ID Task Name bobot Duration Start Finish Predecessors

Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018


Jun Jul Aug Sep Oct
1 Pembangunan Rumah Lantai 1 Tipe 60 / 200 0 76 days Mon 02/07/18 Fri 28/09/18
2 Pembangunan Rumah Lantai 1 Tipe 60 / 200 0 6 days Mon 02/07/18 Sat 07/07/18
3 Pekerjaan Pembersihan Tanah 0,33 4 days Mon 02/07/18 Thu 05/07/18 02/07 05/07
4 Pengukuran & Pemasangan Bowplank 1,09 2 days Fri 06/07/18 Sat 07/07/18 3 06/07 07/07
5 Membuat Bak Adukan (40 x 50 x 20 cm) 0,06 1 day Sat 07/07/18 Sat 07/07/18 4SS+1 day 07/07 07/07
6 Pekerjaan Gal. Tanah & Pondasi 0 8 days Mon 09/07/18 Tue 17/07/18
7 Galian Tanah Biasa 1 meter 0,5 2 days Mon 09/07/18 Tue 10/07/18 4 09/07 10/07
8 Urugan Sirtu (Tanah) 0,04 1 day Thu 12/07/18 Thu 12/07/18 9 12/07 12/07
9 Urugan Pasir 0,1 1 day Wed 11/07/18 Wed 11/07/18 7 11/07 11/07
10 Aanstamping (Batu Kosong) 0,64 2 days Fri 13/07/18 Sat 14/07/18 8 13/07 14/07
11 Pondasi Batu Kali 1,58 2 days Mon 16/07/18 Tue 17/07/18 10 16/07 17/07
12 Pekerjaan Dinding 0 34 days Tue 24/07/18 Sat 01/09/18
13 Pas Batu Merah tb 1/2 bata 1PC : 6 PP 5,17 14 days Tue 24/07/18 Wed 08/08/18 20 24/07 08/08
14 Plesteran 1 PC : 6 PP tebal 1,5 cm 14,48 20 days Thu 09/08/18 Sat 01/09/18 13 09/08 01/09
15 Pekerjaan Beton 0 42 days Wed 18/07/18 Wed 05/09/18
16 Balok Sloof 15 / 20 1PC : 2Ps : 3Kr 0,03 1 day Fri 20/07/18 Fri 20/07/18 17 20/07 20/07
17 Pembesian 1,12 2 days Wed 18/07/18 Thu 19/07/18 11 18/07 19/07
18 Ring Balk 15 / 20 1PC : 2Ps : 3Kr 0,03 1 day Wed 05/09/18 Wed 05/09/18 19 05/09 05/09
19 Pembesian 1,12 2 days Mon 03/09/18 Tue 04/09/18 14 03/09 04/09
20 Kolom Praktis 15 / 15 1PC : 2Ps : 3Kr 0,04 2 days Sat 21/07/18 Mon 23/07/18 16 21/07 23/07
21 Pembesian 1,36 2 days Tue 24/07/18 Wed 25/07/18 20 24/07 25/07
22 Pekerjaan Langit-langit 0 2 days Thu 06/09/18 Fri 07/09/18
23 Langit-langit Eternit Rk Ky Bangkir 1x1 m 5,34 2 days Thu 06/09/18 Fri 07/09/18 18 06/09 07/09
24 Pekerjaan Kayu 0 46 days Thu 26/07/18 Tue 18/09/18
25 Pas. Kusen Pintu & Jendela K. Kruing 13,96 21 days Thu 26/07/18 Mon 20/08/18 13SS+2 days 26/07 20/08
26 Pas. Pintu & Jendela K. Kruing 16,38 21 days Thu 26/07/18 Mon 20/08/18 13SS+2 days 26/07 20/08
27 Pas. Konstruksi Kuda-kuda Kayu Kruing 0,09 1 day Thu 06/09/18 Thu 06/09/18 18 06/09 06/09
28 Kons. Gording Kayu Kruing 0,18 1 day Wed 05/09/18 Wed 05/09/18 18SS 05/09 05/09
29 Pas. Kaso & Reng Kayu Kruing 7,69 4 days Thu 06/09/18 Mon 10/09/18 28 06/09 10/09
30 Pas. Lisplank (3 x 20 cm) Kayu Kruing 3,37 1 day Sat 15/09/18 Sat 15/09/18 33 15/09 15/09

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Milestone Project Summary Start-only
Project: p3pro Summary Group By Summary Finish-only
Date: Thu 01/07/21
Rolled Up Task Inactive Milestone External Tasks
Rolled Up Critical Task Inactive Summary External Milestone
Rolled Up Milestone Manual Task Progress
Rolled Up Progress Duration-only Deadline

