No URAIAN PEKERJAAN VOL SAT H.BAHAN UPAH TOTAL JUMLAH
A. PEKERJAAN LANTAI 1
I PEKERJAAN PERSIAPAN
1 Direksikeet dan Gudang 1 ls Rp - Rp 15,000,000 Rp 4,000,000
2 Pembersihan Lahan 1 ls Rp - Rp 2,000,000
3 Mobilisasi 1 ls Rp - Rp - Rp 10,000,000
4 Air Kerja 1 ls Rp - Rp 3,000,000 Rp -
5 Listrik Kerja 1 ls Rp - Rp 6,000,000 Rp -
6 Pek.Bowplank dan Pengukuran 306 M¹ Rp 10,000 Rp 750,000 Rp 3,060,000
Sub Total Rp 43,810,000
II PEKERJAAN GALIAN 311 M¹
1 Galian Tanah Pondasi 202 M³ Rp 120,000 Rp 24,240,000
2 Urugan Tanah Kembali 78 M³ Rp 122,000 Rp 9,516,000
3 Urug Pasir Bawah Pondasi 31 M³ Rp 220,000 Rp 6,842,000
Sub Total Rp 40,598,000
III PEKERJAAN SLOOF 30x40 19 M³ Rp 750,000 Rp 14,437,500
1 Semen 142 zak Rp 65,000 Rp 9,213,750
2 Pasir 12 M³ Rp 220,000 Rp 2,695,000
3 Batu Split 18 M³ Rp 320,000 Rp 5,600,000
4 Papan cor 2/20 231 lbr Rp 35,000 Rp 8,085,000
5 Kaso 4/6 39 btg Rp 45,000 Rp 1,732,500
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 145 btg Rp 75,000 Rp 10,893,750
7 Besi Ø. 16 SNI (Tulangan Utama) 106 btg Rp 195,000 Rp 20,572,500
8 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 73,680,000
IV PEKERJAAN PONDASI
A. Pekerjaan Pondasi Batu kali 81 M³ Rp 450,000 Rp 36,225,000
1 Semen 184 zak Rp 65,000 Rp 11,960,000
2 Pasir 30 M³ Rp 220,000 Rp 6,600,000
3 Batu Kali 75 M³ Rp 325,000 Rp 24,456,250
Sub Total Rp 79,241,250
B. Pekerjaan P.Cakar Ayam (80x80 ) 18bh 6 M³ Rp 750,000 Rp 4,500,000
1 Semen 49 zak Rp 65,000 Rp 3,185,000
2 Pasir 16 M³ Rp 220,000 Rp 3,520,000
3 Batu Split 25 M³ Rp 320,000 Rp 8,000,000
4 Papan cor 2/20 36 lbr Rp 35,000 Rp 1,260,000
5 Kaso kayu 4/6 60 btg Rp 45,000 Rp 2,700,000
6 Besi Ø. 14 SNI (Tulangan Utama) 142 btg Rp 135,000 Rp 19,170,000
7 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 42,785,000
V PEKERJAAN BETON STRUKTUR
LANTAI 1
A. Pekerjaan Kolom Praktis ( 15 x 15 ) 3 M³ Rp 750,000 Rp 2,250,000
1 Semen 22 zak Rp 65,000 Rp 1,430,000
2 Pasir 2 M³ Rp 220,000 Rp 440,000
3 Batu Split 3 M³ Rp 320,000 Rp 960,000
4 Papan cor 2/20 36 lbr Rp 35,000 Rp 1,260,000
