Anda di halaman 1dari 3

DAFTAR KUANTITAS DAN HARGA

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR MAJELIS DESA ADAT (MDA) KAB. BADUNG
LOKASI : JALAN GUNUNG SARI, KEROBOKAN, KUTA UTARA-BADUNG

JUMLAH JUMLAH HARGA + PERIODE LALU PERIODE INI


NO URAIAN PEKERJAAN SATUAN HARGA SATUAN VOLUME
HARGA (Rp) PPN (Rp) PROGRES JUMLAH HARGA PROGRES HARGA TOTAL
1 2 3 4 5 6 7 8 9 10 11

I PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bouplang m1 113.423,63 25,66 2.910.363,73 3.201.400,10 0% - 100% 3.201.400,10
2.910.363,73 3.201.400,10 - 3.201.400,10

II PEKERJAAN TANAH DAN STRUKTUR


1 Pek galian tanah untuk pondasi setempat type 1 (teras) m3 116.943,75 4,38 511.628,91 562.791,80 0% - 100% 562.791,80
1.a Pek. Galian tanah pinggir pondasi m3 116.943,75 89,31 10.444.334,40 11.488.767,84 0% - 100% 11.488.767,84
2 Pek.urugan pasir bawah pondasi m3 292.818,75 0,16 45.752,93 50.328,22 0% - 100% 50.328,22
3 Pas, beton rabat m3 832.781,78 0,16 130.122,15 143.134,37 0% - 100% 143.134,37
4 Pasangan beton plat kaki K 250 m3 1.050.021,56 0,94 984.395,21 1.082.834,73 0% - 100% 1.082.834,73
Pembesian Fe 145 kg 14.283,31 162,44 2.320.180,47 2.552.198,52 0% - 100% 2.552.198,52
Bekisting pasangan batako m2 104.442,66 3,00 313.327,98 344.660,78 0% - 100% 344.660,78
5 Pek galian tanah untuk pondasi setempat type 2 m3 116.943,75 64,80 7.577.955,00 8.335.750,50 0% - 100% 8.335.750,50
6 Pek.urugan pasir bawah pondasi m3 292.818,75 2,03 592.957,97 652.253,77 0% - 100% 652.253,77
7 Pas, beton rabat m3 832.781,78 2,03 1.686.383,09 1.855.021,40 0% - 100% 1.855.021,40
7.a Pek. Bor Pile Pondasi D30 cm m' 180.986,67 36,00 6.515.520,00 7.167.072,00 0% - 100% 7.167.072,00
Pek. Pembesian bor pile kg 14.283,31 406,25 5.802.623,38 6.382.885,72 0% - 100% 6.382.885,72
Pek. Beton Bor Pile m3 1.050.021,56 5,08 5.337.469,59 5.871.216,54 0% - 100% 5.871.216,54
8 Pekerjan beton K 250 untuk pondasi setempat m3 1.050.021,56 16,20 17.010.349,25 18.711.384,17 0% - 100% 18.711.384,17
Pembesian 190 kg 14.283,31 1.527,98 21.824.665,33 24.007.131,86 0% - 100% 24.007.131,86
Bekisting pasangan batako m2 104.442,66 43,20 4.511.922,91 4.963.115,20 0% - 100% 4.963.115,20
9 Pas. Kolom struktur 35x35 K 250 ( K3) m3 1.050.021,56 9,04 9.492.719,90 10.441.991,89 0% - 100% 10.441.991,89
Pembesian Fe 209 kg 14.283,31 2.184,34 31.199.542,77 34.319.497,05 0% - 100% 34.319.497,05
Pas. Bekisting 2 kali pakai m2 250.521,35 103,32 25.883.865,88 28.472.252,47 0% - 100% 28.472.252,47
10 Pas. Kolom Teras depan 25/25 K 250 m3 1.050.021,56 0,51 538.136,05 591.949,65 0% - 100% 591.949,65
Pembesian 300 kg 14.283,31 163,46 2.334.692,31 2.568.161,54 0% - 100% 2.568.161,54
Bekisting 2kali pakai m2 250.521,35 8,20 2.054.275,07 2.259.702,58 0% - 100% 2.259.702,58
11 Pek galian tanah untuk pondasi menerus m3 95.746,88 18,40 1.761.742,50 1.937.916,75 0% - 100% 1.937.916,75
12 Urugan pasir bawah pondasi m3 292.818,75 0,69 202.044,94 222.249,43 0% - 100% 222.249,43
13 Pas. Batu kosong m3 512.067,15 2,76 1.413.305,33 1.554.635,87 0% - 100% 1.554.635,87
14 Pas batu kali 1 : 6 untuk pondasi menerus m3 931.143,26 29,44 27.412.857,43 30.154.143,17 0% - 100% 30.154.143,17
15 Pek galian tanah pondasi menerus teras depan m3 95.746,88 3,16 302.560,13 332.816,14 0% - 100% 332.816,14
16 Pas batu kali 1 : 6 m3 931.143,26 5,69 5.296.342,83 5.825.977,12 0% - 100% 5.825.977,12
17 Urugan tanah peninggian lantai m3 156.883,13 93,26 14.630.606,47 16.093.667,12 0% - 100% 16.093.667,12
18 Urugan pasir dibawah rabat beton m3 292.818,75 11,66 3.413.461,37 3.754.807,51 0% - 100% 3.754.807,51
19 Pas. Rabat beton camp 1 PC : 3 Psr : 5 Krk di lantai I m3 832.781,78 13,48 11.225.065,55 12.347.572,10 0% - 100% 12.347.572,10
Pembesian 76 kg 14.283,31 734,45 10.490.389,17 11.539.428,09 0% - 100% 11.539.428,09
20 Pas.beton sloof 15/30 K 250 m3 1.050.021,56 2,77 2.905.934,66 3.196.528,13 0% - 100% 3.196.528,13
Pembesian 223 kg 14.283,31 684,50 9.776.923,98 10.754.616,38 0% - 100% 10.754.616,38
Bekisting sloof batako m2 188.445,60 41,22 7.767.727,63 8.544.500,40 0% - 100% 8.544.500,40
21 Pas.beton sloof 15/25 K 175 m3 971.151,93 0,18 172.622,25 189.884,48 0% - 100% 189.884,48
Pembesian 182 kg 14.283,31 531,09 7.585.693,21 8.344.262,53 0% - 100% 8.344.262,53
Bekisting sloof 2 kali pakai m2 188.445,60 5,43 1.022.317,38 1.124.549,12 0% - 100% 1.124.549,12
22 Pas.kolom praktis12/12 K 175 di tembok lantai I m3 971.151,93 2,19 2.125.657,33 2.338.223,07 0% - 100% 2.338.223,07
Pembesian 318 kg 14.283,31 531,09 7.585.693,21 8.344.262,53 0% - 100% 8.344.262,53
23 Pas. Balok latei 15/20 untuk Kusen Pintu Utama m3 971.151,93 0,08 77.206,58 84.927,24 0% - 100% 84.927,24
Pembesian 182 kg 14.283,31 22,87 326.602,11 359.262,32 0% - 100% 359.262,32
Page 1 of 3
JUMLAH JUMLAH HARGA + PERIODE LALU PERIODE INI
NO URAIAN PEKERJAAN SATUAN HARGA SATUAN VOLUME
HARGA (Rp) PPN (Rp) PROGRES JUMLAH HARGA PROGRES HARGA TOTAL
1 2 3 4 5 6 7 8 9 10 11

