Anda di halaman 1dari 6

TRANSLATION

SPECIFICATIONS FOR THE OPERATIONAL


PERFORMANCE OF POWER PLANTS

Introduction 1 GENERATOR AND VOLTAGE


REGULATOR CHARACTERISTICS
Power system security requires that the integrated
operation of power plants and network comply with the
plans in all operational circumstances, including 1.1 Generators
disturbances. The reactance of the generator as well as its step-up
It is important that power plants remain synchronised in transformer shall be as low as technically and
the network and behave as planned in case disturbances economically possible in order to support the system
in the network occur. Otherwise the disturbance may lead stability and reactive power control.
to total blackout, and the restoration after the blackout will Generators with outputs below 500 MVA shall have
be more difficult and may take a considerably longer time.
− no-load short circuit ratio Kc (saturated) of at least
Specifications for the operational performance contribute 0.5,
to the system operational security so that
− direct axis transient reactance Xd' (saturated) of less
− power plant withstands the variations in voltage and than 0.35.
frequency caused by the power system
Generators with outputs above 500 MVA may deviate
− power plant does not cause any inconvenience to from these values, the allowable limits being Kc ≥ 0.43
other power plants synchronised to the electrical and Xd' ≤ 0.42.
power system.
Each generator shall be capable of operating on the rated
In order to maintain security during the normal operation active power continuously at power factor down to at
of the power system, it is also important that power plants least 0.95 underexcited, and 0.9 overexcited. This shall
have adequate and compatible capabilities concerning be possible in connection with voltage and frequency
load following, power control rate and starting times. conditions described in section 3.1, however, at
These specifications follow in applicable parts the Nordel underexcited conditions the normal grid voltage is applied
specification "Operational Performance Specifications for instead of the 90% voltage.
Thermal power Units larger than 100 MW", 1995
1.2 Voltage Regulation
Application The preferred dynamic characteristics of a steady state
Specifications are applied to new power units to be are defined in a measurable way as follows:
connected to the Finnish power system. Specifications The 10% step response of generator voltage is recorded
shall also be applied to the existing units, if new in no-load conditions, the unit disconnected from the grid.
installations or modifications e.g. in the excitation system The set value of the voltage is changed with plus and
is introduced. Otherwise the existing units are supposed minus stepwise changes causing change of generator
to fulfil the requirements, which were valid when terminal voltage from 95% to 105%, and from 105% to
connecting the units to the power system. 95%. In both cases, the step response of the generator
These minimum specifications apply to all units 1 larger terminal voltage shall be as follows:
than 50 MW, if the text does not mention any other power − response is non-oscillating
limit. It is recommended, however, that the requirements
are also applied to power plants smaller than 50 MW. − rise time from 0 to 90% of the change is 0.2 ... 0.3
sec in case of static exciter, or in case of brushless
All the units shall fulfil the requirements specified in exciter: 0.2 ... 0.5 sec at a step upwards, 0.2 ... 0.8
sections 1 - 5. In section 6 there are also sec at a step downwards.
recommendations concerning the power control
characteristics of the power units. In case the power unit − overshoot is less than 15% of the change.
is utilised as frequency control reserve and/or as The excitation system shall be designed so that its ceiling
instantaneous disturbance reserve, a separate contract is voltage is in case of static exciter at least twice and in
concluded concerning the power control properties and case of brushless exciter at least 1.6 times the
power reserve of the unit. magnetising voltage of the generator at its rated values.
In addition to these specifications there can also be However, the other requirements for voltage control have
additional requirements for a unit caused by the local to be taken into account. The excitation system shall be
grid. These shall be agreed separately with the local grid capable of supplying its ceiling voltage for 10 seconds.
owner. To secure the operation of the power system, the
excitation system shall be implemented so that automatic
control system has at least a manual control of the
1
'Unit' refers to one or more generation plants combined in a way excitation current as a reserve.
that one internal fault in the unit will cause the disconnection of the
whole generation plant.

