Grid-connected PV installation

Best practice guidelines

AuSES PV Installation Best Practice Workshop 1


Why best practice?
 AS/NZS mandate minimum requirements
 Best practices go above and beyond and
include non-technical aspects
 Improve the quality/reputation of the PV
industry
 Some best practices may be included in
new versions of AS/NZS

AuSES PV Installation Best Practice Workshop 2


Before installation
 Visit customer’s site before preparing
quote, don’t use satellite imagery
 Watch out for shading
◦ Solar Pathfinder, SunEye, mobile phone apps,
visual estimate
 Plan cable routes, inverter location, panel
layout
◦ Minimize effect of shading

AuSES PV Installation Best Practice Workshop 3


Before installation
 Watch out for meter box upgrades
 Give a firm quote, no hidden costs
 Give a timeline to installation and stick to
it
 Assist with regulatory approvals
◦ Grid connection, planning, RECs

AuSES PV Installation Best Practice Workshop 4


Before installation
 Give an accurate estimated energy yield
(in writing)
◦ PVSyst
◦ RETScreen
◦ Manual calculations using BOM or NASA or
the ASRDH

AuSES PV Installation Best Practice Workshop 5


Before installation
Azimuth

-90° -60° -30° 0° 30° 60° 90°

0° 90% 90% 90% 90% 90% 90% 90%

15° 88% 93% 96% 98% 96% 93% 88%

30° 83% 92% 98% 100% 98% 92% 83%


Inclination

45° 77% 88% 95% 97% 95% 88% 77%

60° 69% 80% 87% 90% 87% 80% 69%

75° 60% 70% 77% 78% 77% 70% 60%

90° 51% 59% 63% 63% 63% 59% 51%

AuSES PV Installation Best Practice Workshop 6


Health and Safety

AuSES PV Installation Best Practice Workshop 7


Health and Safety

AuSES PV Installation Best Practice Workshop 8


PV modules

AuSES PV Installation Best Practice Workshop 9


PV modules

AuSES PV Installation Best Practice Workshop 10


PV modules

AuSES PV Installation Best Practice Workshop 11


PV modules

AuSES PV Installation Best Practice Workshop 12


A note on fuses
 Overcurrent protection may be required
when multiple stings are connected in
parallel
 AS/NZS 5033:2005 provides sizing
requirements for overcurrent protection
 AS/NZS 5033:2005 does not provide
mandatory trip times for protection

AuSES PV Installation Best Practice Workshop 13


A note on fuses
 IEC 61730.2 tests modules to withstand
135% of the maximum series fuse rating
for 2 hours

 => size overcurrent protection so that it


does not trip under normal operation, but
trips within 2 hours of an overcurrent
situation. Look at fuse/MCB
manufacturer’s datasheets.
AuSES PV Installation Best Practice Workshop 14
A note on fuses

AuSES PV Installation Best Practice Workshop 15


Polarized DC circuit breakers
 Pay attention to the
direction of current
 Generally speaking,
the PV array goes in
the terminals marked
+ and –
 Check wiring with
manufacturer

AuSES PV Installation Best Practice Workshop 16


DC cabling

AuSES PV Installation Best Practice Workshop 17


DC cabling

AuSES PV Installation Best Practice Workshop 18


DC cabling

AuSES PV Installation Best Practice Workshop 19


DC cabling

AuSES PV Installation Best Practice Workshop 20


DC cabling

AuSES PV Installation Best Practice Workshop 21


Inverters - good

AuSES PV Installation Best Practice Workshop 22


Inverters - good

AuSES PV Installation Best Practice Workshop 23


Inverters - better

AuSES PV Installation Best Practice Workshop 24


Inverters - best

AuSES PV Installation Best Practice Workshop 25


Inverters - best

AuSES PV Installation Best Practice Workshop 26


Labelling and documentation

AuSES PV Installation Best Practice Workshop 27


Labelling and documentation

AuSES PV Installation Best Practice Workshop 28


Labelling and documentation
 Documentation should be given to
customer after installation is complete:
◦ Overall working of system
◦ Data sheets and handbooks (PV modules,
inverters, mounting rails)
◦ List of equipment supplied, with serial
numbers
◦ Wiring diagrams and string layout

AuSES PV Installation Best Practice Workshop 29


Labelling and documentation
◦ Commissioning sheet and installation checklist
◦ Expected annual yield
◦ Warranty certificates and manufacturer’s
contact details
◦ Maintenance procedures, shutdown
procedure, alarms installed and action
required.

AuSES PV Installation Best Practice Workshop 30


Thank you

AuSES PV Installation Best Practice