegel Keramik Uk. 40 x 40 Cm Dos 75,000.00 11,312.22 /Bh
Tegel Keramik Uk. 40 x 40 Cm (Kasar) Dos 115,000.00 17,345.40 /Bh
Tegel Keramik Uk. 60 x 60 Cm Dos 168,000.00 54,193.55 /Bh
Keramik Granit Tile Uk. 60 x 60 Cm (Colosseum) Dos 220,500.00 71,129.03 /Bh
Keramik Granit Tile Uk. 60 x 60 Cm (China) Dos 213,600.00 68,903.23 /Bh
Keramik Granit Tile Uk. 80 x 80 Cm Dos 229,600.00 82,000.00 /Bh
Plint Granit Tile Uk. 10 x 60 Cm Bh 35,200.00
Plint Granit Tile Uk. 10 x 40 Cm Bh 31,350.00
Plint Keramik Uk. 10 x 40 Cm Bh 29,150.00
Plint Keramik Uk. 10 x 20 Cm Bh 25,300.00
Plint Granit Tile Uk. 10 x 30 Cm Bh 29,700.00
Plint Keramik Uk. 10 x 30 Cm Bh 27,500.00
Stop Nozing Granit Lantai 10 x 60 cm Bh 63,250.00
Plint Keramik Uk. 10 x 60 Cm Bh 33,000.00
Stop Nozing Keramik Lantai 10 x 60 cm Bh 30,800.00
Kuku Tegel Uk. 10 Cm Bh 2,500.00 192,000 Dos
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

8. Bahan Besi dan Alumunium


Besi Beton Polos Uk. Ǿ 4 mm Kg 12,800.00 50,000.00 /Btg
Besi Beton Polos Uk. Ǿ 6 mm Kg 12,800.00 37,000.00 /Btg
Besi Beton Polos Uk. Ǿ 8 mm Kg 12,800.00 62,000.00 /Btg
Besi Beton Polos Uk. Ǿ 10 mm Kg 12,800.00 87,000.00 /Btg
Besi Beton Polos Uk. Ǿ 12 mm Kg 12,800.00 117,000.00 /Btg
Besi Beton Polos Uk. Ǿ 14 mm Kg 12,800.00 152,000.00 /Btg
Besi Beton Polos Uk. Ǿ 16 mm Kg 12,800.00 182,000.00 /Btg
Besi Beton Polos Uk. Ǿ 19 mm Kg 12,800.00 272,000.00 /Kg
Besi Beton Polos Uk. Ǿ 20 mm Kg 12,800.00 315,000.00 /Kg
Besi Beton Polos Uk. Ǿ 22 mm Kg 12,800.00 365,000.00 /Kg
Besi Beton Ulir Uk. Ǿ 10 mm Kg 17,500.00 97,000.00 /Kg
Besi Beton Ulir Uk. Ǿ 12 mm Kg 17,500.00 127,000.00 /Kg
Besi Beton Ulir Uk. Ǿ 16 mm Kg 17,500.00 192,000.00 /Kg
Besi Beton Ulir Uk. Ǿ 19 mm Kg 17,500.00 282,000.00 /Kg
Besi Beton Ulir Uk. Ǿ 22 mm Kg 17,500.00 375,000.00 /Kg
Besi Profil Kg 19,000.00 642.33 /Kg
Besi WF Kg 22,000.00 743.75 /Kg
Besi Plintir Uk. Ǿ 16 mm M1 25,000.00 1,318.57 /Kg
Besi Hollow Embos 10 x 20 x 2 mm x 6 mm Btg 82,000.00 13,666.67 M1
Besi Hollow Embos 20 x 20 x 2 mm x 6 mm Btg 95,000.00 15,833.33 M1
Besi Hollow Embos 30 x 30 x 2 mm x 6 mm Btg 110,000.00 18,333.33 M1
Besi Hollow Embos 20 x 40 x 2 mm x 6 mm Btg 125,000.00 20,833.33 M1
Besi Hollow Embos 40 x 40 x 2 mm x 6 mm Btg 138,000.00 23,000.00 M1
Besi Hollow Embos 50 x 50 x 2 mm x 6 mm Btg 155,000.00 25,833.33 M1
Pipa Penguapan Septictank Bh 150,000.00
Besi Plat 5 mm M2 1,800,000.00
Besi Plat 3 mm M2 1,300,000.00
Besi Plat 2 mm M2 1,040,000.00
Besi Plat 2 mm Kg 18,711.11 842,000.00
Besi Plat 1,4 mm M2 643,500.00
Besi Plat 1,2 mm M2 552,500.00
Besi Plat 1,2 mm M2 42,666.67 512,000.00
Besi Siku Ukuran 30 x 3 mm - 6 M' M1 14,333.33 86,000.00 Btg
Besi Siku Ukuran 40 x 3 mm - 6 M' M1 14,333.33 86,000.00 Btg
Besi Siku Ukuran 40 x 4 mm - 6 M' M1 26,833.33 161,000.00 Btg
Besi Siku Ukuran 50 x 4 mm - 6 M' M1 35,083.33 210,500.00 Btg
Besi Strip Tebal 5 mm Kg 6,503.33 39,020.00 Btg
Besi Strip Kg 18,500.00
Truss Canal / TS C75.75 Btg 87,000.00
Reng R32. 0.45 Btg 55,000.00
Braket L Bh 2,000.00
Ramset bh 13,200.00