-1-
1.3 PSS, Power System Stabiliser the normal voltage at any frequency between 51 and 52
Hz. During such transients, the power may be reduced, if
PSS shall normally be included in each generator. It shall stable operation at full power can be re-established when
be tuned to improve the damping of the oscillations of the the frequency again drops below 50.3 Hz.
generator and the power system, in particular the low
frequency (0.2 ... 1.0 Hz) interarea oscillations. It shall be
possible to disconnect the stabiliser. The stabiliser output
shall also have limiters with adjustable settings.
Frequency (Hz)
1.4 Additional Voltage Control 53
Equipment 3 min island operation
large power reduction
In addition of the excitation system and the power system
stabiliser (PSS), the control system shall also include 52 3 min island operation
protective limiters and reactive current statics (providing large power reduction
or 5 sec transients
droop characteristic) equipment.
at reduced power
51
Current limiters for generator rotor and stator shall have 30 min. 10 hours/year
inverse time characteristics to utilise the generator small power reduction
overloading capability in various network conditions. 50.3 1 hour
1 hour small
50 10 % reduc.
reduction
1.5 Voltage Control Mode 49.7 Continuous operation

The normal way of operation is automatic control of the


49
generator voltage.
30 min
In case a different type of control is needed, such as power reduction
0 % at 49 Hz
control of reactive output or power factor, the control shall 48 15 % at 47.5 Hz
also be able to react to the voltage variation. The
application of these control systems shall be agreed with
the grid company.
47
85 90 95 100 105 110
2 TOLERANCE TO FREQUENCY Grid voltage (%)
VARIATIONS

2.1 Frequency Range 49 Hz to 51 Hz Figure 1. Performance requirements for power production


in relation to voltage (requirements in section 2) and
It shall be possible to operate the unit continuously at the frequency (requirements in section 3).
full output power2 within the grid voltage range of 90-
105% of the normal3 voltage, and at any frequency 2.4 Frequency Range 51 Hz to 53 Hz
between 49 and 51 Hz. A maximum operating time of 10 When feeding a separate electrical network (island
h/year and maximum duration of 30 minutes per case can operation) it shall be possible to operate the unit at a
be assumed within the frequency range of 50.3-51 Hz. At strongly reduced output power within the grid voltage
a frequency above 50.3 Hz, a small power reduction is range of 95-105% of the normal voltage, at any frequency
accepted, if stable operation at full power can be re- between 51 and 53 Hz for 3 min.
established when the frequency again drops below this
value (see Figure 1).
2.5 Frequency Below 47.5 Hz
2.2 Frequency Range 49 Hz to 47.5 Hz
The unit may be tripped from the network at frequencies
It shall be possible to operate the unit in disturbance below 47.5 Hz. The unit shall then be capable of
conditions for 30 minutes within the grid voltage range of changing over to house load operation. However, this
95-105% of the normal voltage, at any frequency down to should not take place instantaneously, the time delay
47.5 Hz. The output power may then be reduced by 0% being determined by the design limits of the unit and so
at 49 Hz and a maximum of 15% at 47.5 Hz, and by a that reliable changeover to house load operation can be
value found with linear interpolation at frequencies obtained.
between these two limits. Efforts should be made to lower
this reduction in output power, if this can be achieved 2.6 Frequency Gradients
without high additional costs.
The control system shall be designed so that the unit will
not trip because of the transient frequency gradients
2.3 Transitory Frequency Variations 51
occurring in case of short-circuits or switchings in the
Hz to 52 Hz
high-voltage network to which the unit is connected.
It shall be possible to operate the unit for 5 seconds in
transitory conditions of the network during exceptional
disturbances within the grid voltage range of 95-105% of 3 TOLERANCE TO VOLTAGE
VARIATIONS
2
In the following, the term power means active power supplied to 3.1 Grid Voltage Range 90% to
the grid. 105% of the Normal Voltage
3
During normal operation of the power system, the variations in It shall be possible to operate the unit continuously at the
400 kV: 380 - 420 kV, in 220 kV: 215 - 245 kV and in 110 kV: 105 - full load within the frequency range of 49 - 51 Hz and at a
123 kV (in a radially operated network 100 - 123 kV) grid voltage between 90 and 105% of the normal voltage.