5 Kaso kayu 4/6 60 btg Rp 45,000 Rp 2,700,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 32 btg Rp 75,000 Rp 2,400,000
7 Besi Ø. 12 SNI (Tulangan Utama) 38 btg Rp 83,600 Rp 3,176,800
8 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 15,066,800
B. Pekerjaan Kolom 30x30 (18 bh} 7 M³ Rp 750,000 Rp 5,250,000
1 Semen 51 zak Rp 65,000 Rp 3,315,000
2 Pasir 5 M³ Rp 220,000 Rp 1,155,000
3 Batu Split 4 M³ Rp 320,000 Rp 1,280,000
4 Papan cor 2/20 48 lbr Rp 35,000 Rp 1,680,000
5 Kaso kayu Meranti 4/6 80 btg Rp 45,000 Rp 3,600,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 65 btg Rp 75,000 Rp 4,856,250
7 Besi Ø. 14 SNI (Tulangan Tengah) 49 btg Rp 135,000 Rp 6,615,000
8 Besi Ø. 16 SNI (Tulangan Utama) 25 btg Rp 195,000 Rp 4,875,000
9 Kawat beton + paku 2 ls Rp 450,000 Rp 900,000
Sub Total Rp 33,526,250
C.Pekerjaan Ring Balk Utama (30x45) 11 M³ Rp 750,000 Rp 8,437,500
1 Semen 86 zak Rp 65,000 Rp 5,557,500
2 Pasir 7 M³ Rp 220,000 Rp 1,485,000
3 Batu Split 11 M³ Rp 320,000 Rp 3,520,000
4 Papan cor 2/20 135 lbr Rp 35,000 Rp 4,725,000
5 Kaso kayu 4/6 22 btg Rp 45,000 Rp 990,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 128 btg Rp 75,000 Rp 9,618,750
7 Besi Ø. 16 SNI (Tulangan Utama) 128 btg Rp 195,000 Rp 25,008,750
8 Kawat beton + paku 2 ls Rp 450,000 Rp 900,000
Sub Total Rp 60,242,500
D. Pekerjaan Ring Balok Anak 20x30 2 M³ Rp 750,000 Rp 1,687,500
1 Semen 18 zak Rp 65,000 Rp 1,170,000
2 Pasir 2 M³ Rp 220,000 Rp 440,000
3 Batu Split 2 M³ Rp 320,000 Rp 640,000
4 Papan cor 2/20 24 lbr Rp 35,000 Rp 840,000
5 Kaso kayu 4/6 50 btg Rp 45,000 Rp 2,250,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 16 btg Rp 75,000 Rp 1,200,000
6 Besi Ø. 14 SNI (Tulangan Tengah) 7 btg Rp 135,000 Rp 945,000
7 Besi Ø. 16 SNI (Tulangan Utama) 11 btg Rp 195,000 Rp 2,145,000
8 Kawat beton + paku 2 ls Rp 450,000 Rp 900,000
Sub Total Rp 12,217,500
PEKERJAAN BETON STRUKTUR
LANTAI 2
B. Pekerjaan Kolom 30x30 (18 bh} 7 M³ Rp 750,000 Rp 5,250,000
1 Semen 51 zak Rp 65,000 Rp 3,315,000
2 Pasir 5 M³ Rp 220,000 Rp 1,155,000

