Rab Posyandu BHKNG
Rab Posyandu BHKNG
1 2 3 4 5
BAHAN BANGUNAN
1 Pasir pasang M³ Rp. 200,000-
2 ###Kerikil Zak Rp. 200,000-
3 Semen PC ( isi 40 Kg ) Gresik Bh Rp. 150,000-
4 Kayu Ulin
10/10 cm - 4 M Btg Rp. 90,000-
5/10 cm - 4 M Btg Rp. 60,000-
8/8 cm - 4 M Btg Rp. 75,000-
5/7 cm - 4 M Btg Rp. 40,000-
5/5 cm - 4 M Btg Rp. 30,000-
3/20 cm - 4 M Kpg Rp. 125,000-
2/20 cm - 4 M Kpg Rp. 60,000-
5 Kayu Meranti
10/10 cm - 4 M Btg Rp. 60,000-
5/10 cm - 4 M Btg Rp. 30,000-
8/8 cm - 4 M Btg Rp. 40,000-
5/7 cm - 4 M Btg Rp. 25,000-
5/5 cm - 4 M Btg Rp. 15,000-
3/5 cm - 4 M Kpg Rp. 10,000-
2/20 cm - 4 M Kpg Rp. 25,000-
6 Paku Kayu Kg Rp. 30,000-
7 Paku Ulin Kg Rp. 50,000-
8 Paku Triplek Kg Rp. 30,000-
9 Paku anti karat Kg Rp. 50,000-
10 Besi Beugel / Baut ( Kuda-kuda ) Kg Rp. 45,000-
11 Genteng metal Prima colour tebal 0,35 mm M² Rp. 95,000-
12 Bubungan Genteng metal M' Rp. 30,000-
13 Seng plat 3" x 6" BJLS 28 Lbr Rp. 60,000-
14 Plywood 3 mm Lbr Rp. 65,000-
15 Bak Mandi Fibreglass ukuran sedang Bh Rp. 200,000-
16 Closed jongkok porselen Bh Rp. 150,000-
17 Pipa PVC diameter 2" AW (Maspion) Btg Rp. 70,000-
18 Pipa PVC diameter 4" AW (Maspion) Btg Rp. 180,000-
19 Cat Kayu Mengkilat merk Platon Kg Rp. 60,000-
20 Cat Menie Kg Rp. 30,000-
21 Cat Dasar Kg Rp. 25,000-
22 Kran Air Kg Rp. 25,000-
23 Baut 10 cm s/d 24 cm Kg Rp. 20,000-
24 Minyak Cat ( Thiner A ) Ltr Rp. 25,000-
25 Hitachi Bh Rp. 600,000-
26 Sambungan, L, T, PVC Lbr Rp. 10,000-
27 Engsel jendela ( kualitas standart ) Bh Rp. 15,000-
28 Engsel pintu ( kualitas standart ) Bh Rp. 20,000-
29 Kunci tanam 2 slag Bh Rp. 150,000-
30 Kaca bening ukuran 3 mm M² Rp. 150,000-
31 Septicktank Unit Rp. 3,000,000-
1 2 3 4 5
UPAH
NO. URAIAN TENAGA SATUAN KET
HARIAN
1 2 3 4 5
1 2 3 4 5
TRIWULAN
TAHUN : 2009
ANALISA
HARGA
URAIAN PEKERJAAN UPAH BAHAH JUMLAH
SATUAN
( SNI )
1 2 3 4 5 6
PEKERJAAN PERSIAPAN
01.6.4 1 M' Pengukuran dan pasang bouwplank
0.0120 M³ Kasau 5/7 cm Rp. 60,000- Rp. 720-
0.0070 M³ Kayu papan 3/20 cm Rp. 25,000- Rp. 175-
0.0200 Kg Paku kayu 2" - 5" Rp. 30,000- Rp. 600-
0.1000 Pekerja Rp. 70,000- Rp. 7,000-
0.1000 Tukang kayu Rp. 90,000- Rp. 9,000-
Rp. 16,000- Rp. 1,495- Rp. 17,495-
PEKERJAAN TANAH
02.6.1 1 M³ Galian tanah biasa sedalam 1 meter.
