Nama Paket DED Pembangunan Pengaman Tebing Sungai Kampa 1 10-Feb

APBN Tahun Anggaran 2017 2 17-Feb


3 25-Feb
4 4-Mar
PPK DANANG SUKMANA, ST., M.Eng 5 12-Mar
NIP. 19860918 200912 2 001 6 19-Mar
7 27-Mar
PENGAWAS PEKERJAAN CAHAYA SANTOSO SAMOSIR, ST., MT 8 3-Apr
NIP. 19840921 200912 1 001 9 11-Apr
10 18-Apr
Ketua Team Ir. ANDI EKAPUTRA, MT 11 26-Apr
Team Leader 12 3-May
13 11-May
Konsultan Perencana PT. TRIDECONST 14 18-May
SYARIF HARTONO, ST 15 26-May
Direktur 16 2-Jun
17 10-Jun
Pekanbaru, Februari 2017 18 17-Jun
19 25-Jun
20 2-Jul
21 10-Jul
22 17-Jul
23 25-Jul
24 1-Aug
25 9-Aug
26 16-Aug
27 24-Aug
28 31-Aug
16-Feb 7 03 Febr05 Maret04 April 04 Mei - 03 juni - 03 Juli - 01 Agustus 2016
24-Feb 8
3-Mar 7
11-Mar 8 30 1 2 3 4 5 6 7 8
18-Mar 7 10-Feb 17-Feb 25-Feb 4-Mar 12-Mar 19-Mar 27-Mar 3-Apr
26-Mar 8 16-Feb 24-Feb 3-Mar 11-Mar 18-Mar 26-Mar 2-Apr 10-Apr
2-Apr 7
10-Apr 8 30
17-Apr 7
25-Apr 8
2-May 7
10-May 8 30
17-May 7
25-May 8
1-Jun 7
9-Jun 8 30
16-Jun 7
24-Jun 8
1-Jul 7
9-Jul 8 30
16-Jul 7
24-Jul 8
31-Jul 7
8-Aug 8 30
15-Aug 7
23-Aug 8
30-Aug 7
7-Sep 8 30

180 180
9 10 11 12 13 14 15 16 17 18 19 20
11-Apr 18-Apr 26-Apr 3-May 11-May 18-May 26-May 2-Jun 10-Jun 17-Jun 25-Jun 2-Jul
17-Apr 25-Apr 2-May 10-May 17-May 25-May 1-Jun 9-Jun 16-Jun 24-Jun 1-Jul 9-Jul
21 22 23 24
10-Jul 17-Jul 25-Jul 1-Aug
16-Jul 24-Jul 31-Jul 8-Aug
RINCIAN BIAYA LANGSUNG PERSONIL DAN BIAYA LANGSUNG NON PERSONIL

Pekerjaan : DED Pembangunan Pengaman Tebing Sungai Kampar Kec. Kampar Kabupaten Kampar
Lokasi : Provinsi Riau
Satuan Kerja : Balai Wilayah Sungai Sumatera III
Waktu Pelaksanaan : 7 (Tujuh) Bulan
Sumber Dana : APBN TA. 2021
Tahun Anggaran : 2021