Page 1
ID Task Name bobot Duration Start Finish Predecessors
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jun Jul Aug Sep Oct
31 Pas. Rangka Langit-langit Kayu Kruing 1x1 m 5 2 days Mon 17/09/18 Tue 18/09/18 34 17/09 18/09
32 Pekerjaan Atap 0 5 days Tue 11/09/18 Sat 15/09/18
33 Pas Atap Genteng Plentong Kecil 3,4 4 days Tue 11/09/18 Fri 14/09/18 29 11/09 14/09
34 Pas Atap Genteng Nok / Kodok 1,18 1 day Sat 15/09/18 Sat 15/09/18 33 15/09 15/09
35 Pekerjaan Sanitasi 0 63 days Tue 17/07/18 Fri 28/09/18
36 Closet Duduk Lengkap Tangki 0,62 1 day Tue 17/07/18 Tue 17/07/18 11SS+1 day 17/07 17/07
37 Pasang Pipa PVC Diam 1/2" Type AW 0,01 1 day Wed 18/07/18 Wed 18/07/18 36SS+1 day 18/07 18/07
38 Pasang Pipa PVC Diam 3/4" Type AW 0,14 1 day Wed 18/07/18 Wed 18/07/18 36SS+1 day 18/07 18/07
39 Pasang Pipa PVC Diam 1" Type AW 0,01 1 day Wed 18/07/18 Wed 18/07/18 36SS+1 day 18/07 18/07
40 Pasang Pipa PVC Diam 1 1/2" Type AW 0,01 1 day Tue 17/07/18 Tue 17/07/18 36SS 17/07 17/07
41 Pasang Pipa PVC Diam 2" Type AW 0,01 1 day Tue 17/07/18 Tue 17/07/18 36SS 17/07 17/07
42 Pasang Pipa PVC Diam 3" Type AW 0,17 1 day Tue 17/07/18 Tue 17/07/18 36SS 17/07 17/07
43 Pasang Kran Diameter 1/2" 0,18 1 day Wed 18/07/18 Wed 18/07/18 36SS+1 day 18/07 18/07
44 Pasang Floor Drain 0,12 1 day Tue 17/07/18 Tue 17/07/18 11SS+1 day 17/07 17/07
45 Pembuatan Septic Tank 1 x 1 x 2 m + Peresapan 2,47 9 days Wed 19/09/18 Fri 28/09/18 31 19/09 28/09
46 Penyambungan PDAM 1,24 1 day Tue 17/07/18 Tue 17/07/18 36SS 17/07 17/07
47 Pekerjaan Lantai 0 6 days Mon 03/09/18 Sat 08/09/18
48 Urugan Sirtu (Tanah) 0,05 2 days Mon 03/09/18 Tue 04/09/18 14 03/09 04/09
49 Pas Keramik Lantai Kelas A 20 x 20 cm 0,04 1 day Wed 05/09/18 Wed 05/09/18 48 05/09 05/09
50 Pas Keramik Lantai Kelas A 30 x 30 cm 1,13 4 days Wed 05/09/18 Sat 08/09/18 49SS 05/09 08/09
51 Pas Keramik Lantai Kelas A 40 x 40 cm 0,14 2 days Wed 05/09/18 Thu 06/09/18 50SS 05/09 06/09
52 Pas Keramik Dinding Kelas A 20 x 20 cm 0,17 2 days Fri 07/09/18 Sat 08/09/18 51 07/09 08/09
53 Pekerjaan Kunci & Kaca 0 2 days Thu 13/09/18 Fri 14/09/18
54 Pasang Kunci Tanam Biasa 0,35 1 day Thu 13/09/18 Thu 13/09/18 52SS+5 days 13/09 13/09
55 Pasang Engsel Pintu 0,06 1 day Thu 13/09/18 Thu 13/09/18 54SS 13/09 13/09
56 Pasang Engsel Jendela Kupu-kupu 0,2 1 day Thu 13/09/18 Thu 13/09/18 54SS 13/09 13/09
57 Pasang Kait Angin Model Lipat 0,24 1 day Fri 14/09/18 Fri 14/09/18 56SS+1 day 14/09 14/09
58 Pasang Kunci Slot 0,31 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
59 Pasang Pegangan Pintu / Door Holder 0,4 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
60 Pasang Kaca Tebal 5 mm 0,99 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Milestone Project Summary Start-only
Project: p3pro Summary Group By Summary Finish-only
Date: Thu 01/07/21
Rolled Up Task Inactive Milestone External Tasks
Rolled Up Critical Task Inactive Summary External Milestone
Rolled Up Milestone Manual Task Progress
Rolled Up Progress Duration-only Deadline

Page 2
ID Task Name bobot Duration Start Finish Predecessors
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jun Jul Aug Sep Oct
61 Pekerjaan Listrik 0 2 days Fri 14/09/18 Sat 15/09/18
62 Pasang Instalasi Titik Lampu 0,74 2 days Fri 14/09/18 Sat 15/09/18 57SS 14/09 15/09
63 Pasang Instalasi Stopkontak 0,78 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
64 Pasang Instalasi Saklar Tunggal 0,1 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
65 Pasang Instalasi Saklar Ganda 0,05 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
66 Pasang Lampu 18 watt 0,05 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
67 Pasang Lampu 20 watt 0,15 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
68 Biaya Administrasi Listrik PLN 900 watt 0,62 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
69 Pemasangan Rumah Panel MCB 0,62 1 day Fri 14/09/18 Fri 14/09/18 57SS 14/09 14/09
70 Pekerjaan Pengecatan 0 7 days Sat 15/09/18 Sat 22/09/18
71 Mendempul & Menggosok Kayu 0,37 2 days Sat 15/09/18 Mon 17/09/18 69SS+1 day 15/09 17/09
72 Mengecat Kayu 1,12 2 days Sat 15/09/18 Mon 17/09/18 69SS+1 day 15/09 17/09
73 Mengecat Tembok Interior 1,03 5 days Tue 18/09/18 Sat 22/09/18 71 18/09 22/09
74 Mengecat Tembok Eksterior 1,03 4 days Wed 19/09/18 Sat 22/09/18 73SS+1 day 19/09 22/09

Task Split Manual Summary Rollup


Critical Task External Tasks Manual Summary
Milestone Project Summary Start-only
Project: p3pro Summary Group By Summary Finish-only
Date: Thu 01/07/21
Rolled Up Task Inactive Milestone External Tasks
Rolled Up Critical Task Inactive Summary External Milestone
Rolled Up Milestone Manual Task Progress
Rolled Up Progress Duration-only Deadline