Bekisting m2 425.147,10 1,46 619.651,90 681.617,09 0% - 100% 681.617,09


24 Pas, beton balok lantai 25/50 K 250 m3 1.050.021,56 13,24 13.901.445,42 15.291.589,96 0% - 100% 15.291.589,96
Pembesian 183 kg 14.283,31 3.274,02 46.763.788,71 51.440.167,59 0% - 100% 51.440.167,59
Bekisting m2 425.147,10 140,75 59.840.984,85 65.825.083,34 0% - 100% 65.825.083,34
25 Pas, beton balok lantai ( B ) 20/40 K 250 m3 1.050.021,56 2,03 2.135.071,84 2.348.579,02 0% - 100% 2.348.579,02
Pembesian 174 kg 14.283,31 533,31 7.617.425,01 8.379.167,51 0% - 100% 8.379.167,51
Bekisting m2 425.147,10 27,60 11.732.189,31 12.905.408,24 0% - 100% 12.905.408,24
26 Pas. Beton lantai II K 250 m3 1.050.021,56 18,69 19.627.107,97 21.589.818,77 0% - 100% 21.589.818,77
Pembesian Fe 104 kg 14.283,31 1.736,56 24.803.791,91 27.284.171,10 0% - 100% 27.284.171,10
Bekisting m2 467.147,10 162,51 75.917.336,52 83.509.070,17 0% - 100% 83.509.070,17
27 Beton lisplang K 250 m3 1.050.021,56 3,71 3.895.432,98 4.284.976,28 0% - 100% 4.284.976,28
Pembesian 104 kg 14.283,31 506,54 7.235.066,58 7.958.573,24 0% - 100% 7.958.573,24
Bekisting m2 425.147,10 75,32 32.022.674,78 35.224.942,26 0% - 100% 35.224.942,26
28 Beton tangga ke lantai II K 250 m3 1.050.021,56 1,66 1.739.591,72 1.913.550,89 0% - 100% 1.913.550,89
Pembesian 154 kg 14.283,31 382,64 5.465.319,08 6.011.850,98 0% - 100% 6.011.850,98
Bekisting m2 367.866,98 17,02 6.259.624,45 6.885.586,89 0% - 100% 6.885.586,89
36 Beton plat bordes 300 x130 m3 1.050.021,56 0,37 384.937,90 423.431,69 0% - 100% 423.431,69
Pembesian 110 kg 14.283,31 80,81 1.154.205,51 1.269.626,06 0% - 100% 1.269.626,06
Bekisting m2 367.866,98 3,62 1.331.310,58 1.464.441,64 0% - 100% 1.464.441,64
37 Balok bordes 20/30 m3 1.050.021,56 0,16 166.953,43 183.648,77 0% - 100% 183.648,77
Pembesian 175 kg 14.283,31 28,75 410.645,09 451.709,60 0% - 100% 451.709,60
Bekisting m2 425.147,10 2,12 901.311,85 991.443,04 0% - 100% 991.443,04
38 Pas. Kolom struktur dilantai II 35x35 K 250 ( K3) m3 1.050.021,56 6,00 6.302.754,40 6.933.029,84 0% - 100% 6.933.029,84
Pembesian Fe 209 kg 14.283,31 1.483,24 21.185.630,15 23.304.193,16 0% - 100% 23.304.193,16
Pas. Bekisting 2 kali pakai m2 250.521,35 68,60 17.185.764,61 18.904.341,07 0% - 100% 18.904.341,07
39 Pas. Kolom struktur plat tower 20x20 K 250 ( K3) m3 1.050.021,56 0,58 604.812,42 665.293,66 0% - 100% 665.293,66
Pembesian Fe 209 kg 14.283,31 170,35 2.433.190,00 2.676.509,00 0% - 100% 2.676.509,00
Pas. Bekisting m2 250.521,35 11,52 2.886.005,95 3.174.606,55 0% - 100% 3.174.606,55
