ude Liwun
HARGA SATUAN, GALIAN C dan PAJAK
Provinsi : Nusa Tenggara Timur Lokasi Sinar Hading
Kabupaten : Flores Timur Jenis Kegiatan TPT
Kecamatan : Lewolema
Desa : Sinar Hading
Pajak HARGA
Harga Dasar
NO UPAH Satuan PPH SATUAN Keterangan
( Rp ) 5% ( Rp )
1 Tukang Hok 85,000 85,000 85,000 4,250 89,250
2 Pekerja Hok 50,000 50,000 50,000 2,500 52,500
Take Of Sheet
NO URAIAN KEGIATAN / GAMBAR SKETSA URAIAN PERHITUNGAN VOLUME SAT
a b c d e
I PEKERJAAN TANAH
1.a Pembersihan Lokasi
Panjang = 45 M
Lebar = 0.5 M
Volume = 22.50 22.50 M³
0.20
0.80
Panjang = 45 M
Lebar Atas = 0.2 M
Lebar Bawah = 0.4 M
0.25 Tinggi = 0.8 M
Volume = 10.80
0.40
Panjang = 45
Lebar = 1.02
0.20
Tebal = 0.02
0.82
TOTAL VOLUME PELESTER 0.92 M³
REKAP VOLUME KEGIATAN VOLUME KEGIATAN
Propinsi : Nusa Tenggara Timur Kegiatan : TPT
Kabupaten : Flores Timur Ukuran : 45
Kecamatan : Lewolema No. RAB : 01
Desa/ Kelurahan : Sinar Hading
REALISASI SWADAYA
NO URAIAN SAT.
MASYARAKAT
A. BAHAN
1 Semen 40 Kg Zak -
2 Besi Beton 6 mm Btg -
3 Besi Beton 10 mm Btg -
4 Besi Beton 12 mm Btg -
5 Kawat Beton Kg -
6 Paku < 5 Cm Kg -
7 Paku > 5 Cm Kg -
8 Batu Kali (M3) M3 -
9 Batu Pecah 2/3 M3 -
10 Pasir Pasang M3 -
11 Sirtu M3 -
12 Kayu Kls III, 5/7-400 Lbr -
13 Papan Kls III, 3/25 - 400 Lbr -
14 Tripleks 6 mm Lbr -
15 Tanah Urug M3 -
16 Kayu Peranca Btg -
B. PERALATAN DLL
1 Molen Unit -
2 Bahan Bakar & Sparepart LS -
3 Papan Proyek Bh -
4 Prasasti Bh -
5 Ember Sedang Bh -
6 Ember Coor Bh -
7 Linggis Bh -
8 Air Kerja Tgky -
9 Pacul Bh -
10 Skop Bh -
11 Terpal 5 x 7 m Lbr -
12 Drum Bh -
13 Waterpas selang M -
14 Selang Air Roll -
15 Pikwel Bh -
E. UPAH
1 Tukang HOK -
2 Pekerja HOK -
ANALISA HARGA SATUAN
Propinsi : Nusa Tenggara Timur Kegiatan : TPT
Kabupaten : Flores Timur Ukuran : 45
Kecamatan : Lewolema No. RAB : 01
Desa/ Kelurahan : Sinar Hading
VOL.
JUMLAH
NO. URAIAN HARGA SAT. PEKER TOTAL HARGA
HARGA
JAAN
Papan
Besi Besi Besi Batu Batu Kayu
Semen Kawat Paku < Paku > Pasir Kls III, Triplek Tanah Kayu
No. Uraian Volume Beton 6 Beton Beton Kali Pecah Sirtu Kls III, Tukng Pekrja
40 Kg Beton 5 Cm 5 Cm Pasang 3/25 - s 6 mm Urug Peranca
mm 10 mm 12 mm (M3) 2/3 5/7-400
400
B. PASANGAN
1 1 M3 Pek. Pasangan Batu Kali, 1 Sp : 5 Psr 10.80
1.1000 M3 Batu Kali (15/20 cm) 11.88
3.1500 Zak Semen Bosowa (40 Kg) 34.02
0.7900 M3 Pasir Pasang 8.53
0.6000 HOK Tukang 6.48
1.5000 HOK Pekerja 16.20
2 1 M2 Pek. Pelesteran Mata Sapi (1 Pc : 4 PP) .92
0.1560 Zak Semen Bosowa (40 Kg) 0.14
0.0240 M3 Pasir Pasang 0.02
0.1700 OH Tukang 0.16
0.2000 OH Pekerja 0.18
Total 34.00 0.00 0.00 0.00 0.00 0.00 1.00 12.00 0.00 9.00 0.00 0.00 0.00 0.00 1.00 0.00 17.00 32.84
KEBUTUHAN ALAT, PERLENGKAPAN DAN LAINNYA
A. PERALATAN
1 Molen Unit - 11,150,000 -
2 Bahan Bakar & Sparepart LS - 1,500,000 -
3 Papan Proyek Bh - 100,000 -
4 Prasasti Bh - 700,000 -
5 Ember Sedang Bh - 25,000 -
6 Ember Coor Bh - 28,000 -
7 Linggis Bh - 95,000 -
8 Air Kerja Tgky 1.00 500,000 500,000.00
9 Pacul Bh - 73,000 -
10 Skop Bh - 80,000 -
11 Terpal 5 x 7 m Lbr - 140,000 -
12 Drum Bh - 223,000 -
13 Waterpas selang M - 6,000 -
14 Selang Air Roll - 279,000 -
15 Pikwel Bh - 73,000 -
Total Dibulatkan 500,000.00
Sinar Hading, Februari 2019
Volume SATUAN
JUMLAH TOTAL JUMLAH JUMLAH Dana
NO URAIAN Dari Dari Dana Sat. HARGA
Total (Rp.) SWADAYA (Rp.) Desa (Rp.)