-2-
At a frequency above 50.3 Hz, a small power reduction is Generator voltage is used in this section to emphasise
accepted, if stable operation at the full power can be re- the effect of grid faults on the unit as a whole. It shall also
established when the frequency again drops below this be noted that the design criteria for the voltage protection
value. A maximum operating time of 10 h/year and a may vary, as the unit must manage several kinds of other
maximum duration of 30 minutes per case can be faults in various operating conditions.
assumed within the frequency range of 50.3 - 51 Hz
(Same requirements as in section 2.1). (Figure 1).

3.2 Grid Voltage Range 85% to 90% of


Generator
the Normal Voltage
voltage (pu)
It shall be possible to operate the unit for 1 hour within
the frequency range of 49.7 - 50.3 Hz at a grid voltage
between 85% and 90% of the normal voltage, and an 1.00
output power reduction of up to some 10% of the full 0.95
output power may then be acceptable.

3.3 Grid Voltage Range 105% to 110% of


the Normal Voltage
It shall be possible to operate the unit for 1 hour at a
frequency within the range of 49.7 - 50.3 Hz and at a grid
voltage between 105% and 110% of the normal voltage. 0.25
A slight reduction in output power is acceptable.
Time (seconds)
3.4 Consequences of Nearby Grid Faults
0 0.25 0.75
3.4.1 Ability to Withstand Mechanical Stresses Figure 2. Deep voltage transient in generator voltage
Due to Line Side Faults caused by a network fault.

Power units shall be designed so that the turbine 3.5 Large Voltage Disturbances
generator set can withstand the mechanical stresses
associated with any kind of single-, two- and three-phase The unit may be disconnected from the power system, if
earth or short circuit faults occurring in the grid on the there occur larger voltage variations or longer durations
high voltage side of the step-up transformer. The fault than those for which the unit has been designed, and
can be assumed to be cleared within 0.25 seconds. shall, in each case, be disconnected if the unit falls out-
Neither damage nor any need for immediate stoppage for of-step.
studying possible consequences is allowed.
The unit and its auxiliary power system shall be designed
for such voltage variations as to enable safe changeover
3.4.2 Maintaining Stability During Line Side to house load operation after disconnection from the grid.
Faults
The faults occurring beyond the line breaker of an 3.6 Reactive Power Output at Low
outgoing line will normally be isolated from the 400 kV Voltages
grid within 0.1 seconds. In exceptional cases the clearing
Power unit shall be equipped with such excitation system
time may, however, extend to 0.25 seconds. In case of
and shall be designed for such power factor as to enable
220 kV and 110 kV line faults the normal clearing time is
the generator to be capable of providing a reactive power
within 0.5 seconds and in exceptional cases 1 second.
output of about the same magnitude as the rated active
The unit shall be designed so that it remains connected to power output for 10 seconds, in conjunction with a
the grid and continues its stable operation after isolation network disturbance where the generator busbar voltage
of a line side fault within 0.25 seconds. has declined to 70% of its rated value.
A unit equipped with a large single-shaft turbine generator
3.7 Reactive Power Capability
may be disconnected from the grid at a shorter time limit,
if it is obvious that it will be impossible to maintain stability Transformation ratio and tap-changers of the step-up
anyway. In this case a solution must be agreed upon with transformer and the auxiliary service transformer of the
the grid operator. unit, as well as voltage range and excitation system of the
generator shall be designed and adjusted so that the
3.4.3 Deep Voltage Transient generator is at normal operating voltage of the grid
capable of generating continuously the reactive power
The units with their auxiliary systems shall be designed defined by the capability curve of the generator (at
so that they can withstand the following generator voltage generator voltage level) and, on the other hand, is at
variations resulting from faults in the grid, without normal operating voltage of the grid capable of
disconnection from the grid (Figure 2): consuming continuously the reactive power defined by
− step reduction to 25% of the rated generator voltage the capability curve of the generator (at the generator
lasting for 0.25 sec, voltage level).

− followed by linear increase to 95% in 0.5 seconds, The generator shall be capable of consuming
continuously the reactive power (underexcited operation)
− followed by constant generator voltage of 95%. defined by the capability curve of the generator also at
the maximum voltages (420, 245 and 123 kV) of the grid,
Consequently, only a small power reduction can be
assuming that the stability is maintained.
accepted.

-3-
4 REQUIREMENTS CONCERNING instantaneous disturbance reserves are not enough to
POWER CONTROL CHARACTERISTICS return the power system to its normal condition.

