PEKERJAAN PEMBANGUNAN
HI MAJOLELO HOTEL MOESLEM FRIENDLY
JL. KOPERTIS, KOTA PADANG
MUH. YANTO
DIREKTUR UTAMA
Luas
Basement 1542.2
Ground 1436.7
Ug 1042
Mzz-Ballroom 651.1
1 950.8
2 950.8
3 950.8
4 950.8
Roof 142.2
8617.4
RENCANA ANGGARAN BIAYA (STRUKTUR)
RUMAH SAKIT, HOTEL & APARTMENT HIKMAH
B PEKERJAAN PONDASI
3 Tie Beam
3.1 Beton tie beam 231.36 M3 570,000 131,875,200.00
3.2 Pembesian 1,334.95 Kg 62,976 84,069,634.87
3.3 Bekisting 976.34 M2 193,059 188,490,581.44
1 Kolom K1 100/60
1.1 Beton Kolom 224.11 M3 570,000 127,743,840.00
1.2 Pembesian Kolom 6,089.12 Kg 17,000 103,515,091.68
1.3 Bekisting kolom 971.08 M2 92,740 90,057,708.43
2 Balok B1 50/30
2.1 Beton Balok B1 106.20 M3 570,000 60,532,290.00
2.2 Pembesian Balok B1 2,460.58 Kg 17,000 41,829,936.33
2.3 Bekisting Balok B1 849.58 M2 92,740 78,789,678.24
4 Balok B2 45/25
4.1 Beton Balok B2 3.54 M3 570,000 2,020,080.00
4.2 Pembesian Balok B2 34.98 Kg 17,000 594,647.76
4.3 Bekisting Balok B2 28.35 M2 92,740 2,629,364.48
5 Plat Lantai 1, 12 cm
5.1 Beton Plat Lantai 281.97 M3 570,000 160,721,760.00
5.2 Pembesian Plat 1,914.56 Kg 17,000 32,547,566.24
5.3 Bekisting Plat 2,819.68 M2 92,740 261,497,123.20
6 Tangga A
6.1 Beton tangga 1.69 M3 685,000 1,156,280.00
6.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
6.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
6.4 Beton Bordes 0.650 M3 685,000 445,250.00
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
6.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
6.6 Bekisting Bordes 14.29 M2 92,740 1,324,976.38
7 Ramp
7.1 Beton Ramp 27.82 M3 685,000 19,059,440.00
7.2 Pembesian Ramp 1629.65 Kg 17,000 27,704,078.56
7.3 Bekisting Ramp 193.15 M2 146,574 28,311,384.88
1 Kolom K1 100/60
1.1 Beton Kolom 96.60 M3 785,000 75,831,000.00
1.2 Pembesian Kolom 2,238.22 Kg 19,500 43,645,329.00
1.3 Bekisting kolom 429.29 M2 105,269 45,190,971.12
2 Balok B1 50/30
2.1 Beton Balok B1 89.70 M3 785,000 70,414,500.00
2.2 Pembesian Balok B1 2,582.46 Kg 19,500 50,358,028.50
2.3 Bekisting Balok B1 777.43 M2 105,269 81,839,268.14
4 Balok B2 45/25
4.1 Beton Balok B2 2.74 M3 785,000 2,150,115.00
4.2 Pembesian Balok B2 27.03 Kg 19,500 527,161.64
4.3 Bekisting Balok B2 34.24 M2 105,269 3,604,147.39
5 Plat Lantai 2, 12 cm
5.1 Beton Plat Lantai 204.61 M3 785,000 160,618,850.00
5.2 Pembesian Plat 1,389.30 Kg 18,000 25,007,434.20
5.3 Bekisting Plat 450.14 M2 146,574 65,978,901.94
6 Tangga A
6.1 Beton tangga 1.69 M3 685,000 1,156,280.00
6.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
6.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
6.4 Beton Bordes 0.650 M3 685,000 445,250.00
6.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
6.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
7 Tangga B
7.1 Beton tangga 1.55 M3 685,000 1059695
7.2 Pembesian Tangga 87.42 Kg 17,000 1486156.49
7.3 Bekisting Tangga 14.76 M2 250,877 3702538.09926
7.4 Beton Bordes 0.668 M3 685,000 457580
7.5 Pembesian Bordes 39.12 Kg 17,000 665120.92
7.6 Bekisting Bordes 14.68 M2 146,574 2152086.3745192
8 Ramp
8.1 Beton Ramp 19.526 M3 685,000 13,375,310
8.2 Pembesian Ramp 1143.64 Kg 17,000 19,441,843
8.3 Bekisting Ramp 135.55 M2 146,574 19,867,968
1 Kolom K1 100/60
1.1 Beton Kolom 96.6 M3 785,000 75,831,000
1.2 Pembesian Kolom 2,238.22 Kg 19,500 43,645,329
1.3 Bekisting kolom 429.29 M2 105,269 45,190,971
2 Balok B1 50/30
2.1 Beton Balok B1 89.7 M3 785,000 70,414,500
2.2 Pembesian Balok B1 2,582.46 Kg 19,500 50,358,029
2.3 Bekisting Balok B1 777.43 M2 105,269 81,839,268
4 Balok B2 45/25
4.1 Beton Balok B2 2.74 M3 785,000 2,150,115
4.2 Pembesian Balok B2 27.03 Kg 19,500 527,162
4.3 Bekisting Balok B2 19.01 M2 105,269 2,001,599
5 Plat Lantai 3, 12 cm
5.1 Beton Plat Lantai 204.61 M3 785,000 160,618,850
5.2 Pembesian Plat 1,389.30 Kg 18,000 25,007,434
5.3 Bekisting Plat 450.14 M2 146,574 65,978,902
6 Tangga A
6.1 Beton tangga 1.69 M3 685,000 1,156,280
6.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
6.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
6.4 Beton Bordes 0.650 M3 685,000 445,250
6.5 Pembesian Bordes 38.07 Kg 17,000 647,199
6.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
7 Tangga B
7.1 Beton tangga 1.55 M3 685,000 1,059,695
7.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156
7.3 Bekisting Tangga 14.76 M2 250,877 3,702,538
7.4 Beton Bordes 0.668 M3 685,000 457,580
7.5 Pembesian Bordes 39.12 Kg 17,000 665,121
7.6 Bekisting Bordes 14.68 M2 146,574 2,152,086
8 Ramp
8.1 Beton Ramp 19.53 M3 685,000 13,375,310
8.2 Pembesian Ramp 1143.64 Kg 17,000 19,441,843
8.3 Bekisting Ramp 135.55 M2 146,574 19,867,968
1 Kolom K1 100/60
1.1 Beton Kolom 96.6 M3 785,000 75,831,000
1.2 Pembesian Kolom 2,238.22 Kg 19,500 43,645,329
1.3 Bekisting kolom 429.29 M2 105,269 45,190,971
2 Balok B1 50/30
2.1 Beton Balok B1 89.7 M3 785,000 70,414,500
2.2 Pembesian Balok B1 2,582.46 Kg 19,500 50,358,029
2.3 Bekisting Balok B1 777.43 M2 105,269 81,839,268
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
4 Balok B2 45/25
4.1 Beton Balok B2 2.74 M3 785,000 2,150,115
4.2 Pembesian Balok B2 27.03 Kg 19,500 527,162
4.3 Bekisting Balok B2 34.24 M2 105,269 3,604,147
5 Plat Lantai 4, 12 cm
5.1 Beton Plat Lantai 204.61 M3 785,000 160,618,850
5.2 Pembesian Plat 1,389.30 Kg 18,000 25,007,434
5.3 Bekisting Plat 450.14 M2 146,574 65,978,902
6 Tangga A
6.1 Beton tangga 1.69 M3 685,000 1,156,280
6.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
6.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
6.4 Beton Bordes 0.650 M3 685,000 445,250
6.5 Pembesian Bordes 38.07 Kg 17,000 647,199
6.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
7 Tangga B
7.1 Beton tangga 1.55 M3 685,000 1,059,695
7.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156
7.3 Bekisting Tangga 14.76 M2 250,877 3,702,538
7.4 Beton Bordes 0.668 M3 685,000 457,580
7.5 Pembesian Bordes 39.12 Kg 17,000 665,121
7.6 Bekisting Bordes 14.68 M2 146,574 2,152,086
8 Ramp
8.1 Beton Ramp 19.53 M3 685,000 13,375,310
8.2 Pembesian Ramp 1143.64 Kg 17,000 19,441,843
8.3 Bekisting Ramp 135.55 M2 146,574 19,867,968
1 Kolom K1 100/60
1.1 Beton Kolom 96.6 M3 785,000 75,831,000
1.2 Pembesian Kolom 2,238.22 Kg 19,500 43,645,329
1.3 Bekisting kolom 429.29 M2 105,269 45,190,971
2 Balok B1 50/30
2.1 Beton Balok B1 89.7 M3 785,000 70,414,500
2.2 Pembesian Balok B1 2,582.46 Kg 19,500 50,358,029
2.3 Bekisting Balok B1 777.43 M2 105,269 81,839,268
4 Balok B2 45/25
4.1 Beton Balok B2 2.74 M3 785,000 2,150,115
4.2 Pembesian Balok B2 27.03 Kg 19,500 527,162
4.3 Bekisting Balok B2 34.24 M2 105,269 3,604,147
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
5 Plat Lantai 5, 12 cm
5.1 Beton Plat Lantai 204.61 M3 785,000 160,618,850
5.2 Pembesian Plat 1,389.30 Kg 18,000 25,007,434
5.3 Bekisting Plat 450.14 M2 146,574 65,978,902
6 Tangga A
6.1 Beton tangga 1.69 M3 685,000 1,156,280
6.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
6.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
6.4 Beton Bordes 0.650 M3 685,000 445,250
6.5 Pembesian Bordes 38.07 Kg 17,000 647,199
6.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
7 Tangga B
7.1 Beton tangga 1.55 M3 685,000 1,059,695
7.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156
7.3 Bekisting Tangga 14.76 M2 250,877 3,702,538
7.4 Beton Bordes 0.668 M3 685,000 457,580
7.5 Pembesian Bordes 39.12 Kg 17,000 665,121
7.6 Bekisting Bordes 14.68 M2 146,574 2,152,086
8 Ramp
8.1 Beton Ramp 19.53 M3 685,000 13,375,310
8.2 Pembesian Ramp 1143.64 Kg 17,000 19,441,843
8.3 Bekisting Ramp 135.55 M2 146,574 19,867,968
1 Kolom K1 100/60
1.1 Beton Kolom 96.6 M3 785,000 75,831,000
1.2 Pembesian Kolom 2,238.22 Kg 19,500 43,645,329
1.3 Bekisting kolom 429.29 M2 105,269 45,190,971
2 Balok B1 50/30
2.1 Beton Balok B1 89.7 M3 785,000 70,414,500
2.2 Pembesian Balok B1 2,582.46 Kg 19,500 50,358,029
2.3 Bekisting Balok B1 777.43 M2 105,269 81,839,268
4 Balok B2 45/25
4.1 Beton Balok B2 2.74 M3 785,000 2,150,115
4.2 Pembesian Balok B2 27.03 Kg 19,500 527,162
4.3 Bekisting Balok B2 34.24 M2 105,269 3,604,147
5 Plat Lantai 6, 12 cm
5.1 Beton Plat Lantai 204.61 M3 785,000 160,618,850
5.2 Pembesian Plat 1,389.30 Kg 18,000 25,007,434
5.3 Bekisting Plat 450.14 M2 146,574 65,978,902
6 Tangga A
6.1 Beton tangga 1.69 M3 685,000 1,156,280
6.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
6.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
6.4 Beton Bordes 0.650 M3 685,000 445,250
6.5 Pembesian Bordes 38.07 Kg 17,000 647,199