HARGA
No. URAIAN SATUAN VOLUME SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6)
I. BIAYA LANGSUNG PERSONIL 40,423,050
A TENAGA AHLI
1 Ketua Team/Ahli Desain Bangunan Air OB 1 x 7 - -
2 Ahli Hidrologi / Hidrolika OB 1 x 5 2,826,540 14,132,700
3 Ahli Morfologi Sungai OB 1 x 3 2,018,880 6,056,640
4 Ahli Geodesi dan GIS OB 1 x 4 2,018,880 8,075,520
5 Ahli Mekanika Tanah OB 1 x 3 2,018,880 6,056,640
6 Ahli Lingkungan & Sosek Kelembagaan OB 1 x 1 2,018,880 2,018,880
7 Ahli K3 Konstruksi OB 1 x 1 2,063,790 2,063,790
8 Ahli Operasi dan Pemeliharaan OB 1 x 1 2,018,880 2,018,880
SUB TOTAL I.A. 40,423,050
B TENAGA TEKNISI
1 Surveyor Topografi, Hidrometri, Pengumpulan data OB 2 x 2 - -
2 Surveyor Hidrologi, Hidrolika Sungai OB 2 x 2 - -
3 Surveyor Mekanika Tanah OB 2 x 2 - -
SUB TOTAL I.B. -
C TENAGA PENDUKUNG
1 Juru Gambar/Drafter OB 1 x 2 - -
2 Tenaga Administrasi/Operator Database OB 1 x 7 - -
SUB TOTAL I.C. -
II. BIAYA LANGSUNG NON PERSONIL 389,770,170
A BIAYA PERJALANAN DINAS
1 Ketua Team/Ahli Desain Bangunan Air OK 1 x 14 200,000 2,800,000
2 Ahli Hidrologi, Hidrolika dan Hidrometri Sungai OK 1 x 10 200,000 2,000,000
3 Ahli Morfologi Sungai OK 1 x 8 200,000 1,600,000
4 Ahli Geodesi dan GIS OK 1 x 10 200,000 2,000,000
5 Ahli Mekanika Tanah OK 1 x 6 200,000 1,200,000
6 Ahli Lingkungan, Sosial Ekonomi dan Kelembagaan OK 1 x 2 200,000 400,000
7 Ahli K3 OK 1 x 2 200,000 400,000
8 Ahli Operasi dan Pemeliharaan OK 1 x 2 200,000 400,000
9 Surveyor Topografi, Hidrometri, Pengumpulan data GI OK 2 x 4 200,000 1,600,000
10 Surveyor Hidrologi, Hidrolika Sungai OK 2 x 4 200,000 1,600,000
11 Surveyor Mekanika Tanah OK 2 x 4 200,000 1,600,000
SUB TOTAL II.A. 15,600,000
B BIAYA PERJALANAN DINAS (PusAir Bandung)
Pesawat
1 Ketua Team / Ahli SDA TRIP 1 X 1 - -
Ahli Teknik Hidrologi dan Hidrolika / Ahli Terkait
2 TRIP 1 X 1 - -
Lainnya
Penginapan
1 Penginapan di Bandung UH 1 X 1 - -
Taksi
1 Taksi di Bandung TRIP 1 x 1 - -
SUB TOTAL II.B. -
B ATK DAN KOMUNIKASI
1 ATK bln 1 x 7 2,000,000 14,000,000
2 Pengadaan Data Sekunder dan Peta-Peta LS 1 2,000,000 2,000,000
3 Komunikasi (telp. & Internet), surat menyurat bln 1 x 7 2,000,000 14,000,000
SUB TOTAL II.B. 30,000,000
C SEWA PERLENGKAPAN KANTOR
1 Sewa Komputer UB 1 x 7 500,000 3,500,000
Sewa Kantor di Pekanbaru (termasuk listrik, PAM dan
2 UB 1 x 7 1,250,000 8,750,000
pemeliharaan lainnya)
3 Sewa Printer A3 dan A4 UB 1 x 7 350,000 2,450,000
4 Sewa Scanner UB 1 x 7 300,000 2,100,000
SUB TOTAL II.C. 16,800,000
D DISKUSI
1 Diskusi Lap. Pendahuluan Kali 1 7,500,000 7,500,000
2 Diskusi Lap. Interim Kali 1 5,000,000 5,000,000
3 Diskusi Draft Lap. Akhir Kali 1 8,500,000 8,500,000
4 Pertemuan Konsultasi Masyarakat (PKM) Kali 1 11,000,000 11,000,000
4 Diskusi Teknis (Di Pekanbaru) Kali 1 - -
5 Diskusi Teknis (Home Doctor, Puslitbang SDA di Bandung) Kali 1 - -
6 Pertemuan Konsultasi Masyarakat (PKM) Kali 2 - -
SUB TOTAL II.D. 32,000,000
E SURVEY
1 Survei Topografi, Hidrometri dan Pengumpulan Data GIS
Sewa Electronic Total Station (Theodolit) UH 1 x 60 75,000 4,500,000
Sewa Water Pass UH 1 x 60 50,000 3,000,000
Sewa GPS UH 1 x 60 50,000 3,000,000
(Set) UB 1 x 1 8,000,000 8,000,000
Tenaga Lokal OH 1 x 60 100,000 6,000,000
Patok CP Bh 16 350,000 5,600,000
Patok Bench Mark Bh 8 750,000 6,000,000
Pengumpulan Peta Geospasial dan Bahan Survey Ls 1 2,500,000 2,500,000

