Anda di halaman 1dari 6

SUMMARY OF SUPPLEMENTARY SPECIFICATIONS

CLAUSES/SECTIONS

71.1 General
71.2 Scope Of Contract
71.3 Drawings
71.4 Control Clause

72.1 Steel Price Fluctuation


72.2 Assessment Of Extension Of Time Due To Exceptionally Inclement
Weather

72.aa * Bonus Scheme For Construction Quality (BSCQ)


72.bb * Phasing Of Works And Commencement Date For Phases Of Work
72.cc * Safety Measures At Handing-Over Stage And Site Work Phase
72.dd * Prefabricated Workers' Quarters
72.ee * Workers' Quarters And TOL Fee For Land Outside Contract Boundary
72.ff * No Preparatory Works During The Night Or On Sunday Or
On Public Holiday
72.gg * Hacking Of Concrete
72.hh * Completion Of Part Of Siteworks Together With Each Building Block
72.ii * Employment Of Contractor's Site Personnel
72.jj * Erection And Removal Of Temporary Metal Hoarding
72.kk * Protective Hoarding
72.ll * Survey Of As-Built Building Height

The contents of this summary on this page shall not be deemed to be part of the Specifications and
shall not be taken into consideration in the interpretation or construction thereof or of the Contract.

( * For drafting purposes : To delete where not applicable. )


SUMMARY OF SUPPLEMENTARY SPECIFICATIONS
CLAUSES/SECTIONS
(CONT'D)

73.1 Testing Of Material


73.2 Provision Of Warranty
73.3 Piling Works To Linkways And Precinct Pavilions
73.4a * Optional Component Scheme For Provision Of Internal Doors And
Floor Finishes To Living Rooms, Bedrooms And Household
Shelters
73.4b * Optional Component Scheme For Provision Of Internal Doors
73.5 Glazed Ceramic Floor Tiles To Living Room And Bedroom – General
73.6 Supply Of Precast Concrete Components

73.aa Reserved
73.bb * Facing Clay Bricks
73.cc * Profiled Steel Roofing Sheets
73.dd * Aluminium False Ceiling For First Storey Lift Lobby
73.ee * Illuminated Estate Block Number Signage
73.ff * Fixing Of Metal Sun-Breakers
73.gg * Lightning Protection To Metallic Roofing System, Wall Cladding And
Metallic Motifs
73.hh * Fluorocarbon Coated Perforated Aluminium Sunbreakers
73.ii * Powder Coated Extruded Aluminium Framed Windows, Openable
Windows, Vents, Fixed Glass Panels, Aluminium Swing Doors
And Aluminium Framed Sliding Doors
73.jj * Laminated Safety Glass For Fixed Panels Below Cill Height
73.kk * Timber Strip Floor And Timber Skirting
73.ll * Glazed Porcelain Ceramic Floor Tiles For Living Rooms, Dining Rooms
And Household Shelter With Door Facing Living Rooms And Dining
Rooms

The contents of this summary on this page shall not be deemed to be part of the Specifications and
shall not be taken into consideration in the interpretation or construction thereof or of the Contract.

( * For drafting purposes : To delete where not applicable. )


SUMMARY OF SUPPLEMENTARY SPECIFICATIONS
CLAUSES/SECTIONS
(CONT'D)

73.mm * Glazed Porcelain Ceramic Floor Tiles For Kitchen, Service Yards And
Household Shelter With Door Facing Kitchen
73.nn * Ceramic Floor Tiles For Bath/WC And WC
73.oo * Schedule Of Ceramic Floor Tiles To Kitchen, Bath/WC, WC, Service
Yards And Household Shelter With Door Facing Kitchen
73.pp * Timber Door With High Pressure Plastic Laminate Finish To Bath/WC
(For 3-Room, 4-Room And 5-Room Flats)
73.qq * Solid Timber Veneered Doors With Decorative Inlay To Bedroom
73.rr. * Ironmongery For Solid Timber Veneered Bedroom Doors With
Decorative Inlays
73.ss * Perimeter Joints For Floor Tiles
73.tt * Aluminium Bi-Fold Sliding Door

74.1 *
75.1 *
76.1 *

The contents of this summary on this page shall not be deemed to be part of the Specifications and
shall not be taken into consideration in the interpretation or construction thereof or of the Contract.

