APPENDIX D INSPECTION SCHEDULE

FOR RISK ASSESSMENT LIMA FIELD 2010


System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
1 LCOM Compressor Suction Drum 05-L-00 8" Gas Lift Launcher Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
2 LCOM Compressor Suction Drum 05-L-50-0 Gas Lift Launcher Detail Assestment Insignificant 2010 2010 Close Visual Inspection
3 LCOM 05-ME-7A Air Compressor Skid Detail Assestment Insignificant 2010 2010 Close Visual Inspection
4 LCOM 05-ME-7B Air Compressor Skid Detail Assestment Insignificant 2010 2010 Close Visual Inspection
5 LCOM Compressor Suction Drum 05-ME-10 Smart Pig Receiver / Launcher Detail Assestment Insignificant 2010 2010 Close Visual Inspection
6 LCOM Slug Catcher & Receiver 05-ME-20 18" LLA Receiver Detail Assestment Insignificant 2010 2010 Close Visual Inspection
7 LCOM 05-ME-30 Smart Pig Receiver / Launcher Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
8 LCOM 05-ME-40 18" Auto Sphere Receiver Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
9 LPRO LPRO-LP-L-001-X Pig Launcher Trap Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
10 LPRO LPRO-LP-L-002-X Pig Launcher Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
11 LPRO LPL-0 18" Pig Launcher Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
12 LPRO Receivers & Launcher 05-ME-R-000 14" Crude Receiver Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
13 LCOM Compressor Suction Drum 05-V-1 Compressor Suction Drum Detail Assestment Insignificant 2010 2010 Close Visual Inspection
14 LCOM Residue Gas Separator 05-V-3 Residue Gas Separator Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Fuel Gas System Compressor
15 LCOM 05-V-4 Fuel Gas Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
module
16 LCOM 05-V-5 Fuel Gas Scrubber Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
17 LCOM Fuel Gas System Copressor Module 05-V-8A Fuel Gas Filter/Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
18 LCOM Fuel Gas System Copressor Module 05-V-8B Fuel Gas Filter/Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
19 LCOM Relief an Disposal System 05-V-08 LP KO Drum Detail Assestment Insignificant 2010 2010 Close Visual Inspection
20 LCOM 05-V-11A Starting Air Tank Detail Assestment Insignificant 2010 2010 Close Visual Inspection
21 LCOM 05-V-11B Starting Air Tank Detail Assestment Insignificant 2010 2010 Close Visual Inspection
22 LCOM Slug Catcher & receiver 05-V-20 Slug Catcher Detail Assestment Insignificant 2010 2010 Close Visual Inspection
23 LCOM Slug Catcher 05-V-30 Slug Catcher Detail Assestment Insignificant 2010 2010 Close Visual Inspection
24 LCOM 05-V-40 Slug catcher Detail Assestment Insignificant 2010 2010 Close Visual Inspection
25 LCOM Water KO Drum 05-V-101 Water KO Drum Detail Assestment Insignificant 2010 2010 Close Visual Inspection
26
6 LA Test Separator AV 1
AV-1 Test Separator Preventive
e e t e Maintenance
a te a ce Insignificant 2015
0 5 2012
0 Close Visual Inspection
27 LA AV-2 Gas Lift Separator Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
28 LSERV P/F FST-96728 Foam Storage Tank Detail Assestment Insignificant 2010 2010 Close Visual Inspection
29 LSERV P/F FST-96727 Foam Storage Tank Detail Assestment Insignificant 2010 2010 Close Visual Inspection
30 LPRO Receivers & Launcher L-649 24" Crude Launcher (Parigi Launcher) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
31 LPRO LPRO-LP-R-001-X LD-Oil Pig Receiver Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
32 LPRO LPRO-LP-R-002-X LB-Oil Pig Receiver Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
33 LCOM Pig Launcher/Receiver LCOMP-R-003 Smart Pig Receiver Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
34 LCOM Pig Launcher/Receiver LCOMP-R-004 Smart Pig Receiver / Launcher Detail Assestment Insignificant 2010 2010 Close Visual Inspection
35 LPRO Pig Launcher LPE-100 Pig Launcher (Ex Pig Receiver) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
36 LPRO Production separator LPV-2 Production Separator Detail Assestment Insignificant 2010 2010 Close Visual Inspection
37 LPRO N/A LPV-3 Production separator Detail Assestment Insignificant 2010 2010 Close Visual Inspection
38 LPRO KO Drum & Atmospheric Separator LPV-5 LP Flare KO Drum Detail Assestment Insignificant 2010 2010 Close Visual Inspection
39 LPRO Separator LPV-6 Atmospheric Separator Detail Assestment Insignificant 2010 2010 Close Visual Inspection
40 LPRO Ex Pig Launcher LPV-6A Ex Pig Launcher Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
41 LPRO Flare, Drain System & Fire Utility LPV-7 Fuel Gas Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
42 LPRO Flare, Drain System & Fire Utility LPV-8 LP Flare KO Drum Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
43 LSER Fuel Gas Inline Scrubber LSV-8 Fuel Gas Inline Scrubber Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
44 LSER LSER DRYER A Air Dryer Tank A Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
45 LSER LSER DRYER B Air Dryer Package Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
46 LPRO Precipitator LV-3 Precipitator (Future) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
47 LPRO Gas Receiver M-630 20" Gas receiver Detail Assestment Insignificant 2010 2010 Close Visual Inspection
48 LPRO Crude Receiver M-640 12" Crude Receiver Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
49 LPRO Crude Receiver P-103-E-14" 14" crude Receiver Detail Assestment Insignificant 2010 2010 Close Visual Inspection
50 LPRO Vapor Recovery Unit PV-4010 VRU Suction Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
51 LPRO Vapor Recovery Unit PV-4020 VRU Interstage Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
52 LPRO Vapor Recovery Unit PV-4040 VRU Discharge Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
53 LCOM 1st Stage Compressor V-102-A Recycle Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
54 LCOM 1st Stage Compressor V-102-B Recycle Scrubber Detail Assestment Insignificant 2010 2010 Close Visual Inspection
55 LPRO Parigi Test & Production Separator V-610 Parigi Test Separator Detail Assestment Insignificant 2010 2010 Close Visual Inspection

56 LPRO Parigi Test & Production Separator V-620 Parigi Production Separator Detail Assestment Insignificant 2010 2010 Close Visual Inspection
57 LCOM 1st Disch. Cooler/2nd Suct. Scrub; V-1100A 2nd Stage Suction Scrubber Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
58 LCOM 1st Disch. Cooler/2nd Suct. Scrub; V-1100B 2nd Stage Suction Scrubber Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
Seawater/Gas Exchanger, Gas/Gas
59 LCOM LCOM-05-11-F1-8" PIPING FROM PG-135-D-8" (E-1500) TO 05-V-3 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

60 LCOM Compressor Suction Drum LCOM-05-12-F1-12-FG PIPING FROM 05-ME-10 TO NC-VALVE Detail Assestment Insignificant 2010 2010 Close Visual Inspection
61 LCOM Relief and Disposal System 05-12-F1-6"-RG Compression Module to 05-12-F1-12"-FG Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
LCOM-LSER-05-21-A1-
62 LCOM/ LSER Module Discharge Valving 18" HP Flare Below LSER Cellar Deck Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
18"
Fuel Gas System Compressor PIPING FROM PG-136-D-8" TO FUEL GAS
63 LCOM LCOM-05-43-D-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module SCRUBBER (05-V-4)
PIPING FROM BALL VALVE 4" A2RF TO SUMP
64 LCOM Relief and Disposal System LCOM-05-58-A1-4" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
TANK 05-V-10
65 LCOM Relief and Disposal System LCOM-05-65-A1-2" PIPING FROM 05-P-5 TO 05-74-A1-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM VALVE 6" D2R (NC) TO 05-01-A1-
66 LCOM Slug Catcher & receiver LCOM-05-307-D1-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
18"
Seawater/Gas Exchanger, Gas/Gas PIPING FROM BALL VALVE 8" D2R2 / E-1400 TO
67 LCOM LCOM-PG-134-D-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator E-1500

Seawater/Gas Exchanger, Gas/Gas


68 LCOM LCOM-PG-135-D-8" PIPING FROM E-1500 TO 05-11-F1-8" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas PIPING FR E-1500/TCV-1501 TO PL-305-D-4" /


69 LCOM LCOM-PL-305-D-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator 05-38-F1-4"-10
70 LPRO "L" Process Platform LPRO-P-100-8" PIPING FROM P 100F-8" TO P 102E-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
71 LCOM 1st Stage Compressor LCOM-05-13-A1-12" PIPING FROM SDV 0204B TO 05-C-1B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
72 LCOM 1st Stage Compressor LCOM-05-14-C1-12"-IS PIPING FROM 05-C-1B TO 05-14-C1-8''-IS Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection

73 LCOM 1st Stage Compressor LCOM-05-14-C1-8" PIPING FROM 05-14-C1-12'' TO PG-122-B-8'' Detail Assestment Insignificant 2010 2010 Close Visual Inspection

74 LCOM 1st Stage Compressor LCOM-05-14-C1-8"-IS PIPING FROM 05-C-1B TO PG-123-B-8'' Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
75 LCOM 1st Stage Compressor LCOM-05-15-C1-8" PIPING FROM PG-123-B-8" TO PG-123-B-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
76 LCOM 1st Stage Compressor LCOM-05-15-C1-8" PIPING FROM 05-14-C1-8"-IS TO E-1000B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
LCOM-LSER-05-1-A1- PIPING FROM COMPRESSION PLAT FORM 'L'
77 LCOM/ LSER Compressor Suction Drum Detail Assestment Insignificant 2010 2010 Close Visual Inspection
18" TO 05-V-1
PIPING FROM 05-300D-16" TO 05-V-20 (10"
78 LCOM Slug Catcher & receiver LCOM-05-301-D1-10" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
INLET TO 05-V-20)
79 LCOM Slug Catcher & receiver LCOM-05-301-D1-4" PIPING FROM 05-ME-20 TO 05-301-DI-10" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
80 LCOM Slug Catcher & receiver LCOM-05-306-D1-8" PIPING FROM 05-V-20 TO VALVE 8" 2RF (NC) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
81 LCOM Slug Catcher & receiver LCOM-05-306-D1-8" 8" CONTIGENCY LINE L-PRO TO LCOM Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
Seawater/Gas Exchanger, Gas/Gas PIPING FROM PL-305-D-6" TO BALL VALVE 4" D2R
82 LCOM LCOM-05-38-F1-4" Detail Assestment Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator (PG-124-B-8")
83 LCOM 1st Stage Compressor LCOM-PG-103-B-8" PIPING FROM 05-C-1A TO PG-104-B-8" Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
84 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-104-B-8" PIPING FROM PG-103-B-8" TO E-1000A Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
85 LCOM Compressor Suction Drum LCOM-05-73-A-6" PIPING FROM 05-V-1 TO 05-73-A1-3" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
LCOM-LSER-05-74-A1- 2” Oil Under LSER Cellar Deck from 05-P-7 to
86 LCOM/ LSER Relief and Disposal System Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
2" Liquid Storage
PIPING FROM 05-V-1 TO 05-74-A1-6"/05-73-A1-
87 LCOM Compressor Suction Drum LCOM-05-74-A1-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
3"
88 LCOM 1st Stage Compressor LCOM-05-8-A1-12" PIPING FROM SDV 0204A TO 05-C-1A Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PIPING FROM 05-L-50-1 (LAUNCHER) TO LB
89 LCOM Compressor Suction Drum LCOM-PG-203-D-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PLTF (BREAK OUT SPOOL)
PIPING FROM PG-100-A-18" TO BALL VALVES
90 LCOM Compressor Suction Drum LCOM-PG-100-A-12" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
12" (05-8-A1-12')
91 LCOM Pig Launcher/Receiver LCOM-PG-120-XD-3/4" PIPING FROM LCOM-R-004 TO PSV-0403 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-C-1B (DISCHARGE OF COMP.
92 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-123-B-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
B) TO E-1000B
PIPING FROM S-102-L-4" TO SP LOCATE 2ND
93 LSER "L" Service Platform LSER-S-102-B-2"-L Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
LEVEL
94 LSER "L" Service Platform LSER-S-102-A-2"-L PIPING FROM F HOSE BOX TO S-101-L-11/2" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
PIPING FROM S-101-L-2"-A TO FHR CELLAR DECK
95 LSER "L" Service Platform LSER-S-101-L-A3-11/2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
EAST
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
PIPING FROM S-101-L-2"-A TO FHR 1ST FLOOR
96 LSER "L" Service Platform LSER-S-101-L-A1-11/2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
NORTH
LSER-S-101-L-A2- PIPING FROM S-101-L-2"-A TO FHR 1ST FLOOR
97 LSER "L" Service Platform Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
11/2" SOUTH
LSER-S-101-L-A3- PIPING FROM S-101-L-2"-A TO FHR CELLAR
98 LSER "L" Service Platform Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
11/2" DECK EAST
99 LCOM Compressor Suction Drum LCOM-05-902-A-2" PIPING FROM PSV-05-ME-10" TO 05-21A1-18" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
100 LCOM Relief and Disposal System LCOM-05-76-A1-1" LPF PIPING FROM 05-S-10 TO 05-V-12 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Seawater/Gas Exchanger, Gas/Gas
101 LCOM LCOM-05-102-D-2" PIPING FROM PCV-0310 TO 05-102-D-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


