November 2, 2010
11/3/2010 1
Background/History
Gym collapsed Feb. 13, 2010
Initial effort was to return students to school, find the cause for the
collapse, and remove collapsed gym roof
To reoccupy the building the cause of collapse had to be identified
and the building evaluated that it could be reoccupied
OWPR, who assisted with the response to collapse, was contracted
to evaluate building
Initially it appeared that main building was not damaged by the
collapse and once gym was removed and some building repairs
made, students could return to the building
As building plans and specifications were reviewed it was
determined that some structural items did not match specifications
11/3/2010 2
Background/History
During the past several months numerous questions, concerns,
myths, cost estimates, and scenarios have been discussed and
presented
All rumors, questions, and concerns cannot be answered
without further evaluation and testing to determine the facts
From the code review, fire inspection, and discussions it
appears that the building will not be approved without
additional changes and upgrades
The following will review, summarize, add, and update options
for BHS
Option A - Repair Estimate
Option B - Full Renovation
Option C - New Construction
Note: All costs listed are estimates and not based on bids
11/3/2010 3
Building Official Items
a. “ Plans did not show building code analysis for the building. Architect
shall provide this information to the Building Official’s office.”
11/3/2010 5
Building Official Items
c. “ 1 hour rated walls, partitions required by the 1969 Southern
Building Code, Section 1106 shall be re-installed. These areas
shall meet the requirements for Fire resistive construction, Type
II., Table 603.1 partitions, Section 702.2 and Section 702.”
Response: Note that the 1969 SSBC was not the governing
design code. The plans for the construction of Blacksburg
High School were reviewed and approved by the State to be
in conformance with the codes and regulations in effect at
that time. Upon review of the Virginia Fire Safety Regulations
and the School Planning Manual, rated walls/partitions are
not required in most areas of the school. Rated walls
indicated on the design documents will be verified and
repaired if necessary. Also the amount of repair work or
renovation could create requirement to comply with current
code.
11/3/2010 7
Cost - $158,400 to date.
Building Official Items
e. “ Heating Ventilation/Air Conditioning (HVAC) - an air balancing
report will be required to be submitted for the entire school due to
numerous complaints received by this department. Primary purpose of
the air balancing report is to verify fresh air requirements for all
classrooms and other areas as well as the new rooms and areas
created.”
11/3/2010 8
Building Official Items
f. “Corridors- during our previous site visits it has been noted that
the required 1 hour firewalls, and other rated walls have been
damaged and/or breeched. They shall be re-established. These
areas shall meet the requirements for Fire resistive construction,
Type II., Table 603.1 partitions, Section 702.2 and Section 702.”
11/3/2010 9
Building Official Items
g. “Additional investigation is required - Reports from ATS,
Schnabel and Forcon - additional borings as stated in reports
shall be performed. Footers, as stated in reports shall be
investigated and verified and will need to be inspected and loads
verified per the reports.”
11/3/2010 10
Building Official Items
h. “Math area - this office has been informed that there was a
significant void under this area of the building and concrete was
placed to fill the void. Please verify whether there was a void, and
if so, how the void was corrected. We want to ensure that there is
not currently a void underneath the Math area or any repair
performed met code requirements.”
Cost - $3,850
11/3/2010 11
Building Official Items
i. “Child day care - during recent site visits it was noticed that the
addition of a child day care area has been created. This office
has no records of approving this change. Must verify that the
child day care area meets all requirements of the building code.”
Response: This area was part of the original design, and has
existed since the school opened. It was approved by the
State as part of the original design. Some changes over the
years may need to be verified.
11/3/2010 12
Building Official Items
j. “Verify Occupant Load - Architect shall verify occupant load in
accordance with the 1969 Southern Building Code for this
structure.”
11/3/2010 13
Building Official Items
k. “Property Maintenance Violations - please be aware that
property maintenance violations noted during inspection will be
required to be corrected.”
11/3/2010 14
Building Official Items
l. “This is not a complete list. We are still gathering information, all
testing is not complete and additional corrections may be warranted
after all tests and through inspection of the facility has been
completed. We will be reviewing the original plans to determine if
any other corrections will be required.”
11/3/2010 15
Plan A
Description Construction Est. Design/CM Contingency Total Budget
11/3/2010 16
Plan A
Description Construction Est. Design/CM Contingency Total Budget
Replace Heating, Ventilation & Air Conditioning $ 2,641,800 $ 220,332 $ 437,868 $ 3,300,000
ATS Math Classroom M-6 Resistivity Imaging /GPR $ 3,500 $ - $ 350 $ 3,850
11/3/2010 17
Additional Items Plan A
Not Included in School Board Approved List
11/3/2010 18
Summary Plan A
Total Plan A $22,749,360
Building Official $3,539,540
Less items in Plan A:
11/3/2010 19
Plan B
Full Renovation of BHS to recapitalize building
Resolve some code issues since work will include current code
Address safety concerns
Change design where feasible to address educational program
needs
11/3/2010 20
Plan C
Build new HS on land at Price’s Fork
Estimated Cost 1200 students 240,000 sq. ft. =
$57,456,000
Estimated Cost 1600 students 270,000 sq. ft =
$64,638,000
11/3/2010 21
Update Blacksburg High School
November 2, 2010
11/3/2010 22