9. Bahan Kawat
Kawat Ikat Beton/ Bendrat Kg 25,000.00
Kawat Duri (50 m) 4 Kg Roll 82,400.00 1,648.00
Kawat Jaringan/ Ayakan M1 33,880.00
Kawat Harmonika M2 31,500.00
Kawat Bronjong Roll 875,000.00
Kawat Las Kg 60,000.00
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

10. Bahan Langit - Langit


Tripleks Uk. 122 Cm x 244 Cm x 2 mm Lbr 55,000.00
Tripleks Uk. 122 Cm x 244 Cm x 3 mm Lbr 49,500.00
Tripleks Uk. 122 Cm x 244 Cm x 4 mm Lbr 77,500.00
Tripleks Uk. 90 Cm x 210 Cm x 3 mm Lbr 56,800.00
Tripleks Lapis Kulit Jeruk Lbr 117,075.00
Teakwood 90 Cm x 210 Cm x 3 mm Lbr 99,400.00
Teakwood 122 Cm x 244 Cm x 3 mm Lbr 107,800.00
Plywood 90 x 240 x 4 mm Lbr 89,250.00
Playwood 122 Cm x 244 Cm x 9 mm Lbr 114,975.00
Playwood 122 Cm x 244 Cm x 4 mm Lbr 106,050.00
Gypsumboard 120 x 240 x 5 mm Lbr 82,720.00
Gypsumboard 120 x 240 x 9 mm Lbr 106,100.00
Kalsiboard GRC 120 x 240 T=4 mm Lbr 86,350.00
Kalsiboard GRC 120 x 240 T=6 mm Lbr 104,500.00
Lisplank GRC 30 Cm Lbr 77,000.00
Lisplank GRC 20 Cm Lbr 66,000.00
Profil Gypsum M1 35,000.00 70,000.00 Btg
List Profil Gypsum (Besar) Btg 26,279.20 13,139.60 /M1
List Profil Gypsum (Kecil) Btg 17,869.60 8,934.80 /M1
Profil Alluminium "T" M1 19,800.00
Kawat Dia. 4 mm Kg 22,000.00
Profil Alumunium Jepitan Kaca 65,000.00