102 LCOM LCOM-05-102-D-6" PIPING FROM 05-102-D-2" TO PL-310-D-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
Fuel Gas System Compressor
103 LCOM LCOM-05-104-A1-1" FG( PIPING FROM 05-61A1-1" TO LV-533/PCV-528 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
104 LCOM COM-05-104-A1-1" FG(I PIPING FROM LV-533 TO 05-P-5 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
105 LCOM Relief and Disposal System LCOM-05-106-A1-1" PIPING FROM 05-P-5 TO 05-106-A-1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
106 LCOM Relief and Disposal System LCOM-05-106-A1-3" PIPING FROM 05-106AI-1" TO 05-55-A-1-10" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Seawater/Gas Exchanger, Gas/Gas
107 LCOM LCOM-05-110-D-6" PIPING FROM 05-102-D-6" TO TCV-1501 / E-1500 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
2nd Stage Compressor & After PIPING FROM T JOINT / E-1200B TO T JOINT /
108 LCOM LCOM-05-113-C1-3"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler 05-113-C1-2"
PIPING FROM 05-20-A1-4" TO BALL VALVE / 05-
109 LCOM Relief and Disposal System LCOM-05-114-A1-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
61A1-1" (KNA TO MMF)
PIPING FROM 05-2-A1-4" TO 05-10-A1-2"/ 05-118-
110 LSER "L"
L Service Platform LSER S 114 A1 2"-FG
LSER-S-114-A1-2 FG Preventive Maintenance Atmospheric Corrosion
Corrosion, Insignificant 2015 2012 Close Visual Inspection
A1-2" FG
LCOM-05-115-A1-2"
111 LCOM Relief and Disposal System PIPING FROM 05-22-AI-2" TO 05-89-AI-2" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
OW
Fuel Gas System Compressor
112 LCOM LCOM-05-116-A1-1" PIPING FROM 05-V-8B TO PL-311-B-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Module
PIPING FROM 05-114-AI-2" FG TO P-113A-6"/P-
LPRO-05-118-A1-2"-
113 LPRO "L" Service Platform 155A-6"/PCV (LPV-7 TO 05-A-011) 2" FUEL Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
FG
LINE FROM LCOM TO LSER
LCOM-05-118-A1-2"
114 LCOM Relief and Disposal System M BALL VALVE/ 05-114-A1-2" TO PCV-560 (HP FLA Preventive Maintenance Atmospheric Corrosion, Insignificant 2015 2012 Close Visual Inspection
FG
LSER-05-118-A1-2" PIPING FROM 05-114-A1-2" FG TO PCV-560 VIA
115 LCOM Relief and Disposal System Preventive Maintenance Atmospheric Corrosion, Insignificant 2015 2012 Close Visual Inspection
FG BRIDGE
LCOM-05-119-A1-1"
116 LCOM Relief and Disposal System PIPING FROM LCV TO 05-55AI-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LPF
LCOM-05-122-A1-1" PIPING FROM ARRESTER / AUTOMATIC DRAIN
117 LCOM Relief and Disposal System Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
HPF TO 05-21A1-18"
LCOM-05-123-A1-1" PIPING FROM AUTOMATIC DRAIN FR TO 05-53-
118 LCOM Relief and Disposal System Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
OW AI-4"
119 LCOM Relief and Disposal System LCOM-05-127-A1-2" G FROM 05-21A1-18" TO ARRESTER / AUTOMATIC DR Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
120 LCOM Relief and Disposal System LCOM-05-128-A1-1" OW PIPING FROM LCV TO 05-58-AI-4" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
LCOM-05-12-F1-6"-
121 LCOM Compressor Suction Drum PIPING FROM PG-136-D-8" TO FE-541 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
RG(I)
LCOM-05-12-F1-6"-
122 LCOM Compressor Suction Drum PIPING FROM FE-5A1 TO BARRED TEE Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
RG(II)
123 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-16-C1-8" PIPING FROM E-1000B TO PG-124-B-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
124 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-17-C1-8" PIPING FROM V-1100B TO PG-125-B-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM VALVE (BALL VALVE) 4" TO 05-1-A1-
125 LCOM Compressor Suction Drum LCOM-05-1-A1-18" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
20"
126 LCOM Compressor Suction Drum LCOM-05-1-A1-20" PIPING FROM 05-1-A1-18" TO 05-1-A1-20" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Fuel Gas System Compressor PIPING FROM PCV-524 TO PCV-521/FUEL GAS
127 LCOM LCOM-05-20-A1-3" Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
Module GENERATOR
Fuel Gas System Compressor
128 LCOM LCOM-05-20-A1-4" PIPING FROM T-JOINT TO BLIND FLANGE Preventive Maintenance Atmospheric Corrosion, Insignificant 2015 2012 Close Visual Inspection
Module
PIPING FROM PSV/ LINE 05-21-A1-8" / HP
LCOM/ LCOM-LSER-LPRO-05-
129 Relief and Disposal System FLARE HEADER TO PL-111A-26" VIA BRIDGE Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
LSER/LPRO 21-A1-18"
(TO HP FLARE - LSER )
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
LCOM-05-22-A1-2" PIPING FROM 05-D-2 SKID DRAINS TO 05-115-
130 LCOM Relief and Disposal System Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
OW A1-2"
131 LCOM Relief and Disposal System LCOM-05-304-A-2" PIPING FROM 05-705-A-1" TO 05-55-A1-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
132 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-304-D1-2" PIPING FROM PL-304-B-3" TO LV-1107B Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LCOM-05-304-D1- PIPING FROM V-1100B TO VALVE 3" B4R/PL-304-
133 LCOM 1st Disch. Cooler/2nd Suct. Scrub. Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
3"(III) B-3"
134 LCOM Relief and Disposal System LCOM-05-307-A1-1" PIPING FROM 05-307DI-6" TO 05-74-A1-2" HL Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection

135 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-31-C1-2"(I) PIPING FROM LV-1107A TO 05-31-C1-3" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
PIPING FROM PL-303-B-3" / 05-31-C1-3" TO LV-
136 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-31-C1-2"(II) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
1107A
PIPING FROM 05-31-C1-2" TO BALL VALVE 3"
137 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-31-C1-3"(I) Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
B2R
138 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-31-C1-3"(II) PIPING FROM 05-31-C1-2" TO 05-29-C1-6"-IC Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
LCOM-05-53-A1-1"
139 LCOM Relief and Disposal System PIPING FROM 05-S-10 TO 05-55-A-1-1" / 10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LPF
LCOM-05-35-A1-2"
140 LCOM Relief and Disposal System PIPING FROM 05-V-10 TO 05-S-10 Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
OW
LCOM-05-35-A1-2"
141 LCOM Relief and Disposal System PIPING FROM 05-V-9 TO 05-53-AI-4" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
OW
PIPING FROM NC VALVE 2" D2RF TO 05-55-A1-
142 LCOM Relief and Disposal System LCOM-05-401-A-2" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
10"
PIPING FROM NC VALVE (OUTLET DRAIN 05-V-
143 LCOM Slug Catcher LCOM-05-404-A-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
30) TO 05-58A1-4" (INLET 05-P-5)
PIPING FROM NC VALVE 1D2206 / L L-COM-R-004
COM R 004
144 LCOM Sl C
Slug Catcher
t h LCOM 05 405 A 1"
LCOM-05-405-A-1" D t il A
Detail Assestment
t t I i ifi
Insignificant
t 2010 2010 Cl
Close Vi
Visuall IInspection
ti
TO 05-410-A-2" / 05-405A-2"
145 LCOM Pig Launcher/Receiver LCOM-05-406-A-1" PIPING FROM PSV-0403 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
146 LCOM Slug Catcher LCOM-05-410-A-2" PIPING FROM PSV-05-V-30 TO 05-308A1-12" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
147 LCOM Relief and Disposal System LCOM-05-410-A-3" PIPING FROM 05-410A-2" TO 05-308-A1-12" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-V-40 TO CHECK VALVE 12" A5R /
148 LCOM Relief and Disposal System LCOM-05-510-A-12"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
05-01A1-18"
PIPING FROM BALL VALVE 12" A2RF / 05-V-40
149 LCOM Relief and Disposal System LCOM-05-510-A-12"(II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
TO 05-01A1-18"
LSER-LCOM-05-55-A1-
150 LCOM/ LSER Relief and Disposal System PIPING FROM 05-V-9 / 05-509-2" TO 05-33-A-1-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
10"(I)
PIPING FROM TO 05-89A1-3"/BLIND
151 LCOM Compressor Utilities LCOM-05-59-A1-3"(I) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
FLANGE
Seawater/Gas Exchanger, Gas/Gas
152 LCOM LCOM-05-606-D-3" PIPING FROM 05-606-D-6" TO 05-V-101 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


153 LCOM LCOM-05-606-D-6" PIPING FROM PL-312-D-3" TO 05-606-D-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
LCOM-05-60-A1-2"
154 LCOM Relief and Disposal System PIPING FROM 05-01A1-18" TO PCV-521 Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
FDG
155 LCOM Relief and Disposal System LCOM-05-61-A1-1" FG PIPING FROM 05-114A1-2" TO PCV-517 Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
PIPING FROM PCV-524 TO PCV-521/FUEL GAS
156 LCOM Relief and Disposal System LCOM-05-61-A1-2" FG Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
GENERATOR
LCOM-05-62-A1-1"- PIPING FROM PSV-534 TO VENT ABOVE
157 LCOM Relief and Disposal System Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
LPF COOLER MODULE
LCOM-05-64-A1-1"
158 LCOM Relief and Disposal System PIPING FROM 05-70-A1-2" TO 05-S-10 Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
OW
PIPING FROM PG-137-D-8" TO PV-018B / VALVE
159 LCOM Module Discharge Valving LCOM-05-68-F1-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
6D4R
160 LCOM Compressor Suction Drum LCOM-05-705-A-1" PIPING FROM PSV/05-L-01 TO 05-304AI-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
LCOM-05-70-A1-2" PIPING FROM 05-S-10 TO 05-53-AI-4"/05-64-AI-
161 LCOM Relief and Disposal System Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
OW 1"
162 LCOM Relief and Disposal System LCOM-05-73-A1-1" (I) PIPING FROM 05-73-A1-2" TO LV-005A Detail Assestment Insignificant 2010 2010 Close Visual Inspection

163 LCOM Relief and Disposal System LCOM-05-73-A1-1" FG PIPING FROM PCV-528 TO 05-V-10 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
164 LCOM Relief and Disposal System LCOM-05-73-A1-1"(II) PIPING FROM LV-005A TO 05-73-A1-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection

165 LCOM Compressor Suction Drum LCOM-05-74-A1-3"(III) PIPING FROM LV-005B TO 05-74-A1-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection

166 LCOM Compressor Suction Drum LCOM-05-74-A1-6"(II) PIPING FROM BOLD VALVE 6" A2R TO SDV 005 Detail Assestment Insignificant 2010 2010 Close Visual Inspection

167 LCOM Compressor Suction Drum LCOM-05-74-A1-6"(III) PIPING FROM SDV 005 TO 05-74-A1-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-74-A1-3" TO BOLD VALVE 6"
168 LCOM Compressor Suction Drum LCOM-05-74-A1-6"(IV) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
A2R
LCOM-05-77-A1-1"
169 LCOM Relief and Disposal System PIPING FROM 05-V-12 TO 05-55-A-1-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LPF
LCOM-05-88-A1-2"
170 LCOM Relief and Disposal System PIPING FROM 05-V-10 TO 05-89-AI-2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
OW
171 LCOM Relief and Disposal System LCOM-05-89A1-1" FG PIPING FROM PCV-519 TO 05-S-10 Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-89-AI-2" TO BLIND FLANGE/05-
172 LCOM Relief and Disposal System LCOM-05-89-A1-2" 0W Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
59-AI-2"
173 LCOM Pig Launcher/Receiver LCOM-05-901-D-12"(I) PIPING FROM 05-12FI-12" TO NC VALVE Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
LCOM-05-920-A1-3"
174 LCOM Compressor Suction Drum PIPING FROM 05-ME-10 TO 05-18-F1-6" Detail Assestment Insignificant 2015 2012 Close Visual Inspection
RG
LCOM-05-92-A1-3"-
175 LCOM Compressor Suction Drum PIPING FROM 05-12FI-6-RG TO 05-ME-10 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
RG(I)
LCOM-05-92-A1-3"-
176 LCOM Compressor Suction Drum PIPING FROM 05-92AI-3-RG TO 05-403D-10 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
RG(II)
177 LCOM Compressor Suction Drum LCOM-PG-100-A-24" PIPING FROM 05-V-1 TO PG-100-A-18" Detail Assestment Insignificant 2015 2012 Close Visual Inspection
178
8 LCOM 1st Stage Compressor LCOM-PG-103-B-8"-1S
CO G 03 8 S PIPING
G FROM
O 05-4-C1-8"
05 C 8 TO O 05-4-C1-8"
05 C 8 Detail
eta Assestment
ssest e t Corrosion Under Insulation 2010
0 0 2010
0 0 Close Visual Inspection
179 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-105-B-8" 0A (INTERCOOLER) TO V-1100 A (2ND STAGE SU Detail Assestment Insignificant 2010 2010 Close Visual Inspection
180 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-106-B-8" PIPING FROM V-1000A TO 05-C-2A Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
181 LCOM 2nd Stage Compressor & After Cooler LCOM-PG-107-D-6"-1S-1.4 PIPING FROM PG-107-D-8"-IS TO E-1200A Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection

182 LCOM 2nd Stage Compressor & After Cooler LCOM-PG-107-D-8"-IS-1.4 PIPING FROM 05-C-2A TO 06-107-D-6-IS Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
2nd Stage Compressor & After
183 LCOM COM-PG-108-D-6"-IS-1. PIPING FROM E-1200A TO PG-108-D-8"-IS Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
Cooler
2nd Stage Compressor & After
184 LCOM COM-PG-108-D-8"-IS-1.
NG FROM PG-108-D-8"-IS TO PSV-2A18/2A17 - E-1 Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
Cooler
2nd Stage Compressor & After
185 LCOM LCOM-PG-109-D-8" PIPING FROM E-1300A TO SDV-2A27 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Cooler
2nd Stage Compressor & After
186 LCOM LCOM-PG-110-D-8"(I) PIPING FROM SDV-2A27 TO PG-111-D-6" / E-1400 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler
Seawater/Gas Exchanger, Gas/Gas
187 LCOM LCOM-PG-111-D-6" G FROM REDUCER 8" X 6" (PG-110-D-8") TO PCV Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
188 LCOM Compressor Suction Drum LCOM-PG-112-A-6" PIPING FROM PCV-0218 TO 05-1-A1-18" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
189 LCOM Module Discharge Valving LCOM-PG-120-D-3" PIPING FROM PG-137-D-8" TO GESV. 300C Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
190 LCOM 1st Stage Compressor LCOM-PG-122-B-8"-IS-1. PIPING FROM 05-14-C1-8"-IS TO 05-14-C1-8"-IS Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
PIPING FROM 05-C-1B (DISCHARGE OF COMP. B)
191 LCOM 1st Stage Compressor LCOM-PG-123-B-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
TO E-1000B
192 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-124-B-8" PIPING FROM 05-16-C1-8' TO V-1100B Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
2nd Stage Compressor & After
193 LCOM LCOM-PG-125-B-8" PIPING FROM 05-17-CI-8" TO 05-C-2B Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
cooler
Seawater/Gas Exchanger, Gas/Gas
194 LCOM LCOM-PG-136-D-3" NG FROM PG-136-D-6" TO PSV-0311A/B / PG-136- Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


195 LCOM LCOM-PG-136-D-6"(I) PIPING FROM PV-0315 TO PG-136-D-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


196 LCOM LCOM-PG-136-D-6"(II) PIPING FROM 05-V-3 TO PG-136-D-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
Seawater/Gas Exchanger, Gas/Gas
197 LCOM LCOM-PG-136-D-8"(I) PING FROM PG-136-D-6" VALVE 8D4R TO SDV-03 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator
Seawater/Gas Exchanger, Gas/Gas
198 LCOM LCOM-PG-136-D-8"(II) PIPING FROM SDV-0316 TO 05-12-F1-6"-RG Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator
PIPING FROM PG-136-D-8" TO BOLD VALVE
199 LCOM Module Discharge Valving LCOM-PG-137-D-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
8D2R
Seawater/Gas Exchanger, Gas/Gas
200 LCOM LCOM-PG-138-D-1" PIPING FROM E-1400 TO PSV 0310 A/B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


201 LCOM LCOM-PG-139-D-2" PIPING FROM PG-136-D-8" TO BDV-0312 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
2nd Stage Compressor & After PIPING FROM 05-V-4 TO T-JOINT/PSV-029 / E-
202 LCOM LCOM-PG-94-C1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler 1200A
PIPING FROM V-1100A / 05-31-C1-3" TO 05-31-
203 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-303-B-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
C1-2" - VALVE 3"
PIPING FROM PL-305-D-6" TO BOLD VALVE
204 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-305-D-4"(I) Detail Assestment Insignificant 2015 2012 Close Visual Inspection
4D2R
Seawater/Gas Exchanger, Gas/Gas PIPING FROM 05-V-101 TO PSV-0309 A/B /
205 LCOM LCOM-PL-309-D-3" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator WELD CAP / PCV-0310

Seawater/Gas Exchanger, Gas/Gas


206 LCOM LCOM-PL-310-D-6" PIPING FROM 05-102-D-6 TO E-1500 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas PIPING FROM GATE VALVE 3D4R TO 05-606-D-


207 LCOM LCOM-PL-312-D-3" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator 6"

Seawater/Gas Exchanger, Gas/Gas


208 LCOM LCOM-PL-312-D-1 1/5(I) PIPING FROM LCV-0304 TO PL-312-D-1.5"/3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


209 LCOM LCOM-PL-312-D-1 1/5(II) PIPING FROM PL-312-D-1.5" / 3" TO LCV-0304 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas PIPING FROM 05-V-3 TO BOLD VALVE 3"


210 LCOM LCOM-PL-312-D-3"(I) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator D2RF/GATE VALVE 3D4R

Seawater/Gas Exchanger, Gas/Gas


211 LCOM LCOM-PL-312-D-3"(II) PIPING FROM PL-312-D-1.5" TO 05-606-D-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


212 LCOM LCOM-PL-313-D-1" PIPING FROM PL-309-D-3" TO BDV-0333 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
213 LCOM Slug Catcher LCOM-R-106-A1-2" PIPING FROM PSV-03-06 TO 05-410-A-2" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
(P-111-A-20")HP FLARE HEADER TO HP FLARE
214 LCOM Production separator LCOM-24" HP FLARE Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
STACK- LPRO
PIPING FROM 8" NC VALVE / RED 12"X 8" TO 05-
215 LPRO Production Separator LPRO-P-103E-8" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
304-DI-12"
216 LPRO "L" Process Platform LPRO-P-111A-12" PIPING FROM PC-LPV-2 TO RED 16" X 12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PIPING FROM RED 16" X 12" TO BALL VALVE / P-
217 LPRO Production separator LPRO-P-111A-16"(II) Preventive Maintenance Corrosion Under Insulation 2015 2012 Close Visual Inspection
111A-24"
218 LPRO Production separator LPRO-P-111A-16"(III) PIPING FROM REDUCER 6 X 16 TO BALL VALVE Preventive Maintenance Corrosion Under Insulation 2015 2012 Close Visual Inspection
PIPING FROM BALL VALVE / RED 16" X 12" TO P-
219 LPRO Production separator LPRO-P-111A-16"(IV) Preventive Maintenance Corrosion Under Insulation 2015 2012 Close Visual Inspection
111A-24"
PIPING FROM BLIND FL TO BOTTOM TWO
220 LPRO "L" Process Platform LPRO-P-111A-24"(I) Detail Assestment Insignificant 2015 2012 Close Visual Inspection
CARDS OF BRIDGES
PIPING FROM BALL VALVE 16" / RED 16" X 12"
221 LPRO "L" Process Platform LPRO-P-111A-24"(II) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
TO P-111A-24"
PIPING FROM RELIEF FROM LA P/F TO P 111A-
222 LPRO "L" Process Platform LPRO-P-111A-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
24"
PIPING FROM A-153-A-6" AT LA P/F TO P-111-A-
223 LPRO "L" Process Platform LPRO-P-111-A-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
20" (FLARE HEADER)
224 LPRO "L" Process Platform LPRO-P-123-8" PIPING FROM P-134A-6" TO P-111A-24" Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
225 LPRO Production separator LPRO-P-128A-6" PIPING FROM PSV LPV-2A TO P-134A-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
226 LPRO Production separator LPRO-P-134A-6" PIPING FROM PSV-LPV-3A TO P 134A-8" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
227 LPRO Production separator LPRO-P-134A-8" PIPING FROM P-134-A-6" TO P-128-A-8" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
228 LPRO Flare, Drain System & Fire Utility LPRO-P-156A-2" PIPING FROM PSV-LPV-7 TO P-111A-24" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
229 LPRO Piping Line LPRO-P-169N-1" PIPING FROM P-169-N-2" TO LA PLATFROM Minimum Survaillance Atmospheric Corrosion, Insignificant 2021 2015 Close Visual Inspection

230 LPRO Flare, Drain System & Fire Utility LPRO-P-169N-2" PIPING FROM S 105N-2" TO REDUCER 2" X 1" Minimum Survaillance Atmospheric Corrosion, Insignificant 2021 2015 Close Visual Inspection
231 LPRO Flare, Drain System & Fire Utility LPRO-S-105N-2" PIPING FROM S 105N-1" TO P-169-N-2" Minimum Survaillance Atmospheric Corrosion, Insignificant 2021 2015 Close Visual Inspection
PIPING FROM FIRE WATER PUMP TO PSV-
232 LSER "L" Service Platform LSER-S-101L-3" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
2/BUTTERFLY VALVE
PIPING FROM S-101-L-6" TO S-101-L-2" (A) / S-
233 LSER "L" Service Platform LSER-S-101L-4" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
101-L-2" (B)
234 LSER "L" Service Platform LSER-S-101L-6" PIPING FROM BUTTERFLY PUMP TO S-101-L-4" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
PIPING FR S-102-L-6" TO S-102-L-2" A/S-102-L-2"
235 LSER "L" Service Platform LSER-S-102L-4" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
B/S-102-L-2"C
236 LSER Foam Concentrate System LSER-S-102L-6" PIPING FROM S-101-L-4" TO P-174-L-6" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
237 LSER Foam Concentrate System LSER-S-103L-4" PIPING FROM S-101-L-4" TO P-171-L-4" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
238 LSER Foam Concentrate System LSER-S-104L-4" PIPING FROM S-101-L-4" TO P-172-L-4" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
6"-150#, SPIKE OIL LINE LCOM TO
239 LPRO Production separator LPRO-05-29-C1-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
INTERSTAGE SEP. LIQUID
240 LCOM Production separator LCOM-05-29-C1-4" LCOM TO LSER VIA BRIDGE Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
SPIKE OIL FROM LCOM TO INTERSTAGE
241 LCOM Production separator LSER-05-29-C1-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
SEPARATOR LIQUID
PIPING FROM RISER FLANGES TO SDV-580 AT
242 LCOM Slug Catcher & receiver LCOM-05-300-E1-16" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
LCOM
PIPING FROM NC BALL VALVE TO 05-V-30
243 LCOM Slug Catcher LCOM-05-401-D-10" (II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
(SLUG CATCHER)
244 LCOM Slug Catcher LCOM-05-405-D-4" PIPING FROM 05-401-D-10" TO 05-501-D-4" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
PIPING FROM 05-405-D-4" TO LA-P-003-4" VIA
245 LPRO Piping Line LPRO-P-XXX-D-4" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LPRO & BRIDGE
PIPING FROM LPRO-P-XXX-D-4" TO HP GAS
246 LA Piping Line LA-P-003-4" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
HEADER
PIPING FROM 05-12FI-12"-FG TO NC-VALVE/T
247 LA Wellheads LA-A-151-D-3" JOINT/05-401D-10" LCOMP TO LINE 05-407-A- Detail Assestment Insignificant 2010 2010 Close Visual Inspection
10" (TO COMPRESSION MODULE)
248 LCOM Slug Catcher LCOM-05-403-D-10"(II) PIPING FROM 05-403D-10" TO VALVE 2D2R Detail Assestment Insignificant 2010 2010 Close Visual Inspection
249 LCOM Compressor Suction Drum LCOM-05-403-D-10"(III) PIPING FROM VALVE 2D2R TO 05-403D-10" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-44D-4" (V-20) TO 05-405-D-3" (
250 LCOM Slug Catcher LCOM-05-501-D-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
LCOM V-30))
251 LCOM Slug Catcher LCOM-05-700-D-6" PIPING FROM 05-700-D-6" TO 05-700-D-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PIPING FROM LPRO (TRANS. PUMP TO P-106-A-
252 LCOM "L" Process Platform LCOM-P-110-B-4" (8") Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
12" (TO LPV-6)
PIPING FROM P/L NGL (RISER FLANGE) TO
253 LCOM Pig Launcher/Receiver LCOM-PG-115-D-24" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LCOM-R-003 (RECEIVER)
254 LCOM Pig Launcher/Receiver LCOM-PG-116-D-16" PIPING FROM PG-115-D-24" TO 05-400D-16" Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection

PIPING FROM PG-117-B-4" (FV-2A03) TO PG-


255 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-117-B-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
105-B-8"
256 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-105-B-8" PIPING FROM E-1000A TO V-1100 A Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
257 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-306-B-4" PIPING FROM SDV-1102A TO PG-105-D-8" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection

258 LPRO Production Separator LPRO-05-01A-18" PIPING FROM LIQUID OUT TO V-40 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
18"-150#, GAS OUTPUT LPV-2/3 TO LCOM
259 LPRO Production Separator LPRO-05-01A-18" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
SUCTION DRUM
PIPING FROM FEED GAS (LPV-2/3 TO LCOM-05-
260 LPRO Production Separator LPRO-05-01A-18" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
V-01)
6"-600#, G/L LINE FROM LCOMP (05-700-D-6")
261 LSER/LPRO Flare, Drain System & Fire Utility LSER-LPRO-05-44-F1-6" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
TO LA PLATF (PRESS. 600#) VIA BRIDGE