40 Balok lantai tower 15/20 m3 1.050.021,56 0,08 87.571,80 96.328,98 0% - 100% 96.328,98
Pembesian 125 kg 14.283,31 38,74 553.335,33 608.668,87 0% - 100% 608.668,87
Pas. bekisting m2 425.147,10 3,82 1.625.124,79 1.787.637,27 0% - 100% 1.787.637,27
41 Pelat dak tower tebal 12 cm m3 1.050.021,56 0,44 462.933,50 509.226,86 0% - 100% 509.226,86
Pembesian 105 kg 14.283,31 86,59 1.236.780,17 1.360.458,19 0% - 100% 1.360.458,19
Bekisting m2 467.147,10 4,60 2.150.184,67 2.365.203,14 0% - 100% 2.365.203,14
42 Waterprofing pelat lantai tower m2 52.832,59 3,67 194.106,93 213.517,62 0% - 100% 213.517,62
43 Plesteran plat lantai tower air m2 75.374,99 3,67 276.927,69 304.620,46 0% - 100% 304.620,46
44 Kolom praktis 12/12 di tembok lantai II m3 971.151,93 1,27 1.235.118,79 1.358.630,67 0% - 100% 1.358.630,67
Pembesian kolom 318 kg 14.283,31 361,45 5.162.695,78 5.678.965,36 0% - 100% 5.678.965,36
45 Beton ring praktis 12/12 m3 971.151,93 0,22 213.964,19 235.360,61 0% - 100% 235.360,61
Pembesian 191 kg 14.283,31 53,36 762.111,58 838.322,74 0% - 100% 838.322,74
46 Pas, beton balok ring 20/40 pemikul konsol K 250 m3 1.050.021,56 3,68 3.864.079,33 4.250.487,27 0% - 100% 4.250.487,27
Pembesian 174 kg 14.283,31 755,69 10.793.752,64 11.873.127,91 0% - 100% 11.873.127,91
Bekisting 2 kali pakai m2 267.169,10 46,00 12.289.778,60 13.518.756,46 0% - 100% 13.518.756,46
47 Pas, beton balok konsol 20/40 K 250 m3 1.050.021,56 2,55 2.676.294,95 2.943.924,44 0% - 100% 2.943.924,44
Pembesian 262 kg 14.283,31 523,63 7.479.214,01 8.227.135,41 0% - 100% 8.227.135,41
Bekisting m2 425.147,10 31,86 13.545.186,61 14.899.705,27 0% - 100% 14.899.705,27
48 Kolom dekorasi 12/12 di luar tembok lantai II m3 1.050.021,56 1,08 1.130.999,22 1.244.099,14 0% - 100% 1.244.099,14
Pembesian kolom 318 kg 14.283,31 263,75 3.767.273,77 4.144.001,15 0% - 100% 4.144.001,15
Bekisting 2 kali pakai m2 250.521,35 35,90 8.994.718,55 9.894.190,41 0% - 100% 9.894.190,41
49 Lagur pada Kolom dekorasi 7/12 di luar tembok lantai II m3 1.050.021,56 0,49 514.392,96 565.832,26 0% - 100% 565.832,26
Pembesian lagur 484 kg 14.283,31 187,22 2.674.143,68 2.941.558,05 0% - 100% 2.941.558,05
Bekisting 2 kali pakai m2 267.169,10 18,08 4.830.203,59 5.313.223,95 0% - 100% 5.313.223,95
50 Pas, beton balok lisplang 12/20 K 250 m3 1.050.021,56 1,49 1.562.180,07 1.718.398,08 0% - 100% 1.718.398,08
Page 2 of 3
JUMLAH JUMLAH HARGA + PERIODE LALU PERIODE INI
NO URAIAN PEKERJAAN SATUAN HARGA SATUAN VOLUME
HARGA (Rp) PPN (Rp) PROGRES JUMLAH HARGA PROGRES HARGA TOTAL
1 2 3 4 5 6 7 8 9 10 11