2 Survei Hidrologi, Hidrolika dan Hidrometri Sungai


Pengumpulan Data / Foto Copy Ls 1 2,500,000 2,500,000
Sewa Perahu UH 1 x 30 - -
Pengukuran Muka Air Sungai (otomatis) Titik / Hari 1 x 60 530,000 31,800,000
Pengukuran Muka Air Laut dan Sungai Pasut -
Titik / Hari 8 x 60 -
(Otomatis) Periode 30 Hari
Sewa Echosounder UH 1 x 30 - -
Sewa Salinometer Bh 1 x 30 - -
Pengukuran Sungai (otomatis) Titik / Hari 1 x 60 800,000 48,000,000
Sewa Curen Meter UH 2 x 60 100,000 12,000,000
PH Meter UB 2 - -
Pemasangan Peil Skaal Bh 4 1,500,000 6,000,000
Botol Sample Botol 30 - -
Tenaga Lokal OH 1 x 60 100,000 6,000,000
Bahan Survey Ls 1 2,250,000 2,250,000

3 Survei Mekanika Tanah


Sewa Mobil Bak UH 1 x 60 150,000 9,000,000
Sewa Sondir UH 1 x 60 150,000 9,000,000
Sewa Hand Auger UH 1 x 60 50,000 3,000,000
Botol Sample Botol 28 -
Tenaga Lokal OH 1 x 60 100,000 6,000,000
Bahan Surveytanah keras) (Jika sebelum kedalaman
menemukan Ls 1 2,250,000 2,250,000
60 meter sudah ditemukan tanah keras, maka jumlah Titik 2 35,000,000 70,000,000
SPT ( per
titik bor inti2 di
meter dengan dan
tambahkan totaldisesuikan
kedalamandi60lokasi
meterlain
Titik 4 200,000 800,000
setiap titik), lokasi sama dengan lokasi Bor Inti
Test Permeabilitas Lapangan (Lugeon) Titik 8 700,000 5,600,000

4 Survei Sosial Ekonomi dan Lingkungan


Bahan Survei Sosial Ekonomi dan Lingkungan Ls 1 2,250,000 2,250,000
5 Pekerjaan Laboratorium
1. Sampel Mekanika Tanah
- Disturb Sample sample 10 350,000 3,500,000
- Undisturb Sample sample 10 350,000 3,500,000
- Falling Head Sample sample 7 - -
- Constanta Head Sample sample 7 - -
2. Sampel Air
- Kualitas Air sample 14 - -
- Sampel Sedimen Melayang dan Dasar sample 10 700,000 7,000,000
SUB TOTAL II.E. 269,050,000
F PELAPORAN
1 Program Mutu bk 3 80,000 240,000

2 Bulanan bk 3 x 7 20,000 420,000

3 Konsep Laporan Pendahuluan bk 3 80,000 240,000

4 Laporan Pendahuluan bk 3 80,000 240,000

5 Konsep Laporan Antara bk 3 80,000 240,000

6 Laporan Antara bk 3 80,000 240,000

7 Konsep Laporan Akhir bk 3 80,000 240,000

8 Laporan Akhir bk 5 80,000 400,000

9 - Buku Topographi, Hidrometri, GIS dan Peta Situasi


bk 3 80,000 240,000
Topografi 1:100 Untuk Detail Bangunan
- Buku Data Ukur, Pengukuran Topografi Aktual Drone
10 Yang Dikaloborasikan Dengan Alat Geodetik dan Hasil bk 3 80,000 240,000
Perhitungannya
11 - Buku Hidrologi, Hidrometri dan Hidrolika Sungai dan
bk 3 80,000 240,000
Hasil Laboratorium
12 - Buku Mekanika Tanah/Soil dan Hasil Laboratorium bk 3 80,000 240,000