0.4000 Pekerja Rp. 70,000- Rp. 28,000-
Rp. 28,000- Rp - Rp. 28,000-
02.6.9 1 M³ Urugan kembali
0.1920 Pekerja Rp. 70,000- Rp. 13,440-
Rp. 13,440- Rp - Rp. 13,440-
PEKERJAAN KAYU
06.6.8 1 M² Pasang pintu panel kayu lanan
0.0400 M³ Papan kayu lanan Rp. 25,000- Rp. 1,000-
1.0000 Pekerja Rp. 70,000- Rp. 70,000-
2.5000 Tukang kayu Rp. 90,000- Rp. 225,000-
Rp. 295,000- Rp. 1,000- Rp. 296,000-
06.6.9 1 M² Pasang pintu dan jendela kaca kayu ulin
0.0350 M³ Papan kayu ulin Rp. 60,000- Rp. 2,100-
0.8000 Pekerja Rp. 70,000- Rp. 56,000-
2.0000 Tukang kayu Rp. 90,000- Rp. 180,000-
Rp. 236,000- Rp. 2,100- Rp. 238,100-
06.6.28 1 M³ Pasang konstruksi kuda-kuda kayu lanan
1.100 M³ Balok kayu lanan Rp. 125,000- Rp. 137,500-
15.000 Kg Besi strip Rp. 45,000- Rp. 675,000-
0.800 Kg Paku biasa 2" - 5" Rp. 30,000- Rp. 24,000-
4.000 Pekerja Rp. 70,000- Rp. 280,000-
12.000 Tukang kayu Rp. 90,000- Rp. 1,080,000-
Rp. 1,360,000- Rp. 836,500- Rp. 2,196,500-
06.6.31 1 M² Pasang kasau + reng genteng metal kayu lanan
0.0120 M³ Balok kayu lanan Rp. 125,000- Rp. 1,500-
0.1500 Kg Paku biasa 2" - 5" Rp. 30,000- Rp. 4,500-
0.1000 Pekerja Rp. 70,000- Rp. 7,000-
0.1000 Tukang kayu Rp. 90,000- Rp. 9,000-
Rp. 16,000- Rp. 6,000- Rp. 22,000-
1 2 3 4 5 6
06.6.39 1 M² Pasang rangka langit-langit (60 x 120) cm kayu lanan
0.0120 M³ Balok kayu lanan Rp. 125,000- Rp. 1,500-
0.1000 Kg Paku biasa 2" - 5" Rp. 30,000- Rp. 3,000-
0.1500 Pekerja Rp. 70,000- Rp. 10,500-
0.2500 Tukang kayu Rp. 90,000- Rp. 22,500-
Rp. 33,000- Rp. 4,500- Rp. 37,500-
1 2 3 4 5 6
06.6.53a 1 M' Pasang lisplang ukuran (2 x 20 dan 2 x 10 ) cm, kayu Ulin
0.0090 M3 Papan kayu ulin Rp. 60,000- Rp. 540-
0.0500 Kg Paku ulin Rp. 50,000- Rp. 2,500-
0.1100 Pekerja Rp. 70,000- Rp. 7,700-
0.2200 Tukang kayu Rp. 90,000- Rp. 19,800-
Rp. 27,500- Rp. 3,040- Rp. 30,540-
06.6.60 1 M' Pasang list plafond kayu profil
1.0500 M' Kayu profil Rp. 15,000- Rp. 15,750-
0.0100 Kg Paku biasa Rp. 30,000- Rp. 300-
0.0210 Pekerja Rp. 70,000- Rp. 1,470-
0.0210 Tukang kayu Rp. 90,000- Rp. 1,890-
Rp. 3,360- Rp. 16,050- Rp. 19,410-
F.22 1 M³ Pekerjaan rangka badan bahan kayu ulin
1.1000 M³ Balok kayu ulin Rp - Rp -
6.0000 Kg Paku ulin Rp. 50,000- Rp. 300,000-