262 LSER Slug Catcher LSER-05-44-F1-6"-LG G/L LINE FROM LCOM TO LA PLTF VIA LPRO Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection

PIPING FROM 05-44-FI-8" TO 05-700-D-6"/BLIND


263 LCOM/ LSER Slug Catcher LSER-LCOM-05-44-F1-6 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
FLANGE
264 LPRO Test Separator & Gas Lift Sept. LPRO-P-XXX-D-3" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
265 LA Wellheads LA-A-151-D-3" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
PIPING FR FLA TO TOP CHORD OF BRIDGE TO
266 LPRO "L" Service Platform LPRO-05-55A1-10"(I) Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
BE LP FLARE LINE
267 LPRO Relief and Disposal System LPRO-05-55-A1-10"(II) PIPING FROM 05-33AI-1" LPF TO FLA Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
268 LSER "L" Service Platform LSER-L-121-A-6" 6" Condensate Preventive Maintenance Atmospheric Corrosion, Insignificant 2015 2012 Close Visual Inspection

PIPING FROM LV-05-V-20 (SLUG CATCHER) TO


269 LSER/LPRO Production separator ER-LPRO-05-304-D1-4" Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
LPV-3 (PRODUCTION SEPARATOR)
PIPING FROM P-101-E-12" (INLET LPV-2) TO
270 LPRO Production separator LPRO-06-29-C1-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
LPRO-05-304-D1-4" (INLET LPV-3)
Production separator, KO Drum & PIPING FROM BLIND FLANGE (CONT TO P-105-
271 LPRO LPRO-P105-A-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Atmospheric Separator A-3")TO CONTROL VALVE/NC VALVE (LPV-5)
PIPING FROM NC VALVE (P-105-A-12") TO
272 LPRO Production separator LPRO-P-106-A-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
CONTROL VALVE LPV-6C (PSV PLV-3)
PIPING FROM 6"-150#, GAS OUT LPV-7 TO
273 LPRO Flare, Drain System & Fire Utility LPRO-P-155-A-6" LCOM VIA LSER AND BRIDGE (PRESS. 35# AS Detail Assestment Insignificant 2010 2010 Close Visual Inspection
BACK UP ST. FUEL LINE)
PIPING FROM BALL VALVE 12" A2RF TO P-114-A-
274 LPRO KO Drum & Atmospheric Separator LPRO-P-149-A-12"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
16"
275 LPRO KO Drum & Atmospheric Separator LPRO-P-149-A-12"(II) PIPING FROM LPV-6 TO BALL VALVE 12" A2RF Detail Assestment Insignificant 2010 2010 Close Visual Inspection
276 LPRO KO Drum & Atmospheric Separator LPRO-P-177-L-10" PIPING FROM LPV-5 TO PSE-LPV-5 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
277 LPRO LPRO-05-511-A-6" 6"-150#, LIQUID OUT V-40 TO LPV-6 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
278 LCOM LCOM-05-511A-6" 6"-150#, LIQUID OUT V-40 TO LPV-6 Preventive Maintenance Atmospheric Corrosion 2010 2010 Close Visual Inspection
279 LSER "L" Service Platform LSER-S-101-A1-L4" PIPING FROM S-101-L-2A TO SP/K2S Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
280 LSER "L" Service Platform LSER-S-101-A2-1.5"-L PIPING FROM S-101-L-2A TO SP 63/K2S Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
281 LSER "L" Service Platform LSER-S-101-A3-1.5"-L PIPING FROM S-101-L-2A TO SP Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
282 LSER "L" Service Platform LSER-S-101-B-1.5"-L PIPING FROM S-101-L-2" (B) TO SP/K2S Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
PIPING FROM S-101-L-4" TO S-101-L-1.5"/ BLIND
283 LSER "L" Service Platform LSER-S-101-B-2"-L Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
FLANGE
PIPING FROM S-101-L-6" TO S-101-L-2"A & S-
284 LSER "L" Service Platform LSER-S-101-L4" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
101-L-2"B
PIPING FROM S-102-L-2" TO SP LOCATE 1ST
285 LSER "L" Service Platform LSER-S-0102-A-1.5"-L Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
LEVEL
286 LSER "L" Service Platform LSER-S-0102-B-2"-L(I) PIPING FROM S-102-L-4" TO S-102-L-1.5 Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
PIPING FROM S-102-L-4" TO SP LOCATE 3RD
287 LSER "L" Service Platform LSER-S-0102-C-2"-L Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
LEVEL
PIPING FROM S105N-2" TO SP 54 / INSTRUMENT
288 LSER Foam Concentrate System LSER-S105N-1" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
AIR RECEIVER
289 LSER Foam Concentrate System LSER-S105N-2"(I) PIPING FROM REDUCER 2" X 1" TO P-169-N-21 Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
PIPING FROM INSTRUMENT AIR RECEIVER TO S 1
290 LSER Foam Concentrate System LSER-S105N-2"(II) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
0 5 N -2"
PIPING FROM AIR INSTRUMENT LINE 3" TO S-106N-
291 LSER "L" Service Platform LSER-S105N-3" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
3"
292 LSER "L" Service Platform LSER-S106N-1"(I) PIPING FROM S-105N-3' TO S-106N-3" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
293 LSER "L" Service Platform LSER-S106N-1"(II) PIPING FROM PCV/LSV TO S-106N-3" (B) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
294 LSER Foam Concentrate System LSER-S106N-3" PIPING FROM S-105N-3" TO S-106N-1" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
295 LSER "L" Service Platform LSER-S107N-1 1/2" PIPING FROM S-106N-3" TO LSG-1A Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
296 LSER "L" Service Platform LSER-S108N-1 1/2" PIPING FROM S-106N-3" TO LSG-1B Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
297 LSER "L" Service Platform LSER-S109N-1 1/2" PIPING FROM S-106N-3" TO LSG-1C Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
298 LSER "L" Service Platform LSER-S110K-1 1/2" PIPING FROM HOSE CONNECTION TO S-112K-2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
299 LSER "L" Service Platform LSER-S112A-1" PIPING FROM HOSE CONNECTION TO S-112K-2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
PIPING FROM HOSE CONNECTION TO S-112K-
300 LSER "L" Service Platform LSER-S112K-1"(I) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
2"
301 LSER "L" Service Platform LSER-S112K-1"(II) PIPING FROM S-112K-2" TO P-180-K-1" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
302 LSER Foam Concentrate System LSER-S112K-2" PIPING FROM S-112K-1.5" TO S-112N-2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
PIPING FROM S-119A-1" TO HOSE
303 LSER "L" Service Platform LSER-S118A-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
CONNECTION
304 LSER "L" Service Platform LSER-S119A-1" PIPING FROM P-159-A-1" TO S-118A-1" Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
PIPING FROM Fuel Gas Scrubber to LSV-9 TO
305 LSER "L" Service Platform LSER-S119A-6"(I) Preventive Maintenance Atmospheric Corrosion, Insignificant 2015 2012 Close Visual Inspection
HEADER (S-119-6")
306 LSER "L" Service Platform LSER-S119A-6"(II) PIPING FROM WELD CAP TO WELD CAP Preventive Maintenance Atmospheric Corrosion, Insignificant 2015 2012 Close Visual Inspection
307 LSER "L" Service Platform LSER-S120A-2" PIPING FROM S-119A-6" TO LSG 1A Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
308 LSER "L" Service Platform LSER-S121A-2" PIPING FROM S-119A-6" TO LSG 1B Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
309 LSER "L" Service Platform LSER-S122A-2" PIPING FROM S-119A-6" TO LSG 1C Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
310 LSER "L" Service Platform LSER-S123A-1" PIPING FROM LSG-1B TO BALL VALVE 1" D 2 S Detail Assestment Insignificant 2010 2010 Close Visual Inspection
311 LSER "L" Service Platform LSER-S123A-1"(I) PIPING FROM LSG-1C TO BALL VALVE 1" D 2 S Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM BALL VALVE 1" D 2 S TO
312 LSER "L" Service Platform LSER-S123A-1"(II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
FLEXIBLE HOSE
313 LSER "L" Service Platform LSER-S123A-1"(III) PIPING FROM LSG-1A TO BALL VALVE 1" D 2 S Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM HOSE CONNECTION TO S-118A-
314 LSER "L" Service Platform LSER-S123A-1"(IV) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
1"
315 LSER "L" Service Platform LSER-S123A-3" PIPING FROM WELD CAP TO S-124A-3" Preventive Maintenance Atmospheric Corrosion, Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
PIPING FROM HOSE CONNECTION TO S-118A-
316 LSER "L" Service Platform LSER-S124A-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
1"
317 LSER "L" Service Platform LSER-S124A-3" PIPING FROM S 123A-3" TO ??? Detail Assestment Insignificant 2010 2010 Close Visual Inspection
318 LSER Slug Catcher LSER-P-018N-4" HIGH PRESSURE GAS LINE FROM LA TO LCOM Detail Assestment Insignificant 2010 2010 Close Visual Inspection

319 LSER LSER- FLOW LINE FROM WELLHEAD TO HEADER Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection

320 LCOM Slug Catcher LSER-4" HP GAS LPRO-LSER, LA (HP WELL) TO LCOM (V-30) Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
321 LCOM Relief and Disposal System LSER-18" FEED GL LPRO TO LCOM (05-01-A-18") Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
HIGH PRESSURE GAS LINE FROM LA HDR TO
322 LA Piping Line LA-P-003-4" (I) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LCOM
HIGH PRESSURE GAS LINE FROM LA HDR TO
323 LA Piping Line LA-P-003-4" (II) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LCOM
HIGH PRESSURE GAS LINE FROM LA HDR TO
324 LA Piping Line LA-P-003-4" (III) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
LCOM
PIPING FROM TEST SEPARATOR (AV1) TO
325 LA T t Separator
Test S t & Gas
G Lift Sept.
S t LA A 152 A 3"
LA-A-152-A-3" D t il A
Detail Assestment
t t I i ifi
Insignificant
t 2010 2010 Cl
Close Vi
Visuall IInspection
ti
ATMOSPHERIC SEPARATOR
326 LA Test Separator & Gas Lift Sept. LA-A-153-A-6"(1) OUTLET LINE FROM TEST SEPARATOR (AV1) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
327 LA Test Separator & Gas Lift Sept. LA-A-153-A-6"(2) PIPING FROM LA P/F TO F FLOW STATION Detail Assestment Insignificant 2010 2010 Close Visual Inspection
328 LA Test Separator & Gas Lift Sept. LA-A-164-A-2" PIPING TO A-152-A-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
HIGH PRESSURE GAS LINE FROM LA-11L TO
329 LA Wellheads LA-PL-106-E-3" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
TEST HDR, LP HDR & LINE P-003N-6"
330 LA Wellheads LA-PL-110-E-3" HIGH PRESSURE GAS LINE FROM LA-11L Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
331 LA Test Separator & Gas Lift Sept. LA-6" GAS OUT TS LA (AV1) TO LPRO [LA & LA-LPRO BRIDGE] Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection

332 LA Wellheads LA-8" MOL 3 PHASE LA TO LPRO (LPV-2) [LA & LA-LPRO BRIDGE] Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
LA-12" PARIGI TEST
333 LA Wellheads LA TO LPRO (V-610) [LA & LA-LPRO BRIDGE] Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
HEADER
LA-10" PARIGI
334 LA Wellheads PRODUCTION LA TO LPRO (V-620) [LA & LA-LPRO BRIDGE] Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
HEADER
LA (HP WELL) TO LCOM V-30) [LA & LA-LPRO
335 LA Flare, Drain System & Fire Utility LA-4" HP GAS Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
BRIDGE]
336 LA Test Separator & Gas Lift Sept. LA-A-114-F-3" PIPING FROM TEST HEADER TO A-161-F-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM A-114-F-3" TO PRODUCTION
337 LA Test Separator & Gas Lift Sept. LA-A-113-F-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
HEADER & LPRO VIA BRIDGE
338 LA Test Separator & Gas Lift Sept. LA-A-113-F-8" PIPING FROM A-113-F-3" TO LPRO Detail Assestment Insignificant 2010 2010 Close Visual Inspection
339 LA Wellheads LA-BR-A-111-A-12" GAS LINE PARIGI HEADER FROM LA TO LPRO Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
PIPING FROM WH-2 & WH-3 TO V-620 (PARIGI
340 LA Wellheads LA-P-XXX-D-12" Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
PROD. SEP.)
PIPING FROM WH-2 & WH-3 TO V-610 (PARIGI
341 LA Wellheads LA-P-XXX-D-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
TEST SEP.)
LCOM-8" 8" CONTIGENCY LINE FROM 05-901-D-
342 LCOM Pig Launcher/Receiver Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
CONTIGENCY 12"/BYPASS LINE-LPRO (NEAR SDV-05-ME-30)
343 LPRO Production Separator LPRO-05-304D1-12" PIPING FROM 05-300-D1-16" TO 05-V-20 Detail Assestment Insignificant 2015 2012 Close Visual Inspection
344 LPRO Production Separator LPRO-05-304D-4"(I) PIPING FROM LPRO TO LCOM Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
PIPING FROM LA P/F TO PARIGI TEST
345 LPRO Parigi Test & Production Separator LPRO-P-XXX-D-10" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
SEPARATOR (V-610)
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
Fuel Gas System Compressor LCOM-05-95-C1-1
346 LCOM PIPING FROM 05-V-4 TO 05-95-C1-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module 1/2"(I)
Fuel Gas System Compressor LCOM-05-95-C1-1
347 LCOM PIPING FROM 05-95-C1-1" TO PL-311-B-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module 1/2"(II)
Fuel Gas System Compressor
348 LCOM LCOM-05-95-C1-1"(I) G FROM 05-95-C1-1.5 TO LV-022 AND TO 05-95-C Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
349 LCOM Fuel Gas System Compressor Module LCOM-05-95-C1-1"(II) PIPING FROM 05-95-C1-1.5 TO VALVE 1D4Z Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Fuel Gas System Compressor
350 LCOM LCOM-05-95-C1-1"(III) PIPING FROM VALVE 1D5S TO PL-05-95-C1-1 1/2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
351 LCOM Slug Catcher LCOM-05-401-D-10" (I)FROM 05-V-30 TO NC VALVE/BALL VALVE/CHECK Detail Assestment Insignificant 2010 2010 Close Visual Inspection
LCOM-05-401-D-
352 LCOM Slug Catcher PIPING FROM NC VALVE TO BALL VALVE 10D2R Detail Assestment Insignificant 2010 2010 Close Visual Inspection
10"(III)
353 LCOM Slug Catcher & receiver LCOM-05-300E-16" PIPING FROM SDV-580 TO 05-ME-20 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
354 LCOM Slug Catcher & receiver LCOM-05-300-E-2" PIPING FROM VALVE 2" E2R TO 05-300D-16" Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
355 LCOM Slug Catcher & receiver LCOM-05-308-A1-12" PIPING FROM PSV-05-V-20 TO 05-21-A1-18" Detail Assestment Insignificant 2010 2010 Close Visual Inspection