Turbine Governor 6.1 Power Control - General


All power plants shall be equipped with a turbine governor
and associated speed control systems. 6.1.1 Starting Time
Units for load following should be designed so that the
4.2 House Load Operation starting time from standstill to full load operation is as
short as possible.
All power plants shall be designed to safely change over
to house load operation from conditions specified in The following guidelines apply to gas turbines for
sections 2.4, 2.5 and 3.5 or when the grid frequency emergency and peak load generation, from rolling-up to
and/or the grid voltage variation exceed the requirements. full power output:
House load operation is a unit operating with its own − gas turbines of the jet engine type 3 to 3.5 minutes
auxiliary supply as the only load.
− industrial gas turbines 10 to 15 minutes.
Power plants shall be designed so that they can operate
in house load operation for at least 1 hour. Nuclear power 6.1.2 Minimum Output
units shall be capable of operating in house load
operation for the duration determined by the nuclear The minimum continuous output power should be as low
safety conditions. as possible. The following practical guidelines for the
minimum output power of power units can be used:
4.3 Island Operation − Coal-fired units: 40% of full output
In island operation the power system is separated into power
smaller systems, which operate asynchronously. In order − Oil and gas-fired units: 20% of full output
to be able to resynchronise the power system, power power
plants connected to islands shall be able to control their − Nuclear units: 20% of full output
power according to instructions given by the grid power
operator. − Hydro units (Francis): 20% of full output
power
− Hydro units (Kaplan): 10% of full output
5 VERIFICATION power

5.1 Tests For different kinds of power plants the above guidelines
can be used when applicable.
The specifications shall be verified with full-scale tests, if
possible. 6.1.3 Overload Capacity
These tests shall be made at the commissioning and by It is recommended to utilise the overload capacity only to
the owner at regular intervals throughout the entire the extent that is intrinsically available in the unit.
lifetime of the power plant. Recordings of data from the
actual operation shall be reviewed regularly in order to 6.1.4 Operational Modes
prove compliance with the specification.
The change of output power of a power unit, during
5.2 Verification during Commissioning normal control and during disturbance control, is normally
activated either with manual operation or with the unit
5.2.1 Tests Concerning the Grid controller.

The tests concerning the grid must be separately agreed The set value of the unit controller is 50 Hz. The set point
with the grid operator. Following tests and measurements resolution or the adjustable frequency dead band of the
shall be done: controller should be 0.05 Hz or less. It shall also be
possible to disengage the dead band.
− Deep voltage transient by short circuit
− Changeover to house load operation The statics set point (providing droop characteristic) is
− House load operation for 1 hour recommended to be adjustable within the range from 2%
to 8%. The normal operation is generally within the
5.2.2 Tests Concerning the Power Unit setting range of 4% to 6%.
Following tests and measurements shall be done:
6.1.5 Power Step Change Limiter
− Full output power and capability curve
− Step response of generator voltage The units are recommended to be equipped with
− Power system stabiliser (PSS) test adjustable devices for limiting the magnitude and rate of
− Overload capacity. the power change.

6 RECOMMENDATIONS CONCERNING 6.1.6 Power Control - Normal Operation and


POWER CONTROL CHARACTERISTICS Disturbances

In this section some recommendations are given, that The required power output during normal operation is the
aim to maintain adequate power control characteristics in manually pre-set power output, modified by a frequency-
power units connected to the Nordic grid. These sensing unit controller (or turbine governor). Power
characteristics may be needed for instance in exceptional control during normal operation is recommended to meet
situations, where normal frequency control and the specifications of section 6.2. When using the power

-4-
unit to frequency control, the control characteristics must power. In the remainder of the power range between the
be specified more accurately in a separate contract. minimum load and the full load, the power response rate
is recommended to be at least 1% of the full power per
The normal operation turns into disturbed operation when minute.
the rate of change in frequency exceeds ± 0.5 Hz/s, or
the error in frequency set point is more than 0.5 Hz. The Comment on items 6.2.4 and 6.2.5: The power response
need for disturbance control shall be governed by the rates of the units equipped with standard versions of light
frequency-sensing equipment (e.g. consisting of water reactors are usually sufficient. However, it should
frequency relay set at a certain value below normal be noted that the power response rate is subject to
frequency). Power control during disturbances is certain restrictions, due to the structure of fuel elements.
recommended to meet the specifications of section 6.3. If It is expected that these problems will be solved, and the
the power unit is utilised as instantaneous disturbance units should therefore be designed to conform to the
reserve, the control characteristics must be specified recommended power response rates. However, in order
more accurately in a separate contract. to limit the stresses imposed, the power changes during
normal daily and weekly load following should be carried
6.2 Power Response Capability during Normal out gradually over a period of about two hours.
Operation of the Power System
6.3 Power Response Capability during Power System
6.2.1 Load Following Disturbances4