8.0000 Pekerja Rp. 70,000- Rp. 560,000-
24.000 Tukang kayu Rp. 90,000- Rp. 2,160,000-
Rp. 2,720,000- Rp. 300,000- Rp. 3,020,000-
F.38a 1 M² Lantai kayu ulin tebal 2 cm diserut rapi
0.0233 M³ Papan kayu ulin Rp. 60,000- Rp. 1,398-
0.2000 Kg Paku ulin Rp. 50,000- Rp. 10,000-
0.6000 Pekerja Rp. 70,000- Rp. 42,000-
1.8000 Tukang kayu Rp. 90,000- Rp. 162,000-
Upah 1/2 x F38 Rp. 102,000- Rp. 11,398- Rp. 113,398-
F.38e 1 M² Dinding kayu ulin tebal 2 cm diserut rapi
dengan sambungan lidah alur
0.0230 M³ Papan kayu ulin Rp. 60,000- Rp. 1,380-
0.2000 Kg Paku ulin Rp. 50,000- Rp. 10,000-
0.6000 Pekerja Rp. 70,000- Rp. 42,000-
1.8000 Tukang kayu Rp. 90,000- Rp. 162,000-
Upah 3/4 x F38e Rp. 153,000- Rp. 11,380- Rp. 164,380-
F.38f 1 M² Dinding kayu lanan tebal 2 cm diserut rapi
dengan sambungan lidah alur
0.0230 M³ Papan kayu lanan Rp. 25,000- Rp. 575-
0.2000 Kg Paku kayu Rp. 30,000- Rp. 6,000-
0.6000 Pekerja Rp. 70,000- Rp. 42,000-
1.8000 Tukang kayu Rp. 90,000- Rp. 162,000-
Upah 3/4 x F38f Rp. 153,000- Rp. 6,575- Rp. 159,575-
PEKERJAAN PENUTUP ATAP
08.6.32 1 M² Pasang atap genteng metal
1.0200 M² Gtg Prima colour tbl 0,35 mm Rp. 95,000- Rp. 96,900-
0.0750 Kg Paku anti karat Rp. 50,000- Rp. 3,750-
0.2000 Pekerja Rp. 70,000- Rp. 14,000-
0.1000 Tukang kayu Rp. 90,000- Rp. 9,000-
Genteng Prima colour tbl 0,35 mm ………………. Rp. 23,000- Rp. 100,650- Rp. 123,650-
08.6.33 160.0000
M² Pasang
0.2000
0.1660
0.2500
0.0250
0.0080 Kg atap
Lb Paku
Pekerja
Tukang
Kepala
Mandor sirap
Sirap sirap
kayu
tukang Rp.
Rp.
Rp 900-- Rp.
13,800-
70,000-
90,000- Rp.
Rp 11,620-- Rp.
22,500- 54,000-
2,760-
34,120- Rp. 56,760- Rp. 90,880-
08.6.36 1 M' Pasang nok genteng metal
1.0000 M' Bubungan metal Rp. 30,000- Rp. 30,000-
0.0075 Kg Paku anti karat Rp. 50,000- Rp. 375-
0.2500 Pekerja Rp. 70,000- Rp. 17,500-
0.1500 Tukang kayu Rp. 90,000- Rp. 13,500-
1 2 3 4 5 6
Rp. 31,000- Rp. 30,375- Rp. 61,375-
1 2 3 4 5 6
PEKERJAAN LANGIT - LANGIT.
09.6.10a 1 M² Langit-langit Plyawood (60 x 120) cm, tebal 3 mm.
0.3750 Lb Plyawood 3mm Rp. 65,000- Rp. 24,375-
0.0300 Kg Paku plywood Rp. 30,000- Rp. 900-
0.0700 Pekerja Rp. 70,000- Rp. 4,900-
0.1000 Tukang kayu Rp. 90,000- Rp. 9,000-
Rp. 13,900- Rp. 25,275- Rp. 39,175-
PEKERJAAN SANITASI.
