Abstract: The Italian Transmission Company (TERNA) since several years was trying to implement an
integrated on-line diagnostic system of their substation apparatus in order to reduce maintenance time and
increase the life time of their asset. To implement this system, TERNA wished to acquire some
significant parameters from various substation apparatus, to have the corresponding alarm signals, and to
base on these alarms its preventive maintenance.
ISA has developed this system in cooperation with TERNA. This paper deals with the development and
achievements.
1 INTRODUCTION
The development is based upon a new concept of on-line diagnostic system that has the goal to reduce the
maintenance cost and increase the substation apparatus lifespan.
Purpose of the line diagnostic system is to highlight malfunctions before these can cause an outage of the
substation. In order to achieve this goal it is necessary to set up a continuous monitoring system of the
field apparatus: any further maintenance with dedicated instruments can be programmed depending on the
information received.
A pivotal design criterion of the system is that the collection of monitoring devices must not lower the
overall system reliability. As a consequence of this design criterion, the actual manufacturing follows
guidelines of extreme reliability for the components used and of minimal connection to the controlled
system. Moreover, if one component of MCS system fails, it doesn’t disturb the system.
The architectural work that was the base for the development has been the following one:
. Decide which devices had to be considered for the continuous monitoring;
. Decide which parameters of these devices had to be monitored;
. Decide the diagnostic criteria to be applied to the measurements that should cause an alarm to the
supervisor.
There are four devices that can be monitored by our system units; they are:
- Circuit Breaker, that includes: CB unit and I2T unit,
- Current Transformer (CT unit),
- Voltage Transformer (VT unit),
- Surge Arrester (SA unit).
In the following are explained the measured parameters of each unit, and the alarm criteria applied by the
feeder unit.
2 SYSTEM DESCRIPTION
The following is the overall connection schematic of the system. There are:
. Measure units connected to the monitored devices;
. Data from these units (via direct wiring connections) go to a remote unit, that performs the analog to
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
digital conversion;
. Remote units are connected (via fiber optics) to the Feeder unit, where these data are analyzed by the
diagnostic criteria;
. Feeder units send their alarm messages (via ETHERNET) to the Substation Monitoring System, via a
Monitoring Recording Events interface.
The physical construction of the MCS system devices is designed to be mounted and fit to a variety of
devices installed in substations, and can be mounted in existing or new enclosures.
Feeder Unit 1
NETWORK
Measuring Unit nnn CONTROL
CENTER
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
3 REMOTE UNITS
In the next figure, you can see is a schematic representation of the signals processed by each remote unit
and where the remote units are mounted.
P.A. P.A.
SURGE
ARRESTER VT UNIT
OUTDOOR UNIT OUTDOOR Voltage (3 AI)
Current (6 AI)
OUTDOOR or VT BOX
OUTDOOR
110 V
110 V
U.S.
MEASURES COMPUTING CT UNIT
BREAKER UNIT: UNIT AND FIBRE SF6 Density (3 AI)
SELECTOR
Commands &
Auxiliary Contacts (13 DI)
110 V OUTDOOR
SF6 Density (3 AI)
Phase R
Phase S
IN FEEDER CUBICLE
CB CONTROL BOX Phase T
Protocol
IEC 60870-5-101
I2T UNIT
Current (3 AI)
MONITORING UNIT (U.M.) Busbar A/B (2 DI)
OF THE SCADA SYSTEM
IN FEEDER CUBICLE
or in Protection Cubicle
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
The following is the overall view of the diagnostic system for one feeder.
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
When an Open or Close command is generated from the substation control system, it is also acquired by
the CB unit. The command signals trigger the CB unit that records all digital signals, and measures the
corresponding timing. All measures, identified by the trigger channel and measured channel, are sent to
the feeder unit for subsequent processing.
Optionally, it is possible to have four more analogue measurements: 3 for CB coil current profile analysis,
one to monitor the subsystem battery.
The analogue signals acquired by I2T units are current measurements, taken from the CT secondary. By
these signals is it possible to compute the energy dissipated in every CB operation.
The unit is continuously ready to measure the current. The measurement is started by the feeder unit that
issues a measurement command when it recognizes an Open command from the CB unit. On the
measured currents, the I2T unit performs the following functions:
- It verifies if the current is greater than the programmed threshold;
- It detects the maximum interrupted current, taking in account the current values corresponding to the
arcing, that is the programmed duration before the current extinction: this is the parameter
transmitted to the feeder unit.
I
I MAX
computing
area DELAY
Te
The digital signals acquired by I2T units are the positions of feeder disconnectors: by means of these
signals is it possible to understand on which bus-bar the feeder is inserted.