11. Bahan Sanitair/ Saluran Air


Bak Mandi Fibber Glass 70 x 70 x 66 Bh 850,000.00
Bak Reservoir Fibber Glass Kap. 1.000 Ltr Bh 1,612,500.00
Bak Reservoir Almunium Kap. 1.000 Ltr Bh 1,988,750.00
Buis Beton 1/2 Dia 20 Cm Bh -
Kran Air 1/2" Bh 17,820.00
Kran Air Stainless Bh 35,750.00
Seal Tape Bh 3,300.00
Bak Teraso Bh 385,000.00
Shower Basuh Bh 66,550.00
Floor Drain Plastik Bh 27,500.00
Floor Drain Stainlees Bh 35,200.00

Pipa Gip :
Diameter 1/2" Btg 78,100.00 13,016.67 /M1
Diameter 3/4" Btg 108,575.00 18,095.83 /M1
Diameter 1" Btg 135,450.00 22,575.00 /M1
Diameter 2" Btg 251,000.00 41,833.33 /M1
Diameter 2" Medium A Btg 651,000.00 108,500.00 /M1
Diameter 2" Medium B Btg 276,000.00 46,000.00 /M1
Diameter 2 1/2" Medium C Btg 61,000.00 10,166.67 /M1
Diameter 3" Btg 525,000.00 87,500.00 /M1
Diameter 4" Btg 650,000.00 108,333.33 /M1
Knie Gip 1/2" Bh 9,500.00 1,583.33 /M1
Double Niple 1" Bh 8,900.00 1,483.33 /M1
Clame Sadle 1/2"-3" Bh 51,500.00 8,583.33 /M1
Tee Gip 1/2" Bh 5,900.00 1,475.00
Socket Drat Gip 1/2" Bh 4,700.00 783.33 /M1
Hanger + Support Pipa GIP 4" Set 140,000.00 23,333.33
Hanger + Support Pipa GIP 3" Set 120,000.00 20,000.00
Hanger + Support Pipa GIP 2" Set 100,000.00 16,666.67
Hanger + Support Pipa GIP 3/4" Set 85,000.00 14,166.67
Hanger + Support Pipa GIP 1/2" Set 65,000.00 10,833.33
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

Pipa PVC Aw (4 mm) :


Diameter 1/2" Panjang 4 m1 Btg 23,000.00 5,750.00 /M1
Diameter 3/4" Btg 29,000.00 7,250.00 /M1
Diameter 1" Btg 38,658.00 9,664.50 /M1
Diameter 1 1/4" Btg 39,000.00 9,750.00 /M1
Diameter 1 1/2" Btg 41,000.00 10,250.00 /M1
Diameter 2" Btg 76,824.00 19,206.00 /M1
Diameter 2,5" Btg 107,140.00 26,785.00 /M1
Diameter 3" Btg 163,108.00 40,777.00 /M1
Diameter 4" Btg 221,408.00 55,352.00 /M1
Hanger + Support Pipa PVC 4" Set 140,000.00 23,333.33
Hanger + Support Pipa PVC 3" Set 120,000.00 20,000.00
Hanger + Support Pipa PVC 2,5" Set 95,000.00 15,833.33
Hanger + Support Pipa PVC 2" Set 85,000.00 14,166.67

12. Bahan Finishing


Cat Kayu :
Cat Kayu Kg 48,500.00
Meni Kayu Kg 28,000.00
Meni Besi/ Seng Kg 28,000.00
Minyak Cat Kg 18,500.00
Plamur Kayu Kg 21,125.00
Dempul Jadi Kg 5,900.00
Afduner/ Tinner Ltr 18,500.00
Vernis Kg 29,000.00
Politur Ltr 45,500.00
Residu/ Ter Kg 15,625.00
Tineer Ltr 25,500.00

Cat Tembok :
Cat Tembok & Plafond (Interior) Kg 60,000.00
Cat Tembok Wathersield (Exterior) Kg 85,000.00
Cat Tembok Metrolait (Exterior) Kg 23,550.00 102,500.00
Cat Tembok Paragon (Interior) Kg 14,275.00 285,500.00
Cat Tembok Bel Mas Kg 11,450.00
Plamur Tembok Kg 32,670.00 30,500.00 Klg
Dempul Tembok Kg 18,750.00
Polimer Mortar Kg 30,000.00
375,500.00
Cat Besi :
Meny Seng Kg 24,000.00
Meny Besi Kg 57,000.00
Meny Kayu Kg 55,000.00
Cat Glotex Kg 58,650.00
Cat Atap Seng Kg 21,875.00 87,500.00 Klg
Cat Atap dan Genting Kg 28,100.00 87,500.00 Klg

