JADWAL PELAKSANAAN PEKERJAAN

NAMA PAKET : PEMBANGUNAN JARINGAN IRIGASI D.I BUKIT RAYA, SALURAN SEKUNDER
NO. KONTRAK : 610/3/SPP-SDA/DPUPR-HS/DAK/III/2021
PELAKSANA : PT. ANTABATIC TIMUR NUSANTARA
LOKASI : DESA BUKIT RAYA, KEC. GANE TIMUR, KAB. HALMAHERA SELATAN
TAHUN ANGGARAN : 2021

KONTRAK PERUBAHAN PERIODE BULAN

NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT I II III IV V VI


(RP) (%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2

I. PERSIAPAN 15,000,000.00 0.32 0.45 0.10 0.76 (0.12) (0.12) (0.12) (0.12)

III PEMBUATAN SALURAN SEKUNDER - - -

A Ruas BRKi.2ka.1 (P = 862.00 m) - - - - - - - - -

1 As Built Drawing 4,685,572,532.62 99.68


Realisasi

A JUMLAH 4,700,572,532.62 100.00 ADDENDUM-01

RENCANA (%) 1.77 1.77 1.77 1.85 1.85 1.85 1.85 5.48 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71
B
C RENCANA KUMULATIF (%) - 1.77 3.53 5.30 7.16 9.01 10.86 12.72 18.19 21.90 25.61 29.32 33.02 36.73 40.44 44.15 47.86 51.56 55.27 58.98 62.69 66.40 70.10

D RENCANA ADD-01 (%) (0.12) (0.12) (0.12) (0.12) - - - - - - -

E RENCANA ADD-01 KUMULATIF (%) 1.00 1.63 1.50 1.38 1.26 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13

F REALISASI (%) - - 0.45 0.10 0.76 - - - - - - 1.43 4.02 3.74 1.25 0.94 2.22 2.15 3.09 5.29 31.75 19.07

G REALISASI KUMULATIF(%) - - - 0.45 0.55 1.31 1.31 1.31 1.31 1.31 1.31 1.31 2.74 6.76 10.50 11.75 12.68 14.90 17.04 20.14 25.43 57.18 76.25

H DEVIASI (%) (1.77) (3.53) (4.85) (6.61) (7.70) (9.55) (11.41) (16.88) (20.59) (24.30) (0.32) 1.24 5.38 9.24 10.61 11.55 13.77 15.91 19.00 24.30 56.05 75.12

Disetuji, Diperiksa, Diperiksa,

PEJABAT PEMBUAT KOMITMEN PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS

(PPK) (PPTK) CV. BUMI KISATA

ALI HASAN YULIANTI AHMAD, ST AZWARNO, ST


NIP. 19730312 200808 1 001 NIP. 19770918 200903 1 008
DIREKTUR
PERIODE BULAN

VI VII VIII KET.

3 4 1 2 3 4 1 2 3 4

-0.1237 -0.1237 -0.1237 -0.1237

Rencana Awal
- - - - - - - - -

33.23 33.23 33.23

Rencana Perubahan
ADD-01

3.71 3.71 3.71 3.71 3.71 3.71 3.71 3.71 0.12 0.12

73.81 77.52 81.23 84.94 88.64 92.35 96.06 99.77 99.88 100.0

- - - - - (0.12) (0.12) 33.10 33.10 33.2

1.13 1.13 1.13 1.13 1.13 1.01 0.88 33.99 67.1 100.3

09 Agustus 2021

Diperiksa, Dibuat,

KONSULTAN PENGAWAS Kontraktor Pelaksana

CV. BUMI KISATA PT. ANTABATIC TIMUR NUSANTARA

AZWARNO, ST DWI W. NANANG U, ST


DIREKTUR PELAKSANA
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

NAMA PAKET : PEMBANGUNAN JARINGAN IRIGASI D.I BUKIT RAYA, SALURAN SEKUNDER MINGGU KE - : 22

NO. KONTRAK : 610/3/SPP-SDA/DPUPR-HS/DAK/III/2021 PERIODE : 02 Agustus 2021 S/d 09 Agustus 2021