Pembesian 191 kg 14.283,31 262,62 3.751.016,51 4.126.118,16 0% - 100% 4.126.118,16


Bekisting m2 425.147,10 32,23 13.704.531,74 15.074.984,91 0% - 100% 15.074.984,91
51 Pas.plat level /talang keliling m3 1.050.021,56 12,94 13.586.657,35 14.945.323,09 0% - 100% 14.945.323,09
Pembesian 105 kg 14.283,31 1.485,79 21.222.035,44 23.344.238,99 0% - 100% 23.344.238,99
Bekisting m2 467.147,10 115,14 53.786.756,52 59.165.432,17 0% - 100% 59.165.432,17
52 Pas, beton lisplang K 250 m3 1.050.021,56 5,36 5.630.357,35 6.193.393,08 0% - 100% 6.193.393,08
Pembesian 95 kg 14.283,31 497,22 7.101.877,60 7.812.065,35 0% - 100% 7.812.065,35
Bekisting m2 425.147,10 122,74 52.182.640,08 57.400.904,09 0% - 100% 57.400.904,09

906.180.545,36 996.798.599,90 - 996.798.599,90

TOTAL 909.090.909,09 1.000.000.000,00 0% - 100% 1.000.000.000,00

TAGIHAN TOTAL S/D PERIODE INI 100% 1.000.000.000,00

Mengetahui, Diperiksa Oleh, Dibuat Oleh,


Pengelola Teknis Kegiatan (PTK) Konsultan Pengawas Kontraktor Pelaksana
Mengetahui / Menyetujui,
Dinas PUPRKIM Provinsi Bali CV. Rusma Indah PT. Dawan Sakti
Majelis Desa Adat (MDA) Provinsi Bali

I Putu Tisnayasa, ST, M.Si


NIP. 19830308 201101 1 002

I Made Mahardika, ST
NIP. 19800806 201101 1 004 I Gede Rustiawan, ST A.A. Kompiang Sudiasa
DR.Drs. I Made Wena, Msi Ir. I Gede Arya Sena, M.Kes
Direktur Direktur
Patajuh Bendesa Agung Patengen Agung
I Nyoman Purnata, ST, M.Si
NIP. 19790710 201407 1 002

Page 3 of 3