Program :
Kegiatan : Penyelenggaraan Jalan Provinsi
Paket : Rekonstruksi Jalan Simp. 3 Sambera - Muara Badak 1
Lokasi : Kalimantan Timur / Kutai Kartanegara
Sumber Dana :
1 2 3 4 5
BOBOT M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17
KUANTITAS 3-Aug 10-Aug 18-Aug 26-Aug 3-Sep 11-Sep 18-Sep 26-Sep 3-Oct 11-Oct 18-Oct 26-Oct 3-Nov 11-Nov 18-Nov 26-Nov 3-Dec
No. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA KONTRAK KET.
KONTRAK s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
(%) 9-Aug 17-Aug 25-Aug 2-Sep 10-Sep 17-Sep 25-Sep 2-Oct 10-Oct 17-Oct 25-Oct 2-Nov 10-Nov 17-Nov 25-Nov 2-Dec 10-Dec
DIVISI 1. UMUM
1.2 Mobilisasi
100%
1.2 Mobilisasi Ls 1.00 Rp 310,500,000.00 Rp 310,500,000.00 3.519 1.284 1.284 0.952
Rp 525,800,000.00 5.960
Rp 133,804,042.45 1.517
Rp 745,868,108.37 8.454
Rp 5,648,190,422.54 64.020
DIVISI 7. STRUKTUR
7.1 (7)a Beton mutu sedang fc’20 Mpa M3 740.00 Rp 1,756,871.70 Rp 1,300,085,058.00 14.736 3.684 3.684 3.684 3.684
Rp 1,300,085,058.00 14.736
Rp 8,822,506,747.63 100.00
RENCANA 1.756 1.768 0.097 0.429 0.429 2.470 2.470 2.470 6.166 6.154 6.154 18.555 14.871 14.871 14.871 4.360 2.112
RENCANA KOMULATIF 0 1.756 3.524 3.621 4.050 4.478 6.948 9.418 11.888 18.054 24.207 30.361 48.916 63.787 78.657 93.528 97.888 100.000