356 LCOM Relief and Disposal System LCOM-05-308-A1-12" PIPING FROM 05-308AI-12" TO VALVE 12" A2RF Detail Assestment Insignificant 2010 2010 Close Visual Inspection
357 LPRO Test Separator & Gas Lift Sept. LPRO-6" GAS OUT TS LA (AV1) TO LPRO Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
358 LPRO Test Separator & Gas Lift Sept. LPRO-8" MOL 3 PHASE LA TO LPRO (LPV2) [LPRO] Detail Assestment Insignificant 2010 2010 Close Visual Inspection
359 LPRO Test Separator & Gas Lift Sept. RO-12" PARIGI TEST HD LA TO LPRO (V-610) [LPRO ] Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
360 LPRO Test Separator & Gas Lift Sept. PRO-0" PARIGI PROD. H LA TO LPRO (V-620) [LPRO] Detail Assestment Insignificant 2010 2010 Close Visual Inspection
361 LPRO Slug Catcher LPRO-4" HP GAS LA (HP WELLS) [LPRO & LPRO-LSER BRIDGE] Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
362 LCOM Slug Catcher LCOM-4" HP GAS LA (HP WELLS) TO LCOM (V-30) Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
363 LCOM Relief and Disposal System LCOM-18" FEED GL LPRO TO LCOM Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
PIPING FROM GATTER TO BLIND FLANGE/05-
364 LCOM Relief and Disposal System LCOM-05-06A1-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
109-AI-4"
PIPING FROM GATTER TO BLIND FLANGE/05-
365 LCOM Relief and Disposal System LCOM-05-07A1-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
57-AI-6"
PIPING FROM GATTER TO BLIND FLANGE/05-
366 LCOM Relief and Disposal System LCOM-05-05-A1-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
57-AI-6"
367 LCOM Relief and Disposal System LCOM-05-09A1-4" PIPING FROM BLIND FLANGE TO 05-57-AI-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection

Seawater/Gas Exchanger, Gas/Gas


368 LCOM LCOM-05-103-D-1" PIPING FROM 05-103-D-2" TO 05-72-A1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas


369 LCOM LCOM-05-103-D-2"(I) PIPING FROM 05-V-101 TO VALVE 2D2R Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator

Seawater/Gas Exchanger, Gas/Gas PIPING FROM BOLD VALVE 2D2R TO 05-103-D-


370 LCOM LCOM-05-103-D-2"(II) Detail Assestment Insignificant 2015 2012 Close Visual Inspection
Exch., Residue Gas Separator 1"
371 LCOM Relief and Disposal System LCOM-05-106A1-4"-OW PIPING FROM GATTER TO 05-06-AI-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
372 LCOM Relief and Disposal System LCOM-05-107A1-4"-OW PIPING FROM GATTER TO 05-07A1-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
373 LCOM Relief and Disposal System LCOM-05-108A1-4"-OW( PIPING FROM GATTER TO 05-08A1-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
374 LCOM Relief and Disposal System COM-05-109A1-4"-OW(I PIPING FROM GATTER TO 05-57A1-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
Fuel Gas System Compressor
375 LCOM LCOM-05-113-C1-1"(I) PIPING FROM 05-113-C1-2" TO PCV-025 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
376 LCOM LCOM-05-113-C1-1"(II) PIPING FROM 05-113-C1-2" TO PCV-024 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
377 LCOM LCOM-05-113-C1-1"(III) PIPING FROM PCV-024 TO 05-113-C1-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
378 LCOM LCOM-05-113-C1-1"(IV) PIPING FROM 05-113-C1-2" TO 05-V-8A/PSV-027 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
379 LCOM LCOM-05-113-C1-1"(V) PIPING FROM PCV-025 TO 05-113-C1-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor PIPING FROM BOLD VALVE 2B2R TO 05-113-C1-
380 LCOM LCOM-05-113-C1-2"(I) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Module 2"
Fuel Gas System Compressor PIPING FROM 05-113-C1-3" TO BOLD VALVE
381 LCOM LCOM-05-113-C1-2"(II) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Module 2B2R
Fuel Gas System Compressor PIPING FROM BOLD VALVE 2B2R TO 05-113-C1-
382 LCOM LCOM-05-113-C1-2"(III) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module 1"
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
2nd Stage Compressor & After
383 LCOM LCOM-05-113-C1-3"(II) PIPING FROM T-JOINT TO 05-113-C1-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Cooler
2nd Stage Compressor & After
384 LCOM LCOM-05-113-C1-3"(III) PIPING FROM E-1200A TO T-JOINT Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Cooler
2nd Stage Compressor & After
385 LCOM LCOM-05-113-C1-3"(IV) PIPING FROM T-JOINT TO 05-113-C1-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Cooler
2nd Stage Compressor & After
386 LCOM LCOM-05-113-C1-3"(V) PIPING FROM E-1200B TO T-JOINT Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Cooler
Fuel Gas System Compressor PIPING FROM 05-113-C1-1" TO 05-V-8B / PSV-
387 LCOM LCOM-05-113-C1-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module 028
Fuel Gas System Compressor
388 LCOM LCOM-05-115-C1-1" PIPING FROM 05-V-8A TO 05-116-C1-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
389 LCOM LCOM-PL-116-C1-1" PIPING FROM 05-V-8B TO PL-311-B-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
2nd Stage Compressor & After
390 LCOM LCOM-05-120-A1-1" PIPING FROM PSV-037 TO R-207-A-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler
PIPING FROM 05-21-A1-8"/BLIND FLANGE TO 05-
391 LCOM Module Discharge Valving LCOM-R-200-A-8" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
21-A1-18"
Fuel Gas System Compressor
392 LCOM LCOM-05-20-A1-4"(I) PIPING FROM 05-V-8A TO T-JOINT Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
Module
Fuel Gas System Compressor
393 LCOM LCOM-05-20-A1-4"(II) PIPING FROM 05-V-8B TO T-JOINT Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Module
394 LCOM Relief and Disposal System LCOM-05-24A1-4" OW PIPING FROM BLIND FLANGE TO 05-57-AI-6" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
395 LCOM Module Discharge Valving LCOM-05-24-A1-4" PIPING FROM R-207-A-4 TO 05-21-A1-18" Preventive Maintenance Atmospheric Corrosion 2010 2010 Close Visual Inspection
396 LCOM Slug Catcher & receiver LCOM-05-300-E-2" PIPING FROM 05-300EI-16" TO VALVE 2" E2R Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection

397 LCOM R li f and


Relief d Di
Disposall S
System
t LCOM 05 302 A 1"
LCOM-05-302-A-1" PIPING FROM PSV
PSV-05-ME-20
05 ME 20 TO 05-302AI-1"
05 302AI 1" D t il A
Detail Assestment
t t I i ifi
Insignificant
t 2010 2010 Cl
Close Vi
Visuall IInspection
ti
PIPING FROM VALVE 3/4' D2S2 (LC) TO HP
398 LCOM Slug Catcher & receiver LCOM-05-302-A1-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
FLARE (05-4-011)
PIPING FROM 05-502-A1-2"/05-303A1-2" TO
399 LCOM Slug Catcher & receiver LCOM-05-303-A1-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
SUMP TANK
PIPING FROM NC VALVE 2D2R/2D2R TO 05-
400 LCOM Slug Catcher & receiver LCOM-05-303D-2"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
303A1-4"
401 LCOM Slug Catcher & receiver LCOM-05-303D-2"(II) PIPING FROM 05-V-20 TO NC VALVE 2D2R/C Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM BLIND FLANGE TO 05-V-20/NC
402 LCOM Slug Catcher & receiver LCOM-05-303D-2"(III) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
VALVE
403 LCOM Slug Catcher & receiver LCOM-05-303D-2"(IV) PIPING FROM NC VALVE TO 05-305D1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
404 LCOM Slug Catcher & receiver LCOM-05-308-A1-6" PIPING FROM PSV-05-V-20 TO 05-308AI-12" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
405 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-33-C1-2" PIPING FROM LV-1107B TO 05-33-CI-3" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PIPING FROM VALVE 3" B4R/05-33-CI-2" TO PL-
406 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-33-C1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
311-B-6"-IC
PIPING FROM 05-400D-16" TO BALL VALVE
407 LCOM Relief and Disposal System LCOM-05-400-D-2"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2D2RF
PIPING FROM BALL VALVE 2D2RF TO 05-400D-
408 LCOM Relief and Disposal System LCOM-05-400-D-2"(II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
16"
409 LCOM Relief and Disposal System LCOM-05-410-D-1 1/2" PIPING FROM 05-V-30 TO PSV-05-V-30 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-401-D-10" TO BALL VALVE
410 LCOM Relief and Disposal System LCOM-05-401-D-2"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2D2R
PIPING FROM BALL VALVE 2D2R TO 05-401-D-
411 LCOM Relief and Disposal System LCOM-05-401-D-2"(II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
10"
412 LCOM Pig Launcher/Receiver LCOM-05-402-D-6"(I) PIPING FROM TEE JOINT TO 05-401-D-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
413 LCOM Pig Launcher/Receiver LCOM-05-402-D-6"(II) PIPING FROM L-COMP-R-004 TO NC VALVE Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
414 LCOM Slug Catcher LCOM-05-405-A-2" PIPING FROM DRIP PAN TO 05-404A-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM NC.VALVE2D2R TO 05-304D1-4-
415 LCOM Slug Catcher & receiver LCOM-05-409-D-2"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
IC
PIPING FROM 05-V-30 TO LCV-05-V-
416 LCOM Slug Catcher & receiver LCOM-05-409-D-2"(II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
30/NC.VALVE2D2R
417 LCOM Slug Catcher & receiver LCOM-05-44-D-4" PIPING FROM 05-306DI-8" TO 05-44FI-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
418 LCOM Slug Catcher & receiver LCOM-05-45-D-4" PIPING FROM 05-44D-4" TO 05-301DI-10" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM RISER (FLANGE) TO SDV-05-ME-
419 LCOM LCOM-05-500D-16" Detail Assestment Insignificant 2015 2012 Close Visual Inspection
40
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
PIPING FROM 05-500-D-16" TO GLOBE VALVE
420 LCOM LCOM-05-500-D-2" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
2" D4R (LC)
PIPING FROM SDV-05-ME-40" TO BALL VALVE
421 LCOM LCOM-05-501A-16" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
18" A2RF
422 LCOM Slug Catcher & receiver LCOM-05-502-A1-2" PIPING FROM VALVE 2" D2RF TO 05-303-AI-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FR BARRED TEE 18" X 18" X 12" TO 05-
423 LCOM LCOM-05-502A-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
V-40
PIPING FROM 05-503A-8" TO BALL VALVE 4"
424 LCOM LCOM-05-503A-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
A2RF
425 LCOM LCOM-05-503A-8" PIPING FROM 05-ME-40 TO 05-502A-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
426 LCOM LCOM-05-506A-2" PIPING FROM DRIP TRAY TO DECK DRAIN Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
427 LCOM LCOM-05-508A-4" PIPING FROM PSV-05-V-40 TO 05-21A1-18" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
428 LCOM LCOM-05-512A-2" PIPING FROM 05-V-40 TO 05-58A1-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
429 LCOM Relief and Disposal System LCOM-05-53A1-4"-OW PIPING FROM 05-V-10 TO 05-35A-2 Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection

430 LCOM Relief and Disposal System LCOM-05-55-A1-10"(II) PIPING FROM 05-V-9 TO FLA-LPV8 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PIPING FROM WELD CAP TO WELD CAP/05-59-
431 LCOM Compressor Utilities LCOM-05-87-A1-1 1/2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
A1-3"
PIPING FROM BLIND FLANGE TO BLIND
432 LCOM Compressor Utilities LCOM-05-59-A1-3"(II) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
FLANGE/05-89-A1-2"
LCOM-05-604-B-1
433 LCOM 1st Stage Compressor PIPING FROM 05-604-B-2" TO LV-0210A Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
1/2"(I)
LCOM-05-604-B-1
434 LCOM 1st Stage Compressor PIPING FROM LV-0210A TO 05-604-B-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
1/2"(II)
PIPING FROM V-102-A TO 05-604-B-1.5 BALL
435 LCOM 1st Stage Compressor LCOM-05-604-B-2"(I) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
VALVE 2B4R
PIPING FROM BALL VALVE 2B4R / 05-604-B TO
436 LCOM 1st Stage Compressor LCOM-05-604-B-2"(II) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PL-301-B-2"
437 LCOM 1st Stage Compressor LCOM-05-605-A-2" PIPING FROM BALL VALVE 2B4R TO 05-72-A1-3" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection

438 LCOM 1st Stage Compressor LCOM-05-605-B-2" PIPING FROM V-102A TO BALL VALVE 2B4R Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
LCOM-05-609-B-1
439 LCOM 1st Stage Compressor PIPING FROM 05-609-B1-2" TO LV-0210B Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
1/2"(I)
LCOM-05-609-B-1
440 LCOM 1st Stage Compressor PIPING FROM LV-0210B TO 05-609-B1-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
1/2"(II)
441 LCOM 1st Stage Compressor LCOM-05-609-B-2"(I) PIPING FROM 05-609-B1-1.5 TO PL-302-B-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
PIPING FROM BOLD VALVE B2RF TO 05 05-609-B1-
609 B1
442 LCOM 1 t Stage
1st St Compressor
C LCOM 05 609 B 2"(II)
LCOM-05-609-B-2"(II) D t il A
Detail Assestment
t t I i ifi
Insignificant
t 2010 2010 Cl
Close Vi
Visuall IInspection
ti
1.5
PIPING FROM V-102-B TO BOLD VALVE
443 LCOM 1st Stage Compressor LCOM-05-609-B-2"(III) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
B2RF/BALL VALVE B4R
444 LCOM Module Discharge Valving LCOM-05-60-A1-12" PIPING FROM 05-60-A1-8" TO 05-21-A1-18" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
445 LCOM Module Discharge Valving LCOM-05-60-A1-6" PIPING FROM PV-018B TO 05-60-A1-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
446 LCOM Module Discharge Valving LCOM-05-60-A1-8" PIPING FROM 05-60-A1-6" TO 05-60-A1-12" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
PIPING FROM BOLD VALVE B2RF TO 05-72-A1-
447 LCOM 1st Stage Compressor LCOM-05-612-A-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
3"
448 LCOM 1st Stage Compressor LCOM-05-612-B-2" PIPING FROM V-102-B TO BOLD VALVE B2RF Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
449 LCOM Compressor Suction Drum LCOM-05-701-D-6" PIPING FROM 05-L-01 TO PIPELINE Detail Assestment Insignificant 2010 2010 Close Visual Inspection
450 LCOM Compressor Suction Drum LCOM-05-702-D-3" PIPING FROM 05-700D-6" TO 05-L-01 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM BOLD VALVE 1" D2S TO 05-72-A1-
451 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-70-A1-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
3"-IC
452 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-70-C1-1" PIPING FROM V-1100A TO BALL VALVE 1" D2S Detail Assestment Insignificant 2010 2010 Close Visual Inspection

Seawater/Gas Exchanger, Gas/Gas


453 LCOM LCOM-05-71-D-1" PIPING FROM 05-V-3 TO 05-103-D-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
PIPING FROM 05-70-A1-1" / 05-V-9 FLARE GAS
454 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-72-A1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
SEPARATOR TO BLIND FLANGE
PIPING FROM BOLD VALVE 1"D2S TO 05-72-A1-
455 LCOM Relief and Disposal System LCOM-05-73-A1-1"(III) Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
3"
PIPING FROM WELD CAP TO WELD CAP/05-59-
456 LCOM Compressor Utilities LCOM-05-87-A1-1 1/2" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
A1-3"
457 LCOM Compressor Utilities LCOM-05-88-A1-3" PIPING FROM 05-20-A1-4" TO WELD CAP Detail Assestment Insignificant 2010 2010 Close Visual Inspection
458 LCOM Compressor Utilities LCOM-05-89-A1-3" PIPING FROM 05-20-A1-4" TO WELD CAP Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM NC VALVE (BALL VALVE) TO 05-
459 LCOM Pig Launcher/Receiver LCOM-05-901-D-12"(II) Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
400D-16"
460 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-05-90-A1-1" PIPING FROM V-1100B TO BOLD VALVE 1" D2S Detail Assestment Insignificant 2010 2010 Close Visual Inspection
461 LCOM Compressor Suction Drum LCOM-05-92-A1-3"-RG(II PIPING FROM 05-ME-10 TO 05-403D-10" Detail Assestment Insignificant 2015 2012 Close Visual Inspection
Fuel Gas System Compressor
462 LCOM LCOM-05-93-A1-3" PIPING FROM PSV-029 TO 05-21-A1-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
463 LCOM Module Discharge Valving LCOM-05-93-A1-4" PIPING FROM PSV-027/028 TO 05-21-A1-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2nd Stage Compressor & After PIPING FROM T-JOINT TO BOLD VALVE
464 LCOM LCOM-05-94-C1-3"(I) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler 3B2R/PSV-058/PSV-029
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
2nd Stage Compressor & After
465 LCOM LCOM-05-94-C1-3"(II) PIPING FROM T-JOINT TO E-1400/PSV-037 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler
2nd Stage Compressor & After
466 LCOM LCOM-05-94-C1-3"(III) PIPING FROM BOLD VALVE 3" B2R TO E-1200B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler
Fuel Gas System Compressor PIPING FROM BOLD VALVE 1D2Z TO 05-97-A1-
467 LCOM LCOM-05-96-A1-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module 1"
Fuel Gas System Compressor
468 LCOM LCOM-05-98-A1-1" PIPING FROM BOLD VALVE TO 05-72-A1-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Module
469 LCOM Pig Launcher/Receiver LCOM-D-104-A1-4" PIPING FROM L-COMP-R-004 TO NC VALVE Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM 05-88-A1-3" TO BALL VALVE
470 LCOM Compressor Utilities LCOM-GF-401-A-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2B2R
PIPING FROM 05-89-A1-3" TO BALL VALVE
471 LCOM Compressor Utilities LCOM-GF-402-A-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2B2R
Fuel Gas System Compressor
472 LCOM LCOM-GF-701-D-1" PIPING FROM 05-20-A1-4" TO VT-500-A-8" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Module
PIPING FROM PG-100-A-24" TO PG-100-A-
473 LCOM Compressor Suction Drum LCOM-PG-100-A-18" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
12"/PSV-0208AI - PG-100-A-12"/PSV
PIPING FROM V-102-A TO 05-8-A1-12" / PSV
474 LCOM 1st Stage Compressor LCOM-PG-102-A-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
0209A2 / PSV 0209A1
2nd Stage Compressor & After PIPING FROM SDV-2827 TO PG-111-D-6" E-
475 LCOM LCOM-PG-110-D-8"(II) Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler 1400/BOLD VALVE 8"
476 LCOM 1st Stage Compressor LCOM-PG-113-B-4" PIPING FROM PG-113-B-6" TO FV-0213A Detail Assestment Insignificant 2010 2010 Close Visual Inspection
477 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-113-B-6" PIPING FROM PG-105-B-8" TO PG-113-B-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
478 LCOM 1st Stage Compressor LCOM-PG-114-A-4" PIPING FROM FV-0213A TO PG-114-A-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
479 LCOM 1st Stage Compressor LCOM-PG-114-A-6" PIPING FROM PG-114-A-4" TO PG-114-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
480
80 LCOM
CO 1st Stage Compressor LCOM-PG-114-A-8"
CO G 8 PIPING FROM PG
PG-114-A-6"
114 A 6 TO V
V-102-A
102 A Detail
eta Assestment
ssest e t Insignificant 2010
0 0 2010
0 0 Close Visual Inspection
PIPING FROM V-1000A TO PSV-1104A/PSV-
481 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-115-B-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
1105A
2nd Stage Compressor & After
482 LCOM LCOM-PG-116-D-2" PIPING FROM PG-116-D-2" TO FV-2A03 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler
2nd Stage Compressor & After
483 LCOM LCOM-PG-116-D-3" PIPING FROM PG-109-D-8" TO PG-116-D-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
Cooler
2nd Stage Compressor & After
484 LCOM LCOM-PG-118-D-2"(I) PIPING FROM PG-109-D-8" TO VALVE 2D5R Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
Cooler
2nd Stage Compressor & After
485 LCOM LCOM-PG-118-D-2"(II) PIPING FROM PG-115-D-24" TO LCOM-R-003 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Cooler
486 LCOM Pig Launcher/Receiver LCOM-PG-119-D-1" PIPING FROM PG-115-D-1" TO LCOM-R-003 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection

487 LCOM 2nd Stage Compressor & After Cooler LCOM-PG-119-D-2" PIPING FROM PG-109-D-8" TO VALVE 2D5R Detail Assestment Insignificant 2010 2010 Close Visual Inspection
PIPING FROM LCOM-R-004 TO NC VALVE
488 LCOM Pig Launcher/Receiver LCOM-PG-120-XD-1" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
1D2Z0
PIPING FROM V-102-B TO 05-13-A1-12 / PSV
489 LCOM 1st Stage Compressor LCOM-PG-121-A-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
0209B2 / PSV 0209B1
490 LCOM Pig Launcher/Receiver LCOM-PG-121-XD-1" PIPING FROM LCOM-R-004 TO 05-400D-16" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
491 LCOM 1st Stage Compressor LCOM-PG-123-B-8"-1.5" PIPING FROM PG-123-B TO-8" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
2nd Stage Compressor & After
492 LCOM COM-PG-126-D-6"-IS-1 1 PIPING FROM PG-126-D-8"-IS TO E-1200B Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
cooler
2nd Stage Compressor & After
493 LCOM COM-PG-126-D-8"-IS-1 1 PIPING FROM 05-C-2B TO PG-126-D-6"-IS Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
cooler
2nd Stage Compressor & After PIPING FROM E-1200B TO E-1300B - PSV-
494 LCOM COM-PG-127-D-8"-IS-1 1 Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
cooler 2818/2817
2nd Stage Compressor & After
495 LCOM LCOM-PG-128-D-8" PIPING FROM E-1300B TO SDV-2827 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
cooler
496 LCOM 1st Stage Compressor LCOM-PG-129-B-4" PIPING FROM PG-129-B-6" TO FV-0213B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
497 LCOM 1st Stage Compressor LCOM-PG-129-B-6" PIPING FROM 05-16-C1-8" TO PG-129-B-4" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
498 LCOM 1st Stage Compressor LCOM-PG-130-A-4" PIPING FROM FV-0213B TO PG-130-A-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
499 LCOM 1st Stage Compressor LCOM-PG-130-A-6" PIPING FROM PG-130-A-4" TO PG-130-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
500 LCOM 1st Stage Compressor LCOM-PG-130-A-8" PIPING FROM PG-130-A-6" TO V-102-B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
501 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-131-B-1" PIPING FROM V-1100B TO PSV-1104B/1105B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2nd Stage Compressor & After
502 LCOM LCOM-PG-132-D-3" PIPING FROM PG-132-D-2" TO FV-2803 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
cooler
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
503 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PG-133-B-6" PIPING FROM FV-2B03 TO PG-124-B-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
2nd Stage Compressor & After
504 LCOM LCOM-PG-140-D-2" PIPING FROM PG-128-D-8" TO VALVE 2 DSR Detail Assestment Insignificant 2010 2010 Close Visual Inspection
cooler
2nd Stage Compressor & After
505 LCOM LCOM-PG-141-D-2" PIPING FROM PG-128-D-8" TO VALVE 2 DSR Detail Assestment Insignificant 2010 2010 Close Visual Inspection
cooler
506 LCOM Compressor Suction Drum LCOM-PG-142-A-1" PIPING FROM PG-100-A-18" TO BDV 0227 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
507 LCOM Module Discharge Valving LCOM-PG-201-A-6" PIPING FROM PSV-0208A1 TO 05-21-A1-18" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
508 LCOM Module Discharge Valving LCOM-PG-202-A-6" PIPING FROM PSV-0208A2 TO 05-21-A1-18" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
509 LCOM Module Discharge Valving LCOM-PG-225-A-1" PIPING FROM BDV-0227 TO 05-21-A1-18" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
510 LCOM Fuel Gas System Compressor Module LCOM-PL-311B-6"-IC PIPING FROM CAP TO 05-29-C1-6"-IC Preventive Maintenance Corrosion Under Insulation, Insignificant 2015 2012 Close Visual Inspection
511 LCOM Compressor Suction Drum LCOM-PL-301-A-2" PIPING FROM PL-301-B-2" TO 05-74-A1-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
512 LCOM 1st Stage Compressor LCOM-PL-301-B-2" PIPING FROM 05-604-B-2 TO PL-301-A-2" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
513 LCOM 1st Stage Compressor LCOM-PL-302-B-2"(I) PIPING FROM PL-301-B-2 TO BOLD VALVE 2" B2RF Detail Assestment Insignificant 2010 2010 Close Visual Inspection
514 LCOM 1st Stage Compressor LCOM-PL-302-B-2"(II) FROM BALL VALVE B2RF / BALL VALVE B4R TO PL-3 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
515 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-305-D-4"(II) NG FROM BALL VALVE 4D2R / PL-305-D-6" TO SDV-11 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
516 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-305-D-4"(III) IPING FROM SDV-1102A TO GATE VALVE / PL-306-B- Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
517 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-307-D-4"(I) PIPING FROM SDV-102B TO BALL VALVE 4" D4R Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
518 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-307-D-4"(II) PIPING FROM BALL VALVE 4" D2R TO SDV-102B Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
519 LCOM 1st Disch. Cooler/2nd Suct. Scrub. LCOM-PL-308-D-4" PIPING FROM BALL VALVE 4" D2R TO PG-124-B-8" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
520 LCOM Module Discharge Valving LCOM-R-119-A1-1" PIPING FROM PSV-058 TO R-200-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
521 LCOM 1st Stage Compressor LCOM-R-203-A-2" PIPING FROM PSV-0209A1 TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
522 LCOM 1st Stage Compressor LCOM-R-204-A-2" PIPING FROM PSV-0209A2 TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
523 LCOM Module Discharge Valving LCOM-R-205-A-2" PIPING FROM PSV-1104A TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
524 LCOM Module Discharge Valving LCOM-R-206-A-2" PIPING FROM PSV-1105A TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
525 LCOM 2nd Stage Compressor & After Cooler LCOM-R-207-A-4" PIPING FROM PSV-2A18/2A17 TO 05-24-A1-4" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection

526 LCOM 2nd Stage Compressor & After Cooler LCOM-R-209-A-2" G FR BOLD VALVE TO WELD CAP/VAL D2ZOS/05-21-A Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
527 LCOM Module Discharge Valving LCOM-R-210-A-2" PIPING FROM PSV-0209B1 TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
528 LCOM Module Discharge Valving LCOM-R-211-A-2" PIPING FROM PSV-0209B2 TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
529 LCOM Module Discharge Valving LCOM-R-212-A-2" PIPING FROM PSV-1104B TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
530 LCOM Module Discharge Valving LCOM-R-213-A-2" PIPING FROM PSV-1105B TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
531 LCOM Module Discharge Valving LCOM-R-215-A-4" PIPING FROM PSV-2B17 TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
532 LCOM Module Discharge Valving LCOM-R-217-A-2" PIPING FROM BOLD VALVE 2D2R TO R-200-A-8" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
533 LCOM Module Discharge Valving LCOM-R-218-A-2" PIPING FROM PSV-0310A TO R-207-A-4" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
Seawater/Gas Exchanger, Gas/Gas
534 LCOM LCOM-R-219-A-2" PIPING FROM PSV-0310B TO R-207-A-4" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
Exch., Residue Gas Separator
535 LCOM Module Discharge Valving LCOM-R-214-A-4" PIPING FROM PSV-2B18 TO R-200-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
536 LCOM Module Discharge Valving LCOM-R-220-A-2" PIPING FROM PSV-0309A TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
537 LCOM Module Discharge Valving LCOM-R-221-A-2" PIPING FROM PSV-0309B TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
538 LCOM Module Discharge Valving LCOM-R-222-A-4" PIPING FROM PSV-0311A TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
539 LCOM Module Discharge Valving LCOM-R-223-A-4" PIPING FROM PSV-0311B TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
540 LCOM Module Discharge Valving LCOM-R-224-A-2" PIPING FROM BDV 0312 TO R-200-A-8" Preventive Maintenance Insignificant 2010 2010 Close Visual Inspection
541 LCOM Module Discharge Valving LCOM-R-226-A-2" PIPING FROM BDV 0333 TO R-200-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
542 LPRO LPRO-05-02A10-2"(I) PIPING FROM 05-02A1-4" TO GLOBE VALVE 2" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
543 LPRO LPRO-05-02A10-2"(II) PIPING FROM GLOBE VALVE 2" TO 05-02A1 (A)-4" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
544 LPRO LPRO-05-02A1-4"(I) PIPING FROM GLOBE VALVE 4" TO 05-C-4A Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
545 LPRO LPRO-05-02A1A-4"(II) PIPING FROM 05-C-4A TO 05-73-A1-4" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
546 LPRO LPRO-05-03A10-2"(I) PIPING FROM 05-103AI-4" TO GLOBE VALVE Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
547 LPRO LPRO-05-03A10-2"(II) PIPING FROM GLOBE VALVE TO 05-101A1-3" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
548 LPRO LPRO-05-101A1-3" PIPING FROM 05-C-4B TO 05-73A1-4" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
549 LPRO LPRO-05-103A1-4" PIPING FROM GLOBE VALVE TO 05-C-4B Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
550 LPRO "L" Process Platform LPRO-05-129A1-6"(I) PIPING FROM PSV-579 TO 05-55A1-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
551 LPRO "L" Process Platform LPRO-05-129A1-6"(II) PIPING FROM 05-80A1-8" TO PSV-579 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
552 LPRO LPRO-05-73A1-4"-FDG-ISOM BLIND FLANGE/05-101-A1-3''/05-02A1-4'' FDG TO 0 Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
553 LPRO LPRO-05-78A1-4"-IS PIPING FROM 05-73A1-4" - IS TO 05-01A1-18" Detail Assestment Corrosion Under Insulation 2010 2010 Close Visual Inspection
554 LPRO Flare, Drain System & Fire Utility LPRO-05-80A1-8"(I) PIPING FROM PV-502/GATE VALVE TO 05-55A1-10" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
555 LPRO Flare, Drain System & Fire Utility LPRO-05-80A1-8"(II) PIPING FROM LPV-8 TO PV-502/GATE VALVE Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
556 LPRO Flare, Drain System & Fire Utility LPRO-05-82A1-4" PIPING FROM LPV-8 TO GLOBE VALVE 4"/WELD CAP Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
557 LPRO Flare, Drain System & Fire Utility LPRO-P-114A-16" PIPING FROM BLIND FLANGE/FLA LPV-8 TO LP FLARE Detail Assestment Insignificant 2010 2010 Close Visual Inspection
558 LPRO Production separator LPRO-F-103E-12"(I) PIPING FROM P-103E-12" TO VALVE Detail Assestment Insignificant 2010 2010 Close Visual Inspection
559 LPRO Production separator LPRO-F-103E-12"(II) PIPING FROM F-103E-12" TO F-103E-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
560 LPRO Production separator LPRO-F-103E-8" PIPING FROM F-103E-12" TO SDV NC Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
561 LPRO LPRO-P-0001-A-4" PIPING FROM P-109-B-10" TO P-109-B-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
562 LPRO "L" Process Platform LPRO-P100F-8" PIPING FROM LA P/F TO P 100P-8"/NO VALVE SP/P4 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
563 LPRO Production Separator LPRO-P101E-8"(I) PIPING FROM NO VALVE SP/P4 TO VALVE 8A2R Detail Assestment Insignificant 2010 2010 Close Visual Inspection
564 LPRO Production Separator LPRO-P101E-8"(II) PIPING FROM VALVE 8A2R TO PL 101E-12" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
565 LPRO Receivers & Launcher LPRO-P101E-12"(I) PIPING FROM NO VALVE 12" F2RF TO NC VALVE Detail Assestment Insignificant 2015 2012 Close Visual Inspection
566 LPRO Receivers & Launcher LPRO-P101E-12"(II) ING FROM 12" NC VALVE TO LC LPV-2C-V/12" NC VA Detail Assestment Insignificant 2015 2012 Close Visual Inspection
567 LPRO Receivers & Launcher LPRO-P101E-12"(III) FROM BALL VALVE 12"/GATE VALVE 12" TO CRUDE Detail Assestment Insignificant 2015 2012 Close Visual Inspection
568 LPRO Receivers & Launcher LPRO-P101E-12"(IV) PIPING FROM P 101-8 (B) TO P 106A-12" Detail Assestment Insignificant 2015 2012 Close Visual Inspection
569 LPRO Production Separator LPRO-P101E-8"(I) PIPING FROM P-101E-12" TO BALL VALVE NC 2" F2RF Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
570 LPRO Production Separator LPRO-P101E-8"(II) PING FROM BALL VALVE NC 2" F2RF TO P 101E-12" ( Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
571 LPRO Production separator LPRO-P101E-8"(I) PIPING FROM BALL VALVE NC 8" TO P 101E-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
572 LPRO Production separator LPRO-P101E-8"(II) PIPING FROM P 101E-12" (A) TO BALL VALVE NC 8" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
573 LPRO Production separator LPRO-P101E-8"(III) PIPING FROM BALL VALVE NC 8" TO P 101E-12" (C) Detail Assestment Insignificant 2015 2012 Close Visual Inspection
574 LPRO Production separator LPRO-P102B-8" PIPING FROM P 102E-12" TO BALL VALVE NC Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
575 LPRO Production separator LPRO-P102E-12" PIPING FROM BLIND FLANGE TO P -125-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
576 LPRO Production separator LPRO-P-103E-12" PIPING FROM P-103E-14" TO F-103E-12" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
577 LPRO "L" Process Platform LPRO-P105A-6" PIPING FROM LA P/F TO P 105A-12" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
578 LPRO KO Drum & Atmospheric Separator LPRO-P-107-A-10" PIPING FROM P-147-A-10" TO P-108-A-10'' Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
579 LPRO Transmission Pumps LPRO-P-107-B-10" PIPING FROM P-147-A-10" TO P-109-B-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
Transmission Pumps, KO Drum &
580 LPRO LPRO-P-108-A-10" PIPING FROM LPV-6 TO P-107-A-10''/LPP-1C Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Atmospheric Separator
581 LPRO Transmission Pumps LPRO-P-109-B-10" PIPING FROM RED 10 X 6 TO P-109-B-14'' Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
Production separator, Flare, Drain
582 LPRO LPRO-P-111A-20" PIPING FROM 05-21AI-18" TO HP FLARE Preventive Maintenance Atmospheric Corrosion 2015 2012 Close Visual Inspection
System & Fire Utility
583 LPRO Piping Line LPRO-P-112A-4" PIPING FROM LA P/F DRAIN TO P 112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
Production separator, Flare, Drain
584 LPRO LPRO-P112A-6" IPING FROM BLIND FLANGE TO BLIND FLANGE LPM- Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
System & Fire Utility

585 LPRO Flare, Drain System & Fire Utility LPRO-P-112A-3" PIPING FROM S-124A-3" TO P-122-A-6" Preventive Maintenance Atmospheric Corrosion, Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
Production
P d i separator, Fl Flare, D
Drain
i
586 LPRO LPRO-P113A-6" PIPING FROM WELD CAP TO LPV-7 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
System & Fire Utility
587 LPRO "L" Process Platform LPRO-P-113L-1 1/2" G FROM REDUCER 2" X 1.5" TO CELLAR DECK/MAIN Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
588 LPRO "L" Process Platform LPRO-P-113L-2" PIPING FROM P-113-L-4" TO REDUCER 2" X 1.5" Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
589 LPRO Flare, Drain System & Fire Utility LPRO-P-113L-4" PIPING FROM P-174-L-6" TO P-113L-2" Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
590 LPRO Flare, Drain System & Fire Utility LPRO-P-114-A-16" PIPING FROM WELD CAP TO LPV-8 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
591 LPRO "L" Process Platform LPRO-P122A-2" PIPING FROM LA P/F WATER TO P 112A-6" Preventive Maintenance Atmospheric Corrosion, Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

592 LPRO Production separator LPRO-P124A-4"(I) PIPING FROM LPV-2A-V TO P 112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

593 LPRO Production separator LPRO-P124A-4"(II) PIPING FROM LPV 2 TO LPV-2A V Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

594 LPRO Production separator LPRO-P125A-4"(I) PIPING FROM BALL VALVE LC TO P 112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

595 LPRO Production separator LPRO-P125A-4"(II) PIPING FROM LPV 2 TO BALL VALVE-LC 4" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
596 LPRO Production separator LPRO-P125-A-8" PIPING FROM P-102E-12" TO P -102E-12" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
597 LPRO Production separator LPRO-P126-12" PIPING FROM LPV-2 TO PCV-LPV-2 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
598 LPRO Production separator LPRO-P126A-1"(I) PIPING FROM P 126A-12" TO BALL VALVE 1" D2S Detail Assestment Insignificant 2010 2010 Close Visual Inspection
599 LPRO Production separator LPRO-P126A-1"(II) PIPING FROM BALL VALVE 1" D2S TO P 127A-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
600 LPRO Production separator LPRO-P126A-2" PIPING FROM P 126A-12" TO PCV-LPV-2 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
601 LPRO Production separator LPRO-P126A-8" PIPING FROM P-126A-12" TO BALL VALVE 8" A2RF Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
602 LPRO Production separator LPRO-P127A-2" PIPING FROM PCV-LPV-2 TO P 113A-6" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
603 LPRO Production separator LPRO-P128A-4" PIPING FROM LPV-2 TO PSV LPV-2A Detail Assestment Insignificant 2010 2010 Close Visual Inspection
604 LPRO Production separator LPRO-P-129A-4"(I) PIPING FROM LPV-3 TO NC VALVE 4" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