PELAKSANA : PT. ANTABATIC TIMUR NUSANTARA REALISASI : 72.88 %

LOKASI : DESA BUKIT RAYA, KEC. GANE TIMUR, KAB. HALMAHERA SELATAN RENCANA : 1.13 %

TAHUN ANGGARAN : 2021 DEVIASI : 71.75 %

ADDENDUM CONTRACT CHANGE ORDER (ADD-CCO1) REALISASI


No. Uraian Pekerjaan Minggu Lalu Minggu Ini Kumulatif Bobot Thdp
Sat Volume Harga Satuan (Rp) Jumlah Harga (Rp) Bobot (%) Jumlah Harga (Rp)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%) Item Pek.(%)

I.PERSIAPAN

1 Mobilisasi dan Demobilisasi Peralatan dan Tena Dihitung 1.00 71,000,000.00 71,000,000.00 1.52 0.75 1.14 - - 0.75 1.14 53,250,000.00 75.00

2 Papan Proyek Dihitung 1.00 822,537.50 822,537.50 0.02 1.00 0.02 - - 1.00 0.02 822,537.50 100.00

3 Pembuatan Direksi Keet, Los Kerja dan Gudang Ls 1.00 10,000,000.00 10,000,000.00 0.21 1.00 0.21 - - 1.00 0.21 10,000,000.00 100.00

4 Pengukuran Kembali (Uitzt Trase Saluran) m' 1,856.00 6,742.07 12,513,281.92 0.27 1,856.00 0.27 - - 1,856.00 0.27 12,513,281.92 100.00

5 Land Clearing dan Perataan m2 8,850.41 33,010.68 292,157,887.25 6.24 7,522.84 5.30 - - 7,522.84 5.30 248,334,204.16 85.00

6 Jalan Inspeksi m3 2,079.90 320,818.25 667,269,878.18 14.24 1,247.94 8.54 311.99 2.14 1,559.93 10.68 500,452,408.63 75.00

7 Dewatering m3 921.05 201,184.21 185,299,898.38 3.95 921.05 3.95 - - 921.05 3.95 185,299,898.38 100.00

1,239,063,483.22 26.44 19.43 2.14 21.57 1,010,672,330.59

II. SISTEM MANAGEMEN KESELAMATAN KEDihitung 1.00 15,000,000.00 15,000,000.00 0.32 1.00 0.32 - - 1.00 0.32 15,000,000.00 100.00

B Ruas BRKa.1

B.1 SEGMEN 1 (SALURAN PRIMER ; P = 75 M)

1 Pekerjaan Tanah

a Galian Saluran m3 23.25 201,184.21 4,677,532.88 0.10 23.25 0.10 - - 23.25 0.10 4,677,532.88 100.00

b Pembuatan Badan Tanggul m3 180.00 289,016.83 52,023,029.40 1.11 180.00 1.11 - - 180.00 1.11 52,023,029.40 100.00

c Finishing Badan Tanggul m3 180.00 64,216.89 11,559,040.20 0.25 - - - - - - - -

2 Pekerjaan Pasangan Batu

a Pas. Batu 1 Pc : 3 Psr m3 90.86 1,070,362.50 97,247,784.94 2.08 45.43 1.04 45.43 1.04 90.86 2.08 97,247,784.94 100.00

b Plesteran 1 Pc : 3 Psr m2 245.25 83,872.03 20,569,615.36 0.44 - - 122.63 0.22 122.63 0.22 10,284,807.68 50.00

c Acian (Pasta Semen) m2 245.25 45,971.25 11,274,449.06 0.24 - - - - - - - -

197,351,451.84 4.21 2.25 1.26 3.51 164,233,154.90


ADDENDUM CONTRACT CHANGE ORDER (ADD-CCO1) REALISASI
No. Uraian Pekerjaan Minggu Lalu Minggu Ini Kumulatif Bobot Thdp
Sat Volume Harga Satuan (Rp) Jumlah Harga (Rp) Bobot (%) Jumlah Harga (Rp)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%) Item Pek.(%)

