Anda di halaman 1dari 1

PT. WASKITA KARYA (Persero) Form .

Prod 01-1
Tbk Edisi : Mei 2020 Rev : 01

DIVISI : …………………..

PROYEK : …………………..

LOKASI : …………………..

NO. AB : …………………..

LAPORAN BULAN : …………………. LAPORAN EVALUASI BEBAN DI PEKERJAAN


BAHAN, UPAH, SUB KONTRAKTOR DAN PERALATAN
BY SISTEM
KODE KODE RAB MACAM PEKERJAAN VOLUME HARGA SATUAN DAN JUMLAH HARGA ESTIMASI EVALUASI
AK (WBS) (PAY ITEM) Unit/ Sesuai Periode Sisa Est. Sisa APP Periode s/d bl ini Est. sisa s/d selesai S/D SELESAI (%)
Sat APP s/d bl ini APP s/d sls H.Sat Jumlah Jumlah H.Sat H.Sat Jumlah Volume Jumlah H.Sat Beban Progres
1 2 3 4 5 6 7=5-6 8=15-6 9 10=5x9 11 12=11/6 13 14=8x13 15=6+8 16=11+14 17=16/15 18=11/10 19=6/15
3 PEK. STRUKTUR
3.1 PEKERJAAN LANTAI 1
3.1.1 KOLOM
3.1.1.1 Beton K-300 M3 3,000 1,300 1,700 1,800 2,914,700 ### 3,763,461,000 2,894,970 2,927,450 ### 3,100 ### 2,913,829 43.040% 41.9%
610.111 BAHAN : ### 3,353,311,000 ### ###
1 Semen Zak 30,000 13,000 17,000 18,000 55,000 ### 741,000,000 57,000 57,600 ### 31,000 ### 57,348
2 Pasir beton M3 1,620 702 918 972 150,000 243,000,000 103,896,000 148,000 160,000 155,520,000 1,674 259,416,000 154,968
3 Split M3 2,400 1040 1,360 1,440 225,000 540,000,000 208,000,000 200,000 225,000 324,000,000 2,480 532,000,000 214,516
4 Besi beton D 22 Kg ### 273,000 357,000 ### 7,050.00 ### 1,924,650,000 7,050 7,050 ### 651,000 ### 7,050
5 Besi beton ø 8 Kg ### 52,000 68,000 72,000 7,050.00 846,000,000 366,600,000 7,050 7,050 507,600,000 124,000 874,200,000 7,050
6 Besi beton D 19 Kg - 1,300 0 1,800 0.00 0 9,165,000 7,050 7,050 12,690,000 3,100 21,855,000 7,050

610.112 UPAH ### 410,150,000 567,900,000 978,050,000


1 Bekisting M2 1,800 780 1,020 1,080 77,000 138,600,000 62,400,000 80,000 80,000 86,400,000 1,860 148,800,000 80,000
2 Pembesian Kg ### 325,000 425,000 ### 800 600,000,000 230,750,000 710 710 319,500,000 775,000 550,250,000 710
3 Pengecoran M3 3,000 1,300 1,700 1,800 95,000 285,000,000 117,000,000 90,000 90,000 162,000,000 3,100 279,000,000 90,000

610.113 SUBKON : ……………

CONTOH
610.114 PERALATAN : ……………
diambil dari diambil dari
Kartu Kartu
Rekapitulasi Rekapitulasi
PEKERJAAN : …………… Beban (KRB) Beban (KRB)
610.111 Bahan : ……………

dst dan seterusnya …….

...……….., ……………….
Diketahui / Disetujui, Dibuat oleh :
PM SEM/SCARM

.................................................... ....................................................