605 LPRO Production separator LPRO-P-129A-4"(II) PIPING FROM NC VALVE 4" A2R TO P-112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

606 LPRO Production Separator LPRO-P-130A-4"(I) PIPING FROM LPV-3 TO VALVE 4" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

607 LPRO Production Separator LPRO-P-130A-4"(II) PIPING FROM VALVE 4" A2R TO P-112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
608 LPRO Production separator LPRO-P-132A-12" PIPING FROM LPV-3 TO P-132A-2"/P-132A-4" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
609 LPRO Production separator LPRO-P-132A-2"(I) PING FROM P-132A-12" TO BALL VALVE D2RF/P 132A Detail Assestment Insignificant 2010 2010 Close Visual Inspection
610 LPRO Production separator LPRO-P-132A-2"(II) PIPING FROM BALL VALVE D2RF TO P-113A-6" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
611 LPRO Production separator LPRO-P-132A-2"(III) PIPING FROM BALL VALVE D2RF TO PCV LPV-3 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
612 LPRO Production separator LPRO-P-132A-2"(IV) PIPING FROM PCV LPV-3 TO BALL VALVE D2RF 2' Detail Assestment Insignificant 2010 2010 Close Visual Inspection
613 LPRO Production separator LPRO-P-134A-4" PIPING FROM LPV-3 TO PSV-LPV-3A Detail Assestment Insignificant 2010 2010 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
614 LPRO KO Drum & Atmospheric Separator LPRO-P-146-A-4"(I) PIPING FROM BALL VALVE (L) 4" A2R TO P-112-A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

615 LPRO KO Drum & Atmospheric Separator LPRO-P-146-A-4"(II) PIPING FROM LPV-5 TO BALL VALVE (LC) 4" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
616 LPRO KO Drum & Atmospheric Separator LPRO-P-147-A-10" PIPING FROM LPV-5 TO LPP-1A Detail Assestment Insignificant 2010 2010 Close Visual Inspection
617 LPRO KO Drum & Atmospheric Separator LPRO-P-147-A-2"(I) PIPING FROM BALL VALVE (LC) 2" A2R TO P-112-A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

618 LPRO KO Drum & Atmospheric Separator LPRO-P-147-A-2"(II) PIPING FROM LPV-5 TO BALL VALVE (LC) 2" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
619 LPRO KO Drum & Atmospheric Separator LPRO-P-148-A-12"(I) PIPING FROM BALL VALVE 12" A2RF TO P-114-A-16" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
620 LPRO Flare, Drain System & Fire Utility LPRO-P154A-2"(I) PIPING FROM LPV-7 TO BALL VALVE 2" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

621 LPRO Flare, Drain System & Fire Utility LPRO-P154A-2"(II) PIPING FROM BALL VALVE 2" A2R TO LC-LPV-7 Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

622 LPRO Flare, Drain System & Fire Utility LPRO-P154A-2"(III) PIPING FROM LC-LPV-7 TO BALL VALVE 2" A2R Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

623 LPRO Flare, Drain System & Fire Utility LPRO-P154A-2"(IV) PIPING FROM BALL VALVE TO REDUCER 3 X 2 Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

624 LPRO Flare, Drain System & Fire Utility LPRO-P154A-3" PIPING FROM REDUCER 3" X 2" TO P 112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
625 LPRO Flare, Drain System & Fire Utility LPRO-P155A-6" PIPING FROM LPV-7 TO S119A Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
626 LPRO Flare, Drain System & Fire Utility LPRO-P156A-1" PIPING FROM P-156A-2" TO PSV-LPV-7 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
627 LPRO Flare, Drain System & Fire Utility LPRO-P156A-2" PIPING FROM LPV-7 TO REDUCER 2 X 1 Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
628 LPRO Flare, Drain System & Fire Utility LPRO-P157A-2"(I) PIPING FROM LC LPV-8V TO P 112A-6" Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

629 LPRO Flare, Drain System & Fire Utility LPRO-P157A-2"(II) PIPING FROM BALL VALVE (NC) TO REDUCER 3 X 2 Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

630 LPRO Fl
Flare, Drain
D i S System
t & Fire
Fi Utility
Utilit LPRO P157A 2"(III)
LPRO-P157A-2"(III) NG FROM LPV-8
LPV 8 TO LC LPV 8V/BALL VALVE (NC) 2" A Preventive
LC-LPV-8V/BALL P ti M Maintenance
i t Mi bi l IInduced
Microbial d dCCorrosion
i 2015 2012 Ult
Ultrasonic
i IInspection
ti scanning
i
631 LPRO KO Drum & Atmospheric Separator LPRO-P-158A-2" PIPING FROM SUMP PUMP TO P-106A-12"/P-105A-12" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
632 LPRO Piping Line LPRO-P-159-A-1" PIPING FROM P-169A-1 TO S-119A-1" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
633 LPRO Flare, Drain System & Fire Utility LPRO-P-160A-1"(I) G FROM P-155-A-6" TO PCV-LPM1B/PCV-LPM-1C GAT Detail Assestment Insignificant 2010 2010 Close Visual Inspection
634 LPRO Flare, Drain System & Fire Utility LPRO-P-160A-1"(II) PIPING FROM PCV-LPM-1B TO # LPM-1 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
635 LPRO Flare, Drain System & Fire Utility LPRO-P164A-4" PIPING FROM AUTOMATIC PUMP TO P 112A-6" Detail Assestment Microbial Induced Corrosion 2010 2010 Ultrasonic Inspection scanning

636 LPRO Flare, Drain System & Fire Utility LPRO-P165A-2"(I) PIPING FROM AUTOMATIC PUMP TO P 164A-4" Detail Assestment Microbial Induced Corrosion 2010 2010 Ultrasonic Inspection scanning

637 LPRO Flare, Drain System & Fire Utility LPRO-P165A-2"(II) M TOP CHORD OF BRIDGE TO BE LP FLARE LINE TO Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
638 LPRO Flare, Drain System & Fire Utility LPRO-P165A-4"(I) BOTTOM TWO CHARDS OF BRIDGE/ HP FLARE LINE Detail Assestment Insignificant 2010 2010 Close Visual Inspection
639 LPRO Flare, Drain System & Fire Utility LPRO-P165A-4"(II) PIPING FROM DISPOSAL TUBE TO FLA-LPP-4 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
640 LPRO Flare, Drain System & Fire Utility LPRO-P-166A-1 1/4" NG FROM P-166A/Y-2" TO DIESEL TRANFER PUMP (LP Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
641 LPRO Flare, Drain System & Fire Utility LPRO-P169A-1" PIPING FROM DIESEL TRANSFER PUMP TO P-159A-1 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
642 LPRO Flare, Drain System & Fire Utility LPRO-P-171-L-4" PIPING FROM S 103L-4" TO ??? Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
643 LPRO Flare, Drain System & Fire Utility LPRO-P-172-L-4" G FR P-104L-4" TO WELD CAP/DIESEL STR/PUMPING Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
644 LPRO Flare, Drain System & Fire Utility LPRO-P-174-L-6" NG FROM S 102L-4" TO P 176L-4"/??? PL-113L-4"/BL Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
645 LPRO Flare, Drain System & Fire Utility LPRO-P175U-3" PIPING FROM S-128U-3" TO P 175U-6" Preventive Maintenance Atmospheric Corrosion, Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning

646 LPRO Flare, Drain System & Fire Utility LPRO-P175U-6" PIPING FROM DISPOSAL TUBE TO BLIND FLANGE Preventive Maintenance Microbial Induced Corrosion 2015 2012 Ultrasonic Inspection scanning
647 LPRO Production separator LPRO-P-176-L-4" G FROM P-174L-6" TO BLIND FLANGE/BALL VALVE 1 Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
648 LPRO KO Drum & Atmospheric Separator LPRO-P-177-A-12" PIPING FROM PSE-LPV-5 TO P-114-A-16" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
649 LPRO KO Drum & Atmospheric Separator LPRO-P-178-A-10" PIPING FROM PSE-LPV-6A TO P-114-A-16" Preventive Maintenance Insignificant 2015 2012 Close Visual Inspection
650 LPRO Transmission Pumps LPRO-PL-A-4" PIPING FROM P-109-B-10" TO P-109-B-10" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
651 LPRO "L" Process Platform LPRO-S119A-6" PIPING FROM P-155-A-6" TO LSV-9 Detail Assestment Atmospheric Corrosion, Insignificant 2010 2010 Close Visual Inspection
652 LCOM Relief and Disposal System LCOM-05-104-A1-1" PIPING FROM BOLD VALVE 1D2Z (NC) TO VT-505-A-3 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
653 LCOM Fuel Gas System Compressor Module LCOM-05-108-A1-1" PIPING FROM BALL VALVE 1D2Z (NC) TO 05-104-A1-1 Detail Assestment Insignificant 2010 2010 Close Visual Inspection
654 LCOM Compressor Utilities LCOM-05-505-A-3" PIPING FROM VT-104-A1-1" TO VT-500-A-8" Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
655 LCOM Relief and Disposal System LCOM-05-509A-2" FR BALL VALVE 2" A2RF TO LP VENT HEADER 05-55 Detail Assestment Atmospheric Corrosion 2010 2010 Close Visual Inspection
656 LCOM Compressor Utilities LCOM-05-53-A1-6" NG FR STARTING GAS / VENT MIST EXT TO VT-508-A Detail Assestment Insignificant 2010 2010 Close Visual Inspection
657 LCOM Compressor Utilities LCOM-05-80-A1-6" ROM STARTING GAS VENT / MIST EXTRATING TO VT Detail Assestment Insignificant 2010 2010 Close Visual Inspection
658 LCOM Compressor Utilities LCOM-VT-500-A-8" PIPING FROM WELD CAP TO ATM Minimum Survaillance Atmospheric Corrosion 2021 2015 Close Visual Inspection
659 LCOM Compressor Utilities LCOM-VT-501-A-4" FROM LUBE OIL TANK VENT MIST EXTRACTOR TO B Detail Assestment Insignificant 2010 2010 Close Visual Inspection
660 LCOM Compressor Utilities LCOM-VT-501-A-6" PIPING FROM BLOWER TO ATM Detail Assestment Insignificant 2010 2010 Close Visual Inspection
661 LCOM Compressor Utilities LCOM-VT-502-A-4" FROM LUBE OIL TAN VENT MIST EXTRACTOR TO BL Detail Assestment Insignificant 2010 2010 Close Visual Inspection
APPENDIX D INSPECTION SCHEDULE
FOR RISK ASSESSMENT LIMA FIELD 2010
System Information Heading DNV Time Inspection Schedule
No. PLATFORM
Next Inspection Plan
System Name Tag Number Description Overall Risk Screening Degradation Mechanism Inspection Technique
Option #1 (SF: 1) Option #2 (SF: 2)
662 LCOM Compressor Utilities LCOM-VT-502-A-6" PIPING FROM BLOWER TO ATMS Detail Assestment Insignificant 2010 2010 Close Visual Inspection
663 LCOM Compressor Utilities LCOM-VT-503-A-2" PIPING FROM 05-C+A TO FLAME ARRESTOR Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
664 LCOM Compressor Utilities LCOM-VT-504-A-2" PIPING FROM 05-C-1B TO FLAME ARRESTOR Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
665 LCOM Module Discharge Valving LCOM-VT-505-A-3" PIPING FROM GESV-300C TO VT-500-A-8" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
666 LCOM 2nd Stage Compressor & After Cooler LCOM-VT-506-A-2" PIPING FROM BALL VALVE TO VT-505-A-3" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
667 LCOM Compressor Utilities LCOM-VT-507-A-2" PIPING FROM BALL VALVE 2D2R TO VT-507-A-2" Detail Assestment Insignificant 2010 2010 Close Visual Inspection
668 LCOM Compressor Utilities LCOM-VT-508-A-6"(I) PIPING FROM 05-53-A1-6" TO ATM Detail Assestment Insignificant 2010 2010 Close Visual Inspection
669 LCOM Compressor Utilities LCOM-VT-508-A-6"(II) PIPING FROM 05-80-A1-6" TO ATMS Detail Assestment Insignificant 2010 2010 Close Visual Inspection
670 LCOM Slug Catcher & receiver LCOM-05-305D1-2"(I) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
671 LCOM Slug Catcher & receiver LCOM-05-305D1-2"(II) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
672 LCOM Slug Catcher & receiver LCOM-05-305-D1-3"(I) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
673 L-COM Slug Catcher & receiver LCOM-05-305D1-3"(II) Minimum Survaillance Insignificant 2021 2015 Close Visual Inspection
674 LPRO Production Separator O-8" MOL 3 PHASE(P-100- LA TO LPRO (LPV2) [LPRO] Detail Assestment Insignificant 2010 2010 Close Visual Inspection