B.2 SEGMEN II (SALURAN SEKUNDER ; P = 163 M)

1 Pekerjaan Tanah

a Galian Saluran m3 166.63 201,184.21 33,523,304.79 0.72 166.63 0.72 - - 166.63 0.72 33,523,304.79 100.00

b Pembuatan Badan Tanggul m3 232.06 289,016.83 67,067,800.49 1.43 232.06 1.43 - - 232.06 1.43 67,067,800.49 100.00

c Finishing Badan Tanggul m3 232.06 64,216.89 14,901,850.41 0.32 - - - - - - - -

2 Pekerjaan Pasangan Batu

a Pas. Batu 1 Pc : 3 Psr m3 282.71 1,070,362.50 302,606,999.01 6.46 141.36 3.23 141.36 3.23 282.71 6.46 302,606,999.01 100.00

b Plesteran 1 Pc : 3 Psr m2 678.43 83,872.03 56,901,259.38 1.21 - - 141.01 0.25 141.01 0.25 11,826,926.76 20.79

c Acian (Pasta Semen) m2 648.91 45,971.25 29,831,295.78 0.64 - - - - - - - -

504,832,509.85 10.77 5.38 3.48 8.86 415,025,031.05

B.3 SEGMEN III (SALURAN SEKUNDER ; P = 430 M)

1 Pekerjaan Tanah

a Galian Saluran m3 257.52 201,184.21 51,808,092.67 1.11 257.52 1.11 - - 257.52 1.11 51,808,092.67 100.00

b Pembuatan Badan Tanggul m3 321.00 289,016.83 92,774,402.43 1.98 321.00 1.98 - - 321.00 1.98 92,774,402.43 100.00

c Finishing Badan Tanggul m3 321.00 64,216.89 20,613,621.69 0.44 - - - - - - - -

2 Pekerjaan Pasangan Batu

a Pas. Batu 1 Pc : 3 Psr m3 403.32 1,070,362.50 431,696,569.81 9.21 224.57 5.13 100.31 2.29 324.87 7.42 347,731,586.98 80.55

b Plesteran 1 Pc : 3 Psr m2 969.78 83,872.03 81,337,417.25 1.74 - - 391.31 0.70 391.31 0.70 32,819,647.86 40.35

c Acian (Pasta Semen) m2 954.38 45,971.25 43,874,041.58 0.94 - - - - - - - -

722,104,145.43 15.41 8.22 2.99 11.21 525,133,729.94


ADDENDUM CONTRACT CHANGE ORDER (ADD-CCO1) REALISASI
No. Uraian Pekerjaan Minggu Lalu Minggu Ini Kumulatif Bobot Thdp
Sat Volume Harga Satuan (Rp) Jumlah Harga (Rp) Bobot (%) Jumlah Harga (Rp)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%) Item Pek.(%)

B.4 SEGMEN IV (SALURAN SEKUNDER, P = 478 M)

1 Pekerjaan Tanah

a Galian Saluran m3 88.13 201,184.21 17,730,364.43 0.38 44.07 0.19 44.07 0.19 88.13 0.38 17,730,364.43 100.00

b Pembuatan Badan Tanggul m3 731.35 289,016.83 211,372,458.62 4.51 731.35 4.51 - - 731.35 4.51 211,372,458.62 100.00

c Finishing Badan Tanggul m3 731.35 64,216.89 46,965,022.50 1.00 - - - - - - - -

2 Pekerjaan Pasangan Batu

a Pas. Batu 1 Pc : 3 Psr m3 415.57 1,070,362.50 444,813,969.29 9.49 198.21 4.53 136.33 3.11 334.54 7.64 358,075,245.27 80.50

b Plesteran 1 Pc : 3 Psr m2 1,563.06 83,872.03 131,097,015.21 2.80 - - 715.10 1.28 715.10 1.28 59,976,884.46 45.75

c Acian (Pasta Semen) m2 1,563.06 45,971.25 71,855,822.03 1.53 - - 394.36 0.39 394.36 0.39 18,129,223.90 25.23