The CT unit is acquires 3 analogue signals, that are the measurement of SF6 gas density. The
measurement is started by the feeder unit.
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
The analogue signals acquired by SA units are made of a central unit and of two peripheral units. Each
unit includes:
- 1 low current measurement: this allows testing the quality of ZnO, as per the method outlined by
IEC standards 60099-5 A1 ED. 1.0 Section 6: Diagnostic indicators of metal-oxide surge arresters
in service (method B1). Measurements performed are the peak of the total current and the rms
value of the third harmonic component.
- 1 high current measuring, that measures the current peak and time of occurrence when the arrester
is operating.
Units sense the current crossing the arrester ground connection.
The central unit receives the measurements from the peripheral units and converts them for the feeder
unit.
The low current measurement is started by the feeder unit at a low pace. The high current measurement is
polled by the feeder unit at high pace.
The VT unit is acquires 3 voltage signals. Purpose of this unit is to provide an accurate measure of the VT
secondary voltage: the MRE will detect the VT fault by comparing the measurements of the other VT in
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
the plant.
Upon a synchronization signal from the feeder unit, the VT unit computes true rms values of the voltages,
and transmits them to the feeder unit. In this way it’s possible to get measurements coming from
different VT units performed at the same time.
4 FEEDER UNIT
Each feeder units is connecting to up to 5 remote units and it is time synchronized with GPS clock (like
the remote units). Signals acquired by the feeder units are computed to generate alarms, trends,
measurements for the substation monitoring system.
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
For each type of timing there is a defined tolerance. The feeder unit checks the values against the
tolerances and, if surpassed, an alarm message is sent to the MRE system.
- RAPID VARIATION, FAULT: The density measurement is performed at a fast pace (for instance 10 s);
then it is performed an average over a programmable number of measures.
- SLOW VARIATION. The density measurement is performed once a day, overnight, when the
temperature is more stable, at the programmed time. The derivative is calculated on the average of a
programmable number of values, as a difference of the readings over two or more days.
In both instances, if the average varies of a value greater than the fault thresholds (programmable), the
corresponding event is immediately raised.
4.3.3 I2T
The current peak for each interruption is used to:
- Compute the corresponding I2T;
- Add up the measured value to the cumulated total, and refresh it.
The cumulated total is checked against the programmed threshold value, and the alarm is generated when
the threshold is surpassed. It is possible set a number of thresholds.
When the device is installed, the operator can program the cumulated I2T value at the moment of
installation.
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009
Session I-3
For the low current measurements, the peak and third harmonic values are checked against the
programmed thresholds. The feeder unit raises an alarm when the maximum programmed threshold is
surpassed. Two different alarm thresholds are defined: one for the fundamental current and the other one
for the 3rd harmonic current. The measure of the fundamental current is stored together with that of 3rd
harmonic, to complete the event information.
For the high current measurements, the feeder unit counts the total number of discharges, along with the
timing of the various events, and passes to the MRE this information along with the current peak value.
4.3.5 VT monitoring
The algorithm for the monitoring of the VT has the purpose of highlighting anomalies in the transformer,
despite the line voltage variations and the unavoidable measurement errors. The algorithm needs the
measurements coming from at least three VT connected to the same phase. These measures (every 4
hours) are synchronized by an IRIG-B device.
The algorithm operates on the differences between measurements, and locates the VT with the minimum
voltage output, having a difference with respect to the others that is beyond the pre-set limit.
Implementation of the monitoring algorithm for VTs could also be made in feeder units.
Each remote units and feeder units as well, have their firmware and setting parameters. By means of a
dedicated line on the feeder unit, separate from the interface to the substation monitoring system, but
using the same physical connections to send request to remote unit and receiving signals information, it
will also be possible to modify parameters of remote units or measuring units, and also to upgrade their
firmware without the need of physically go in the field.
5 CONCLUSIONS
The on-line monitoring system is very flexible as the remote units are not dependent from the devices
manufacturer and the feeder central unit can handle different protocols.
The proposed ISA on-line diagnostic system allows to monitor a variety of substation devices (existing
and new) with reduced impact with the existing circuit in order to have a condition based maintenance
reducing the outage time, the related cost and increase the devices lifespan.
6 REFERENCES
[1] EN 60694: Common specifications for high voltage switchgear and controlgear standards
[2] IEC standards 60099-5 A1 ED. 1.0 Section 6: Diagnostic indicators of metal-oxide surge arresters in
service (method B1).
[3] M. Puricelli “MCS System for continuous monitoring of substation devices” Rev 6 – dated
09/12/2008 – ISA Doc number SIIMCS_6.
International Conference on Condition Monitoring & Diagnostic Engineering Management of Power Station / Substation Equipment - 2009