Perencanaan Saluran: Sal Primer
Perencanaan Saluran: Sal Primer
I 0.0002225
Im 0.002
BANGUNAN TERJUN
Bangunan Terjun
L 1000 m
Delta H 1.777513 m
n 2.3700173
34 buah
H1 1.5177267
B 0.9130235
B1 1.1412794
q 3.1973226
hc 0.1736811
a 0.0868406
C1 2.6004103
L2 1.3337228
t 1.25
Sal Sekunder Sal Tersier
As 450 ha As 225 ha
Q 1273.8462 lt/det Q 477.69231 lt/det
1.2738462 m3/det 0.4776923 m3/det
b/h 2 b/h 1.5
b 1.8 m= 1 b 0.9 m= 1.5
h 0.9 k= 40 h 0.6 k= 35
A 2.43 A 1.08
v 0.5242165 v 0,5 - 0,55 v 0.4423077 v 0,6 - 0,65
p 5.0449961 p 3.0633308
R 0.4816654 R 0.3525574
I 0.0004549 I 0.0006412
Im 0.002 Im 0.002