Swadaya Desa (Rp.)
A. BAHAN
1 Semen 40 Kg 34.00 - 34.00 Zak 70,000 2,380,000 - 2,380,000
2 Besi Beton 6 mm 0.00 - - Btg 55,000 - - -
3 Besi Beton 10 mm 0.00 - - Btg 129,000 - - -
4 Besi Beton 12 mm 0.00 - - Btg 153,000 - - -
5 Kawat Beton 0.00 - - Kg 28,000 - - -
6 Paku < 5 Cm 0.00 - - Kg 29,000 - - -
7 Paku > 5 Cm 1.00 - 1.00 Kg 28,000 28,000 - 28,000
8 Batu Kali (M3) 12.00 - 12.00 M3 300,000 3,600,000 - 3,600,000
9 Batu Pecah 2/3 0.00 - - M3 450,000 - - -
10 Pasir Pasang 9.00 - 9.00 M3 252,000 2,268,000 - 2,268,000
11 Sirtu 0.00 - - M3 250,000 - - -
12 Kayu Kls III, 5/7-400 0.00 - - Lbr 55,000 - - -
13 Papan Kls III, 3/25 - 400 0.00 - - Lbr 37,000 - - -
14 Tripleks 6 mm 0.00 - - Lbr 106,000 - - -
15 Tanah Urug 1.00 - 1.00 M3 152,000 152,000 - 152,000
16 Kayu Peranca 0.00 - - Btg 10,000 - - -
C. UPAH
1 Tukng 17.00 - 17.00 OH 89,250 1,517,250.00 - 1,517,250.00
2 Pekrja 33.00 - 33.00 OH 52,500 1,732,492.13 - 1,732,492.13
Sub Total 3,249,700.00 - 3,249,700.00
Kegiatan : TPT
Ukuran : 45
No URAIAN Bobot %
Jumlah :
No RAB : 01
Dana Desa Swadaya
I BAHAN 8,428,000 200,000 69.21
( tidak perlu dirinci )
II PERALATAN 500,000 - 4.11
( tidak perlu dirinci )
III UPAH 3,249,700 - 26.69
( tidak perlu dirinci )
Jumlah 12,177,700 200,000 100.00
IV Insentif TPK 243,600.00
Kecamatan : Master
Desa : Master
Kegiatan : Master TPT
Pagu OPS : 4,283,763.73
Sub Total 1.
2. Transportasi (20%)
Kepala Desa 1 Ls 85,675.27
Sekretaris Desa 1 Ls 85,675.27
PK 5 Ls 85,675.27
KPMD 2 Ls 42,837.64
KTD 2 Ls 85,675.27
Sub Total 2.
3. ATK dan Dokumen (40%)
Buku Tulis Tebal 5 Buah 17,135.05
Balpoint 1 Dos 34,270.11
Map Snelhekter Plastik 3 Buah 34,270.11
Map Biasa 5 Buah 51,405.16
Biaya Desain & RAB 1 paket 891,022.86
Dokumen Lelang 1 Buah 171,350.55
Biaya Foto Copy 1 Lembar 171,350.55
Sub Total 3.
Jumlah Total (1 + 2 + 3 )
PK 3%
Jumlah Pembiayaan
(Rp)
1,713,505.49
428,376.37
342,701.10
342,701.10
599,726.92
1,713,505.49
856,752.75
85,675.27
85,675.27
428,376.37
85,675.27
171,350.55
856,752.75
1,713,505.49
85,675.27
34,270.11
102,810.33
257,025.82
891,022.86
171,350.55
171,350.55
1,713,505.49
4,283,763.73