13. Bahan Penggantung


Kunci - Kunci :
Kunci Tanam Antik Set 234,300.00
Kunci Tanam Stainless Set 430,000.00
Kunci Pintu Gagang Ex. Muller Set 250,500.00
Kunci Pintu Tanam Kualitas Baik Set 180,000.00
Kunci Tanam Royal 2 Slaag Set 55,550.00
Kunci Tanam Royal 1 Slaag Set 55,000.00
Kunci Tanam Kuda Terbang Set 99,000.00
Kunci Tanam Yale Set 90,200.00
Kunci Tanam Putar untuk Km/Wc Set 50,000.00
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
Kunci Pintu Bulat Ex. Muller Set 104,500.00
Handle Stainless Steel 80 cm Set 787,500.00
Handle Stainless Steel 30 cm Set 262,500.00
Handle Jendela Alumunium Buah 35,000.00
Door Closer Set 393,750.00 196,875.00 /Bh
Door Holder Bh 85,000.00 /Bh
Hak Angin Jendela Psg 17,160.00 8,580.00 /Bh
Hak Angin Jendela Biasa Psg 9,845.00 4,922.50 /Bh
Kait Angin Jendela Bh 7,950.00 3,975.00 /Bh
Hak Tarikan Pintu Lemari Bh 7,800.00
Grendel Pintu Bh 10,400.00
Grendel Jendela Bh 8,000.00
Pegangan Pintu dan Jendela Bh 7,000.00
Hengsel Kupu - Kupu Psg 26,000.00 13,000.00 /Bh
Hengsel Ring Pintu Psg 112,750.00 37,583.33 /Bh
Hengsel Per Pintu Koboy Buah 65,650.00
Hengsel Pintu Nilon Buah 17,500.00
Hengsel Pintu Kualitas Baik Buah 31,200.00
Hengsel Jendela Kualitas Baik Buah 25,200.00
Hengsel Jendela Nilon Buah 12,000.00 4,000.00 /Bh
Friction Stay (Hak Angin Alumunium) Bh 27,600.00
Spring Knip (Grendel Alumunium) Bh 27,000.00
Floor Hinges Kaca Frameless Set 1,627,500.00

Paku dan Sekrup :


Paku Beton 1" - 2" Bh 3,000.00
Paku Beton 2,5" - 3,5" Bh 3,900.00
Paku Beton 4" - 6" Bh 4,950.00
Paku Tripleks Kg 27,300.00
Paku Biasa 1/2" - 1" Kg 20,000.00
Paku Biasa 2" - 5" Kg 23,400.00
Paku Biasa 2,5" - 3,5" Kg 23,400.00
Paku Biasa 4" - 10" Kg 21,450.00
Paku Payung Dos 9,750.00
Paku Gypsum Kg 36,400.00
Paku Seng Kepala Kecil Kg 35,000.00
Paku Seng Kepala Besar Kg 31,200.00
Paku Genteng Metal Kg 37,200.00
Paku Sekrup 3 - 5" Dos 15,000.00
Screw 12 - 14 x 20 Bh 980.00
Screw 10 - 16 x 16 Bh 700.00
Screw 1" Bh 700.00
Paku Sekrup Kg 19,800.00
Paku Sekrup Bh 350.00
Sekrup Genteng Metal Kg 30,000.00
Skrup Baja Ringan Bh 280.00
Skrup Fixer Bh 1,540.00
Skrup Fixer Kg 37,200.00
Baut Mur Bh 2,520.00
Besi Beugel/Baut, Kawat Jepit Bh 60,060.00