923,834,652.07 19.72 9.23 4.97 14.20 665,284,176.68

B.5 SEGMEN V (SALURAN SEKUNDER ; P = 300 M)

1 Pekerjaan Tanah

a Galian Saluran m3 185.38 201,184.21 37,296,162.58 0.80 185.38 0.80 - - 185.38 0.80 37,296,162.58 100.00

b Pembuatan Badan Tanggul m3 131.50 289,016.83 38,005,713.15 0.81 131.50 0.81 - - 131.50 0.81 38,005,713.15 100.00

c Finishing Badan Tanggul m3 131.50 64,216.89 8,444,521.04 0.18 - - - - - - - -

2 Pekerjaan Pasangan Batu

a Pas. Batu 1 Pc : 3 Psr m3 292.86 1,070,362.50 313,465,184.35 6.69 223.30 5.10 69.55 1.59 292.86 6.69 313,465,184.35 100.00

b Plesteran 1 Pc : 3 Psr m2 727.19 83,872.03 60,990,733.75 1.30 - - 363.59 0.65 363.59 0.65 30,495,366.88 50.00

c Acian (Pasta Semen) m2 718.50 45,971.25 33,030,113.27 0.70 - - 359.25 0.35 359.25 0.35 16,515,056.63 50.00

491,232,428.13 10.48 6.71 2.59 9.30 435,777,483.59

B.7 BENDUNG/TANGKAPAN

1 Pekerjaan Tanah

a Galian Saluran m3 101.94 201,184.21 20,509,214.29 0.44 50.97 0.22 50.97 0.22 101.94 0.44 20,509,214.29 100.00

b Pembuatan Badan Tanggul m3 753.43 289,016.83 217,753,661.21 4.65 188.36 1.16 188.36 1.16 376.71 2.32 108,876,830.61 50.00

c Finishing Badan Tanggul m3 753.43 64,216.89 48,382,867.22 1.03 - - - - - - - -

2 Pekerjaan Pasangan Batu

a Pas. Batu 1 Pc : 3 Psr m3 113.06 1,070,362.50 121,016,289.40 2.58 - - 11.31 0.26 11.31 0.26 12,101,628.94 10.00

b Plesteran 1 Pc : 3 Psr m2 294.78 83,872.03 24,723,987.81 0.53 - - - - - - - -

c Acian (Pasta Semen) m2 161.09 45,971.25 7,405,692.55 0.16 - - - - - - - -

439,791,712.47 9.39 1.38 1.64 3.02 141,487,673.83


ADDENDUM CONTRACT CHANGE ORDER (ADD-CCO1) REALISASI
No. Uraian Pekerjaan Minggu Lalu Minggu Ini Kumulatif Bobot Thdp
Sat Volume Harga Satuan (Rp) Jumlah Harga (Rp) Bobot (%) Jumlah Harga (Rp)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%) Item Pek.(%)

IV PEKERJAAN LAIN LAIN

1 As Built Drawing Ls 1.00 4,000,000.00 4,000,000.00 0.09 - - - - - - - -

2 Dokumentasi dan Pelaporan Ls 1.00 6,000,000.00 6,000,000.00 0.13 - - - - - - - -

3 Pintu Air Ls 10.00 10,000,000.00 100,000,000.00 2.13 - - - - - - - -

4 Pekerjaan Gorong2/Decker (3 Buah) -

a Galian m3 46.80 201,184.21 9,415,421.03 0.20 46.80 0.20 - - 46.80 0.20 9,415,421.03 100.00

b Pas. Batu 1 Pc : 3 Psr m3 27.96 1,070,362.50 29,927,335.50 0.64 27.96 0.64 - - 27.96 0.64 29,927,335.50 100.00

c Plesteran 1 Pc : 3 Psr m2 36.00 83,872.03 3,019,393.08 0.06 36.00 0.06 - - 36.00 0.06 3,019,393.08 100.00

