JADWAL PELAKSANAAN PEKERJAAN ( TIME SCHEDULE )

PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI KEC. WARA TIMUR KOTA PALOPO
TAHUN ANGGARAN 2020

JADWAL PELAKSANAAN PEKERJAAN 120 HARI KALENDER


DURASI WAKTU (HARI/MINGGU)
1 2 3 4
JUMMLAH
NO. URAIAN KEGIATAN BOBOT I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII XVIII
HARGA (Rp.)
(%)
05- 10- 17- 24- 31/08- 07- 14- 21- 29/08- 05- 12- 19- 26/10- 02- 09- 16- 23- 30/11- KET.
09/08/2 16/08/2 23/08/2 30/08/2 06/09/2 13/09/2 20/09/2 27/09/2 04/10/2 11/10/2 18/10/2 25/10/2 01/11/2 08/11/20 15/11/2 22/11/2 29/11/2 03/12/2
020 020 020 020 020 020 020 020 020 020 020 020 020 20 020 020 020 020
Chart Title
I PEKERJAAN PENDAHULUAN 5.451 37,693,900.467 1.090 1.090 1.090 1.090 1.090 100%

II PEKERJAAN PONDASI 7.365 65,307,757.422 2.455 2.455 2.455

75%
III PEKERJAAN STRUKTUR 11.303 86,270,868.810 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028

IV PEKERJAAN ARSITEKTUR 54.338 418,161,865.139 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180
50%
V PEKERJAAN ATAP 13.517 130,164,657.970 2.253 2.253 2.253 2.253 2.253 2.253

VI PEKERJAAN INSTALASI LISTRIK 1.647 10,174,342.200 0.549 0.549 0.549


25
%
VII PEKERJAAN SANITAIR 4.248 26,835,269.088 1.062 1.062 1.062 1.062

PEKERJAAN PELENGKAP
VIII 2.131 17,232,248.622 0.533 0.533 0.533 0.533
BANGUNAN LAINNYA
0
BOBOT RENCANA MINGGUAN 100.000 791,840,909.718 1.090 4.573 4.573 8.753 6.298 5.207 5.207 7.460 7.993 7.993 7.460 8.009 8.044 5.791 5.242 5.774 0.533 - %

BOBOT KOMULATIF MINGGUAN 1.090 5.663 10.236 18.988 25.286 30.493 35.701 43.161 51.154 59.147 66.607 74.617 82.660 88.451 93.693 99.467 100.00 100.00

BOBOT REALISASI - 4.688 16.076 21.926 25.432 32.864 38.617 47.427 63.171 66.378 74.982 80.780 96.515 96.515

DEVIASI (1.090) (0.975) 5.840 2.938 0.146 2.371 2.916 4.266 12.017 7.231 8.375 6.16 13.85 8.06

Disetujui Oleh, Palopo , 18 Oktober 2020


Pejabat Pembuat Komitmen (PPK) CV. Paraga Nusantara

Drs.H. Armin, H. Sis. I H. MULYADI, Spd. IAI


Nip: 19671231194031011 Direktur
RENCANA ANGGARAN BIAYA
PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI KEC. WARA TIMUR KOTA PALOPO
TAHUN ANGGARAN 2020