10.6.3 Memasang 1 buah closed jongkok teraso
1.0000 Bh Closed jongkok teraso Rp. 150,000- Rp. 150,000-
7.0000 Bh Bata merah 5 x 11 x 22 cm Rp. 150,000- Rp. 1,050,000-
6.0000 Kg Semen PC Rp. 200,000- Rp. 1,200,000-
0.0100 M³ Pasir pasang Rp. 200,000- Rp. 2,000-
1.0000 Pekerja Rp. 70,000- Rp. 70,000-
1.5000 Tukang batu Rp. 90,000- Rp. 135,000-
Rp. 205,000- Rp. 2,402,000- Rp. 2,607,000-
10.6.6 Memasang 1 buah bak mandi teraso volume 0,30 m³
1.0000 Bh Bak teraso Rp. 200,000- Rp. 200,000-
6.0000 Kg Semen PC Rp. 200,000- Rp. 1,200,000-
0.0100 M³ Pasir pasang Rp. 200,000- Rp. 2,000-
2.1000 Pekerja Rp. 70,000- Rp. 147,000-
0.7500 Tukang batu Rp. 90,000- Rp. 67,500-
Rp. 214,500- Rp. 1,402,000- Rp. 1,616,500-
11.6.19 1 M' Pasang talang miring, seng BJLS 28
0.5000 Lbr Seng plat 3' x 6' BJLS 28 Rp. 60,000- Rp. 30,000-
0.0150 Kg Paku biasa ½" - 1" Rp. 30,000- Rp. 450-
0.0190 M³ Kayu borneo papan #REF! #REF!
0.0400 Pekerja Rp. 70,000- Rp. 2,800-
0.4000 Tukang kayu Rp. 90,000- Rp. 36,000-
Rp. 38,800- #REF! #REF!
PEKERJAAN KUNCI DAN KACA
12.6.2 1 Buah pasang kunci tanam biasa
1.0000 Bh Kunci tanam biasa Rp. 150,000- Rp. 150,000-
0.0100 Pekerja Rp. 70,000- Rp. 700-
0.5000 Tukang kayu Rp. 90,000- Rp. 45,000-
Rp. 45,700- Rp. 150,000- Rp. 195,700-
12.6.5 1 Buah pasang engsel pintu
1.0000 Bh Engsel pintu Rp. 20,000- Rp. 20,000-
0.0150 Pekerja Rp. 70,000- Rp. 1,050-
0.1500 Tukang kayu Rp. 90,000- Rp. 13,500-
Rp. 14,550- Rp. 20,000- Rp. 34,550-
12.6.6 1 Buah pasang engsel jendela kupu-kupu
1.0000 Bh Engsel jendela Rp. 15,000- Rp. 15,000-
0.0100 Pekerja Rp. 70,000- Rp. 700-
0.1000 Tukang kayu Rp. 90,000- Rp. 9,000-
Rp. 9,700- Rp. 15,000- Rp. 24,700-
12.6.17 1 M² pasang kaca, tebal 5 mm
1.1000 M² Kaca tebal 5 mm Rp. 150,000- Rp. 165,000-
0.0150 Pekerja Rp. 70,000- Rp. 1,050-
0.1500 Tukang kayu Rp. 90,000- Rp. 13,500-
1 2 3 4 5 6
Rp. 14,550- Rp. 165,000- Rp. 179,550-
1 2 3 4 5 6
PEKERJAAN PENGECATAN
14.6.6 1 M² Mendempul dan menggosok kayu
0.0800 Kg Dempul jadi Rp. 20,000- Rp. 1,600-
0.0200 Kg Minyak cat Rp. 25,000- Rp. 500-
0.0100 Kg Batu apung Rp. 10,000- Rp. 100-
0.0400 Pekerja Rp. 70,000- Rp. 2,800-
0.0400 Tukang cat Rp. 90,000- Rp. 3,600-
Rp. 6,400- Rp. 2,200- Rp. 8,600-
14.6.8 1 M² Pengecatan bidang kayu baru (1 lapis plamir,
1 lapis cat dasar, 2 lapis cat penutup)
0.2000 Kg Cat meni Rp. 30,000- Rp. 6,000-
0.1500 Kg Plamir Rp. 25,000- Rp. 3,750-
0.1700 Kg Cat dasar Rp. 25,000- Rp. 4,250-
0.2600 Kg Cat penutup Rp. 60,000- Rp. 15,600-
0.0700 Pekerja Rp. 70,000- Rp. 4,900-
0.0090 Tukang cat Rp. 90,000- Rp. 810-
Rp. 5,710- Rp. 29,600- Rp. 35,310-
14.6.12 1 M² Pelaburan bidang kayu dengan cat residu dan ter
0.3500 Ltr Ter atau residu Rp. 600,000- Rp. 210,000-
0.1000 Pekerja Rp. 70,000- Rp. 7,000-
Rp. 7,000- Rp. 210,000- Rp. 217,000-
14.6.14 1 M² Pengecatan bidang tembok baru (1 lapis plamir,
1 lapis cat dasar, 2 lapis cat penutup).
