The document provides a cost breakdown for removing 3mm thick coldplastic road markings using a scrapper machine in the Jabodetabek area of Indonesia. It lists the various labor, equipment, consumable, accommodation, and technical staffing costs and calculates a total cost per square meter of 108,366 Rupiah or 13,004 Rupiah per running meter.
The document provides a cost breakdown for removing 3mm thick coldplastic road markings using a scrapper machine in the Jabodetabek area of Indonesia. It lists the various labor, equipment, consumable, accommodation, and technical staffing costs and calculates a total cost per square meter of 108,366 Rupiah or 13,004 Rupiah per running meter.
The document provides a cost breakdown for removing 3mm thick coldplastic road markings using a scrapper machine in the Jabodetabek area of Indonesia. It lists the various labor, equipment, consumable, accommodation, and technical staffing costs and calculates a total cost per square meter of 108,366 Rupiah or 13,004 Rupiah per running meter.
PENGHAPUSAN MARKA JALAN COLDPLASTIC DENGAN SCRAPPER
Pekerjaan : Penghapusan marka jalan coldplastic
Spesifikasi : Dengan mesin hapus (Scrapper) Satuan : m2 Ketebalan : 3 mm Kapasitas Prod. : 50 m2/ hari Lokasi : Jabodetabek
HARGA SATUAN JUMLAH HARGA
NO URAIAN KOEF. SATUAN (RP) (RP) 1 UPAH Mandor 1,00 Hok 230.000 230.000 Pekerja 2,00 Hok 171.000 342.000 Operator 1,00 Hok 185.000 185.000 Sopir 1,00 Hok 175.000 175.000 JUMLAH 1. UPAH 932.000 2 ALAT Mesin Hapus Marka (Scrapper) 1,00 Unit 500.000 500.000 Peralatan Bantu 1,00 Ls 100.000 100.000 Pick Up 1,00 Unit 550.000 550.000 Hand Blower 1,00 Unit 95.000 95.000 Rubber Cone 15,00 Unit 500 7.500 Rambu kerja 8,00 Unit 4.000 32.000 Flasing light 2,00 Unit 1.500 3.000 Bendera 2,00 Unit 200 400 JUMLAH 3. ALAT 1.287.900 3 KONSUMABEL Mata Pisau 0,02 Unit 120.000 2.400 BBM (Alat) 6,25 Liter 8.000 50.000 BBM (Pick Up) 12,50 Liter 8.000 100.000 JUMLAH 2. KONSUMABEL 152.400 4 AKOMODASI PEKERJA Mess Pekerja 1,00 Hari 89.286 89.286 Mobilisasi Pekerja 6,00 Orang - 2 Trip 214.286 1.285.714 Mobilisasi Peralatan 2,00 Trip 357.143 714.286 JUMLAH 4. AKOMODASI PEKERJA 2.089.286 5 TENAGA TEKNIS Tenaga Teknis lapangan 1,00 Hok 250.000 250.000 JUMLAH 5. TENAGA TEKNIS 250.000 JUMLAH TOTAL (1+2+3+4+5) 4.711.586 OH & PROFIT 15% 706.738 JUMLAH TOTAL + OH & PROFIT 5.418.324 JUMLAH HARGA DALAM M2 108.366 JUMLAH HARGA DALAM (1 M2/8,333) 13.004