6.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
7 Tangga B
7.1 Beton tangga 1.55 M3 685,000 1,059,695
7.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156
7.3 Bekisting Tangga 14.76 M2 250,877 3,702,538
7.4 Beton Bordes 0.668 M3 685,000 457,580
7.5 Pembesian Bordes 39.12 Kg 17,000 665,121
7.6 Bekisting Bordes 14.68 M2 146,574 2,152,086
8 Ramp
8.1 Beton Ramp 19.53 M3 685,000 13,375,310
8.2 Pembesian Ramp 1143.64 Kg 17,000 19,441,843
8.3 Bekisting Ramp 135.55 M2 146,574 19,867,968
1 Kolom K1 100/60
1.1 Beton Kolom 103.2 M3 785,000 81,012,000.00
1.2 Pembesian Kolom 2,391.14 Kg 19,500 46,627,308.00
1.3 Bekisting kolom 458.62 M2 105,269 48,278,553.00
2 Balok B1 50/30
2.1 Beton Balok B1 80.133 M3 785,000 62,904,405.00
2.2 Pembesian Balok B1 2,307.03 Kg 19,500 44,987,066.87
2.3 Bekisting Balok B1 694.51 M2 105,269 73,110,658.57
4 Plat Lantai 7, 12 cm
4.1 Beton Plat Lantai 188.72 M3 785,000 148,144,415.00
4.2 Pembesian Plat 1,281.40 Kg 18,000 23,065,236.18
4.3 Bekisting Plat 415.18 M2 146,574 60,854,662.02
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga B
6.1 Beton tangga 1.55 M3 685,000 1,059,695.00
6.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156.49
6.3 Bekisting Tangga 14.76 M2 250,877 3,702,538.10
6.4 Beton Bordes 0.668 M3 685,000 457,580.00
6.5 Pembesian Bordes 39.12 Kg 17,000 665,120.92
6.6 Bekisting Bordes 14.68 M2 146,574 2,152,086.37
2 Balok B1 50/30
2.1 Beton Balok B1 80.133 M3 785,000 62,904,405.00
2.2 Pembesian Balok B1 2,307.03 Kg 19,500 44,987,066.87
2.3 Bekisting Balok B1 694.51 M2 105,269 73,110,658.57
4 Plat Lantai 8, 12 cm
4.1 Beton Plat Lantai 188.72 M3 785,000 148,144,415.00
4.2 Pembesian Plat 1,281.40 Kg 18,000 23,065,236.18
4.3 Bekisting Plat 415.18 M2 146,574 60,854,662.02
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga B
6.1 Beton tangga 1.55 M3 685,000 1,059,695.00
6.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156.49
6.3 Bekisting Tangga 14.76 M2 250,877 3,702,538.10
6.4 Beton Bordes 0.668 M3 685,000 457,580.00
6.5 Pembesian Bordes 39.12 Kg 17,000 665,120.92
6.6 Bekisting Bordes 14.68 M2 146,574 2,152,086.37
1 Kolom K1 100/60
1.1 Beton Kolom 103.2 M3 785,000 81,012,000.00
1.2 Pembesian Kolom 2,391.14 Kg 19,500 46,627,308.00
1.3 Bekisting kolom 458.62 M2 105,269 48,278,553.00
2 Balok B1 50/30
2.1 Beton Balok B1 80.133 M3 785,000 62,904,405.00
2.2 Pembesian Balok B1 2,307.03 Kg 19,500 44,987,066.87
2.3 Bekisting Balok B1 694.51 M2 105,269 73,110,658.57
4 Plat Lantai 9, 12 cm
4.1 Beton Plat Lantai 188.72 M3 785,000 148,144,415.00
4.2 Pembesian Plat 1,281.40 Kg 18,000 23,065,236.18
4.3 Bekisting Plat 415.18 M2 146,574 60,854,662.02
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga B
6.1 Beton tangga 1.55 M3 685,000 1,059,695.00
6.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156.49
6.3 Bekisting Tangga 14.76 M2 250,877 3,702,538.10
6.4 Beton Bordes 0.668 M3 685,000 457,580.00
6.5 Pembesian Bordes 39.12 Kg 17,000 665,120.92
6.6 Bekisting Bordes 14.68 M2 146,574 2,152,086.37
1 Kolom K1 100/60
1.1 Beton Kolom 103.2 M3 785,000 81,012,000.00
1.2 Pembesian Kolom 2,391.14 Kg 19,500 46,627,308.00
1.3 Bekisting kolom 458.62 M2 105,269 48,278,553.00
2 Balok B1 50/30
2.1 Beton Balok B1 80.133 M3 785,000 62,904,405.00
2.2 Pembesian Balok B1 2,307.03 Kg 19,500 44,987,066.87
2.3 Bekisting Balok B1 694.51 M2 105,269 73,110,658.57
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga B
6.1 Beton tangga 1.55 M3 685,000 1,059,695.00
6.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156.49
6.3 Bekisting Tangga 14.76 M2 250,877 3,702,538.10
6.4 Beton Bordes 0.668 M3 685,000 457,580.00
6.5 Pembesian Bordes 39.12 Kg 17,000 665,120.92
6.6 Bekisting Bordes 14.68 M2 146,574 2,152,086.37
1 Kolom K1 100/60
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
1.1 Beton Kolom 103.2 M3 785,000 81,012,000.00
1.2 Pembesian Kolom 2,391.14 Kg 19,500 46,627,308.00
1.3 Bekisting kolom 458.62 M2 105,269 48,278,553.00
2 Balok B1 50/30
2.1 Beton Balok B1 80.133 M3 785,000 62,904,405.00
2.2 Pembesian Balok B1 2,307.03 Kg 19,500 44,987,066.87
2.3 Bekisting Balok B1 694.51 M2 105,269 73,110,658.57
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga B
6.1 Beton tangga 1.55 M3 685,000 1,059,695.00
6.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156.49
6.3 Bekisting Tangga 14.76 M2 250,877 3,702,538.10
6.4 Beton Bordes 0.668 M3 685,000 457,580.00
6.5 Pembesian Bordes 39.12 Kg 17,000 665,120.92
6.6 Bekisting Bordes 14.68 M2 146,574 2,152,086.37
1 Kolom K1 100/60
1.1 Beton Kolom 79.2 M3 785,000 62,172,000.00
1.2 Pembesian Kolom 1,835.06 Kg 19,500 35,783,748.00
1.3 Bekisting kolom 351.96 M2 105,269 37,050,982.53
2 Balok B1 50/30
2.1 Beton Balok B1 68.16 M3 785,000 53,505,600.00
2.2 Pembesian Balok B1 1,962.33 Kg 19,500 38,265,364.80
2.3 Bekisting Balok B1 590.74 M2 105,269 62,186,895.39
5 Tangga A
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga B
6.1 Beton tangga 1.55 M3 685,000 1,059,695.00
6.2 Pembesian Tangga 87.42 Kg 17,000 1,486,156.49
6.3 Bekisting Tangga 14.76 M2 250,877 3,702,538.10
6.4 Beton Bordes 0.668 M3 685,000 457,580.00
6.5 Pembesian Bordes 39.12 Kg 17,000 665,120.92
6.6 Bekisting Bordes 14.68 M2 146,574 2,152,086.37
1 Kolom K1 100/60
1.1 Beton Kolom 100.8 M3 785,000 79,128,000.00
1.2 Pembesian Kolom 2,335.54 Kg 19,500 45,542,952.00
1.3 Bekisting kolom 447.96 M2 105,269 47,155,795.95
2 Balok B1 50/30
2.1 Beton Balok B1 57.123 M3 785,000 44,841,555.00
2.2 Pembesian Balok B1 1,644.57 Kg 19,500 32,069,137.82
2.3 Bekisting Balok B1 495.09 M2 105,269 52,117,107.18
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga C (Room)
6.1 Beton tangga 23.07 M3 535,000 12,339,775.00
6.2 Pembesian Tangga 1,303.40 Kg 17,000 22,157,853.55
6.3 Bekisting Tangga 220.04 M2 250,877 55,203,000.17
1 Kolom K1 100/60
1.1 Beton Kolom 100.8 M3 785,000 79,128,000.00
1.2 Pembesian Kolom 2,335.54 Kg 19,500 45,542,952.00
1.3 Bekisting kolom 447.96 M2 105,269 47,155,795.95
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
2 Balok B1 50/30
2.1 Beton Balok B1 57.123 M3 785,000 44,841,555.00
2.2 Pembesian Balok B1 1,644.57 Kg 19,500 32,069,137.82
2.3 Bekisting Balok B1 495.09 M2 105,269 52,117,107.18
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga C (Room)
6.1 Beton tangga 23.07 M3 535,000 12,339,775.00
6.2 Pembesian Tangga 1,303.40 Kg 17,000 22,157,853.55
6.3 Bekisting Tangga 220.04 M2 250,877 55,203,000.17
1 Kolom K1 100/60
1.1 Beton Kolom 100.8 M3 785,000 79,128,000.00
1.2 Pembesian Kolom 2,335.54 Kg 19,500 45,542,952.00
1.3 Bekisting kolom 447.96 M2 105,269 47,155,795.95
2 Balok B1 50/30
2.1 Beton Balok B1 57.123 M3 785,000 44,841,555.00
2.2 Pembesian Balok B1 1,644.57 Kg 19,500 32,069,137.82
2.3 Bekisting Balok B1 495.09 M2 105,269 52,117,107.18
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
6 Tangga C (Room)
6.1 Beton tangga 23.07 M3 535,000 12,339,775.00
6.2 Pembesian Tangga 1,303.40 Kg 17,000 22,157,853.55
6.3 Bekisting Tangga 220.04 M2 250,877 55,203,000.17
1 Kolom K1 100/60
1.1 Beton Kolom 100.8 M3 785,000 79,128,000.00
1.2 Pembesian Kolom 2,335.54 Kg 19,500 45,542,952.00
1.3 Bekisting kolom 447.96 M2 105,269 47,155,795.95
2 Balok B1 50/30
2.1 Beton Balok B1 57.123 M3 785,000 44,841,555.00
2.2 Pembesian Balok B1 1,644.57 Kg 19,500 32,069,137.82
2.3 Bekisting Balok B1 495.09 M2 105,269 52,117,107.18
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga C (Room)
6.1 Beton tangga 23.07 M3 535,000 12,339,775.00
6.2 Pembesian Tangga 1,303.40 Kg 17,000 22,157,853.55
6.3 Bekisting Tangga 220.04 M2 250,877 55,203,000.17
1 Kolom K1 100/60
1.1 Beton Kolom 100.8 M3 785,000 79,128,000.00
1.2 Pembesian Kolom 2,335.54 Kg 19,500 45,542,952.00
1.3 Bekisting kolom 447.96 M2 105,269 47,155,795.95
2 Balok B1 50/30
2.1 Beton Balok B1 57.123 M3 785,000 44,841,555.00
2.2 Pembesian Balok B1 1,644.57 Kg 19,500 32,069,137.82
2.3 Bekisting Balok B1 495.09 M2 105,269 52,117,107.18
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga C (Room)
6.1 Beton tangga 23.07 M3 535,000 12,339,775.00
6.2 Pembesian Tangga 1,303.40 Kg 17,000 22,157,853.55
6.3 Bekisting Tangga 220.04 M2 250,877 55,203,000.17
1 Kolom K1 100/60
1.1 Beton Kolom 100.8 M3 785,000 79,128,000.00
1.2 Pembesian Kolom 2,335.54 Kg 19,500 45,542,952.00
1.3 Bekisting kolom 447.96 M2 105,269 47,155,795.95
2 Balok B1 50/30
2.1 Beton Balok B1 57.123 M3 785,000 44,841,555.00
2.2 Pembesian Balok B1 1,644.57 Kg 19,500 32,069,137.82