0.1000 Kg Plamir Rp. 25,000- Rp. 2,500-
0.1000 Kg Cat dasar Rp. 25,000- Rp. 2,500-
0.2600 Kg Cat penutup 2 x Rp. 60,000- Rp. 15,600-
0.0200 Pekerja Rp. 70,000- Rp. 1,400-
0.0630 Tukang cat Rp. 90,000- Rp. 5,670-
Rp. 7,070- Rp. 20,600- Rp. 27,670-
E.4 Membuat 1 Pasang Pen dan Lobang
0.6000 Tukang Kayu Rp. 90,000- Rp. 54,000-
Rp. 54,000- Rp. 54,000-
Upah x 1/4 Rp. 13,500- Rp. 13,500-
E.13 1 M' Tiang Dipancang kedalam Tanah
(Dihitung Bagian Yang Masuk )
0.6000 Pekerja Rp. 70,000- Rp. 42,000-
0.0400 Tukang Kayu Rp. 90,000- Rp. 3,600-
Rp. 45,600- Rp. 45,600-
Upah x 1/4 Rp. 11,400- Rp. 11,400-
11.2.6 1 M3 Pasang Gording Bahan Kayu Lanan
(Kayu Kls Kuat II) :
5.8000 Tukang Kayu Rp. 90,000- Rp. 522,000-
1.9400 Pekerja Rp. 70,000- Rp. 135,800-
1.1000 M3 Balok Lanan Rp. 125,000- Rp. 137,500- Rp. 137,500-
2.2000 Kg Paku Biasa (Paku Kayu) Rp. 30,000- Rp. 66,000- Rp. 66,000-
Rp - Rp. 203,500- Rp. 203,500-
11.2.4 1 M3 Kuda-Kuda Bentang 6 s/d 9 m
Kayu Lanan (Kayu Kls Kuat II) :
20.0000 Tukang Kayu Rp. 90,000- Rp. 1,800,000-
1 2 3 4 5 6
6.7000 Pekerja Rp. 70,000- Rp. 469,000-
1.1000 M3 Balok Lanan Rp. 125,000- Rp. 137,500- Rp. 137,500-
3.0000 Kg Paku Biasa Rp. 30,000- Rp. 90,000- Rp. 90,000-
15.0000 Kg Besi Strip/Mur Baut Rp. 45,000- Rp. 675,000- Rp. 675,000-
Rp - Rp. 902,500- Rp. 902,500-
Kabupaten : Katingan Jenis Prasarana : Posyandu
Kecamatan : Bukit Raya Take Of Sheet Tipe Konstruksi : Bgn Kayu
Desa : Rangan Bahekang Ukuran/Dimensi : 6.00 x 8.00 m
a b c
2. PEKERJAAN TANAH
2.a. Pekerjaan Penggalian Tanah Pondasi
Volume (((0.60+0.80)/2)x0.50) x ((8.40x7)+(3.40x2)) 22.96 meter kubik
Bahan :
- - -
Upah :
- Pekerja 0.4000 x 22.96 9.18 HOK
Upah :
- Pekerja 0.1920 x 17.22 3.31 HOK
3. PEKERJAAN PONDASI
Pondasi dari Bahan Tiang Pancang Kayu Ulin 10/10 cm
Volume : Bangunan Utama 8 x 7 = 56
: Bangunan Teras 4 x 2 = 8
- Total Tiang Pondasi Total Bahan = 64 64 Buah
Bahan :
- Balok Kayu Ulin 10/10 cm - 4.00 m 6 6 Buah
- Balok Kayu Ulin 10/10 cm - 2.00 m 64 - 6 58 Buah
dalam kubikan 0.1 x 0.1 x 4 x 6 0.24
0.1 x 0.1 x 2 x 58 1.16
Total Kubikan Kayu Ulin 10/10 cm 0.24 + 1.16 1.40 meter kubik
dlm Batang Kayu Ulin 10/10cm-4.00m 1.4 / ( 0.10 x 0.10 x 4.00 ) 35 batang
Upah :
-
Upah :
- Pekerja 8.0000 x 0.88 7.04 HOK
Upah :
- Tukang Kayu 24.0000 x 0.62 14.88 HOK
- Pekerja 8.0000 x 0.62 4.96 HOK