14. Bahan Listrik


Macam - macam Kabel :
NYM 2 x 1,5 mm M1 15,288.00 764,400.00 Roll
NYM 2 x 2,5 mm M1 21,840.00 1,092,000.00 Roll
NYM 2 x 4 mm M1 27,408.00 1,370,400.00 Roll
NYM 2 x 6 mm M1 36,558.00 1,827,900.00 Roll
NYM 2 x 10 mm M1 60,300.00 3,015,000.00 Roll
NYM 3 x 2,5 mm M1 28,080.00 1,404,000.00 Roll
NYM 4 x 2,5 mm M1 37,440.00 1,872,000.00 Roll
NYY 2 x 1,5 mm M1 15,060.00 753,000.00 Roll
NYY 2 x 2,5 mm M1 18,306.00 915,300.00 Roll
NYY 2 x 4 mm M1 31,100.00 1,555,000.00 Roll
NYY 2 x 6 mm M1 42,050.00 2,102,500.00 Roll
NYY 2 x 10 mm M1 54,550.00 2,727,500.00 Roll
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

NYA 2 x 1,5 mm M1 8,400.00 420,000.00 Roll


NYA 2 x 2,5 mm M1 10,800.00 540,000.00 Roll
NYA 3 x 2,5 mm M1 13,200.00 660,000.00 Roll

Pipa Listrik :
Pipa listrik 5/8" Btg 6,000.00 1,500.00

Saklar/ Sekring :
Saklar Double (Setara Broco) Bh 27,540.00
Saklar Tunggal (Setara Broco) Bh 18,500.00
Stop Kontak (Setara Broco) Bh 20,100.00
Saklar Double Bh 9,600.00
Saklar Tunggal Bh 9,390.00
Saklar + Stop Kontak Standart Bh 9,600.00
Saklar Engkel Standart Bh 7,800.00
Saklar Seri Standart Bh 13,560.00
Stop Kontak Standart Bh 9,390.00
Saklar Engkel Panasonic Bh 28,750.00
Saklar Seri Panasonic Bh 38,500.00
Saklar Triple Panasonic Bh 44,000.00
Stop Kontak Daya 200 Watt 2 Phase Bh 30,800.00
Stop Kontak Daya 200 Watt 1 Phase Bh 24,200.00
Stop Kontak AC Daya 200 Watt 1 Phase Bh 25,850.00
Box Sekring 1 Fase Bh 5,040.00
Box Sekring 2 Fase Bh 9,390.00
Sekring Kas Kosong DN 2 G Bh 41,250.00
Sekring Kas Kosong DN 3 G Bh 60,000.00
Sekring Kas Kosong DN 4 G Bh 63,250.00
Fitting Plafond Bh 3,600.00
T Duss Bh 4,200.00
L Bow Bh 420.00
Las dop Bh 1,200.00
Klem Biasa Bh 120.00
Sub Distribusi Panel Box 20 x 40 Include Unit 1,260,000.00

Lampu Pijar :
Lampu 5 Watt Bh 6,750.00
10 - 40 Watt Bh 12,000.00
60 - 100 Watt Bh 13,500.00
Lampu Philips SL 23 Watt Bh 44,550.00
Lampu Philips SL 18 Watt Bh 40,825.00
Lampu Philips SL 15 Watt Bh 34,500.00
Lampu Philips SL 10 Watt Bh 32,200.00
Lampu Philips SL 11 Watt Bh 32,200.00
Lampu Philips SL 8 Watt Bh 35,075.00
Lampu Philips SL 5 Watt Bh 11,500.00
Lampu Philips SL 20 Watt Type Down Light Ø 4" + Box Set 110,250.00
Lampu Philips SL 18 Watt Type Down Light Ø 4" + Box Set 99,750.00
Lampu Philips SL 15 Watt Type Down Light Ø 4" + Box Set 89,250.00
Armatur Down Light Bh 57,750.00
Lampu Mercury 400 Watt Bh 135,000.00
Down light 4,5" Bh 67,500.00
Down light 3,5" Bh 54,000.00