2.3 Bekisting Balok B1 495.09 M2 105,269 52,117,107.18
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga C (Room)
6.1 Beton tangga 23.07 M3 535,000 12,339,775.00
6.2 Pembesian Tangga 1,303.40 Kg 17,000 22,157,853.55
6.3 Bekisting Tangga 220.04 M2 250,877 55,203,000.17
1 Kolom K1 100/60
1.1 Beton Kolom 46.8 M3 785,000 36,738,000.00
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
1.2 Pembesian Kolom 1,084.36 Kg 19,500 21,144,942.00
1.3 Bekisting kolom 207.98 M2 105,269 21,893,762.40
2 Balok B1 50/30
2.1 Beton Balok B1 54.495 M3 785,000 42,778,575.00
2.2 Pembesian Balok B1 1,568.91 Kg 19,500 30,593,765.48
2.3 Bekisting Balok B1 472.31 M2 105,269 49,719,408.22
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga C (Room)
6.1 Beton tangga 9.92 M3 535,000 5,306,130.00
6.2 Pembesian Tangga 560.47 Kg 17,000 9,527,925.06
6.3 Bekisting Tangga 94.62 M2 250,877 23,737,409.74
1 Kolom K1 100/60
1.1 Beton Kolom 46.8 M3 785,000 36,738,000
1.2 Pembesian Kolom 1,084.36 Kg 19,500 21,144,942
1.3 Bekisting kolom 207.98 M2 105,269 21,893,762
2 Balok B1 50/30
2.1 Beton Balok B1 54.495 M3 785,000 42,778,575
2.2 Pembesian Balok B1 1,568.91 Kg 19,500 30,593,765
2.3 Bekisting Balok B1 472.31 M2 105,269 49,719,408
4 Plat Lantai 2, 12 cm
4.1 Beton Plat Lantai 158.655 M3 785,000 124,544,175
4.2 Pembesian Plat 1,077.27 Kg 18,000 19,390,814
4.3 Bekisting Plat 349.04 M2 146,574 51,160,171
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
5.4 Beton Bordes 0.650 M3 685,000 445,250
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (Rp) TOTAL (Rp)
5.5 Pembesian Bordes 38.07 Kg 17,000 647,199
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
6 Tangga C (Room)
6.1 Beton tangga 9.92 M3 535,000 5,306,130
6.2 Pembesian Tangga 560.47 Kg 17,000 9,527,925
6.3 Bekisting Tangga 94.62 M2 250,877 23,737,410
1 Kolom K1 100/60
1.1 Beton Kolom 46.8 M3 785,000 36,738,000
1.2 Pembesian Kolom 1,084.36 Kg 19,500 21,144,942
1.3 Bekisting kolom 207.98 M2 105,269 21,893,762
2 Balok B1 50/30
2.1 Beton Balok B1 54.495 M3 785,000 42,778,575
2.2 Pembesian Balok B1 1,568.91 Kg 19,500 30,593,765
2.3 Bekisting Balok B1 472.31 M2 105,269 49,719,408
4 Plat Lantai 2, 12 cm
4.1 Beton Plat Lantai 158.655 M3 785,000 124,544,175
4.2 Pembesian Plat 1,077.27 Kg 18,000 19,390,814
4.3 Bekisting Plat 349.04 M2 146,574 51,160,171
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
5.4 Beton Bordes 0.650 M3 685,000 445,250
5.5 Pembesian Bordes 38.07 Kg 17,000 647,199
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
6 Tangga C (Room)
6.1 Beton tangga 9.92 M3 535,000 5,306,130
6.2 Pembesian Tangga 560.47 Kg 17,000 9,527,925
6.3 Bekisting Tangga 94.62 M2 250,877 23,737,410
1 Kolom K1 100/60
1.1 Beton Kolom 46.8 M3 785,000 36,738,000
1.2 Pembesian Kolom 1,084.36 Kg 19,500 21,144,942
1.3 Bekisting kolom 207.98 M2 105,269 21,893,762
2 Balok B1 50/30
2.1 Beton Balok B1 54.495 M3 785,000 42,778,575
2.2 Pembesian Balok B1 1,568.91 Kg 19,500 30,593,765
2.3 Bekisting Balok B1 472.31 M2 105,269 49,719,408
4 Plat Lantai 2, 12 cm
4.1 Beton Plat Lantai 158.655 M3 785,000 124,544,175
4.2 Pembesian Plat 1,077.27 Kg 18,000 19,390,814
4.3 Bekisting Plat 349.04 M2 146,574 51,160,171
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
5.4 Beton Bordes 0.650 M3 685,000 445,250
5.5 Pembesian Bordes 38.07 Kg 17,000 647,199
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
6 Tangga C (Room)
6.1 Beton tangga 9.92 M3 535,000 5,306,130
6.2 Pembesian Tangga 560.47 Kg 17,000 9,527,925
6.3 Bekisting Tangga 94.62 M2 250,877 23,737,410
1 Kolom K1 100/60
1.1 Beton Kolom 46.8 M3 785,000 36,738,000
1.2 Pembesian Kolom 1,084.36 Kg 19,500 21,144,942
1.3 Bekisting kolom 207.98 M2 105,269 21,893,762
2 Balok B1 50/30
2.1 Beton Balok B1 54.495 M3 785,000 42,778,575
2.2 Pembesian Balok B1 1,568.91 Kg 19,500 30,593,765
2.3 Bekisting Balok B1 472.31 M2 105,269 49,719,408
4 Plat Lantai 2, 12 cm
4.1 Beton Plat Lantai 158.655 M3 785,000 124,544,175
4.2 Pembesian Plat 1,077.27 Kg 18,000 19,390,814
4.3 Bekisting Plat 349.04 M2 146,574 51,160,171
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,611
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,003
5.4 Beton Bordes 0.650 M3 685,000 445,250
5.5 Pembesian Bordes 38.07 Kg 17,000 647,199
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096
6 Tangga C (Room)
6.1 Beton tangga 9.92 M3 535,000 5,306,130
6.2 Pembesian Tangga 560.47 Kg 17,000 9,527,925
6.3 Bekisting Tangga 94.62 M2 250,877 23,737,410
1 Kolom K1 100/60
1.1 Beton Kolom 54.60 M3 785,000 42,861,000.00
1.2 Pembesian Kolom 1,265.08 Kg 19,500 24,669,099.00
1.3 Bekisting kolom 473.22 M2 105,269 49,815,206.70
2 Balok B1 50/30
2.1 Beton Balok B1 38.35 M3 785,000 30,102,787.50
2.2 Pembesian Balok B1 1,104.02 Kg 19,500 21,528,478.24
2.3 Bekisting Balok B1 332.36 M2 105,269 34,986,971.41
4 Plat Lantai 2, 12 cm
4.1 Beton Plat Lantai 107.33 M3 785,000 84,255,306.00
4.2 Pembesian Plat 728.78 Kg 18,000 13,118,068.15
4.3 Bekisting Plat 236.13 M2 146,574 34,610,337.28
5 Tangga A
5.1 Beton tangga 1.69 M3 685,000 1,156,280.00
5.2 Pembesian Tangga 95.39 Kg 17,000 1,621,610.96
5.3 Bekisting Tangga 16.10 M2 250,877 4,040,002.79
5.4 Beton Bordes 0.650 M3 685,000 445,250.00
5.5 Pembesian Bordes 38.07 Kg 17,000 647,198.50
5.6 Bekisting Bordes 14.29 M2 146,574 2,094,096.02
6 Tangga D
6.1 Beton tangga 0.85 M3 535,000 456,997.00
6.2 Pembesian Tangga 48.27 Kg 17,000 820,604.31
6.3 Bekisting Tangga 8.15 M2 250,877 2,044,413.73
1 Plat Lantai 2, 12 cm
1.1 Beton Plat Lantai 58.719 M3 785,000 46,094,415.00
1.2 Pembesian Plat 398.70 Kg 18,000 7,176,636.18
1.3 Bekisting Plat 129.18 M2 146,574 18,934,632.44
AB COOR LIFT
2 Dinding Koorlift
2.1 Beton dinding Koorlift 7,419 M3 235,200 1,744,948,800.00
2.2 Pembesian Plat 171,898 Kg 17,000 2,922,269,910.00
2.3 Bekisting Plat 146 M2 146,574 21,431,981.56
2.4 Kawat Tarik 1 Bh 92,162,761 92,162,761.00
TOTAL 36,011,683,639.66
RENCANA ANGGARAN BIAYA ( ELECTRICAL)
RUMAH SAKIT, HOTEL & APARTMENT HIKMAH
A SERVICE LEVEL
3 KABEL FEEDER
3.1 Kabel Tegangan Menengah
3.1.1 Kabel dari Gardu PLN ke Incomonig Cubicle NXSEFGB 7.00 m' 600,000.00 4,200,000.00
3.1.2 Kabel dari Outgoing Cubicle ke Trafo N2XSY 3 x 1x 9 11.00 m' 500,000.00 5,500,000.00
3.2 Kabel Tegangan Rendah
3.2.1 Kabel Feeder Dari Trafo ke PUTR NYY 3 x 4 x (1 x 300 11.00 m' 3,750,000.00 41,250,000.00
3.2.2 Kabel Feeder Dari PKG ke PUTR NYY 3 x 4 x (1 x 300 12.50 m' 3,750,000.00 46,875,000.00
3.2.3 Kabel Sensing Dari PKG ke PUTR NYY 4 x 2.5 mm2 7.00 m' 20,000.00 140,000.00
3.2.4 Kabel Kontrol Dari Trafo (DGPT-2) ke PUTR NYY 3 x 2 8.50 m' 15,000.00 127,500.00
3.2.5 Kabel Kontrol Dari Trafo (DGPT-2) ke Cubicle (Shunt T 9.00 m' 15,000.00 135,000.00
3.2.6 LP BS Service - NYY 4 x 16 mm2 + BC 10 mm2 42.35 m' 86,000.00 3,642,100.00
3.2.7 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
3.2.8 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
5 PEKERJAAN TELEPHONE
5.1 Pengurusan Perizinan pemasangan line telepon Gedu 24.00 Buah 600,000.00 14,400,000.00
5.2 Pengadaan dan Pemasangan MDF150 Pair, Billing Sys 1.00 Buah 135,000,000.00 135,000,000.00
5.3 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 3.00 Buah 290,000.00 870,000.00
5.4 Panel Distribusi ( TB - TP ) 4 Pair 1.00 Unit 140,000.00 140,000.00
8 PEKERJAAN AC
8.1 AC 5.00 Buah 3,400,000.00 17,000,000.00
8.2 Testing & Commisison 5.00 Titik 200,000.00 1,000,000.00
10 PEKERJAAN CCTV
10.1 Digital Multiplexer Recorder hard disk 320 Gb, 16 1.00 Unit 87,550,000.00 87,550,000.00
10.2 LCD monitor 21 2.00 Unit 14,875,000.00 29,750,000.00
10.3 UPS 1KVA lengkap dengan back up battery, rectifier da 1.00 Unit 6,375,000.00 6,375,000.00
10.4 Pengkabelan untuk peralatan utama CCTV 1.00 Lot 1,487,500.00 1,487,500.00
10.5 Pekerjaan grounding sistem untuk peralatan utama C 1.00 Lot 3,612,375.00 3,612,375.00
10.6 Camera Fix Domme 2.00 Unit 4,462,500.00 8,925,000.00
10.7 Kabel Power NYM 3x1.5mm + conduit untuk camera 34.00 m' 21,038.00 715,292.00
10.8 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 34.00 m' 17,531.00 596,054.00
10.9 Testing & Commision 2.00 Titik 250,000.00 500,000.00
11 PEKERJAAN MATV
11.1 head end amplifier 1.00 Unit 4,560,000.00 4,560,000.00
11.2 Box panel TB - TV 6.00 Unit 960,000.00 5,760,000.00
11.3 Instalasi peralatan utama 1.00 Ls 5,400,000.00 5,400,000.00
11.4 TV Monitor 14", 1.00 Unit 1,500,000.00 1,500,000.00
11.5 Kabel dari antena UHF dan VHF ke ruang service ( Kont 34.00 m' 30,000.00 1,020,000.00