LANTAI 1 Page 1
BILL OF QUANTITY
PRIVATE HOUSE
LOCATION : PALU CITY
OWNER : Mr. Hendrik
No URAIAN PEKERJAAN VOL SAT H.BAHAN UPAH TOTAL JUMLAH
3 Batu Split 4 M³ Rp 320,000 Rp 1,280,000
4 Papan cor 2/20 48 lbr Rp 35,000 Rp 1,680,000
5 Kaso kayu 4/6 80 btg Rp 45,000 Rp 3,600,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 65 btg Rp 75,000 Rp 4,856,250
7 Besi Ø. 14 SNI (Tulangan Tengah) 49 btg Rp 135,000 Rp 6,615,000
8 Besi Ø. 16 SNI (Tulangan Utama) 25 btg Rp 195,000 Rp 4,875,000
9 Kawat beton + paku 2 ls Rp 450,000 Rp 900,000
Sub Total Rp 33,526,250
B. Pekerjaan Kolom Praktis ( 15 x 15 ) 2 M³ Rp 750,000 Rp 1,687,500
1 Semen 18 zak Rp 65,000 Rp 1,170,000
2 Pasir 2 M³ Rp 220,000 Rp 440,000
3 Batu Split 2 M³ Rp 320,000 Rp 640,000
4 Papan cor 2/20 24 lbr Rp 35,000 Rp 840,000
5 Kaso kayu 4/6 50 btg Rp 45,000 Rp 2,250,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 16 btg Rp 75,000 Rp 1,200,000
7 Besi Ø. 12 SNI (Tulangan Utama) 7 btg Rp 83,600 Rp 585,200
8 Kawat beton + paku 2 ls Rp 450,000 Rp 900,000
Sub Total Rp 9,712,700
C.Pekerjaan Ring Balk ( 15 x 20 ) 6 M³ Rp 750,000 Rp 4,500,000
1 Semen 44 zak Rp 65,000 Rp 2,860,000
2 Pasir 44 M³ Rp 220,000 Rp 9,680,000
3 Batu Split 6 M³ Rp 320,000 Rp 1,920,000
4 Papan cor 2/20 72 lbr Rp 35,000 Rp 2,520,000
5 Kaso kayu 4/6 12 btg Rp 45,000 Rp 540,000
6 Besi Ø. 8 ex. Sii ( Sengkang jarak 0.15 ) 32 btg Rp 42,000 Rp 1,344,000
7 Besi Ø. 12 ex. Sii (Tulangan Utama) 32 btg Rp 83,600 Rp 2,675,200
8 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 26,489,200
D. Pekerjaan Balok 20 X 30 2 M³ Rp 750,000 Rp 1,687,500
1 Semen 32 zak Rp 65,000 Rp 2,047,500
2 Pasir 4 M³ Rp 220,000 Rp 770,000
3 Batu Split 5 M³ Rp 320,000 Rp 1,600,000
4 Papan cor 2/20 38 lbr Rp 35,000 Rp 1,330,000
5 Kaso kayu 4/6 69 btg Rp 45,000 Rp 3,105,000
6 Besi Ø. 10 SNI (Sengkang jarak 0.15 ) 42 btg Rp 75,000 Rp 3,150,000
6 Besi Ø. 14 SNI (Tulangan Tengah) 16 btg Rp 135,000 Rp 2,160,000
7 Besi Ø. 16 SNI (Tulangan Utama) 16 btg Rp 195,000 Rp 3,120,000
8 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 19,420,000
VI PEKERJAAN BETON NON STRUKTUR
A. PekerjaanTangga beton 1 M³ Rp 800,000 Rp 1,120,000
1 Semen 10 zak Rp 65,000 Rp 650,000
2 Pasir 1 M³ Rp 220,000 Rp 220,000
3 Batu Split 1 M³ Rp 320,000 Rp 320,000
4 Triplek cor 9mm 5 lbr Rp 132,000 Rp 660,000
5 Kaso kayu 4/6 18 btg Rp 45,000 Rp 810,000
6 Besi Ø. 10 SNI 18 btg Rp 75,000 Rp 1,350,000
6 Besi Ø. 14 SNI 23 btg Rp 450,000 Rp 10,350,000
8 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 15,930,000
B. Pekerjaan Dak Lantai 2 26 M³ Rp 750,000 Rp 19,500,000
1 Semen 188 zak Rp 65,000 Rp 12,220,000
2 Pasir 18 M³ Rp 220,000 Rp 3,960,000
3 Batu Split 24 M³ Rp 320,000 Rp 7,680,000
4 Triplek cor 9mm 91 lbr Rp 132,000 Rp 12,012,000
5 Kaso kayu 4/6 338 btg Rp 45,000 Rp 15,210,000
6 Besi Ø. 10 SNI 434 btg Rp 75,000 Rp 32,550,000
7 Kawat beton + paku 2 ls Rp 450,000 Rp 900,000
Sub Total Rp 104,032,000
C. Pekerjaan Pet beton 1 M³ Rp 750,000 Rp 750,000
1 Semen 8 zak Rp 65,000 Rp 520,000
2 Pasir 1 M³ Rp 220,000 Rp 220,000
3 Batu Split 1 M³ Rp 320,000 Rp 320,000
4 Triplek cor 9mm 4 lbr Rp 132,000 Rp 528,000
5 Kaso kayu 4/6 13 btg Rp 45,000 Rp 585,000
6 Besi Ø. 10 SNI 17 btg Rp 75,000 Rp 1,275,000
7 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 4,648,000
D. Pekerjaan Profilan 1 ls Rp 3,000,000 Rp 3,000,000
Sub Total Rp 3,000,000