4.c. Pekerjaan Memasang Gelagar Balok Kayu Ulin 5/10 cm
Volume : Bangunan Utama 8.00 / 0.50 + 1 = 17
: Bangunan Teras 3.00 / 0.50 + 1 = 7
Total panjang bahan = 24
dalam kubik : 24.00 x 0.05 x 0.10 = 0.12 0.12 meter kubik
Bahan :
- Balok Kayu Ulin 5/10 cm - 4.00 m 1.1000 x 0.12 0.13 meter kubik
dalam batang 0.13 / 0.05 x 0.10 x 4.00 6.60 Batang
- Paku Ulin 6.0000 x 0.12 0.72 Kilogram
Upah :
- Tukang Kayu 24.0000 x 0.12 2.88 HOK
- Pekerja 8.0000 x 0.12 0.96 HOK
Upah :
- Tukang Kayu 24.0000 x 0.40 9.60 HOK
Upah :
- Tukang Kayu 24.000 x 0.36 8.64 HOK
Upah :
- Tukang Kayu 24.0000 x 0.48 11.52 HOK
5.d. Pekerjaan Malangan Kuzen Pintu/jendela Balok Kayu Ulin 5/10 cm
Volume
Pintu P1 : 1 buah 0.05 x 0.10 x 1.82 x 2 0.02
Pintu P2 : 3 Buah 0.05 x 0.10 x 0.92 x 6 0.03
Pintu P3 : 1 Buah 0.05 x 0.10 x 0.62 x 2 0.01
Jendela J1 : 4 Buah 0.05 x 0.10 x 0.72 x 24 0.09
Ventilasi V1 : 1 Buah 0.05 x 0.10 x 0.62 x 2 0.01
0.14 meter kubik
Bahan :
- Balok Kayu Ulin 5/10 cm - 4.00 m 1.1000 x 0.14 0.16 meter kubik
dalam batang 0.16 / 0.05 x 0.10 x 4.00 7.95 Batang
- Paku Ulin 6.0000 x 0.14 0.87 Kilogram
Upah :
- Tukang Kayu 24.0000 x 0.14 3.47 HOK
Upah :
- Tukang Kayu 24.0000 x 0.30 7.26 HOK
Bahan :
- Balok Kayu Lanan 6/12 cm - 4.00 m 1.1000 x 0.85 0.93 meter kubik
dalam batang 0.93 / 0.06 x 0.12 x 4.00 32.29 Batang
- Paku Biasa 3.0000 x 0.85 2.54 Kilogram
- Besi Strip/Baut-Mur 15.0000 x 0.85 12.68 Kilogram
Upah :
- Tukang Kayu 20.0000 x 0.85 16.91 HOK
- Pekerja 6.7000 x 0.85 5.66 HOK
Bahan :
- Balok Kayu Lanan 6/12 cm - 4.00 m 1.1000 x 0.73 0.80 meter kubik
dalam batang 0.80 / 0.06 x 0.12 x 4.00 27.73 Batang
- Paku Biasa 2.2000 x 0.73 1.60 Kilogram
Upah :
- Tukang Kayu 5.8000 x 0.73 4.21 HOK
- Pekerja 1.9400 x 0.73 1.41 HOK
6.c. Pekerjaan Memasang Kasau & Reng Kayu Lanan
Luas Rangka Atap Bangunan Utama
- Arah Memanjang (( 4.45 + 10 ) / 2 ) x 3.55 x 2 51.30
- Arah Melintang (( 2 + 8 ) / 2 ) x 3.67 x 2 36.70
Luas Atap Anak Bangunan Utama (( 4.45 + 5.85) / 2 ) x 1.85 x 2 19.06
Total Luas atap bangunan utama 19.06 - 8.99 10.07 meter kuadrat
Total Luas Rangka Atap Seluruhnya 10.07 + 6.15 + 8.99 25.21 meter kuadrat
Bahan :
- Balok Kayu Lanan 0.0120 x 25.21 0.30 meter kubik
- Paku Biasa 0.1500 x 25.21 3.78 Kilogram
Upah :
- Tukang Kayu 0.1000 x 25.21 2.52 HOK
- Pekerja 0.1000 x 25.21 2.52 HOK
Bahan :