11.6 YAGI -VHF 23.00 Buah 400,000.00 9,200,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 107.00 m' 23,476.00 2,511,932.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 76.00 m' 43,032.00 3,270,432.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 145.00 m' 19,450.00 2,820,250.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 35.00 m' 12,329.00 431,515.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.10 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 6.00 Unit 290,000.00 1,740,000.00
3.20 Panel Distribusi ( TB - TP ) 6 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN AC
6.1 AC 18.00 Buah 3,400,000.00 61,200,000.00
6.2 Testing & Commisison 18.00 Titik 200,000.00 3,600,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 24.00 m' 30,000.00 720,000.00
9.2 kabel coaxial type 5-C 24.00 m' 18,000.00 432,000.00
9.3 Splitter 4 way 6.00 Buah 228,000.00 1,368,000.00
9.4 Outlet TV & T-Dos 7.00 Buah 126,000.00 882,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 124.00 m' 23,476.00 2,911,024.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 78.00 m' 19,450.00 1,517,100.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 41.00 m' 12,329.00 505,489.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.10 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 1.00 Unit 290,000.00 290,000.00
3.20 Panel Distribusi ( TB - TP ) 1 Pair 1.00 Unit 140,000.00 140,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 124.00 m' 23,476.00 2,911,024.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 78.00 m' 19,450.00 1,517,100.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 41.00 m' 12,329.00 505,489.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.10 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 1.00 Unit 228,000.00 228,000.00
3.20 Panel Distribusi ( TB - TP ) 1 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN CCTV
8.1 Camera Fix Domme 5.00 Unit 4,462,500.00 22,312,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 26.90 m' 21,038.00 565,922.20
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 26.90 m' 17,531.00 471,583.90
8.4 Testing & Commision 5.00 Titik 250,000.00 1,250,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 124.00 m' 23,476.00 2,911,024.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 78.00 m' 19,450.00 1,517,100.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 41.00 m' 12,329.00 505,489.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.10 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 1.00 Unit 270,000.00 270,000.00
3.20 Panel Distribusi ( TB - TP ) 1 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN CCTV
8.1 Camera Fix Domme 5.00 Unit 4,462,500.00 22,312,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 26.90 m' 21,038.00 565,922.20
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 26.90 m' 17,531.00 471,583.90
8.4 Testing & Commision 5.00 Titik 250,000.00 1,250,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 124.00 m' 23,476.00 2,911,024.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 78.00 m' 19,450.00 1,517,100.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 41.00 m' 12,329.00 505,489.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.10 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 1.00 Unit 270,000.00 270,000.00
3.20 Panel Distribusi ( TB - TP ) 1 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN CCTV
8.1 Camera Fix Domme 5.00 Unit 4,462,500.00 22,312,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 26.90 m' 21,038.00 565,922.20
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 26.90 m' 17,531.00 471,583.90
8.4 Testing & Commision 5.00 Titik 250,000.00 1,250,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 124.00 m' 23,476.00 2,911,024.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 78.00 m' 19,450.00 1,517,100.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 41.00 m' 12,329.00 505,489.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.10 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 1.00 Unit 270,000.00 270,000.00
3.20 Panel Distribusi ( TB - TP ) 1 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN CCTV
8.1 Camera Fix Domme 5.00 Unit 4,462,500.00 22,312,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 26.90 m' 21,038.00 565,922.20
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 26.90 m' 17,531.00 471,583.90
8.4 Testing & Commision 5.00 Titik 250,000.00 1,250,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 231.00 m' 23,476.00 5,422,956.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 76.00 m' 43,032.00 3,270,432.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 87.00 m' 19,450.00 1,692,150.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 54.00 m' 12,329.00 665,766.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 15.00 Unit 3,000,000.00 45,000,000.00
3.2 Panel Distribusi ( TB - TP ) 15 Pair 1.00 Unit 1,241,000.00 1,241,000.00
6 PEKERJAAN AC
6.1 AC 36.00 Buah 3,400,000.00 122,400,000.00
6.2 Testing & Commisison 36.00 Titik 200,000.00 7,200,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 5.00 Unit 4,462,500.00 22,312,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 48.00 m' 21,038.00 1,009,824.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 48.00 m' 17,531.00 841,488.00
8.4 Testing & Commision 5.00 Titik 250,000.00 1,250,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 96.50 m' 30,000.00 2,895,000.00
9.2 kabel coaxial type 5-C 96.50 m' 18,000.00 1,737,000.00
9.3 Splitter 4 way 6.00 Buah 228,000.00 1,368,000.00
9.4 Outlet TV & T-Dos 6.00 Buah 126,000.00 756,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 241.00 m' 23,476.00 5,657,716.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 45.00 m' 43,032.00 1,936,440.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 64.00 m' 19,450.00 1,244,800.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 45.00 m' 12,329.00 554,805.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 14.00 Unit 270,000.00 3,780,000.00
3.2 Panel Distribusi ( TB - TP ) 14 Pair 1.00 Unit 1,243,000.00 1,243,000.00
6 PEKERJAAN AC
6.1 AC 37.00 Buah 3,400,000.00 125,800,000.00
6.2 Testing & Commisison 37.00 Titik 200,000.00 7,400,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 6.00 Unit 4,462,500.00 26,775,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 78.00 m' 17,531.00 1,367,418.00
8.4 Testing & Commision 6.00 Titik 250,000.00 1,500,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 147.00 m' 30,000.00 4,410,000.00
9.2 kabel coaxial type 5-C 146.00 m' 18,000.00 2,628,000.00
9.3 Splitter 4 way 6.00 Buah 228,000.00 1,368,000.00
9.4 Outlet TV & T-Dos 16.00 Buah 126,000.00 2,016,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 211.00 m' 23,476.00 4,953,436.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 46.00 m' 43,032.00 1,979,472.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 68.00 m' 19,450.00 1,322,600.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 34.00 m' 12,329.00 419,186.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 4.00 Unit 270,000.00 1,080,000.00
3.2 Panel Distribusi ( TB - TP ) 4 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN AC
6.1 AC 49.00 Buah 3,400,000.00 166,600,000.00
6.2 Testing & Commisison 49.00 Titik 200,000.00 9,800,000.00
7 PEKERJAAN FIRE ALARAM
7.1 ROR (Rate Of Rise) 33.00 Buah 174,960.00 5,773,680.00
7.2 Heat Detector 8.00 Buah 216,000.00 1,728,000.00
7.3 Smoke Detector 9.00 Buah 270,000.00 2,430,000.00
7.4 Alaram bell, lampu indikator, break glass 9.00 Set 432,000.00 3,888,000.00
7.5 Flow swich 1.00 Titik 270,000.00 270,000.00
7.6 Instalasi detektor 50.00 Ls 300,000.00 15,000,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 8.00 Unit 4,462,500.00 35,700,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 98.00 m' 21,038.00 2,061,724.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 121.00 m' 17,531.00 2,121,251.00
8.4 Testing & Commision 6.00 Titik 250,000.00 1,500,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 147.00 m' 30,000.00 4,410,000.00
9.2 kabel coaxial type 5-C 146.00 m' 18,000.00 2,628,000.00
9.3 Splitter 4 way 6.00 Buah 228,000.00 1,368,000.00