152,362,149.61 3.25 0.90 - 0.90 42,362,149.61

A Total 4,685,572,532.62 100.00 53.81 19.07 72.88 3,414,975,730.18

B Ppn 10 % 468,557,253.26 341,497,573.02

C Jumlah Total 5,154,129,785.88 3,756,473,303.20

D Dibulatkan 5,154,129,785.00 3,756,473,303.00

09 Agustus 2021
Disetuji, Diperiksa, Diperiksa, Dibuat,
PEJABAT PEMBUAT KOMITMEN PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PENGAWAS Kontraktor Pelaksana
(PPK) (PPTK) CV. BUMI KISATA PT. ANTABATIC TIMUR NUSANTARA

ALI HASAN YULIANTI AHMAD, ST AZWARNO, ST DWI W. NANANG U, ST


NIP. 19730312 200808 1 001 NIP. 19770918 200903 1 008
DIREKTUR PELAKSANA
1
2

BULAN 1 1 03 Maret 2021 09 Maret 2021 7


2 10 Maret 2021 17 Maret 2021 8
3 18 Maret 2021 24 Maret 2021 7
4 25 Maret 2021 31 Maret 2021 7

BULAN 2 5 01 April 2021 07 April 2021 7


6 08 April 2021 15 April 2021 8
7 16 April 2021 22 April 2021 7
8 23 April 2021 29 April 2021 7

BULAN 3 9 30 April 2021 06 Mei 2021 7


10 07 Mei 2021 14 Mei 2021 8
11 15 Mei 2021 21 Mei 2021 7
12 22 Mei 2021 28 Mei 2021 7

BULAN 4 13 29 Mei 2021 04 Juni 2021 7


14 05 Juni 2021 12 Juni 2021 8
15 13 Juni 2021 19 Juni 2021 7
16 20 Juni 2021 26 Juni 2021 7

BULAN 5 17 27 Juni 2021 03 Juli 2021 7


18 04 Juli 2021 11 Juli 2021 8
19 12 Juli 2021 18 Juli 2021 7
20 19 Juli 2021 25 Juli 2021 7

BULAN 6 21 26 Juli 2021 01 Agustus 2021 7


22 02 Agustus 2021 09 Agustus 2021 8
23 10 Agustus 2021 16 Agustus 2021 7
24 17 Agustus 2021 23 Agustus 2021 7

BULAN 7 25 24 Agustus 2021 30 Agustus 2021 7


26 31 Agustus 2021 07 September 2021 8
27 08 September 2021 14 September 2021 7
28 15 September 2021 21 September 2021 7

BULAN 8 29 22 September 2021 28 September 2021 7


30 29 September 2021 06 Oktober 2021 8
31 07 Oktober 2021 13 Oktober 2021 7
32 14 Oktober 2021 18 Oktober 2021 5
230
1 2
03 Maret 2021 10 Maret 2021 18 Maret 2021 25 Maret 2021 01 April 2021 08 April 2021 16 April 2021
09 Maret 2021 17 Maret 2021 24 Maret 2021 31 Maret 2021 07 April 2021 15 April 2021 22 April 2021
3 4
23 April 2021 ### 07 Mei 2021 15 Mei 2021 22 Mei 2021 29 Mei 2021 05 Juni 2021 13 Juni 2021
29 April 2021 06 Mei 2021 14 Mei 2021 21 Mei 2021 28 Mei 2021 04 Juni 2021 12 Juni 2021 19 Juni 2021
5 6
20 Juni 2021 27 Juni 2021 04 Juli 2021 12 Juli 2021 19 Juli 2021 26 Juli 2021
26 Juni 2021 03 Juli 2021 11 Juli 2021 18 Juli 2021 25 Juli 2021 01 Agustus 2021
6 7
02 Agustus 2021 10 Agustus 2021 17 Agustus 2021 24 Agustus 2021 31 Agustus 2021 08 September 2021
09 Agustus 2021 16 Agustus 2021 23 Agustus 2021 30 Agustus 2021 07 September 2021 14 September 2021
8
15 September 2021 22 September 2021 29 September 2021 07 Oktober 2021 14 Oktober 2021
21 September 2021 28 September 2021 06 Oktober 2021 13 Oktober 2021 18 Oktober 2021