- Papan Ulin 0.0090 x 48.80 0.44 meter kubik
dalam batang 0.44 / 0.02 x 0.20 x 4.00 27.45 Keping
- Paku Ulin 0.0500 x 48.80 2.44 Kilogram
Upah :
- Tukang Kayu 0.2200 x 48.80 10.74 HOK
- Pekerja 0.1100 x 48.80 5.37 HOK
6.e. Pekerjaan Memasang Penutup Atap Genteng Metal
Luas Atap = Luas Rangka Atap 25.21 meter kuadrat
Bahan :
- Genteng Metal 0.35 mm 1.0200 x 25.21 25.71 meter kuadrat
- Paku anti karat 0.0750 x 25.21 1.89 Kilogram
Upah :
- Tukang Kayu 0.1500 x 25.21 3.78 HOK
- Pekerja 0.2500 x 25.21 6.30 HOK
Upah :
Upah :
- Tukang Kayu 0.4000 x 7.20 2.88 HOK
Upah :
- Tukang Kayu 1.8000 x 52.50 94.50 HOK
7.b. Pekerjaan Memasang Dinding Kayu Ulin
Volume
Luas Dinding Kayu Ulin 0.90 x 25.30 22.77 meter kuadrat
Bahan :
- Papan Kayu Ulin 2/18 cm-4.00m 0.0230 x 22.77 0.52 meter kubik
dalam batang 0.52 / 0.02 x 0.18 x 4.00 36.37 Keping
- Paku Ulin 0.2000 x 22.77 4.55 Kilogram
Upah :
- Tukang Kayu 1.8000 x 22.77 40.99 HOK
Upah :
- Tukang Kayu 1.8000 x 99.85 179.72 HOK
Upah :
- Tukang Kayu 1.8000 x 3.13 5.63 HOK
- Pekerja 0.6000 x 3.13 1.88 HOK
PEKERJAAN DAUN PINTU/JENDELA dan VENTILASI
8.a. Pekerjaan Memasang Daun Pintu Kaca Kayu Ulin
Volume
- Daun pintu P1 & P2 0.90 x 2.10 x 3 5.67 meter kuadrat
Bahan :
- Papan Kayu Uin 0.0350 x 5.67 0.20 meter kubik
dalam batang 0.20 / 0.02 x 0.18 x 4.00 13.78 Keping
Upah :
- Tukang Kayu 2.0000 x 5.67 11.34 HOK
- Pekerja 0.0500 x 5.67 0.28 HOK
Upah :
- Tukang Kayu 2.5000 x 4.86 12.15 HOK
- Pekerja 1.0000 x 4.86 4.86 HOK
8.c. Pekerjaan Memasang Daun Jendela Kaca Kayu Ulin & Ventilasi
Volume
- Daun Jendela J1 0.70 x 1.20 x 8 = 6.72
- Ventilasi P1 0.40 x 1.80 x 1 = 0.72
- Ventilasi P2 0.40 x 0.90 x 3 = 1.08
- Ventilasi P3 0.40 x 0.60 x 1 = 0.24
- Ventilasi J1 0.40 x 0.70 x 8 = 2.24
- Ventilasi V1 0.40 x 0.60 x 1 = 0.24
Total Daun Jendela & Ventilasi = 11.24 11.24 meter kuadrat
Bahan :
- Papan Kayu Uin 0.0350 x 11.24 0.39 meter kubik
dalam batang 0.39 / 0.02 x 0.18 x 4.00 27.32 Keping
Upah :
- Tukang Kayu 2.0000 x 11.24 22.48 HOK
- Pekerja 0.8000 x 11.24 8.99 HOK
8.d. Pekerjaan Memasang Kaca tebal 5 mm
Volume
- Luas bidang Kaca P1 : 0.90 x 2.10 x 2 = 3.78
P2 : 0.90 x 2.10 x 1 = 1.89
J1 : 0.70 x 1.20 x 8 = 6.72
- Ventilasi P1 0.40 x 1.80 x 1 = 0.72
- Ventilasi P2 0.40 x 0.90 x 3 = 1.08
- Ventilasi P3 0.40 x 0.60 x 1 = 0.24
- Ventilasi J1 0.40 x 0.70 x 8 = 2.24