LANTAI 1 Page 2
BILL OF QUANTITY
PRIVATE HOUSE
LOCATION : PALU CITY
OWNER : Mr. Hendrik
No URAIAN PEKERJAAN VOL SAT H.BAHAN UPAH TOTAL JUMLAH
PEKERJAAN BETON NON STRUKTUR
A. Pekerjaan Pet + Dak Talang beton belakang 4 M³ Rp 750,000 Rp 3,000,000
1 Semen 29 zak Rp 65,000 Rp 1,885,000
2 Pasir 3 M³ Rp 220,000 Rp 660,000
3 Batu Split 4 M³ Rp 320,000 Rp 1,280,000
4 Triplek cor 9mm 14 lbr Rp 132,000 Rp 1,848,000
5 Kaso kayu 4/6 52 btg Rp 45,000 Rp 2,340,000
6 Besi Ø. 10 SNI 67 btg Rp 75,000 Rp 5,025,000
8 Kawat beton + paku 1 ls Rp 450,000 Rp 450,000
Sub Total Rp 16,488,000
B. Pekerjaan Profilan 1 ls Rp 3,000,000 Rp 3,000,000
Sub Total Rp 3,000,000
VII PEKERJAAN DINDING LANTAI 1
PEKERJAAN PASANGAN 438 M² Rp 45,000 Rp 19,710,000
1 Bata 35040 bh Rp 1,200 Rp 42,048,000
2 Semen 144 Zak Rp 65,000 Rp 9,360,000
3 Pasir Pasang 35 M³ Rp 220,000 Rp 7,700,000
Sub Total Rp 78,818,000
PEKERJAAN PLESTERAN 876 M² Rp 55,000 Rp 48,180,000
1 Semen 180 Zak Rp 65,000 Rp 11,700,000
2 Pasir pasang 26 M³ Rp 220,000 Rp 5,720,000
Sub Total Rp 65,600,000
PEKERJAAN ACIAN 876 M² Rp 18,000 Rp 15,768,000
1 Semen 180 Zak Rp 65,000 Rp 11,700,000
Sub Total Rp 27,468,000
PEKERJAAN DINDING LANTAI 2
PEKERJAAN PASANGAN 595 M² Rp 45,000 Rp 26,775,000
1 Bata 47600 bh Rp 1,200 Rp 57,120,000
2 Semen 195 Zak Rp 65,000 Rp 12,675,000
3 Pasir Pasang 48 M³ Rp 220,000 Rp 10,560,000
Sub Total Rp 107,130,000
PEKERJAAN PLESTERAN 1190 M² Rp 55,000 Rp 65,450,000
1 Semen 245 Zak Rp 65,000 Rp 15,925,000
2 Pasir pasang 36 M³ Rp 220,000 Rp 7,920,000
Sub Total Rp 89,295,000
PEKERJAAN ACIAN 1190 M² Rp 18,000 Rp 21,420,000
1 Semen 245 Zak Rp 65,000 Rp 15,925,000
Sub Total Rp 37,345,000
VIII PEK.LANTAI DAN FINISHING LANTAI 1
A.LANTAI 1
1 TERAS/CORIDOOR 91 M² Rp 55,000 Rp 5,005,000
1. Lantai Granit 120 x 60 91 M² Rp 325,000 Rp 29,575,000
2. Semen 28 Zak Rp 65,000 Rp 1,820,000
3. Pasir pasang 10 M³ Rp 220,000 Rp 2,200,000
Sub Total Rp 38,600,000
2 RUANG TAMU, KERJA, KAMAR 182 M² Rp 55,000 Rp 10,010,000
1. Lantai Granit 60 x 60 182 M² Rp 275,000 Rp 50,050,000
2. Semen 52 Zak Rp 65,000 Rp 3,380,000
3. Pasir pasang 21 M³ Rp 220,000 Rp 4,620,000
Sub Total Rp 68,060,000
4 DAPUR 20 M² Rp 55,000 Rp 1,100,000
1. Lantai Granit 60 x 60 DOFF 20 M² Rp 275,000 Rp 5,500,000
2. Semen 8 Zak Rp 65,000 Rp 520,000
3. Pasir pasang 3 M³ Rp 220,000 Rp 660,000
Sub Total Rp 7,780,000
5 KM/WC 14 M² Rp 55,000 Rp 770,000
1. Lantai Granit 60 x 60 15 M² Rp 275,000 Rp 4,125,000
2. Semen 5 Zak Rp 65,000 Rp 325,000
3. Pasir pasang 2 M³ Rp 220,000 Rp 440,000
Sub Total Rp 5,660,000
PAS. DINDING km/wc 72 M² Rp 55,000 Rp 3,960,000
1. Dinding Keramik 33/25 ex Roman 72 M² Rp 175,000 Rp 12,600,000
2. Semen 21 Zak Rp 65,000 Rp 1,365,000
3. Pasir pasang 5.00 M³ Rp 220,000 Rp 1,100,000
Sub Total Rp 19,025,000
PEK.LANTAI DAN FINISHING LANTAI 2
A.LANTAI 2
1 CORIDOOR+TANGGA 40 M² Rp 55,000 Rp 2,200,000
1. Lantai 30 X 60 40 M² Rp 225,000 Rp 9,000,000
2. Semen 12 Zak Rp 65,000 Rp 780,000
3. Pasir pasang 4 M³ Rp 220,000 Rp 880,000
Sub Total Rp 12,860,000
2 RUANG TIDUR dan BALKON 168 M² Rp 55,000 Rp 9,240,000
1. Lantai Granit 60 x 60 163 M² Rp 275,000 Rp 44,825,000
2. Semen 48 Zak Rp 65,000 Rp 3,120,000
3. Pasir pasang 19 M³ Rp 220,000 Rp 4,180,000
Sub Total Rp 61,365,000
4 KM/WC 29 M² Rp 55,000 Rp 1,595,000
1. Lantai Keramik 25X25 ex Roman 29 M² Rp 125,000 Rp 3,625,000
2. Semen 8 Zak Rp 65,000 Rp 520,000
3. Pasir pasang 4 M³ Rp 220,000 Rp 880,000
Sub Total Rp 6,620,000
5 PAS. DINDING km/wc 132 M² Rp 55,000 Rp 7,260,000
1. Dinding Keramik 33/25 ex Roman 132 M² Rp 175,000 Rp 23,100,000
2. BORDER 10/25 ex Roman 38 BH Rp 5,000 Rp 190,000
3. Semen 58 Zak Rp 65,000 Rp 3,770,000
4. Pasir pasang 15.00 M³ Rp 220,000 Rp 3,300,000
Sub Total Rp 37,620,000