13 - Buku Sosial Ekonomi Kelembagaan bk 3 80,000 240,000

14 - Buku Dokumen Lingkungan bk 3 80,000 240,000

15 -Laporan Rancangan Konseptual SMKK bk 3 80,000 240,000


- Nota Perhitungan Desain, System Planning dan
16 Perhitungan Desain Rinci Bangunan Pengaman bk 3 80,000 240,000
Tebing Sungai
17 - Buku Permodelan Pengaman Tebing Sungai bk 3 80,000 240,000

18 - Buku Spesifikasi Teknik, Dokumen Tender, Rencana


bk 3 80,000 240,000
Anggaran Biaya (RAB) dan Bill of Quantity (BOQ)
19 Bahan Material, Sumber Daya Manusia, Resiko,
bk 3 80,000 240,000
Kebutuhan Alat Berat, Mobilisasi dan demobilisasi,
20 Banjir Eksisting dan Lokasi Rencana, Analisa
bk 3 80,000 240,000
Bangunan Pengaman Tebing Sungai dan Sistem
21 - Buku Pedoman dan Manual OP Pekerjaan bk 3 80,000 240,000

22 - Buku Metode Pelaksanaan Konstruksi Bangunan


bk 3 80,000 240,000
Pengaman Tebing Sungai
23 Master Gambar Peta Ploting A3 Warna (set) Set 3 1,250,000 3,750,000

24 Master Gambar Peta Ploting Print A1 Warna (set) Set 3 2,000,000 6,000,000

25 Master Gambar Masterplan Print A1 Warna (set) Set 3 2,000,000 6,000,000


26 Master Gambar Masterplan Print A3 Warna (set) Set 3 1,250,000 3,750,000

Soft Copy Laporan, Gambar Desain & Pemodelan


27 bh 1 900,170 900,170
(external harddisk 1000 GB)
28 Foto Dokumentasi Album 2 150,000 300,000
SUB TOTAL II.F. 26,320,170
RENCANA JADWAL PELAKSANAAN PEKERJAAN ( TIME SCHEDULE )

Pekerjaan : DED Pembangunan Pengaman Tebing Sungai Kampar Kec. Kampar Kabupaten Kampar
Lokasi : Provinsi Riau
Satuan Kerja : Balai Wilayah Sungai Sumatera III
Waktu Pelaksanaan : 7 (Tujuh) Bulan
Sumber Dana : APBN TA. 2021
Tahun Anggaran : 2021 3.20 % 2.22 %
4.10 % 2.22%
2021
BOBOT PERIODE BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 BULAN 7
No. URAIAN PEKERJAAN % BOBOT KET.
(%) MINGGU KE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
10-Feb 17-Feb 25-Feb 4-Mar 12-Mar 19-Mar 27-Mar 3-Apr 11-Apr 18-Apr 26-Apr 3-May 11-May 18-May 26-May 2-Jun 10-Jun 17-Jun 25-Jun 2-Jul 10-Jul 17-Jul 25-Jul 1-Aug 9-Aug 16-Aug 24-Aug 31-Aug
WAKTU
16-Feb 24-Feb 3-Mar 11-Mar 18-Mar 26-Mar 2-Apr 10-Apr 17-Apr 25-Apr 2-May 10-May 17-May 25-May 1-Jun 9-Jun 16-Jun 24-Jun 1-Jul 9-Jul 16-Jul 24-Jul 31-Jul 8-Aug 15-Aug 23-Aug 30-Aug 7-Sep