- Ventilasi V1 0.40 x 0.60 x 1 = 0.24
Total Luas Bidang Kaca = 16.91 16.91 meter kuadrat
Bahan :
- Kaca tebal 5 mm 1.1000 x 16.91 18.60 meter kuadrat
Upah :
- Tukang Kayu 0.1500 x 16.91 2.54 HOK
- Pekerja 0.0150 x 16.91 0.25 HOK
9. PEKERJAAN PLAFOND
9.a. Pekerjaan Memasang Rangka Plafond
Volume
- Luas bangunan 8.00 x 6.00 + 1.50 x 3.00 52.5
- Luar Tepi Bangunan/Surau 0.80 x 35.00 28.00
80.50 meter kuadrat
Bahan :
- Balok Kayu Lanan 0.0120 x 80.50 0.97 meter kubik
- Paku Biasa 2"-5" 0.1000 x 80.50 8.05 Kilogram
Upah :
- Tukang Kayu 0.2500 x 80.50 20.13 HOK
- Pekerja 0.1500 x 80.50 12.08 HOK
Upah :
- Tukang Kayu 0.1000 x 80.50 8.05 HOK
- Pekerja 0.0700 x 80.50 5.64 HOK
9.c. Pekerjaan Memasang List Frofil Plafond
Volume
Panjang List profil 4 cm 10+(8x4)+(6X4)+(2.50x14)+5+(3x4)+(1.50x8)+(2x2) 134 meter panjang
Bahan :
- Kayu Profil 1.0500 x 134.00 140.70 meter panjang
- Paku 0.0100 x 134.00 1.34 Kilogram
Upah :
- Pekerja 0.0210 x 134.00 2.81 HOK
Upah :
- Pekerja 0.0200 x 127.75 2.55 HOK
Bahan :
- Dempul Jadi 0.0800 x 23.27 1.86 Kilogram
- Minyak Cat 0.0200 x 23.27 0.47 Kilogram
- Batu Apung/Ampelas 0.0100 x 23.27 0.23 Kilogram
Upah :
- Pekerja 0.0400 x 23.27 0.93 HOK
Upah :
- Pekerja 0.0700 x 23.27 1.63 HOK
Upah :
- Pekerja 0.0200 x 80.50 1.61 HOK
Upah :
- Pekerja 0.0700 x 20.50 1.43 HOK
10.f. Pekerjaan Mengeter Kuda-kuda, Gording dan Kasau/Reng Kayu Lanan
Volume
- Luas ( 0.36 x ( 129.15 + 110.90 )) + 25.21 111.62 meter kuadrat
Bahan :
- Ter atau Residu 0.3500 x 111.62 39.07 Liter
Upah :
- Pekerja 0.1000 x 111.62 11.16 HOK
Upah :
- Tukang Batu 1.5000 x 1 1.50 HOK
Upah :
- Tukang Batu 0.7500 x 1 0.75 HOK
Catatn Bahan lain yang dibutuhkan :
- Pipa PVC Ø 4" 1 1.00 Buah
- Pipa PVC Ø 2" 1 1.00 Buah
Upah :
- Tukang Kayu 0.5000 x 5 2.50 HOK
12.b. Pekerjaan Memasang Engsel Pintu
Volume
- Jumlah Pintu P1, P2 & P3 5.00 x 3.00 15.00 Buah
Bahan :
- Engsel Pintu 1.0000 x 15 15.00 Buah
Upah :
- Tukang Kayu 0.1500 x 15 2.25 HOK
Upah :
- Tukang Kayu 0.1000 x 16 1.60 HOK
Catatan :
Sumbangan lahan tidak dimasukkan RAB tetapi dilaporkan dengan form. 6a, 6b dan 6c
Sumbangan dalam bentuk bahan upah dan alat, ditulis dalam kolom Volume dari Swadaya
Operasional TPK dilaporkan pada form Rekapitulasi
Kategori Biaya
I-a Pembelian bahan hasil tenaga manusia
I-b Pembelian bahan hasil industri