Balon Lampu TL :
TL Biasa 20 Watt Philips Bh 47,250.00
TL Biasa 40 Watt Philips Bh 78,750.00
TL Blok Bambu 20 Watt Set 105,000.00
TL Blok Bambu 40 Watt Set 153,268.50
Halaman - 10
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

15. Bahan Kaca


Kaca Bening 3 mm M2 108,000.00
Kaca Bening 5 mm M2 185,600.00
Kaca Bening 8 mm M2 194,250.00
Kaca Rayben 3 mm M2 139,200.00
Kaca Rayben 5 mm M2 194,600.00
Kaca Rayben 8 mm M2 220,000.00
Sealent (lem Kaca) Tube 24,750.00
Sealent (lem Kaca) Kg 25,000.00
Karet Kaca Kg 24,750.00
Kaca Glass Block Bh 27,500.00
Kaca Tempered m2 500,000.00

16. Bahan Sanitair


Closet :
Kloset Duduk Monoblock (Komplit) Buah 3,605,000.00
Kloset Duduk Standar Type INA Buah 554,400.00
Kloset Duduk Lengkap Buah 1,642,400.00
Kloset Jongkok Standar Ex. INA Buah 175,000.00
Kloset Jongkok Biasa Ex. INA Buah 161,700.00
Urinoir Dinding Standart Buah 367,500.00
Urinoir Biasa Buah 183,750.00
Tangki Air 1000 Liter Buah 1,270,500.00
Tangki Air 2000 Liter Buah 2,402,400.00

Meja Dapur/ Pantri :


Wastafel Standar Ex KIA Set 1,912,500.00
Wastafel Biasa Ex KIA Set 386,760.00
Bak Cuci Stainless Steel 1 Lubang Set 393,750.00
Bak Cuci Stainless Steel 2 Lubang Set 525,000.00
Water Drain + Acessories Set 71,500.00

Pompa Air :
Sanyo 150 Watt Set 500,000.00
National 125 Watt Set 485,000.00
National 250 Watt Set 615,000.00

18. Bahan Lain - Lain


Minyak Bekisting Ltr 10,000.00
Aspal Kg 14,200.00
Air Ltr 100.00
List Profil Beton Jadi M1 40,000.00
HPL (High Pressure Laminate) Uk. 1,22 x 2,44 cm Lbr 465,000.00
Wall Paper m² 75,000.00
Sticker Kaca Sanblast M1 50,000.00
Ventilasi Matahari Adat Banggai Bh 650,000.00
Water Proofing Aquaproof Kg 50,375.00
Kwas No. 1" Bh 4,500.00
Kwas No. 2" Bh 8,400.00
Kwas No. 3" Bh 9,000.00
Kwas No. 4" Bh 12,000.00
Kwas No. 5" Bh 17,500.00
Kwas Roll Bh 25,000.00
Kertas Pasir (Amplas) Lbr 17,000.00
Lem Kayu Kg 18,810.00
Lem Wallpaper Kg 20,400.00
Cornice Adhesive Kg 93,600.00
Perban Gypsum Roll 54,000.00
Pisau Dempul Set 17,000.00
Strorox - 100 Kg 30,000.00
Soda Api Kg 16,650.00
Sabun Rinso Kg 18,000.00
Sealant Tube 25,000.00
Batu Apung Kg 3,000.00
Ijuk Kg 42,000.00
Ijuk M3 180,000.00
Tali Ijuk Kg 42,000.00
Urinoir Keramik Bh 275,000.00
Kitchen Zink Bh 1,575,000.00
Wather Drain + Acessories Bh 71,500.00
Shower Basuh Bh 98,500.00
Railing Tangga Stainless M1 577,500.00 2,310,000.00 Btg
Reservoir Air Rangka Baja 1 M3 Bh 4,095,000.00
Septictank dan Rembesan 1 M3 Bh 2,214,500.00
Penangkal Petir Set 6,150,000.00

Anda mungkin juga menyukai