I PEKERJAAN PERSIAPAN 22.26%

RENCANA 1.66 % 0.83 % 0.83 % 0.83 % 0.83 % 0.83 % 0.83 % 100


1 Persiapan Administrasi, Mobilisasi Tenaga Ahli dan Peralatan 6.64%
REALISASI 0.83 % 0.83 % 0.83 % 1.66 % 0.83 % 0.83 % 0.84 %
RENCANA 1.24 % 0.62 % 0.62 % 0.31 % 0.31 % 0.31 % 0.31 % 0.62 % 0.62 %
2 Pengumpulan Data Sekunder 4.97%
REALISASI 0.62 % 0.62 % 0.62 % 0.31 % 0.62 % 0.62 % 0.62 % 0.94 %
RENCANA 1.55 % 0.78 % 1.55 % 0.78 %
3 Penyusunan Program Mutu 4.66%
REALISASI 1.55 % 1.55 % 1.55 %
RENCANA 2.00 % 2.00 % 2.00 %
4 Orientasi Lapangan 5.99%
REALISASI 2.99 % 2.99 %

II PENGUMPULAN DATA LAPANGAN 54.46%

RENCANA 1.59 % 1.59 % 1.59 % 1.59 %


1 Survei Topografi, Hidrometri dan Pengumpulan Data GIS 6.37%
REALISASI 3.00 % 1.00 % 1.00 %
RENCANA 1.10 % 1.10 % 1.10 % 1.10 %
2 Pemasangan BM & Patok CP 4.38%
REALISASI 1.10 % 1.00 % 2.00 %
RENCANA 1.59 % 1.59 % 1.59 % 1.59 % 1.59 % 1.59 % 1.59 % 1.59 % 1.59 %
3 Survei Hidrologi, Hidrolika dan Hidrometri Sungai 14.35%
REALISASI 2.00 %
RENCANA 1.00 % 1.00 % 1.00 % 1.00 % 1.00 %
4 Pemasangan Peil Skaal 5.02%
REALISASI 1.00 %
RENCANA 0.76 % 0.76 % 0.76 % 0.76 %
5 Pengambilan Data Hand Auger 3.04%
REALISASI 1.00 %
RENCANA 1.32 % 1.32 % 1.32 % 1.32 % 0.66 % 0.66 % 0.66 % 0.66 % 1.32 % 1.32 %
6 Pengambilan Data Bor Inti 10.60%
REALISASI 0.50 % 80
RENCANA 0.45 % 0.45 % 0.45 % 0.45 % 0.45 % 0.45 % 0.45 % 0.45 %
7 Pengambilan Data SPT 3.60%
REALISASI 1.20 % 0.25 % 0.25 %
RENCANA 1.03 % 1.03 % 1.03 %
8 Test Permeabilitas Lapangan (Lugeon) 3.10%
REALISASI
RENCANA 0.59 % 0.59 % 0.59 %
9 Survei Sosial Ekonomi dan Lingkungan 1.77%
REALISASI
RENCANA 0.12 % 0.12 % 0.12 % 0.37 % 0.74 % 0.74 %
10 Pengujian Sample Laboratorium 2.22%
REALISASI

III DISKUSI 13.92%

RENCANA 0.80 % 0.80 % 0.80 % 0.80 %


1 Diskusi Lap. Pendahuluan 3.20%
REALISASI 0.80 % 0.80 % 0.80 % 0.80 %
RENCANA 2.98 %
2 Diskusi Lap. Interim 2.98%
REALISASI
RENCANA 1.14 % 1.14 % 1.14 %
3 Diskusi Draft Lap. Akhir 3.42%
REALISASI
RENCANA 2.16 % 2.16 %
4 Pertemuan Konsultasi Masyarakat (PKM) 4.33%
REALISASI