All condensing units are recommended to be designed so 6.3.1 Power Step Change - Fossil Fuel
that they can be used for load following using the load
change rates specified in sections 6.2.2 - 6.2.5. In case of Fossil-fired thermal units are recommended to be
other type of units than mentioned in these sections, the designed with an operating mode allowing an
recommendations given in section 6.2.3 can be used instantaneous step change in output power of at least 5%
when applicable. of the full output within the range of 50-90% when
requested.
6.2.2 Power Response Rate and Range - Oil and Gas Backpressure units with condensing turbines are
Oil-fired and gas-fired units are recommended to be recommended to be designed so that during network
designed for a power response rate of at least plus or disturbances the maximum condensed power is available
minus 8% of the full power per minute. for 15 minutes by steering the heating power to the
condenser.
The above rate of change is recommended to be
applicable to any 30% change between 40% and 100% of 6.3.2 Power Step Change - Nuclear
the full power according to the load schedule. The power
response rate may be limited to the maximum power PWR nuclear power units to which the power change
response rate permissible for the turbines or the steam signal is applied directly to adjust the turbine control valve
boilers in the range below 40% and above 90%. are recommended to be designed so that a power step of
10% of the full power can be accommodated within 30%
6.2.3 Power Response Rate and Range - Coal of the power range. BWR nuclear power units operating
on pressure control are recommended to be designed so
Coal-fired units are recommended to be designed for a that, within the range of the pump control, they will be
power response rate of at least plus or minus 4% of the capable of accommodating a power step change of 10%
full power per minute. of the initial value.
The above rate of change should be applicable to any
30% change between 60% and 100% of the full power 6.3.3 Subsequent Power Response Rate
according to the load schedule. This range may be After the power step changes specified above, thermal
restricted to 20% in certain cases. The power response power units are also recommended to be capable of
rate may be limited to the maximum power response rate accommodating a load change at the rates specified in
permissible for the turbines or steam boilers in the range section 6.2. However, the total load change may then be
below 60% and above 90% limited to the values specified in sections 6.2.2 - 6.2.5
above.
6.2.4 Power Response Rate and Range - PWR
Nuclear 6.3.4 Spinning Disturbance Reserve
PWR nuclear power units are recommended to be Power units are recommended to be designed so that
designed for a power response rate of at least plus or they can be used as spinning disturbance reserves. In
minus 5% of the full power per minute within the output case the power system can not be restored to its normal
range of 60% to 100% of the full power. At outputs below state by utilising the separately contracted reserve, the
60%, the power response rate may be limited to the grid operator has the right to demand units to adjust their
maximum power response rate permissible for the power in the region specified above. This kind of
turbines. exceptional situation can be caused by a disturbance
more severe than the main grid dimensioning criteria
6.2.5 Power Response Rate and Range - BWR specify, or by some other unexpected reason.
Nuclear
BWR nuclear power units are recommended to be 6.3.5 Island Operation
designed for a power response rate per minute of at least In case of very serious (and exceptional) disturbances, in
plus or minus 10% of the initial output value. This is which the power system is separated into smaller islands,
recommended to be maintained throughout the output
range within which the power can be controlled with the 4
Power system disturbances are frequency or voltage
speed of the main circulation pumps. This output range is disturbances and include in severe cases stability disturbances as
recommended to be at least 30% of the initial output well.

-5-
the units are also recommended to be capable of The additional requirements for the units caused by the
performing the above power changes (upwards or local grid shall be taken into account separately.
downwards), and then achieving stable operation and
14.4.2000 / JYJU
normal power control capability according to section 6.2.

-6-

Anda mungkin juga menyukai