VOLU HARGA JUMLAH HARGA


NO ITEM PEKERJAAN SAT
ME SATUAN (Rp.) (Rp.)
A PEKERJAAN PENDAHULUAN
1 Pekerjaan Pembuatan Papan Nama Proyek 1.00 ls 150,000.00 150,000.00
2 Pelaksanaan K3 (SMKK) 1.00 Ls 7,000,000.00 7,000,000.00
3 Pekerjaan Pemasangan Bouplank 133.43 m 60,068.93 8,014,997.14
4 Pekerjaan Penimbunan tanah 146.25 m3 97,150.00 14,208,187.50
5 Pekerjaan Pemadatan tanah 146.25 m3 45,750.00 6,690,937.50
SUB TOTAL 36,064,122.14
B PEKERJAAN PONDASI
1 Pekerjaan Galian Pondasi 55.45 m3 62,875.00 3,486,418.75
2 Pekerjaan Pasir Urug T.10 cm 10.08 m3 107,650.00 1,085,112.00
3 Pekerjaan Pas.Batu Kosong 15cm 10.08 m3 323,970.00 3,265,617.60
4 Pekerjaan Pas. Pondasi Batu Kali Camp 1:4 59.22 m3 683,325.00 40,466,506.50
5 Pekerjaan Pengurugan Kembali (1/3 galian) 18.48 m3 22,875.00 422,730.00
SUB TOTAL 48,726,384.85
C PEKERJAAN STRUKTUR
1 Pekerjaan Sloef (15X20) Tipe S1
- Pekerjaan Bekisting 2 Kali Pakai 37.80 m2 134,805.00 5,095,629.00
- Pekerjaan Pembesian 743.68 kg 13,756.50 10,230,433.92
- Pekerjaan Pengecoran K225 3.78 m3 888,665.40 3,359,155.20
2 Pekerjaan Kolom Praktis Tipe K1 (15x15) cm 160.00 m' 75,530.00 12,084,800.00
3 Pekerjaan Kolom Tipe K2 (25x25) cm
- Pekerjaan Bekisting 2 Kali Pakai 14.33 m2 189,815.00 2,720,048.95
- Pekerjaan Pembesian 365.27 kg 13,756.50 5,024,836.76
- Pekerjaan Pengecoran K225 2.49 m3 888,665.40 2,212,776.84
4 Pekerjaan plat poer - 1.2 (60x60)
- Pekerjaan Bekisting 2.34 m2 180,930.00 423,376.20
- Pekerjaan Pembesian 111.89 kg 13,756.50 1,539,214.79
- Pekerjaan Pengecoran K225 0.54 m3 888,665.40 479,879.31
5 Pekerjaan Balok latei praktis +2.2 (15x15) 59.10 m' 95,557.50 5,647,448.25
6 Pekerjaan Plat Meja & Plat overstek jendela Beton 0.79 m3 3,836,015.00 3,030,451.85
7 Pekerjaan Balok (15x25) +2.35
- Pekerjaan Bekisting 2 Kali Pakai 23.20 m2 193,565.00 4,490,708.00
- Pekerjaan Pembesian 152.25 kg 13,756.50 2,094,427.13
- Pekerjaan Pengecoran K175 1.09 m3 888,665.40 968,645.28
8 Pekerjaan Kanopi/plat Beton +2.35 0.77 m3 3,836,015.00 2,953,731.55
9 Pekerjaan Ring balk 15x15 +4.00 130.00 m' 95,557.50 12,422,475.00
SUB TOTAL 74,778,038.02
C PEKERJAAN ARSITEKTUR
1 Plesteran Tutup Dinding Pondasi bagian Luar
1 Pekerjaan Plasteran Camp. 1:4 52.61 m2 55,338.00 2,911,332.18
2 Pekerjaan Pengacian 51.78 m2 33,606.25 1,740,131.63
3 Pekerjaan Pengecetan 51.78 m2 31,299.00 1,620,662.22

2 Pekerjaan Lantai Kasar Lebar 80 cm keliling Bangunan


1 Pekerjaan Cansteen Batu Bata Camp. 1 : 4 18.60 m2 97,202.00 1,807,957.20
2 Pekerjaan Plasteran cansting Camp. 1 : 4 12.40 m2 55,338.00 686,191.20
3 Pekerjaan timbunan tebal 15 cm 7.56 m3 97,150.00 734,454.00
4 Pekerjaan Rabat Beton K 100 T.5 cm 2.33 m3 733,132.86 1,708,199.56

3 Pekerjaan Dinding
4 Pekerjaan Pas. Dinding Bata Camp. 1:4 473.60 m2 97,202.00 46,034,867.20
5 Pekerjaan Plasteran Camp. 1:4 994.56 m2 55,338.00 55,036,961.28
6 Pekerjaan Pengacian 994.56 m2 33,606.25 33,423,432.00
7 Pekerjaan Pengecetan 994.56 m2 31,299.00 31,128,733.44