9.4 Outlet TV & T-Dos 15.00 Buah 126,000.00 1,890,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 113.00 m' 23,476.00 2,652,788.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 153.00 m' 43,032.00 6,583,896.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 45.00 m' 19,450.00 875,250.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 34.00 m' 12,329.00 419,186.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 6.00 Unit 270,000.00 1,620,000.00
3.2 Panel Distribusi ( TB - TP ) 6 Pair 1.00 Unit 240,000.00 240,000.00
6 PEKERJAAN AC
6.1 AC 27.00 Buah 3,400,000.00 91,800,000.00
6.2 Testing & Commisison 27.00 Titik 200,000.00 5,400,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 147.00 m' 30,000.00 4,410,000.00
9.2 kabel coaxial type 5-C 146.00 m' 18,000.00 2,628,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 15.00 Buah 126,000.00 1,890,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 143.00 m' 23,476.00 3,357,068.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 112.00 m' 43,032.00 4,819,584.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 76.00 m' 19,450.00 1,478,200.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 45.00 m' 12,329.00 554,805.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 36.00 Unit 270,000.00 9,720,000.00
3.2 Panel Distribusi ( TB - TP ) 36 Pair 1.00 Unit 4,320,000.00 4,320,000.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 5.00 Unit 4,462,500.00 22,312,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 5.00 Titik 250,000.00 1,250,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 245.00 m' 30,000.00 7,350,000.00
9.2 kabel coaxial type 5-C 197.00 m' 18,000.00 3,546,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 44.00 Buah 126,000.00 5,544,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 87.00 m' 23,476.00 2,042,412.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 67.00 m' 43,032.00 2,883,144.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 89.00 m' 19,450.00 1,731,050.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 32.00 m' 12,329.00 394,528.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 32.00 Unit 270,000.00 8,640,000.00
3.2 Panel Distribusi ( TB - TP ) 32 Pair 1.00 Unit 4,123,674.00 4,123,674.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 7.00 Unit 4,462,500.00 31,237,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 7.00 Titik 250,000.00 1,750,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 321.00 m' 30,000.00 9,630,000.00
9.2 kabel coaxial type 5-C 210.00 m' 18,000.00 3,780,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 32.00 Buah 126,000.00 4,032,000.00
N 13th FLOOR LEVEL (HOTEL + MEZZANINE)
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 96.00 m' 23,476.00 2,253,696.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 153.00 m' 19,450.00 2,975,850.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 240.00 m' 12,329.00 2,958,960.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 31.00 Unit 270,000.00 8,370,000.00
3.2 Panel Distribusi ( TB - TP ) 31 Pair 1.00 Unit 3,943,000.00 3,943,000.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 159.00 m' 30,000.00 4,770,000.00
9.2 kabel coaxial type 5-C 251.00 m' 18,000.00 4,518,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 31.00 Buah 126,000.00 3,906,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 96.00 m' 23,476.00 2,253,696.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 153.00 m' 19,450.00 2,975,850.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 240.00 m' 12,329.00 2,958,960.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 31.00 Unit 270,000.00 8,370,000.00
3.2 Panel Distribusi ( TB - TP ) 31 Pair 1.00 Unit 3,943,000.00 3,943,000.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 159.00 m' 30,000.00 4,770,000.00
9.2 kabel coaxial type 5-C 251.00 m' 18,000.00 4,518,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 31.00 Buah 126,000.00 3,906,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 96.00 m' 23,476.00 2,253,696.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 153.00 m' 19,450.00 2,975,850.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 240.00 m' 12,329.00 2,958,960.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 31.00 Unit 270,000.00 8,370,000.00
3.2 Panel Distribusi ( TB - TP ) 31 Pair 1.00 Unit 3,943,000.00 3,943,000.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 159.00 m' 30,000.00 4,770,000.00
9.2 kabel coaxial type 5-C 251.00 m' 18,000.00 4,518,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 31.00 Buah 126,000.00 3,906,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 96.00 m' 23,476.00 2,253,696.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 153.00 m' 19,450.00 2,975,850.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 240.00 m' 12,329.00 2,958,960.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 31.00 Unit 270,000.00 8,370,000.00
3.2 Panel Distribusi ( TB - TP ) 31 Pair 1.00 Unit 3,943,000.00 3,943,000.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 159.00 m' 30,000.00 4,770,000.00
9.2 kabel coaxial type 5-C 251.00 m' 18,000.00 4,518,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 31.00 Buah 126,000.00 3,906,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 96.00 m' 23,476.00 2,253,696.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 153.00 m' 19,450.00 2,975,850.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 240.00 m' 12,329.00 2,958,960.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 31.00 Unit 270,000.00 8,370,000.00
3.2 Panel Distribusi ( TB - TP ) 31 Pair 1.00 Unit 3,943,000.00 3,943,000.00
6 PEKERJAAN AC
6.1 AC 44.00 Buah 3,400,000.00 149,600,000.00
6.2 Testing & Commisison 44.00 Titik 200,000.00 8,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 159.00 m' 30,000.00 4,770,000.00
9.2 kabel coaxial type 5-C 251.00 m' 18,000.00 4,518,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 31.00 Buah 126,000.00 3,906,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 96.00 m' 23,476.00 2,253,696.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 56.00 m' 43,032.00 2,409,792.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 153.00 m' 19,450.00 2,975,850.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 240.00 m' 12,329.00 2,958,960.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 31.00 Unit 270,000.00 8,370,000.00
3.2 Panel Distribusi ( TB - TP ) 31 Pair 1.00 Unit 3,943,000.00 3,943,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 159.00 m' 30,000.00 4,770,000.00
9.2 kabel coaxial type 5-C 251.00 m' 18,000.00 4,518,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 31.00 Buah 126,000.00 3,906,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 34.00 m' 23,476.00 798,184.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 21.00 m' 43,032.00 903,672.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 43.00 m' 19,450.00 836,350.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 67.00 m' 12,329.00 826,043.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 21.00 Unit 270,000.00 5,670,000.00
3.2 Panel Distribusi ( TB - TP ) 21 Pair 1.00 Unit 2,421,000.00 2,421,000.00
6 PEKERJAAN AC
6.1 AC 40.00 Buah 3,400,000.00 136,000,000.00
6.2 Testing & Commisison 40.00 Titik 200,000.00 8,000,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 113.00 m' 30,000.00 3,390,000.00
9.2 kabel coaxial type 5-C 96.00 m' 18,000.00 1,728,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 20.00 Buah 126,000.00 2,520,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 34.00 m' 23,476.00 798,184.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 21.00 m' 43,032.00 903,672.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 43.00 m' 19,450.00 836,350.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 67.00 m' 12,329.00 826,043.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 21.00 Unit 270,000.00 5,670,000.00
3.2 Panel Distribusi ( TB - TP ) 21 Pair 1.00 Unit 2,421,000.00 2,421,000.00
6 PEKERJAAN AC
6.1 AC 40.00 Buah 3,400,000.00 136,000,000.00
6.2 Testing & Commisison 40.00 Titik 200,000.00 8,000,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 113.00 m' 30,000.00 3,390,000.00
9.2 kabel coaxial type 5-C 96.00 m' 18,000.00 1,728,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 20.00 Buah 126,000.00 2,520,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 34.00 m' 23,476.00 798,184.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 21.00 m' 43,032.00 903,672.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 43.00 m' 19,450.00 836,350.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 67.00 m' 12,329.00 826,043.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 21.00 Unit 270,000.00 5,670,000.00