IV PENYUSUNAN LAPORAN 9.36% 60


RENCANA 0.43 %
1 Laporan Program Mutu 0.43%
REALISASI 0.43 %
RENCANA 0.07 % 0.07 % 0.07 % 0.07 % 0.07 % 0.07 % 0.07 %
2 Laporan Bulanan 0.49%
REALISASI 0.07 % 0.07 %
RENCANA 0.23 % 0.23 %
3 Konsep Laporan Pendahuluan 0.45%
REALISASI 0.23 % 0.23 %
RENCANA 0.46 %
4 Laporan Pendahuluan 0.46%
REALISASI 0.46 %
RENCANA 0.44 %
5 Konsep Laporan Antara 0.44%
REALISASI
RENCANA 0.47 %
6 Laporan Antara 0.47%
REALISASI
RENCANA 0.46 %
7 Konsep Laporan Akhir 0.46%
REALISASI
RENCANA 0.47 %
8 Laporan Akhir 0.47%
REALISASI

9 Laporan Pendukung

- Buku Topographi, Hidrometri, GIS dan Peta Situasi Topografi 1:100 RENCANA
0.22% 0.22 % 40
Untuk Detail Bangunan REALISASI
RENCANA 0.20 %
- Buku Data Ukur, Pengukuran Topografi Aktual Drone 0.20%
REALISASI

- Buku Hidrologi, Hidrometri dan Hidrolika Sungai dan Hasil RENCANA 0.18 %
0.18%
Laboratorium REALISASI
RENCANA 0.18 %
- Buku Mekanika Tanah/Soil dan Hasil Laboratorium 0.18%
REALISASI
RENCANA 0.18 %
- Buku Sosial Ekonomi Kelembagaan 0.18%
REALISASI
RENCANA 0.19 %
- Buku Dokumen Lingkungan 0.19%
REALISASI
RENCANA 0.18 %
- Laporan Rancangan Konseptual SMKK 0.18%
REALISASI

- Nota Perhitungan Desain, System Planning dan Perhitungan Desain RENCANA 0.18 %
0.18%
Rinci Bangunan Pengaman Tebing Sungai REALISASI
RENCANA 0.18 %
- Buku Permodelan Pengaman Tebing Sungai 0.18%
REALISASI

- Buku Spesifikasi Teknik, Dokumen Tender, Rencana Anggaran Biaya RENCANA 0.17 %
0.17%
(RAB) dan Bill of Quantity (BOQ) REALISASI
- Buku Analisis Biaya, Mutu, Waktu, Sumber dan Bahan Material, Sumber Daya RENCANA 20
Manusia, Resiko, Kebutuhan Alat Berat, Mobilisasi dan demobilisasi, Perijinan yang 0.17% 0.17 %
diperlukan dan Ekonomi Teknik. REALISASI
- Buku Inventarisir, Analisa Bangunan Pengendali Banjir Eksisting dan Lokasi RENCANA
Rencana, Analisa Bangunan Pengaman Tebing Sungai dan Sistem Perbaikan 0.17% 0.17 %
Pengaturan Sungai REALISASI
RENCANA 0.17 %
- Buku Pedoman dan Manual OP Pekerjaan 0.17%
REALISASI

- Buku Metode Pelaksanaan Konstruksi Bangunan Pengaman Tebing RENCANA 0.17 %


0.17%
Sungai REALISASI
RENCANA 0.67 %
10 Master Gambar Peta Ploting A3 Warna (set) 0.67%
REALISASI
RENCANA 0.85 %
11 Master Gambar Peta Ploting Print A1 Warna (set) 0.85%
REALISASI
RENCANA 0.85 %
12 Master Gambar Masterplan Print A1 Warna (set) 0.85%
REALISASI
RENCANA 0.67 %
13 Master Gambar Masterplan Print A3 Warna (set) 0.67%
REALISASI

Soft Copy Laporan, Gambar Desain & Pemodelan (external harddisk RENCANA 0.08 %
14 0.08%
1000 GB) REALISASI
RENCANA 0.03 %
15 Foto Dokumentasi 0.03%
REALISASI 0

TOTAL 100.00% KETERANGAN : RENCANA REALISASI

RENCANA KEMAJUAN MINGGUAN 4.46% 4.22% 5.43% 1.99% 3.94% 2.17% 4.86% 6.68% 6.98% 9.45% 6.76% 5.20% 5.13% 3.71% 2.71% 2.76% 4.11% 1.45% 1.45% 0.19% 0.37% 0.74% 1.88% 3.37% 1.14% 2.16% 2.15% 4.55%