4 Pekerjaan Profil Dinding


1 Pembuatan Profil horizontal penebalan 6cm x 20 c 24.50 m2 65,000.00 1,592,500.00
2 Pembuatan Profil horizontal penebalan 3cm x 10 c 11.00 m2 65,000.00 715,000.00
3 Pembuatan Profil vertikal penebalan 4cm x 30 cm 22.40 m2 65,000.00 1,456,000.00
4 Pembuatan Profil 2 bh Tiang Entrance 2.00 m2 125,000.00 250,000.00
5 Pembuatan Profil mahkota atap Entrance 7.00 m2 65,000.00 455,000.00
6 Pembuatan Profil mahkota Utama atap 12.00 m2 65,000.00 780,000.00
7 Pembuatan Profil lisplank kanopi 8.20 set 225,000.00 1,845,000.00

5 Pekerjaan Lantai
1 Pekerjaan lantai dasar (Rabat Beton K 100 T.5 cm) 10.15 m3 733,132.86 7,441,298.50
2 Pekerjaan Lantai Keramik ukuran 60x60 200.40 m2 240,900.00 48,276,360.00
3 Pekerjaan Lantai Keramik Kasar 40x40 untuk tang 8.80 m2 197,566.00 1,738,580.80
4 Pekerjaan Lantai Keramik Kasar 400x400 u/ kama 2.80 m2 197,566.00 553,184.80
5 Pekerjaan Dinding Keramik 400x400 U/ kamar ma 16.00 m2 218,100.00 3,489,600.00

6 Pekerjaan Pintu dan Jendela


1 Pasang Pintu Kaca tempered 12 mm 2 daun + lengk 1.00 unit 13,000,000.00 13,000,000.00
2 Pasang Pintu Kamar Mandi bahan Kusen & daun 2.00 bh 550,000.00 1,100,000.00

7 Pekerjaan Kusen
1 Kusen Pintu Kayu 10.00 bh 400,000.00 4,000,000.00
2 Kusen Jendela Kayu 2 daun 13.00 bh 450,000.00 5,850,000.00
3 Kusen Loster Kayu 63.00 bh 35,000.00 2,205,000.00

8 Pekerjaan Daun Pintu Jendela


1 Daun Pintu Bingkai Kayu panil kayu (ukuran 80 11.00 bh 600,000.00 6,600,000.00
2 Daun Jendela Bingkai Kayu Panil Kaca 5 mm (11 26.00 bh 400,000.00 10,400,000.00

9 Pekerjaan pengecetan Pintu Jendela


1 Pengecetan Pintu Panil Kayu 11.25 m2 55,630.00 625,837.50
2 Pengecetan Jendela Panil Kayu 19.50 m2 55,630.00 1,084,785.00
3 Penegcetan Loster 27.45 m2 55,630.00 1,527,043.50
10 Pekerjaan pemasangan Aksesoris Pintu & Jendela
1 Pasang Engsel Pintu 10.00 buah 42,017.00 420,170.00
2 Pasang Kunci Tanam 2 x Slag 10.00 buah 176,150.00 1,761,500.00
3 Pasang grandel Pintu 2.00 buah 75,000.00 150,000.00
4 Pasang Engsel, kait angin & grendel Jendela 26.00 buah 100,000.00 2,600,000.00
5 Pekerjaan pemasangan Bingkai Besi Pengaman Jen 26.00 buah 500,000.00 13,000,000.00