3.2 Panel Distribusi ( TB - TP ) 21 Pair 1.00 Unit 2,421,000.00 2,421,000.00
6 PEKERJAAN AC
6.1 AC 40.00 Buah 3,400,000.00 136,000,000.00
6.2 Testing & Commisison 40.00 Titik 200,000.00 8,000,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 113.00 m' 30,000.00 3,390,000.00
9.2 kabel coaxial type 5-C 96.00 m' 18,000.00 1,728,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 20.00 Buah 126,000.00 2,520,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 34.00 m' 23,476.00 798,184.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 21.00 m' 43,032.00 903,672.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 43.00 m' 19,450.00 836,350.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 67.00 m' 12,329.00 826,043.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 21.00 Unit 270,000.00 5,670,000.00
3.2 Panel Distribusi ( TB - TP ) 21 Pair 1.00 Unit 2,421,000.00 2,421,000.00
6 PEKERJAAN AC
6.1 AC 40.00 Buah 3,400,000.00 136,000,000.00
6.2 Testing & Commisison 40.00 Titik 200,000.00 8,000,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 113.00 m' 30,000.00 3,390,000.00
9.2 kabel coaxial type 5-C 96.00 m' 18,000.00 1,728,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 20.00 Buah 126,000.00 2,520,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 21.00 Unit 270,000.00 5,670,000.00
3.2 Panel Distribusi ( TB - TP ) 21 Pair 1.00 Unit 2,421,000.00 2,421,000.00
6 PEKERJAAN AC
6.1 AC 40.00 Buah 3,400,000.00 136,000,000.00
6.2 Testing & Commisison 40.00 Titik 200,000.00 8,000,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 4.00 Unit 4,462,500.00 17,850,000.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 78.00 m' 21,038.00 1,640,964.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 111.00 m' 17,531.00 1,945,941.00
8.4 Testing & Commision 4.00 Titik 250,000.00 1,000,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 113.00 m' 30,000.00 3,390,000.00
9.2 kabel coaxial type 5-C 96.00 m' 18,000.00 1,728,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 20.00 Buah 126,000.00 2,520,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 21.00 m' 23,476.00 492,996.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 27.00 m' 43,032.00 1,161,864.00
1.3 NYY 4 x 10 mm2 + BC 6 mm2 43.00 m' 19,450.00 836,350.00
1.4 NYY 4 x 6 mm2 + BC 4 mm2 54.00 m' 12,329.00 665,766.00
1.5 Material Bantu 1.00 Ls 3,000,000.00 3,000,000.00
1.6 Testing & Commissioning 1.00 Ls 5,000,000.00 5,000,000.00
2 LIGHTING & SOCKET OUTLET INSTALLATION
2.1 Lampu down light 18 watt 12.00 Buah 55,250.00 663,000.00
2.2 Lampu TKO 2x18 watt 13.00 Buah 54,450.00 707,850.00
2.3 Lampu RM 2x36 watt 2.00 Buah 67,437.00 134,874.00
2.4 TL 2 x 18 W TKI + Battery 2.00 Buah 515,313.00 1,030,626.00
2.5 Exit 2 x 10 W + Battery 1.00 Buah 949,375.00 949,375.00
2.6 Instalasi Penerangan, NYM 3x2,5 mm2 (In Conduit PVC 75.00 Titik 211,250.00 15,843,750.00
2.7 Instalasi Stop Kontak, NYM 3x2,5 mm2 (In Conduit PVC 75.00 Titik 241,250.00 18,093,750.00
2.8 Stop Kontak 1Phase 10 A 200 Watt 12.00 Buah 45,625.00 547,500.00
2.9 Saklar Seri 25.00 Buah 14,345.00 358,625.00
2.10 Saklar Tunggal 4.00 Buah 16,430.00 65,720.00
2.11 Testing & Commision 1.00 Ls 3,000,000.00 3,000,000.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 4.00 Unit 270,000.00 1,080,000.00
3.2 Panel Distribusi ( TB - TP ) 4 Pair 1.00 Unit 140,000.00 140,000.00
6 PEKERJAAN AC
6.1 AC 9.00 Buah 3,400,000.00 30,600,000.00
6.2 Testing & Commisison 9.00 Titik 200,000.00 1,800,000.00
8 PEKERJAAN CCTV
8.1 Camera Fix Domme 3.00 Unit 4,462,500.00 13,387,500.00
8.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 24.00 m' 21,038.00 504,912.00
8.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 43.00 m' 17,531.00 753,833.00
8.4 Testing & Commision 3.00 Titik 250,000.00 750,000.00
9 PEKERJAAN MATV
9.1 kabel coaxial type 7-C 34.00 m' 30,000.00 1,020,000.00
9.2 kabel coaxial type 5-C 34.00 m' 18,000.00 612,000.00
9.3 Splitter 4 way 3.00 Buah 228,000.00 684,000.00
9.4 Outlet TV & T-Dos 2.00 Buah 126,000.00 252,000.00
1 KABEL FEEDER
1.1 NYY 4 x 35 mm2 + BC 25 mm2 21.00 m' 23,476.00 492,996.00
1.2 NYY 4 x 120 mm2 + BC 50 mm2 27.00 m' 43,032.00 1,161,864.00
3 PEKERJAAN TELEPHONE
3.1 Kabel ITC 3 x 0.6 mm (Inconduit Pipa PVC dia.20), sok, 1.00 Unit 270,000.00 270,000.00
3.2 Panel Distribusi ( TB - TP ) 1 Pair 1.00 Unit 140,000.00 140,000.00
4 PEKERJAAN CCTV
4.1 Camera Day & Night + Housing 3.00 Unit 7,241,500.00 21,724,500.00
4.2 Kabel Power NYM 3x1.5mm + conduit untuk camera 24.00 m' 21,038.00 504,912.00
4.3 Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 43.00 m' 17,531.00 753,833.00
4.4 Testing & Commision 3.00 Titik 250,000.00 750,000.00
TOTAL 9,679,053,270.50
RENCANA ANGGARAN BIAYA ( FURNITURE)
RUMAH SAKIT, HOTEL & APARTEMENT HIKMAH
A #REF!
B #REF!
D #REF!
E #REF!
F #REF!
G #REF!
H #REF!
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (RP) TOTAL (Rp)
HOSPITAL
1 Kursi Tunggu ( 5 Seat) 7.00 Unit 654,000.00 4,578,000.00
2 Meja Kerja 4.00 Unit 784,500.00 3,138,000.00
3 Kursi Kerja 4.00 Unit 487,000.00 1,948,000.00
4 Kursi Biasa 15.00 Unit 75,600.00 1,134,000.00
5 Lemari File 2.00 Unit 1,325,000.00 2,650,000.00
6 Lemari Locker 2.00 Unit 4,500,000.00 9,000,000.00
7 TV Monitor 14", 2.00 Unit 1,745,000.00 3,490,000.00
8 TV Flat 20'' 13.00 Unit 4,256,000.00 55,328,000.00
9 Refrigator mini 12.00 Unit 2,500,000.00 30,000,000.00
10 Bath Room Hanger 60.00 Unit 74,500.00 4,470,000.00
11 Meja Rak 12.00 Unit 2,150,000.00 25,800,000.00
12 Kursi Roda 3.00 Unit 2,155,000.00 6,465,000.00
13 Brankar 2.00 Unit 3,875,000.00 7,750,000.00
14 Bed Pasien 13.00 Unit 3,357,000.00 43,641,000.00
15 Rak Peralatan Medis 5.00 Unit 4,200,500.00 21,002,500.00
16 Cermin dinding 50x30 cm 13.00 Unit 230,000.00 2,990,000.00
17 Bed Cover 24.00 Unit 326,000.00 7,824,000.00
18 Bantal 24.00 Unit 43,500.00 1,044,000.00
19 Tempat Sampah Stenlistill 17.00 Unit 425,000.00 7,225,000.00
HOTELS
20 Bed Queen size 160x200 cm 24.00 Unit 7,915,000.00 189,960,000.00
21 Bed King size 200 x 200 cm 6.00 Unit 9,750,000.00 58,500,000.00
22 TV Flat 20", 24.00 Unit 4,256,000.00 102,144,000.00
23 TV Flat 24", 6.00 Unit 4,756,000.00 28,536,000.00
24 Bed Cover Hotel 60.00 Unit 475,500.00 28,530,000.00
25 Bantal Hotel 60.00 Unit 98,500.00 5,910,000.00
26 Nakas 60.00 Unit 1,500,000.00 90,000,000.00
27 Meja Rias 30.00 Unit 2,900,000.00 87,000,000.00
28 Bath Room Hanger 180.00 Unit 74,500.00 13,410,000.00
29 Cermin dinding 80x150 cm 30.00 Unit 425,500.00 12,765,000.00
30 Lemari Pakaian 30.00 Unit 6,250,000.00 187,500,000.00
31 Tempat Sampah Stenlistill 35.00 Unit 425,000.00 14,875,000.00
37 Refrigator mini 30.00 Unit 2,500,000.00 75,000,000.00
38 Water Dispenser 6.00 Unit 750,000.00 4,500,000.00
UMUM
39 Smoke Filter 8.00 Unit 3,050,000.00 24,400,000.00
40 Komputer PC 4.00 Unit 6,500,000.00 26,000,000.00
41 Meja PC 4.00 Unit 1,250,000.00 5,000,000.00
42 Printer 2.00 Unit 2,100,000.00 4,200,000.00
43 Refrigator 40 Ltr 4.00 Unit 3,954,000.00 15,816,000.00
44 Water Dispenser 3.00 Unit 750,000.00 2,250,000.00
45 Sofa 2 Seater 3.00 Unit 4,500,000.00 13,500,000.00
46 Sofa 4 Seater 6.00 Unit 6,100,000.00 36,600,000.00
J #REF!
K #REF!
L #REF!
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (RP) TOTAL (Rp)
1 Sofa 2 Seater 4.00 Unit 654,000.00 2,616,000.00
2 Sofa 1 Seater 72.00 Unit 654,000.00 47,088,000.00
3 Bed Queen size 160x200 cm 18.00 Unit 7,915,000.00 142,470,000.00
4 Bed King size 200 x 200 cm 18.00 Unit 9,750,000.00 175,500,000.00
5 TV Flat 20", 18.00 Unit 4,256,000.00 76,608,000.00
6 TV Flat 24", 18.00 Unit 4,756,000.00 85,608,000.00
7 Bed Cover 72.00 Unit 475,500.00 34,236,000.00
8 Pillow 288.00 Unit 98,500.00 28,368,000.00
9 Long Pillow 288.00 75,000.00 21,600,000.00
10 Nakas 144.00 Unit 1,500,000.00 216,000,000.00
11 Meja Rias 36.00 Unit 2,900,000.00 104,400,000.00
12 Gradenza 36.00 Unit 3,725,000.00 134,100,000.00
13 Bath Room Hanger 252.00 Unit 74,500.00 18,774,000.00
14 Cermin dinding 80x150 cm 36.00 Unit 425,500.00 15,318,000.00
15 Lemari Pakaian 36.00 Unit 6,250,000.00 225,000,000.00
16 Tempat Sampah Stenlistill 43.00 Unit 425,000.00 18,275,000.00
17 Refrigator mini 18.00 Unit 2,500,000.00 45,000,000.00
18 Water Dispenser 18.00 Unit 750,000.00 13,500,000.00
19 Smoke Filter 25.00 Unit 3,050,000.00 76,250,000.00
M #REF!