LANTAI 1 Page 3
BILL OF QUANTITY
PRIVATE HOUSE
LOCATION : PALU CITY
OWNER : Mr. Hendrik
No URAIAN PEKERJAAN VOL SAT H.BAHAN UPAH TOTAL JUMLAH
IX PEKERJAAN PLAFOND LANTAI 1
PEKERJAAN PLAFOND 168 M² Rp 55,000 Rp 9,240,000
1 Plafond Gypsum 9 mm 68 LBR Rp 80,000 Rp 5,440,000
2 Hollow 120 btg Rp 7,000 Rp 840,000
3 Dempul Canstein + Paku Gypsum 1 ls Rp 50,000 Rp 50,000
Sub Total Rp 15,570,000

PEKERJAAN PLAFOND LANTAI 2 260 M² Rp 55,000 Rp 14,300,000


1 Plafond Gypsum 9 mm 104 LBR Rp 80,000 Rp 8,320,000
2 Hollow 150 btg Rp 7,000 Rp 1,050,000
3 Dempul Canstein + Paku Gypsum 1 ls Rp 50,000 Rp 50,000
Sub Total Rp 23,720,000
X PEKERJAAN PINTU & JENDELA LANTAI 1
1 Kusen+ Daun Pintu Utama (PU) 1 unit Rp 5,500,000 Rp 100,000 Rp 5,600,000
2 Kusen+ Daun Pintu Kamar (P1) 3 unit Rp 3,500,000 Rp 100,000 Rp 10,800,000
3 Kusen+ Daun Pintu Km/ Wc (PVC) 4 unit Rp 1,750,000 Rp 100,000 Rp 7,400,000
4 Kusen+ Daun + kaca Jendela empat lubang (J1) 4 unit Rp 3,500,000 Rp 100,000 Rp 14,400,000
5 Kusen+ Daun + kaca Jendela dua lubang (J2) 3 unit Rp 6,700,000 Rp 100,000 Rp 20,400,000
6 Kusen+ Daun Pintu Geser 2 unit Rp 7,000,000 Rp 100,000 Rp 14,200,000
7 BOVENLIGHT KM/WC 1 unit Rp 250,000 Rp 100,000 Rp 350,000
Sub Total Rp 73,150,000
ACCESSORIES PINTU & JENDELA LANTAI 1
1 Kunci Pintu Utama + Handle Engsel 1 unit Rp 1,500,000 Rp 1,500,000
2 Kunci Pintu Standart + Handle + Engsel 4 unit Rp 300,000 Rp 1,200,000
3 hak angin,grendel + Engsel jendela ex standar 28 unit Rp 150,000 Rp 4,200,000
Sub Total Rp 6,900,000