11 Pekerjaan Plafond
1 Pemasangan Rangka Plafon 248.60 m2 132,595.00 32,963,117.00
2 Pekerjaan Pemasangan Gypsum board t.9mm 248.60 m2 42,702.00 10,615,717.20
3 Pekerjaan Pengecetan Plafon 248.60 m2 24,799.50 6,165,155.70
SUB TOTAL 359,493,771.90
D PEKERJAAN ATAP
1 Memasang Rangka Baja Ringan 324.20 m2 164,900.00 53,460,580.00
2 Memasang Atap Metal Roof (Setara) 324.20 m2 83,665.00 27,124,193.00
3 Memasang Nok Atap 68.10 m' 52,310.00 3,562,311.00
4 Memasang Jurai Atap 16.00 m' 52,310.00 836,960.00
5 Memasang Lisplank GRC 64.00 m' 58,300.00 3,731,200.00
6 Mengecat Lisplank 28.80 m2 24,799.50 714,225.60
SUB TOTAL 89,429,469.60
E PEKERJAAN INSTALASI LISTRIK
1 Pemasangan MCB dan Box Sekring 2.00 titik 241,500.00 483,000.00
2 Pekerjaan Instalasi listrik 33.00 titik 201,125.00 6,637,125.00
3 Pemasangan Saklar Tunggal 9.00 titik 22,500.00 202,500.00
4 Pemasangan Saklar Serie 3.00 titik 106,875.00 320,625.00
5 Pemasangan Stop Kontak 12.00 titik 104,875.00 1,258,500.00
6 Pemasangan Fitting Lampu 21.00 titik 45,000.00 945,000.00
7 Pemasangan Lampu 18 Watt 21.00 titik 50,000.00 1,050,000.00
SUB TOTAL 10,896,750.00
F PEKERJAAN SANITAIR
1 Memasang Pipa Air Bersih (Pipa PVC 3/4'') 48.00 m 23,360.00 1,121,280.00
2 Memasang Pipa Air Bersih (Pipa PVC 1/2'') 20.00 m 21,335.00 426,700.00
3 Memasang Kran Air 1/2" 4.00 titik 104,975.00 419,900.00
4 Memasang Kloset duduk Ful aksesoris 2.00 buah 2,365,550.00 4,731,100.00
5 Memasang wastafel cuci piring 1.00 buah 245,575.00 245,575.00
6 Memasang Pipa Air Limbah (Pipa PVC 3) 24.00 m 73,967.50 1,775,220.00
7 Memasang Pipa Sanitasi/Kloset (Pipa PVC 4') 23.20 m 86,117.50 1,997,926.00
8 Pekerjaan pembuatan & pasang Tower tinggi 6 m u 6.00 m 1,300,000.00 7,800,000.00
9 Pekerjaan pasang Tandon air bersih kapasitas 650 li 1.00 ls 1,406,969.70 1,406,969.70
10 Memasang Floor Drain 2.00 buah 63,525.00 127,050.00
11 Pekerjaan Pembuatan Septick tank 1.00 buah 2,500,000.00 2,500,000.00
12 Pekerjaan Saluran Air ukuran 15 cm x 15 cm 61.00 m 91,000.00 5,551,000.00
SUB TOTAL 28,102,720.70
G PEKERJAAN PELENGKAP BANGUNAN LAINNYA
1 Pembuatan Logo Papan Nama Stainless Steel 1.00 m2 7,000,000.00 7,000,000.00
2 Pekerjaan Timbunan 2.85 m3 97,150.00 276,877.50
3 Pekerjaan Pas. Dinding Bata Camp. 1:4 2.12 m2 97,202.00 206,068.24
4 Pekerjaan Plasteran camp. 14 2.85 m2 55,338.00 157,713.30
5 Pekerjaaan Rabat Lantai Ramp. Tbl. 7cm 0.39 m3 733,132.86 285,921.81
6 Pasang Reiling Ramp pipa gip 2.5 13.50 m 450,000.00 6,075,000.00
7 Pekerjaan Pengacian 2.85 m 33,606.25 95,777.81
SUB TOTAL 14,097,358.67
TOTAL REAL COST 661,588,615.88
PPN 10% 66,158,861.59
TOTAL HARGA 727,747,477.47
DIBULATKAN 727,747,000.00
JADWAL PELAKSANAAN PEKERJAAN ( TIME SCHEDULE )
PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI KEC. WARA TIMUR KOTA PALOPO
TAHUN ANGGARAN 2020

JADWAL PELAKSANAAN PEKERJAAN 120 HARI KALENDER


DURASI WAKTU (HARI/MINGGU)
1 2 3 4
JUMMLAH
NO. URAIAN KEGIATAN BOBOT I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII XVIII
HARGA (Rp.)
(%)
05- 10- 17- 24- 31/08- 07- 14- 21- 29/08- 05- 12- 19- 26/10- 02- 09- 16- 23- 30/11- KET.