N #REF!
O #REF!
P #REF!
Q #REF!
R #REF!
S #REF!
T #REF!
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN (RP) TOTAL (Rp)
1 Sofa 2 Seater 4.00 Unit 654,000.00 2,616,000.00
2 Sofa 1 Seater 28.00 Unit 654,000.00 18,312,000.00
3 Bed Queen size 160x200 cm 7.00 Unit 7,915,000.00 55,405,000.00
4 Bed King size 200 x 200 cm 7.00 Unit 9,750,000.00 68,250,000.00
5 TV Flat 20", 7.00 Unit 4,256,000.00 29,792,000.00
6 TV Flat 24", 7.00 Unit 4,756,000.00 33,292,000.00
7 Bed Cover 28.00 Unit 475,500.00 13,314,000.00
8 Pillow 112.00 Unit 98,500.00 11,032,000.00
9 Long Pillow 112.00 Unit 75,000.00 8,400,000.00
10 Nakas 56.00 Unit 1,500,000.00 84,000,000.00
11 Meja Rias 14.00 Unit 2,900,000.00 40,600,000.00
12 Gradenza 14.00 Unit 3,725,000.00 52,150,000.00
13 Bath Room Hanger 98.00 Unit 74,500.00 7,301,000.00
14 Cermin dinding 80x150 cm 14.00 Unit 425,500.00 5,957,000.00
15 Lemari Pakaian 14.00 Unit 6,250,000.00 87,500,000.00
16 Tempat Sampah Stenlistill 21.00 Unit 425,000.00 8,925,000.00
17 Refrigator mini 14.00 Unit 2,500,000.00 35,000,000.00
18 Water Dispenser 14.00 Unit 750,000.00 10,500,000.00
19 Smoke Filter 21.00 Unit 3,050,000.00 64,050,000.00
U #REF!
TOTAL 22,791,364,990.00
PB 6.17 1 m3 Pembuatan tiang pancang 40 cm X 40 cm beton bertulang
6.17.1 B a h a n
Pasir urug darat 0,019 M3 x
Pasir Beton 0,094 M3 x
Koral Beton 0,150 M3 x
Semen Abu-Abu 60,50 KG x
Besi Beton 45,00 KG x
Kawat Beton 0,900 KG x
Kayu Kaso 5/7 0,032 M3 x
Paku 0,120 KG x
Minyak bekisting 0,090 KG x
Plamuur Tembok 0,240 M2 x
6.17.2 T e n a g a
Pekerja 1,000 Oh x
Tukang batu 0,670 Oh x
Kepala tukang 0,067 Oh x
Mandor 0,050 Oh x
PB 6.12 Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
6.12.1 Bahan
PC 448,000 Kg x Rp 1,575 = Rp 705,600,000
PB 667 Kg x Rp 2,880 = Rp 1,920,960
KR (Min 3mm) 1000 Kg x Rp 4,714 = Rp 4,714,000
Air 215 Liter x Rp 10 = Rp 2,150
Jumlah (1) Rp 712,237,110
6.12.2 Tenaga
Pekerja 2.1 Oh x 80,000 = Rp 168,000
Tukang Batu 0.35 Oh x 100,000 = Rp 35,000
Kepala Tukang 0.035 Oh x 110,000 = Rp 3,850
Mandor 0.105 Oh x 100,000 = Rp 10,500
Jumlah (2) = Rp 217,350
Jumlah (1) + (2) = Rp 712,454,460
6.13.1. Bahan
- Semen portland 336.000 Kg x Rp. 1,575 = Rp. 529,200.00
- Pasir beton 0.540 M³ x Rp. 144,000 = Rp. 77,760.00
- Koral beton/batu pecah 2/3 0.810 M³ x Rp. 123,200 = Rp. 99,792.00
Jumlah (1) = Rp. 706,752.00
6.13.2. Tenaga
- Pekerja 2.000 Oh x Rp. 80,000 = Rp. 160,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00
- Mandor 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
Jumlah (2) = Rp. 298,850.00
Jumlah (1) + (2) = Rp. 1,005,602.00
6.14.1. Bahan
- Semen portland 291.000 Kg x Rp. 1,575 = Rp. 458,325.00
- Pasir beton 0.470 M³ x Rp. 144,000 = Rp. 67,680.00
- Koral beton/batu pecah 2/3 0.930 M³ x Rp. 123,200 = Rp. 114,576.00
Jumlah (1) = Rp. 640,581.00
6.14.2. Tenaga
- Pekerja 2.000 Oh x Rp. 80,000 = Rp. 160,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00
- Mandor 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
Jumlah (2) = Rp. 298,850.00
Jumlah (1) + (2) = Rp. 939,431.00
6.15.1. Bahan
- Semen portland 367.000 Kg x Rp. 1,575 = Rp. 578,025.00
- Pasir beton 0.440 M³ x Rp. 144,000 = Rp. 63,360.00
- Koral beton 2/3 0.880 M³ x Rp. 123,200 = Rp. 108,416.00
Jumlah (1) = Rp. 749,801.00
6.15.2. Tenaga
6.17.1. Bahan
- Semen portland 615.000 Kg x Rp. 1,575 = Rp. 968,625.00
- Pasir beton 0.520 M³ x Rp. 144,000 = Rp. 74,880.00
- Koral beton 2/3 0.520 M³ x Rp. 123,200 = Rp. 64,064.00
Jumlah (1) = Rp. 1,107,569.00
6.17.2. Tenaga
- Pekerja 2.000 Oh x Rp. 80,000 = Rp. 160,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00
- Mandor 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
Jumlah (2) = Rp. 298,850.00
Jumlah (1) + (2) = Rp. 1,406,419.00
6.25.1 Bahan
Besi beton polos 1.050 Kg x Rp. Err:509 = Rp. Err:509
Kawat beton 0.015 Kg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.25.2 Tenaga
Pekerja 0.007 Oh x Rp. 0= Rp. 0.00
Tukang besi 0.007 Oh x Rp. Err:509 = Rp. Err:509
Kepala tukang 0.007 Oh x Rp. 0= Rp. 0.00
Mandor 0.003 Oh x Rp. x = Rp. #VALUE!
Jumlah (2) = Rp. Err:509
Jumlah (1) + (2) = Rp. Err:509
6.26.1 Bahan
Besi Presstressed polos 1.050 Kg x Rp. Err:509 = Rp. Err:509
Kawat beton 0.010 Kg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.26.2 Tenaga
Pekerja 0.005 Oh x Rp. 0= Rp. 0.00
Tukang besi 0.005 Oh x Rp. Err:509 = Rp. Err:509
Kepala tukang 0.005 Oh x Rp. 0= Rp. 0.00
Mandor 0.003 Oh x Rp. x = Rp. #VALUE!
Jumlah (2) = Rp. Err:509
Jumlah (1) + (2) = Rp. Err:509
6.28.1 Bahan
Kayu sembarang 0.040 M³ x Rp. Err:509 = Rp. Err:509
Paku biasa 2" - 5" 0.300 Kg x Rp. Err:509 = Rp. Err:509
Minyak bekisting 0.100 Ltr x Rp. 12,710 = Rp. 1,271.00
Jumlah (1) = Rp. Err:509
6.28.2 Tenaga
Pekerja 0.300 Oh x Rp. 0= Rp. 0.00
Tukang besi 0.260 Oh x Rp. Err:509 = Rp. Err:509
Kepala tukang 0.026 Oh x Rp. 0= Rp. 0.00
Mandor 0.005 Oh x Rp. x = Rp. #VALUE!