RENCANA KUMULATIF MINGGUAN 4.46 % 8.68 % 14.11 % 16.10 % 20.03 % 22.20 % 27.06 % 33.74 % 40.72 % 50.16 % 56.92 % 62.12 % 67.26 % 70.97 % 73.68 % 76.44 % 80.54 % 81.99 % 83.44 % 83.63 % 84.00 % 84.74 % 86.63 % 90.00 % 91.14 % 93.30 % 95.45 % 100.00 %

REALISASI KEMAJUAN MINGGUAN 3.00 % 6.43 % 6.00 % 2.04 % 2.25 % 2.48 % 2.49 % 7.57 % 2.25 % 7.75 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 % 0.00 %

REALISASI KUMULATIF MINGGUAN 3.00 % 9.43 % 15.43 % 17.46 % 19.71 % 22.19 % 24.68 % 32.25 % 34.50 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 % 42.25 %

D E V I A S I (+) / (-) -1.45% 0.75% 1.32% 1.37% -0.32% -0.01% -2.38% -1.49% -6.22% -7.92% -14.67% -19.88% -25.01% -28.72% -31.43% -34.19% -38.30% -39.74% -41.19% -41.39% -41.76% -42.50% -44.38% -47.75% -48.89% -51.06% -53.20% -57.75%

Diketahui/Disetujui Oleh : Dibuat Oleh


PEJABAT PEMBUAT KOMITMEN Konsultan Perencana
PERENCANAAN DAN PROGRAM PT. TRIDECONST

DANANG SUKMANA, ST., M.Eng SYARIF HARTONO, ST


19880606 201012 1 002 Direktur
JADWAL PERSONIL
Satuan Kerja : Operasi dan Pemeliharaan SDA Sumatera III
Pekerjaan : Penyusunan Penilaian Kinerja dan Penyusunan AKNOP Sarana Prasarana Sungai WS Indragiri
Tahun Anggaran : 2017
No. Kontrak : KU.02.08/09/PPK/OP SDA I/SATKER OP SDAS III/2017 Tanggal 09 Februari 2017

WAKTU PELAKSANAAN
Kebutuhan
NO JABATAN DALAM TEAM NAMA Bulan 1 Bulan 2 Bulan 3 Bulan 4 Bulan 5 Bulan 6 KET
Man-Month
10-Feb 17-Feb 25-Feb 4-Mar 12-Mar 19-Mar 27-Mar 3-Apr 11-Apr 18-Apr 26-Apr 3-May 11-May 18-May 26-May 2-Jun 10-Jun 17-Jun 25-Jun 2-Jul 10-Jul 17-Jul 25-Jul 1-Aug
16-Feb 24-Feb 3-Mar 11-Mar 18-Mar 26-Mar 2-Apr 10-Apr 17-Apr 25-Apr 2-May 10-May 17-May 25-May 1-Jun 9-Jun 16-Jun 24-Jun 1-Jul 9-Jul 16-Jul 24-Jul 31-Jul 8-Aug
I TENAGA AHLI PROFESIONAL

6.00
1 Team Leader Ir. Andi Ekaputra, MT

2 Ahli Perencanaan SDA Eduard, ST 2.00

3 Ahli Sungai Nofia Sari, ST 2.00

II TENAGA AHLI PENDUKUNG

1 Operator Input Data Komp/ T Adm Irawan 6.00

2 Juru Gambar / Drafter Elvarida Sudanti, A.Md 2.00

3 Surveyor 1
Muhammad Zul Ichwan

Surveyor 2
Robi Kurniawan 2.00

Diketahui Oleh : Dibuat Oleh


PEJABAT PEMBUAT KOMITMEN Konsultan Perencana
OPERASI DAN PEMELIHARAAN SDA I PT. TRIDECONST