020 020 020 020 020 020 020 020 020 020
Chart Title
09/08/2 16/08/2 23/08/2 30/08/2 06/09/2 13/09/2 20/09/2 27/09/2 04/10/2 11/10/2 18/10/2 25/10/2 01/11/2 08/11/20 15/11/2 22/11/2 29/11/2 03/12/2
020 020 020 20 020 020 020 020

I PEKERJAAN PENDAHULUAN 5.451 37,693,900.467 1.090 1.090 1.090 1.090 1.090 100%

II PEKERJAAN PONDASI 7.365 65,307,757.422 2.455 2.455 2.455

75%
III PEKERJAAN STRUKTUR 11.303 86,270,868.810 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028

IV PEKERJAAN ARSITEKTUR 54.338 418,161,865.139 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180 4.180
50%
V PEKERJAAN ATAP 13.517 130,164,657.970 2.253 2.253 2.253 2.253 2.253 2.253

VI PEKERJAAN INSTALASI LISTRIK 1.647 10,174,342.200 0.549 0.549 0.549


25
%
VII PEKERJAAN SANITAIR 4.248 26,835,269.088 1.062 1.062 1.062 1.062

PEKERJAAN PELENGKAP
VIII 2.131 17,232,248.622 0.533 0.533 0.533 0.533
BANGUNAN LAINNYA
0
BOBOT RENCANA MINGGUAN 100.000 791,840,909.718 1.090 4.573 4.573 8.753 6.298 5.207 5.207 7.460 7.993 7.993 7.460 8.009 8.044 5.791 5.242 5.774 0.533 - %

BOBOT KOMULATIF MINGGUAN 1.090 5.663 10.236 18.988 25.286 30.493 35.701 43.161 51.154 59.147 66.607 74.617 82.660 88.451 93.693 99.467 100.00 100.00

BOBOT REALISASI - 4.688 16.076 21.926 25.432 32.864 38.617 47.427 63.171 66.378 74.982 80.780 96.515 96.515

DEVIASI (1.090) (0.975) 5.840 2.938 0.146 2.371 2.916 4.266 12.017 7.231 8.375 6.16 13.85 8.06

Disetujui Oleh, Palopo , 09 November 2020


Pejabat Pembuat Komitmen (PPK) CV. Paraga Nusantara

Drs.H. Armin, H. Sis. I H. MULYADI, Spd. IAI


Nip: 19671231194031011 Direktur

JADWAL PELAKSANAAN PEKERJAAN ( TIME SCHEDULE )


PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI KEC. WARA TIMUR KOTA PALOPO
TAHUN ANGGARAN 2020

JADWAL PELAKSANAAN PEKERJAAN 120 HARI KALENDER


DURASI WAKTU (HARI/MINGGU)
1 2 3 4
JUMMLAH
NO. URAIAN KEGIATAN BOBOT I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII XVIII
HARGA (Rp.)
(%)
05- 10- 17- 24- 31/08- 07- 14- 21- 29/08- 05- 12- 19- 26/10- 02- 09- 16- 23- 30/11- KET.
09/08/2 16/08/2 23/08/2 30/08/2 06/09/2 13/09/2 20/09/2 27/09/2 04/10/2 11/10/2 18/10/2 25/10/2 01/11/2 08/11/20 15/11/2 22/11/2 29/11/2 03/12/2
020 020 020 020 020 020 020 020 020 020 020 020 020 20 020 020 020 020