Jumlah (2) = Rp. Err:509
Jumlah (1) + (2) = Rp. Err:509
6.29.1. Bahan
- Kayu sembarang 0.045 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2' - 5" 0.300 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.100 Lt x Rp. 12,710 = Rp. 1,271.00
Jumlah (1) = Rp. Err:509
6.29.2. Tenaga
- Pekerja 0.300 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.260 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.026 Oh x Rp. 0= Rp. 0.00
- Mandor 0.005 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.30.1. Bahan
- Kayu sembarang 0.040 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2' - 5" 0.400 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.200 Lt x Rp. 12,710 = Rp. 2,542.00
- Balok kayu sembarang 0.015 M³ x Rp. Err:509 = Rp. Err:509
- Plywood tebal 9 mm 0.350 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 2.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.30.2. Tenaga
- Pekerja 0.300 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.330 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.033 Oh x Rp. 0= Rp. 0.00
- Mandor 0.006 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.31.1. Bahan
- Kayu sembarang 0.040 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2' - 5" 0.400 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.200 Lt x Rp. 12,710 = Rp. 2,542.00
- Balok kayu sembarang 0.018 M³ x Rp. Err:509 = Rp. Err:509
- Plywood tebal 9 mm 0.350 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 2.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.31.2. Tenaga
- Pekerja 0.320 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.330 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.033 Oh x Rp. 0= Rp. 0.00
- Mandor 0.006 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.32.1. Bahan
- Kayu sembarang 0.040 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2' - 5" 0.400 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.200 Lt x Rp. 12,710 = Rp. 2,542.00
- Balok kayu sembarang 0.015 M³ x Rp. Err:509 = Rp. Err:509
- Plywood tebal 9 mm 0.350 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 6.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.32.2. Tenaga
- Pekerja 0.320 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.330 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.033 Oh x Rp. 0= Rp. 0.00
- Mandor 0.006 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.33.1. Bahan
- Kayu sembarang 0.030 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2' - 5" 0.400 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.200 Lt x Rp. 12,710 = Rp. 2,542.00
- Balok kayu sembarang 0.020 M³ x Rp. Err:509 = Rp. Err:509
- Plywood tebal 9 mm 0.350 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 3.000 Btg x Rp. Err:509 = Rp. Err:509
- Formtie/penjaga jarak bekisting/ 4.000 Btg x Rp. 5,000 = Rp. 20,000.00
Jumlah (1) = Rp. Err:509
6.33.2. Tenaga
- Pekerja 0.320 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.330 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.033 Oh x Rp. 0= Rp. 0.00
- Mandor 0.006 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.34.2. Tenaga
- Pekerja 0.320 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.330 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.033 Oh x Rp. 0= Rp. 0.00
- Mandor 0.006 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.35.1. Bahan
- Semen portland 388.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.650 M³ x Rp. Err:509 = Rp. Err:509
- Batu pecah 0.650 M³ x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.35.2. Tenaga
- Pekerja 6.000 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 1.000 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.100 Oh x Rp. 0= Rp. 0.00
- Mandor 0.300 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.36.1. Bahan
- Semen portland 400.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.400 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.820 M³ x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.36.2. Tenaga
- Pekerja 6.000 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 1.000 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.100 Oh x Rp. 0= Rp. 0.00
- Mandor 0.300 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.37.1. Bahan
- Kayu sembarang 0.0264 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 0.600 Kg x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 0.500 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.37.2. Tenaga
- Pekerja 0.150 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.050 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.005 Oh x Rp. 0= Rp. 0.00
- Mandor 0.007 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.38.1. Bahan
- Kayu sembarang 0.2000 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 1.500 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.400 Lt x Rp. 12,710 = Rp. 5,084.00
- Besi beton polos 150.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 2.250 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.38.2. Tenaga
- Pekerja 3.900 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 1.040 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 1.050 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.245 Oh x Rp. 0= Rp. 0.00
- Mandor 0.165 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.39.1. Bahan
- Kayu sembarang 0.2700 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 2.000 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 0.600 Lt x Rp. 12,710 = Rp. 7,626.00
- Besi beton polos 200.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 3.000 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.39.2. Tenaga
- Pekerja 4.850 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 1.560 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 1.400 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.331 Oh x Rp. 0= Rp. 0.00
- Mandor 0.170 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.40.1. Bahan
- Kayu sembarang 0.4000 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 4.000 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 2.000 Lt x Rp. 12,710 = Rp. 25,420.00
- Besi beton polos 300.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 4.500 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
- Kayu sembarang balok 0.150 M³ x Rp. Err:509 = Rp. Err:509
- Plywood 9 mm 3.500 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 20.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.40.2. Tenaga
- Pekerja 7.300 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 3.300 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 2.100 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.570 Oh x Rp. 0= Rp. 0.00
- Mandor 0.250 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.41.1. Bahan
- Kayu sembarang 0.3200 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 3.200 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 1.600 Lt x Rp. 12,710 = Rp. 20,336.00
- Besi beton polos 200.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 3.000 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
- Kayu sembarang balok 0.140 M³ x Rp. Err:509 = Rp. Err:509
- Plywood 9 mm 2.800 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 16.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.41.2. Tenaga
- Pekerja 5.960 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 2.800 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 1.400 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.455 Oh x Rp. 0= Rp. 0.00
- Mandor 0.208 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.42.1. Bahan
- Kayu sembarang 0.320 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 3.200 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 1.600 Lt x Rp. 12,710 = Rp. 20,336.00
- Besi beton polos 150.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 2.250 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
- Kayu sembarang balok 0.120 M³ x Rp. Err:509 = Rp. Err:509
- Plywood 9 mm 2.800 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 32.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.42.2. Tenaga
- Pekerja 5.800 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 2.800 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 1.050 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.420 Oh x Rp. 0= Rp. 0.00
- Mandor 0.185 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.43.1. Bahan
- Kayu sembarang 0.240 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 3.200 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 1.600 Lt x Rp. 12,710 = Rp. 20,336.00
- Besi beton polos 150.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 2.250 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
- Kayu sembarang balok 0.160 M³ x Rp. Err:509 = Rp. Err:509
- Plywood 9 mm 2.800 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 24.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.43.2. Tenaga
- Pekerja 5.600 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 2.640 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 1.050 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.400 Oh x Rp. 0= Rp. 0.00
- Mandor 0.193 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
6.44.1. Bahan
- Kayu sembarang 0.250 M³ x Rp. Err:509 = Rp. Err:509
- Paku biasa 2" - 5 " 3.000 Kg x Rp. Err:509 = Rp. Err:509
- Minyak bekisting 1.200 Lt x Rp. 12,710 = Rp. 15,252.00
- Besi beton polos 200.000 Kg x Rp. Err:509 = Rp. Err:509
- Kawat beton 3.000 Kg x Rp. Err:509 = Rp. Err:509
- Semen portland 323.000 Kg x Rp. Err:509 = Rp. Err:509
- Pasir beton 0.520 M³ x Rp. Err:509 = Rp. Err:509
- Koral beton 0.780 M³ x Rp. Err:509 = Rp. Err:509
- Kayu sembarang balok 0.105 M³ x Rp. Err:509 = Rp. Err:509
- Plywood 9 mm 2.500 Lbr x Rp. Err:509 = Rp. Err:509
- Kayu dolken/Laut Ø 3"-4"/4 m 14.000 Btg x Rp. Err:509 = Rp. Err:509
Jumlah (1) = Rp. Err:509
6.44.2. Tenaga
- Pekerja 5.600 Oh x Rp. x = Rp. #VALUE!
- Tukang batu 0.350 Oh x Rp. x = Rp. #VALUE!
- Tukang kayu 2.300 Oh x Rp. x = Rp. #VALUE!
- Tukang besi 1.400 Oh x Rp. x = Rp. #VALUE!
- Kepala tukang 0.405 Oh x Rp. 0= Rp. 0.00
- Mandor 0.202 Oh x Rp. 0= Rp. 0.00
Jumlah (2) = Rp. #VALUE!
Jumlah (1) + (2) = Rp. #VALUE!
KOLOM KOLOM BALOK BALOK BALOK TANGGA TANGGA LIFT LIFT RAMP TIE BEAM
LANTAI 100 x 60 15 x 15 50 x 30 50 x 30 45 x 25 APARTEMENT RS APARTEMENT RS BETON RAILLING PONDASI DINDING
Bordes Tangga Railling Bordes Tangga Railling A1 A2 A3 RS 1 RS 2
SERVICE (BASEMENT)
X1
PONDASI
GALIAN P. PONDASI
DINDING KOLOM 15 x 15 PLESTERAN PENGECATAN LANTAI
GYPSUM PAS. BATU LUASAN DINDING PENGURANG TOTAL LUASAN DINDING DINDING DINDING KERAMIK KERAMIK KERAMIK KERAMIK KERAMIK VYNIL
LANTAI GYPSUM PAS. BATU BATU BATA BATU BATA PINTU JENDELA JENDELA 60X60 40 X 40 30 X 30 30 X 60 DINDING VEGA PLUS
W1 W3 BT BR BATA TAMAN RAMP J1,J2,J3,J9,J10,15J4,J5,J6,J7,J11,12,13,14 GYPSUM PAS. BATA BATU BATA BATU BATA
m' m' 0.50 1.00 2.23 TAMAN RAMP
1 ST Floor
Y = 4.88
X1 48.9 238.632 0 0 236.45 0.1125 472.8932 378.31
X2 6.9 2.3 33.672 1.15 33.672 1.15 53.88
X3 2.5 12.2 2.19 10.01 16.02
X4 1.7 8.296 8.30 13.27
X5 4.618 22.53584 4.37 18.17 29.06
X6 2.6 12.688 12.69 20.30
X7 12.45 60.756 60.76 97.21
X8 2.9 2.3 14.152 1.15 14.15 1.15 22.64
X9 12.894 62.92272 62.92 100.68
X10 1.15 5.612 5.61 8.98
X11 19.95 97.356 12.98 84.38 84.38
X12 7 34.16 34.16 34.16
X13 1.85 9.028 9.03 9.03
X14 9.2 44.896 4.24 40.66 40.66
X15 13.4 65.392 65.39 65.39
X16 4.75 23.18 23.18 23.18
X17 4.6 22.448 2.19 20.26 20.26
X18 0.2 0.976 0.98 0.98
-
X19 0.2 0.976 0.98 0.98
X20 17.4 84.912 84.91 84.91
X21 14.85 20.4 30.678 72.468 10.20 30.68 72.47 10.20 30.68 72.47
X22 30.678 30.68 - 30.68 -
X23 17.142 17.14 - 17.142 -
X24 17.142 - -
X25 17 8.50 - -
X26 17.793 8.90 - -
- -
- -
- -
Y1 22.767 11.38 - 11.38 -
Y2 14.65 4.504 71.492 2.25 71.49 71.49
Y3 14.7 71.736 71.736 71.74 71.74
Y4 7.6 37.088 4.37 32.72 32.72
Y5 6.35 30.988 0 2.19 28.80 28.80
Y6 4.9 23.912 0 23.91 23.91
Y7 0.7 3.416 0 3.42 3.42
Y8 4.8 23.424 0 23.42 23.42
Y9 1.4 6.832 0 6.83 6.83
Y10 0.35 4.5 1.708 2.25 - 1.708 2.73
Y11 12 58.56 0 58.56 58.56
Y12 14.612 0 0 7.31 - -
Y13 17.3 0 0 8.65 - -
Y14 22.75 17.5 111.02 0 8.75 111.02 111.02
Y15 9 0 0 4.50 - -
Y16 10.091 49.24408 0 49.24 49.24
Y17 2 9.76 0 9.76 9.76
Y18 2.6 12.688 0 2.19 10.50 10.50
Y19 1.5 7.32 0 7.32 7.32
Y20 2 9.76 0 9.76 9.76
Y21 1.5 7.32 0 7.32 7.32
Y22 6.55 31.964 0 31.96 31.96
Y23 3.95 19.276 0 19.28 19.28
Y24 17.85 87.108 0 2.19 84.92 84.92
Y25 10.145 49.5076 0 4.37 45.14 45.14
Y26 2.1 2.847 10.248 0 1.42 4.37 5.88 5.88
Y27 41.348 0 201.77824 201.77824 0.2025 322.85
291.248 49.25 45.6258 1375.66444 439.93284 1815.5973 2,215.32
PEKERJAAN PEMBANGUNAN
RMAH SAKIT, HOTEL & APARTMENT
HIKMAH
KOTA MAKASSAR
2014
2014