DANANG SUKMANA, ST., M.Eng SYARIF HARTONO, ST


NIP. 19860918 200912 2 001 Direktur
DAFTAR DAN JADWAL ALAT KERJA
Satuan Kerja : Operasi dan Pemeliharaan SDA Sumatera III
Pekerjaan : Penyusunan Penilaian Kinerja dan Penyusunan AKNOP Sarana Prasarana Sungai WS Indragiri
Tahun Anggaran : 2017
No. Kontrak : KU.02.08/09/PPK/OP SDA I/SATKER OP SDAS III/2017 Tanggal 09 Februari 2017

WAKTU PELAKSANAAN
Bulan 1 Bulan 2 Bulan 3 Bulan 4 Bulan 5 Bulan 6
No Peralatan Yang dipakai Unit Quantity Jumlah Satuan
10-Feb 17-Feb 25-Feb 4-Mar 12-Mar 19-Mar 27-Mar 3-Apr 11-Apr 18-Apr 26-Apr 3-May 11-May 18-May 26-May 2-Jun 10-Jun 17-Jun 25-Jun 2-Jul 10-Jul 17-Jul 25-Jul 1-Aug
16-Feb 24-Feb 3-Mar 11-Mar 18-Mar 26-Mar 2-Apr 10-Apr 17-Apr 25-Apr 2-May 10-May 17-May 25-May 1-Jun 9-Jun 16-Jun 24-Jun 1-Jul 9-Jul 16-Jul 24-Jul 31-Jul 8-Aug
I Survey Topografi

1 Theodolit 1 60 60 Hari

2 Water Pass 1 60 60 Hari

3 GPS 1 60 60 Hari

4 Bak Ukur 1 60 60 Hari

5 Bahan Survey 1 Ls 1 LS

6 Kendaraan Roda 2 2 2 2 UB

7 Kendaraan Mobil 1 2 1 UB

II Pengadaan dan Pemasangan Patok BM dan CP Sungai

1 Patok Bench Mark (BM) 10 Buah 12 Buah

2 Patok Control Point (CP) 10 Buah 12 Buah

3 Perahu 1 5 5 Hari

III Peralatan Kantor

1 Komputer + Printer 1 6 6 Bulan

2 Bahan Kantor/ATK 1 6 6 Bulan

3 Fax 1 6 6 Bulan

4 Telepon 1 6 6 Bulan

5 Surat Menyurat 1 6 6 Bulan

Diketahui Oleh : Dibuat Oleh:


PEJABAT PEMBUAT KOMITMEN Konsultan Perencana
OPERASI DAN PEMELIHARAAN SDA I PT. TRIDECONST

DANANG SUKMANA, ST., M.Eng SYARIF HARTONO, ST


NIP. 19860918 200912 2 001 Direktur
JADWAL ARUS KAS
Satuan Kerja : Operasi dan Pemeliharaan SDA Sumatera III
Pekerjaan : Penyusunan Penilaian Kinerja dan Penyusunan AKNOP Sarana Prasarana Sungai WS Indragiri
Tahun Anggaran : 2017
No. Kontrak : KU.02.08/09/PPK/OP SDA I/SATKER OP SDAS III/2017 Tanggal 09 Februari 2017

WAKTU PELAKSANAAN
NO URAIAN Bulan 1 Bulan 2 Bulan 3 Bulan 4 Bulan 5 Bulan 6 KET
10-Feb 17-Feb 25-Feb 4-Mar 12-Mar 19-Mar 27-Mar 3-Apr 11-Apr 18-Apr 26-Apr 3-May 11-May 18-May 26-May 2-Jun 10-Jun 17-Jun 25-Jun 2-Jul 10-Jul 17-Jul 25-Jul 1-Aug
16-Feb 24-Feb 3-Mar 11-Mar 18-Mar 26-Mar 2-Apr 10-Apr 17-Apr 25-Apr 2-May 10-May 17-May 25-May 1-Jun 9-Jun 16-Jun 24-Jun 1-Jul 9-Jul 16-Jul 24-Jul 31-Jul 8-Aug

1 Penarikan Uang Muka (20%)

2 Penarikan Terminj I (30%)

3 Penarikan Terminj II (40%)

4 Penarikan Terminj III (30%)