PEKERJAAN PINTU & JENDELA LANTAI 2


1 Kusen+ Daun Pintu Kamar (P1) 3 unit Rp 3,500,000 Rp 100,000 Rp 10,800,000
2 Kusen+ Daun Pintu Km/ Wc (PVC) 3 unit Rp 1,750,000 Rp 100,000 Rp 5,550,000
3 Kusen+ Daun + kaca Jendela kamar 2 lubang (JK) 3 unit Rp 6,700,000 Rp 100,000 Rp 20,400,000
4 BOVENLIGHT KM/WC 3 unit Rp 250,000 Rp 100,000 Rp 1,050,000
Sub Total Rp 37,800,000
ACCESSORIES PINTU & JENDELA LANTAI 2
1 Kunci Pintu Standart + Handle + Engsel 12 unit Rp 1,500,000 Rp 18,000,000
2 hak angin,grendel + Engsel jendela ex standar 6 unit Rp 150,000 Rp 900,000
Sub Total Rp 18,900,000
XI PEKERJAAN SANITAIR LANTAI 1
Kamar Mandi Lantai 1
1 Closet duduk TOTO 4 bh Rp 2,500,000 Rp 125,000 Rp 10,500,000
2 Shower TOTO 3 bh Rp 1,500,000 Rp 125,000 Rp 4,875,000
3 Wastafel TOTO 4 bh Rp 1,250,000 Rp 125,000 Rp 5,500,000
4 Floor Drain TOTO 4 bh Rp 75,000 Rp 20,000 Rp 380,000
Sub Total Rp 21,255,000
PEKERJAAN SANITAIR LANTAI 2
Kamar Mandi Lantai 2
1 Closet duduk TOTO 3 bh Rp 2,500,000 Rp 125,000 Rp 7,875,000
2 Shower TOTO 3 bh Rp 1,500,000 Rp 125,000 Rp 4,875,000
3 Wastafel TOTO 3 bh Rp 1,250,000 Rp 125,000 Rp 4,125,000
4 Floor Drain TOTO 3 bh Rp 75,000 Rp 20,000 Rp 285,000
Sub Total Rp 17,555,000
XII PEKERJAAN INSTALASI AIR LANTAI 1
A.AIR BERSIH 1 ls
1 Pipa PVC AW 1/2 " Wavin 12 btg Rp 60,000 Rp 12,000 Rp 864,000
2 Pipa PVC AW 3/4 " Wavin 5 btg Rp 64,800 Rp 12,000 Rp 384,000
3 Kran Air 9 bh Rp 45,000 Rp 12,000 Rp 513,000
B.AIR KOTOR 1 ls
1 Pipa PVC 3 " Wavin AW 24 btg Rp 75,000 Rp 12,000 Rp 2,088,000
2 Pipa PVC 4 " Wavin AW 24 btg Rp 85,000 Rp 12,000 Rp 2,328,000
3 Pipa PVC 6 " Wavin AW 24 btg Rp 115,000 Rp 12,000 Rp 3,048,000
3 Fitting + Sambungan dll 1 ls Rp 125,000 Rp 12,000 Rp 137,000
Sub Total Rp 9,362,000
PEKERJAAN INSTALASI AIR LANTAI 2
A.AIR BERSIH 1 ls
1 Pipa PVC AW 1/2 " Wavin 24 btg Rp 60,000 Rp 12,000 Rp 1,728,000
2 Pipa PVC AW 3/4 " Wavin 4 btg Rp 64,800 Rp 12,000 Rp 307,200
3 Kran Air 12 bh Rp 45,000 Rp 12,000 Rp 684,000
B.AIR KOTOR 1 ls
1 Pipa PVC 3 " Wavin AW 30 btg Rp 75,000 Rp 12,000 Rp 2,610,000
2 Pipa PVC 4 " Wavin AW 48 btg Rp 85,000 Rp 12,000 Rp 4,656,000
3 Fitting + Sambungan dll 1 ls Rp 125,000 Rp 12,000 Rp 137,000
Sub Total Rp 10,122,200