I PEKERJAAN PENDAHULUAN 5.451 37,693,900.467 1.090 1.090 1.090 1.090 1.090 100%

II PEKERJAAN PONDASI 7.365 65,307,757.422 2.455 2.455 2.455


75%
III PEKERJAAN STRUKTUR 11.303 86,270,868.810 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028

IV PEKERJAAN ARSITEKTUR 54.338 418,161,865.139 4.180 4.180 4.180 4.180 4.180 4.180
50%

V PEKERJAAN ATAP 13.517 130,164,657.970 2.253 2.253

VI PEKERJAAN INSTALASI LISTRIK 1.647 10,174,342.200


25
%
VII PEKERJAAN SANITAIR 4.248 26,835,269.088

VIII PEKERJAAN PELENGKAP BANGU 2.131 17,232,248.622 0.533


0
%
BOBOT RENCANA MINGGUAN 100.000 791,840,909.718 1.090 4.573 4.573 8.753 6.298 5.207 5.207 7.460 7.993

BOBOT KOMULATIF MINGGUAN 1.090 5.663 10.236 18.988 25.286 30.493 35.701 43.161 51.154

BOBOT REALISASI - 4.688 16.076 21.926 25.432 32.864 38.617 47.427 63.171

DEVIASI (1.090) (0.975) 5.840 2.938 0.146 2.371 2.916 4.266 12.017

Disetujui Oleh, Palopo , 04 Oktober 2020


Pejabat Pembuat Komitmen (PPK) CV. Paraga Nusantara
Drs.H. Armin, H. Sis. I H. MULYADI, Spd. IAI
Nip: 19671231194031011 Direktur

JADWAL PELAKSANAAN PEKERJAAN ( TIME SCHEDULE )


PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI KEC. WARA TIMUR KOTA PALOPO
TAHUN ANGGARAN 2020

JADWAL PELAKSANAAN PEKERJAAN 120 HARI KALENDER


DURASI WAKTU (HARI/MINGGU)
1 2 3 4
JUMMLAH
NO. URAIAN KEGIATAN BOBOT I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII XVIII
HARGA (Rp.)
(%)
05- 10- 17- 24- 31/08- 07- 14- 21- 29/08- 05- 12- 19- 26/10- 02- 09- 16- 23- 30/11- KET.
09/08/2 16/08/2 23/08/2 30/08/2 06/09/2 13/09/2 20/09/2 27/09/2 04/10/2 11/10/2 18/10/2 25/10/2 01/11/2 08/11/20 15/11/2 22/11/2 29/11/2 03/12/2
020 020 020 020 020 020 020 020 020 020 020 020 020 20 020 020 020 020

I PEKERJAAN PENDAHULUAN 5.451 37,693,900.467 1.090 1.090 1.090 1.090 1.090 100%

II PEKERJAAN PONDASI 7.365 65,307,757.422 2.455 2.455 2.455


75%

III PEKERJAAN STRUKTUR 11.303 86,270,868.810 1.028 1.028 1.028 1.028

IV PEKERJAAN ARSITEKTUR 54.338 418,161,865.139 4.180 4.180


50%

V PEKERJAAN ATAP 13.517 130,164,657.970

VI PEKERJAAN INSTALASI LISTRIK 1.647 10,174,342.200


25
%
VII PEKERJAAN SANITAIR 4.248 26,835,269.088

VIII PEKERJAAN PELENGKAP BANGU 2.131 17,232,248.622 0


%
BOBOT RENCANA MINGGUAN 100.000 791,840,909.718 1.090 4.573 4.573 8.753 6.298

BOBOT KOMULATIF MINGGUAN 1.090 5.663 10.236 18.988 25.286

BOBOT REALISASI - 4.688 16.076 21.926 25.432

DEVIASI (1.090) (0.975) 5.840 2.938 0.146

Disetujui Oleh, Palopo , 06 September 2020


Pejabat Pembuat Komitmen (PPK) CV. Paraga Nusantara
Drs.H. Armin, H. Sis. I H. MULYADI, Spd. IAI
Nip: 19671231194031011 Direktur