( * For drafting purposes : To delete where not applicable. )


BSS S71
71-1 of 71-3

HOUSING & DEVELOPMENT BOARD

SECTION 71

71.0 SUPPLEMENTARY SPECIFICATIONS FOR BUILDING AND


ELECTRICAL WORKS
AT___________________________________________________

___________________________________________________________
__

71.1 GENERAL

Supplementary Specifications Sections 71, 72, 73, 74*, 75* and 76* shall
be read in conjunction with the Standard Specifications For Building
Works And Other Installations (2009 Edition). In case of discrepancies
between the Supplementary Specifications and the Standard
Specifications, the Supplementary Specifications shall prevail.

71.2 SCOPE OF CONTRACT

The Works included in this Contract shall be the #Construction,


Completion and Maintenance of :

(a)

Model `A' Imp Executive


Bldg No. Total
4-Rm 5-Rm 5-Rm Apt Mai SH/ EH/
Blk of No. of Remarks
1st 1st 1st 1st LQ LQ
No. Sty Typ Typ Typ Typ Typ DU
Sty Sty Sty Sty

Total

( # Include Design if so applicable. )


( * For drafting purposes : Delete if not applicable. )

BLDG09/S71.DOC(1)
OCO(010109)
(DPD)
BSS S71
71-2 of 71-3

71.2 SCOPE OF CONTRACT (CONT'D)

*(b) storey garage/carpark at Block including .

*(c) Sanitary, Water and Other Installations.

*(d) Electrical, Mechanical and Other Installations.

*(e) Precinct Pavilion(s) and Linkway(s).

*(f) Children Playground Type .

(g) General Siteworks including Trimming, Forming Embankments and


Earthmounds, Turfing, Footpaths, Steps, etc.

(h) Underground Pipe System For LT Reticulation Cables And


Telecommunication Cables.

*(i) Provisional Sum(s) and PC Sum(s)*

~(j)

~(k)

~(l)

and other Works required under the Contract.

( * For drafting purposes : Delete if not applicable. )


( ~ For drafting purposes : To include where applicable. )

BLDG09/S71.DOC(2)
OCO(010109)
(DPD)
BSS S71
71-3 of 71-3

71.3 DRAWINGS

71.3.1 The Drawings referred to in the Contract shall be as listed in the Schedule
of Drawings issued by the Employer, including any modifications of such
Drawings approved in writing by the Superintending Officer or the SO Rep
and such other drawings as may from time to time be issued or approved
in writing by the Superintending Officer or the SO Rep.

71.3.2 Where the Standard Architectural Construction Details Manual, Standard


Structural Details Manual, Standard Electrical Drawings Manual and
Standard Civil Engineering Construction Details Manual (hereinafter
referred to as "Manuals" for the purpose of this subclause), are specified
in the Schedule of Drawings, such Manuals shall form part of the Contract
and shall be read in conjunction with the other Drawings referred to in the
Contract. In a case of discrepancies between such Manuals and the other
Drawings referred to in the Contract, the latter shall prevail.

The standard construction detail or details in respect of an item of work


contained in the above-mentioned Manuals shall apply in so far as such
an item of work is part of the Works under the Contract.

71.4 CONTROL CLAUSE

(A) The following Specifications shall be applicable to this Contract :

(a) Standard Specifications For Building Works And


Other Installations (2009 Edition)

(b) *Standard Specifications For Civil Engineering Works


(2009 Edition)

(c) Supplementary Specifications Section 71, 72, 73, 74*,


75* and 76*.

(B) * The following Section(s) of the Standard Specifications shall not be


applicable to this Contract :

(a) ~
(b) ~

( * For drafting purposes: Delete if not applicable. )


( ~ For drafting purposes: To include where applicable. )

BSS S72/....

BLDG09/S71.DOC(3)
OCO(010109)
(DPD)

Anda mungkin juga menyukai