XIII PEK. INSTALASI LISTRIK LANTAI 1 65


1 Lampu LED PHILIPS 18 WATT 20 ttk Rp 72,000 Rp 45,000 Rp 2,340,000
2 Lampu Tl 40 w 4 ttk Rp 85,000 Rp 45,000 Rp 520,000
3 Lampu exterior Pet beton 4 ttk Rp 85,000 Rp 45,000 Rp 520,000
4 Lampu cawan 1 ttk Rp 200,000 Rp 45,000 Rp 245,000
5 Stop Kontak 20 ttk Rp 25,000 Rp 45,000 Rp 1,400,000
6 Saklar Tunggal PANASONIC 4 ttk Rp 25,000 Rp 45,000 Rp 280,000
7 Saklar Double PANASONIC 12 ttk Rp 35,000 Rp 45,000 Rp 960,000
8 Box MCB 1 bh Rp 200,000 Rp 45,000 Rp 245,000
9 KABEL Ex ETERNA 2 Roll Rp 1,200,000 Rp 2,400,000
Sub Total Rp 8,910,000

LANTAI 1 Page 4
BILL OF QUANTITY
PRIVATE HOUSE
LOCATION : PALU CITY
OWNER : Mr. Hendrik
No URAIAN PEKERJAAN VOL SAT H.BAHAN UPAH TOTAL JUMLAH
PEK. INSTALASI LISTRIK LANTAI 2 73
1 Lampu LED PHILIPS 18 WATT 36 ttk Rp 72,000 Rp 45,000 Rp 4,212,000
2 Lampu Tl 40 w 4 ttk Rp 85,000 Rp 45,000 Rp 520,000
3 Lampu exterior Pet beton 4 ttk Rp 85,000 Rp 45,000 Rp 520,000
4 Lampu cawan 4 ttk Rp 200,000 Rp 45,000 Rp 980,000
5 Stop Kontak 14 ttk Rp 25,000 Rp 45,000 Rp 980,000
6 Saklar Tunggal PANASONIC 3 ttk Rp 25,000 Rp 45,000 Rp 210,000
7 Saklar Double PANASONIC 8 ttk Rp 35,000 Rp 45,000 Rp 640,000
8 Box MCB 1 bh Rp 200,000 Rp 45,000 Rp 245,000
9 KABEL Ex ETERNA 2 Roll Rp 1,200,000 Rp 2,400,000
Sub Total Rp 10,707,000
XIV PEKERJAAN FINISHING LANTAI 1
1 Cat Dinding Dalam ex ICI 416 M² Rp 20,000 Rp 12,000 Rp 13,312,000
2 Cat Dinding Luar ex ICI 155 M² Rp 20,000 Rp 12,000 Rp 4,960,000
3 Plitur Pintu + Jendela 1 ls Rp 2,000,000 Rp 2,000,000
4 Cat Plafond ex Jotun 168 M² Rp 5,000 Rp 12,000 Rp 2,856,000
5 Nat Keramik 1 ls Rp 500,000 Rp 500,000
6 Railing Tangga+Void 33 M¹ Rp 500,000 Rp 16,500,000
Sub Total Rp 40,128,000
PEKERJAAN FINISHING LANTAI 2
1 Cat Dinding Dalam ex ICI 388 M² Rp 20,000 Rp 12,000 Rp 12,416,000
2 Cat Dinding Luar ex ICI 143 M² Rp 20,000 Rp 12,000 Rp 4,576,000
3 Plitur Pintu + Jendela 1 ls Rp 2,000,000 Rp 2,000,000
4 Cat Plafond ex Jotun 260 M² Rp 5,000 Rp 12,000 Rp 4,420,000
5 Nat Keramik 1 ls Rp 500,000 Rp 500,000
Sub Total Rp 23,912,000
XV PEKERJAAN ATAP 299 M²
1 Rangka Baja ringan 299 M² Rp 160,000 Rp 55,000 Rp 64,285,000
2 Atap Spandek Polos 299 M² Rp 90,000 Rp 45,000 Rp 40,365,000
3 Almunium foil pereda panas 299 M² Rp 20,000 Rp 15,000 Rp 10,465,000
4 Lisplang Grc 15 lbr Rp 200,000 Rp 8,000 Rp 3,120,000
5 Paku 5,7 + Baut + Plat 1 ls Rp 200,000 Rp 200,000
Sub Total Rp 118,435,000

XVI PEKERJAAN LAIN LAIN


1 SEPTICTANK dan Tandon air 2000 m3 1 ls Rp 10,000,000 Rp 10,000,000
2 Pemanas Air 300 Liter 1 Ls Rp 40,000,000 Rp 40,000,000
Sub Total Rp 50,000,000

JUMLAH
TOTAL BIAYA L ANTAI 1 Rp 138,877,800 Rp 49,552,000 Rp 1,761,940,650 Rp 1,787,085,650